Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT SEPTEMBER, 2018 RAS OFFICERS’ INSTITUTE (CLUB HOUSE) (2, institutional Area, Near Dainik Bhaskar, Jaipur) Developers: M/S RAS Officers’ Institute 2, institutional Area, Near Dainik Bhaskar-Jaipur

Upload: others

Post on 30-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

Prepared By

SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS)

MONTHLY PROGRESS REPORT

SEPTEMBER, 2018

RAS OFFICERS’ INSTITUTE (CLUB HOUSE)

(2, institutional Area, Near Dainik Bhaskar, Jaipur)

Developers: M/S RAS Officers’ Institute

2, institutional Area, Near Dainik Bhaskar-Jaipur

Page 2: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

Project Highlights

Total Built up Area: - 1, 20,000Sq.ft

Total Floor of Project: -2 Basement + 6 Floors

(Gym, Swimming pool, Banquet hall, Conference hall, Bar, Tennis& Squash)

Builders & Developers

M/S RAS Officers’ Institute,

Registered office at 2, institutional Area,

Near Dainik Bhaskar- Jaipur (Raj.)

Consultants & Management Team

Architectural Consultant Project Management Consultants

Architect Design & Services (ADS) M/S SUPERSTRUCTURES E-6B, Hanuman Path, Office No. 40, 4th Floor, Trinity Mall,

New Sanganer Road Sodala- Jaipur New Sanganer Road, Jaipur

Mr. Lokesh JoshiMob: 91-9680282624. Phone: 91-9314932438, 0141 5106606

Mr. Kulvinder Singh Mob: 91-9314480610

Structural Consultant MEP Consultant M/S SANRACHNA M/S Cube Consultant

S-41, AMBA BARI, JAIPUR A-8, Jamna Nagar Sodala- Jaipur

Mr. Sandeep Garg Mob: 91-9799496696 Mr. Sanjay Vajpayee Mob: 91-9214308430

Interior Designer Consultant M/S Sthapatya Architects A-58 Shanti path, Tilak Nagar, JAIPUR

Ms. Ritu Khandelwal Mob: 91-9829016773

Page 3: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

Contractor Agencies

Civil Contractor Electrical Work Contractor

M/S H. R. Gwala M/S Vijay Electric service

F9/465, Chitrakoot, Vaishali Nagar-Jaipur VivekVihar, New Sanganer Road, Sodala.

Mr. H.R. Gwala Mob: 91-9783940001 Mr. Shyam Vijay Mob: 91-9783300501

Plumbing Contractor Waterproofing Contractor M/S Gayatri Plumbing M/S NS Solutions

B-50, Jawahar Nagar, Jaipur 3/77, Agarwal Farm, Mansarovar, Jaipur

Mr. Jeet Ram Mob: 91-9829008082 Mr. Shrikant Dandia Mob: 91-9214529486

Fire Fighting Contractor False Ceiling Contractor

M/S Men At Work M/s Shakuntalam Interiors Pvt. Ltd.

S-3, CD 304, Dadudayal Residency, 100-A, Civil Lines, Ajmer Road, Jaipur

Dadudayal Nagar, Mansarover, Jaipur. Mr. Sandeep Tholiya Mob: 91-9829059622

Mr. Ravi Kumawat Mob: 91-9928084922

Heating, ventilation, and air conditioning (HVAC)

Daikin Air conditioning India Pvt. Ltd (Higher Side)

S-10-11-12, Second Floor, Geejgarh Tower, Hawa Sadak

Jaipur,302006

M/s K.P. Airtech (Lower Side)

Yashoda Nikunj,BB-51, Jai Ambey Nagar, Tonk Road,

Jaipur – 203018, Rajasthan.

Mr. K.K. Sharma Mob: 91-9829063283

Page 4: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

4 | P a g e

INDEX

S. No. Content Page. No.

(i) Executive Summary 5

(ii) Project View 5

(iii) Milestone Achieved: At Execution Level 6

(iv) Manpower & Material Status 6-8

(v) Proposed Schedule & Material Procurement Details 8-11

(vi) Drawing Status 12

(vii) Progress Photographs 13-19

(viii) Cube Test Report 19

(ix) Pending Decisions & Requirements 20

Distribution to:-

(i) RASO’I Members

(ii) Architect Design & Services (ADS)-Architectural Consultant

(iii) Sthapatya- Interior Designer

Page 5: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

5 | P a g e

EXECUTIVE SUMMARY

Terrace floor columns and parapet shuttering,bar binding & casting 40% completed.

