8/12/2019 MS Project Tutorial 11-14-12
1/27
Instructions & Legend
1. Click topics in blue box to view tutorials
2. Click down arrow to advance to next slide3. Click to return to this page
4. Text in Purple box indicates a Process
5. Text in Aqua box indicates Information
6. Text in Orange box indicates Hint
MS Project Home Page
Change Novel Password (UDOT only)Access problems assistance
Project Creation Process
Project Update Process
MS Project Consultant Access
Access to UDOT Microsoft Project Scheduling
UDOT Microsoft Project SchedulingTutorial - Main Page
Set Up MS Project 2010 Server Account
-
8/12/2019 MS Project Tutorial 11-14-12
2/27
Step 1. Request an Active Directory ID
by completing and submitting the request
form via the link below.
UDOT Network Login Request Form
MS Project Consultant Access
Step 2.Only complete this step if you dont have
ePM access. Both an Active Directory ID and
an ePM log-in are required to access UDOT MS
Project Scheduling.ePM Access Request Form
Completion of these steps will give you access
into the UDOT MS Project Scheduling system.
For the UDOT Contact, you
can use a UDOT Project
Manager or Dave Adamson
Back
to
Main
https://docs.google.com/spreadsheet/viewform?formkey=dENPU0o3RExYSU8zXzkxU2FRbnlmRXc6MQhttps://www.google.com/url?q=http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:716,42021&sa=U&ei=ylh4UMWBC-iY2wWlgIHYDQ&ved=0CAcQFjAA&client=internal-uds-cse&usg=AFQjCNFxecPLZ5mABew6GPFYcZ6eKOFHIwhttps://www.google.com/url?q=http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:716,42021&sa=U&ei=ylh4UMWBC-iY2wWlgIHYDQ&ved=0CAcQFjAA&client=internal-uds-cse&usg=AFQjCNFxecPLZ5mABew6GPFYcZ6eKOFHIwhttps://www.google.com/url?q=http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:716,42021&sa=U&ei=ylh4UMWBC-iY2wWlgIHYDQ&ved=0CAcQFjAA&client=internal-uds-cse&usg=AFQjCNFxecPLZ5mABew6GPFYcZ6eKOFHIwhttps://www.google.com/url?q=http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:716,42021&sa=U&ei=ylh4UMWBC-iY2wWlgIHYDQ&ved=0CAcQFjAA&client=internal-uds-cse&usg=AFQjCNFxecPLZ5mABew6GPFYcZ6eKOFHIwhttps://docs.google.com/spreadsheet/viewform?formkey=dENPU0o3RExYSU8zXzkxU2FRbnlmRXc6MQ -
8/12/2019 MS Project Tutorial 11-14-12
3/27
Back
to
Main
MS Project Home Page
MS Project Access
Click on link to access MS Project Scheduling
http://sp.udot.utah.gov
Enter Novel login
User name: Utah\(your Novel user name)
Password: (your Novel password)
http://sp.udot.utah.gov/http://sp.udot.utah.gov/http://sp.udot.utah.gov/http://sp.udot.utah.gov/ -
8/12/2019 MS Project Tutorial 11-14-12
4/27
2. Enter your current NOVEL
username and password and
then click on
Re-set Novel Password
Back
to
Main
1. Please click on the link below
https://login2.utah.gov
3. Click on My Accounts
4. Click on Change Password
5. Enter Current Password and
New Password and click on
https://login2.utah.gov/https://login2.utah.gov/ -
8/12/2019 MS Project Tutorial 11-14-12
5/27
Project Web Application
Project schedule can be viewed and modified via any internet connection.
This is a scaled down version of MS Project Professional.
Project Status Report
Displays schedule % complete
and Task % complete
Projects
Location where the PM can link and unlink
projects. When a project is linked, basic project
data is synced to an MS Project Template
Activity End Date Change Approval
Location where Project Managers "approve" or
"modify" requests to change project activity end dates.
Initial Activity Setup
Location where Functional Managers can input
the initial effort (hrs) and duration (days) during
setup of the project schedule. Can also create
subtasks of assigned parent task
Activity Updates
Location where functional managers update and
status project activities.
