mixed use development project, sector-72, gurgaon, haryana

39
POINT-WISE COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE E NVIRONMENTAL CLEARANCE LETTER NO. SEIAA/HR/2013/283 DATED 17 th June , 2013 Tata Center- Mixed Use Development Project, Sector-72, Gurgaon, Haryana Sl. No. Conditions Status of Compliance PART A – SPECIFIC CONDITIONS: Construction Phase - 1 “Consent to Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. Agreed. “Consent to Establish” has been obtained from Haryana State Pollution Control Board under Air and Water Act. Copy of the same had been submitted to SEIAA, Haryana along with previous compliances. Copy of “Consent to Establish” is enclosed as Annexure-I. 2 A first aid room as proposed in the project report shall be provided both during construction and operation phase of the project. Agreed. A first aid room has been provided during the construction phase and same will be maintained during operation phase of the Page 1 of 39

Upload: dinhquynh

Post on 01-Jan-2017

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

POINT-WISE COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE

E NVIRONMENTAL CLEARANCE LETTER NO. SEIAA/HR/2013/283

DATED 17 th June , 2013

Tata Center- Mixed Use Development Project, Sector-72, Gurgaon, Haryana

Sl.

No.

Conditions Status of Compliance

PART A – SPECIFIC CONDITIONS:

Construction Phase -

1 “Consent to Establish” shall be obtained from

Haryana State Pollution Control Board under

Air and Water Act and a copy shall be

submitted to the SEIAA, Haryana before the

start of any construction work at site.

Agreed. “Consent to Establish” has been

obtained from Haryana State Pollution

Control Board under Air and Water Act.

Copy of the same had been submitted to

SEIAA, Haryana along with previous

compliances. Copy of “Consent to

Establish” is enclosed as Annexure-I.

2 A first aid room as proposed in the project

report shall be provided both during

construction and operation phase of the

project.

Agreed. A first aid room has been provided

during the construction phase and same will

be maintained during operation phase of the

project.

3 Adequate drinking water and sanitary

facilities should be provided for construction

workers at the site. Provision should be made

for mobile toilets. Open defecation by

laboures is strictly prohibited. The safe

disposal of waste water and solid wastes

generated during the construction phase

should be ensured.

Agreed. Adequate drinking water and

sanitary facilities has been provided for

construction workers at site. Provisions are

there for mobile toilets. The safe disposal

of waste-water and solid wastes generated

during the construction phase is being

ensured.

Page 1 of 22

Page 2: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

4 All top soil excavated during construction

activities should be stored for use in

horticulture/landscape development within the

project site.

Agreed. All the top soil excavated during

the construction activities is being properly

stored and will be utilized for the

horticulture/landscape development within

the site.

5 The project proponent shall ensure that the

building material required during construction

phase is properly stored within the project

area and disposal of construction waste

should not create any adverse effect on the

neighboring communities and should be

disposed of after taking necessary precautions

for general safety and health aspects of

people, only in approved sites with the

approval of competent authority.

Agreed. Building material required during

construction phase has been properly stored

within the project area and construction

waste has been used for site development

and land filling of the project site, it will

not create any adverse effect on the

neighboring communities.

6 Construction spoils, including bituminous

material and other hazardous materials, must

not be allowed to contaminate watercourses

and dump sites for such material must be

secured so that they should not leach into the

ground water and any hazardous waste

generated during construction phase, should

be disposed off as per applicable rules and

norms with necessary approval of the Haryana

State Pollution Control Board.

Agreed. Construction spoils will be used

for site development and land filling of the

project site, other hazardous materials will

be disposed-off as per norms

7 The diesel generator sets to be used during

construction phase should be of ultra-low

sulphur diesel type and should confirm to

Environment (Protection) Rules prescribed

for air and noise emission standards.

Agreed. D.G sets used will be of low

sulphur diesel, conforming to Noise &

National Air Quality Standards.

8 The diesel required for operating DG sets

shall be stored in underground tanks and if

Agreed. The diesel required for operating

DG set will be stored in HDPEdrums and

Page 2 of 22

Page 3: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

required, clearance from Chief Controller of

Explosives shall be taken.

log books will be managed for

accountability. Storage will be within the

threshold limit hence clearance from chief

control of explosive is not required.

9 Ambient noise levels should confirm to the

residential standards both during day and

night. Incremental pollution loads on the

ambient air and noise quality should be

closely monitored during the construction

phase. Adequate measures should be taken to

reduce ambient air and noise level during

construction phase, so as to confirm to the

stipulated residential standards.

Agreed. Ambient noise and ambient air has

been closely monitored during the

construction phase. Noise quality data

monitored is enclosed as Annexure-II.

10 Fly ash should be used as building material in

the construction as per the provisions of Fly

Ash Notification of September 1999 and as

amended on 27th August 2003.

