mixed use development project, sector-72, gurgaon, haryana
TRANSCRIPT
POINT-WISE COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE
E NVIRONMENTAL CLEARANCE LETTER NO. SEIAA/HR/2013/283
DATED 17 th June , 2013
Tata Center- Mixed Use Development Project, Sector-72, Gurgaon, Haryana
Sl.
No.
Conditions Status of Compliance
PART A – SPECIFIC CONDITIONS:
Construction Phase -
1 “Consent to Establish” shall be obtained from
Haryana State Pollution Control Board under
Air and Water Act and a copy shall be
submitted to the SEIAA, Haryana before the
start of any construction work at site.
Agreed. “Consent to Establish” has been
obtained from Haryana State Pollution
Control Board under Air and Water Act.
Copy of the same had been submitted to
SEIAA, Haryana along with previous
compliances. Copy of “Consent to
Establish” is enclosed as Annexure-I.
2 A first aid room as proposed in the project
report shall be provided both during
construction and operation phase of the
project.
Agreed. A first aid room has been provided
during the construction phase and same will
be maintained during operation phase of the
project.
3 Adequate drinking water and sanitary
facilities should be provided for construction
workers at the site. Provision should be made
for mobile toilets. Open defecation by
laboures is strictly prohibited. The safe
disposal of waste water and solid wastes
generated during the construction phase
should be ensured.
Agreed. Adequate drinking water and
sanitary facilities has been provided for
construction workers at site. Provisions are
there for mobile toilets. The safe disposal
of waste-water and solid wastes generated
during the construction phase is being
ensured.
Page 1 of 22
4 All top soil excavated during construction
activities should be stored for use in
horticulture/landscape development within the
project site.
Agreed. All the top soil excavated during
the construction activities is being properly
stored and will be utilized for the
horticulture/landscape development within
the site.
5 The project proponent shall ensure that the
building material required during construction
phase is properly stored within the project
area and disposal of construction waste
should not create any adverse effect on the
neighboring communities and should be
disposed of after taking necessary precautions
for general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
Agreed. Building material required during
construction phase has been properly stored
within the project area and construction
waste has been used for site development
and land filling of the project site, it will
not create any adverse effect on the
neighboring communities.
6 Construction spoils, including bituminous
material and other hazardous materials, must
not be allowed to contaminate watercourses
and dump sites for such material must be
secured so that they should not leach into the
ground water and any hazardous waste
generated during construction phase, should
be disposed off as per applicable rules and
norms with necessary approval of the Haryana
State Pollution Control Board.
Agreed. Construction spoils will be used
for site development and land filling of the
project site, other hazardous materials will
be disposed-off as per norms
7 The diesel generator sets to be used during
construction phase should be of ultra-low
sulphur diesel type and should confirm to
Environment (Protection) Rules prescribed
for air and noise emission standards.
Agreed. D.G sets used will be of low
sulphur diesel, conforming to Noise &
National Air Quality Standards.
8 The diesel required for operating DG sets
shall be stored in underground tanks and if
Agreed. The diesel required for operating
DG set will be stored in HDPEdrums and
Page 2 of 22
required, clearance from Chief Controller of
Explosives shall be taken.
log books will be managed for
accountability. Storage will be within the
threshold limit hence clearance from chief
control of explosive is not required.
9 Ambient noise levels should confirm to the
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be
closely monitored during the construction
phase. Adequate measures should be taken to
reduce ambient air and noise level during
construction phase, so as to confirm to the
stipulated residential standards.
Agreed. Ambient noise and ambient air has
been closely monitored during the
construction phase. Noise quality data
monitored is enclosed as Annexure-II.
10 Fly ash should be used as building material in
the construction as per the provisions of Fly
Ash Notification of September 1999 and as
amended on 27th August 2003.
Agreed. Fly ash based material will be
used.
11 Storm water control and its re-use as CGWB
and BIS standards for various applications
should be ensured.
Agreed. Storm water will be collected to
recharge the ground water, 08 RWH pits
are proposed to be constructed within the
project site for this purpose.
12 Water demand during construction should be
reduced by use of pre-mixed concrete, curing
agents and other best practices.
Agreed. Water demand during construction
will be reduced by use of pre-mixed
concrete, curing agents and other best
practices.
