1
15.053 February 8, 2005
More Linear and Non-linear Programming Models
Announcements:– Lecture check problems = practice for quiz– Can everyone attend office hours?
• 3-5 Monday and Wednesdays– Should I post lectures on web before class?– Homework cover sheets
2
Overview of Lecture
Goals– get practice in recognizing and modeling linear
constraints and objectives– and non-linear objectives– to see a broader use of models in practice
Models– Postal Worker Problem– Portfolio Optimization– Conjoint Analysis
3
Overview
Scheduling Postal Workers (5 in 7)– The model– Practical enhancements or modifications– Two non-linear objectives that can be made
linear– A non-linear constraint that can be made linear
4
Scheduling Postal WorkersEach postal worker works for 5 consecutive days, followed by 2 days off, repeated weekly.
Day Mon Tues Wed Thurs Fri Sat Sun
Demand 17 13 15 19 14 16 11
Minimize the number of postal workers (for the time being, we will permit fractional workers on each day.)
5
Formulating as an LP
Select the decision variables– Let x1 be the number of workers who start
working on Monday, and work till Friday– Let x2 be the number of workers who start on
Tuesday …– Let x3, x4, …, x7 be defined similarly.
6
The linear programDay Mon Tues Wed Thurs Fri Sat Sun
Demand 17 13 15 19 14 16 11
Minimize z = x1 + x2 + x3 + x4 + x5 + x6 + x7
x1 + x4 + x5 + x6 + x7 ≥ 17 Mon. subject tox1 + x2 + x5 + x6 + x7 ≥ 13 Tues.x1 + x2 + x3 + x6 + x7 ≥ 15 Wed.x1 + x2 + x3 + x4 + x7 ≥ 19 Thurs.x1 + x2 + x3 + x4 + x5 ≥ 14 Fri.
x2 + x3 + x4 + x5 + x6 ≥ 16 Sat.x3 + x4 + x5 + x6 + x7 ≥ 11 Sun.
xj ≥ 0 for j = 1 to 7
7
A Closer Look at the Constraint Matrix
x1 x2 x3 x4 x5 x6 x7
1 0 0 1 1 1 1 ≥ 17 Mon
1 1 0 0 1 1 1 ≥ 13 Tues
1 1 1 0 0 1 1 ≥ 15 Wed
1 1 1 1 0 0 1 ≥ 19 Thurs
1 1 1 1 1 0 0 ≥ 14 Fri
0 1 1 1 1 1 0 ≥ 16 Sat
0 0 1 1 1 1 1 ≥ 11 Sun
It is cyclically repeating in both rows and columns.
8
On the selection of decision variables
A choice of decision variables that doesn’t work– Let yj be the number of workers on day j.– No. of Workers on day j is at least dj. (easy to formulate)– Each worker works 5 days on followed by 2 days off (hard).
Conclusion: sometimes the decision variables incorporate constraints of the problem. – Hard to do this well, but worth keeping in mind– We will see more of this in integer programming.
9
Some Modifications of the Model
Suppose that there was a pay differential. The cost of workers who start work on day j is cj per worker.
Suppose that one can hire part time workers (one day at a time), and that the cost of a part time worker on day j is pj.
Work with your partner to modify the model taking into account the new information.What are the new decision variables?What are the changes to the model?
10
What are the new decision variables?
subject to x1 + x4 + x5 + x6 + x7 ≥ 17x1 + x2 + x5 + x6 + x7 ≥ 13x1 + x2 + x3 + x6 + x7 ≥ 15x1 + x2 + x3 + x4 + x7 ≥ 19x1 + x2 + x3 + x4 + x5 ≥ 14
x2 + x3 + x4 + x5 + x6 ≥ 16x3 + x4 + x5 + x6 + x7 ≥ 11
xj ≥ 0 for j = 1 to 7
Minimize z =
11
Another EnhancementSuppose that the desirable number of workers on day j is dj, but it is not required. Let sj be the “excess” number of workers day j. sj > 0 if there are more workers on day j than dj; otherwise sj ≤ 0.
What is the minimum cost schedule, where the “cost” of having too many workers on day j is fj(sj), which is a non-linear function?