Agreed. Fly ash based material will be

used.

11 Storm water control and its re-use as CGWB

and BIS standards for various applications

should be ensured.

Agreed. Storm water will be collected to

recharge the ground water, 08 RWH pits

are proposed to be constructed within the

project site for this purpose.

12 Water demand during construction should be

reduced by use of pre-mixed concrete, curing

agents and other best practices.

Agreed. Water demand during construction

will be reduced by use of pre-mixed

concrete, curing agents and other best

practices.

13 In view of the severe constrains in water

supply augmentation in the region and

sustainability of water resources, the

developer will submit the NOC from CGWB

specifying water extraction quantities and

assurance from HUDA/utility provider

Agreed. No ground water is extracted

during the construction as well as operation

phase. So, CGWB permission is not

required. However during construction

phase water is being supplied by HUDA

(Treated Water), permission letter from

Page 3 of 22

Page 4: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

indicating source of water supply and quantity

of water with details of intended use of water

– potable and non-potable. Assurance is

required for both construction and operation

stages separately. It shall be submitted to the

SEIAA and RO, MOEF, Chandigarh before

the start of construction.

HUDA is enclosed as Annexure-III.

Duringoperational phase HUDA will

supply fresh water, copy of

acknowledgement is enclosed as

Annexure-IV.

14 Roof should meet prescriptive requirement as

per Energy Conservation Building Code by

using appropriate thermal insulation material.

Agreed. During construction phase care

will be taken that roof area meets Energy

Conservation Building Code requirement

by using appropriate thermal insulation

material to fulfill requirement.

15 Opaque wall should meet prescriptive

requirement as per Energy Conservation

Building Code which is proposed to be

mandatory for all air conditioned spaces while

it is aspirational for non-air-conditioned

spaces by use of appropriate thermal

insulation material to fulfill requirement.

Agreed. Material having appropriate R &

U value will be used to meet prescriptive

requirement of opaque wall as per energy

conservation building Code.

16 The approval of the competent authority shall

be obtained for structural safety of the

building on account of earthquake, adequacy

of fire-fighting equipment, etc. as per

National Building Code including protection

measures from lightening etc. If any forest

land is involved in the proposal site, clearance

under Forest Conservation Act shall be

obtained from the competent authority.

Agreed. The approval of the competent

authority will be obtained for structural

safety of the building on account of

earthquake, adequacy of fire-fighting

equipment, etc. as per National Building

Code including protection measures from

lightening etc. The project site does not fall

under the Forest Conservation Act. Copy of

forest NOC is enclosed as Annexure-V

17 Overexploited groundwater and impending

severe shortage of water supply in the region

requires the developers to redraw the water

and energy conservation plan. Developer shall

Agreed. Ground water will not be

extracted. To recharge the ground water

level of the area rain water harvesting has

been proposed in the project. The water

Page 4 of 22

Page 5: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

reduce the overall footprint of the proposed

development. Project proponent shall

incorporate water efficiency/savings measures

as well as water reuse/recycling within 3

months and before start of construction to the

SEIAA, Haryana and RO, MOEF, GOI,

Chandigarh.

reuse/recycling and water efficiency/saving

measures are being incorporated within 3

months and before start of construction to

SEIAA, Haryana and RO, MOEF, GOI,

Chandigarh.

18 The project proponent shall construct 08 rain

water harvesting pits for recharging the

ground water within the project premises.

Rain water harvesting pits shall be designed

to make provisions for silting chamber and

removal of floating matter before entering

harvesting pit. Maintenance budget and

persons responsible for maintenance must be

provided. Care shall also be taken that

contaminated water do not enter any RWH

pit.

Agreed. 08 rain water harvesting pits for

recharging the ground water within the

project premises will be constructed. Rain

water harvesting pits will be designed in

such a way that silt and floating material

will not enter in the ground water level..

Maintenance budget and persons

responsible for maintenance are being

provided and care will also be taken that

contaminated water do not enter any RWH

pit.Storm water plan showing the RWH pit

location is enclosed as Annexure-VI.

19 The project proponent will provide minimum

one hydraulic ladder for escape of people in

case of fire.

Agreed, permanent ladder will be provided

instead of hydraulic ladder. As hydraulic

ladder can be provided upto only 12m.

20 The project proponent shall submit assurance

from the DHBVN for supply of 5016KVA of

power supply before the start of the

construction. In no case project will be

operational solely on generators without any

power supply from any external power utility.

Agreed. An application has been filed to

the Superintending Engineer of HVPNL

for power supply. The acknowledgment

copy of the same is enclosed as Annexure

VII.

21 Detail calculation of power load and ultimate

power load of the project shall be submitted

to DHBVN under intimation to SEIAA

Haryana before the start of the construction.

