msc thesis
TRANSCRIPT
i
TITLE PAGE
BUSINESS PROCESS SIMULATION OF A
PRODUCTION LINE
By
Tony Ponsonby
A report submitted to the
Faculty of Science and Engineering
In partial fulfilment of the requirement for the degree of
Master of Science in Manufacturing with Management
Department of Engineering and Technology
August 2013
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
ii
DECLARATION OF ACADEMIC CONFORMITY
I certify that the material contained in this report is my own work and does not
contain significant portions of unreferenced or unacknowledged material. I also
warrant that the above statement applies to the implementation of the project and all
associated documentation.
In the case of electronically submitted work, I also consent to this work being stored
electronically and copied for assessment purposes, including the department’s use
of plagiarism detection systems in order to check the integrity of assessed work.
Name: Tony Ponsonby Signed:
Student ID: 02968984 Dated: 23/08/13
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
iii
PROCESS SIMULATION OF A PRODUCTION LINE
ABSTRACT
Thesis directed by Dr Muhammad Latif
This project by Tony Ponsonby, an MSc student in the Department of
Engineering and Technology, focuses upon a production line used to assemble a
range of wire rope hoists. The combination of make-to-order, manual assembly and
variations in size, design and assembly time, means each hoist to enter the
production line presents invariably different manufacturing implications. For this
reason, discrete event simulation is used to analyse the systems complex,
stochastic behaviour. The aim of this piece of work is to determine how the
production capacity can be maximised within the same production line space
constraints. The use of Witnesses Experimenter has provided a number of
optimised solutions within a range of parameters to minimise unnecessary delays
and optimise equipment levels. The solutions allow constraints to be reduced in
stages of financial investment and waste reduction which could be undertaken as
sales increase. The findings show, at 10% year-on-year growth the life of the
existing production line could be extended until May 2022, based on a combination
of financial investment and waste reduction. Given that output could increase from
1590 to 3890 hoists/year, it is dependent upon throughput efficiency increasing from
5.1% to 12.2%. In the event external constraints prevent the efficiency levels to be
surpassed, longevity of the production line could extend until November 2016, to
produce 2293 hoists/year. This analysis in addition to answering the aims and
objectives; provides an unbiased mechanism to assess scenarios before committing
resources, therefore, reducing risk and the potential to make poor decisions.
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
iv
ACKNOWLEDGEMENTS
Firstly I would like to thank my partner Erica for the continued support received
throughout this Masters degree.
I would also like to thank Dr Muhammad Latif for supervising this project and
providing advice where needed.
Also, I would like to thank Martin Street for sponsorship of this degree and Tony
Waller from the Lanner Group for providing a loan copy of Witness 12/13
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
v
LIST OF CONTENTS
Title Page.....................................................................................................................i
Declaration of Academic Conformity ......................................................................... ii
Abstract......................................................................................................................iii
Acknowledgements .................................................................................................. iv
List of Contents ......................................................................................................... v
List Of figures............................................................................................................viii
List of Tables..............................................................................................................xi
List of Equations ...................................................................................................... xi
Glossary....................................................................................................................xii
Chapter 1 Introduction ....................................................................................... 1
1.1. Project Purpose..........................................................................2
1.2. Scope of Project.........................................................................2
1.3. Aims............................................................................................3
1.4. Objectives...................................................................................3
1.5. Background................................................................................4
Chapter 2 Literature Survey.................................................................................5
2.1. Search Tools Used.....................................................................5
2.2. Search Keywords.......................................................................5
2.3. Literature....................................................................................5
Chapter 3 Approaches and Methods Considered................................................11
3.1. Approach to Maximise Output..................................................11
3.2. Enterprise Resource Planning Systems...................................12
3.3. Spreadsheet Based Systems...................................................12
3.4. Continuous Simulation..............................................................13
3.5. Discrete Event Simulation........................................................13
3.6. Lean Tools................................................................................14
Chapter 4 Methodology......................................................................................16
4.1. Tools Used...............................................................................16
4.2. Data Collection.........................................................................16
4.3. Distributions..............................................................................17
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
vi
4.4. Model Structure........................................................................17
4.5. Hoists.......................................................................................19
4.6. Labour and Shift Pattern..........................................................21
4.7. Generator.................................................................................21
4.8. Build-Frames............................................................................22
4.9. Throughput Efficiency...............................................................24
4.10. Entity Feeding..........................................................................26
4.11. Variable Buffer Sizes................................................................26
4.12. Usable Cell Area.......................................................................27
4.13. Warm-Up Period.......................................................................28
4.14. Assumptions.............................................................................30
Chapter 5 Verification and Validation ................................................................ 31
5.1. Verification................................................................................31
5.2. Validation..................................................................................32
Chapter 6 Experimentation and Optimisation.................................................... 35
6.1. Experiment 1 - Determine the Maximum
Output for the Existing Factory.................................................35
6.2. Experiment 2 - Optimise the Production
Line without Capital Investment................................................37
6.2.1. Part A: Optimise The Production Line
Configuration.....................................................................37
6.2.2. Part B - Quantify the Optimised Configuration..................40
6.3. Experiment 3 - Optimise the Production
Line with Capital Investment....................................................41
6.4. Experiment 4 - Check Optimum Configuration.........................46
6.5. Experiment 5 - Influence of Generator
Requirement on Output............................................................48
6.6. Experiment 6 - Effect of TE on
Lead-time, WIP & Arrival Rate.................................................50
Chapter 7 Discussion.........................................................................................53
Chapter 8 Future work.......................................................................................57
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
vii
8.1. Short-Term Capacity Planning.................................................57
8.2. Inventory Scenarios..................................................................57
8.3. Reduce Non-Value Activities....................................................58
Chapter 9 Conclusions ..................................................................................... 60
References................................................................................................................62
Bibliography..............................................................................................................66
Appendix 1- Sample data used to establish cycle times .......................................... 67
Appendix 2 - Street Crane Cycle Time Distribution ................................................. 68
Appendix 3 - Cycle-time Distributions ..................................................................... 69
Appendix 4 - Confidence Levels of Validation 2 ...................................................... 82
Appendix 5 - Zero Time Labour Bookings 2012 ...................................................... 83
Appendix 6 - Experiment 2 Top 40 Scenarios ......................................................... 84
Appendix 7 - Experiment 3 Results ......................................................................... 85
Appendix 8 - Iuniform Distributions Governing Hoist Attributes ............................... 86
Appendix 9 - Hoist Size Look-Up Table .................................................................. 87
Appendix 10 - Experiment 4 Results ....................................................................... 88
Appendix 11 - Health and Safety Assessment ........................................................ 89
Appendix 12 - Ethics Check Form ........................................................................... 90
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
viii
LIST OF FIGURES
Figure 1 - Sample Of Hoist Data Used Within A Spreadsheet .................................16
Figure 2 - Code To Input Theoretical Distributions ..................................................17
Figure 3 - Flowchart Of Hoist Routing Through Production .....................................18
Figure 4 - Simulated Production Line ......................................................................19
Figure 5 - Flowchart To Assign Hoist Attributes ......................................................20
Figure 6 - Code Defining The Type Hoist Variant Entering The Model ....................20
Figure 7 - Witness Coding To Determine The Hoist Size ........................................21
Figure 8 - Code To Push A Build-Frame Entity Into The Model At Zero Time .........23
Figure 9 - Code To Allow Hoists To Link To The Correct Build-Frame Queue ........23
Figure 10 - Output Condition For Buffers Feeding Cells1, 8 And 11 ........................24
Figure 11 - Sample Witness Code To Control TE ...................................................25
Figure 12 - Logic Governing Hoist Entry Into A Buffer .............................................26
Figure 13 - Layout Of The Production Line & Assembly Cell Sizes .........................27
Figure 14 - Coding To Determine The Usable Cell Area .........................................28
Figure 15 - Warm-Up Period Without Starting Conditions .......................................28
Figure 16 - Code To Inject Hoists Into The Model At Initialisation ...........................29
Figure 17 - Warm-Up Period With Starting Conditions ............................................30
Figure 18 - Model Showing Element Flow Lines To Verify Routings .......................31
Figure 19 - Coding To Prevent The Processing Of Unwanted Attributes .................32
Figure 20 - Confidence Levels For The Existing Production Line Capacity .............36
Figure 21 - Potential Life Of The Existing System ...................................................36
Figure 22 - Confidence Levels For The Existing Production Line (No Delay) ..........37
Figure 23 - Production Line Balance Comparison ...................................................39
Figure 24 - Experiment 2 Confidence In Capacity (No Forced Delay) .....................40
Figure 25 - Experiment 2 Confidence In Capacity (With Forced Delay) ...................40
Figure 26 - Potential Life Of 1st Optimised System ..................................................41
Figure 27 - Experiment 3 Throughput Efficiency .....................................................42
Figure 28 - Experiment 3 Average WIP ...................................................................43
Figure 29 - Experiment 3 Hoists / Year ...................................................................44
Figure 30 - Potential Life Of Experiment 3 ..............................................................45
Figure 31 - Experiment 4 Parameter Analysis .........................................................46
Figure 32 - Potential Life Of Experiment 4 ..............................................................48
Figure 33 - Potential For Generator Requirement To Grow With Sales ...................49
Figure 34 – Output Vs Generator Requirement .......................................................50
Figure 35 - Effect of Throughput Efficiency on Little’s Law ......................................51
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
ix
Figure 36 - Experiment Comparison (Dispatch QTY Vs Space Utilisation) ..............53
Figure 37 - Experiment Comparison (Lead-Time Vs WIP) ......................................54
Figure 38 - Observed Delays ..................................................................................56
Figure 39 - Summary Sheet Of Distribution Data Sampling ....................................68
Figure 40 - PDF for all variants of ZX10 on End of Line Test ..................................69
Figure 41 - PDF for DT variants of ZX10 on Wire and Test .....................................69
Figure 42 - PDF for SS & ST variants of ZX10 on Wire and Test ............................69
Figure 43 - PDF for DT variants of ZX10 on Assembly ...........................................70
Figure 44 - PDF for SS & ST variants of ZX10 on Assembly ...................................70
Figure 45 - PDF for CRB & FM variants of ZX8 on Barrel Assembly .......................70
Figure 46 - PDF for LHR variants of ZX8 on Barrel Assembly .................................71
Figure 47 - PDF for CRB & FM 2/4 Fall variants of ZX8 on Frame Assembly ..........71
Figure 48 - PDF for 6/8 Fall variants of ZX8 on Frame Assembly ...........................71
Figure 49 - PDF for LHR variants of ZX8 on Trolley Assembly................................72
Figure 50 - PDF for LHR variants of ZX8 on Trolley Assembly 2/3 ..........................72
Figure 51 - PDF for CRB 2/4 Fall variants of ZX8 on Cable Routing .......................72
Figure 52 - PDF for CRB 6/8 Fall variants of ZX8 on Cable Routing .......................73
Figure 53 - PDF for FM variants of ZX8 on Cable Routing ......................................73
Figure 54 - PDF for LHR 2/4 Fall variants of ZX8 on Cable Routing........................73
Figure 55 - PDF for LHR 6/8 Fall variants of ZX8 on Cable Routing........................74
Figure 56 - PDF for all variants of ZX8 on Line Pull Test .........................................74
Figure 57 - PDF for all 2 fall variants of ZX8 on Rope-up ........................................74
Figure 58 - PDF for all 4 fall variants of ZX8 on Rope-up ........................................75
Figure 59 - PDF for all 6 fall variants of ZX8 on Rope-up ........................................75
Figure 60 - PDF for all 8 fall variants of ZX8 on Rope-up ........................................75
Figure 61 - PDF for all variants of ZX8 on End-of-Line Test ....................................76
Figure 62 - PDF for all variants of ZX8 on Packing .................................................76
Figure 63 - PDF for CRB 2/4 fall variants of ZX8 on Crab Assembly .......................76
Figure 64 - PDF for LHR 6/8 fall variants of ZX8 on Crab Assembly .......................77
Figure 65 - PDF for All variants of ZX6 on Barrel Assembly ....................................77
Figure 66 - PDF for All variants of ZX6 on Frame Assembly ...................................77
Figure 67 - PDF for LHR variants of ZX6 on Trolley Assembly 1 .............................78
Figure 68 - PDF for LHR variants of ZX6 on Trolley Assembly2/3 ...........................78
Figure 69 - PDF for LHR variants of ZX6 on Cable Routing ....................................78
Figure 70 - PDF for CRB variants of ZX6 on Cable Routing ....................................79
Figure 71 - PDF for FM variants of ZX6 on Cable Routing ......................................79
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
x
Figure 72 - PDF for all variants of ZX6 on Line Pull Test .........................................79
Figure 73 - PDF for all variants of ZX6 on Rope-up ................................................80
Figure 74 - PDF for all variants of ZX6 on End-of-Line Test ....................................80
Figure 75 - PDF for all CRB variants of ZX6 on Crab Assembly ..............................80
Figure 76 - PDF for all variants of ZX6 on packing ..................................................81
Figure 77 - 2012 Zero time labour bookings ............................................................83
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
xi
LIST OF TABLES
Table 1 - Product Throughput Efficiency .................................................................11
Table 2 - Labour Resources Used Within The Simulation .......................................21
Table 3 - Generator Requirement ...........................................................................22
Table 4 - Existing Build-Frame Types And Quantities .............................................22
Table 5 - 2010 to 2012 Output & TE .......................................................................24
Table 6 - Workstation Sizes / Cell ...........................................................................27
Table 7 - Average cycle times .................................................................................33
Table 8 - Actual 2012 Production Data To Validate Against ....................................33
Table 9 - Comparison Of Actual To Simulated Products Built .................................34
Table 10 - Comparison Showing The Actual To Simulated Throughput Efficiency ..34
Table 11 - Comparison Of Actual To Simulated Labour Hours ................................34
Table 12 - Existing Workstation Quantities / Production Cell ...................................35
Table 13 - Experiment 2 Maximum / Minimum Workstation Parameters .................37
Table 14 - Experiment 2 Optimum Scenario ...........................................................38
Table 15 - Experiment 3 Maximum / Minimum Workstation Parameters .................42
Table 16 - Experiment 4 Parameters To Check ......................................................46
Table 17 - Experiment 4 Optimum Scenario ...........................................................47
Table 18 - Iuniform Data to Assign Hoist Model Attribute ........................................86
Table 19 - Iuniform Data to Assign ZX6 Attributes ..................................................86
Table 20 - Iuniform Data to Assign ZX8 Attributes ..................................................86
Table 21 - Iuniform Data to Assign ZX10 Attributes ................................................86
LIST OF EQUATIONS
Equation 1 - Throughput Efficiency .......................................................................... 6
Equation 2 - Total non-value added time ................................................................. 6
Equation 3 - Little’s Law ..........................................................................................11
Equation 4 - Forced Delay Time .............................................................................25
Equation 5 - Customer Demand ..............................................................................39
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
xii
GLOSSARY
Autocad Computer aided design software used for engineering design
BPS Business Process Simulation
Cell 1 An inline production cell undertaking barrel assembly on ZX6 & 8 LHR
hoists
Cell 3 An inline production cell undertaking frame assembly on ZX6 & 8 LHR
hoists
Cell 4 An inline production cell undertaking trolley assembly on ZX6 & 8 LHR
hoists
Cell 6 An inline production cell undertaking cable routing on ZX6 & 8 hoists
Cell 7 An inline production cell undertaking line pull test (load test) and rope-
up on ZX6 & 8 hoists
Cell 8 An offline production cell assembling all 2/4 fall, ZX6 & 8 CRB & FM
hoists
Cell 9 An inline production line undertaking End-of-Line test (Inspection) on
all hoists
Cell 10 An inline production line undertaking packing and dispatch on all hoists
Cell 11 An offline production cell assembling all 6/8 fall, ZX8 and ZX10 hoists
CRB A Crab hoist available in all hoist models.