Upper basement ramp slab & driveway slab casting completed.

UGWT excavation work in progress.

Fourth & fifth floor brick masonry work in progress.

First Floor plastering work completed & fourth Floor Plastering work in progress.

First & second floor low-voltage wall conducting work in progress.

Ground & first floor electrical ceiling conducting work in progress.

Sprinkler line laying of fourth & ground floor.(scope of fire fighting work).

HVAC copper piping work in progress at ground floor & first floor ducting work in progress.

Fire Staircase fifth floor LVL. BB, Shuttring & Casting in progress.

Plumbing work in progress at fourth floor.LVL.

Earth filling in South & East Side areas of building.

PROJECT VIEW as on 30th

SEPTEMBER 2018

Page 6: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

6 | P a g e

MILESTONES ACHIEVED

(i) At Execution Level:-

(i) Terrace floor Parapet wall & mumty slab concreting (casting) completed.

(ii) Casting of terrace floor columns concreting (casting) 40% completed.

(iii) North side Boundary wall Stone masonry work started.

(iv) Plastering work started at fourth floor.

(v) HVAC copper piping work Started at ground floor.

(vi) Electrical Wall conducting work Completed at fourth floor.

(vii) Building Front Side Plantation completed.

(viii) UGWT Excavation work started.

(ii) At Decision Level:-

(i) UG water tanks floor level redesigned from lower basement to upper basement floor level.

(ii) Astral PVC Material Finalized for Electrical Conducting work.

(iii) Italian Marble finalized for flooring from R.K. Marble.

(iv) SCM Engineering finalized for Swimming pool work.

(v) ThyssenKrupp finalized for elevator (lift).

MANPOWER DEPLOYED AT SITE STATUS

Total Manpower Deployed at Site by different Agencies / Vendors

Manpower Details Till 30th

September‘18

S. No. Name of Contractor Work Skilled Unskilled Total

1.0 H.R. Gwala Civil Work 60 210 270

1.1 SK Burman/ (H.R. Gwala) Shuttering 70 140 300

1.2 Govind/(H.R. Gwala) Bar Binding 90 150 240

1.3 Ashok/ (H.R. Gwala) Brick Work 210 230 440

1.4 Bharosi/ (H.R. Gwala) Plaster Work 150 160 310

2.0 Vijay Electrical Service Electrical 110 100 210

3.0 Gayatri Plumbing Plumbing 20 20 40

4.0 NS Solutions Waterproofing 0 0 0

5.0 Man At Work Fire Fighting 50 130 180

6.0 WhiteWash White Wash 30 40 70

7.0 K.P. Airtech HVAC 45 60 105

Total 835 1240 2075

Page 7: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

7 | P a g e

MATERIAL STATUS

A. Steel Received & Consumed Details in September‘18

Diameter of Bar Received Till

Date (MT)

Received in

September

18 (MT)

Consumed in

September ’18

(MT)

Total

Consumed

till Date

(MT)

Balance at

Site as on

30.09.18 (MT)

8mm 85.68

- 1.00 82.68 3.00

10mm 206.97

- 5.00 203.97 3.00

12mm 94.43

- 1.50 94.43 0.00

16mm 55.09

- - 55.09 0.00

20mm 73.59

- 0.50 69.59 4.00

25mm 179.52

- 2.00 176.52 3.00

32mm 132.21

- - 132.21 0.00

Total (MT) 827.53

- 10.00 814.49 13.00

B. Cement Consumed & Received Details in month of September ’18

Location Received

Till Date

(Bags)

Received in

September

’18 (Bags)

Consumed

Till Date

(Bags)

Consumed in

September

’18 (Bags)

Balance at

Site as on

30.09.18

(Bags)

Remarks

At Site 33237 600 33177 1540 60

At RMC

Plant

5792-

372=5420

0 5420 0 0 372 Bags Amount

adjusted in Vendor’s

Bill

Total (Bags) 38657 600 38597 1540 60

C. Aggregate Consumed & Received Details in month of September’18

(i) 10mm Aggregate

Location Received

Till Date

(C.Ft)

