mm subsea case study pack

Upload: jromerorpg

Post on 06-Jul-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 MM Subsea Case Study Pack

    1/12

    CASE STUDY

    www.miragemachines.com

    Subsea

    Case Studies

  • 8/17/2019 MM Subsea Case Study Pack

    2/12

    CASE STUDY

    www.miragemachines.com

    Contents

    • Subsea Window Machining 

    • Subsea Pipe Cutting 

    • Weld Seam Removal

    • Platform Leg Crack Termination

    •  Tidal Fin Removal

    • Seam Weld and Doubler Plate Removal

    • CIMV Removal & Torque Tool Development

    • Injection Point in Trace Heated Supply Line

    • About Mirage Machines

  • 8/17/2019 MM Subsea Case Study Pack

    3/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    Subsea WindowMachining Case Study

    PORTABLE PERFORMANCE

     A 26-1/2” conductor required a 1.3 x 0.45m windowmachining with 50mm radii 9m from the sea bed for a

    mud dump vent clamp to be fitted.

    Location: Apache North Sea – Forties Delta – 115m

    water depth.

    Requirements

    Cold cutting was specified due to the 26-1/2”

    conductor housing 13-3/8” casing and a power line

    that could not be damaged during cutting.

    The four corners were pilot drilled and then the 4 off100mm diameter holes were trepanned at fixed

    centres, with hydraulic valves acting as datum point

    stops. The gantry system was then used to mill

    between the corners to produce the window. The cut

    out portion of the conductor was retained by cross

    member clamps with drilled and tapped holes in the

    conductor.

    Drilling and trepanning took 45 minutes per hole,

    machining top, bottom and sides through conductor

    thickness.

    Equipment used

    • Mirage gantry GM2000 and milling rail MR1500.

    • Used with a chain pipe clamp.

    Solution

    • Machining completed within 2 days.

    • Operation time kept to a minimum using

    hydraulic stops and auto feeds on the main axis.

    .

    Outcomes

    Workshop trial.

    Milling rail mounted onto the Gantry system

    with large hand wheel for the diver to control

    the in feed. The auto stop hydraulic valves

    controlled the size of the window and

    spindle positioning.

    Click to watch the

     YouTube video

    https://www.youtube.com/watch?v=r6acVR6Zgo4https://www.youtube.com/watch?v=r6acVR6Zgo4

  • 8/17/2019 MM Subsea Case Study Pack

    4/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    Subsea PipeCutting 

    Case Study

    PORTABLE PERFORMANCE

    • To remove a 512 metre length of Super

    Duplex pipe from the sea bed, at a depth of

    50 metres. Pipe specification 12” diameter

    with a 1” wall thickness.• Location: Saudi Arabia.

    Requirements

    • The Mirage MDWS used with a 3 circuit

    hydraulic controller. The diamond wire

    travelled at 1200 metres per minute at a

    feed rate set at 8mm per minute.

    Solution

    • 22 cuts made within 72 hours.

    • Pipe sections around 23m long raised to deck.

    • With the pipeline removed the customer was

    able to construct a new pipeline.

    Outcomes

    The first two pipe sections recovered from the sea bed.

    The MDWS being lowered into the sea.

    Click to watch the

    Diamond Wire Saw

    animation on YouTube

    https://www.youtube.com/watch?v=h5KNAyN3dHAhttps://www.youtube.com/watch?v=h5KNAyN3dHA

  • 8/17/2019 MM Subsea Case Study Pack

    5/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    Weld SeamRemoval

    Case Study

    PORTABLE PERFORMANCE

    Removal of a longitudinal weld seam to allow fitting

    of a ‘Morgrip’ connector.

    Location: Apache North Sea, Forties Delta.

    Requirements

    • Use of the Mirage MR1500SS milling rail

    • Workshop trials carried out in advance.

    Solution

    Successful machining allowed fitting of the

    ‘Morgrip’ mechanical connector.

    .

    Outcome

    Workshop trial.

    Subsea cutting operation.

  • 8/17/2019 MM Subsea Case Study Pack

    6/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    Platform LegCrack Termination

    Case Study

    PORTABLE PERFORMANCE

    Cracking discovered in the main caisson around a

    vent exhaust duct on the platform leg.

    The requirement was to machine an elliptical hole

    into a 5m diameter platform leg.

    Location: Siri Platform, Denmark.

    Requirements

    • Use the Mirage 3 axis gantry milling

    machine.

    • Workshop trials carried out in advance.

    Solution

     All machining operations were completed first

    time, to customer’s specification and within

    time critical operations window.

    .

    Outcome

    Workshop trial.

  • 8/17/2019 MM Subsea Case Study Pack

    7/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

     Tidal Fin Removal

    Case Study

    PORTABLE PERFORMANCE

    • Structural plates required removal from tidal

    turbine monopoles.

    • Diving time severely restricted to 20 minutes due

    to tidal direction change and ‘Neap Tide’.

    Requirements

    • Plates (1.8m x 150mm x 30mm) removed

    using a slitting saw. Remaining material

    removed using face milling.

    • Quick release tooling used to allow fast

    project completion.

    Solution

     All machining operations were completed first

    time, to specification and within time criticaloperations window.

