modeling decision variables: dollars, deaths, and downtime judith mitrani-reiser (jhu) james l. beck...

36
Modeling Decision Variables: Dollars, Deaths, and Downtime Judith Mitrani-Reiser (JHU) James L. Beck (Caltech) PEER Annual Meeting San Francisco, CA January 19, 2007

Post on 21-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Modeling Decision Variables: Dollars, Deaths, and Downtime

Judith Mitrani-Reiser (JHU)

James L. Beck (Caltech)

PEER Annual Meeting

San Francisco, CA

January 19, 2007

PEER Annual Meeting January 19, 2007

Outline

• Methodology to estimate building safety for PEER’s PBEE framework (using ATC-20 guidelines).

• Methodology to estimate probability of fatalities and downtime for PEER’s PBEE framework.

• Applied comprehensive damage and loss analysis to PEER’s benchmark study.

• Express all performance metrics in economic terms for a benefit-cost analysis.

PEER Annual Meeting January 19, 2007

PBEE methodology for PEER: collaboration for benchmark study

C. GouletJ. Stewart

C. HaseltonG. Deierlein

J. Mitrani-ReiserJ. Beck

K. Porter

PEER Annual Meeting January 19, 2007

Facility definition: benchmark site

LA Bulk Mail Facility, Bell, CA, 7 miles SE of downtown L.A.

Representative of urban area in highly seismic region.

Site is within 20 km of 7 known faults, but no one fault dominates the site hazard.

Near-fault effects are not a concern at this site.

High-quality geotechnical data is available for this site.

from USGS (by way of Goulet)

PEER Annual Meeting January 19, 2007

Facility definition: benchmark building

RC 4-story frame building Typical office building 4 x 6 bays (bay width = 30 ft) T1= 1 sec

from Haselton

PEER Annual Meeting January 19, 2007

Design Description

A: Baseline perimeter frame design.

B: Same as A, but with code min strengths.

C: Same as A, but with uniform beam/column throughout.

D: Same as C, but no SCWB provision.

E: Baseline space frame design.

Benchmark Building Design Variants

• Structural analysis performed using Opensees software.

• Fiber and lumped plasticity models used to estimate structural response for a range of hazard levels.

• Sa(T1) used as IM in benchmark study.

PEER Annual Meeting January 19, 2007

Repair Cost: component contribution

Repair costs for damageable

building components.

PEER Annual Meeting January 19, 2007

Repair Cost: vulnerability functions

Mean repair costMDF =

Replacement cost

Replacement cost $9M

.1 .19 .3 .44 .55 .82 1.20

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

Design A, Baseline Perimeter-Frame DesignDesign E, Baseline Space-Frame Design

.26

Spectral Acceleration (g)

Mea

n D

amag

e Fa

ctor

10%-in-50yr 2%-in-50yr

Sum repair costs at each hazard level

PEER Annual Meeting January 19, 2007

Repair Cost : expected annual loss

0 [ | ] ( | )dcr

im

EAL E TC im p im im im im

where is the mean annual rate of events where:

0

0.1crIM im g

0 0.5 1 1.5 20

0.2

0.4

0.6

0.8

1

PGA (g)P

Hazard Curve

Spectral Acceleration (g)1.51.0 0.1 0.5

PEER Annual Meeting January 19, 2007

Results of Benchmark Study: EAL

Design Description EAL ($)

A: Baseline perimeter frame design. 66,585

B: Same as A, but with code minimum strengths.

95,656

C: Same as A, but with uniform beam/column throughout.

51,933

D: Same as C, but no SCWB provision. 112,930

E: Baseline space frame design. 49,422

PEER Annual Meeting January 19, 2007

Results of Benchmark Study: EAL

Design Description EAL ($)

A: Baseline perimeter frame design. 66,585

B: Same as A, but with code minimum strengths.

95,656

C: Same as A, but with uniform beam/column throughout.

51,933

D: Same as C, but no SCWB provision. 112,930

E: Baseline space frame design. 49,422

43% increase

PEER Annual Meeting January 19, 2007

Results of Benchmark Study: EAL

Design Description EAL ($)

A: Baseline perimeter frame design. 66,585

B: Same as A, but with code minimum strengths.

95,656

C: Same as A, but with uniform beam/column throughout.

51,933

D: Same as C, but no SCWB provision. 112,930

E: Baseline space frame design. 49,422

115% increase

PEER Annual Meeting January 19, 2007

EAL Contributions

Contribution from collapse ~ 1%

Baseline Perimeter-Frame Design

PEER Annual Meeting January 19, 2007

ATC 20 guidelines (ATC 1985, 1995, 1996)

Event Tree

Building Safety: virtual inspector

PEER Annual Meeting January 19, 2007

ATC 20 guidelines (ATC 1985, 1995, 1996)

Event Tree

Building Safety: virtual inspector

PEER Annual Meeting January 19, 2007

Building Safety: rapid evaluation results

PEER Annual Meeting January 19, 2007

Building Safety: detailed evaluation results

PEER Annual Meeting January 19, 2007

Life Safety

Event Tree

P[C|im] determined by structural analysis

P[LC|im, NC] determined by virtual inspector

pDM from epidemiological studies and expert opinion

PEER Annual Meeting January 19, 2007

Life Safety

P[C|im] determined by structural analysis

P[LC|im, NC] determined by virtual inspector

pDM from epidemiological studies and expert opinion

Event Tree

PEER Annual Meeting January 19, 2007

Life Safety: mean population at risk

Mean # occupants determined from ATC-13 (1985).