Agreed. The total power requirement is

5016 KVA that will be supplied by

DHBVN. The detailed power load

calculation has been submitted to the

Page 5 of 22

Page 6: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

Provisions shall be made for electrical

infrastructure in the project area.

DHBVN. An application has been filed to

the Superintending Engineer NCR

Planning. The acknowledgment copy of the

same is enclosed as Annexure VII.

22 The project proponent shall obtain NOC from

the nearest fire station before start of the

construction.

Agreed. An application has been filled to

municipal corporation Gurgaon for

obtaining the fire NOC. Acknowledgement

copy of the same is enclosed as Annexure

VIII

23 The project proponent shall not raise any

construction in the natural land

depression/Nallah/water course and shall

ensure that the natural flow from the

Nallah/water course is not obstructed.

Agreed. The project site does not contain

any natural land depression nallah/ water

course as well as no natural flow is

obstructed by the project.

24 The project proponent shall keep the plinth

level of the building blocks sufficiently above

the level of the approach road to the project as

per prescribed by-laws. Levels of the other

areas in the projects shall also be kept suitably

so as to avoid flooding.

Agreed. The plinth level of the building

blocks is being sufficiently above the level

of the approach road.. Section and

Elevation plan are enclosed as Annexure-

IX

25 Construction shall be carried out so that

density of population does not exceed norms

approved by Director General Town and

Country Department Haryana.

Agreed. As it is a mixed use development

project so, population density kept as per

the approved Building plan by Director

General Town and Country Department,

Haryana.

26 The project proponent shall submit an

affidavit with the declaration that ground

water will not be used for construction and

only treated water should be used for

construction.

Agreed. Ground water is not used for the

construction activity. An affidavit has been

submitted to SEIAA, Haryana. Copy of the

same is enclosed as Annexure-X.

27 The project proponent shall not cut any

existing tree and project landscaping plan

Agreed. As the project site was a vacant

land so there was no need to cut the trees.

Page 6 of 22

Page 7: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

should be modified to include those trees in

green area

Plantation will be carried out around the

periphery of plot & along internal road

preferably with local species.

28 The project proponent shall provide helipad

facility as required under NBC norms and

shall seek permission of helipad from AAI

accordingly.

Agreed Helipad facility will be provided

for building having height more than 60m

as per NBC norms. NOc from avitation

department has been taken. Copy of AAI

NOC is enclosed as Annexure-XI.

29 The project proponent shall ensure that ECBC

norms for composite climate zone are met. In

particular building envelope, HVAC services,

water heating, pumping, lighting and

electrical infrastructure must meet ECBC

norms.

Agreed. ECBC norms for composite

climate zone, water heating, pumping,

lighting and electrical infrastructure are

being followed.

30 The project proponent shall provide 3m high

barricade around the project area, dust screen

for every floor above the ground, proper

sprinkling and covering of stored material to

restrict dust and air pollution during

construction.

Agreed. 3m high barricade around the

project area is being provided, dust screen

for every floor above the ground, proper

sprinkling and covering of stored material

to restrict dust and air pollution during

construction will be provided.

31 The project proponent shall construct a

sedimentation basin in the lower level of the

project site to trap pollutant and other wastes

during rains.

Agreed. Sedimentation basin constructed

to trap the pollutants and other wastes

during rains is being in lower level of the

project site.

32 The project proponent shall provide proper

Rasta of proper width and proper strength for

his project before the start of construction.

Agreed. Proper roads of adequate width

will be provided in the project for

movement of vehicle within the project

site. Site plan is enclosed as an Annexure-

XII.

33 The project proponent shall provide all the

safety measures for the workers during

construction phase of high rise building.

Agreed. All the safety measures for the

workers during construction phase of high

rise building will be provided.

Page 7 of 22

Page 8: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

34 The project proponent shall ensure that the U-

value of the glass is less than 3.177 and

maximum solar heat gain co-efficient is 0.25

for vertical fenestration.

Agreed. Glass having U value less than

3.177 & maximum solar heat gain to

efficient 0.25 Vertical Fenestration will be

used.

35 The project proponent shall submit

permission of Municipal Commissioner

Gurgaon for disposal of excavated soil before

the start of construction.

Agreed. Mining approval is obtained from

the assistant mining engineer, Gurgaon,

Haryana. The copy of same is enclosed as

Annexure-XIII.

36 The project proponent shall seek NOC from

Town and Country department regarding

height of the building allowed in the skyline

of that city.

Agreed. NOC from Town and Country

department regarding height of the building

allowed in the skyline of that city is being

taken. Building plan approval from the

DTP is already obtained.

Operational phase -

a “Consent to Operate” shall be obtained from

Haryana State Pollution Control Board under

Air and Water Act and a copy shall be

submitted to the SEIAA, Haryana.