DT A variety of ZX10 hoist that has a double gearbox and true vertical lift
ERP Enterprise Resource Planning
Falls The number of strands of wire rope that connect the hoist to the hook
FIFO First In First Out
FM A Foot Mount hoist available in all hoist models.
LHR A Low Headroom hoist available in the ZX6 and ZX8 hoist models
Matflow Software used for the planning of materials flow
MRP Materials Resource Planning
PDF Probability Density Function
SolidEdge Computer aided design software used for engineering design
Tony Ponsonby Business Process Simulation of a Production Line
___________________________________________________________________
xiii
SS A variety of ZX10 hoist that has a single gearbox and a single rope
ST A variety of ZX10 hoist that has a single gearbox and true vertical lift
TE Throughput Efficiency
WIP Work In Progress
Witness Discrete event simulation software developed by the Lanner Group
ZX6 The smallest hoist variant in the range of pre-engineered electric wire
rope hoist with a capacity that ranges from 0.5 to 6.3 tonnes
ZX8 The middle hoist variant in the range of pre-engineered electric wire
rope hoist with a capacity that ranges from 2 to 25 tonnes
ZX10 The largest hoist variant in the range of pre-engineered electric wire
rope hoist with a capacity that ranges from 5 to 50 tonnes
Tony Ponsonby Process Simulation of a Production Line
Chapter 1 Introduction
1
CHAPTER 1 INTRODUCTION
StreetCrane Company Ltd is a rapidly growing business specialising in the
manufacture and supply of electrified overhead travelling cranes and wire rope
hoists. With around 60% of the business income generated from the sale of hoist
units, the company aims to develop this market further using a strategic reduction of
selling prices to boost sales volume to an anticipated 10% year on year growth.
Whilst beneficial to the company, this growth potential has led to the speculation by
top management that only by relocating to larger premises will the existing
production levels be surpassed and higher throughput sustained. This notion has led
the board of directors to seek planning permission for a larger building
(highpeak.gov, 2012) to relocate the hoist production line.
The concept that more space allows more products to be produced over a
specified time-frame seems a reasonable assumption. Yet to date, the company has
no mechanism to quantify what the maximum capacity of the existing hoist
production line is, or how elements other than labour constrain the capacity.
Although the company does operate an Enterprise Resource Planning system for
master production scheduling and capacity planning (Sanderson.com, 2012); only
resource and time availability is seen to restrict capacity (Kim & Kim, 2001). This
notion stems from capacity, calculated as the percentage of hours required to
assemble products to the actual labour hours available within the same timeframe.
If 100% capacity is exceeded, only increased levels of overtime, additional labour or
extended lead-times will allow products to be completed within the designated
timeframe.
While the ERP system plays a crucial planning role, the system does not
consider parameters such as the available area, product size, Work-In-Progress
(Bolden et al. 1997) and variation in cycle-times which also influence capacity
(Byrne & Bakir, 1999). Simply by adding more resource availability, the ERP system
Tony Ponsonby Process Simulation of a Production Line
Chapter 1 Introduction
2
will increase output accordingly without limit. As such, it cannot determine what the
maximum capacity of the existing site is, or when factory expansion should begin;
specifically when influences other than time or resources constrain the output (Kim
& Kim, 2001).
A practical solution could reside with building like products in batches, thereby
minimising the impact of the other parameters and making maximum capacity
determinable under known operating conditions. Unfortunately, the company
operates a make-to-order system (Kumar, 2007) to customer specification. This can
result in each product to enter the production line varying considerably in design or
size to the last. This variation can cause buffer holding capacities and cycle-times to
fluctuate from one product to the next, resulting in imbalances in flow which leads to
bottlenecks and reduced throughput efficiency (Sweeney & Szwejczewski, 1996).
1.1. Project Purpose
Given the desire to increase production volumes, the purpose of this project is
to present a case to maximise the life of the existing production facilities by
identifying ways to become more efficient to increase the maximum capacity. In
doing so, to reduce the risk of uncertainty by simulating probable outcomes to
ensure the right changes are made, at the right time, using data in the absence of
personal bias.
1.2. Scope of Project
Whilst Street Crane Ltd manufacture a wide range of lifting products, the
scope of this project will reside in the assembly of higher volume pre-engineered
wire rope hoists only. Specifically, the analysis will focus upon ZX6, ZX8 and ZX10
hoist models, subdivided further by barrel length, lifting format, and the number of
rope falls from the barrel. To simplify the analysis, the possible product
Tony Ponsonby Process Simulation of a Production Line
Chapter 1 Introduction
3
configurations are limited to 78. These ensure the impact on the production line is
assessed on the basis of product size, type and cycle-time variations.
The simulation for this piece of work does not use any data to assess the
impact on production capacity from stock outs, the manufacture of sub-assembled
components or the need for more parts storage space when production volumes
increase. Other influences on capacity from rework or operator inefficiency, while
not formally identified or recorded, are assumed to be part of the empirical cycle
times. The use of distribution curves allow for instances where work duration has
deviated from the average, however it is not possible to quantify the effect these
instances have on the overall cycle-time in isolation.
1.3. Aims
The aim of this project is to determine how and by how much, Street Crane
Ltd’s hoist production can be increased within a set of operating conditions, in the
confines of existing production areas. The completion of this aim will extend the life
of the existing production facility and answer investment questions; at what time
should the business buy new equipment or relocate the production line to increase
production levels further?
1.4. Objectives
To construct a Witness simulation which accurately represents the ZX hoist
production line
To use the simulation to quantify the maximum production capacity of the
existing production line
Through experimentation, to quantify how much the capacity could be
increased;
o With changes which do not require high time/cost investment
o With changes which require high time/cost investments
Tony Ponsonby Process Simulation of a Production Line
Chapter 1 Introduction
4
To determine how product-mix can alter capacity constraints
All simulations will focus upon cycle-times, WIP, throughput, cell size, product size
and mix to recreate the existing production line.
1.5. Background
Globalisation and competitor pressure are increasingly influencing businesses
to engage in process improvement through changes in the way a business operates
to improve efficiency and competitor advantage, while reducing costs (Hlupic &
Robinson, 1998). Moreover, whilst the motives to change maybe beneficial, the act
of making the change is not guaranteed success (Hammer & Champy, 2009). In
aid, tools such as flowcharts or work flow diagrams are available to analyse and
base decisions upon; yet in reality these tools fall short where processes are
dynamic, stochastic and usually complex (Aguilar-Saven, 2004).
In view of this, Business Process Simulations are employed to improve the
success rate of business process change projects; in part, achieved by enabling
greater understanding of the complex systems with interdependencies (Greasley,
2003). Simulation enables the creation of a virtual model to mimic a real world
system (Gogg & Mott, 1993). Through experimentation, the cause and effect from
specific modifications can be assessed prior to committing actual resources to the
project (Greasley, 2003). With this in mind, BPS allows decision makers to base
judgement on predictions that specific events will occur as opposed to one’s own
personal bias (Hlupic & Robinson, 1998).
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 2 Literature Survey
5
CHAPTER 2 LITERATURE SURVEY
2.1. Search Tools Used
Http://scholar.google.co.uk/
Http://metalib5.hosted.exlibrisgroup.com
Http://www.google.co.uk/
2.2. Search Keywords
Witness simulation, discrete event simulation, make to order, continuous simulation,
lean metrics, throughput efficiency, simulation of a production line, work in progress,
business process simulation.
2.3. Literature
In a real world scenario, where changes to business processes justify the use
of simulation, undoubtedly will involve stakeholders from various areas of the
business. Whilst an appreciation of simulation is useful, many stakeholders will have
little or no knowledge of BPS (Gogg & Mott, 1993). With this in mind, simulation
packages with a graphical user interface are more able to engage with stakeholders,
by facilitating an easier understanding of model behaviour without the need for
technical simulation knowledge (Greasley, 2003). Stakeholder interaction is
essential to get the most from the simulation. This communication facilitates the
development and verification of the simulation while enhancing the credibility of
results (Gogg & Mott, 1993).
Given the objective to determine the existing production line’s capacity and
how it could be improved, it does not indicate how efficient the existing or improved
systems are. Using performance measurements to gauge the existing system, the
“as is” state can then be benchmarked against experimental improvements (Mathur,
et al., 2011). The performance metric “Throughput Efficiency” is particularly relevant
due to the impact large products and often lengthy assembly times impose onto
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 2 Literature Survey
6
build cell areas, which influence the amount of products that can be built at any point
in time.
This metric has several derivations including the ratio of actual output to
theoretical output in terms of production units (Muthiah & Huang, 2007) and the ratio
of value added time to the total manufacturing time shown in Equation 1 (Sweeney
& Szwejczewski, 1996). Although related, the later derivative is useful to find the
non-value added time that products will eventually spend in buffers shown in
Equation 2. This metric is particularly apt when considering by what method other
than the number of hoists shipped does the simulation reflect real world.