13 In view of the severe constrains in water
supply augmentation in the region and
sustainability of water resources, the
developer will submit the NOC from CGWB
specifying water extraction quantities and
assurance from HUDA/utility provider
Agreed. No ground water is extracted
during the construction as well as operation
phase. So, CGWB permission is not
required. However during construction
phase water is being supplied by HUDA
(Treated Water), permission letter from
Page 3 of 22
indicating source of water supply and quantity
of water with details of intended use of water
– potable and non-potable. Assurance is
required for both construction and operation
stages separately. It shall be submitted to the
SEIAA and RO, MOEF, Chandigarh before
the start of construction.
HUDA is enclosed as Annexure-III.
Duringoperational phase HUDA will
supply fresh water, copy of
acknowledgement is enclosed as
Annexure-IV.
14 Roof should meet prescriptive requirement as
per Energy Conservation Building Code by
using appropriate thermal insulation material.
Agreed. During construction phase care
will be taken that roof area meets Energy
Conservation Building Code requirement
by using appropriate thermal insulation
material to fulfill requirement.
15 Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
mandatory for all air conditioned spaces while
it is aspirational for non-air-conditioned
spaces by use of appropriate thermal
insulation material to fulfill requirement.
Agreed. Material having appropriate R &
U value will be used to meet prescriptive
requirement of opaque wall as per energy
conservation building Code.
16 The approval of the competent authority shall
be obtained for structural safety of the
building on account of earthquake, adequacy
of fire-fighting equipment, etc. as per
National Building Code including protection
measures from lightening etc. If any forest
land is involved in the proposal site, clearance
under Forest Conservation Act shall be
obtained from the competent authority.
Agreed. The approval of the competent
authority will be obtained for structural
safety of the building on account of
earthquake, adequacy of fire-fighting
equipment, etc. as per National Building
Code including protection measures from
lightening etc. The project site does not fall
under the Forest Conservation Act. Copy of
forest NOC is enclosed as Annexure-V
17 Overexploited groundwater and impending
severe shortage of water supply in the region
requires the developers to redraw the water
and energy conservation plan. Developer shall
Agreed. Ground water will not be
extracted. To recharge the ground water
level of the area rain water harvesting has
been proposed in the project. The water
Page 4 of 22
reduce the overall footprint of the proposed
development. Project proponent shall
incorporate water efficiency/savings measures
as well as water reuse/recycling within 3
months and before start of construction to the
SEIAA, Haryana and RO, MOEF, GOI,
Chandigarh.
reuse/recycling and water efficiency/saving
measures are being incorporated within 3
months and before start of construction to
SEIAA, Haryana and RO, MOEF, GOI,
Chandigarh.
18 The project proponent shall construct 08 rain
water harvesting pits for recharging the
ground water within the project premises.
Rain water harvesting pits shall be designed
to make provisions for silting chamber and
removal of floating matter before entering
harvesting pit. Maintenance budget and
persons responsible for maintenance must be
provided. Care shall also be taken that
contaminated water do not enter any RWH
pit.
Agreed. 08 rain water harvesting pits for
recharging the ground water within the
project premises will be constructed. Rain
water harvesting pits will be designed in
such a way that silt and floating material
will not enter in the ground water level..
Maintenance budget and persons
responsible for maintenance are being
provided and care will also be taken that
contaminated water do not enter any RWH
pit.Storm water plan showing the RWH pit
location is enclosed as Annexure-VI.
19 The project proponent will provide minimum
one hydraulic ladder for escape of people in
case of fire.
Agreed, permanent ladder will be provided
instead of hydraulic ladder. As hydraulic
ladder can be provided upto only 12m.
20 The project proponent shall submit assurance
from the DHBVN for supply of 5016KVA of
power supply before the start of the
construction. In no case project will be
operational solely on generators without any
power supply from any external power utility.
Agreed. An application has been filed to
the Superintending Engineer of HVPNL
for power supply. The acknowledgment
copy of the same is enclosed as Annexure
VII.
21 Detail calculation of power load and ultimate
power load of the project shall be submitted
to DHBVN under intimation to SEIAA
Haryana before the start of the construction.
Agreed. The total power requirement is
5016 KVA that will be supplied by
DHBVN. The detailed power load
calculation has been submitted to the
Page 5 of 22
Provisions shall be made for electrical
infrastructure in the project area.
DHBVN. An application has been filed to
the Superintending Engineer NCR
Planning. The acknowledgment copy of the
same is enclosed as Annexure VII.
22 The project proponent shall obtain NOC from
the nearest fire station before start of the
construction.
Agreed. An application has been filled to
municipal corporation Gurgaon for
obtaining the fire NOC. Acknowledgement
copy of the same is enclosed as Annexure
VIII
23 The project proponent shall not raise any
construction in the natural land
depression/Nallah/water course and shall
ensure that the natural flow from the
Nallah/water course is not obstructed.
