moving from corporate strategy to project strategy

Upload: bregebre95

Post on 02-Jun-2018

239 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    1/15

    MOVINGFROM CORPORATESTRATEGYTOPROJECTSTRATEGY

    Much of the management writing around

    strategy tends to cover the practices at

    the corporate and business level; there is

    a dearth of writing about how corporate

    strategy gets implemented by projects

    and programs and translated into pro-

    gram or project strategies. This paper

    reviews evidence from four case studies

    together with questionnaire data from

    PMI Europe members, which shows that

    the processes, practices, and people

    issues involved in moving from corporate

    strategy to programs and projects is done

    in a much more systematic way than is

    generally recognized. The findings point

    to areas that future revisions of the

    PMBOKGuide should be looking at.

    Keywords: corporate strategy; project strat-egy; portfolio management; programmanagement; project management; valuemanagement; risk management; leader-ship; competencies

    2005 by the Project Management Institute

    Vol. 36, No. 4, 5-18, ISSN 8756-9728/03

    Introduction

    Corporate strategy is one of the most actively researched and taught subjects

    in business today. Projects and project management are often quoted as

    important means of implementing strategy, but there is some confusion in

    the literature on how this happens and, in any case, the topic has not been the sub-

    ject of detailed review.

    This paper reports on research funded by PMI, industry, and academia that

    addressed the way corporate strategy is developed and implemented via the man-

    agement of portfolios, programs, and projects. It does so by detailing the key find-

    ings from four case studies, together with data from a survey of PMI members.

    Developing Corporate Strategy

    Corporate strategy is a means of thinking through and articulating how an organi-

    zations corporate goals and objectives will be achieved. This strategy is then typically

    operationalized at a strategic business unit [SBU] level; strategic initiatives are then

    often clustered into portfolios of programs and projects for implementation. (The

    distinction between programs and projects and portfolios is defined shortly.)

    Much of traditional management writing tends only to cover the strategic man-

    agement processes that formulate and implement strategy at the corporate level (for

    example, Thompson, 2001; Mintzberg & Quinn, 1996; Hill & Jones, 2001); there is

    a dearth of writing about how corporate strategy gets translated into implementa-

    tion, particularly at the program or project level. Yet, in practice, the two sets of activ-

    ities are well connected; projects and programs are important ways for strategy to beimplemented in the enterprise and we ought to understand much better how this

    occurs.

    Strategic management is often ambiguous and complex, fundamental and

    organization-wide, and generally has long-term implications (Johnson & Scholes,

    1997). While the typical corporate planning process is generally ordered and ana-

    lytical, strategy management is also a dynamic process. Mintzberg (1996) has dis-

    tinguished deliberate strategy from that which is emergent that is, becomes

    evident as it, and events, emerge with time (Mintzberg & Waters, 1994). This emer-

    gence suggests a more incremental approach to strategy formulation and imple-

    mentation where results are regularly appraised against benefits and changes are

    made and managed against the evolving picture of performance.

    PETER W. G. MORRIS, Professor of Construction and Project Management

    School of Construction and Project Management, The Bartlett School of

    Graduate Studies, University College London

    ASHLEY JAMIESON, Research Fellow, School of Construction and Project

    Management, The Bartlett School of Graduate Studies, University College London

    ABSTRACT

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    2/15

    Similarly, the interaction between

    projects or programs and the enter-

    prises strategy may be both deliber-

    ate (as formal vehicles for strategy

    implementation, as in capital expendi-

    ture projects, for example), and emer-

    gent (in that when they are

    implemented, they create new condi-tions that, in turn, influence and shape

    the intended strategy) (Grabher,

    2002). Consequently projects and pro-

    grams often have a two-way relation-

    ship with the corporate environment

    in which they evolve. And though

    there may be formal strategy planning

    processes and practices, strategy may

    not be realized in as rigid or formal a

    manner as many planners assume. This

    said, however, a formal strategy

    process is important it brings clarity

    and discipline.

    But the role of project manage-

    ment in implementing such strategy is

    often not clear. Crawford (2005), for

    example, found that senior managers

    believed project managers should not

    be involved in strategy formulation.

    Thomas, Delisle, Jugdev, and Buckle

    (2002) found that project manage-

    ment is seen as strongly execution ori-

    ented and as such is not perceived as

    strategically important by senior man-

    agers. Bourgeois and Brodwin (1984)proposed that project managers

    should be involved in strategy formu-

    lation but are not competent to carry

    out implementation effectively since

    they will not have been exposed to the

    factors that initiate change in projects,

    a view echoed by Englund and

    Graham (1999). And there is a grow-

    ing view, at least in the UK, that busi-

    ness and organizational change

    projects are really managed best by

    program management, as defined, forexample, by the Office of Government

    Commerce (OGC, 2003), rather than

    by project management (Bartlett,

    1998; Partington, Pellegrinelli, &

    Young, 2005; Reiss, 1996).

    It is important that organizations

    understand properly their business

    management model and the position

    of project, or program, management

    within it; and hence for project man-

    agement to see how they are sit along-

    side and are perceived by the

    business management functions.

    Research shows, for example, that one

    of the reasons new product innovation

    projects often fail is because they lack

    wider organizational support

    (Wheelwright & Clark, 1992). While

    project management practitioners may

    think their function is central to thesuccess of a company, it may have little

    meaning within the enterprise unless it

    is clearly established and embedded

    within the enterprises structure and

    business management models and

    processes.

    The involvement of some disci-

    pline explicitly concerned with the

    management of projects in strategy

    implementation seems a priori to be

    sensible, if only because of the need of

    senior management to have some con-

    trol over expenditure and intended

    action. McElroy (1996) emphasizes

    the need for senior management

    involvement if project management is

    to be successful in strategy implemen-

    tation, a view shared by Broner,

    Ruekert, and Walker (2002). And good

    governance practice now explicitly

    requires, among several things, formal

    alignment between business, portfolio,

    program and project plans, and trans-

    parent reporting of status and risks to

    the Board (Association for ProjectManagement [APM], 2004).

    Senior management involvement

    may also be needed for quite opera-

    tional issues. Not all strategy imple-

    mentation is just downwards from the

    corporate level through portfolios to

    programs and projects. Just as in strate-

    gic planning there is upward flow from

    Strategic Business Units (SBUs), so in

    implementation there is, as we have

    seen, management information and

    action bearing up from programs andprojects onto portfolio, business unit

    and corporate strategy. For example, a

    fundamental responsibility of project/

    program management is to manage

    the resources needed to define and

    deliver its programs and projects effec-

    tively. We shall see that resource man-

    agement becomes a critical factor in

    moving from corporate strategy into

    project implementation.

    Hierarchy is usually important in

    any discussion of implementing strate-

    gy. A hierarchy of objectives and strate-

    gies can generally be formed as a result

    of using a strategy planning process;

    this can be a highly effective means of

    structuring and managing strategy, and

    communicating it to the organization.

    One such model is Archibalds hierar-

    chy of objectives, strategies and projects(Cleland, 1990; Archibald, 2003). This

    model proposes that objectives and

    strategies are developed at the policy,

    strategic, operational and project levels

    and cascaded down, thereby ensuring

    alignment and continuity of strategy.

    Similarly, Kerzner (2000) shows a hier-

    archy where strategic plans are cascad-

    ed from corporate strategy to SBUs and

    from SBUs to supporting plans.

    Another model is the Stanford Research

    Institutes System of Plans

    (Mintzberg, Ahlstrand, & Lampel,

    1998).