Equation 1 - Throughput Efficiency (Sweeney & Szwejczewski, 1996)
Equation 2 - Total non-value added time
otal non alue a e ti e otal t ou ut ti e otal alue a e ti e
Using TE will allow comparisons of the existing production output and
efficiency performance to an overall optimum, but also to the performance of an
optimum system which fails to improve efficiency. As such, improvements driven
from waste reduction are quantified yet require solutions, in addition to those found
using the simulation. The level of WIP and floor space required are other lean
metrics which relate to this project to quantify the existing and experimental states
(Andreeva, 2012).
In part, this project will focus on the effect product and buffer sizes have on
the output. The work by Markt & Mayer (1997) has a similar objective, however the
authors use a combination of tools and techniques to undertake tasks where this
project aims to undertake in Witness alone. More precisely Markt & Mayer (1997)
are using Autocad to generate a layout, Matflow to optimise the routing of parts and
to calculate floor space requirements, and Witness to develop a simulation. This
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 2 Literature Survey
7
project uses SolidEdge to create a layout and Witness alone for all simulation
activities. The date when Markt & Mayer undertook this work may explain the use of
other software.
Qu et al, (2001) have also undertaken a comparable project, using simulation
to ascertain how to best design a new production line. They focus upon the cost
implications of tooling and operator requirements and various shift patterns to
determine what pattern works best over a 5-year period with varying levels of
product demand. Their dynamic analysis of costings over this duration could be
applied to this project, however financial information has been unavailable.
Tjahjono & Fernández (2008) present a practical guide to simulation based on
an engine assembly line. Whilst all approaches are relevant, in particular the
analysis of bottlenecks and recommended modelling techniques, it is the validation
study on initial setup that is particularly intriguing. They have used the daily
production output to illustrate graphically the warm up period for the model to reach
steady state and maintain a consistent output per day. Likewise, Mahajan & Ingalls
(2004) focus their work exclusively on methods used to obtain the warmup period.
The authors present a variety of graphical, statistical and heuristic tools to calculate
the warm-up duration to ensure that initialisation bias does not form part of the
results. Witness itself does offer an alternative to reduce the initialisation bias by
importing data from an initialise status file (Lanner, 2012). This has the effect of
starting the simulation as though the model has already run; entities and resources
can be positioned while activities or queues can be set to predefined states that
would not be achieved until reaching a steady state. Regardless of the best method;
Tjahjono & Fernández, (2008) show that initial output must be scrutinised to
understand at what point the output becomes accurate to a specified level before
results can be measured.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 2 Literature Survey
8
The work by Mehta (2000) provides an exceptionally structured approach to
simulation; as such, the tasks within this project are based upon this work. The
succinct best practice methodology highlights both basic and advanced tools to
enhance the effectiveness of a simulation, in essence providing a reference to guide
this project. The recommended use of Excel to provide input data will be one of the
insights incorporated into this project, allowing the simulation to remain flexible
enabling changes without time consuming modifications to the simulation coding.
To provide credibility in the simulation, the results will need to be analysed to
determine if they are sensible and representative of the real world. The work by
Sargent (2009) provides many techniques that could be used to verify and validate
the simulation. In particular is the use of historical data and sales forecasts to
compare the simulation data against for validation. Cuatrecasas-Arbos et al (2011)
offers a checking process that is undertaken at various simulation stages that can
be applied to this project, including; data validation, conceptual model validation,
simulation model verification and operational validation.
Data validation, being the process of ensuring that the information inputted
into the simulation is correct; in large, falls outside the focus of this project. Data
used will be from the historical record, and whilst the integrity could be affected by
those providing and processing the information, for this study it must be assumed to
be correct. Conceptual model validation focuses on the validity of the underlying
principles that will be used to construct the simulation model. In the project, this will
be undertaken through discussions with the company, observation of the production
line and sampling historical data records. These findings will be compared to a
flowchart to verify the routing logic is correct. Simulation model verification entails
checking the computerised model structure against the conceptual model to ensure
the underlying principles and logic have been applied correctly. In practice, this will
be undertaken in various stages throughout model construction using a controlled
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 2 Literature Survey
9
simulation run to assess for more subtle anomalies rather than after the model is
built; making errors easier to find. Operational validation involves checking that the
simulation produces results that are consistent with real world performance. This
requires the simulation to be replicated a number of times to judge the simulation
output against actual historical output. Whilst it is not expected that the simulation
will exactly match real world, it should be reasonably accurate and repeatable to
provide a reliable source to base decisions.
Considering the random nature of the system there can be no one exact
answer, all experiments should be run over a number of replications so that result
confidence levels are determined (Lanner, 2012). The use of the Witness 13
Experimenter allows the random number stream per scenario replication to change.
Therefore, results are predictable within a upper and lower range.
The quick reference book by Lanner (2012) provides concise descriptions of
modelling actions, attributes, functions, rules, states and simulation features which is
invaluable to aid construction of the Witness simulation and also a point of reference
for technical modelling queries. Additionally, the Lanner.com, (2012) website
provides numerous articles showcasing how Witness has been applied within
industry. These are both inspirational and insightful; providing a background of what
is possible to maximise the project potential.
The papers by Gogg & Mott (1993), Greasley (2003) and Hlupic & Robinson
(1998), whilst dated, do provide a compelling overview of business process
simulation. Although these papers are not suitable to answer technical simulation
queries, they do offer a rationale for the use of simulation which is quite appealing.
In particular; why simulation is used and the importance of financial justification to
support the simulation findings, which has not changed from the time of publication.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 2 Literature Survey
10
The study by Host, et al (2001) into bottlenecks, outlines the influences a
changing market has on buffers levels. Even though the products between the
authors paper and to this thesis differ, in essence the problems faced are the same.
A drawback in this work is the assumption all resources are of the same
competency. In reality where there are variations in the product-mix (Al-Aomar,
2000), some resources will be more competent than others resulting in bottlenecks
where skills are in short supply.
To enable the simulation to accurately reflect process variation, some data
sampling is required to draw a statistical picture of how the process varies
(Greasley, 2003). Whilst mean values could be used in substitution for theoretical or
empirical distributions, the effects may not always be the same. Law (2007)
demonstrates the differences this can make on a simple queuing system. The use of
mean values to represent the flow into a queue ensures that a bottleneck does not
occur, yet conversely using a distribution causes a queue to backup.
Using theoretical distributions instead of empirical data has the advantage of
providing a complete view of the system, gaps in data are filled in, and irregularities
smoothed out (Gogg & Mott, 1993). To enable the use of theoretical distributions,
statistical analysis must be undertaken to obtain a distribution type that matches the
empirical data best (Greasley, 2003). Unfortunately, Witness does not provide this
feature; it is however available in other simulation packages such as the Input
Analyser module within Arena (Kelton et al. 2002). Instead of using a simulation with
this feature, various standalone statistical analysis tools are available (Law, 2007).
This project uses the Excel add-on module EasyFitXL by MathWave for data
analysis. Albeit not part of the simulation, it does present the advantage of working
inside excel which is used to store all data.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 3 Approaches and Methods Considered
11
CHAPTER 3 APPROACHES AND METHODS CONSIDERED
Undoubtedly, a project such as this could be undertaken using a range of
approaches, tools and techniques. This section is intended to review some of the
potential ways and present an argument for those chosen to undertake this project.
3.1. Approach to Maximise Output
Referring back to the argument that more floor space could allow more
products to be built, does hold true considering Little’s Law (Equation 3) (Little &
Graves, 2008).
Equation 3 - Little’s Law
Where
L = Average number of items in the queuing system
λ = Average number of items arriving per unit time
W = Average waiting time in the system per item
This idea also appears logical considering that throughput efficiency has remained
fairly consistent over the past 3 years (Table 1). As such, if the average waiting time
remains constant, only by increasing the number of items queuing (WIP) will enable
more products to enter the system. The overarching factor governing the amount of
WIP stored is the available production line space, leading to the conclusion that a
larger area is required.
Table 1 - Product Throughput Efficiency
Whilst investment into larger premises is an option it is not the only approach
available to increase output. If constraints governing the average waiting time are
reduced, WIP could remain fixed whilst output is increased. It is this approach which
Average of
Throughput
Efficiency 2010 2011 2012
ZX10 - 5.4 6.4
ZX6 5.1 4.5 5.1
ZX8 5.0 5.6 5.5
Total 5.1 5.0 5.3
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 3 Approaches and Methods Considered
12
is adopted for this project, by targeting constraints which cause unnecessary waiting
time thereby preventing other products from entering the production line. Success
using this approach will extend the life of the existing production site by producing
more hoists from the same overall area.
3.2. Enterprise Resource Planning Systems
ERP systems are used within businesses to undertake a wide variety of tasks
from sales to dispatch (Sanderson.com, 2012). Specifically relating to this project, is
the ability to determine capacity plans. The use of linear programming algorithms in
capacity planning and scheduling, allow an optimised model to be attained to reduce
production costs by manipulating capacity and inventory constraints (Kim & Kim,
2001). Although widely used commercially for capacity planning, limitations for this
option become apparent when the system exhibits queuing and is non deterministic
(Byrne & Bakir, 1999). Whilst ERP systems consider costs, processing times,
available labour or machine capacity, demand and stock (Kim & Kim, 2001), they
on’t take into account product size and variation in cycle-times which also influence
capacity. Both Byrne & Bakir (1999) and Kim & Kim (2001) exceed this fact and
have developed hybrid capacity planning tools using simulations to support the ERP
shortcomings. Unlike this project, the authors do not consider physical size as a
restriction.
3.3. Spreadsheet Based Systems
Cuatrecasas-Arbos et al (2011) developed an operations time chart within a
spreadsheet, to evaluate a production environment in much the same way as a
discrete event simulation package, such as Witness. Given that this method
employs a graphical interface, the presentation differs significantly to a simulation
package with results shown chronologically, similar to a Gantt chart. Conceding this
fact, it can simulate an MRP pull system and measure metrics relevant to this
project including efficiencies, WIP, process and queue times. Unfortunately, this
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 3 Approaches and Methods Considered
13
method is a static analysis tool and is unable to process a stochastic input typical of
a make to order environment or a complex production system.
3.4. Continuous Simulation
Continuous simulation, in contrast to discrete event simulation allows inputs to
change continuously with respect to time (Özgün & Barlas, 2009). This is ideally
suited to determine the velocity fluids at any point in time within continuous systems
such as a river or processing plant. Other differences include the method to change
state, occurring at a specified time as opposed to a discrete event and output rule,
operating with a First In First Out basis only (Extendsim.com, 2012).
The research by Özgün & Barlas (2009) compares both approaches by
simulating a crowd control using a simple queuing system. While both systems
could be applied to this problem, the authors note that input rates need to be
significantly high for the continuous simulation to obtain accurate results.
Additionally, where the continuous system is more able to illustrate system
dynamics, it is not so able to make statistical predictions. Considering hoist
production is relatively slow, has output rules which deviate from FIFO, and requires
statistical predictions for analysis, continuous simulation is rendered unsuitable.
3.5. Discrete Event Simulation
Discrete event simulation is a dynamic tool which allows inputs to change at
discrete points in time, ideally suited to simulate stochastic models. Unlike
continuous simulation, discrete event simulation is ideally suited to processes which
involve queuing (Özgün & Barlas, 2009). The simulation package Witness, provides
the ability to model dynamic processes typical of a production line (Lanner.com,
2012). Parameters which influence model performance such as resources,
stoppages, shift patterns or logical routing of entities which are difficult and time
consuming to calculate by other methods, can be readily inputted into the simulation
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 3 Approaches and Methods Considered
14
and results displayed on screen (Lanner.com, 2012). Additonally, the use of a
simulation package employing a graphical user interface, provides the suitable
platform to facilitate stakeholder interaction and understanding, while reducing the
risk of misinterpreting results (Greasley, 2003).
It is for these reasons a dynamic simulation will be used to model and analyse
the operation of a production line at StreetCrane. Granted that other discrete event
simulation packages are available, Witness has been used due to availability within
Manchester Metropolitan University for use on this project.