Agreed. The project site does not contain
any natural land depression nallah/ water
course as well as no natural flow is
obstructed by the project.
24 The project proponent shall keep the plinth
level of the building blocks sufficiently above
the level of the approach road to the project as
per prescribed by-laws. Levels of the other
areas in the projects shall also be kept suitably
so as to avoid flooding.
Agreed. The plinth level of the building
blocks is being sufficiently above the level
of the approach road.. Section and
Elevation plan are enclosed as Annexure-
IX
25 Construction shall be carried out so that
density of population does not exceed norms
approved by Director General Town and
Country Department Haryana.
Agreed. As it is a mixed use development
project so, population density kept as per
the approved Building plan by Director
General Town and Country Department,
Haryana.
26 The project proponent shall submit an
affidavit with the declaration that ground
water will not be used for construction and
only treated water should be used for
construction.
Agreed. Ground water is not used for the
construction activity. An affidavit has been
submitted to SEIAA, Haryana. Copy of the
same is enclosed as Annexure-X.
27 The project proponent shall not cut any
existing tree and project landscaping plan
Agreed. As the project site was a vacant
land so there was no need to cut the trees.
Page 6 of 22
should be modified to include those trees in
green area
Plantation will be carried out around the
periphery of plot & along internal road
preferably with local species.
28 The project proponent shall provide helipad
facility as required under NBC norms and
shall seek permission of helipad from AAI
accordingly.
Agreed Helipad facility will be provided
for building having height more than 60m
as per NBC norms. NOc from avitation
department has been taken. Copy of AAI
NOC is enclosed as Annexure-XI.
29 The project proponent shall ensure that ECBC
norms for composite climate zone are met. In
particular building envelope, HVAC services,
water heating, pumping, lighting and
electrical infrastructure must meet ECBC
norms.
Agreed. ECBC norms for composite
climate zone, water heating, pumping,
lighting and electrical infrastructure are
being followed.
30 The project proponent shall provide 3m high
barricade around the project area, dust screen
for every floor above the ground, proper
sprinkling and covering of stored material to
restrict dust and air pollution during
construction.
Agreed. 3m high barricade around the
project area is being provided, dust screen
for every floor above the ground, proper
sprinkling and covering of stored material
to restrict dust and air pollution during
construction will be provided.
31 The project proponent shall construct a
sedimentation basin in the lower level of the
project site to trap pollutant and other wastes
during rains.
Agreed. Sedimentation basin constructed
to trap the pollutants and other wastes
during rains is being in lower level of the
project site.
32 The project proponent shall provide proper
Rasta of proper width and proper strength for
his project before the start of construction.
Agreed. Proper roads of adequate width
will be provided in the project for
movement of vehicle within the project
site. Site plan is enclosed as an Annexure-
XII.
33 The project proponent shall provide all the
safety measures for the workers during
construction phase of high rise building.
Agreed. All the safety measures for the
workers during construction phase of high
rise building will be provided.
Page 7 of 22
34 The project proponent shall ensure that the U-
value of the glass is less than 3.177 and
maximum solar heat gain co-efficient is 0.25
for vertical fenestration.
Agreed. Glass having U value less than
3.177 & maximum solar heat gain to
efficient 0.25 Vertical Fenestration will be
used.
35 The project proponent shall submit
permission of Municipal Commissioner
Gurgaon for disposal of excavated soil before
the start of construction.
Agreed. Mining approval is obtained from
the assistant mining engineer, Gurgaon,
Haryana. The copy of same is enclosed as
Annexure-XIII.
36 The project proponent shall seek NOC from
Town and Country department regarding
height of the building allowed in the skyline
of that city.
Agreed. NOC from Town and Country
department regarding height of the building
allowed in the skyline of that city is being
taken. Building plan approval from the
DTP is already obtained.
Operational phase -
a “Consent to Operate” shall be obtained from
Haryana State Pollution Control Board under
Air and Water Act and a copy shall be
submitted to the SEIAA, Haryana.
Agreed. Permission will be obtained after
completion of construction work of the
project.
b The STP shall be installed for the treatment of
the sewage to the prescribed standards
including odour and treated effluent will be
recycled. The installation of STP should be
certified by an independent expert and a
report in this regard should be submitted to
the SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
Discharge of treated sewage shall confirm to
norms and standards of HSPCB, Panchkula.
Project Proponent shall implement such STP
technology which does not require filter
Agreed. The Sewage Treatment Plant
(STP) will be installed for the treatment of
the sewage to be prescribed standards
including odor and treated effluent shall be
recycled to achieve zero exit discharge.