12
What are the new decision variables?
What is the resulting non-linear model?
subject to x1 + x4 + x5 + x6 + x7 d1
x1 + x2 + x5 + x6 + x7 d2
x1 + x2 + x3 + x6 + x7 d3
x1 + x2 + x3 + x4 + x7 d4
x1 + x2 + x3 + x4 + x5 d5
x2 + x3 + x4 + x5 + x6 d6
x3 + x4 + x5 + x6 + x7 d7
xj ≥ 0 for j = 1 to 7
z = Minimize
13
A non-linear function that can be made linear.Suppose we want to minimize |x – 4| + |y – 7|
subject to other constraints.
This is equivalent to minimize z1
s.t. z1 ≥ x – 4z1 ≥ 4 – x
+ other constraints
minimize z1 + z2s.t.
z2 ≥ y – 7z2 ≥ 7 – y
Suppose the objective is minimize |s1| + … + |s7|. Take a minute and modify the last NLP to make it a linear program.
14
subject to x1 + x4 + x5 + x6 + x7 d1
x1 + x2 + x5 + x6 + x7 d2
x1 + x2 + x3 + x6 + x7 d3
x1 + x2 + x3 + x4 + x7 d4
x1 + x2 + x3 + x4 + x5 d5
x2 + x3 + x4 + x5 + x6 d6
x3 + x4 + x5 + x6 + x7 d7
xj ≥ 0 for j = 1 to 7
Minimize
15
A 2nd non-linear objective that can be made linear.
Minimize y = max[ (x - 1) , (.5x + 1) ] s.t. other constraints.
1 2 3 4 5 6
1
2
3
4
5
min ys.t. y ≥ x - 1
y ≥ .5x + 1+ other constraints
16
Exercise: minimize the maximum number of excess workers needed on any day: that is
Minimize max (s1, …, s7), where sj ≥ 0 for each j.
Minimize
subject to x1 + x4 + x5 + x6 + x7 - s1 = 17x1 + x2 + x5 + x6 + x7 - s2 = 13x1 + x2 + x3 + x6 + x7 - s3 = 15x1 + x2 + x3 + x4 + x7 - s4 = 19x1 + x2 + x3 + x4 + x5 - s5 = 14
x2 + x3 + x4 + x5 + x6 - s6 = 16x3 + x4 + x5 + x6 + x7 - s7 = 11
xj ≥ 0 , sj ≥ 0 for j = 1 to 7
17
A ratio constraint:
Suppose that we need to ensure that at least 30% of the workers have Sunday off.
How do we model this?
(x1 + x2 )/(x1 + x2 + x3 + x4 + x5 + x6 + x7) ≥ .3
Note: the denominator is always positive.
If we multiply both sides of the inequality by the denominator, we get a linear constraint.
(x1 + x2 ) ≥ .3 (x1 + x2 + x3 + x4 + x5 + x6 + x7)
.7x1 + .7x2 - .3x3 - .3x4 - .3x5 - .3x6 - .3x7 ≥ 0
18
Other enhancements
Require that each shift has an integral number of workers – integer program
Consider longer term scheduling– model 6 weeks at a time
Consider shorter term scheduling– model lunch breaks
Model individual workers– permit worker preferences
19
Towards a Portfolio Model
an investment model over multiple time periods
maximize return and minimize risk
NEOS Portfolio Problem
20
Returns of a portfolioExample: Stock A has a return of 10%
Stock B has a return of 20%
Return on Investment
0.10.120.140.160.180.2
0 0.2 0.4 0.6 0.8 1
Proportion of Stock A
Ret
urn
21
Evaluating Risk
0.1500.1600.1700.1800.1900.2000.2100.2200.230
0 0.2 0.4 0.6 0.8 1Proportion of Stock A
SD o
f Ret
urn
of
Port
folio
Stock A has a s.d. of .223
Stock B has a s.d. of .223
Cov(A, B) = 0
Varying the Covariance
22
Portfolio Selection Example
There are 3 candidate assets for out portfolio, X, Y and Z. The expected returns are 30%, 20% and 8% respectively (if possible we would like at least a 12% return). Suppose the covariance matrix is:
What are the variables?3 1 0.51 2 0.40.5 0.4 1
X Y ZXYZ
−−
− −
Let X,Y,Z be percentage of portfolio of each asset.