Agreed. Permission will be obtained after

completion of construction work of the

project.

b The STP shall be installed for the treatment of

the sewage to the prescribed standards

including odour and treated effluent will be

recycled. The installation of STP should be

certified by an independent expert and a

report in this regard should be submitted to

the SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

Discharge of treated sewage shall confirm to

norms and standards of HSPCB, Panchkula.

Project Proponent shall implement such STP

technology which does not require filter

Agreed. The Sewage Treatment Plant

(STP) will be installed for the treatment of

the sewage to be prescribed standards

including odor and treated effluent shall be

recycled to achieve zero exit discharge.

Installation of STP certified by an

independent expert will be submitted to the

SEIAA before start of operation stage of

the mixed use project. Plumbing plan

showing the STP location is enclosed as

Annexure-XIV.

Page 8 of 22

Page 9: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

backwash.

c Separation of the grey and black water should

be done by the use of dual plumbing line.

Treatment of 100% grey water by

decentralized treatment should be done

ensuring that the re-circulated water should

have BOD maximum 10 mg/litre and the

recycled water will be used for flushing,

gardening and DG set cooling and running of

fountain in the water body to achieve zero exit

discharge.

Agreed. Treatment of grey and black water

will be done. Dual plumbing plan and water

balance diagram are attached as Annexure

–XV.

d For disinfection of the treated wastewater

ultra-violate radiation or ozonization process

should be used.

Agreed. For disinfection of the treated

wastewater ultra-violet radiation or

ozonization process will be used.

e The solid waste generated should be properly

collected and segregated. Bio-degradable

waste shall be decomposed at site and

dry/inert solid waste should be disposed-off to

approved sites for land filling after recovering

recyclable material.

Agreed. The solid waste generated will be

properly collected and segregated. Bio-

degradable waste will be decomposed at

site and dry/inert solid waste will be

disposed-off to approve sites for land filling

after recovering recyclable material.

f Diesel power generating sets proposed as

source of back-up power for lifts, common

area illumination and for domestic use should

be enclosed type and conform to rules made

under the Environmental (Protection) Act,

1986. The location of the DG sets should be

in the basement as promised by the project

proponent with appropriate stack height i.e

above the roof level as per the CPCB norms.

The diesel used for DG sets should be ultra

low sulphur diesel (0.05% sulphur), instead of

low sulphur diesel.

D.G. Sets to be used for power back up are

of enclosed type and confirming to rules

made under the Environment (Protection)

Act, 1986. The D.G. sets are run on low

sulphur diesel.

Page 9 of 22

Page 10: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

g Ambient Noise level should be controlled to

ensure that it does not exceed the prescribed

standards both within and at the boundary of

the Proposed Residential Complex

Agreed. Ambient Noise level is being

controlled to ensure that it does not exceed

the prescribed standards both within and at

the boundary of the Residential Complex.

A copy of ambient noise quality data is

enclosed as Annexure-II.

h The project proponent should maintain at

least 22% as green cover area for tree

plantation especially all around the periphery

of the project and on the road sides preferably

with local species so as to provide protection

against particulars and noise. The 8% open

spaces inside the plot should be preferably

landscaped and covered with vegetation/grass,

herbs & shrubs. Only locally available plant

species shall be used.

Agreed. Project Proponent will provide

30% as a green area. Landscape plan is

enclosed as Annexure –XVI.

i The project proponent shall strive to

minimum water in irrigation of landscape by

minimizing grass area, using native variety,

xeriscaping and mulching, utilizing

efficientirrigation system, scheduling

irrigation only after checking evapo-

transpiration data.

Agreed. Minimum water will be used in

irrigation of landscape by minimizing grass

area, using native variety, xeriscaping and

mulching, utilizing efficient irrigation

system, scheduling irrigation. Treated water

will be used for the landscaping purposes.

j Rain water harvesting for roof run-off and

surface, as per plan submitted should be

implemented. Before recharging the surface

run-off, pre-treatment through sedimentation

tanks must be done to remove suspended

matter, oil and grease. The bore well for

rainwater recharging should be kept at least

5m. above the highest ground water table.

Care shall be taken that contaminated water

Agreed. Rain water harvesting for roof

run-off and surface, as per plan submitted

will be implemented. Before recharging the

surface run-off, pre-treatment through

sedimentation tanks will be done to remove

suspended matter, oil and grease. The bore

well for rainwater recharging will be kept

at least 5m above the highest ground water

table. Rain water harvesting plan is

Page 10 of 22

Page 11: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

do not enter any RWH pit. The project

proponent shall avoid RWH of first 10

minutes of rain fall. Roof top of the building

shall be without any toxic material or paint

which can contaminate rain water. Wire mess

and filters should be used wherever required.

enclosed as Annexure-VI.

k The ground water level and its quality should

be monitored regularly in consultation with

Central Ground Water Authority.

