mm2100 case study 11feb2016

Upload: kushargeo

Post on 05-Jul-2018

234 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/16/2019 MM2100 Case Study 11Feb2016

    1/20

    ORGANICA

    MM2100 WWTPBekasi Fajar, INDONESIA

    Detailed Case Study

  • 8/16/2019 MM2100 Case Study 11Feb2016

    2/20

    © 2016 Organica Water 2

    Project Background

    • MM 2100 is one of the leading industrial park

    in Indonesia

    • Located at Bekasi, West Java, Indonesia

    • Founded in 1989 spread over a total Area

    1,350 hectares• Tenants comprising 320 companies with a total

    of 135,000 employees

    • Existing centralized WWTP capacity of 27 MLD

    operating at 20 MLD capacity

    • Unhappy tenants in the neighborhood of the

    WWTP as the existing facility is emitting bad

    odor

  • 8/16/2019 MM2100 Case Study 11Feb2016

    3/20

    © 2016 Organica Water 3

    Project Background

    Project Municipal WWTP; design, build

    Population Served 200 000 equivalent

    Project Type Greenfield

    Contract Award March 2013

    Hydraulic capacity 45 000 m3/day

    Design Completion October 2013

    Construction Begins January 2014

    Expected Commissioning September 2015

  • 8/16/2019 MM2100 Case Study 11Feb2016

    4/20

    © 2016 Organica Water 4

    Design Parameters

    Parameter Influent Average (mg/L) Effluent/Limit (mg/L)

    COD 1000 50

    BOD 500 25

    NH3-N - 1

    TKN 47 -

    NO2-N - 1

    NO3-N - 20

    TSS 220 50

    Water temperature Min. 23oC Max. 31oC

  • 8/16/2019 MM2100 Case Study 11Feb2016

    5/20

    © 2016 Organica Water 5

    • One of the leading industrial parks in

    the country with high-profile multi-national tenant/resident companies

    • Need for expanding WWTP capacity

    to 45 MLD which required additional

    land

    • Existing, traditional 27 MLD ActivatedSludge WWTP occupying prime real

    estate in the industrial park (1.6

    hectare site)

    • Existing WWTP - large, unsightly, and

    emits bad odors thus anyneighboring tenants negatively

    impacted.

    • Huge buffer zone (which is not

    available) required around WWTP

    due to odors and negative aesthetics

    Original Situation

  • 8/16/2019 MM2100 Case Study 11Feb2016

    6/20

    © 2016 Organica Water

    Demand Drivers

    6

    • Increase WWTP capacity

    • Remove need for buffer zone by

    containing odors and improving

    aesthetics

    Small footprint to minimize landrequirement

    • Lower energy consumption (by

    approximately 30%) for reducing

    operating costs (client responsible for

    operating plant)

    • Lower sludge generation (by

    approximately 30%) to avoid disposal

    issues

  • 8/16/2019 MM2100 Case Study 11Feb2016

    7/20© 2016 Organica Water 7

    Demand Drivers

    Additional Benefits

    • No need for buffer zone due to

    odorless and aesthically

    appealing installation

    • Lower energy consumption

    resulting in significantly loweroperational costs, higher profit

    by maintaining the same tariff 

    • Client recovers complete

    investment in Organica facility

    by selling land occupied byexisting plant

    WWTP Options Capacity

    (MLD)

    Land Occupied/

    Required

    (in Hectares)

    Existing Plant

    (Conventional

    Approach)

    27 2.0

    Ultimate Capacity

    Required

    (Conventional)

    45 4.0 – 4.5 *

    Organica Solution

    (under construction)

    45 1.5 **

    * Land Available for additional capacity Only 2.0 Hectares

    ** Land Savings obtained by client by choosing Organica– 2.5 hectares

  • 8/16/2019 MM2100 Case Study 11Feb2016

    8/20© 2016 Organica Water 8

    67% higher capacity in 30% lowerfootprint than existing WWTP = 138%

    improvement in capacity/area (twice the

    capacity in less space - 1.2 hectares)

    • No need for buffer zone due to odorless

    and aesthically appealing installation

    • Lower energy consumption and sludgegeneration resulting in significantly lower

    operational costs and site issues

    • New plant to be built on a small piece of 

    land already available resulting in:

    No disruption in wastewatertreatment

    • Land utilized by existing plant made

    available for sale/lease (offsets costs

    of new plant)

    Organica Solution

  • 8/16/2019 MM2100 Case Study 11Feb2016

    9/20© 2016 Organica Water

    Existing M2100 WWTP – 27 MLD

    9

    Future Site of Organica FCR

    Existing CAS WWTP

  • 8/16/2019 MM2100 Case Study 11Feb2016

    10/20© 2016 Organica Water

    Paradigm Shift

    10

    The Paradigm Shift

  • 8/16/2019 MM2100 Case Study 11Feb2016

    11/20© 2016 Organica Water 11 11

    Series Of Food Chain Reactor Zones

    •   The biological process takes place in a series of cascade reactors, with standard pretreatment at the beginning,

    and phase separation (via Organica Disc Filters or Secondary Clarifiers) and final polishing at the end.

    •   As water flows through from one reactor zone to the next, different ecologies will grow and adapt to the

    conditions in each stage. This configuration allows the “food

     chain effect”

     to develop, as higher level organismsbecome predators for the simpler organisms.

    •   The result is enhanced removal efficiency and resiliency, while utilizing less energy and producing less sludge.

  • 8/16/2019 MM2100 Case Study 11Feb2016

    12/20© 2016 Organica Water

    Process Scheme – MM2100 Design

    13

    Chemical

    Pretreatment

    Areated Grit

    Chamber

    Coagulation

    OrganicaFCR

    Container Container

    Coagulation

    FlocculationCoagulation

    Organica

    FCR

    Organica

    FCR

    Flocculation

    Flocculation

    Screen

    3 mmDisc Filter

    Sludge

    Storage

    Mechanical

    Sludge

    Thickening

    Sludge

    Storage

    Dewatering

    Container

    Ultra Violet

    Disinfection

    Transport

    Transport

    INFLUENT

    EFFLUENT

  • 8/16/2019 MM2100 Case Study 11Feb2016

    13/20© 2016 Organica Water

    Architectural Design – Site Plan 45 MLD in 1.2 ha

    14

  • 8/16/2019 MM2100 Case Study 11Feb2016

    14/20© 2016 Organica Water

    Architectural Design – Section Views

    15

  • 8/16/2019 MM2100 Case Study 11Feb2016

    15/20© 2016 Organica Water

    Construction site nearing completion

    16

  • 8/16/2019 MM2100 Case Study 11Feb2016

    16/20

    © 2016 Organica Water

    Organica Discfilters Installed

    17

  • 8/16/2019 MM2100 Case Study 11Feb2016

    17/20

    © 2016 Organica Water

    Shading Structures in Operation

    18

  • 8/16/2019 MM2100 Case Study 11Feb2016

    18/20

    © 2016 Organica Water

    Front Stradale of the Facility

    19

  • 8/16/2019 MM2100 Case Study 11Feb2016

    19/20

    © 2016 Organica Water

    Proposed Alternative – Enclosure

    20

  • 8/16/2019 MM2100 Case Study 11Feb2016

    20/20

    www.organicawater.com

    [email protected]

    + 36 1 455 8060