23
Portfolio Optimization
Minimize Variance of Portfolio
subject toExpected Return >= Required returninvestments sum to 100%investments are non-negative
Variance of portfolio = variance due to individual investments + 2 * sum of covariances.
24
Portfolio Selection Example2 2 23 2 2 0.8X Y Z XY XZ YZ+ + + − −Min
st 1.3 1.2 1.08 1.121
0, 0, 0
X Y ZX Y ZX Y Z
+ + ≥+ + =≥ ≥ ≥
The quadratic programs (non-linear programs) arising from portfolio problems are easy to solve.
Portfolio Example
25
Risk vs. ReturnRisk vs. Return
0
0.5
1
1.5
2
2.5
3
3.5
0.12 0.17 0.22 0.27Expected Return
Varia
nce
of P
ortfo
lio
26
Portfolio Optimization in Practice
Problems arising in practice often have additional constraints.
Using linear programming one can handle:– upper bounds on each investment– lower bound (or upper bound) on the proportion
of assets held in high tech firms, or whatever.
Other constraints and costs can be handled using integer programming– transaction costs– lower bounds on investments that are chosen
27
What is Conjoint Analysis?
Conjoint analysis is a data analysis for estimating how much respondents value different features.
Illustration: Consider a PDA that has 6 attributes– Size– Cell phone– Hands free operation– Extended battery– Wireless internet– Price
How much does the respondent value each attribute?
28
Why Use Conjoint Analysis?
Possibility: Ask the respondent to estimate the partworths.
Alternative: Use stated preferences on final products to backward infer partworth values.
29
Conjoint Analysis
Widely used in product designs and pricing
Lots of research over the past 25 years.
30
Simplified PDA Example
BTB T∅
T = Titanium Case; B = Big Size
Four PDA Models:• Model ∅ – Small / Leather Case• Model B – Big / Leather Case• Model T – Small / Titanium Case• Model BT – Big / Titanium Case
31
Simplified PDA Example
B BT∅ T
T = Titanium Case; B = Big Size
Utilities given partworths v(B) and v(T):
U∅ = 0 UB = v(B)UT = v(T) UBT = v(B) + v(T)
32
v(T)
BT
B
T
∅
BB
∅
T
BT
v(B)
Which PDA is preferred?
33
BTB T∅
T = Titanium Case; B = Big Size
A consumer then rank orders the products (or cards), and we infer information about the values.
Example: The customer prefers BT, B, T, and ∅, in order
Consider a graph in 2 dimensions.
Then u(BT) > u(B) > u(T) > u(∅).
v(B) + v(T) > v(B) > v(T) > 0
34
v(T)
BT > T > B > ∅
BT > B > T > ∅
B > BT > ∅ > T
B > ∅ > BT > T∅ > B > T > BT
∅ > T > B > BT
T > ∅ > BT > B
T > BT > ∅ > B
BB
∅
T
BT
BT
B
T
∅
v(B)
Example: Suppose 0 < v(T) < v(B) ≤ $50.
35
36
Conjoint Analysis.
Let v(j) be the value of aspect j.
For each product i, ∈
= ∑ ( )( )i j Aspect i
U v j
∑ 2,
( )iji jMin y
∈= ∑ ( )
. . ( )i j Aspect is t U v j
whenever product i is preferred to product j.+ ≥ ( )i ijU y U j
for all i and j≥ 0i jy
37
Conjoint analysis
There are lots of bells and whistles one can add
Important part of marketing profession
presented in a lecture in May: a recent improvement that may yield better results due to – Dahan– Hauser– Orlin– Yee
38
Summary
Postal worker problem– illustration of different types of constraints and
objectives that can arise and how to deal with them
Portfolio Optimization
Conjoint Analysis
39
Lecture check problems**
Section 3.7 #2Section 3.8 #1Section 3.9 #1Section 3.10 #1Section 3.11 #1