Received in

September

’18 (C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

September

’18 (C.Ft)

Balance at Site

as on 30.09.18

(C.Ft)

Remarks

At Site 47539 - 47439 1400 100

At RMC

Plant

11506 - 12271 - 0 Excess 765 C.ft Amount

adjusted in Vendor’s Bill

Total (C.Ft) 59045 - 59710 1400 100

(i) 20mm Aggregate

Location Received

Till Date

(C.Ft)

Received in

September’18

(C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

September

’18 (C.Ft)

Balance at Site

as on 30.09.18

(C.Ft)

Remarks

At Site 77530 1520 76630 2020 900

At RMC

Plant

17911 - 18130 - 0 Excess 219 C.ft Amount

adjusted in Vendor’s Bill

Total (C.Ft) 95441 1520 94760 2020 900

Page 8: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

8 | P a g e

D. Sand Consumed & Received Details in month of September ’18

Location Received

Till Date

(C.Ft)

Received in

September

’18 (C.Ft)

Consumed

Till Date

(C.Ft)

Consumed in

September

’18 (C.Ft)

Balance at Site

as on30.09.18

(C.Ft)

Remarks

At Site 95404 2160 94904 1677 500

At RMC

Plant

18112 - 18100 - 0 12 C.ft Amount adjusted

in Vendor’s Bill

Total (C.Ft) 113516 2160 113004 1677 500

E. Bricks Consumed & Received Details in month of September ’18

Location Received

Till Date

(Nos.)

Received in

September

’18 (Nos.)

Consumed Till

Date (Nos.)

Consumed in

September

(Nos.)

Balance at Site

as on 30.09.18

(Nos.)

At Site 381000 0 377000 15000 4000

Total (Nos.) 381000 0 377000 15000 4000

F. AAC Block Consumed & Received Details in month of September ’18

Location Received

Till Date

(Nos.)

Received in

September’18

(Nos.)

Consumed Till

Date (Nos.)

Consumed in

September

(Nos.)

Balance at Site

as on 30.09.18

(Nos.)

At Site 6222 3022 5422 3822 800

Total (Nos.) 6222 3022 5422 3822 1600

PROPOSED SCHEDULES FOR THE MONTH OF OCTOBER ‘18

Following activities are planned for the Month of October ‘18

(i) Completion of O.H. Tank R/W shuttering, bar binding & casting work.

(ii) Fire Staircase up-to Terrace Floor Level bar binding, shuttering & Casting work.

(iii) Fourth & Fifth Floor brick work.

(iv) Earth filling in surrounding areas of building.

(v) Lower Basement & Ground Floor Plumbing Drainage & fourth floor Toilets Internal Works.

(vi) U.G. Water tank shuttering, bar binding & concreting (casting) work.

(vii) Fourth & Third Floor Electrical Wall & Ceiling Conducting Works.

(viii) Ground Floor Fire Alarm wiring work. (Fire Fighting).

(ix) First Floor HVAC Duct making , Installation & copper Piping of ground floor.

(x) North & East Side Boundary wall foundation & brick work.

(xi) Second & Third Floor Plastering Work.

(xii) Lower & Upper Basement Trimix flooring work.

Page 9: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

9 | P a g e

STEEL & CEMENT REQUIREMENT FOR THE MONTH OF OCTOBER ‘18

A. Steel Requirement Detail for the Month of October‘18

S. No. Location of Use Dia. Of Bars # Required

Quantity (MT)

Available at

Site (MT)

Net Required

Quantity (MT)

1.

U.G. water tanks, Fire

staircase Boundary wall

Beams & Columns.

8mm 3.00 3.00 -

10mm 8.00 3.00 5.00

12mm 12.00 - 12.00

16mm 5.00 - 5.00

20mm 4.00 4.00 -

25mm 5.00 3.00 2.00

32mm - - -

Total Qty Required (MT) 37.00 MT 13.00 MT 24 MT

B. Cement Requirement Detail for the Month of October‘18

(i) Cement (PPC) At site

S. No. Description of Work Qty. Unit Coefficient Quantity Reqd. (Bags)

1 PCC & RCC Work

(i) UGWT Casting including R/W 220 Cum 7.08 1558

(ii) Terrace Floor Water Tanks Top Slab

& R/W 80 Cum 7.08 566

(iii) O.H. water tank raft & Walls 50 Cum 7.08 354

(iv) Plaster Work 3020 Sqmtr 0.11 334

(v) Stone masonry for Boundary Wall 200 cum 0.84 168

Total Required Bags of Cement for the Month of October ’18 2980

Total Available Bags of Cement at Site 60

Net Required Bags of Cement for the Month of October’18 2920

Say 3000

Page 10: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

10 | P a g e

C. Aggregate Requirement Detail for the Month of October‘18

(i) 10mm Aggregate

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) UGWT Casting including R/W 220 Cum 11.515 2534