Installation of STP certified by an
independent expert will be submitted to the
SEIAA before start of operation stage of
the mixed use project. Plumbing plan
showing the STP location is enclosed as
Annexure-XIV.
Page 8 of 22
backwash.
c Separation of the grey and black water should
be done by the use of dual plumbing line.
Treatment of 100% grey water by
decentralized treatment should be done
ensuring that the re-circulated water should
have BOD maximum 10 mg/litre and the
recycled water will be used for flushing,
gardening and DG set cooling and running of
fountain in the water body to achieve zero exit
discharge.
Agreed. Treatment of grey and black water
will be done. Dual plumbing plan and water
balance diagram are attached as Annexure
–XV.
d For disinfection of the treated wastewater
ultra-violate radiation or ozonization process
should be used.
Agreed. For disinfection of the treated
wastewater ultra-violet radiation or
ozonization process will be used.
e The solid waste generated should be properly
collected and segregated. Bio-degradable
waste shall be decomposed at site and
dry/inert solid waste should be disposed-off to
approved sites for land filling after recovering
recyclable material.
Agreed. The solid waste generated will be
properly collected and segregated. Bio-
degradable waste will be decomposed at
site and dry/inert solid waste will be
disposed-off to approve sites for land filling
after recovering recyclable material.
f Diesel power generating sets proposed as
source of back-up power for lifts, common
area illumination and for domestic use should
be enclosed type and conform to rules made
under the Environmental (Protection) Act,
1986. The location of the DG sets should be
in the basement as promised by the project
proponent with appropriate stack height i.e
above the roof level as per the CPCB norms.
The diesel used for DG sets should be ultra
low sulphur diesel (0.05% sulphur), instead of
low sulphur diesel.
D.G. Sets to be used for power back up are
of enclosed type and confirming to rules
made under the Environment (Protection)
Act, 1986. The D.G. sets are run on low
sulphur diesel.
Page 9 of 22
g Ambient Noise level should be controlled to
ensure that it does not exceed the prescribed
standards both within and at the boundary of
the Proposed Residential Complex
Agreed. Ambient Noise level is being
controlled to ensure that it does not exceed
the prescribed standards both within and at
the boundary of the Residential Complex.
A copy of ambient noise quality data is
enclosed as Annexure-II.
h The project proponent should maintain at
least 22% as green cover area for tree
plantation especially all around the periphery
of the project and on the road sides preferably
with local species so as to provide protection
against particulars and noise. The 8% open
spaces inside the plot should be preferably
landscaped and covered with vegetation/grass,
herbs & shrubs. Only locally available plant
species shall be used.
Agreed. Project Proponent will provide
30% as a green area. Landscape plan is
enclosed as Annexure –XVI.
i The project proponent shall strive to
minimum water in irrigation of landscape by
minimizing grass area, using native variety,
xeriscaping and mulching, utilizing
efficientirrigation system, scheduling
irrigation only after checking evapo-
transpiration data.
Agreed. Minimum water will be used in
irrigation of landscape by minimizing grass
area, using native variety, xeriscaping and
mulching, utilizing efficient irrigation
system, scheduling irrigation. Treated water
will be used for the landscaping purposes.
j Rain water harvesting for roof run-off and
surface, as per plan submitted should be
implemented. Before recharging the surface
run-off, pre-treatment through sedimentation
tanks must be done to remove suspended
matter, oil and grease. The bore well for
rainwater recharging should be kept at least
5m. above the highest ground water table.
Care shall be taken that contaminated water
Agreed. Rain water harvesting for roof
run-off and surface, as per plan submitted
will be implemented. Before recharging the
surface run-off, pre-treatment through
sedimentation tanks will be done to remove
suspended matter, oil and grease. The bore
well for rainwater recharging will be kept
at least 5m above the highest ground water
table. Rain water harvesting plan is
Page 10 of 22
do not enter any RWH pit. The project
proponent shall avoid RWH of first 10
minutes of rain fall. Roof top of the building
shall be without any toxic material or paint
which can contaminate rain water. Wire mess
and filters should be used wherever required.
enclosed as Annexure-VI.
k The ground water level and its quality should
be monitored regularly in consultation with
Central Ground Water Authority.
The ground water level and its quality is
being monitored in consultation with
Central Ground Water Authority.
l There should be no traffic congestion near the
entry and exit points from the roads adjoining
the proposed project site. Parking should be
fully internalized and no space should be
utilized.
