model for improvement and tests of change denise remus, phd, rn improvement advisor, cynosure health...
TRANSCRIPT
Model for Improvement and Tests of Change
Denise Remus, PhD, RNImprovement Advisor, Cynosure Health / HRET HEN
2
40/20 Goal
Adverse Drug Events (ADE) Injuries from Falls and Immobility
Central Line-Associated Blood Stream Infections (CLABSI)
Catheter-Associated Urinary Tract Infection (CAUTI)
Ventilator Associated Pneumonia (VAP) Venous Thromboembolism (VTE)
Pressure Ulcers Safe Surgery / Surgical Site Infections
Obstetrical Harm Readmissions
Reduce Harm by 40% and Reduce Readmissions by 20%
3
Drive Improvement Faster
• Science of improvement• Accountability• Structure change• Document progress• Be fearless, take risks, be wiling to fail
4
5
One day Alice came to a fork in the road and saw a Cheshire Cat. “Which road do I take?” she asked. His response was a question “Where do you want to go?” “I don’t know,” Alice answered. “Then,” said the cat “it doesn’t matter.”
Lewis Carroll
6
Aim Statements
• What are we trying to accomplish?
• Communicate expectations
• Measurable (how good?)
• Time specific (by when?)
• Define the specific population (s) (who?)
• Clear, concise and unambiguous
7
WHAT?
HOW MUCH?
WHERE?
BY WHEN?
Aim Statement
WHO?
8
Aim Statement Example
VTE: At St. Luke’s Hospital, we will reduce hospital-acquired VTE for all inpatients by 40% by December 31, 2013.
• What: Hospital-acquired VTE
• Where: St. Luke’s Hospital
• Who: All inpatients
• By When: December 31, 2013
• How Much: By 40%
9
Measure
10
Select Measures
• For each clinical topic, must report data for at least
1 Process Measure and
1 Outcome Measure
11
Measures
• Voice of the customer or patient• How is the system performing? • What is the result?
Outcome Measures
• Voice of the workings of the system• Are the parts / steps in the system or
process working as planned?
Process Measures
• What happened as we improved the outcome and process measures?
• Unanticipated consequences, other factors influencing the outcome?
Balancing Measures
12
Reduce HarmImprove Processes
Where is your Greatest Opportunity to?
13
Consider. . .
• What are you already measuring?• What are you planning to measure?
1. Identify existing measures2. Are they in the HRET HEN
Encyclopedia of Measures?3. If not, user-defined measure option
14
VTE Example – Potential Measures
• Process Measures: – ICU VTE Prophylaxis (JC VTE-2)– VTE Discharge Instructions (JC VTE-5)
• Outcome Measures:– Potentially Preventable VTE (JC VTE-6)– Post-op PE or DVT (All Adults) (AHRQ PSI 12)
15
Does your organization have an aim statement?
Which process and outcome measures will
you report?
16
17
The PDSA Cycle
Plan• Objective• Questions &
predictions• Plan to carry out:
Who?When?How? Where?
Do• Carry out plan• Document
problems• Begin data
analysis
Act• Ready to
implement?• Try something
else?• Next cycle
Study• Complete data
analysis• Compare to
predictions• Summarize
“What will happen if we try something different?”
“Let’s try it!”“Did it work?”
“What’s next? ”
The Sequence for Improvement
Sustaining improvements and Spreading changes to other locations
Developing a change
Implementing a change
Testing a change
Act Plan
Study Do
Theory and Prediction
Test under a variety of conditions
Make part of routine operations
Repeated Use of the PDSA Cycle for Testing
Changes That Result in
Improvement
Hunches Theories
Ideas
DATA
Very Small Scale Test
Follow-up Tests
Wide-Scale Tests of Change
Implementation of Change
What are we trying toaccomplish?
How will we know that achange is an improvement?
What change can we make thatwill result in improvement?
Model for Improvement
Sequential building of knowledge under a wide range
of conditions
Spreading
AP D
S
AP
D S
APD
SA P
DS
Sustaining the gains
Guidelines For Testing Change
• Do not try to get buy-in, consensus
• Be innovative to make the test feasible
• Collect useful data during each test
• Test over a wide range of conditions
Guidelines For Testing Change
• Fail early, fail often• What can we do by next
Tuesday?• Pick willing volunteers• AIM big, but test small• Steal shamelessly
Remember to. . .
• Adapt
• Adopt
• Abandon
Common Traps
• Plan Do, Plan Do
• Do Act, Do Act
• No testing, only data collection
• No ramps of tests, random PDSAs
• Undisciplined PDSAs, no documentation
• No prediction – what are we going to learn?
• Beware of Cycles longer than 30 days
25
Tips for Testing
• Use a form to document your test.
• Scale down – think “Drop Two.”
• Oneness
• Know the situation in your organization.
26
Value of “Failed” Tests
Do something. If it works, do more of it. If it doesn't, do something else.
Franklin D. Roosevelt
• Learning• Accelerate development• Innovation
27
Failed Test…Now What?
• Be sure to distinguish the reason: – Change was not executed – Change was executed, but not effective
• If the prediction was wrong – not a failure!– Change was executed but did not result in
improvement– Local improvement did not impact the secondary
driver or outcome– In either case, we’ve improved our understanding of
the system!
28
2929
• What are you going to test?• What do you need to conduct the test?• Who will be involved in the test?• How will you educate & inform the
participant(s)?• Where will the test occur?• When will the test occur?• How will you know if you’ve been successful?
Rapid Cycle Test of Change
30
Rapid Cycle Test of Change
31
Improvement Project Worksheet
32
Share . . .
33