    Partington (2000), in distinguish-

    ing the three levels of strategy as corpo-

    rate, business and operational, suggests

    that operational level strategies tend to

    focus on programs and projects

    (though Shenar and Dvir [2004] define

    the levels slightly differently). However,

    the implications of Archibalds work

    (2003) and Kerzners (2000) is that the

    linkage often starts or can start even

    higher: something we shall, in fact, findconfirmed in the research reported

    here.

    Turner (1999) proposes a cascade

    to show how organizations position

    programs and projects to achieve their

    development objectives. As a result of

    our research we have adapted this

    model to include business strategy and

    portfolios, as shown in Figure 1. This

    said, the model should be treated with

    caution for it reflects the intended

    deliberate sequencing of movementfrom corporate strategy to projects and

    fails to capture the iterative nature of

    emergent information and strategy

    modification described above.

    Artto and Dietrich (2004) outline

    a number of practices for managing

    the strategic-portfolio-project linkage

    in multiple project environments.

    Grundy (1998) too has proposed a

    number of techniques to move corpo-

    rate strategy into portfolios, programs

    (and projects), such as scenario plan-

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    3/15

    ning, force-field analysis, stakeholder

    analysis, and attractiveness/imple-

    mentation difficulty analysis. Indeed,

    as the case studies reported below

    show, many companies have, in fact,

    developed structured approaches for

    creating and managing strategy via

    portfolios, programs, and projects inways which are integrated with busi-

    ness strategy.

    Portfolios, programs, and projects

    Turner (2000) points out that the

    majority of projects take place as part of

    a portfolio of several projects or pro-

    grams. Project portfolio management is

    the art and science of applying a set of

    knowledge, skills, tools, and techniques

    to a collection of projects or programs

    to meet or exceed the needs and expec-tations of an organizations investment

    strategy (Dye & Pennypacker, 1999).

    According to Platje, Seidel, and

    Wadman (1994), a project portfolio is

    a set of projects that are managed in a

    coordinated way to deliver benefits that

    would not be possible if the projects

    were managed independently, a view

    shared by Artto, Martinsuo, and Aalto

    (2001). A slightly different but wide-

    ly accepted view is that a project port-

    folio is a collection of projects to be

    managed concurrently under a single

    management umbrella, where each

    project may be related or independent

    of the others (Thiry, 2004; Martinsuo &

    Dietrich, 2002). Archer and

    Ghasemzadeh (2004) stress that port-

    folio management is pre-eminently

    about selecting or prioritizing thebest projects or programs to proceed

    with. Project portfolio management,

    then, is predominantly about choos-

    ing the right project, whereas project

    management is about doing the proj-

    ect right (Cooke-Davies, 2002, 2004).

    Archer and Ghasemzadeh (1999)

    have provided a general framework for

    project portfolio selection that demon-

    strates the need for strategy to be set at

    the corporate level and then filtered

    down to the project level.Subsequently, they emphasized the

    importance of aligning resource

    demand with resource availability to

    achieve a set of strategic goals (Archer &

    Ghasemzadeh, 2004). Knutson (2001)

    points out that the project portfolio

    management process provides a means

    of consistently and objectively evaluat-

    ing each proposed project that is vying

    for a limited pool of resources, thereby

    aiding the process of making the most

    effective strategic use of the resources.

    Linking company strategy to port-

    folio development is critical, particular-

    ly when company strategy involves both

    a high degree of innovation and a high

    rate of growth (Wadlow, 1999).

    Advances in portfolio selection and

    management practice have been

    notably strong in new product develop-ment (Archer & Ghasemzadeh, 2004;

    Cooper, Edgett, & Kleinschmidt, 2001),

    whereas there is evidence that the top

    performing businesses display strong

    management support for portfolio

    selection and management, using for-

    mal portfolio management methods to

    manage their portfolio strategy within

    the context of the enterprise business

    strategy (Cooper, Edgett, &

    Kleinschmidt, 1999). Other examples of

    portfolio management practiceemployed by a diversity of major com-

    panies are given in Cooper, Edgett, and

    Kleinschmidt (1998). Artto and

    Dietrich (2004) provide examples of

    portfolios of different project types and

    an outline of the major types of

    methodologies used in portfolio selec-

    tion. Shenhar and Dvir (2004) propose a

    strategic portfolio classification frame-

    work that is based on the need to select

    projects due to their strategic impact and

    to form a policy for project selection.

    Portfolio

    Strategy

    Portfolio

    Objectives

    Program

    Strategy

    Program

    Objectives

    Project

    Strategy

    ProjectObjectives

    Phase

    Strategy

    Phase

    Objectives

    Team

    Strategy

    Team

    Objectives

    Individual

    Strategy

    Individual

    Objectives

    STRATEGIC PLANNING FOR PROJECTS

    Business

    Strategy

    Context

    Source: The Handbook of Project-Based Management, 2nd ed.J.R.Turner 1999 Reproduced by kind permission of the Open University Press / McGraw-Hill Publishing Company.

    Adapted by Morris and Jamieson (2004).

    Figure 1: Linking corporate and project strategy

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    4/15

    Archer and Ghasemzadeh (2004)

    identify risk and outsourcing as having

    a particularly strong impact on portfo-

    lio selection and management. They

    point out that a key criterion for suc-

    cessfully applying risk evaluation in

    portfolio selection is that risk assess-

    ment and quantification be uniformlyapplied across all projects and teams, a

    requirement now mandated by good

    governance (APM, 2004).

    Programs

    Program management is a powerful

    way of coordinating projects that have

    a shared business aim and, according

    to Thiry (2004), is the most suitable

    methodology for ensuring the success-

    ful implementation of strategies, since

    it is subtler and more able to respond

    to emerging data. Both portfolio man-

    agement and program management

    focus on prioritizing resources and

    optimizing the business benefit

    (Bartlett, 1998; Partington, 2004; Reiss,

    1996). Program management is more

    involved in day-to-day implementation

    management than portfolio manage-

    ment, which is more periodic and is

    strongly analytical. Pellegrinelli,

    Partington and Young (2003) see

    implementing strategy through pro-

    gram management as involving contin-uous re-formulation and adjustment.

    There is some confusion in the lit-

    erature and a variation in practice

    over just what really is involved in pro-

    gram management. Most commenta-

    tors define program management as

    involving the management of a collec-

    tion of interrelated projects. Several

    perspectives exist on the optimal ways

    to configure programs to achieve

    strategic objectives and deal with

    change (Murray-Webster & Thiry,2000). Some emphasize the technolo-

    gy base, as in platform projects

    (Wheelwright & Clark, 1992). Others,

    particularly those coming from

    Information Technology, also empha-

    size the importance of business benefit

    (OGC, 2003). Pellegrinelli (1997) and

    Murray-Webster and Thiry (2000) have

    proposed a more generic portfolio and

    program typologies.

    Programs are often ongoing or

    long-term and are subjected to both

    uncertainty and ambiguity (Thiry,

    2004). Programs and program man-

    agement are frequently used in large

    organizations to implement strategic

    initiatives. The UK Office of

    Government Commerce (OGC), for

    example, considers the alignment

    between strategy and projects to beone of the main benefits of program

    management (OGC, 2003) though

    this seems rather dated in light of the

    more recent guidance on good gover-

    nance (APM, 2004): they require a

    decision management paradigm which

    takes into account the appropriate

    strategic perspective. Programs often

    have to strive for the achievement of a

    number of conflicting aims whereas

    projects aim to achieve single predeter-

    mined results (Wijen & Kor, 2000).

    Projects on the other hand are more

    typically seen as concentrating on

    achieving one single particular result

    within set time and cost constraints

    (Grg & Smith, 1999). Many com-

    mentators position projects as more

    appropriate for implementing delib-

    erate (planned) strategies, while see-

    ing programs for both deliberate and

    emergent (unplanned) strategies.