Agreed. There is no traffic congestion near
the entry and exit points from the roads
adjoining the project site. Parking will be
fully internalized and no public space will
be utilized. A traffic plan is enclosed as
Annexure-XVII.
m A report on the energy conservation measures
conforming to energy conservation norms
finalized by Bureau of Energy Efficiency
should be prepared incorporating details about
building materials & technology, R & U
Factors etc and submit to the SEIAA,
Haryana in three month time.
Agreed. A report on the energy
conservation measures conforming to
energy conservation norms finalized by
Bureau of Energy Efficiency is being
prepared incorporating details about
building materials & technology, R & U
Factors etc has been submit to the SEIAA,
Haryana in three month time.
n Energy conservation measures like
installation of LED for Lighting the areas
outside the building should be integral part of
the project design and should be in place
before project commissioning. Use of solar
panels must be adapted to the maximum
energy conservation.
Agreed. Energy conservation measures like
installation of CFLs/TFLs for lighting the
areas outside the building is integral part of
the project design and shall be in place
before project commissioning. Solar
lighting is proposed for open spaces and
signage.
o The project proponent shall use zero ozone
depleting potential material in insulation,
Agreed. As it is a Mixed Use Development
Project, all the material going to be use like
Page 11 of 22
refrigeration, air-conditioning and adhesive.
Project proponent shall also provide Halon
free fire suppression system.
refrigeration, air-conditioning etc. are of
non-ozone depleting.
p The solid waste generated should be properly
collected and segregated as per the
requirement of the MSW Rules, 2000 and as
amended from time to time. The bio-
degradable waste should be composed by
vermin-composting at the site war marked
within the project area and dry/inert solid
waste should be disposed-off to the approved
sites for land-filling after recovering
recyclable material.
Agreed. Solid waste generated will be
collected & segregated as per MSW rule,
2000. Bio degradable waste will be
composed by vermin-composting.
q The provision of the solar water heating
system shall be as per norms specified by
HAREDA and shall be made operational in
each building block.
Agreed. As it is a Mixed Use Development
Project, solar water heating system will be
used as per norms by HAREDA.
r The traffic plan and the parking plan proposed
by the project proponent should be adhered to
meticulously with further scope of additional
parking for future requirement. There should
be no traffic congestion near the entry and
exit points from the roads adjoining the
proposed project site. Parking should be fully
internalized and no public space should be
used.
Agreed. The traffic plan is being
meticulously adhered to with further scope
of additional parking for future
requirement. Parking is being completely
internalized and no public space is being
utilized. Care is being taken to ensure that
there will be no traffic congestion at the
entry and exit points.
s The project shall be operationalized only
when HUDA/public authority will provide
domestic water supply system in the areas.
Agreed. The project shall be
operationalized only when HUDA/public
authority will provide domestic water
supply system in the areas.
t Operation and maintenance of STP, solid
waste management and electrical
Agreed. Operation and maintenance of
STP, solid waste management and
Page 12 of 22
Infrastructure, pollution control measures
shall be ensured even after the completion of
sale.
electrical Infrastructure, pollution control
measures will be ensured even after the
completion of sale.
u Different type of waste should be disposed-
off as per provisions of municipal solid waste,
biomedical waste, hazardous waste, e-waste,
batteries & plastic rules made under
Environment Protection Act, 1986.
Particularly E-Waste and Battery waste shall
be disposed of as per existing E-waste
Management Rules 2011 and Batteries
Management Rules 2001. The project
proponent should maintain a collection center
for E-Waste and it should be disposed of to
only registered and authorized
dismantler/recycler.
Agreed. MSW will be disposed off as per
provisions of municipal solid waste made
under Environment Protection Act, 1986.
Negligible quantity of hazardous waste, e-
waste, and plastic waste generated will be
disposed off as per hazardous waste, e-
waste, batteries & plastic rules made under
Environment Protection Act, 1986.
v Standards for discharging of environmental
pollutants as enshrined in various schedules
of rules 3 of Environment Protection Rules
1986 shall be strictly complied with.
Agreed. Standards for discharging of
environmental pollutants as enshrined in
various schedules of rules 3 of
Environment Protection Rules 1986 will be
strictly complied with.
w Water supply be metered to different
residential units and different utilities.
Agreed. Water supply will be metered to
different units and different utilities.
x The project proponent shall ensure that the
stack height of DG sets is as per the CPCB
guide lines and also ensure that the emission
standards of noise and air are within the
CPCB prescribed limits. Noise and Emission
level of DG sets are greater than 800KVA
shall be as per CBCB latest standards for high
Agreed. Stack height of DG sets are kept 6
mtrs above the roof level as per the CPCB
guide lines and also ensured that the
emission standards of noise and air are
within the CPCB prescribed limits.