Program Manager
Region Program Manager access to the Region projects
Team Maintenance
Location where Resource Teams are defined and
staffed. Also used for resource hierarchy for
management access and reports.Back
toMain
Click on Link
names to
view pages
Name of individual logged
into MS Project Scheduling
-
8/12/2019 MS Project Tutorial 11-14-12
6/27
Back
to
Main
Click on Link to MS Project
to create project in
enterprise system
Click on Un-Link todelete the project in
MS Project
After project link, click on
Project Name to open
schedule in Project Web
Application (PWA)
Click UDOT icon to return to HOME page in UDOT
Project scheduling tool and also in this tutorial
-
8/12/2019 MS Project Tutorial 11-14-12
7/27
1. Project Manager can Approve or
Modify proposed Activity End Date
Difference
The Current EndDate subtracted
from the Proposed
End Date
Back
to
Main
Current Activity Float
Zero float means that the
Activity is on Critical Path.
If float is greater than
Difference then Approval of
new end date will not
change Project End Date
Current
End Date
Proposed
End Date
Click UDOT icon to return to HOME page in UDOT
Project scheduling tool and also in this tutorial
-
8/12/2019 MS Project Tutorial 11-14-12
8/27
2. Select Project
5. Re-assign Activity Lead if different
from original assignment. Just click
on cell, press the delete key andthen type new name auto pick list
will appear as you type name.
Also can assign others to task.
3. Create
Subtasks to
Activity if
desired4. Enter anticipated Hours & Days
for assigned Activities and
Subtasks
Back
to
Main
Click UDOT icon to return to HOME page in UDOT
Project scheduling tool and also in this tutorial
1. Select Team or Person .
(should auto default to your name)
Parent Activity totals
roll up from Subtasks
Subtasks are
indented
Toggle to show all project tasks or
just tasks for selected name
Auto defaults to your name.
Can also select those
subordinate to you as per the
Team Maintenance logic
Task Lead is the first name listed.
Task Lead is responsible for
Activity Duration (Days) and their
Hours. Others assigned to task are
responsible only for their Hours.
Click on Add Resource to add
additional Resources to Activity
-
8/12/2019 MS Project Tutorial 11-14-12
9/27
-
8/12/2019 MS Project Tutorial 11-14-12
10/27
Back
to
Main
Click PMs name toview projects
Information on this screen
is only available to Region
Program Managers
Displays number of Projects in
Scoping or Active ePM status and
also shows number of those projects
linked in MS Project Scheduling.
Click UDOT icon to return to HOME page in UDOT
Project scheduling tool and also in this tutorial
-
8/12/2019 MS Project Tutorial 11-14-12
11/27
Back
to
Main
Team Maintenance Under construction
Click To go to Home Page
-
8/12/2019 MS Project Tutorial 11-14-12
12/27
Back
to
Main
Project Schedule Maintenance Under construction
Click To go to Home Page
-
8/12/2019 MS Project Tutorial 11-14-12
13/27
Back
to
Main
Project Creation Process
1. PM Links Project
2. PM Opens Project
a) Project Web Access
b) Project Professional 2010
3. PM Modifies Project Activities & Logic
4. PM Assigns Resources to Activities
a) Add New Resource to Team
5. FM Inputs Initial effort(hrs) &
Durations(days)
6. PM Reviews Initial Schedule and
Negotiates Effort and Durations.
7. PM Publishes and Baselines Schedule.
Click PMs name to
view projects
-
8/12/2019 MS Project Tutorial 11-14-12
14/27
Back
toMain
Project Creation Process
1 of 2
For selected project, click on
Link to MS Project
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Application
b) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
15/27
Back
toMain
Project Creation Process
2 of 2
1. Select Template
2. Select Start Date
3. Click Link
Window Pops up during Project Linking(Linking usually takes about 30 seconds)
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Application
b) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
16/27
Back
toMain
Project Creation Process
1 of 3
Project is now Linked
Screen regeneration is required to see that
project is linked.
Do one of the following:
- hit the F5 button- hit the regeneration button
- click in the address bar and hit ENTER
Click on Project Name to open in
Project Web Application (PWA)
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Application
b) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
17/27
Back
toMain
Project Creation Process
2 of 3
Project Activities
Project Web Application is a simplified version
of MS Project. It is web based and can be
accessed from any internet connection. It can
only be accessed using MS Internet Explorer.