The ground water level and its quality is

being monitored in consultation with

Central Ground Water Authority.

l There should be no traffic congestion near the

entry and exit points from the roads adjoining

the proposed project site. Parking should be

fully internalized and no space should be

utilized.

Agreed. There is no traffic congestion near

the entry and exit points from the roads

adjoining the project site. Parking will be

fully internalized and no public space will

be utilized. A traffic plan is enclosed as

Annexure-XVII.

m A report on the energy conservation measures

conforming to energy conservation norms

finalized by Bureau of Energy Efficiency

should be prepared incorporating details about

building materials & technology, R & U

Factors etc and submit to the SEIAA,

Haryana in three month time.

Agreed. A report on the energy

conservation measures conforming to

energy conservation norms finalized by

Bureau of Energy Efficiency is being

prepared incorporating details about

building materials & technology, R & U

Factors etc has been submit to the SEIAA,

Haryana in three month time.

n Energy conservation measures like

installation of LED for Lighting the areas

outside the building should be integral part of

the project design and should be in place

before project commissioning. Use of solar

panels must be adapted to the maximum

energy conservation.

Agreed. Energy conservation measures like

installation of CFLs/TFLs for lighting the

areas outside the building is integral part of

the project design and shall be in place

before project commissioning. Solar

lighting is proposed for open spaces and

signage.

o The project proponent shall use zero ozone

depleting potential material in insulation,

Agreed. As it is a Mixed Use Development

Project, all the material going to be use like

Page 11 of 22

Page 12: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

refrigeration, air-conditioning and adhesive.

Project proponent shall also provide Halon

free fire suppression system.

refrigeration, air-conditioning etc. are of

non-ozone depleting.

p The solid waste generated should be properly

collected and segregated as per the

requirement of the MSW Rules, 2000 and as

amended from time to time. The bio-

degradable waste should be composed by

vermin-composting at the site war marked

within the project area and dry/inert solid

waste should be disposed-off to the approved

sites for land-filling after recovering

recyclable material.

Agreed. Solid waste generated will be

collected & segregated as per MSW rule,

2000. Bio degradable waste will be

composed by vermin-composting.

q The provision of the solar water heating

system shall be as per norms specified by

HAREDA and shall be made operational in

each building block.

Agreed. As it is a Mixed Use Development

Project, solar water heating system will be

used as per norms by HAREDA.

r The traffic plan and the parking plan proposed

by the project proponent should be adhered to

meticulously with further scope of additional

parking for future requirement. There should

be no traffic congestion near the entry and

exit points from the roads adjoining the

proposed project site. Parking should be fully

internalized and no public space should be

used.

Agreed. The traffic plan is being

meticulously adhered to with further scope

of additional parking for future

requirement. Parking is being completely

internalized and no public space is being

utilized. Care is being taken to ensure that

there will be no traffic congestion at the

entry and exit points.

s The project shall be operationalized only

when HUDA/public authority will provide

domestic water supply system in the areas.

Agreed. The project shall be

operationalized only when HUDA/public

authority will provide domestic water

supply system in the areas.

t Operation and maintenance of STP, solid

waste management and electrical

Agreed. Operation and maintenance of

STP, solid waste management and

Page 12 of 22

Page 13: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

Infrastructure, pollution control measures

shall be ensured even after the completion of

sale.

electrical Infrastructure, pollution control

measures will be ensured even after the

completion of sale.

u Different type of waste should be disposed-

off as per provisions of municipal solid waste,

biomedical waste, hazardous waste, e-waste,

batteries & plastic rules made under

Environment Protection Act, 1986.

Particularly E-Waste and Battery waste shall

be disposed of as per existing E-waste

Management Rules 2011 and Batteries

Management Rules 2001. The project

proponent should maintain a collection center

for E-Waste and it should be disposed of to

only registered and authorized

dismantler/recycler.

Agreed. MSW will be disposed off as per

provisions of municipal solid waste made

under Environment Protection Act, 1986.

Negligible quantity of hazardous waste, e-

waste, and plastic waste generated will be

disposed off as per hazardous waste, e-

waste, batteries & plastic rules made under

Environment Protection Act, 1986.

v Standards for discharging of environmental

pollutants as enshrined in various schedules

of rules 3 of Environment Protection Rules

1986 shall be strictly complied with.

Agreed. Standards for discharging of

environmental pollutants as enshrined in

various schedules of rules 3 of

Environment Protection Rules 1986 will be

strictly complied with.

w Water supply be metered to different

residential units and different utilities.