(ii) Terrace Floor Water Tanks Top

Slab & R/W 80 Cum

11.515 912

(iii) O.H. water tank raft & Walls 50 Cum 11.515 576

Total Required Qty of 10mm Aggregates for the Month of October’18 4022

Total Available Qty of 10mm Aggregate at Site 100

Net Required Qty of 10mm Aggregate for the Month of October’18 3922

Say 4000

(ii) 20mm Aggregate

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) UGWT Casting including R/W 220 Cum 16.8 3696

(ii) Terrace Floor Water Tanks Top

Slab & R/W 80 Cum

16.8

1344

(iii) O.H. water tank raft & Walls 50 Cum 16.8 840

Total Required Qty of 20mm Aggregates for the Month of October’18 5880

Total Available Qty of 20mm Aggregate at Site 900

Net Required Qty of 20mm Aggregate for the Month of October’18 4980

Say 5000

A. Sand Requirement Detail for the Month of October ‘18

(i) Sand

S.No Description of Work Qty. Unit Coefficient Quantity Reqd. (C.Ft)

(i) UGWT Casting including R/W 220 Cum 17.30 3086

(ii) Terrace Floor Water Tanks Top

Slab & R/W 80 Cum

17.30 1384

(iii) O.H. water tank raft & Walls 50 Cum 17.30 865

(iv) Plaster Work 3020 Sqmtr 0.50 1510

(v) Stone masonry for Boundary Wall 200 Cum 14.82 2965

Total Required Qty of Sand for the Month of October’18 9810

Total Available Qty of Sand at Site 500

Net Required Qty of Sand for the Month of October’18 9310

Say 9500

Page 11: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

11 | P a g e

A. Bricks Requirement Detail for the Month of October ‘18

S.No Description of Work Unit Qty Reqd.

(i) Fourth &Fifth Floor Brickwork. Nos. 5000

(ii) Boundary Wall Brickwork.(front Side) Nos. 26500

Total Required Qty. of Bricks for the Month of October ‘18 31500

Total Available Qty of Bricks at Site 4000

Net Required Qty of Bricks for the Month of October ‘18 27500

Say 27500

B. AAC Block (9”)Requirement Detail for the Month of October ‘18

S.No Description of Work Unit Qty Reqd.

(i) Fifth Floor Brick work. Nos. 1600

Total Required Qty. of Bricks for the Month of October ‘18 1600

Total Available Qty of Bricks at Site -

Net Required Qty of Bricks for the Month of October ‘18 1600

Say 1600

C. Weekly Material Procurement Schedule month of October ‘18

WEEKLY MATERIAL REQUIREMENT SCHEDULE FOR THE MONTH OF SEPTEMBER‘18

S.

NO.

MATERIAL

DESCRIPTION 1st WEEK 2nd WEEK 3rd WEEK 4th WEEK

TOTAL

QUANTITY

Remarks

(if any)

1 Steel 16 9 - - 24 MT

2 Cement(PPC) 1500 600 600 300 3000 Bags

3 10mm Aggregate 2000 1400 600 - 4000 C.Ft

4 20mm Aggregate 2000 1500 800 700 5000C.Ft

5 Sand 4000 3000 1000 1500 9500C.Ft

6 Stone 7056 - - - 7056 cft

7 Bricks 15000 10000 2500 - 27500 Nos.

8 AAC Block 1600 - - - 1600 Nos.

Page 12: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

12 | P a g e

DRAWING STATUS

Status of Drawings in the Month of September‘18

Following is the status of drawings in month of August from Architect Design & Services (ADS) by PMC

Engineer and issued to concerning Contractors at site.

S.No Date of

Received Drawing Title Drawing No.

