Page 1: Morphettville Racecourse Sandtrack Rehabilitation Works AustStab Awards of Excellence 2013 South Australian Jockey Club Innovation or Excellence in Sustainability

Morphettville Racecourse Sandtrack Rehabilitation Works

AustStab Awards of Excellence 2013AustStab Awards of Excellence 2013

South Australian Jockey ClubInnovation or Excellence in Sustainability in pavement stabilisation

Sponsored by

Page 2: Morphettville Racecourse Sandtrack Rehabilitation Works AustStab Awards of Excellence 2013 South Australian Jockey Club Innovation or Excellence in Sustainability

Overview Morphettville Sandtrack

Increasingly contaminated with material from the base of the sandtrack. Source for hoof bruising in the race horses

Prone to saturation Inadequate drainage Subsurface drainage

Water-proof the sandtrack to allow year round operation without soft clay contamination from the subgrade.

Potentially expensive risks that needed a solution and not just treatment.

ObjectivesEliminate material contamination from the base of the sandtrack into the both the sand of the sandtrack and the material of the ‘Pro-Ride

Page 3: Morphettville Racecourse Sandtrack Rehabilitation Works AustStab Awards of Excellence 2013 South Australian Jockey Club Innovation or Excellence in Sustainability

Operating Environment/Context

Several different types of tracks at the Morphettville Racecourse.

Training carried out on the sandtracks and the ‘Pro-Ride’ each morning.

Training is carried out year round

Time to carry out the rehabilitation works minimised.

Critical tasks that could not be avoided Removal of the existing contaminated sand Placement of new clean sand.

Page 4: Morphettville Racecourse Sandtrack Rehabilitation Works AustStab Awards of Excellence 2013 South Australian Jockey Club Innovation or Excellence in Sustainability

Cement Stabilisation Treated with 3% cement Provided a bound layer for additional strength Designed to mitigate material migration from the base

into the sand layer.

The Initiative

Lime Stabilisation Scraper used Treated with 2% lime. Assists in the drying of the existing base Helped to waterproof flood prone areas of the

track.

Removal of the contaminated sand, lime and cement stabilisation of the existing base material, priming of this surface prior to the placement of clean sand.

Sand removal Scraper used with a scraper and carried out in less than two days.

Page 5: Morphettville Racecourse Sandtrack Rehabilitation Works AustStab Awards of Excellence 2013 South Australian Jockey Club Innovation or Excellence in Sustainability

Remove the sand and place new base course on top of the existing base course. Not feasible due to the required drainage of the ‘Pro-Ride’ track

Excavation/Removal of existing base material and replace with a 20mm FCR. Significantly more expensive Increased the required time to establish as suitable base course. Did not treat the problem Material migration would occur much sooner

Alternative Options

Page 6: Morphettville Racecourse Sandtrack Rehabilitation Works AustStab Awards of Excellence 2013 South Australian Jockey Club Innovation or Excellence in Sustainability

Outcomes InnovationPavement loading from a horse’s hoof is one of the highest point loads a pavement is exposed to. Lime &

cement stabilisation provided the endurance increasing strength and durability without harsh stones that potentially breaks free and harm the horses’ hooves.

 Economic ImpactThis stabilisation option represents great value for money and a faster alternative to get a superior project

outcome. Traditionally this has been done using remove & replace which proves expensive.

Productivity It was required that the job had to start and finish between race meetings therefore the task was time

critical. Using this process reduced the impact on the down time of this part of the racecourse.

Sustainability & EnduranceThis process eliminated some of the reoccurring problems that have existed in the past with the base at

this location.

 Environmental ImpactUsing this process increased the amount of material that was able to be recycled and utilised site worn

materials.