Agreed. Water supply will be metered to

different units and different utilities.

x The project proponent shall ensure that the

stack height of DG sets is as per the CPCB

guide lines and also ensure that the emission

standards of noise and air are within the

CPCB prescribed limits. Noise and Emission

level of DG sets are greater than 800KVA

shall be as per CBCB latest standards for high

Agreed. Stack height of DG sets are kept 6

mtrs above the roof level as per the CPCB

guide lines and also ensured that the

emission standards of noise and air are

within the CPCB prescribed limits.

Page 13 of 22

Page 14: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

capacity DG sets.

y All electric supply exceeding 100amp, 3-

phase shall maintain the power factor between

0.98 lag to 1 at the point of connection.

Agreed. All electric supply exceeding

100amp, 3-phase will be maintain the

power factor between 0.98 lag to 1 at the

point of connection.

z The project proponent shall use only treated

water instead of fresh water for HVAC and

DG cooling. The project proponent shall use

evaporative cooling technology and double

stage cooling system for HVAC in order to

reduce water consumption. Further

temperature, relative humidity during summer

and winter session should be kept at optimal

level. Variable speed drive, best co-efficient

of performance, as well as optimal integrated

point load value and minimum outside fresh

air supply may be resorted for conservation of

power and water. Coil type cooling DG sets

shall be used for saving cooling water

consumption for water cooled DG sets.

Agreed. Instead of fresh water for DG

cooling, treated water will be used.

Evaporative cooling technology and double

stage cooling system is being used for

HVAC in order to reduce water

consumption. Maximum treated water will

be used for various processes instead of

fresh water to reduce the water

consumption.

PART-B GENERAL CONDITIONS :-

i The project proponent should ensure the

commitments made in Form-1, Form-1A,

EIA/EMP and other documents submitted to

the SEIAA for protection of environment and

proposed environmental safeguards are

complied with in letter and spirit. In case of

contradiction between two or more documents

on any point, the most environmentally

friendly commitment on the point shall be

Agreed. All safeguards mentioned in the

application are being implemented during

the construction phase and will be

implemented during the operation phase.

Page 14 of 22

Page 15: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

taken as commitment by project proponent.

ii Six monthly compliance reports should be

submitted to the Haryana State Pollution

Control Board and Regional Office, MoEF,

GOT, Northern Region, Chandigarh and a

copy to the SEIAA Panchkula, Haryana.

Agreed. Six monthly compliance report is

being submitted to the Haryana State

Pollution Control Board and Regional

Office, MoEF, GOI, Northern Region,

Chandigarh, Haryana.

iii Noise , STP outlet and stack emission shall be

monitored daily. Other environmental

parameters shall be monitored on monthly

basis. After every 3 months the project

proponent shall conduct environmental audit

and shall take corrective measure, if required,

without delay.

Agreed. Noise, STP outlet and stack

emission will be monitored daily. Other

environmental parameters will be

monitored on monthly basis. After every 3

months environmental audit will be

conducted and corrective measure will be

taken, if required, without delay.

iv The SEIAA, Haryana reserves the right to add

additional safeguard measures subsequently,

if found necessary. Environmental Clearance

granted will be revoked if it is found that false

information has been given for getting

approval of this project. SEIAA reserves the

right to revoke the clearance if conditions

stipulated are not implemented to the

satisfaction of SEIAA/MOEF.

Agreed. The SEIAA, Haryana reserves the

right to add additional safeguard measures

subsequently, if found necessary.

Environmental Clearance granted will be

revoked if it is found that false information

has been given for getting approval of this

project. SEIAA reserves the right to revoke

the clearance if conditions stipulated are

not implemented to the satisfaction of

SEIAA/MOEF.

v The project proponent shall not violate any

judicial orders/pronouncements issued by any

Court/Tribunal.

No judicial order/ pronouncements issued

by the Hon’ble Supreme Court/High Courts

to the developers.

vi All other statutory clearances such as the

approvals for storage of diesel from Chief

Controller of Explosives, Fire Department,

Civil Aviation Department, Forest

Agreed. All the required applicable

clearances have been taken from the

respective authority.

Forest NOC is enclosed as Annexure-V

Page 15 of 22

Page 16: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

Conservation Act, 1980 and Wildlife

(Protection) Act. 1972, Forest Act, 1927,

PLPA 1900, etc. shall be obtained, as

applicable by project proponents from the

respective authorities prior to construction of

the project.

AAI NOC is enclosed as Annexure-X

NOC from Chief Controller of Explosive

shall be taken at the appropriate stage.

vii The project proponent should inform the

public that the project has be accorded

Environment Clearance by the SEIAA and

copies of the clearance letter are available

with the Haryana State Pollution Control

Board & SEIAA. This should be advertised

within 7 days from the date of issue of

clearance letter at least in two local

newspapers that are widely circulated in the

region and the copy of the same be forwarded

to SEIAA Haryana. A copy of Environment

Clearance collections shall also be put on

project proponent’s website for public

awareness.