Page 13 of 22
capacity DG sets.
y All electric supply exceeding 100amp, 3-
phase shall maintain the power factor between
0.98 lag to 1 at the point of connection.
Agreed. All electric supply exceeding
100amp, 3-phase will be maintain the
power factor between 0.98 lag to 1 at the
point of connection.
z The project proponent shall use only treated
water instead of fresh water for HVAC and
DG cooling. The project proponent shall use
evaporative cooling technology and double
stage cooling system for HVAC in order to
reduce water consumption. Further
temperature, relative humidity during summer
and winter session should be kept at optimal
level. Variable speed drive, best co-efficient
of performance, as well as optimal integrated
point load value and minimum outside fresh
air supply may be resorted for conservation of
power and water. Coil type cooling DG sets
shall be used for saving cooling water
consumption for water cooled DG sets.
Agreed. Instead of fresh water for DG
cooling, treated water will be used.
Evaporative cooling technology and double
stage cooling system is being used for
HVAC in order to reduce water
consumption. Maximum treated water will
be used for various processes instead of
fresh water to reduce the water
consumption.
PART-B GENERAL CONDITIONS :-
i The project proponent should ensure the
commitments made in Form-1, Form-1A,
EIA/EMP and other documents submitted to
the SEIAA for protection of environment and
proposed environmental safeguards are
complied with in letter and spirit. In case of
contradiction between two or more documents
on any point, the most environmentally
friendly commitment on the point shall be
Agreed. All safeguards mentioned in the
application are being implemented during
the construction phase and will be
implemented during the operation phase.
Page 14 of 22
taken as commitment by project proponent.
ii Six monthly compliance reports should be
submitted to the Haryana State Pollution
Control Board and Regional Office, MoEF,
GOT, Northern Region, Chandigarh and a
copy to the SEIAA Panchkula, Haryana.
Agreed. Six monthly compliance report is
being submitted to the Haryana State
Pollution Control Board and Regional
Office, MoEF, GOI, Northern Region,
Chandigarh, Haryana.
iii Noise , STP outlet and stack emission shall be
monitored daily. Other environmental
parameters shall be monitored on monthly
basis. After every 3 months the project
proponent shall conduct environmental audit
and shall take corrective measure, if required,
without delay.
Agreed. Noise, STP outlet and stack
emission will be monitored daily. Other
environmental parameters will be
monitored on monthly basis. After every 3
months environmental audit will be
conducted and corrective measure will be
taken, if required, without delay.
iv The SEIAA, Haryana reserves the right to add
additional safeguard measures subsequently,
if found necessary. Environmental Clearance
granted will be revoked if it is found that false
information has been given for getting
approval of this project. SEIAA reserves the
right to revoke the clearance if conditions
stipulated are not implemented to the
satisfaction of SEIAA/MOEF.
Agreed. The SEIAA, Haryana reserves the
right to add additional safeguard measures
subsequently, if found necessary.
Environmental Clearance granted will be
revoked if it is found that false information
has been given for getting approval of this
project. SEIAA reserves the right to revoke
the clearance if conditions stipulated are
not implemented to the satisfaction of
SEIAA/MOEF.
v The project proponent shall not violate any
judicial orders/pronouncements issued by any
Court/Tribunal.
No judicial order/ pronouncements issued
by the Hon’ble Supreme Court/High Courts
to the developers.
vi All other statutory clearances such as the
approvals for storage of diesel from Chief
Controller of Explosives, Fire Department,
Civil Aviation Department, Forest
Agreed. All the required applicable
clearances have been taken from the
respective authority.
Forest NOC is enclosed as Annexure-V
Page 15 of 22
Conservation Act, 1980 and Wildlife
(Protection) Act. 1972, Forest Act, 1927,
PLPA 1900, etc. shall be obtained, as
applicable by project proponents from the
respective authorities prior to construction of
the project.
AAI NOC is enclosed as Annexure-X
NOC from Chief Controller of Explosive
shall be taken at the appropriate stage.
vii The project proponent should inform the
public that the project has be accorded
Environment Clearance by the SEIAA and
copies of the clearance letter are available
with the Haryana State Pollution Control
Board & SEIAA. This should be advertised
within 7 days from the date of issue of
clearance letter at least in two local
newspapers that are widely circulated in the
region and the copy of the same be forwarded
to SEIAA Haryana. A copy of Environment
Clearance collections shall also be put on
project proponent’s website for public
awareness.