    (However, in the research to be report-

    ed here, we found this to be so for the

    aerospace case, but not for the drugdevelopment or construction cases.)

    Projects

    Projects, in distinction to programs,

    have a unique objective and follow a

    single development life cycle. PMIs

    PMBOK Guide (2004) is cursory in its

    treatment of the linkage between the

    organizations business requirements

    (there is no real discussion of business

    strategy) and the project (via its charter

    [4.1], project plan [4.3], and scope[4.2; 5.1.1]). Turner (1999) is better,

    by advocating the development of a

    comprehensive definition of a project

    at the start of the project, in which

    business plans are aligned with project

    plans containing key elements of proj-

    ect strategy. Simister (2000) shows the

    development of business cases and

    strategic briefs as part of the project

    definition process. Gardiner (2005)

    provides an authoritative text with sev-

    eral case studies on project strategy.

    Morris (1997) summarizes the elements

    a project strategy based on an analysis

    many projects in his historical account

    the development of project managemen

    The Association for Project Managem

    Body of Knowledge (APM BOK) (Dixo

    2000) gives fuller recognition to the bu

    ness context within which the projresides, as well as recognizing portfolio a

    program management, and requireme

    management. (The business and operati

    requirements of a project frequently aff

    project strategy significantly and, for t

    reason, the APM BOK identifies requi

    ments as a key project manageme

    process (Davis, Hickey, & Zweig, 20

    Stevens, Brook, Jackson, & Arnold, 1997

    Work by the authors in integrat

    what the PMBOK Guide and the AP

    BOK have to say about the way strate

    shapes project definition shows the la

    number of factors involved in creati

    project strategy at the front-end of a pr

    ect (Morris & Jamieson, 2004). This hig

    lights the need for an effective way

    manage project strategy creation, cover

    not only the front end of a project, but t

    entire project life cycle.

    As the case studies reported bel

    show, many companies have, in fa

    developed structured approaches for cre

    ing and managing project (and progra

    strategy that cover the entire project lcycle and are integrated with the busin

    strategy development processes.

    Competencies, roles, responsibilities a

    accountabilities for moving strategy

    Corporate strategy is not translated in

    project strategy by process alone. Movi

    strategy through such processes and pr

    tices as we have just reviewed requires

    extensive range of personal competenc

    and a clear definition of roles, responsib

    ities and accountabilities.Following Boyatzis (1982), seve

    definitions of competence (and capabili

    have been offered. Hornby & Thom

    (1989) for example defined competen

    as the knowledge, skills and qualities

    effective managers, and pointed to t

    ability to perform effectively in a spec

    work situation.

    The UK Institution of Civil Enginee

    competency framework (2000) compri

    12 key management roles and appro

    mately 140 associated competenci

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    5/15

    Elements of strategy management are

    covered in both the corporate and

    business management roles, and proj-

    ect management is shown as having

    responsibility for project strategy.

    Crawford (2000) reveals a number of

    knowledge, skills and personal attrib-

    utes of project managers, includingthat of strategic direction although, as

    we noted above, her later survey

    (Crawford, 2005) found that senior

    managers did not consider that project

    managers should be involved in proj-

    ect strategy. Morris, Jamieson, and

    Shepherd (2005) have suggested that

    this might be a result of her having

    used the PMBOK Guide (Project

    Management Institute, 2004) for her

    conceptual definition of project man-

    agement: the PMBOK Guide, as we

    have seen, assumes no real involve-

    ment of project management in front-

    end definition, including strategy

    formulation (Morris, 2005).

    Examples of core competences

    related to project strategy are provided

    in the case studies in Morris &

    Jamieson (2004). We shall also see evi-

    dence in the case studies that project

    leadership is increasingly being recog-

    nized as a key competence in shaping

    and implementing project strategy.

    (See the drug development and trans-portation case studies.)

    Research methodology

    The literature on how corporate strate-

    gy gets implemented via portfolios,

    programs, and projects is thus diverse

    and patchy. While that on portfolio

    management is quite thorough, the

    treatment is primarily from an analytic

    viewpoint. There is little on implemen-

    tation issues (although there is more in

    the more recent material; for example,Archer & Ghasemzadeh, 2004). The lit-

    erature on program management, as

    we have already seen, is often quite

    confused, not least on what indeed

    program management is. There is a lack

    of detail in the APM BOK (Dixon,

    2000) on how corporate strategy influ-

    ences project strategy while the subject

    is not addressed in the PMBOK Guide

    (PMI, 2004). New guidelines on proj-

    ect and corporate governance, however,

    stress the importance of clear align-

    ment between corporate and project

    strategy (APM, 2005).

    This research project was, there-

    fore, set up to explore and illustrate in

    more rigorous detail how corporate

    strategy is implemented by project,

    program, and portfolio management.

    Given the availability of fundingand time available, the research was

    designed to be exploratory. That is, it

    was recognized that only a limited

    number of case studies and survey data

    could be undertaken, and that the find-

    ings, therefore, could not be, and

    should not be, taken as either exhaus-

    tive or conclusive. (There is much room

    for additional research in this area.)

    The case study method is particu-

    larly appropriate for exploratory

    research since cases are descriptive and

    explanatory. Case studies were selected

    from four different but important

    areas: the aerospace, financial, phar-

    maceutical and transportation (con-

    struction) sectors (though admittedly

    all from the sponsoring organizations

    perspective: that is, from the perspec-

    tive of the company making a capital

    investment).

    Semi-structured interviews were

    conducted with senior managers using

    a questionnaire-based approach. Data

    and information gathered from theinterviews, and documentation from

    each company, were analyzed and syn-

    thesized to develop models of how

    corporate strategy was formulated and

    implemented through portfolios, pro-

    grams, and projects. The results and

    findings of each case study were vali-

    dated by the appropriate company

    before a cross analysis of all the results

    and findings was carried out.

    A full report on the research was

    published by PMI in the fall of 2004(Morris & Jamieson, 2004). This publi-

    cation contains full details of the four

    case studies, the highlights of which

    are as follows.

    Four case studies of moving from corpo-

    rate to project strategy

    We studied four companies to provide

    evidence and insight into the way cor-

    porate strategy is created and moved

    into programs and projects a global

    aerospace company, a division of a

    global pharmaceutical company, a

    group within a global financial servic-

    es company, and an international

    transportation facility owner and oper-

    ator for our purposes, a leading con-

    struction client [owner]. A summary of

    some of the key findings are summa-

    rized below.

    Aerospace company

    The company is a Tier 2 supplier. It

    requires all of its business activities to

    be assigned to a program. Each pro-

    gram has to have a client. There is a

    hierarchical cascade of objectives from

    the corporate level, through SBUs, to

    programs and projects. Orders are pro-

    gressed through a stage-gated develop-

    ment process. Eleven key project

    management topics are reviewed at

    each gate, one of which is project strat-

    egy. Project strategy is managed, in

    considerable detail, by project teams

    throughout all the stages and all the

    associated phases of the project man-

    agement process, as illustrated

    schematically by Figure 2.

    The company also has a specific

    process for managing a rapid response

    to changes impacting strategy.

    The companys highly integrat-

    ed, structured approach used to

    translate corporate and businessstrategies into project strategy, and

    then to manage it through the entire

    project management process and

    project life cycle, illustrates the

    importance it gives to project strate-

    gy and its management, as well as

    the level of priority which should be

    given; it provides a good model of

    how this can be done.

    Global financial services company

    The company has a highly structuredprocess of developing and approving

    its corporate plan but the role of

    project management in its imple-

    mentation is not made explicit. The

    program and project processes are

    self-standing and begin with refer-

    ence to the business units vision,

    mission, strategies and objectives.