Agreed. A copy of advertisement has been

advertised in two local newspapers.

viii Any appeal against this Environmental

Clearance shall lie with the National Green

Tribunal, if preferred within a period of 30

days as prescribed under Section 16 of the

National Green Tribunal Act, 2010.

Agreed. Any appeal against this

Environmental Clearance shall lie with the

National Green Tribunal, if preferred

within a period of 30 days as prescribed

under section 16 of the National Green

Tribunal Act, 2010.

ix The project proponent shall put in place

Corporate Environment Policy as mentioned

in MOEF, GOI, ON No. J-11013/41/2006-IA

II (I) dated 26.04.12 within 3 months period.

Latest Corporate Environment Policy should

Agreed. The project proponent shall put in

place Corporate Environment Policy as

mentioned in MOEF, GOI, ON No. J-

11013/41/2006-IA II (I) dated 26.04.12

within 3 months period. Latest Corporate

Page 16 of 22

Page 17: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

be submitted to SEIAA within 3 months of

issuance of this letter.

Environment Policy should be submitted to

SEIAA within 3 months of issuance of this

letter.

x The fund ear-marked for environment

protection measures should be kept in

separate account and should not be diverted

for other purposes and year wise expenditure

shall be reported to the SEIAA/RO MoEF

GOI under rules prescribed for Environment

Audit.

Agreed. The fund ear-marked for

environment protection measures is being

kept in separate account and will not be

diverted for other purposes and year wise

expenditure will be reported to the

SEIAA/RO MoEF GOI under rules

prescribed for Environment Audit.

xi The project proponent shall obtain NOC

under Aravalli Notification from CEC of

Hon’ble Supreme court regarding coverage

under Aravalli Notification before start of

construction.

Agreed. Application has already given to

the District Collector, Gurgaon, Haryana

for taking clearance of Forest and Aravalli

Acknowledgment copy is enclosed as

Annexure-V.

xii The project proponent shall ensure that no

vehicle during construction/operation phase

enter the project premises without valid

‘Pollution Under Control’ certificate from

competent Authority.

Agreed. It is being ensured that no vehicle

during construction/operation phase enter

the project premises without valid

‘Pollution Under Control’ certificate from

competent Authority.

B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF

S. No. Points as per EIA Guidance Manual Status of ComplianceA. Air Environment1. Wind erosion is a serious problem in areas

where the ground is virtually bare and devoid

of vegetation. Vegetation methods are found to

be most effective in the form of windbreaks

and shelterbelts.

Windbreaks and shelterbelts will be

provided to reduce wind erosion during

the construction phase.

Page 17 of 22

Page 18: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

S. No. Points as per EIA Guidance Manual Status of Compliance2. Sprinkling of water and fine spray from

nozzles to suppress the dust.

Sprinkling will be provided during the

construction phase.

3. On-Road-Inspection should be done for black

smoke generating machinery.

All the machineries used at site having

highest standard and of reputed make and

will be compiled with emission & noise

standards.

4. Promotion of use of cleaner fuel should be

done.

Ultra low sulphur diesel (ULSD) (sulphur

content less than 0.05%) wil be use for

running of DG sets, vehicles and

construction machineries.

5. All DG sets should comply emission norms

notified by MoEF.

The DG sets used in such a way that it

will comply with the emission norms

notified by MoEF.

6. Vehicles having pollution under control

certificate may be allowed to ply.

It will be ensured that all the vehicles used

for construction activities having valid

Pollution Under Check (PUC) certificates.

The vehicles without valid Pollution

Under Check (PUC) certificate is not

permitted at project site.

7. Use of covering sheet to prevent dust

dispersion at buildings and infrastructure sites,

which are being constructed.

Covering sheet will be use to prevent dust

dispersion during the construction phase.

8. Use of covering sheets should be done for

trucks to prevent dust dispersion from the

trucks, implemented by district offices.

Covering sheets will be use on trucks to

prevent dust dispersion from the trucks.

9. Paving is a more permanent solution to dust

control, suitable for longer duration projects.

High cost is the major drawback to paving.

During construction, access road has been

covered with gravels to prevent dust

emission.

Page 18 of 22

Page 19: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

S. No. Points as per EIA Guidance Manual Status of Compliance10. Reducing the speed of a vehicle to 20 kmph

can reduce emissions by a large extent. Speed

bumps are commonly used to ensure speed

reduction. In cases where speed reduction

cannot effectively reduce fugitive dust, it may

be necessary to divert traffic to nearby paved

areas.

Speed of the vehicles has beenrestricted

by erecting speed bumps at regular

intervals at project site and proper signage

will be provided for guided vehicular

movement and speed restrictions.

