mm subsea case study pack
TRANSCRIPT
-
8/17/2019 MM Subsea Case Study Pack
1/12
CASE STUDY
www.miragemachines.com
Subsea
Case Studies
-
8/17/2019 MM Subsea Case Study Pack
2/12
CASE STUDY
www.miragemachines.com
Contents
• Subsea Window Machining
• Subsea Pipe Cutting
• Weld Seam Removal
• Platform Leg Crack Termination
• Tidal Fin Removal
• Seam Weld and Doubler Plate Removal
• CIMV Removal & Torque Tool Development
• Injection Point in Trace Heated Supply Line
• About Mirage Machines
-
8/17/2019 MM Subsea Case Study Pack
3/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Subsea WindowMachining Case Study
PORTABLE PERFORMANCE
A 26-1/2” conductor required a 1.3 x 0.45m windowmachining with 50mm radii 9m from the sea bed for a
mud dump vent clamp to be fitted.
Location: Apache North Sea – Forties Delta – 115m
water depth.
Requirements
Cold cutting was specified due to the 26-1/2”
conductor housing 13-3/8” casing and a power line
that could not be damaged during cutting.
The four corners were pilot drilled and then the 4 off100mm diameter holes were trepanned at fixed
centres, with hydraulic valves acting as datum point
stops. The gantry system was then used to mill
between the corners to produce the window. The cut
out portion of the conductor was retained by cross
member clamps with drilled and tapped holes in the
conductor.
Drilling and trepanning took 45 minutes per hole,
machining top, bottom and sides through conductor
thickness.
Equipment used
• Mirage gantry GM2000 and milling rail MR1500.
• Used with a chain pipe clamp.
Solution
• Machining completed within 2 days.
• Operation time kept to a minimum using
hydraulic stops and auto feeds on the main axis.
.
Outcomes
Workshop trial.
Milling rail mounted onto the Gantry system
with large hand wheel for the diver to control
the in feed. The auto stop hydraulic valves
controlled the size of the window and
spindle positioning.
Click to watch the
YouTube video
https://www.youtube.com/watch?v=r6acVR6Zgo4https://www.youtube.com/watch?v=r6acVR6Zgo4
-
8/17/2019 MM Subsea Case Study Pack
4/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Subsea PipeCutting
Case Study
PORTABLE PERFORMANCE
• To remove a 512 metre length of Super
Duplex pipe from the sea bed, at a depth of
50 metres. Pipe specification 12” diameter
with a 1” wall thickness.• Location: Saudi Arabia.
Requirements
• The Mirage MDWS used with a 3 circuit
hydraulic controller. The diamond wire
travelled at 1200 metres per minute at a
feed rate set at 8mm per minute.
Solution
• 22 cuts made within 72 hours.
• Pipe sections around 23m long raised to deck.
• With the pipeline removed the customer was
able to construct a new pipeline.
Outcomes
The first two pipe sections recovered from the sea bed.
The MDWS being lowered into the sea.
Click to watch the
Diamond Wire Saw
animation on YouTube
https://www.youtube.com/watch?v=h5KNAyN3dHAhttps://www.youtube.com/watch?v=h5KNAyN3dHA
-
8/17/2019 MM Subsea Case Study Pack
5/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Weld SeamRemoval
Case Study
PORTABLE PERFORMANCE
Removal of a longitudinal weld seam to allow fitting
of a ‘Morgrip’ connector.
Location: Apache North Sea, Forties Delta.
Requirements
• Use of the Mirage MR1500SS milling rail
• Workshop trials carried out in advance.
Solution
Successful machining allowed fitting of the
‘Morgrip’ mechanical connector.
.
Outcome
Workshop trial.
Subsea cutting operation.
-
8/17/2019 MM Subsea Case Study Pack
6/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Platform LegCrack Termination
Case Study
PORTABLE PERFORMANCE
Cracking discovered in the main caisson around a
vent exhaust duct on the platform leg.
The requirement was to machine an elliptical hole
into a 5m diameter platform leg.
Location: Siri Platform, Denmark.
Requirements
• Use the Mirage 3 axis gantry milling
machine.
• Workshop trials carried out in advance.
Solution
All machining operations were completed first
time, to customer’s specification and within
time critical operations window.
.
Outcome
Workshop trial.
-
8/17/2019 MM Subsea Case Study Pack
7/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Tidal Fin Removal
Case Study
PORTABLE PERFORMANCE
• Structural plates required removal from tidal
turbine monopoles.
• Diving time severely restricted to 20 minutes due
to tidal direction change and ‘Neap Tide’.
Requirements
• Plates (1.8m x 150mm x 30mm) removed
using a slitting saw. Remaining material
removed using face milling.
• Quick release tooling used to allow fast
project completion.