    Once an initiating letter of intent

    is authorized for the project, work

    begins on defining the business case.

    This defines, inter alia:

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    6/15

    The program operational vision

    The relationship with the business

    strategy plan

    Program/project organization structure

    Risk and resource plans

    Delivery plan

    Project briefs

    WBS

    Upon approval of the business

    case, the project is prepared for execu-

    tion using a Mobilize Program

    process, which takes the results of the

    previous planning processes and incor-

    porates them into the project manage-

    ment plan. Project strategy as a term

    and activity is not mentioned in the

    project management process from this

    point onward. However, the way inwhich the project is to be managed is

    covered in detail in the following sec-

    tions of the project management plan:

    Project objectives

    Project schedule

    Project budget

    Resource plan

    Risk management plan

    A complete set of project briefs.

    The strategy for the project is man-aged and maintained through the

    operational vision within the business

    case, and is in force until the close of

    Phases of

    Each Process

    Stage

    Key Tasks of

    Each Phase

    Key Topics of

    Each Key Task

    Strategy Strategy

    Scope

    Risk

    Scope

    Risk

    Concept Execute

    Project Management Process

    Managing Major Projects Process

    Business Process Model

    In-Service

    Figure 2: A structured approach to creating and moving project strategy

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    7/15

    the project. The lack of a single coher-

    ent project strategy document, clearly

    related to the business case, can lead to

    loss of business rationale in some

    cases. It is recognised that there could

    be a tighter linkage between business

    strategy and project implementation.

    Global drug development company

    Drug development involves the pro-

    gression of chemical entities discov-

    ered in the laboratory through a highly

    structured series of tests in animals and

    humans for clinical efficacy and com-

    mercial attractiveness. In a big phar-

    ma like the one studied here there

    will be several dozen chemical entities

    (candidates) being progressed

    through the pipeline at any one time.

    The management of this development

    activity involves a complex matrix of

    functional lines and projects and

    programs, clustered under therapeutic

    areas (Foulkes & Morris, 2004).

    Most compounds prove not to

    work in the way hoped and the attri-

    tion rate is thus enormously high, cer-

    tainly in the earlier stages of the

    pipeline. However, large pharma com-

    panies typically have many more com-

    pounds in hand than they have

    resources available to work on them.

    Hence there is an on-going dialoguebetween senior management working

    at the therapeutic governance level on

    portfolio prioritization and resource

    allocation and project-level status and

    outlook.

    Portfolios are very important: they

    essentially form the hand from

    which the future of the company is

    being played. The term programs is

    less well embedded. Programs are seen

    as constituting a technical platform a

    particular type of drug of which theremay be various versions (slightly dif-

    ferent indications, dosages or delivery

    mechanisms, for example). Projects, in

    effect, have two meanings. One is the

    major project of developing a com-

    pound from discovery to regulatory

    approval and into the marketplace.

    The other is the activity of getting the

    compound to the next milestone

    review point in its development.

    The company uses a very struc-

    tured project management process to

    manage projects. The process is geared

    to each of the phases of the life cycle

    and utilizes a plan, form team, moni-

    tor and replan structure. It is also

    linked to a series of project manage-

    ment methodologies, which identify

    the actions to be taken by the project

    team at any point in the project orphase of the development life cycle.

    Project strategy is identified as one of

    the topics that need to be implement-

    ed by the project team during the

    plan phase and there is a standard

    list of contents for the project strategy.

    Because of the high rate of attri-

    tion, spending too much time detail-

    ing long-term project strategy is not

    seen to be useful. However, it is still

    considered essential to develop and

    maintain a flexible strategy for the suc-

    cess of the project. Thus project strate-

    gy is aligned with the portfolio strategy

    and is revised as the project progresses.

    Most pharmaceutical project man-

    agement organizations distinguish

    between a Project Leader (or Director)

    role and the Project Manager.

    Typically, the former has a strong feel-

    ing for the science of the development;

    the latter is more concerned with the

    operational management of the proj-

    ect. The project leader/director typical-

    ly assumes a much more prominent

    role in shaping project strategy, though

    this is not always the case. The split is

    reminiscent of Kotters distinction

    between leadership and management

    (Kotter, 1990; Morris, 2004).

    Transportation (construction) companyThe company is one of the largest and

    most efficient airport operators in the

    world. It applies the OGSM method-

    ology developed in Procter and

    Gamble for defining objectives, goals,

    strategies, and measures in a sequen-

    tial manner cascading these down

    through business units to programs

    and projects.

    Figure 3 shows that the strategic

    business units, capital investment plans

    (CIPs), business governance, project

    governance and major and minor proj-

    ects are all set within the environ-

    ment of the corporate OGSMs, and

    that each level determines that of the

    next in descending order.

    The company does not use the

    term portfolio but does use a process

    for measuring the strategic contribu-

    tion, uncertainty/complexity, and

    value-for-money of its capital invest-

    ments at the SBU levels and for evalu-

    ating, selecting and prioritizing its

    M

    ajo

    rPr

    ojectsPro

    ces

    s

    ProjectBoard

    ProjectGovernance

    BusinessGovernance

    SBUs/O

    ther OGSMs

    Corporate

    OGSMs

    AMProcess

    ProjectEnvironment

    SBU/ProjectEnvironment

    MinorProjectsProcess

    SBUs & OtherFunctions CIPs(Inc AM)

    Corporate CIP

    Figure 3: Corporate, business unit, and project environments

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    8/15

    programs and projects. Program man-

    agement is seen as the management of

    a group of projects with similar aims.

    Projects are managed via a stage

    gate process with a project board

    responsible to project governance for

    the day-to-day running of the project.

    The project is split into two stages:development and project delivery. The

    former is managed by a development

    manager, the latter by a project leader

    (not project manager this term is

    deliberately avoided by the company,

    since, to some, it seems too bureau-

    cratic and does not sufficiently empha-

    size the required level of leadership: a

    view reminiscent of the preceding

    pharma case and Kotter).

    The gated review process ensures

    that projects are aligned to business

    strategy (and corporate strategy) as they

    are set up, authorized and executed. A

    project management process is used to

    develop the project definition and key

    project management plans, a summary

    of which is considered to encapsulate

    project strategy. However, project strat-

    egy as a term and practice is not used

    in the company. The performance of

    the project team is not measured

    against the objectives of the project,

    expressed in terms of project strategy,

    but only in terms of business strategy.

    Cross-cutting findings

    The following general findings can be

    drawn from the case studies.

    Business models

    Some companies had project manage-

    ment clearly embedded in their busi-

    ness model; others did not. The

    aerospace company had a very power-

    ful business process model in which

    program management (and projectstrategy) played a prominent part. The

    international transportation compa-

    ny/construction owner also had a

    strong business process model, though

    project management, as a formal disci-

    pline had a less visible role. The phar-

    maceutical company had a process

    model that was dominated by the drug

    development process this is not the

    same as a business model per se, but is

    common to all drug development

    being driven by regulatory require-

    ments and was clearly the major busi-

    ness process. Project and portfolio

    management (and program manage-

    ment to a lesser extent) are important

    aspects of this process. The financial

    services company had a high-level

    business process but this was less visi-

    ble than the aerospace and transporta-tion business models.

    Cascading corporate strategies into proj-

    ects and strategy plans

    All the companies created corporate

    objectives, goals and strategies using

    processes like the strategic manage-

    ment processes described by Mintzberg

    and others. As in Turners model, these

    objectives, goals and strategies were

    cascaded to the SBUs or equivalent

    organizational entities, which, in turn,

    and in conjunction with corporate

    strategy planners, developed their own

    objectives, goals, and strategies. The

    SBUs subsequently developed objec-

    tives, goals, and strategies with and for

    their respective program and project

    teams, again in some instances using

    fully interconnecting business and

    project management processes. The

    importance of project portfolio man-

    agement was recognized by all the

    companies.

