mn/dot cs pre-qualification best practices review august 19, 2002

15
Mn/DOT CS Pre- Qualification Best Practices Review August 19, 2002

Upload: milton-marshall-hopkins

Post on 16-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Mn/DOT CS Pre-Qualification

Best Practices Review

August 19, 2002

Page 2: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 2August 19, 2002

Agenda

• Best Practices research plan & subsequent adjustments

• How we determined Best Practices • Results of Best Practices Review

– The States with best practices– Overview of work-paper index

• Best Practice Findings for:– Work-type definitions– Work-type qualification criteria– Process of creating a Pre-qualification List

Page 3: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 3August 19, 2002

The July Plan

• Research 13 states preliminarily identified for best practices in pre-qualification; 8 states identified for best practices in consultant evaluation. Complete the question-set for all.

• Do research primarily on the Web with subsequent follow-up telephone calls as needed.

• Conduct ALL best practice research before defining Mn/DOT’s processes and implementing Wave 1.

Page 4: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 4August 19, 2002

Adjustments to July Plan

• Focused research effort on the Web to obtain – Pre-qualification process documentation;– Work-type definitions– Work-type pre-qualification criteria

• Focused analysis effort on Wave 1 work groups.• Deferred follow-up telephone calls• Deferred research into Best Practices for using a Pre-

Qualified list and doing consultant evaluations.

To meet the 9/3 deadline, the Phase 2 Best Practice research has become a parallel activity with Phase 3. That makes it “messier”, but

doesn’t endanger achievement of the project’s objectives.

Page 5: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 5August 19, 2002

What is “Best Practice”

• Theory: Process Maturity– Five Levels of Process Maturity

• Refer to: Process Maturity Article on L&C Web Page

• Application of theory focused on:• Criterion 1: Documented addresses the extent to which an organization’s

processes are documented. The least mature state of documentation maturity is one in which processes typically are ad hoc, perhaps even chaotic. . . Alternatively, in the most mature state, written documentation is not only consistent throughout the organization, it is an intrinsic element of the process itself.

• Criterion 2: Practiced criterion addresses the consistency of process performance. In the least mature state, processes are practiced in an ad hoc or, at best, intermittent manner. By contrast, the processes of a more mature organization are practiced consistently and throughout the organization

Page 6: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 6August 19, 2002

Best Practice StatesDOT Pre-Qualified System Post Selection

Evaluation

1. A lberta √ √

2. Ar izona √ √

3. Colorado √

4. Florida √

5. Georgi a √

6. Iowa √

7. Kansas √ √

8. Louisiana √

9. Massachusetts √

10. Michigan √

11. Nevada √

12. New Brnswck. √

13. New Mexico √

14. Ohio √

15. Ontario √ √

16. Texas √ √

count 13 8

Page 7: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 7August 19, 2002

Introducing Workpaper Index

• Refer to Attached Document

DOTdatabase.xls

Page 8: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 8August 19, 2002

BP: Work-type Definitions

• Work type definitions are clearly delineated from the qualifications required to perform the work. (i.e., A work type is not defined by the required qualifications) (Georgia, Kansas, Florida, Iowa, Ohio)

• Work types are specifically assigned to a functional entity or individual who is referred to as the “owner”.

(Iowa)• Work types are defined systematically and

comprehensively, often consistent with the DOT’s internal organization. (Kansas, Iowa)

Page 9: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 9August 19, 2002

BP: Work-type Definitions (2)

• Work type definitions are a part of the formal pre-qualification process documentation. (I.e., a section within or an appendix to the formal procedure or rule) (Georgia, Florida, Iowa, Ohio)

• Work types are defined at the departmental activity level, not the task level.(Georgia, Kansas, Florida, Iowa)

• Work types are defined in terms of process outputs. (Georgia, Kansas, Florida, Iowa, Ohio)