PEER Annual Meeting January 19, 2007

DMpBuilding Characteristics

Fatality Model

Damage State (DM)

For all construction types except light steel and wood

frame.

ATC-13 (1985)

LC 0.01

C 0.20

Reinforced-concrete (non-near-field ground motions)

Coburn et al. (1992)

LC 0.31

C 0.49

Mid-rise concrete moment frame

HAZUS 99-SR2 (2002)

LC 0.0001

C 0.1

Mid-rise non-ductile reinforced-concrete frame

Shoaf and Seligson

(2005)

LC 0.015

C 0.131

Life Safety: fatality probabilities

PEER Annual Meeting January 19, 2007

DMpBuilding Characteristics

Fatality Model

Damage State (DM) E[Yn|DM] Var[Yn|DM]

For all construction types except light steel and wood

frame.

ATC-13 (1985)

LC 0.01 1.33 1.32

C 0.20 26.68 21.34

Reinforced-concrete (non-near-field ground motions)

Coburn et al. (1992)

LC 0.31 41.35 28.53

C 0.49 65.37 33.2

Mid-rise concrete moment frame

HAZUS 99-SR2 (2002)

LC 0.0001 0.01 0.01

C 0.1 13.34 12.01

Mid-rise non-ductile reinforced-concrete frame

Shoaf and Seligson

(2005)

LC 0.015 2.00 1.97

C 0.131 17.47 15.19

Life Safety: number of fatalities

Use Binomial distribution to estimate mean and variance of fatalities.

PEER Annual Meeting January 19, 2007

0 [ | ] ( | )dn cr

im

EANF E Y im p im im im im

Design DescriptionEANF(*10-3)

A: Baseline perimeter frame design. 1.4

B: Same as A, but with code-min strengths.

1.3

C: Same A, but with uniform beam/column throughout.

1.6

D: Same as C, but no SCWB provision. 22.8

E: Baseline space frame design. 1.0

Life Safety: expected annualnumber of fatalities

PEER Annual Meeting January 19, 2007

Design DescriptionEANF(*10-3)

EALF ($)

A: Baseline perimeter frame design. 1.4 4,900

B: Same as A, but with code-min strengths.

1.3 4,550

C: Same A, but with uniform beam/column throughout.

1.6 5,600

D: Same as C, but no SCWB provision. 22.8 79,800

E: Baseline space frame design. 1.0 3,500

value of a statistical life = $3.5M (FHWA 1994, Mrozeck and Taylor 2002)

EALF VSL EANF

VSL

Life Safety: expected annual lossdue to fatalities

PEER Annual Meeting January 19, 2007

[ | , ] [ | ] ( | , )

[ | ] ( | , )

[ | ] ( | , )

TO TO G G

TO Y Y

TO R R

E R NC im E R TAG P TAG NC im

E R TAG P TAG NC im

E R TAG P TAG NC im

• ABAG’s building inspection data from over 700 buildings after the Loma Prieta earthquake, 10 days (Blecher and Comerio 2006).

• Estimate by expert, 1 month (Scawthorne 2006).

• Estimate from Stanford case study of closed buildings after Loma Prieta earthquake, 6 months (Comerio 2006).

Results from the Virtual Inspector.

Downtime: mobilization delay

Use Virtual Inspector results to determine

mobilization delay.

PEER Annual Meeting January 19, 2007

Baseline Perimeter-Frame Design

Downtime: mobilization delay & repair time

10%-in-5yr

DT ~ 4 months

2%-in-50yr

DT ~ 17 months

PEER Annual Meeting January 19, 2007

Design DescriptionDown-time Type

Sa(T1)

EALD ($USD)

0.1 0.19 0.26 0.3 0.44 0.55 0.82 1.2

A: Baseline perimeter frame design.

Total(days) 24 52 114 157 284 388 518 655 20,519

B: Same as A, but with code-min strengths.

Total(days) 28 89 221 238 363 426 543 635 28,362

C: Same A, but with uniform beam/column throughout.

Total(days) 26 57 94 124 245 335 485 642 22,207

D: Same as C, but no SCWB provision.

Total(days) 30 94 220 239 386 491 726 942 32,726

E: Baseline space frame design.

Total(days) 26 42 85 119 217 332 577 949 19,517

Comerio (2006)

Downtime: economic losses

PEER Annual Meeting January 19, 2007

Comerio (2006) 16-32 months

Downtime: economic losses

Design DescriptionDown-time Type

Sa(T1)

EALD ($USD)

0.1 0.19 0.26 0.3 0.44 0.55 0.82 1.2

A: Baseline perimeter frame design.