    In all four cases the programand/or project teams developed project

    strategies that aligned with the SBU and

    corporate strategy using project strategy

    or similar processes. The outputs of the

    processes containing the objectives,

    goals, and strategies included strategy

    plans, business plans, deployment

    plans and project plans, the hierarchy of

    which, in most cases, was similar to

    Archibalds hierarchy of objectives,

    strategies and projects, as reflected in

    the aerospace case in Figure 2.The pharmaceutical development

    company reviewed and rebalanced its

    portfolios frequently formally, every

    six months. The interaction of emerging

    trial results data on the therapy area

    portfolio strategy was strongly evident,

    and project managers (and project

    directors) took a leadership role in

    shaping the next phase of implementa-

    tion. This required new proposals for

    project or program strategy and these

    influenced portfolio strategy.

    The aerospace company formally

    reviewed project strategy as a p.m.

    topic alongside a dozen or so other

    prescribed aspects of project manage-

    ment at each phase gate review, very

    much as good governance practice

    now recommends. The drug develop-

    ment company did the same thing atmajor gate reviews (going into

    Exploratory Development and then

    into Full Development).

    Portfolio management

    The importance of project portfolio

    management was recognized by all the

    companies. The pharmaceutical com-

    pany had a dedicated project portfolio

    management practice that played a very

    important part in project development.

    Within the companies, portfolio man-

    agement was used primarily to select

    and prioritize programs and projects,

    not to manage programs or projects.

    Corporate and business units assem-

    bled a strategic portfolio of programs

    and projects, or measured the strategic

    contribution of a program or project,

    using a number of strategic and project

    management processes, tools and tech-

    niques. Company management boards

    or committees of senior managers

    adopted or rejected projects based on

    this information. (This was in almostthe identical manner described in Artto

    & Dietrich, 2004.)

    Program management

    Program management was practiced

    by all the companies primarily in the

    sense of managing a group of high

    value projects sharing a common aim

    and/or of delivering regular benefits

    over a protracted period of time.

    In the aerospace company pro-

    gram management was positioned asthe management of a number of inter-

    related projects but critically also cov-

    ering operations and maintenance.

    This is crucial in this company since

    much of the product margin is in oper-

    ations and logistics support rather

    than initial capital sales. In the finan-

    cial services company there was much

    more emphasis in program manage-

    ment on managing multiple, interre-

    lated projects for business benefit. In

    the pharmaceutical case the emphasis

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    9/15

    was on asset management, in the

    sense that the program represented a

    basic chemical entity (a technology

    platform in Wheelwright and Clarks

    phrase [1990]), which can be promot-

    ed as a brand. Program management

    in the transportation/construction case

    was used to manage multiple, interre-lated projects.

    Program management and project

    management activities were carried out

    in all cases using the same set of com-

    mon processes, variously called inte-

    grated program management, program

    management, or even project manage-

    ment. The development of program

    strategy and its alignment with corpo-

    rate and business strategy was, as a

    consequence, achieved in a similar way

    to that for projects. (This aligns with a

    finding by the authors from a later

    piece of work, on updating the APM

    BOK (Morris, Jamieson, & Shepherd,

    2005), where we found program man-

    agers identified the same practices as

    being needed as project managers,

    though in some cases by a slightly

    reduced amount.)

    Project strategy

    The business case was the key element

    of the corporate and project manage-

    ment interface in all the companies. Anoutline project strategy was developed

    early in all the projects and was aligned

    with corporate and business strategies.

    Subsequently, business strategy, in

    most of the companies, was turned into

    a comprehensive project strategy fol-

    lowing project management processes

    and incorporating many of the usual

    project management practices.

    It is important to note that good

    governance practice now clearly

    requires that projects and programshave an approved implementation

    plan which is aligned with the overall

    business strategy and that this be

    reviewed at pre-defined authorization

    points (APM, 2005). Many companies

    now do this on a routine basis.

    Two of the companies used a very

    structured approach to create and

    manage project strategy. The aerospace

    company had institutionalized a proj-

    ect strategy management practice that

    was equivalent to, for example, risk

    management or technical manage-

    ment. The pharmaceutical company

    had identified specific project strategy-

    related issues for each phase and stage

    of the project development life cycle.

    Both companies assigned roles and

    responsibilities for managing the exe-

    cution of these processes. The othertwo companies used a less structured

    approach. Though they developed

    management plans for their projects,

    they tended to neither summarize the

    plans nor develop a single project strat-

    egy statement from them. The compa-

    nies also tended not to use the term

    project strategy in their project man-

    agement processes. (There is a research

    issue left open here, namely whether it

    would be beneficial to manage project

    strategy as a more formal, single docu-

    ment and process.)

    The aerospace and pharmaceutical

    companies managed project strategy

    for effectively the entire project life

    cycle and not just at the front-end of a

    project. The other two companies

    managed the project strategy as part of

    managing the business case for the

    project.

    Processes and procedures

    The processes that were most consis-

    tently used were those in which thestructure and content were described

    at a practical level (e.g., flowcharts

    with inputs and outputs for key

    processes) and those that identified

    who was accountable and responsible

    for carrying out the process activities.

    Conversely, when the procedures were

    described in too much detail staff

    tended not to use them. The best

    examples of the deployment of the

    business models and associated

    processes were those that were fullydocumented and incorporated within

    the companys Quality Management

    System, and were web-based and

    available online throughout the

    organization (see also Artto &

    Dietrich, 2004). Where this approach

    was not used, companies, neverthe-

    less, linked the activities of their busi-

    ness units and projects to ensure

    alignment of strategy.

    Strategy was consciously and sys-

    tematically value managed in the

    pharmaceutical company. The trans-

    portation/construction company had a

    strong value-for-money (VM) orien-

    tation, but did not use VM as a special

    practice.

    All the companies integrated other

    key project development practices into

    their strategy development processes,such as risk management, technical

    and commercial management, and

    safety management.

    Roles, responsibilities and accountabilities

    In the pharmaceutical and transporta-

    tion/construction companies, project

    strategy was developed and main-

    tained by governance and project lead-

    ership teams through business related

    processes and not exclusively through

    project management processes. In the

    pharmaceutical case this was driven by

    the characteristics of the regulated

    development process and by gover-

    nance review of the emerging portfo-

    lio and individual project data. Project

    managers focused more on the sched-

    uling, follow-up and general control

    activities in support of the project lead-

    ers strategy-shaping activities. In the

    transportation/construction case, strat-

    egy was developed using the OGSM

    method cascaded down through SBUs

    in classical deliberate manner.

    Competencies and frameworks

    In general, project management resources

    and capabilities figured highly in creat-

    ing, deploying and maintaining enter-

    prise, portfolio, program, and project

    strategies. All the companies specified the

    roles, responsibilities and accountabili-

    ties of those involved in the business

    management and project management

    processes, some using comprehensive

    sets of tables and matrices for example,RACI tables (Responsible, Accountable,

    C o o r d i n a t i o n / C o n s u l t a t i o n ,

    Information) that were linked directly to

    the processes. These covered in detail all

    the phases and stages of the project man-

    agement process and project life cycle,

    including those for creating and main-

    taining project strategy or for implement-

    ing enterprise strategy within the context

    of the project business case, these RACI

    tables identifying who does what and

    when at any point along the process.