Agreed. A copy of advertisement has been
advertised in two local newspapers.
viii Any appeal against this Environmental
Clearance shall lie with the National Green
Tribunal, if preferred within a period of 30
days as prescribed under Section 16 of the
National Green Tribunal Act, 2010.
Agreed. Any appeal against this
Environmental Clearance shall lie with the
National Green Tribunal, if preferred
within a period of 30 days as prescribed
under section 16 of the National Green
Tribunal Act, 2010.
ix The project proponent shall put in place
Corporate Environment Policy as mentioned
in MOEF, GOI, ON No. J-11013/41/2006-IA
II (I) dated 26.04.12 within 3 months period.
Latest Corporate Environment Policy should
Agreed. The project proponent shall put in
place Corporate Environment Policy as
mentioned in MOEF, GOI, ON No. J-
11013/41/2006-IA II (I) dated 26.04.12
within 3 months period. Latest Corporate
Page 16 of 22
be submitted to SEIAA within 3 months of
issuance of this letter.
Environment Policy should be submitted to
SEIAA within 3 months of issuance of this
letter.
x The fund ear-marked for environment
protection measures should be kept in
separate account and should not be diverted
for other purposes and year wise expenditure
shall be reported to the SEIAA/RO MoEF
GOI under rules prescribed for Environment
Audit.
Agreed. The fund ear-marked for
environment protection measures is being
kept in separate account and will not be
diverted for other purposes and year wise
expenditure will be reported to the
SEIAA/RO MoEF GOI under rules
prescribed for Environment Audit.
xi The project proponent shall obtain NOC
under Aravalli Notification from CEC of
Hon’ble Supreme court regarding coverage
under Aravalli Notification before start of
construction.
Agreed. Application has already given to
the District Collector, Gurgaon, Haryana
for taking clearance of Forest and Aravalli
Acknowledgment copy is enclosed as
Annexure-V.
xii The project proponent shall ensure that no
vehicle during construction/operation phase
enter the project premises without valid
‘Pollution Under Control’ certificate from
competent Authority.
Agreed. It is being ensured that no vehicle
during construction/operation phase enter
the project premises without valid
‘Pollution Under Control’ certificate from
competent Authority.
B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF
S. No. Points as per EIA Guidance Manual Status of ComplianceA. Air Environment1. Wind erosion is a serious problem in areas
where the ground is virtually bare and devoid
of vegetation. Vegetation methods are found to
be most effective in the form of windbreaks
and shelterbelts.
Windbreaks and shelterbelts will be
provided to reduce wind erosion during
the construction phase.
Page 17 of 22
S. No. Points as per EIA Guidance Manual Status of Compliance2. Sprinkling of water and fine spray from
nozzles to suppress the dust.
Sprinkling will be provided during the
construction phase.
3. On-Road-Inspection should be done for black
smoke generating machinery.
All the machineries used at site having
highest standard and of reputed make and
will be compiled with emission & noise
standards.
4. Promotion of use of cleaner fuel should be
done.
Ultra low sulphur diesel (ULSD) (sulphur
content less than 0.05%) wil be use for
running of DG sets, vehicles and
construction machineries.
5. All DG sets should comply emission norms
notified by MoEF.
The DG sets used in such a way that it
will comply with the emission norms
notified by MoEF.
6. Vehicles having pollution under control
certificate may be allowed to ply.
It will be ensured that all the vehicles used
for construction activities having valid
Pollution Under Check (PUC) certificates.
The vehicles without valid Pollution
Under Check (PUC) certificate is not
permitted at project site.
7. Use of covering sheet to prevent dust
dispersion at buildings and infrastructure sites,
which are being constructed.
Covering sheet will be use to prevent dust
dispersion during the construction phase.
8. Use of covering sheets should be done for
trucks to prevent dust dispersion from the
trucks, implemented by district offices.
Covering sheets will be use on trucks to
prevent dust dispersion from the trucks.
9. Paving is a more permanent solution to dust
control, suitable for longer duration projects.
High cost is the major drawback to paving.
During construction, access road has been
covered with gravels to prevent dust
emission.
Page 18 of 22
S. No. Points as per EIA Guidance Manual Status of Compliance10. Reducing the speed of a vehicle to 20 kmph
can reduce emissions by a large extent. Speed
bumps are commonly used to ensure speed
reduction. In cases where speed reduction
cannot effectively reduce fugitive dust, it may
be necessary to divert traffic to nearby paved
areas.