3.6. Lean Tools
Lean methodology could be adopted to improve process performance through
the use of tools designed to eliminate waste to maximise profitability and throughput
(Hicks, 2007). Unlike other systems, lean can be viewed as a way of thinking as
opposed to just a tool for continual improvement. By successfully embedding lean
into an organisation, a culture driven towards process improvement and waste
reduction can develop throughout the workforce (Angelis, et al., 2011). This
presents a possible advantage over alternative solutions; via the potential to
integrate far more people into the improvement process. Furthermore, lean is
documented in many papers and is able to be applied to any system and utilises a
range of techniques geared towards process improvement (Hicks, 2007). Unlike
simulation, lean is not able to analyse and compare stochastic or variable systems,
nor is it able to validate possible solutions prior to execution (Standridge & Marvel,
2006). Whilst not being the focus of this work, it is likely some other tools, lean or
otherwise will be required in addition to simulation, when;
Insufficient data is available which could be gained using value stream,
process flow or time value mapping (Melton, 2005)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 3 Approaches and Methods Considered
15
The simulation can quantify a constraint but cannot identify the root-cause
which could be gained using Pareto analysis or the 5 W y’s (Johnson, et al.,
2010)
Process improvement can be achieved using practical solution such as 5S
(Chapman, 2005)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
16
CHAPTER 4 METHODOLOGY
The methodology for this project assumes the reader has some knowledge of
Witness, including basic features and coding language.
4.1. Tools Used
ZXHoistProd Report (Specific to StreetCrane Ltd)
Microsoft Excel
EasyFitXL
Witness 12
Witness 13 including Experimenter Module
4.2. Data Collection
Data used for this project has been gathered ia t e co any’s o uction
operatives over a 3 year period; each specifying the time to complete the operation,
the type of operation undertaken and contract number. It is this information, which is
stored inside t e co any’s ZXHoistProd management Report (Appendix 1) and
used to extract 3-years ZX6 & ZX8 / 2-years ZX10 production data to build the
Witness simulation. Using Excel, this information is input into a spreadsheet
(Hoist.xls) and manipulated to show 1 record per row, with relevant information
placed into defined cells along the row (Figure 1). Pivot tables are used to ascertain
cycle times, throughput efficiency and the percentage each design variant
contributes to the product-mix.
Figure 1 - Sample Of Hoist Data Used Within A Spreadsheet
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
17
4.3. Distributions
To represent the probable duration hoists spend in each production cell, a
distribution function is used at each activity, to specify the cycle time and allow the
simulation to behave dynamically. Prior to statistical analysis; suspect or erroneous
data such as zero labour hours have been filtered from the empirical cycle times, to
ensure distributions are not distorted. Using EasyFitXL for statistical analysis, 37
theoretical continuous distributions (Appendix 3) have been obtained from the
empirical data. These describe the product and process groups listed in Appendix 2.
To select the closest matching distribution, grading has been made using EasyFitXL
and the Kolmogorov-Smirnov test.
Of the distributions found, none are standard types being incorporated within
Witness. This is overcome by importing a distribution probability density function for
all time increments within an upper and lower limit, into a Witness real distribution at
model initialisation (Figure 2). This method allows any distribution, empirical or
theoretical to be used within the model.
Figure 2 - Code To Input Theoretical Distributions
4.4. Model Structure
Mehta (2000) recommends a map of the existing system should be created to
help fully understand what is to be modelled prior to building the simulation. In
response to this advice, a flow chart (Figure 3) has been developed through direct
observation of the production line and communication with the company. This chart
defines the logic to route hoists through the production facilities based upon the
design of product entering.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
18
Figure 3 - Flowchart Of Hoist Routing Through Production
This information has been used to construct a Witness simulation to represent
the production line shown in Figure 4. Whilst the actual production line could deviate
from these routings in exceptional circumstances, the logic defined in Figure 3
dictates the routing of entities inside the simulation without exception.
Hoist Type
Cell 1
Barrel Assembly
Cell 3
Frame Assembly
Cell 4
Trolley
Assembly 1&2
Cell 6 Cable
Routing
Cell 7 Load Test
& Rope Up
Cell 8 CRB / FM
Assembly
Cell 9
End-of-Line
Test
Cell 10
Packing
Cell 11.1
Mechanical
Assembly
Cell 11.3 Cable
Route &Test
Hoist Type
All ZX10 HoistsAll ZX10 Hoists
All ZX8 HoistsAll ZX8 Hoists
ZX86 , 88
OR 10
ZX86 , 88
OR 10
Hoist Type
Any 2or4
Fall CRB
Hoist
Any 2or4
Fall CRB
Hoist
LHR & FM
Hoists
LHR & FM
Hoists
Any 2 or 4 Fall
ZX6 or 8 LHR
Hoist Model
Any 2 or 4 Fall
ZX6 or 8 LHR
Hoist Model
Cell 11.4
Crab
Assembly
OutOut
Any 2 or 4 Fall
ZX6/8 FM / CRB
Hoist Model
Any 2 or 4 Fall
ZX6/8 FM / CRB
Hoist Model
Cell 8
Fit Crab
Frame
to Hoist
Any 6or8
Fall CRB
Hoist
Any 6or8
Fall CRB
Hoist
Order In
In If Hoist
is a ZX8
Model
In If Hoist
is a ZX8
Model
BuildFrame
From Store
InIn
BuildFrame
From Store
OutOutBuildFrame
To Store
Despatch
Hoist
InIn
Generator used
if hoist is a Non-UK
mains supply
Generator used
if hoist is a Non-UK
mains supply
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
19
Figure 4 - Simulated Production Line
4.5. Hoists
Upon creation, the hoist entity is assigned a set of attributes (Figure 5) based
upon the probability certain features are likely to occur. Whilst only one entity type is
used, these attributes ensure all 78 hoist combinations are represented. Using 4
Iuniform distributions, the likelihood of characteristics including design type, size,
routing and processing duration per cell are allocated to the hoist by randomly
selecting a number between 1 and;
The number of hoists produced in the past 12 months
The number of ZX6 hoists produced in the past 3 years
The number of ZX8 hoists produced in the past 3 years
The number of ZX10 hoists produced in the past 2 years
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
20
Figure 5 - Flowchart To Assign Hoist Attributes
The numbers selected are used in a logic statement (Figure 6), to cross reference
against Table 18, Table 19, Table 20 and Table 21 (Appendix 8) to assign the
attributes which characterise the hoist entity.
Figure 6 - Code Defining The Type Hoist Variant Entering The Model
Hoist Entity
Arrives
Iuniform distribution
determines the
hoist model
Iuniform distribution
determines the hoist type,
number of falls &
the barrel length
Hoist entity created
having 18 possible
attribute combinations
Iuniform distribution
determines the hoist type,
number of falls &
the barrel length
Iuniform distribution
determines the hoist
type, configuration
& barrel length
"ZX8" Hoist Model
Attribute Assigned
"ZX8" Hoist Model
Attribute Assigned
"ZX10" Hoist Model
Attribute Assigned
"ZX10" Hoist Model
Attribute Assigned"ZX6" Hoist Model
Attribute Assigned
"ZX6" Hoist Model
Attribute Assigned
Hoist Type,
Hoist Falls &
BarrelType
Attribute Assigned
Hoist Type,
Hoist Falls &
BarrelType
Attribute Assigned
Hoist Type,
Hoist Falls &
BarrelType
Attribute Assigned
Hoist Type,
Hoist Falls &
BarrelType
Attribute Assigned
Hoist Type,
Hoist Configuration &
BarrelType
Attribute Assigned
Hoist Type,
Hoist Configuration &
BarrelType
Attribute Assigned
Hoist entity created
having 36 possible
attribute combinations
Hoist entity created
having 24 possible
attribute combinations
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
21
Using coding in Figure 7, a numeric value quantifying the size of the hoist is
assigned by cross referencing the attribute combination in Figure 5 to the look-up
table in Appendix 9. Using this method ensures that hoists entering the model
represent the actual products entering the production line.
Figure 7 - Witness Coding To Determine The Hoist Size
4.6. Labour and Shift Pattern
Due to the manual assembly process, labour resources are used at every cell
at the ratio of 1 per workstation. These resources have been grouped into five
categories as shown in Table 2.
Table 2 - Labour Resources Used Within The Simulation
The shift pattern used in the simulation allows resources to operate 45 hours per
week including 8 hours Monday to Friday and 5 Hours on Saturday morning. This
represents the total number of hours normally worked by an employee on the day
shift, excluding breaks.
4.7. Generator
The generator resource provides power to operate all non-UK electrical supply
hoists in Cell7 (Rope-up and Line pull test) and Cell9 (End-of-Line test) for the
duration of the activity (Figure 3). It is assumed product type has no bearing on the
required power supply. As such, each hoist to enter the model is assigned a
Labour TypeExisting
QuantityOperations Performed Cell Used In
Mechanical 9 All Except Cable Routing, Packing & EoL Test 1,3,4,7,8,11
Electrical 3 Cable Routing 6,11
Despatch 2 Packing 10
Test 2 End of Line Test 9
Mech_Elect 1 All Except Packing & EoL Test 1,2,3,4,6,7,8,11
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
22
voltage/frequency attribute corresponding to the % split obtained from historical data
in Table 3.
Table 3 - Generator Requirement
4.8. Build-Frames
A Build-Frame is used to assemble every ZX6 and ZX8 hoist model, at the
ratio of 1 per hoist. These are attached to the hoist at the end of barrel assembly in
Cell1, Cell8 or Cell11 and remain so until removal at the packing stage in Cell10
(Figure 3). It is assumed the time to fit or remove these items is part of the barrel
assembly and packing distribution duration.
In total, eight types of build-frame are available in quantities as per Table 4.
This quantity will remain unchanged for this project to help control WIP levels. It is
recognised, increased production levels or variation in the production mix may
cause insufficient availability, causing delays for hoists to enter into the production
line, however this will not form part of this analysis.
Table 4 - Existing Build-Frame Types And Quantities
Voltage Frequency % Split
Generator
Requirement
380 50 2.10 Yes
400 50 75.94 No
230 60 0.03 Yes
380 60 2.13 Yes
440 60 0.03 Yes
460 60 11.43 Yes
575 60 8.35 Yes
Grand Total 100
Model
Design
Type
Number
of Falls
ZX6 LH ZX6 LHR ALL 35
ZX6 FM ZX6 FM ALL 6
ZX6 CRB ZX6 CRB ALL 8
ZX8 LH 2/4Fall ZX8 LHR 2 & 4 16
ZX8 FM ZX8 FM ALL 5
ZX8 CRB 2/4Fall ZX8 CRB 2 & 4 9
ZX8 CRB 6/8Fall ZX8 CRB 6 & 8 11
ZX8 LH 6/8Fall ZX8 LHR 6 & 8 2
92Total
BuildFrame
Simulation
Name
Hoists The BuildFames
are Designed to FitQty
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
23
Whilst each build-frame must be attached to the correct hoist (Table 4), only one
entity is used to represent all build-frame types. This reduces the number of entities,
allows build-frame pre-emption and simplifies entry into and out of the model. At
time zero, build-frame entities are pushed into eight queues (Figure 8).
Figure 8 - Code To Push A Build-Frame Entity Into The Model At Zero Time
To ensure build-frames enter and exit the same queue, each hoist is assigned an
attribute at creation with the name of the queue that contains the required build-
frame (Figure 8).
Figure 9 - Code To Allow Hoists To Link To The Correct Build-Frame Queue
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
24
This attribute is used to push and pull build-frames to and from the correct queue,
and to ensure hoists only enter barrel assembly if the corresponding build-frame is
available (Figure 10). Whilst pre-emption of build-frame availability prior to starting
work may not always be realistic, it does prevent blockages inside the simulation.
Figure 10 - Output Condition For Buffers Feeding Cells1, 8 And 11
4.9. Throughput Efficiency
Throughput efficiency is used within the simulation to benchmark against the
existing production line (Equation 1). Where the total value added time is the
number of labour hours booked to the hoist, and the total throughput time is the
entire duration from start to the completion date.
TE for hoists produced in 2012 (Table 5) indicate a large proportion of the total
throughput time is the total non-value added time (Equation 2).
Table 5 - 2010 to 2012 Output & TE
Hoists
Produced
Average
ThroughPut
Efficiency
Hoists
Produced
Average
ThroughPut
Efficiency
Hoists
Produced
Average
ThroughPut
Efficiency
ZX10 1 3.7 61 5.4 60 6.4
ZX6 614 5.1 749 4.5 863 5.1
ZX8 459 5.0 532 5.6 667 5.5
Total 1074 5.1 1342 5.0 1590 5.3
2010 2011 2012
Model
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
25
Through assessment of the simulation, it is evident the duration an entity
spends inside the production line as WIP, waiting to enter next activity or off-shift,
does not account for the total non-value added time. As such, forced delays
(Equation 4) have been used to allow the simulation to benchmark throughput
efficiency levels recorded in 2012.
