modeling of post-tensioned segmental box girders

Upload: ulissipo1955

Post on 02-Nov-2015

56 views

Category:

Documents


4 download

DESCRIPTION

Use of Midas in the analysis of Post Tensioned Box Girder Bridges

TRANSCRIPT

  • Modeling of Post-Tensioned Segmental

    Box Girders

    Cast Study Calgary West LRT

    Neon Koon, P.Eng. July 12 2012

  • Overview

    Post Tensioned Segmental Concrete Bridges

    Case Study Calgary West LRT

    Modeling Techniques and Applications in Design Process

    Conclusion

  • What Are Segmental Concrete Bridges?

    Built in short pieces of concrete sections, one piece at a time

    The concrete segments can be cast-in-place or precast

    Large size cranes, referred to as gantry, are typically used to erect the precast segments or slip forms are used to produce cast-in-place concrete

    The segments are joined together by applying a high compressive force from high strength bundled wires, referred to as strands

    Post Tensioned Segmental Concrete Bridges

  • What Are Segmental Concrete Bridges?

    Post Tensioned Segmental Concrete Bridges

    Precast segment at batch plant Segments being erected using gantry

    19-strand tendon Tendon stressing in operation

  • Issues To Be Considered in Segmental Bridge Construction

    Span length

    Project size

    Site restrictions

    Local labor and material costs

    Aesthetic/Appearance

    Quality Assurance / Quality Control (QA/QC)

    Construction Methods and Continuing Engineering Services During Construction

    Post Tensioned Segmental Concrete Bridges

  • Various Types of Segmental Bridge Construction

    Span-by-Span

    Balanced Cantilever

    Incremental Launching

    Cable Stayed

    Post Tensioned Segmental Concrete Bridges

  • Various Types of Segmental Bridge Construction

    Span-By-Span

    Courtesy: VSL Systems (CZ) Ltd.

    Post Tensioned Segmental Concrete Bridges

  • Various Types of Segmental Bridge Construction

    Balanced Cantilever

    Courtesy: VSL Systems (CZ) Ltd.

    Post Tensioned Segmental Concrete Bridges

  • Various Types of Segmental Bridge Construction

    Incremental Launching

    Courtesy: VSL Systems (CZ) Ltd.

    Post Tensioned Segmental Concrete Bridges

  • Various Types of Segmental Bridge Construction

    Cable Stayed

    Post Tensioned Segmental Concrete Bridges

  • Typical Concrete Box Girder Section

    Single cell box preferable due to its high torsional resistance, ease of construction and inspection access

    For constant girder depth, span to depth ratio ranging from 15 to 30, with optimum value around 18 to 20

    Top flange width is preferably limited to 6 times the box depth and can be pushed up to about 18 m

    Web spacing normally between 4.6 m to 7.6 m

    Post Tensioned Segmental Concrete Bridges

  • Typical Concrete Box Girder Section

    Minimum top flange thickness = 200mm

    Minimum ribbed web thickness = 180mm

    Very wide bridge deck can be accommodated by using several box girders with a joint between the two box sections

    Post Tensioned Segmental Concrete Bridges

  • Typical Concrete Box Girder Section

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    Tendons Longitudinal post-tensioning vs transverse post-tensioning

    External tendons vs internal tendons

    Courtesy: FHWA

    Typical Tendon Profile for Longitudinal Post-Tensioning

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    Longitudinal External Tendons

    Post Tensioned Segmental Concrete Bridges

    Mid Span Deviator

  • Major Components of Segmental Box Girders

    Transverse Post-Tensioning

    Courtesy: FHWA

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    Prestressing Strands in Tendons in bridge structures Each strand composed of 7 bundled wires, low relaxation

    Tensile strength = 1860 MPa

    Size typically 13 mm or 15 mm diameter

    Nominal cross sectional area = 99 mm2 or 140 mm2

    Duct at least 2.5 times > the net area of post-tensioning strands

    Corrosion protection Water-proofing membrane/sealant at the exterior surface of concrete