Speed of the vehicles has beenrestricted
by erecting speed bumps at regular
intervals at project site and proper signage
will be provided for guided vehicular
movement and speed restrictions.
11. Material storages/ warehouses-Care should be
taken to keep all material storages adequately
covered and contained so that they are not
exposed to situations where winds on site
could lead to dust/ particulate emissions.
Fabrics and plastics for covering piles of soils
and debris is an effective means to reduce
fugitive dust.
Construction material will be stored in
storage yard.
B. Noise EnvironmentSetting up the barriers: National Building Code
2005 suggests that design solutions such as
barrier blocks should be used to reduce
external LA10 noise levels to at least 60-
70dB(A) at any point 1.0 m from any inward
looking façade.
The site has been enclosed with barricade
wall around the project boundary.
The DG sets will be acoustic enclosed
which conforms to the permissible noise
standards notified by MOEF.
C. Water Environment
1. Curing water should be sprayed on concrete
structures; free flow of water should not be
allowed for curing.
Curing chemical will be applied to reduce
the water demand.
2. After liberal curing on the first day, all
concrete structures should be painted with
curing chemical to save water. This will stop
daily water curing hence save water.
To save water curing chemicals will be
painted.
Page 19 of 22
S. No. Points as per EIA Guidance Manual Status of Compliance3. Concrete structures should be covered with
thick cloth/gunny bags and then water should
be sprayed on them. This would avoid water
rebound and will ensure sustained and
complete curing.
Sewage treated water will be sprayed on
concrete structures. As well as to reduce
the demand concrete structure will be
cover with thick cloth/gunny bags.
4. Ponds should be made using cement and sand
mortar to avoid water flowing away from the
flat surface while curing
Ponds will be made using cement and
sand mortar to avoid water flowing away
from the flat surface while curing.
5. Water ponding should be done on all sunken
slabs; this would also highlight the importance
of having an impervious formwork.
Water ponding will be done.
(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO CONSTRUCTION
S. No. NGT Order dated 10.04.2015 Status of Compliance
1. Every builder or owner shall put tarpaulin on
scaffolding around the area of construction and
the building. No person including builder,
owner can be permitted to store any
construction material particularly sand on any
part of the street, roads in any colony.
Tarpaulin covers were provided around
the area of construction, wherever
required. No construction materials such
as cement, sand and aggregates was stored
at site.
2. The construction material of any kind that is
stored in the site will be fully covered in all
respects so that it does not disperse in the Air
in any form.
Construction material on site will be fully
covered.
Page 20 of 22
S. No. NGT Order dated 10.04.2015 Status of Compliance
3. All the construction material and debris shall
be carried in the trucks or other vehicles which
are fully covered and protected so as to ensure
that the construction debris or the construction
material does not get dispersed into the air or
atmosphere, in any form whatsoever.
The trucks carrying construction materials
and debris will be suitably covered by
tarpaulin and plastic sheets.
4. The dust emissions from the construction site
should be completely controlled and all
precautions taken in that behalf.
Water sprinkling system will be provided
to control the dust emission.
5. The vehicles carrying construction material
and construction debris of any kind should be
cleaned before it is permitted to ply on the road
after unloading of such material.
Vehicles carrying construction material
and construction debris will be cleaned
before it permitted to ply on the road after
unloading of such material.
6. Every worker working on the construction site
and involved in loading, unloading and
carriage of construction material and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
All health and safety measures of workers
will be taken during construction period.
7. Every owner and or builder shall be under
obligation to provide all medical help,
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
First aid facility has been provided at the
construction site.
8. It shall be the responsibility of every builder to
transport construction material and debris
waste to construction site, dumping site or any
other place in accordance with rules and in
terms of this order.
Construction material and debris waste
will be disposed off to construction site,
dumping site or any other place in
accordance with rules and in terms of this
order.
Page 21 of 22
S. No. NGT Order dated 10.04.2015 Status of Compliance
9. All to take appropriate measures and to ensure
that the terms and conditions of the earlier
order and these orders should strictly comply
with by fixing sprinklers, creations of green air
barriers.
Regular sprinkling of water will be carried
out at site at the construction.
10. Compulsory use of wet jet in grinding and
stone cutting.
Wet jet in grinding and stone cutting will
be used.
11. Wind breaking walls around construction site. Wind breaking walls will be provided
around the construction site.
12. All the builders who are building commercial,
residential complexes which are covered under
the EIA Notification of 2006 shall provide
green belt around the building that they
construct. All Authorities shall ensure that such
green belts are in existence prior to issuance of
occupancy certificate.
Green area will be developed as per
approved building plan.
Page 22 of 22