Equation 4 - Forced Delay Time
o ce elay ti e otal non alue a e ti e otal ueuin ti e otal ff ift ti e
The additional delay could stem from any one of the seven deadly wastes of
lean manufacturing (Melton, 2005) (Ramaswamy, et al., 2002). Yet for this
simulation, no data has been available to indicate the causes, or where in the
production process is affected most. For this reason, it is assumed delays occur
equally across the production line. The simulation seeks to maintain TE through the
use of an output rule, used to control the exit from a buffer at each production cell
(Figure 11). Only if an entities TE is less than or equal to 2012 TE will the entity be
able to leave the buffer.
Figure 11 - Sample Witness Code To Control TE
To enable this method, three attributes are assigned to every hoist which define;
The historic Throughput Efficiency
The cumulative value added time
The time spent waiting to enter the production line.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
26
This approach will maintain 2012 TE levels, with the exception of some system
configurations which exhibit significantly large queuing, causing the simulated TE to
fall below the historical value.
4.10. Entity Feeding
The hoist arrival rates are set sufficiently high for all scenarios to ensure the
output is not constrained. To mimic the release of works instructions into the
production line, hoist entities are released in batches of 10. Like production
management, this allows the simulation to select from the batch which entity can
enter the production line.
4.11. Variable Buffer Sizes
Through observation, it is apparent the maximum hoist storage capacity of each cell
will vary depending on the area available within the cell and the size of products
inside the cell. The simulation governs product entry into a cell using the logic
controlling size in Figure 12.
Figure 12 - Logic Governing Hoist Entry Into A Buffer
Unfortunately, this entry logic does not account for gaps between products. As such,
more hoists potentially could be stored inside the simulated area than is realistic. An
alternative method could be constructed using an array of dummy activities to
represent the usable area. Using product length and width attributes to represent the
hoists size, the entry into each dummy activity could be controlled using similar logic
to Figure 12. While the alternative approach has proven more accurate by allowing
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
27
for wasted space, multiple dummy arrays complicate the model significantly and
restrict change. It is for these reasons it has not been adopted for this project.
4.12. Usable Cell Area
The usable area within each cell is the maximum space available minus the total
area imposed by the number of workstations. For this project, the maximum area of
a cell will remain fixed, shown in Figure 13.
Figure 13 - Layout Of The Production Line & Assembly Cell Sizes
The size of a workstation varies depending on the process undertaken. Whilst some
processes do not require any workstation area, others require physical items such a
workbench or test equipment which occupy space in the cell regardless of WIP
(Table 6).
Table 6 - Workstation Sizes / Cell
Given that too few workstations can cause bottlenecks via insufficient
processing capacity, too many can also reduce the storage capacity within the cell,
yet both can also lead to a reduction in output. The Witness coding used to calculate
the usable cell area at “initialise actions” is shown in Figure 14.
Cell 11
Cell 9
Cell 10
Cell 1
Cell 9
Cell 3Cell 4
Cell 6Cell 7Cell 7Cell 8Cell 10
Cell 7
12m
11.6
m
4.4
m
9.8m
7.6m 7.2m 6.3m
3.9
m
2.3m
5.9
m
5m
6.5
m
8.3m5.4m
6.5
m
4.9m 3.6
m
4.7m
7.4
m
7.5m
10.8
m
Cell Cell4 Cell 6 Cell 8 Cell 9 Cell 10 Cell 11
ActivityBarrel
Assembly
Frame
assembly
Trolley
Assembly
Cable
Routing
Line Pull
Test
Rope
Up
ZX6 & ZX8
2/4 Fall Crab
Assembly
End of
Line
Test
Packing
ZX8 6/8
Fall &
ZX10
Assembly
Cell Area (m²) 29.2 32.5 54.0 35.1 115.8 61.0 139.2
Workstation
RequirementsBench Bench Bench None Load Test Rig None Bench Bench None Bench
Area Imposed Per
Workstation (m²)2 0 4 0 2 2 0 2
Cell1 & 3
2
57.7
Cell 7
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
28
Figure 14 - Coding To Determine The Usable Cell Area
4.13. Warm-Up Period
The daily operation of the production line requires a constant presence of WIP
to ensure resources have tasks to perform at the start of each day. In contrast, the
simulation will start with zero WIP, allowing levels to build up over a period. The use
of a simulation warm-up period ensures behaviour at initialisation does not bias the
results (Lanner, 2012).
To determine the warm-up duration, an assessment of labour utilisation has
been made in the early stages of model start-up, using the existing production line
parameters. It has been found without any initial starting conditions; the simulation
must run for 2184hours before the labour utilisation reaches a steady condition
(Figure 15).
Figure 15 - Warm-Up Period Without Starting Conditions
73.5 - Avg72.1 - Min
74.9 - Max
0
10
20
30
40
50
60
70
80
90
0
16
8
33
6
50
4
67
2
84
0
10
08
11
76
13
44
15
12
16
80
18
48
20
16
21
84
23
52
25
20
26
88
28
56
30
24
31
92
33
60
35
28
36
96
38
64
40
32
42
00
43
68
45
36
47
04
48
72
Lab
ou
r U
tilis
atio
n %
Time (Hours)
Warm-Up Period (Without Starting Conditions)
Labour Utilisation
Average Labour Utilisation
Minimum Labour
Utilisation
Maximum Labour Utilisation
Transient Steady State
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
29
Although the warm-up duration is necessary to remove bias, it does add
additional real-time onto the length of the experimentation. As a remedy, initial
conditions have been set to reduce the warm-up duration and overall simulation
running time for subsequent experiments.
On start-up, 60 hoist entities are input into the model at a zero time, those
arriving at cell 1 are processed at zero time and pushed to buffers at cell 4, 6 and 7
Figure 16.
Figure 16 - Code To Inject Hoists Into The Model At Initialisation
Once these initial hoists have entered the model, the arrival rate is increased and
normal operation starts. In effect, this method injects entities into the model thereby
ramping up labour utilisation and dispatch rate much faster whilst reducing
simulation time by approximately 16%.By this initialisation method, the warm-up
duration can reduce to 500hours (Figure 17).
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 4 Methodology
30
Figure 17 - Warm-Up Period With Starting Conditions
4.14. Assumptions
Only direct labour is required to operate the production line
Entities arriving into the model are not part of a batch of the same product
No account has been made for holidays or sickness
Labour resources use the same shift pattern for the duration of the simulation
The product-mix will remain constant
Unless specified, experiments are run for 12-months (8760hour) duration plus a
500 hour warm-up, with the mean value taken over 10 replications.
To find the maximum capacity of a system, labour resources are set sufficiently
high to ensure labour availability does not constrain the output.
Forecasted sales projections grow at 10% year on year
75.1 - Avg72.5 - Min
78.85 - Max
0
10
20
30
40
50
60
70
80
90
0
16
8
33
6
50
4
67
2
84
0
10
08
11
76
13
44
15
12
16
80
18
48
20
16
21
84
23
52
25
20
26
88
28
56
30
24
31
92
33
60
35
28
36
96
38
64
40
32
42
00
43
68
45
36
47
04
48
72
Lab
ou
r U
tilis
atio
n %
Time (Hours)
Warm-Up Period (With Starting Conditions)
Labour Utilisation
Average Labour
Utilisation
Minimum Labour Utilisation
Maximum Labour
Utilisation
Transient Steady State
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
31
CHAPTER 5 VERIFICATION AND VALIDATION
5.1. Verification
In order to verify the simulation operates in the way intended, the model has
been observed running after each incremental change. The use of element flow
lines shown in Figure 18 allows a visual verification to determine if cells are correctly
linked. Due to the number of attribute combinations from a single hoist entity, this
method is not suitable to check the routing of specific products.
Figure 18 - Model Showing Element Flow Lines To Verify Routings
Whilst the individual routing can be checked manually via inspection of the
input and output rules, in practice this has proven time consuming and prone to
error. Instead, 4 additional lines of code used at “actions on input”, activate should a
hoist entity with an unwanted attribute arrive. This code verifies product routings
automatically and reduces the time to remove errors by causing the simulation to
stop and highlight the activity name, the unwanted attribute and the time (Figure 19).
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
32
Figure 19 - Coding To Prevent The Processing Of Unwanted Attributes
5.2. Validation
To validate if the simulation data is representative of the production line, two
tests have been undertaken to compare cycle-times, overall production hours,
product-mix and throughput efficiency.
5.2.1. Validation 1 - Comparison of simulated to actual processing time
For this exercise, the model was run once for 100,000hrs to record the total
processing time for every hoist entity exiting the packing stage at cell 10. To allow
like-for-like comparison, the results from both historical and simulated data have
been grouped into 11 product categories. Table 7 shows the comparisons between
the historical and simulated average processing times. It can be seen that the
simulated times compare closely to the historical times, with a maximum error of
2.79%.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
33
Table 7 - Average Cycle-Times
5.2.2. Validation 2: Comparison of simulation to 2012 production figures
To compare against historical data, the simulation was run over 50
replications, to quantify; product-mix, total produced, labour hours and throughput
efficiency (Table 8). For comparison, only performance indicators of hoists built in
2012 are used. The confidence levels for all results of validation 2 are shown in
Appendix 4 .
Table 8 - Actual 2012 Production Data To Validate Against
Table 9 shows the comparison of actual to simulated mean quantity of
products dispatched. Whilst these results do not show an exact correlation, the
product split and the total number despatched are similar. This validates the
Iuniform distributions, which control the model split are correct.
Model Historical
ZX6 CRB 2 TO 4 14.52 14.66 -0.94%
ZX6 FM 2 TO 4 11.81 11.98 -1.34%
ZX6 LHR 2 TO 4 13.76 13.91 -1.05%
ZX8 CRB 2 TO 4 23.29 23.44 -0.66%
ZX8 FM 2 TO 4 19.78 20.24 -2.27%
ZX8 LHR 2 TO 4 19.63 19.99 -1.81%
ZX8 CRB 6 TO 8 35.91 35.00 2.59%
ZX8 FM 6 TO 8 29.87 30.09 -0.72%
ZX8 LHR 6 TO 8 35.99 35.24 2.12%
ZX10 DD ALL 42.93 41.77 2.79%
ZX10 ST OR SS ALL 32.05 31.93 0.40%
Hoist
Model
Average Processing
Time (hrs)
Error %
Hoist
Type
Number of
Falls
Model
Number of
Hoists
Produced
Model
Split (%)
Total Hours
to Complete
Average
Throughput
Efficiency (%)
ZX10 60 3.77% 1652.0 6.4
ZX6 863 54.28% 11952.2 5.1
ZX8 667 41.95% 12509.4 5.5
Total 1590 26113.6
2012 Hoist Production
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
34
Table 9 - Actual Vs Simulated Products Built
Table 10 shows the comparison of actual throughput efficiency to the
simulated mean throughput efficiency. Although the simulated TE values are all
slightly less than the actual values, this has not restricted the output, as shown in
the quantity of hoists despatched (Table 9) being 4.78 more than the actual. This
indicates that the TE errors are not significant to influence the results.
Table 10 - Actual Vs Simulated Throughput Efficiency
Table 11 shows the comparison of actual to simulated total labour hours.
These results show a significant difference, with the simulation being 2887.6 hours
or 11.06% more. On closer inspection of the data used to find the total labour hours
booked in 2012, it was found that 1171 operations were recorded with a zero labour
time. This means that the total actual time used to validate the simulation against is
questionable. To quantify this effect, the 1171 instances of zero labour time have
been multiplied by the average process time (Appendix 5). When the average times
for the missing data are added to the actual labour hours, the simulation is only
125.6 hours or 0.43% less.