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    10/15

    Roles, responsibilities and accountabilities

    The companies also employed a num-

    ber of other methods to identify and

    specify the skills, knowledge, behaviors

    and experience required to develop

    and manage project strategy. These

    included competencies for senior proj-

    ect management staff, such as manag-ing vision and strategy; and project

    management functional competencies

    covering knowledge and experience of

    strategy-related areas like scope man-

    agement.

    Survey data on how companies move

    strategy from the corporate level to

    projects

    The case studies provided a rich quali-

    tative context in which to explore how

    companies moved from the corporate

    level to program and project strategy.

    But the data sample was obviously

    small. To provide more evidence we

    carried out a survey of members in a

    number of PMI Chapters in European

    countries. A series of 32 multiple-

    choice questions were developed and

    used to examine the processes, prac-

    tices, and people issues involved in

    moving strategy from the corporate

    level to projects.

    Seventy-five responses (about

    50% from UK) were received frompeople at various levels of seniority, in

    small, medium, and large enterprises

    in a diverse range of business sectors

    such as aerospace, automotive, IT,

    telecommunications, pharmaceuticals,

    retail, transportation and publishing;

    and academia and consultancy. The

    response rate about 2% is too

    small for the results to be considered

    as statistically valid, but can be taken

    as indicative: the research is, as we have

    said, at best only exploratory. Theresults are as follows.

    How business management models are used

    67% used a generic business model.

    50% of those believed they had exten-

    sive processes for moving corporate

    goals into project strategy; 90% had

    adequate or better interconnection

    between corporate, business and proj-

    ect management processes. Over 53%

    recognized a hierarchy of objectives

    and strategies.

    Program management and portfolio

    management50% used some form of portfolio man-

    agement, of which 95% used some

    form of program management (with

    75% having business benefit manage-

    ment as an explicit part of this).

    Project management and project strategy

    85% used extensive or partial project

    management processes to manage proj-

    ect strategy; most (75%+) had specific

    strategy inputs into project manage-

    ment, and 65% did this in an emer-

    gent manner; 85% used a gate review

    POPULATION %

    BOX 1: Project Management and Project Strategy

    1.Organizations had extensive or partially integrated project Almost all management processes to help manage project strategy, which contained:

    Project strategy management 85

    Requirements management, project strategy, project 75 definition, and project scope management

    Requirements management, project definition, and 85 project scope management

    2.Organizations had specific strategy inputs to integrated project Most management processes, which included:

    Corporate strategy 75

    Corporate strategy and business strategies 65

    Corporate, business, and portfolio strategies 50

    Corporate, business, portfolio, and program strategies 45

    Portfolio and program strategies only 55

    Program strategy 75

    3.The integrated project management processes delivered the following outputs:

    A project or program plan and strategy plan 50

    Other project management plans 75

    A project or program plan, strategy plan and other plans 45

    4.Organizations with integrated project management processes 65 managed project strategy dynamically

    5.The roles and responsibilities for developing, implementing, andupdating project strategy were specified in:

    Project management procedures 60

    Project plans 55

    6.Project plans were formally reviewed at project gates 85

    Those who did not and thought they should 85

    7.Peer groups formally reviewed project plans 75

    Those who did not and thought it would be sensible to do 65

    8.It was clear who approved and signed off project strategy 75

    9.Strategy was expected to be upgraded and reviewed:

    During the development of the project 65 Systematically as projects develop from concept to execution 55

    Of which:

    It was systematically undertaken at project review gates 85

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    11/15

    process with clear sponsorship respon-

    sibilities, and 65% upgraded strategy as

    the project progressed. (See Box 1.)

    Project value management and its link to

    project strategy.

    55% had a process for optimizing the

    value of the project, of which 75%

    combined it with risk management.

    Only 25% used Value Engineering.

    (See Box 2.)

    Project management competencies.

    80% had project management compe-

    tencies defined, of which 75% includ-

    ed those for managing the strategy

    development process. (See Box 3.)

    A combined analysis of the find-

    ings of the case studies and survey was

    then carried out, the results of which

    are reflected in the findings and con-

    clusions below.

    Overall findings and conclusions

    Before reviewing the overall conclu-

    sions of the research, a number of

    caveats and cautions should be made

    regarding the reliability and generaliz-

    ability of the research findings.

    There is clearly a limitation on the

    generalizability due to:

    The size and scale of the investigation;

    The sample of case studies;

    The size of the survey;

    The types of programs and projects; and

    The effectiveness and performance of

    the processes, practices and compe-

    tencies surveyed.

    All the companies were at differ-

    ent stages of developing, implement-

    ing or improving their business

    models and the information therefore

    was time-specific.

    The scope of the survey was

    broad and therefore the number of

    questions per topic was relativelysmall. Consequently the coverage

    and depth of some topics such as

    value management and competencies

    were limited. A few respondents to

    the questionnaire indicated that

    some questions were ambiguous and

    could be interpreted differently. Also,

    some of the terms may not be well

    known, for example Value

    Management. The survey analysis did

    not take account of different business

    sectors.Overall, the response rate was

    too small for the results to be statisti-

    cally valid and to be treated as any-

    thing other than indicative.

    Despite these caveats, we neverthe-

    less feel a number of conclusions can

    be drawn from the research.

    Moving from corporate to project strategy

    Project and program management is

    widely used as a means of implement-

    ing corporate and business strategy

    POPULATION %

    BOX 2: Survey Findings Value Management

    1.A process was used for optimizing the value of proposed 55 project/program strategy. Of which:

    Value was expressed as a benefit over resources used 80

    The process was formalized as value management 55

    Value management workshops were held 40 at strategic stages in the life of the project

    Those not using a process for optimizing the value of 55 project/program strategy, but believed they should

    2.Value engineering was practiced on programs and projects. 25 Of which:

    Value engineering (optimizing the value of the technical 80 configuration) was distinguished from value management

    Those not practicing value engineering on programs and 56 projects thought they should

    3.The value optimization process was integrated with risk management 75

    Those that thought it should not be done 40

    POPULATION %

    BOX 3: Survey Findings Project Management Competencies

    1.Project management skills and knowledge competencies 80required to manage programs or projects were formally defined

    Of which:

    Those required to develop program and project strategy 75

    Linking the competencies to personal appraisal 80 and development systems

    Linking personal objectives to project objectives 65

    2.Those that did not formally define the project management skills 50 and knowledge competencies incorporated the management of

    project strategy in job descriptions or job specifications.

    3.Organization-wide behavioral competency frameworks were used 60

    Those that did not use them, but believed they should 45

    4.Competency support programs for program and project managers 70 were provided.

    Of which:

    Covered support for project strategy development 66

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    12/15

    and is a key business process.

    Normatively, we should expect strate-

    gies to be aligned and moved from the

    corporate level through portfolios,

    programs and projects in a systematic

    and hierarchical manner that provides

    cohesion, visibility and an effective

    means of communication. Not all isdeliberate, however; there is emer-

    gence and iteration. Project strategy is

    managed dynamically.

    Business management and strategy

    Enterprise-wide business models are

    seen to play an important part in

    effecting this transformation. Business

    models are used widely by organiza-

    tions and the business units within

    many of these organizations apply

    them collectively. The models may dif-

    fer in size and complexity but most

    appear to incorporate project/program

    management processes as key business

    management processes. Processes hav-

    ing a high interconnectivity between

    corporate, business and project levels

    are an important means of translating

    corporate goals, objectives and strategy

    into programs and projects; and of

    ensuring that continuity of strategy is

    achieved in a systematic and structured

    way. Hierarchies of objectives and

    strategies allow organizations to cas-cade strategy in a systematic way.

    Project and program strategy is

    not always managed as a formal

    process. Often it is developed and

    maintained by project or program

    leadership teams and governance

    through business case processes and

    not exclusively through project man-

    agement processes.