    .

    Outcome

    Workshop trials using the Mirage MR2000.

  • 8/17/2019 MM Subsea Case Study Pack

    8/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    Seam Weld andDoubler PlateRemoval

    Case Study

    PORTABLE PERFORMANCE

    • Remove a seam weld from 30” pipeline

    over 3m length.

    • Remove anode doubler plates for

    relocation at 90m water depth.

    • Location: North Sea.

    Requirements

    • Cold cutting to prevent cutting into the

    parent pipeline.

    • Use of Mirage gantry MR1000SS with

    pipe chain clamping system, fixed feed,

    and depth stops.• Workshop trials carried out on a circular

    test piece.

    Solution

    • Milling of seam: less than 1 hour.

    • Doubler plate removed in 3 hours.

    Outcomes

  • 8/17/2019 MM Subsea Case Study Pack

    9/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    CIMV Removal& Torque ToolDevelopment

    Case Study

    PORTABLE PERFORMANCE

    The client’s problem was a subsea tree equipped

    with a latch lock removal system on a chemical

    injection valve which had a mechanical failure on

    the connection rod.

    Requirements

    Mirage developed three innovative contingency

    solutions to allow an ROV to remove the valve.

    The first solution used a one inch, left-handed, four

    flute endmill to attempt to turn the inconel rod to

    unlatch the CIMV. This solution was delivered to the

    Client’s design, but was unable to remove the

    damaged valve.

    Second solution: Having anticipated that a second

    solution might be required, we designed and

    engineered a contingency tool, which incorporated an

    eight inch lathe chuck, with ROV handles, to deploythe latch onto the inconel rod, in an attempt to turn

    the inconel rod to unlatch the valve. This tool was

    successful in removing the valve.

    Third solution: We designed an additional

    contingency tool, which was a hydraulically operated

    chucking system. This solution was not deployed, as

    the valve was removed with solution two.

    Solution

    • The client’s problem was resolved.

    •  All three tooling solutions were provided in 10 days.

    • Client requested we design a tool to prevent the

    problem from occurring in the future.

    Outcomes

    The resulting torque tool created for

    the customer.

    Workshop development of contingency solutions.

  • 8/17/2019 MM Subsea Case Study Pack

    10/12

    www.miragemachines.comEmail [email protected]

    PORTABLE PERFORMANCE

    05.02.16

    Injection Point in Trace HeatedSupply Line

    Case Study

    PORTABLE PERFORMANCE

    • To machine an injection point within a

    heavy wall Super Duplex pipe.

    • No swarf ingress or tool dwelling.

    • One chance on offshore application.

    Location: Islay Project, North Sea.

    Requirements

    • Mirage provided a complete

    machine/offshore service package.

    •  A process was identified to series

    trepan the external of the supply line.• Extensive workshop testing carried out

    in advance.

    • Machine used: HT50 Portable Drill

    Solution

    Client testimonial:

    “ Did a great job offshore and everyone

    was very pleased ”

    Outcomes

    Images above: Test pieces in the workshop.

  • 8/17/2019 MM Subsea Case Study Pack

    11/12

    www.miragemachines.comEmail [email protected]

    IndustriesMirage manufacture a range of portable machines for a wide variety of

    applications and industries including:

    Our products are supported by industry experts who work closely with our

    customers to optimise performance for industry specific applications.

    With extensive experience within service companies, our teams understand

    the dynamics of a wide range of industries and have the capability to

    deliver turn-key solutions that both meet specific requirements and address

    complex challenges.

    About Mirage MachinesMirage portable machine tools optimise the performance of on-site

    assets by achieving operational excellence, maximising uptime and

    improving productivity.

    Our proprietary technology drives the development of the most reliable,

    durable, efficient and precise portable machine tools on the market, that

    are capable of delivering the most exacting standards of tolerance with the

    highest quality output.

    Our portfolio of portable machine tools are suitable for a diverse range of

    on-site machining applications. Mirage have been granted ISO 9001:2008certification for our design and manufacturing systems

    and we are able to provide full CE certification for our products.

    • Oil & Gas • Mining & Construction

    • Wind Power  • Subsea

    • Decommissioning • Utilities

    • Ship Build & Repair  • Nuclear 

    • Petrochemical • Power Generation

  • 8/17/2019 MM Subsea Case Study Pack

    12/12

    www.miragemachines.comEmail [email protected]

    Contact Us

    UKMirage Machines

    8-10 Enterprise Way

    Jubilee Parkway

    Stores Road

    Derby DE21 4BB

    T: +44 (0) 1332 291767

    F: +44 (0) 1332 370356

    E: [email protected]

    SingaporeMirage Machines

    107 Tuas South Avenue 8

    Offshore Marine Centre 637036

    Singapore

    Tel: +65 9855 0117

    [email protected]

    PerthMirage Machines

    15/4 Wharton Road

    Kewdale

    WA 6105

    Tel: +61 0 452 48 1964

    [email protected]

    HoustonMirage Subsea Inc.

    8615 Jackrabbit Rd

    Houston

    TX 77095

    United States

    Tel: +1-281-859-1234

    E: [email protected]