11. Material storages/ warehouses-Care should be

taken to keep all material storages adequately

covered and contained so that they are not

exposed to situations where winds on site

could lead to dust/ particulate emissions.

Fabrics and plastics for covering piles of soils

and debris is an effective means to reduce

fugitive dust.

Construction material will be stored in

storage yard.

B. Noise EnvironmentSetting up the barriers: National Building Code

2005 suggests that design solutions such as

barrier blocks should be used to reduce

external LA10 noise levels to at least 60-

70dB(A) at any point 1.0 m from any inward

looking façade.

The site has been enclosed with barricade

wall around the project boundary.

The DG sets will be acoustic enclosed

which conforms to the permissible noise

standards notified by MOEF.

C. Water Environment

1. Curing water should be sprayed on concrete

structures; free flow of water should not be

allowed for curing.

Curing chemical will be applied to reduce

the water demand.

2. After liberal curing on the first day, all

concrete structures should be painted with

curing chemical to save water. This will stop

daily water curing hence save water.

To save water curing chemicals will be

painted.

Page 19 of 22

Page 20: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

S. No. Points as per EIA Guidance Manual Status of Compliance3. Concrete structures should be covered with

thick cloth/gunny bags and then water should

be sprayed on them. This would avoid water

rebound and will ensure sustained and

complete curing.

Sewage treated water will be sprayed on

concrete structures. As well as to reduce

the demand concrete structure will be

cover with thick cloth/gunny bags.

4. Ponds should be made using cement and sand

mortar to avoid water flowing away from the

flat surface while curing

Ponds will be made using cement and

sand mortar to avoid water flowing away

from the flat surface while curing.

5. Water ponding should be done on all sunken

slabs; this would also highlight the importance

of having an impervious formwork.

Water ponding will be done.

(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO CONSTRUCTION

S. No. NGT Order dated 10.04.2015 Status of Compliance

1. Every builder or owner shall put tarpaulin on

scaffolding around the area of construction and

the building. No person including builder,

owner can be permitted to store any

construction material particularly sand on any

part of the street, roads in any colony.

Tarpaulin covers were provided around

the area of construction, wherever

required. No construction materials such

as cement, sand and aggregates was stored

at site.

2. The construction material of any kind that is

stored in the site will be fully covered in all

respects so that it does not disperse in the Air

in any form.

Construction material on site will be fully

covered.

Page 20 of 22

Page 21: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

S. No. NGT Order dated 10.04.2015 Status of Compliance

3. All the construction material and debris shall

be carried in the trucks or other vehicles which

are fully covered and protected so as to ensure

that the construction debris or the construction

material does not get dispersed into the air or

atmosphere, in any form whatsoever.

The trucks carrying construction materials

and debris will be suitably covered by

tarpaulin and plastic sheets.

4. The dust emissions from the construction site

should be completely controlled and all

precautions taken in that behalf.

Water sprinkling system will be provided

to control the dust emission.

5. The vehicles carrying construction material

and construction debris of any kind should be

cleaned before it is permitted to ply on the road

after unloading of such material.

Vehicles carrying construction material

and construction debris will be cleaned

before it permitted to ply on the road after

unloading of such material.

6. Every worker working on the construction site

and involved in loading, unloading and

carriage of construction material and

construction debris shall be provided with

mask to prevent inhalation of dust particles.

All health and safety measures of workers

will be taken during construction period.

7. Every owner and or builder shall be under

obligation to provide all medical help,

investigation and treatment to the workers

involved in the construction of building and

carry of construction material and debris

relatable to dust emission.

First aid facility has been provided at the

construction site.

8. It shall be the responsibility of every builder to

transport construction material and debris

waste to construction site, dumping site or any

other place in accordance with rules and in

terms of this order.

Construction material and debris waste

will be disposed off to construction site,

dumping site or any other place in

accordance with rules and in terms of this

order.

Page 21 of 22

Page 22: Mixed Use Development Project, Sector-72, Gurgaon, Haryana

S. No. NGT Order dated 10.04.2015 Status of Compliance

9. All to take appropriate measures and to ensure

that the terms and conditions of the earlier

order and these orders should strictly comply

with by fixing sprinklers, creations of green air

barriers.

Regular sprinkling of water will be carried

out at site at the construction.

10. Compulsory use of wet jet in grinding and

stone cutting.

Wet jet in grinding and stone cutting will

be used.

11. Wind breaking walls around construction site. Wind breaking walls will be provided

around the construction site.

12. All the builders who are building commercial,

residential complexes which are covered under

the EIA Notification of 2006 shall provide

green belt around the building that they

construct. All Authorities shall ensure that such

green belts are in existence prior to issuance of

occupancy certificate.

Green area will be developed as per

approved building plan.

Page 22 of 22