Solution
All machining operations were completed first
time, to specification and within time criticaloperations window.
.
Outcome
Workshop trials using the Mirage MR2000.
-
8/17/2019 MM Subsea Case Study Pack
8/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Seam Weld andDoubler PlateRemoval
Case Study
PORTABLE PERFORMANCE
• Remove a seam weld from 30” pipeline
over 3m length.
• Remove anode doubler plates for
relocation at 90m water depth.
• Location: North Sea.
Requirements
• Cold cutting to prevent cutting into the
parent pipeline.
• Use of Mirage gantry MR1000SS with
pipe chain clamping system, fixed feed,
and depth stops.• Workshop trials carried out on a circular
test piece.
Solution
• Milling of seam: less than 1 hour.
• Doubler plate removed in 3 hours.
Outcomes
-
8/17/2019 MM Subsea Case Study Pack
9/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
CIMV Removal& Torque ToolDevelopment
Case Study
PORTABLE PERFORMANCE
The client’s problem was a subsea tree equipped
with a latch lock removal system on a chemical
injection valve which had a mechanical failure on
the connection rod.
Requirements
Mirage developed three innovative contingency
solutions to allow an ROV to remove the valve.
The first solution used a one inch, left-handed, four
flute endmill to attempt to turn the inconel rod to
unlatch the CIMV. This solution was delivered to the
Client’s design, but was unable to remove the
damaged valve.
Second solution: Having anticipated that a second
solution might be required, we designed and
engineered a contingency tool, which incorporated an
eight inch lathe chuck, with ROV handles, to deploythe latch onto the inconel rod, in an attempt to turn
the inconel rod to unlatch the valve. This tool was
successful in removing the valve.
Third solution: We designed an additional
contingency tool, which was a hydraulically operated
chucking system. This solution was not deployed, as
the valve was removed with solution two.
Solution
• The client’s problem was resolved.
• All three tooling solutions were provided in 10 days.
• Client requested we design a tool to prevent the
problem from occurring in the future.
Outcomes
The resulting torque tool created for
the customer.
Workshop development of contingency solutions.
-
8/17/2019 MM Subsea Case Study Pack
10/12
www.miragemachines.comEmail [email protected]
PORTABLE PERFORMANCE
05.02.16
Injection Point in Trace HeatedSupply Line
Case Study
PORTABLE PERFORMANCE
• To machine an injection point within a
heavy wall Super Duplex pipe.
• No swarf ingress or tool dwelling.
• One chance on offshore application.
Location: Islay Project, North Sea.
Requirements
• Mirage provided a complete
machine/offshore service package.
• A process was identified to series
trepan the external of the supply line.• Extensive workshop testing carried out
in advance.
• Machine used: HT50 Portable Drill
Solution
Client testimonial:
“ Did a great job offshore and everyone
was very pleased ”
Outcomes
Images above: Test pieces in the workshop.
-
8/17/2019 MM Subsea Case Study Pack
11/12
www.miragemachines.comEmail [email protected]
IndustriesMirage manufacture a range of portable machines for a wide variety of
applications and industries including:
Our products are supported by industry experts who work closely with our
customers to optimise performance for industry specific applications.
With extensive experience within service companies, our teams understand
the dynamics of a wide range of industries and have the capability to
deliver turn-key solutions that both meet specific requirements and address
complex challenges.
About Mirage MachinesMirage portable machine tools optimise the performance of on-site
assets by achieving operational excellence, maximising uptime and
improving productivity.
Our proprietary technology drives the development of the most reliable,
durable, efficient and precise portable machine tools on the market, that
are capable of delivering the most exacting standards of tolerance with the
highest quality output.
Our portfolio of portable machine tools are suitable for a diverse range of
on-site machining applications. Mirage have been granted ISO 9001:2008certification for our design and manufacturing systems
and we are able to provide full CE certification for our products.
• Oil & Gas • Mining & Construction
• Wind Power • Subsea
• Decommissioning • Utilities
• Ship Build & Repair • Nuclear
• Petrochemical • Power Generation
-
8/17/2019 MM Subsea Case Study Pack
12/12
www.miragemachines.comEmail [email protected]
Contact Us
UKMirage Machines
8-10 Enterprise Way
Jubilee Parkway
Stores Road
Derby DE21 4BB
T: +44 (0) 1332 291767
F: +44 (0) 1332 370356
SingaporeMirage Machines
107 Tuas South Avenue 8
Offshore Marine Centre 637036
Singapore
Tel: +65 9855 0117
PerthMirage Machines
15/4 Wharton Road
Kewdale
WA 6105
Tel: +61 0 452 48 1964
HoustonMirage Subsea Inc.
8615 Jackrabbit Rd
Houston
TX 77095
United States
Tel: +1-281-859-1234