Click on Edit to
check-out project
Project Gantt Chart
Prior to project check-out, only
the most recent Published
version of schedule is visible
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Application
b) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
18/27
Back
toMain
Project Creation Process
3 of 3
Project Activities can now
be modified
After project check-out
menu buttons are active
After project check-out,
schedule modifications made
since the last Publish are visible
If project is checked out in PWA, then it
must be checked-in before opening it inMS Project Professional 2010 (MSPP10). It
is good practice to check in project after
modification. If project is not checked in,
then Functional Managers can not input
initial hrs & days.
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
19/27
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
Project Creation Process
1. Open
Microsoft
Project 2010
2. Select UDOT MS Project
Server & click on OK
3. Enter novel User
name and
Password.
Remember to type
utah\ before
User name
4. Select File
and click on
Open
5. Select
Retrieve the
list of all
projects from
Project Server
& click on Open
6. Select
the desired
project &
click onOpen
Project is now
open in MS Project
Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
20/27
Project Creation Process
Under Construction
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
21/27
Project Creation Process
Under Construction
1. PM Links Project
2. PM Opens Project
a) Project Web Applicationb) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
22/27
-
8/12/2019 MS Project Tutorial 11-14-12
23/27
2. Select Project
5. Re-assign Activity Lead if different
from original assignment. Just click
on cell, press the delete key and
then type new name auto pick list
will appear as you type name.
Activity Lead Enters Days and Hours.
3. Create
Subtasks
to Activity
if desired
4. Enter anticipated Work (hrs)
& Duration (days) for assigned
Activities and Subtasks
Back
toMain
1. Select Team or Person .
(should auto default to your name)
Project Creation Process
1. PM Links Project
2. PM Opens Project
a) Project Web Application
b) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
6. Enter only Initial Activity Hours if
not Activity Lead
-
8/12/2019 MS Project Tutorial 11-14-12
24/27
2. Select Project
4. Re-assign Activity Lead if different
from original assignment. Just click
on cell, press the delete key and then
type new name auto pick list will
appear as you type name
5. Create
Subtasks to
Activity if
desired
3. Enter anticipated Work (hrs) &
Duration (days) for assigned
Activities and Subtasks
Back
toMain
1. Select Team or Person .
(should auto default to your name)
Project Creation Process
1. PM Links Project
2. PM Opens Project
a) Project Web Application
b) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
25/27
Back
toMain
Project Creation Process
2 of 2
1. PM reviews the initial Activity durations and
the overall schedule.2. PM decides if schedule end date is
acceptable.
3. If schedule end date is too late, then PM
negotiates with Functional Managers to shorten
Activity durations.
4. PM enters updated Activity duration in PWA
or MS Project Professional.
1. PM Links Project
2. PM Opens Project
a) Project Web Application
b) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
-
8/12/2019 MS Project Tutorial 11-14-12
26/27
Back
toMain
Project Creation Process
2 of 2
A schedule baseline can only
be created in MS ProjectProfessional
1. PM Links Project
2. PM Opens Project
a) Project Web Application
b) Project Professional 2010
3. PM Modifies Project
Activities & Logic
4. PM Assigns Resources to
Activities
a) Add New Resource to
Team
5. PM Closes Project
a) Project Web Applicationb) Project Professional 2010
6. FM Inputs Initial
effort(hrs) &
Durations(days)
7. PM Reviews Initial
Schedule and Negotiates
Effort and Durations.
8. PM Publishes andBaselines Schedule.
a) Project Web Application
b) Project Professional 2010
Click to Publish project.
When project is published, the submit for
advertisement date in ePM screen 510 will
be linked to the MS Project end date so that
the only way to modify this date is update
the project schedule.
-
8/12/2019 MS Project Tutorial 11-14-12
27/27
Set Up MS Project 2010 Server Account Under Construction
1. Open MS Project Professional
2. Click on File and then Infoand then Manage Accounts
3. Click on Add
4. Enter Account Name and Project Server URL as shown.
5. Click on OK
Back