    Cover

    HDPE duct

    Grout

    Sheathing/coating

    Proper design detailing and construction procedures

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    Levels of Corrosion Protection to Internal Tendons

    Courtesy: FHWA

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    Levels of Corrosion Protection to External Tendons

    Courtesy: FHWA

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    External Deviators Function as a intermediate anchorage point to transfer the vertical

    component of the post-tensioning force

    Anchorage Blocks Provide an anchorage point at the ends of the span to develop the

    required post-tensioning forces

    Provide a jacking area for the post-tensioning equipment

    Special attention and design details required to increase the levels of corrosion protection at anchorages

    Post Tensioned Segmental Concrete Bridges

  • Major Components of Segmental Box Girders

    Stressing of Strands in Process at Anchorage Block

    Post Tensioned Segmental Concrete Bridges

  • Design Aspects of Post-Tensioned Box Girders

    Design Codes AASHTO LRFD Bridge Design Specifications

    AASHTO Guide Specifications for Design and Construction of Segmental Concrete Bridges

    Ultimate Flexure, Shear, Torsion, Axial

    Bursting at anchorages, jacking of superstructure during launching

    Service Stress within concrete segments and at segment joints

    Fatigue

    Deflection

    Seat width

    Post Tensioned Segmental Concrete Bridges

  • Factors Affecting the Expected Performances

    Concrete mix

    Temperature

    Creep and shrinkage

    Curing methods

    End restraints (secondary effects)

    Stress losses in tendons

    Construction sequence

    Construction practice/load

    Post Tensioned Segmental Concrete Bridges

  • Case Study Calgary West LRT

    Case Study Calgary West Light Rail Transit

  • Case Study Calgary West Light Rail Transit

    Total length 8 km extending from west end of 7th Ave Downtown to 69th St S.W.

    Track works on elevated guideway, trenches, tunnels, and grounds

    Expected opening schedule in early Spring 2013

    Case Study Calgary West LRT

  • Case Study Calgary West Light Rail Transit

    Total length of the elevated guideway is about 1.5 km

    Comprised of standard 30m, 33m, and 36m single span segments and two-continuous spans constructed using the span-by-span method as well as a four-span continuous structure using the balanced cantilever method

    Case Study Calgary West LRT

  • Courtesy: City of Calgary

    Mewata Bridge

    11 th St SW

    Bow Trail SW

    Bow River

  • Courtesy: City of Calgary

  • Launching Trusses

  • Launching Trusses Stored on Ground

  • Steel Form for End Segment Casting

    Cured End Segment at Batch Plant

  • Preparation of Reinforcing Cage

  • Standard segment for spans constructed using balanced cantilever method Standard segment for

    spans constructed using span-by-span method

  • Erected girder segments using the span-by-span method

  • Erected girder segments using the balanced cantilever method

  • Crews applying stressing to tendons at end segment

  • Two Span Continuous with Integral Connection at Straddle Bent

  • Two Span Continuous with Integral Connection at Straddle Bent

  • Crews working in a heated tent in winter

    Courtesy: City of Calgary

  • Modeling Demonstration of a Two-Span Continuous Structure

    Modeling Techniques and Applications in Design Process

  • Modeling Demonstration of a Two-Span Continuous Structure

    Plan View

    Modeling Techniques and Applications in Design Process

  • Modeling Demonstration of a Two-Span Continuous Structure

    Elevation View (Longitudinal)

    Modeling Techniques and Applications in Design Process

  • Modeling Demonstration of a Two-Span Continuous Structure

    Elevation View (Transverse)

    Modeling Techniques and Applications in Design Process

  • Defining the Geometry

    Can be either imported from Midas Civil, CAD, or other structural software such as SAP or Lusas

    Define nodes and elements manually using the geometry defining features under the Menu Tab

    Modeling Techniques and Applications in Design Process

  • Defining the Geometry

    Modeling Techniques and Applications in Design Process

  • Non-time dependent material

    Time dependent material including creep and shrinkage as well concrete strength development used in construction staging analysis