Rev.

No. Remark

1 01.09.2018 First Floor Working Plan 176/RASC/FFW/10 03 Received

2 01.09.2018 Third Floor Working Plan 176/RASC/FFW/12 - Received

3 01.09.2018 Fourth Floor Working Plan 176/RASC/FFW/13 - Received

4 - Terrace Floor Working Plan - - Not Received

5 01.09.2018 Fifth Floor Working Plan 176/RASC/FFW/14 - Received

6 03.09.2018 O.H. Water Tank Detail - - Received

7 03.09.2018 Water Tank Covering Slab Detail - Received

8 03.09.2018 Shuttering plan Mumti Slab 176/RASC/TFA/WT/15B Received

9 03.09.2018 Water Tank Section Detail - Received

10 18.09.2018 Lower to fifth Floor Working Plan 176/RASC/FFW/07-14 Received

11 28.09.2018 U.G.Tank Section Detail - Received

12 28.09.2018 U.G.Tank Detail - Received

13 28.09.2018 Pump Room Floor Slab Detail - Received

14 28.09.2018 Puddle Flange Detail for UGT 176/RASC/U.G.Tank Detail Received

15 28.09.2018 Puddle Flange Detail for OGT 176/RASC/TFP/WTS/15B Received

16 28.09.2018 North Side Boundary Wall Section

176/EASC/Ground floor

plan

Received

17 28.09.2018 Swimming Pool Area Working Plan - Received

18 28.09.2018 Swimming Pool Area Section Details - Received

List of Drawings Required in October ’18

Following Drawings are required at site in the Month of October’18

S. No. Drawing Title Date of Requirement

on OR Before

1 Terrace Floor Column & Covering Details with Sections. 10.10.2018

2 STP & Rain water harvesting Pit Details With Sections. 10.10.2018

3 West Side Boundary Wall Plans With Sections. 10.10.2018

4 Final Building Elevation Details With Sections. 10.10.2018

5 Outer Development Details With Sections including All MEP Services. 10.10.2018

6 Fire Staircase Covering detail with Brick work & Railing Details. 10.10.2018

7 Main Gate MS Section Details & Guard Rooms Shuttering & Reinforcement Details.

10.10.2018

8 Revised Door-Window Schedule. 10.10.2018

9 Revised MEP Plan (HVAC, Fire Fighting System) 14.10.2018

10 False Ceiling Plans (Second to Fifth Floor) with Section & Sectional Details.

10.10.2018

Page 13: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

13 | P a g e

PROGRESS PHOTOGRAPHS

Site View 30th

September ’18

Site visit by Structural consultant & Architect

Page 14: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

14 | P a g e

Progress Review Meeting at DLB Office

Page 15: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

15 | P a g e

Project Review Meeting at Site (06.09.2018)

Kishangarh Visit for Italian Marble Finalization of Flooring Material (12.09.2018)

Page 16: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

16 | P a g e

Plastering Work in Progress at First & Fourth Floor

AAC Block Masonry Work In Progress at Fourth & Fifth Floor Outer Side

Page 17: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

17 | P a g e

Fire Fighting Work In Progress at Ground Floor

UGWT Excavation Work In Progress

Page 18: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

18 | P a g e

HVAC Work (Copper piping & Ducting) In Progress at Ground & First Floor

Electrical & Plumbing Work In Progress at Fourth Floor

Page 19: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

19 | P a g e

Stone Masonry Work (North & East Side)

Cube Testing Report Month of October-2018

Page 20: MONTHLY PROGRESS REPORT - RAS Associationrasassociation.com/news/RASO'I MPR September-2018.pdf · Prepared By SUPERSTRUCTURES (PROJECT MANAGEMENT CONSULTANTS) MONTHLY PROGRESS REPORT

RAS Officers Institute (Club House) Monthly Progress Report September ‘18

20 | P a g e

MAJOR PENDING DECISIONS & REQUIREMENTS AT SITE

Some other decisions pending at site are as follows:-

(i) Electrical Accessories & Fixtures Vendors to be finalized.

(ii) STP Vendor to be finalized.

Signature Signature

Mr. Vipin Pachlangia Mr. Kulvinder Singh

(Project Head) (PMC Head)

Mobile: 91-9929312666 Mobile: 91-9314480610