Page 10: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 10August 19, 2002

BP: Correlation with Mn/DOT

Phase WG # Work Group # of MatchesI 1 Project Development/ Preliminary Design 6

I 2 Highway Design 16

I 3 Bridge Design 19

I 4 Bridge Inspection 14

I 5 Environmental Sudies 20

II 6 Materials Testing 19

II 7 Transportation Planning 19

II 8 Communications/Market Research 0

II 9 Mechanic Training 0

II 10 Architectural Design 7

II 11 Right of Way Assistance 8

II 12 Landscape Architecture 11

II 13 Land Surveys 23

III 14 Cultural Resources 4

III 15 CEI/Contract Administration 9

III 16 Right of Way Appraisals 9

III 17 Asbestos Abatement 1

III 18 Sewer Video Inspection 0

III 19 Pre-Construction Project Management 0

III 20 Traffic Engineering 19Multi-modal 34

Total matched 238 of 246 possible

Page 11: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 11August 19, 2002

BP: Correlation with Mn/DOT

Sum of count BP State

Mn/DOTWork Group Correlation 1. Georgia 2. Kansas 3. Florida 4. Iowa 5. Ohio Grand Total

Asbestos Abatement 1 1

Cultural Resources 1 1 2 4

Project Development/ Preliminary Design 2 2 1 1 6

Architectural Design 1 1 1 4 7

Right of Way Assistance 8 8

(blank) 2 3 3 8

Right of Way Appraisals 6 1 2 9

CEI/Contract Administration 1 1 3 4 9

Landscape Architecture 5 4 1 1 11

Bridge Inspection 1 4 4 3 2 14

Highway Design 6 2 3 3 2 16

Bridge Design 4 4 4 5 2 19

Materials Testing 4 3 6 4 2 19

Traffic Engineering 3 2 6 4 4 19

Transportation Planning 5 7 5 2 19

Environmental Sudies 2 3 7 8 20

Land Surveys 8 4 4 7 23

Multi-Modal 14 9 11 34

Grand Total 59 49 44 62 32 246

Page 12: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 12August 19, 2002

BP: Qualification Criteria

• Qualification criteria are defined for each work type defined.(Georgia, Kansas, Florida, Iowa, Ohio)

• Qualification criteria are focused on the technical requirements of the work type.(Georgia, Kansas, Florida, Iowa, Ohio)

• Technical requirements are defined to include– Description of the professional staff

(I.e., “a registered engineer… with proficiency”)(Georgia, Kansas, Florida, Iowa, Ohio)

– Capacity (I.e., “at least two engineers…”)(Georgia, Kansas, Florida, Iowa, Ohio)

– Past record and experience of the Firm(Georgia, Kansas, Florida, Iowa, Ohio)

Page 13: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 13August 19, 2002

BP: Qualification Criteria (2)

• The experience of “individuals” (used to satisfy “staff proficiency” requirements) is separated from the past record and experience of the Firm. (Georgia)

• Submittal requirements are defined separately from qualification requirements. (Ohio)

• Quality assurance (QA) and quality control (QC) requirements are uniquely identified. (Ohio)

• Administrative qualifications are uniquely identified. (Georgia, Kansas, Florida, Iowa, Ohio)

Page 14: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 14August 19, 2002

BP: Process to Create the List

• A formal documented process exists to create and update the list. (Georgia, Florida, Iowa, Ohio)

• The process is always open. (Georgia, Florida, Iowa, Ohio)

• The pre-qualification expires. (Georgia-3, Florida-1, Iowa-1, Ohio-2)

• Administrative pre-qualification criteria (separate from technical criteria) are predefined and documented. (Georgia, Florida, Iowa, Ohio)

Page 15: Mn/DOT CS Pre-Qualification Best Practices Review August 19, 2002

Slide 15August 19, 2002

BP: Process to Create the List (2)

• Forms are a part of the documented process(Georgia, Florida, Iowa, Ohio)

• Selection Committees are pre-determined (Georgia, Iowa)

• A formal appeals process exists and is documented. (Georgia, Florida, Iowa)

• A proactive DBE policy/process exists and is documented (Iowa)