    Plastic material for non-linear analysis

    AASHTO and Canadian Codes implemented in material database

    Defining Material

    Modeling Techniques and Applications in Design Process

  • Various guidelines such as the CEB-FIP (1990), ACI, PCA, and AASHTO implemented to predict the creep and shrinkage effects

    Defining Material

    Modeling Techniques and Applications in Design Process

  • Sections can be found from the database or manually enter dimensions

    Sections like basic bare steel, generic sectional properties, hybrid sections, prestressed concrete section, taper section, and composite section can be defined

    Additional stress points can be defined using the Section Manager feature

    General sections using SPC

    Defining Sections

    Modeling Techniques and Applications in Design Process

  • Box Section Developed by SPC

    Modeling Techniques and Applications in Design Process

  • Used AutoCAD to accurately define the tendon profile

    Simply copy & paste the coordinates in 2D / 3D into Midas Civil

    Defining Tendons

    Modeling Techniques and Applications in Design Process

  • Tendon property was defined based on the CEB-FIP

    Tendon diameter, relaxation coefficient, tensile strength, and anchorage set, and first jacking force were all defined in the model

    Defining Tendons

    Modeling Techniques and Applications in Design Process

  • Structure, Boundary, Load, and Tendon Groups were defined accordingly for construction stage analysis and subsequent data manipulation

    Defining Groups

    Modeling Techniques and Applications in Design Process

  • Defining Construction Stage Analysis

    Construction staging had to be accurately defined to capture accumulated stresses built up during construction

    Tendon stresses at service after all the losses, secondary moment effects, and stresses at the segmental box girders and other structural components were all examined

    Challenges

    Integral connection between the straddle bent beam and each end of the spans, resulting consideration of secondary moment effect

    Excessive amount of flexural reinforcing originally required in the bent beam, resulting issue of proper concrete placement

    Defining Construction Stage Analysis & Challenges

    Modeling Techniques and Applications in Design Process

  • Accurately defined all the member section properties, their design locations, time dependent materials, tendon properties, stressing and construction sequences in the construction staging analysis

    Used internal post-tensioning to replace the flexural reinforcing

    Solution...

    Modeling Techniques and Applications in Design Process

  • Construction Staging Rendering

    Modeling Techniques and Applications in Design Process

  • Canadian and AASHTO LRFD available

    Traffic lanes can be defined based on beam or plate elements

    Program can consider a number of sub-load cases and perform independent analyses of each sub-load case and provide the maximum and minimum results at a particular location or run combined analyses of all sub-load cases and provide the maximum and minimum results

    Dynamic load factor in Canadian code

    Defining Moving Load

    Modeling Techniques and Applications in Design Process

  • Simulate the construction staging and review stresses and forces at each stage

    Report forces and stresses in tendons over time

    Post-processing Information

    Modeling Techniques and Applications in Design Process

  • Moving load tracer used to find out location of live load to produce the maximum/minimum forces/stresses at a certain point

    Post-processing Information

    Modeling Techniques and Applications in Design Process

  • Advantages of Post-Tensioned Box Girder Constructed Using Segmental Construction Methods

    Design Issues

    Challenges Encountered During Construction of CWLRT

    Useful Modelling Techniques

    Conclusion

    Modeling Techniques and Applications in Design Process

  • Case Study Calgary West Light Rail Transit

    http://www.westlrt.ca/contentdesign/constructiondashboard.cfm

    Modeling Techniques and Applications in Design Process

  • Segmental Concrete Bridge Design Resources

    AASHTO LRFD Bridge Design Specifications

    AASHTO Guide Specifications for Design and Construction of Segmental Concrete Bridges

    American Segmental Bridge Institute (AASHTO-PCI-ASBI Segmental Box Girder Standard Drawings)

    ASBI Recommended Practice for Design and construction of Concrete Segmental Bridges

    FHWA

    Post Tensioning Manual, PTI

    Modeling Techniques and Applications in Design Process

  • THANK YOU FOR YOUR TIME!

    Email address: [email protected]