Table 11 - Actual Vs Simulated Labour Hours
Model
Number
of Hoists
Produced
Product
Split (%)
Average
Number
of Hoists
Produced
Product
Split (%)
ZX10 60 3.77% 47.56 2.98%
ZX6 863 54.28% 885.4 55.52%
ZX8 667 41.95% 661.72 41.49%
Total 1590 1594.78
Validation Model2012 Hoist Production
Model
Actual Average
Throughput
Efficiency in
2012 (%)
Simulation
Average
Throughput
Efficiency (%)
% Error
From
Actual
ZX10 6.4 6.222 -2.8408%
ZX6 5.1 5.004 -2.0135%
ZX8 5.5 5.269 -4.7702%
2012 Actual Simulation Difference Error (%)
Labour Hours Recorded 26113.6 29001.261 2887.6 11.06%
Calculated Time Not Recorded 3013.2 - - -
Total Labour Hours 29126.8 29001.261 -125.6 -0.43%
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 9
35
CHAPTER 6 EXPERIMENTATION AND OPTIMISATION
Experimentation has been undertaken in a number of stages using the Witness
13 Experimenter module, to analyse the effect system parameters have on maximum
output. This module provides the ability to optimise the simulated model using a
range of inbuilt algorithms to determine which parameter combination provides the
optimum object function (Lanner.com, 2012). In addition, it allows the same
experiment to be run over a number of replications, to test for variation by using a
different number stream per replication. This generates confidence levels in the
results, so the overall variability of the system can be gauged. The experiments in
this piece of work use the “all combinations” method, to test all the possible
parameter combinations, with the object function or goal to maximise the number of
hoists shipped
6.1. Experiment 1 - Determine the Maximum Output for the Existing Factory
The first experiment aims to quantify the maximum output of the existing
factory, without any changes other than allowing sufficient labour to work. The
purpose is to establish a benchmark to measure future improvements. The quantity
of simulation elements is set to reflect the existing quantities shown in Table 12.
Table 12 - Existing Workstation Quantities / Production Cell
Cell 1 ZX6 & 8 LHR 2/4 Fall Barrel Assembly 2
Cell 3 ZX6 & 8 LHR 2/4 Fall Frame Assembly 2
Cell 4 ZX6 & 8 LHR 2/4 Fall Trolley Assembly 2
Cell 6 Cable Routing 3
Cell 7 Line Pull Test 1
Cell 7 Rope-Up Only 2
Cell 8 ZX6 & 8 2/4 Fall Crab / Foot mount Assembly 1
Cell 9 End of Line Test 3
Cell 10 Packing Assembly 2
Cell 11 ZX10 & 6/8 Fall ZX8 Assembly 4
Generator Power supply for non 400Volt / 50Hz Products 1
BuildFrame ZX6 LHR Buildframe 35
BuildFrame ZX6 FM Buildframe 6
BuildFrame ZX6 CRB Buildframe 8
BuildFrame ZX8 2/4 Fall LHR Buildframe 16
BuildFrame ZX8 FM Buildframe 5
BuildFrame ZX8 2/4 Fall CRB Buildframe 9
BuildFrame ZX8 6/8 Fall LHR Buildframe 11
BuildFrame ZX8 6/8 Fall CRB Buildframe 2
DescriptionElement
QTY
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
36
The mean value of 10 replications shows the capacity of the existing production
line is 1718.8. At 99% confidence levels; the system achieves a minimum output of
1690 at the lower limit, yet this could increase to 1748 at the upper limit (Figure 20).
Figure 20 - Confidence Levels For The Existing Production Line Capacity
Given production levels of 1590 hoists in 2012 and 10% growth, the existing
production line would require changes other than just additional labour between
August 2013 and January 2014 (Figure 21).
Figure 21 - Potential Life Of The Existing System
In contrast, and to demonstrate the requirement for forced delays, this
experiment has run under the same conditions but without forced delays applied.
1580
1600
1620
1640
1660
1680
1700
1720
1740
1760
Jan 1
3
Feb
13
Mar 1
3
Ap
r 13
May 1
3
Jun
13
Jul 1
3
Au
g 13
Sep
13
Oct 1
3
No
v 13
De
c 13
Jan 1
4
Feb
14
Mar 1
4
An
nu
al D
esp
atch
Vo
lum
e
Date
Potential Life of Existing System
10% Year on Year Sales
Growth
Mean Capacity
99% Min Capacity
99% Max Capacity
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
37
Using this scenario the same model could achieve a mean output of 1801.8
hoists/year; with 99% confidence levels achieving 1756.7 at the lower limit and
1846.9 at the upper limit (Figure 22).
Figure 22 - Confidence Levels For The Existing Production Line (No Delay)
This additional capacity stems from the throughput efficiency increasing from 5.12%
to 5.38%, which reduces the average total production time from 351 to 331hours.
6.2. Experiment 2 - Optimise the Production Line without Capital Investment
The purpose of this experiment is to determine how to increase the production
output without investment in equipment such as generators or line pull testrigs. In
discussion with the company, it has been decided that the possible changes to
workstation quantities should be limited to those given in Table 13.
Table 13 - Experiment 2 Maximum / Minimum Workstation Parameters
6.2.1. Part A: Optimise The Production Line Configuration
The first part of this experiment will ascertain the optimum configuration based
upon forced delays being removed. Considering the lengthy duration to perform this
experiment; each scenario is run for a shorter duration of 4380 hours with only 5
replications. The top 40 scenarios for this experiment are shown in Appendix 6 with
From To
Cell 1 ZX6 & 8 LHR 2/4 Fall Barrel Assembly 2 4 3 3
Cell 3 ZX6 & 8 LHR 2/4 Fall Frame Assembly 2 4 3 9
Cell 4 ZX6 & 8 LHR 2/4 Fall Trolley Assembly 2 4 3 27
Cell 6 Cable Routing 3 6 4 108
Cell 7 Line Pull Test 1 1 1 108
Cell 7 Rope - Up 2 4 3 324
Cell 8 ZX6 & 8 CRB & FM Assebly 1 3 3 972
Cell 9 End of Line Test 3 4 2 1944
Cell 10 Packing Assembly 2 4 3 5832
Cell 11 ZX10 & 6/8 Fall ZX8 Assembly 4 6 3 17496
Configuration Combinations
Total
Combinations
Element to
changeDescription
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
38
the optimum scenario, achieving a mean of 976.2 hoists shipped in 6 months shown
in Table 14.
Table 14 - Experiment 2 Optimum Scenario
Using a comparison showing the average cycle-time per cell, the work load for
existing and optimised cell configurations, it becomes apparent why this is the
optimum solution (Figure 23). On inspection of this chart, it is clear a significant
imbalance in cycle-times occur from one cell to the next. Without being able to
redistribute work, increase working hours or buffer sizes to balance workload; the
simulation has optimised the production line via the quantity of workstations per cell.
This has reduced Takt-time (Simons & Zokaei, 2005) by 0.67 hours, and imbalance
by 0.45 hours in the optimised configuration.
Mean Quantity Dispatched 976.2
Cell1 Quantity 3
Cell3 Quantity 4
Cell4 Quantity 3
Cell6 Quantity 6
Cell8 Quantity 1
Cell9 Quantity 4
Cell11 Quantity 6
Cell10 Quantity 4
Cell7_RopeUp Quantity 4
Generator Utilisation 96.2
90% Min 937.6
90% Max 1015
95% Min 925.8
95% Max 1027
99% Min 892.8
99% Max 1060
Co
nfi
de
nce
Op
tim
ise
d C
on
figu
rati
on
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
39
Figure 23 - Production Line Balance Comparison
Whilst this analysis does not consider potential variation in cycle-times, it does
indicate that production levels could increase significantly (Equation 5).
Equation 5 - Customer Demand
Even though this experiment is 6 months duration, the output is 744 hoists less
than Equation 5 would suggest is possible to produce. This analysis does not
consider lower volume products such as CRB and FM designs or any ZX10 hoists
therefore, 3441 hoists/year, is potentially an under estimate of what can be produced.
The explanation for this could stem from the generator resource being used nearly all
of the time (Table 14), which probably has a significant influence on the output. One
could speculate that output will increase by maximising the number of
workstations/cell, by creating redundancy to cope with variation; however excessive
quantities constrain the output by reducing floor space and storage capacity
unnecessarily.
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
Cell 1 Barrel Assy
Cell 3 Frame Assy
Cell 4 Trolley
Assy
Cell 6 Cable
Routing
Cell 7 Load Test
Cell 7 Rope-Up
Cell 9 EOL test
Cell 10 Packing
Pro
du
ctio
n H
ou
rs /
Wo
rk S
tati
on
Production Cells
Time / Hoist Line Balance Comparison Average Cycle-
Time / Cell
Existing Production Line Configuration
Optimised Production Line Configuration
Existing Minimum Takt Time
Optimised Minimum Takt Time
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
40
6.2.2. Part B - Quantify the Optimised Configuration
To allow comparison, the optimised scenario has been repeated for a 1-year
duration, with and without forced delays. This enables the output to be quantified at
the worst case scenario; maintaining the existing TE or best case scenario; with the
removal of forced delays.
At best case, the removal of forced delays increases the mean output to 1978
hoists/year. This is 260 more than is possible from the existing production line when
maximum capacity is reached. The confidence levels for this are shown in Figure 24.
Figure 24 - Experiment 2 Confidence In Capacity (No Forced Delay)
With TE set to ensure it does not exceed existing levels; at the worst case the
mean output increases to 1915 hoists/year, 197 extra than the existing production
line. The confidence levels for this are shown in Figure 25.
Figure 25 - Experiment 2 Confidence In Capacity (With Forced Delay)
Assuming 10% growth, the optimised configuration will extend the life of the
existing production facilities until at least August 2014 based upon 99% minimum
confidence levels at the existing TE. If forced delays are removed, the longevity could
be extended until August 2015 based upon 99% maximum confidence levels (Figure
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
41
26). To achieve higher production volumes, further changes are required such as
working additional hours, or by removing other constraints.
Figure 26 - Potential Life Of 1st
Optimised System
6.3. Experiment 3 - Optimise the Production Line with Capital Investment
This experiment will quantify the effect investment in additional line pull test
equipment and generators have on production output at best and worst case
scenarios. Using 2012 TE levels to constrain the model at the worst case, and
unconstrained TE at the best case, a definitive lifespan and capacity can be assigned
to the production facility. The possible investment configurations are shown in Table
15. The purpose of this experiment is to show that changes driven by waste
reduction can make a significant contribution to the output.
Table 15 - Experiment 3 Maximum / Minimum Workstation Parameters
1800
1850
1900
1950
2000
2050
2100
Jun
14
Jul
14
Aug
14
Sep
14
Oct
14
Nov
14
Dec
14
Jan
15
Feb
15
Mar
15
Apr
15
May
15
Jun
15
Jul
15
Aug
15
Sep
15
Oct
15
Nov
15
An
nu
al D
esp
atch
Vo
lum
e
Date
Potential Life of Optimised System
10% Year on Year Sales Growth
Mean capacity -no delay
99% Max capacity - no delay
99% Min capacity -no delay
Mean capacity -delay
99% Max capacity - delay
99% Min capacity -delay
From To
Cell 7 Line Pull Test 1 3 3 3
Generator Generator Resource 1 11 11 33
Element
To ChangeDescription
Configuration
CombinationsTotal
Combinations
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
42
When forced delays constrain the system, it is clear the optimum configuration
from the last experiment does not achieve the average TE from 2012 until a second
generator resource is used (Figure 27). Furthermore, a third or fourth generator or
any additional line pull testrig provides no additional benefit.
Figure 27 - Experiment 3 Throughput Efficiency
Interestingly if the forced delays are removed; the use of a second and third
line pull testrig does improve TE using a single generator, yet with additional
generators and a higher output, a third testrig does not. This stems from hoist entities
arriving at the line pull test and blocking the activity until the generator resource is
free, thus additional testrigs offer the potential to test more products and improve TE.
In reality, this scenario would not manifest unless the operator at the line pull test had
no UK electrical supply hoists to test. As such, the requirement for the third line pull
testrig can be discounted, yet in all cases, a second unit does offer improvement.
Referring to Little’s Law, the approach adopted for this project was to increase
output by maintaining WIP but reducing the overall throughput time. Figure 28 shows
4%
5%
6%
7%
8%
9%
10%
11%
12%
13%
1 2 3
Thro
ugh
pu
t Ef
fici
en
cy %
Number of Line Pull Test Rigs
Throughput Efficiency 1 Generator (With Delay)
2 Generators (With Delay)
3 Generators (With Delay)
4 Generators (With Delay)
1 Generator (No delay)
2 Generators (No delay)
3 Generators (No delay)
4 Generators (No delay)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
43
WIP levels, instead of being maintained, can reduce whilst production output
increases (Figure 29)
Figure 28 - Experiment 3 Average WIP
Comparison of Figure 27 and Figure 29; shows the overall duration a hoist
spends inside the production line has a significant impact on the number of hoists
that are able to be produced. Under the same operating conditions, the output can be
seen to differ by as much as 1139 hoists/year. This amount depends entirely on TE
ranging from 5.16% to 12.6% (Figure 29).