    Portfolio management and program

    managementSome form of portfolio management

    is implemented by many organizations

    but most survey respondents perceived

    it to be about managing projects

    around a common theme rather than

    maintaining a balanced portfolio or

    selecting the right project (contrary to

    the literature). In contrast, three of the

    case study companies implemented

    portfolio management mainly as a

    process for selecting and prioritizing

    the right projects.

    Programs are important vehicles

    for implementing corporate strategy

    and for implementing change. Most

    companies considered that program

    management emphasizes the manage-

    ment of business benefits (as well as

    the ideas of product, brand or platform

    management). There is broad agree-ment that program management

    includes the management of a portfo-

    lio or groups of projects using integrat-

    ed project teams, managing resources

    in an integrated manner, together with

    the management of benefits and of

    aggregated risk. Some organizations

    use a single fully integrated project

    management process for managing

    both programs and projects.

    Project management and project strategy

    Project strategy management is widely

    recognized as an important project

    management practice that systemati-

    cally relates project definition and

    development to corporate goals and

    strategies. Project management

    approaches are now being used by

    organizations at all stages of the proj-

    ect life cycle with project strategy

    development, review and optimization

    occurring at specific points. A combi-

    nation of program or project plans and

    other management plans are mostcommonly used to manage programs

    and projects, parts of which describe

    how the project is to be undertaken

    in other words, its strategy. These parts

    may not be summarized in a single

    project strategy document. Value

    Management is quite widely used in

    optimizing the strategy, often in com-

    bination with Risk Management.

    Project resources and capabilities

    are key factors in creating, deploying

    and maintaining program and projectstrategies. The project management

    roles, responsibilities and accountabil-

    ities required for this are generally well

    defined. And, as the survey showed, a

    high percentage of organizations

    define the personal project manage-

    ment competencies required to devel-

    op project strategy.

    Several organizations stressed the

    leadership qualities that they expected

    of their executives in shaping and

    delivering strategy, at both the project

    level as well as the corporate level.

    It can be concluded, therefore,

    that although project strategy manage-

    ment is an underexplored and insuffi-

    ciently described subject in the

    business and project literature, it is, in

    fact, a relatively well-trodden area,

    deserving of more recognition, formalstudy, and discussion.

    References

    Archer, N. P., & Ghasemzadeh, F.

    (1999). An integrated framework for

    project portfolio selection. International

    Journal of Project Management, 17,

    207216.

    Archer, N. P., & Ghasemzadeh, F.

    (2004). Project portfolio selection and

    management. In P. W. G. Morris & J. K.

    Pinto (Eds.), The Wiley guide to manag-

    ing projects. New York: John Wiley &

    Sons Inc.

    Archibald, R. (2003). Managing

    high-technology programs and projects (3rd

    ed.). New York: John Wiley & Sons Inc.

    Artto, K. A., Martinsuo, M., & Aalto,

    T. (2001). Project portfolio management,

    PMA Finland.

    Artto, K. A., & Dietrich, P. H.

    (2004). Strategic business management

    through multiple projects. In P. W. G.

    Morris & J. K. Pinto (Eds.), The Wiley

    guide to managing projects. New York:John Wiley & Sons Inc.

    Association for Project

    Management (2004). Directing change:

    A guide to governance of project manage-

    ment. High Wycombe, UK: Association

    for Project Management.

    Bartlett, J. (1998). Managing pro-

    grammes of business change. Wokingham,

    UK: Project Manager Today

    Publications.

    Boyatzis, R. E. (1982). The compe-

    tent manager: A model for effective per-formance. New York: John Wiley & Sons

    Inc.

    Bourgeois, L. J., & Brodwin, D.

    (1984). Strategic implementation: Five

    approaches to an elusive phenome-

    non. Strategic Management Journal, 5,

    241-264.

    Broner, J. M., Ruekert, R. W., &

    Walker, O. C. (2002). Upper manage-

    ment control of new product develop-

    ment projects and project

    performance. The Journal of Product

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    13/15

    Innovation Management, 19, 233-245.

    Cleland, D. I. (1990). Strategic

    design and implementation. Blue Ridge

    Summit, PA: TAB Books Inc.

    Cooke-Davies, T. J. (2002). The

    Real Success Factors on Projects.

    International Journal of Project

    Management, 20(3), 185-90.Cooke-Davies, T. J. (2004). Project

    success. In P. W. G. Morris & J. K. Pinto

    (Eds.), The Wiley guide to managing proj-

    ects. New York: John Wiley & Sons Inc.

    Cooper, R. G., Edgett, S. J., &

    Kleinschmidt, E. J. (1998). Portfolio

    management for new products. Reading,

    MA: Perseus Books.

    Cooper, R. G., Edgett, S. J., &

    Kleinschmidt, E. J. (1999). New prod-

    uct portfolio management: Practices

    and performance. Journal of Product

    Innovation Management, 16, 333-351.

    Cooper, R. G., Edgett, S. J., &

    Kleinschmidt, E. J. (2001). Portfolio

    management for new products.

    Cambridge, MA: Perseus Publishing.

    Crawford, L. (2000). Profiling the

    competent project manager. In D. P.

    Slevin, D. I. Cleland, & J. K. Pinto

    (Eds.), The frontiers of project manage-

    ment research PMI, 2002: PMI research

    conference, Paris, June 2000.

    Crawford, L. (2005). Senior man-

    agement perceptions of project manage-ment competence. International Journal

    of Project Management, 23(1) 7-16.

    Davis, A. M., Hickey, A. M., &

    Zweig, A. S. (2004). Requirements

    management in a project management

    context. In P. W. G. Morris & J. K. Pinto

    (Eds.), The Wiley guide to managing proj-

    ects. New York: John Wiley & Sons Inc.

    Dixon, M. (2000). Project manage-

    ment body of knowledge (4th ed.). High

    Wycombe, UK: Association of Project

    Management.Dye, L. D., & Pennypacker J. S.

    (1999). An introduction to project

    portfolio management. In L. D. Dye &

    J. S. Pennypacker (Eds.), Project portfolio

    management: Selecting and prioritizing

    projects for competitive advantage. West

    Chester, PA: Center for Business

    Practices.

    Englund, R. L., & Graham, R. J.

    (1999). From experience: Linking proj-

    ects to strategy. Journal of Product

    Innovation Management, 16, 52-64.

    Foulkes, J., & Morris, P. W. G.

    (2004). Pharmaceutical drug develop-

    ment project management. In P. W. G.

    Morris & J. K. Pinto (Eds.), The Wiley

    guide to managing projects. New York:

    John Wiley & Sons Inc.

    Grg, M., & Smith, N. (1999).

    Project management for managers. Sylva,NC: Project Management Institute.

    Grabher, G. (2002). Cool projects,

    boring institutions: Temporary collab-

    oration in social context. Regional

    Studies, 36(3), 205-214.

    Grundy, T. (1998). Strategy imple-

    mentation and project management.

    International Journal of Project

    Management, 16(1), 43-50.

    Hill, C. W. L., & Jones, G. R.

    (2001). Strategic management: An inte-

    grated approach (5th ed.). Boston:

    Houghton Mifflin Co.

    Hornby, D., & Thomas, R. (1989).

    Towards a better standard of management.

    London: Pan Books

    Institution of Civil Engineers

    (2000).Management development in the

    construction industry Guidelines for the

    construction professional. London:

    Institution of Civil Engineers.

    Johnson, G., & Scholes, K. (1997).

    Exploring Corporate Strategy (4th ed.).

    Hemel Hempstead, UK: Prentice Hall

    Europe.Kerzner, H. (2000). Applied project

    management: Best practices on implemen-

    tation. New York: J. Wiley & Sons Inc.