Total(days) 24 52 114 157 284 388 518 655 20,519

B: Same as A, but with code-min strengths.

Total(days) 28 89 221 238 363 426 543 635 28,362

C: Same A, but with uniform beam/column throughout.

Total(days) 26 57 94 124 245 335 485 642 22,207

D: Same as C, but no SCWB provision.

Total(days) 30 94 220 239 386 491 726 942 32,726

E: Baseline space frame design.

Total(days) 26 42 85 119 217 332 577 949 19,517

PEER Annual Meeting January 19, 2007

Downtime: economic losses

Design DescriptionDown-time Type

Sa(T1)

EALD ($USD)

0.1 0.19 0.26 0.3 0.44 0.55 0.82 1.2

A: Baseline perimeter frame design.

Total(days) 24 52 114 157 284 388 518 655 20,519

B: Same as A, but with code-min strengths.

Total(days) 28 89 221 238 363 426 543 635 28,362

C: Same A, but with uniform beam/column throughout.

Total(days) 26 57 94 124 245 335 485 642 22,207

D: Same as C, but no SCWB provision.

Total(days) 30 94 220 239 386 491 726 942 32,726

E: Baseline space frame design.

Total(days) 26 42 85 119 217 332 577 949 19,517

28% increase in EALD for code-min design.

PEER Annual Meeting January 19, 2007

Downtime: economic losses

Design DescriptionDown-time Type

Sa(T1)

EALD ($USD)

0.1 0.19 0.26 0.3 0.44 0.55 0.82 1.2

A: Baseline perimeter frame design.

Total(days) 24 52 114 157 284 388 518 655 20,519

B: Same as A, but with code-min strengths.

Total(days) 28 89 221 238 363 426 543 635 28,362

C: Same A, but with uniform beam/column throughout.

Total(days) 26 57 94 124 245 335 485 642 22,207

D: Same as C, but no SCWB provision.

Total(days) 30 94 220 239 386 491 726 942 32,726

E: Baseline space frame design.

Total(days) 26 42 85 119 217 332 577 949 19,517

47% increase in EALD for

non-code-conforming design.

PEER Annual Meeting January 19, 2007

Design DescriptionEAL($)

EALD ($)

EALF ($)

EALTOTAL

($)

A: Baseline perimeter frame design. 66,585 20,519 4,900 92,004

B: Same as A, but with code-min strengths. 95,656 28,362 4,550 128,568

C: Same A, but with uniform beam/column throughout.

51,933 22,207 5,600 79,740

D: Same as C, but no SCWB provision. 112,930 32,726 79,800 225,456

E: Baseline space frame design. 49,422 19,517 3,500 72,439

Summary of Results: “3 D” Losses

PEER Annual Meeting January 19, 2007

Design DescriptionEAL($)

EALD ($)

EALF ($)

EALTOTAL

($)

A: Baseline perimeter frame design. 66,585 20,519 4,900 92,004

B: Same as A, but with code-min strengths. 95,656 28,362 4,550 128,568

C: Same A, but with uniform beam/column throughout.

51,933 22,207 5,600 79,740

D: Same as C, but no SCWB provision. 112,930 32,726 79,800 225,456

E: Baseline space frame design. 49,422 19,517 3,500 72,439

Summary of Results: “3 D” Losses

PEER Annual Meeting January 19, 2007

Design DescriptionEAL($)

EALD ($)

EALF ($)

EALTOTAL

($)E[PVL(50yr)]

($M)

A: Baseline perimeter frame design. 66,585 20,519 4,900 92,004 1.84

B: Same as A, but with code-min strengths. 95,656 28,362 4,550 128,568 2.50

C: Same A, but with uniform beam/column throughout.

51,933 22,207 5,600 79,740 1.64

D: Same as C, but no SCWB provision. 112,930 32,726 79,800 225,456 6.66

E: Baseline space frame design. 49,422 19,517 3,500 72,439 1.44

Summary of Results: “3 D” Losses

PEER Annual Meeting January 19, 2007

Benefit-Cost Analysis

Benefit = [ (50yr)] [ (50yr)] $403,500

Cost = [upfront cost] [upfront cost)] $100, 000

Benefit4

Cost

perimeter space

space perimeter

E PVL E PVL

E E

A risk-neutral decision maker will choose the space-frame design!

PEER Annual Meeting January 19, 2007

Summary

• Established framework for estimating the 3 D’s (dollars, deaths and downtime) as part of PEER’s PBEE framework.

• Used PEER benchmark study to illustrate this loss framework.

• Results show that all metrics are important in estimating overall building performance, and should all be included in a building loss estimation and BCA.

• We hope that this effort will contribute to the ongoing ATC-58 effort (downtime & deaths).

PEER Annual Meeting January 19, 2007

Thank You!