55
60
65
70
75
80
85
90
95
1 2 3
Ave
rage
Qu
anti
ty o
f W
IP
Number of Line Pull Test Rigs
Average WIP 1 Generator (With Delay)
2 Generators (With Delay)
3 Generators (With Delay)
4 Generators (With Delay)
1 Generator (No delay)
2 Generators (No delay)
3 Generators (No delay)
4 Generators (No delay)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
44
Figure 29 - Experiment 3 Hoists / Year
In concurrence, the use of a 3rd or 4th generator is pivotal to achieve the
optimum output, TE and WIP. Yet in all cases, a second generator provides a notable
increase in output to exceed existing levels.
If 2012 TE levels are not able to be surpassed, the production line could only
achieve an average 2293 hoists/year, irrespective of any other investments. Should
these circumstances become evident, the company should look to move into larger
premises.
If factors constraining TE are eliminated, a second unit will support production
output without constraint until levels approach 3144 hoists/year. Further investment
would then be required in a 3rd generator to allow the configuration to achieve a
maximum of 3425 hoists/year.
Figure 33 shows the difference this could have on a timeline; making
comparison of 5.16% TE using 2 generators to 11.74% TE using 3 generators.
Clearly without TE improvement this configuration can be expected to serve
1900
2100
2300
2500
2700
2900
3100
3300
3500
1 2 3
Nu
mb
er
of
Ho
ists
Sh
ipp
ed
Number of Line Pull Test Rigs
Hoists Produced / Year 1 Generator (With Delay)
2 Generators (With Delay)
3 Generators (With Delay)
4 Generators (With Delay)
1 Generator (No delay)
2 Generators (No delay)
3 Generators (No delay)
4 Generators (No delay)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
45
production until November 2016 at maximum confidence levels, yet improvement in
TE could extend the lifespan until February 2021 (Figure 30).
Figure 30 - Potential Life Of Experiment 3
This experiment shows that throughput has a significant bearing on both output
and longevity of the existing facilities. Despite the ability to develop an optimum
production configuration to cope with high output, the simulation is unable to provide
a solution to show how waste reduction is achieved or even if it is possible.
2200
2300
2400
2500
2600
2700
2800
2900
3000
3100
3200
3300
3400
3500
Jun
16
Au
g 1
6
Oct
16
De
c 1
6
Fe
b 1
7
Ap
r 1
7
Jun
17
Au
g 1
7
Oct
17
De
c 1
7
Fe
b 1
8
Ap
r 1
8
Jun
18
Au
g 1
8
Oct
18
De
c 1
8
Fe
b 1
9
Ap
r 1
9
Jun
19
Au
g 1
9
Oct
19
De
c 1
9
Fe
b 2
0
Ap
r 2
0
Jun
20
Au
g 2
0
Oct
20
De
c 2
0
Fe
b 2
1
Ap
r 2
1
Jun
21
An
nu
al D
esp
atch
Vo
lum
e
Date
Potential Life of Optimised System with Investment 10% Year on Year Sales Growth
99% Max capacity -11.74% TE
Mean capacity -11.74% TE
99% Min capacity -11.74% TE
99% Max capacity -5.16% TE
Mean capacity -5.16% TE
99% Min capacity -5.16% TE
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
46
6.4. Experiment 4 - Check Optimum Configuration
Given that additional generators allow the output to grow significantly if forced
delays are removed, Experiment 4 will re-evaluate the optimum configuration from
experiment 2 using 4 generators. The purpose is to determine if this configuration is
still valid to produce the maximum output, or if some other elements now constrain
the system. The possible parameter combinations are shown in Table 16.
Table 16 - Experiment 4 Parameters To Check
Using the parameter analysis feature within Witness Experimenter (Figure 31), it is
clear that cell 8 was constraining the output in the last experiment, with cell 7 (line
pull test) being close behind.
Figure 31 - Experiment 4 Parameter Analysis
If workstations within these cells are increased, the production line could achieve an
average of 3890 hoists/year using the configuration highlighted in Table 17.
From To
Cell 1 ZX6 & 8 LHR 2/4 Fall Barrel Assembly 3 4 2 2
Cell 4 ZX6 & 8 LHR 2/4 Fall Trolley Assembly 3 4 2 4
Cell 7 Line Pull Test 1 2 2 8
Cell 8 ZX6 & 8 CRB & FM Assebly 1 3 3 24
Element
to
change
DescriptionConfiguration
CombinationsTotal
Combinations
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
47
Table 17 - Experiment 4 Optimum Scenario
As suspected using Takt time to analyse the balance of work (Figure 23), the
use of additional workstations in cells 1 and 4 do not contribute to additional output.
Interestingly the use of additional workstations has proven to reduce the output. This
effect, described by Lepore & Cohen (1999:9) as “local optimization at the expense
of global optimization”, is caused by a reduction in the available buffer storage space
due to unnecessary workstations.
The results from experiment 4 are shown in
Appendix 10, from which the optimum configuration allows the life of the
production facility to increase to at least April 2022 based on 10% year on year
growth (Figure 32). At 3890 hoists/year, this configuration represents the maximum
output achievable using the possible parameter combinations.
Optimum Scenario 6 18 12 24
Mean Hoists Shipped 3890.2 3890.1 3888.1 3884.9
Cell1 Quantity 3 4 3 4
Cell3 Quantity 4 4 4 4
Cell4 Quantity 3 3 4 4
Cell6 Quantity 6 6 6 6
Cell8 Quantity 3 3 3 3
Cell9 Quantity 4 4 4 4
Cell11 Quantity 6 6 6 6
Cell10 Quantity 4 4 4 4
Cell7 Rope-Up Quantity 4 4 4 4
Generator Quantity 4 4 4 4
Cell7 LinePull Quantity 2 2 2 2
Generator Utilisation (%) 47.1 47.1 46.8 46.9
ZX6 Throughput Efficiency (%) 9 9 9 9
ZX8 Throughput Efficiency (%) 23 23.4 23.1 23
ZX10 Throughput Efficiency (%) 14 14 14 14
Line Pull Utilisation (%) 51.6 51.4 51.4 51.5
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
48
Figure 32 - Potential Life Of Experiment 4
Fundamentally, it is the extra workstations inside cell 8 which has enabled the
output to grow. The additional line pull testrig in cell 7 has reduced the loading on the
existing unit, allowing throughout efficiency to improve. It is foreseeable that the
output could increase further if additional hours be applied to the same timeframe
through shift patterns or overtime.
6.5. Experiment 5 - Influence of Generator Requirement on Output
Until this point, the percentage of non-UK electrical supply products was
assumed to remain constant throughout growth. Experiment 5 illustrates how product
voltage and frequency requirement could affect the output in the absence of any
constraint other than generator requirement.
In 2012, hoists produced with non UK electrical systems contributed 24.06% of
total sales (Table 3). With hoist sales forecast to grow at 10% year on year, it is
feasible that UK sales may not contribute to this growth. Should this scenario occur;
expansion into overseas markets could result in a disproportionate increase of non-
3800
3820
3840
3860
3880
3900
3920
3940
3960
3980
4000
Mar 22 Apr 22 May 22 Jun 22 Jul 22 Aug 22
An
nu
al D
esp
atch
Vo
lum
e
Date
Potential Life of Experiment 4
10% Year on Year Sales Growth
Mean capacity
99% Min capacity
99% Max capacity
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
49
UK electrical systems. If this scenario is true, by 2023 as many as 3328 hoists or
73% of all products sold will require the use of the generator (Figure 33).
Figure 33 - Potential For Generator Requirement To Grow With Sales
With this possibility in mind, experiment 5 will run the optimised solution from
experiment 4 to determine the quantity of generators required to sustain sales growth
with the percentage of non-UK mains supply products ranging from 0 to 70%.
The results of this experiment have been plotted onto Figure 34; analysis
shows a single generator will allow sales up to 2100 units/year at the existing
percentage requirement. If the sales of non-UK electrical systems continue at
24.06% of total sales; 4 generators are required to allow the system to reach a
maximum output of 3890 hoists/year. If the generator requirement grows
disproportionately with respect to sales volume (shown in Figure 34), 7 generators
would be required by 2021, to allow the system to reach maximum output.
0%
10%
20%
30%
40%
50%
60%
70%
80%
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
20
12
20
13
20
14
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
% G
en
era
tor
Re
uir
em
en
t
Ho
ists
Sh
ipp
ed
/ Y
ear
Year
Potential Growth of Hoists With Non UK Mains Supply
Total Hoists Produced / Year
Total Non UK Suppy Hoists / Year
Overall Generator Requirement (%)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
50
Figure 34 – Output Vs Generator Requirement
The purpose of this experiment is to demonstrate that factors other than those
considered in the ERP system can have a significant impact on what can be
produced, within a given timeframe. A danger could arise if the company were to
accept a large overseas order on a standard lead-time without considering the
generator available capacity. This would cause a bottleneck to develop, and only
resolved through working additional hours in all processes requiring the generator. If
additional time is not worked, the company will fail to make an on-time delivery.
6.6. Experiment 6 - Effect of TE on Lead-time, WIP & Arrival Rate
The purpose of this experiment is to illustrate the relationship between
Throughput Efficiency and Little’s Law when the production line operates at
maximum capacity. The aim is to quantify the maximum output of a system when the
system is constrained to a lower throughput than is theoretically achievable. This
idea applies to the time directly after a production line change, when the system is
constrained by elements external to change such as waste, until such time when
waste is reduced and system again constrains the output.
20122013
2014
2015
2016
2017
2019
2020
2021
2022
0
250
500
750
1000
1250
1500
1750
2000
2250
2500
2750
3000
3250
3500
3750
4000
0% 10% 20% 30% 40% 50% 60% 70%
Nu
mb
er
of
Ho
ists
Sh
ipp
ed
% Generator Requirement
Output vs Generator Requirement
Future Generator Requirement8 Generators
7 Generators
6 Generators
5 Generators
4 Generators
3 Generators
2 Generators
1 Generator
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
51
As such, when only throughput efficiency at the “as is” state is known, the
reserved capacity at the “as is” state and at the point when the system configuration
constrains the output is quantifiable.
Using the optimum configuration from experiment 4 (Table 17), this experiment
shows the manufacturing lead-time, WIP & arrival rate when the average throughput
efficiency increases from 4 to 12% (Figure 35).
For clarity these terms will be defined as;
Arrival rate is the mean number of hoists produced divided by the total hours
in 1 year (8760 hours)
Average lead-time is the total number of hours from barrel assembly in cells
1, 8 or 11 to dispatch at cell 10
WIP is the number of entities from barrel assembly in cells 1, 8 or 11 to
packing at cell 10
Figure 35 - Effect of Throughput Efficiency on Little’s Law
From analysis of Figure 35; the arrival rate is a linear response to throughput
efficiency until 9.2% TE, showing only external constraints are present up until this
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0
50
100
150
200
250
300
350
400
450
500
4% 5% 6% 7% 8% 9% 10% 11% 12%
Hoi
sts
/ hr
WIP
Qua
ntit
y H
ours
Avg Throughput Efficiency (%)
Effect of Throughput Efficiency on Littles Law Avg Wip
Avg Leadtime (hrs)
Avg Wasted Time (hrs)
Arrival Rate (Hoists/hr)
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 5 Verification and Validation
52
time. Between 9.2% and 10.2%, the system undergoes a transition from external to
system constraint. Albeit less noticeable in WIP; this transition phase affects both the
arrival rate and WIP responses in coincidence. Beyond 10.2% TE, no further
increase in the arrival rate is possible, yet WIP continues to reduce as lead-times
decay.
In experiment 4; the maximum output achieved 3890 hoists/year at an average
TE of 12.2%
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 6 Experimentation and Optimisation
53
Appendix 10), yet analysis of Figure 35 shows the same number of hoists
could be produced at a lower efficiency but with higher WIP levels.