    Kirkpatrick, D., McInally, S., &

    Pridie-Sale, D. (2004). Integrated

    logistic support and all that: A review

    of through-life project management.

    In P. W. G. Morris & J. K. Pinto (Eds.),

    The Wiley guide to managing projects.

    New York: John Wiley & Sons Inc.

    Knutson, J. (2001). Succeeding in

    project-driven organizations: People,processes and politics. New York: John

    Wiley & Sons Inc.

    Martinsuo, M., & Dietrich, P.

    (2002). Public sector requirements:

    Towards project portfolio manage-

    ment. Proceedings of PMI Research

    Conference 2002, July 2002, Seattle WA,

    Newtown Square, PA: Project

    Management Institute.

    McElroy, W. (1996). Implementing

    strategic change through projects.

    International Journal of Project

    Management, 14(6) 325-329.

    Mintzberg, H., Ahlstrand, B., &

    Lampel, J. (1998). Strategy safari.

    London: Pearson Education Ltd.

    Mintzberg, H., & Quinn, J. B.

    (1996). The strategy process: Concepts,

    contexts and cases (3rd ed.). Upper

    Saddle River, NJ: Prentice-Hall.Morris, P. W. G. (1994). The man-

    agement of projects. London: Thomas

    Telford.

    Morris, P. W. G. (2004). Moving

    corporate strategy to project strategy:

    Processes, practices and leadership. In

    D. P. Slevin, D. I. Cleland, & J. K. Pinto

    (Eds.), Innovations: Project management

    research 2004. Newtown Square, PA:

    Project Management Institute.

    Morris, P. W. G. (2005). Managing

    the front-end: How project managers

    shape business strategy and manage

    project definition. In Proceedings of

    the 2005 Project Management Institute

    EMEA Symposium, Edinburgh.

    Newtown Square, PA: Project

    Management Institute.

    Morris, P. W. G., & Hough, G. H.

    (1987). The anatomy of major projects.

    Chichester, UK: John Wiley & Sons.

    Morris, P. W. G., & Jamieson, H. A.

    (2004). Translating corporate strategy

    into project strategy: Achieving corpo-

    rate strategy through project manage-ment. Newtown Square, PA: Project

    Management Institute.

    Morris, P. W. G., Jamieson, H. A., &

    Shepherd, M. M. (2005). Updating the

    APM Body of Knowledge. Manuscript

    submitted for publication.

    Morris, P. W. G., & Pinto, J. K.

    (Eds.). (2004). Wiley guide to managing

    projects. New York: John Wiley & Sons

    Inc.

    Murray-Webster, R., & Thiry, M.

    (2000). Managing programmes of proj-ects. In R. Turner & S. Simister (Eds.),

    The Gower handbook of project manage-

    ment (3rd ed.). Aldershot, UK: Gower

    Publishing.

    Office of Government Commerce

    (2003).Managing successful programmes.

    Norwich, UK: The Stationery Office.

    Partington, D. (2000). Implementing

    strategy through programmes of projects.

    In R. Turner & S. Simister (Eds.), The Gower

    handbook of project management (3rd ed.).

    Aldershot, UK: Gower Publishing.

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    14/15

    Partington, D., Pellegrinelli, S., &

    Young, M. (2005). Attributes and levels

    of programme management compe-

    tence: An interpretive study.

    International Journal of Project

    Management. 23, 87-95.

    Pellegrinelli, S. (1997). Programme

    management: organizing project-basedchange. International Journal of Project

    Management. 15(3), 141-150.

    Pellegrinelli, S., Partington, D., &

    Young, M. (2003). Understanding and

    assessing programme management

    competence. In Proceedings of the PMI

    Europe Congress, The Hague.

    Platje, A., Seidel, H., & Wadman,

    S. (1994). Project and portfolio plan-

    ning cycle: Project based management

    for multi-project challenge.

    International Journal of ProjectManagement. 12(2), 100-106.

    Project Management Institute

    (2004). A Guide to the Project

    Management Body of Knowledge

    (PMBOK Guide)Third Edition.

    Newtown Square, PA: Author.

    Reiss, G. (1996). Programme manage-

    ment demystified. London: E & F N Spon.

    Shenhar, A. J., & Dvir, D. (2004).

    How projects differ, and what to do

    about it. In P. W. G. Morris & J. K. Pinto

    (Eds.), The Wiley guide to managing proj-

    ects. New York: John Wiley & Sons Inc.

    Simister, S. J. (2000). Proposal,initiation and feasibility. In R. J. Turner

    & S. J. Simister (Eds.), The Gower hand-

    book of project management (3rd ed.).

    Aldershot, UK: Gower Publishing.

    Stevens, R., Brook, P., Jackson, K., &

    Arnold, S. (1997). Systems engineering.

    Hemel Hempstead, UK: Prentice Hall.

    Thiry, M. (2002). Combining

    value and project management into an

    effective programme management

    model. International Journal of Project

    Management, 20(3), 221-228.Thiry, M. (2004). Program man-

    agement: A strategic decision manage-

    ment process. In P. W. G. Morris & J. K.

    Pinto (Eds.), The Wiley guide to manag-

    ing projects. New York: John Wiley &

    Sons Inc.

    Thomas, J., Delisle, C., Jugdev, K.,

    & Buckle, P. (2002). Selling project

    management to senior executives: The

    case for avoiding crisis sales. Project

    Management Journal, 33(4), 9-28.

    Thompson, J. L. (2001). Strategic

    management (4th ed.). London:

    Thomson Learning.

    Turner, R. J. (1999).The handbook of

    project-based management. Maidenhead,

    UK: McGraw-Hill.

    Turner, R. J., & Simister, S. J. (Eds.).

    (2000). The Gower handbook of project

    management (3rd ed.). Aldershot, UK:

    Gower Publishing.

    Ward, J., & Peppard, J. (1999).

    Strategic planning for information systems.

    London: John Wiley & Sons.

    Wheelwright, S. C., & Clark, K. B.

    (1992). Revolutionizing New Product

    Development. New York: The Free Press.

    Wijen, G., & Kor, R. (2000).

    Managing unique assignments.Aldershot,

    UK: Gower Publishing.

    DR. PETER MORRIS is Professor of Construction and Project Management at University College London (UCL) and Visiting

    Professor of Engineering Project Managementat the Universityof Manchester. He is also Executive Director of INDECO, an

    international projects-based management consultancy. He has written over 120 papers on project management as well

    as the books The Anatomy of Major Projects (Wiley, 1987) and The Management of Projects (ThomasTelford, 1997); he is

    the editor, with Jeffrey Pinto, of the Wiley Guide to Managing Projects (Wiley, 2004) and co-author with Ashley Jamieson

    ofTranslating Corporate Strategy into Project Strategy: Achieving Corporate Strategy Through Project Management (PMI,

    2004). In 2005, he received the PMI Research Achievement Award.

    ASHLEY JAMIESON worked for many years as a business manager, senior program manager, and project manager withglobal aerospace and defense companies. For the last few years, he has been working with Peter Morris on a variety of

    research projects. At Manchester, he carried out research into design management in major construction projects, and

    was a visiting lecturer in project management. At UCL, he recently completed the PMI-funded research project on how

    corporate strategy is translated into projectstrategy, which forms the basis of thispaper. He was recently Research Fellow

    on a project updating theAPM BOK. He holds an MSc in Engineering Business Management. In addition to this PMI

    publication, he is a contributor to the Wiley Guide to Managing Projects (Wiley, 2004).

  • 8/10/2019 MOVING FROM CORPORATE STRATEGY TO PROJECT STRATEGY

    15/15