The main advantage using this analysis is the ability to quantify the maximum arrival
rate and WIP for a given system when only throughput efficiency is known. If this is
combined with an efficiency improvement rate; the potential life of a system can be
ete ine not just by t e t eo etical ca acity but also at any oint f o t e “as is”
TE to the theoretical TE.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 7 Discussion
54
CHAPTER 7 DISCUSSION
The purpose of this project; to extend the life of the existing production
facilities through the ability to produce more from the same area, has proven
possible through simulation. Experimentation has shown the output can be
increased from 1590 to 3890 hoists/year (Figure 36) and longevity extended until
2022 using the same hours of operation. Under the approach adopted, the annual
output/m² of production floor space could rise from 3.28 to 7.42 hoists/m². This has
been achieved using an improved production line configuration and sufficient
availability in equipment, which permit throughput efficiency to increase from 5.1%
to 12.2%.
Figure 36 - Experiment Comparison (Dispatch QTY Vs Space Utilisation)
Whilst this is theoretically possible, no data has been available to quantify the
external constraints as the output increases. In experiment 1, these influences have
been observed to restrict the throughput efficiency via increasing the manufacturing
lead-time by an average of 20 hours/hoist. Going forward when there are clear
merits to reconfigure the line and invest in a 2nd generator, to improve flow and
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
1500
1750
2000
2250
2500
2750
3000
3250
3500
3750
4000
Existing System
Exp 1 -Max
Output
Exp 1 -Max
Output
Exp 2 - 1st Opt Conf
Exp 2 - 1st Opt Conf
Exp 3 -Investment
Exp 3 -Investment
Exp 4 - 2nd Opt Conf
Delayed Delayed No Delay Delayed No Delay Delayed No Delay No Delay
Ho
ists
Dis
pat
che
d /
m ²
Ho
ists
Dis
pat
che
d /
Ye
ar
ExperimentScenario
Experiment Comparison (Dispatch Quantity Vs Space Utilisation)QTY Dispatched
Hoists / m² of building
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 7 Discussion
55
reduce waiting time; the likelihood the changes will achieve full efficiency potential is
unclear.
In the worst case scenario when external constraints limit throughout
efficiency to exceed existing levels, an optimised production line could yield 1915
hoists/year, whilst the addition of a generator could increase this to 2293 hoists/
year. Despite delaying the requirement for further change until December 2014 or
November 2016 respectively, these solutions on’t come without cost implications.
In both cases, WIP and lead-times will increase (Figure 37). From a financial
perspective; these will tie-up extra working capital over a longer period thus
reducing the liquidity of the business (Gupta & Boyd, 2008). From an operations
perspective; these will congest the production line and potentially reduce on-time
delivery and customer goodwill (Yücesan & Groote, 2000), however no data is
available to verify or quantify lateness.
Figure 37 - Experiment Comparison (Lead-Time Vs WIP)
Clearly, the only viable way to grow the business within the same space
constraints is via a sustained improvement in throughput efficiency. To achieve 3890
50.0
55.0
60.0
65.0
70.0
75.0
80.0
85.0
90.0
95.0
100.0
6
7
8
9
10
11
12
13
14
15
16
Existing System
Exp 1 -Max
Output
Exp 1 -Max
Output
Exp 2 - 1st Opt Conf
Exp 2 - 1st Opt Conf
Exp 3 -Investment
Exp 3 -Investment
Exp 4 - 2nd Opt Conf
Delayed Delayed No Delay Delayed No Delay Delayed No Delay No Delay
WIP
Lead
-Tim
e (
Day
s)
ExperimentScenario
Experiment Comparison (Lead-time Vs WIP)Lead-Time (days)
WIP Quantity
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 7 Discussion
56
hoists/year, this represents a significant reduction in the lead-time. To put this into
context; a hoist with an average assembly time of 18.1 hours, needs to be
manufactured in an average lead-time of 6.2-days as opposed to 14.6-days
currently (Figure 37).
Even if the business increases throughput efficiency as experiment 4
demonstrates, other factors which influence cycle-time variations, could still threaten
system stability. Reduced redundant capacity and reliance on known efficiency
levels could yield the system susceptible to localised spikes in variation (Fearne &
Fowler, 2006). In the event of a series of defects; a short delay in dispatch will cause
WIP to build up significantly faster in the optimised model than the existing. Such
that a 2-day delay in experiment 4 causes all available floor space to be consumed,
in contrast the existing model could survive 6-days.
Evidently, limitation to analysis using discrete event simulation resides in the
extents of simulated model and data available to describe the state of the real
system. Given that delays other than waiting rate are known to occur, in the
absence of data to specify what the cause of the delay could be, a solution to
guarantee improved throughput efficiency using Witness is not possible. Whilst it is
argued, Lean needs simulation for analysis of complex systems (Standridge &
Marvel, 2006); the simulation needs tools, lean or otherwise to provide data. In this
instance, sufficient data was only available to allow the simulation to quantify the
effect of forced delays. Like the concept of the Hidden Factory (Kesting & Ulhø,
2010), this does show that improved performance is achievable if wastes are
removed.
With this concept in mind, an investigation outside of Witness has been
undertaken throughout July 2013 using Pareto Analysis, to identify why throughput
efficiency is lower that the simulation would suggest possible. By taking a headcount
of the reasons why WIP was not being processed, both the cause and frequency of
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 7 Discussion
57
delay are identified (Figure 38). To reflect meaningful problems seen by the
company, the cause of delays are categorised as;
Waiting in a queue
Waiting for In-house parts
Waiting for bought-In parts
Incorrect product planning (technical defects)
Waiting for people
Waiting for information
Figure 38 - Observed Delays
Conceding the fact that this investigation does not provide data suitable for
simulation, from a waste reduction point of view, it does allow management to
prioritise what to deal with first (Johnson, et al., 2010). Intriguingly and
unexpectedly, the number of delay occurrences for In-house made components is
double those for bought-In components. These findings suggest the company is its
own worst supplier in terms of the quantity of delays.
86
2722
13 10 7 60%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
60
70
80
90
100
Wai
ting
in
Que
ues
Wai
ting
for
In-
Hou
se P
arts
Inco
rrec
t Pl
anni
ng
Wai
ting
for
Boug
ht-In
Par
ts
Wai
ting
for
Peop
le
Wai
ting
for
Equi
pmen
t
Wai
ting
for
Info
rmat
ion
Num
ber
of D
elay
s Obs
erve
d
Delay Category
Instances of Delay
Delay Occurances
Cummulative Percentage
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 8 Future Work
58
CHAPTER 8 FUTURE WORK
The work undertaken in this project highlights a myriad of other opportunities
for further work to improve production output. It is believed that the following
recommendations are relevant to this project and have the potential to benefit a
wider audience at Street Crane Ltd.
8.1. Short-Term Capacity Planning
As opposed to optimising the production line to produce a higher production
output over the long-term, there is also potential benefit to focus the simulation
towards short-term production. Considering MRP systems are known to have
limitations regarding variations, queuing and complexity, (Byrne & Bakir, 1999)(Kim
& Kim, 2001) the use of dynamic simulation in conjunction could prove
advantageous (Al-Aomar, 2000).
At planning and control; the use of Witness could help to fine-tune the master
production schedule by illustrating the effect the actual schedule is likely to have.
This could be achieved by modifying the simulation developed in this project to input
hoists which reside on the order book, with experimentation designed to schedule
hoists into production in the best sequence. In this instance, Experimenter could not
just improve production flow (Melton, 2005) and resource utilisation but also on-time
delivery, which could be affected through a poor sequence of work.
After the publication of the production schedule, this simulation could then
facilitate sound decision making by production management when daily events
deviate from the planned schedule. In this application, the simulation should be
carefully designed to reduce the requirement for in-depth Witness knowledge of
users, who ultimately will use simulation as a support tool.
8.2. Inventory Scenarios
In reality, inventory also has a significant role in the production process
(Figure 38). The inclusion of inventory in the simulation, would provide an insight
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 8 Future Work
59
into how stocking levels affect the behaviour of the production line as sales volumes
increase or the product-mix alters (Kleijnen, 2005). These insights could include
determining an optimised stocking level of components (Petrovic, 2001), the space
required to store components and the effect storage space has on usable cell
space. Given that the MRP system can set stock levels based upon historical usage
and lead-time, it cannot allow for possible variation of products, delivery
performance variability or production size.
To optimise stock levels; the simulation will need linking to the bill of materials
for each hoist configuration and process stage, the existing stocking levels,
component lead-time and on-time delivery data. Using random number streams
governing product entry, confidence levels can be determined in the quantity of
specific parts held to prevent stock-outs and delays in output (Kleijnen, 2005). By
introducing a component size into the bill of materials, the required storage space
can also be determined as hoist volumes grow and stocking levels change. Should
additional storage space become a requirement, the effect on usable space and
production output can be quantified. The outcome of this work should facilitate
improved on-time delivery, reduced WIP and lower operational costs (Jammernegg
& Reiner, 2007).
8.3. Reduce Non-Value Activities
This project has only considered direct labour activities within the production
line; in reality operation requires indirect labour to service direct activities and
sustain output. Further work could therefore focus upon quantifying these non-value
added indirect activities to allow simulation and optimisation of the layout
configuration to reduce indirect labour costs. Specifically these activities stem from
transportation, motion and inventory issues, identified in the seven deadly wastes
(Ramaswamy, et al., 2002).
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 8 Future Work
60
The use of lean tools such as value stream mapping, process flow, time-value
or spaghetti diagrams could form a basis of this work to gather data to identify and
quantify waste (Melton, 2005). This information could then be used inside Witness to
optimise the production line by reducing the indirect workload without adverse effect
on the production output.
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 9 Conclusions
61
CHAPTER 9 CONCLUSIONS
Through the course of this work, it has been confirmed that it is possible to
extend the lifespan of the existing production line, although the duration and
practicality depend heavily on increased throughput efficiency. If influences outside
of this study constrain TE, an optimised configuration (Table 14) using 2 generators
could be expected to produce 2293 hoists/year sufficing sales levels until November
2016 (Figure 30). Unfortunately, as volumes increase, this scenario is at risk of
reduced on-time delivery performance (Figure 37). In contrast; if TE is improved, a
2nd optimised configuration (Figure 17) could increase the output to 3890 hoists/year
sufficing sales levels until April 2022 (Figure 32).
Mindful that future sales could be composed from a greater proportion of non-
UK electrical systems; analysis has shown the actual number of generators could
vary from 1 to 7 as sales increase (Figure 34). Using sales volumes verses
anticipated requirement, this analysis enables the exact requirement to be
determined to help prevent wasted investment or unforeseen overloading.
Albeit not part of this work, it is clear through observation the cycle-times are out-of-
balance between production cells (Figure 23). Whilst balancing can be achieved
using an optimum number of workstations, unless cycle-time/Takt-time equates to
an integer, cells will be unbalanced and require buffers or displacement of
operatives to balance load. Knowing unbalance could result in excessive WIP, under
utilisation of resources, quality defects and conflict (Simons & Zokaei, 2005); it is
recommended workload is redistributed.
Undeniably, the simulation developed could have been constructed in a
countless number of ways, yet through the course of this work; the use of Excel to
store and transfer data to and from Witness has proven advantageous. Code linking
the simulation to a spreadsheet has reduced the model size, the time to make
Tony Ponsonby Business Process Simulation of a Production Line
Chapter 9 Conclusions
62
changes and model complexity. In addition, Excel provides functionality beyond
Witness to analyse transient behaviour typical of initialisation.
Given that manual analysis proved useful for verification and rudimentary
understanding, for lengthy experiments it becomes burdensome. Instead, Witness
Experimenter for semi-automated experimentation and optimisation has shown to be
essential to understand how the production line can be improved within a large
number of possible scenarios.
The use of Experimenter in conjunction with Excel requires data to be
imported into a Witness variable at model initialisation, to allow Experimenter to alter
the variable at the start of each scenario. In contrast, data can be imported directly
into an action or rule without use of a Witness variable; whilst enabling faster
modelling, this does limit analysis to manual experimentation.
Similar to the Theory of Constraints (Goldratt, 1990) objective, Witness
Experimenter is able quantify at what point a variable becomes a constraint to the
object function. In being able to identify the weakest link, its influence on other
interdependent links, and how the link limits the goal of the system, one can answer
Theory of Constraint uestions “w at s oul be c an e ?” an “w at s oul it be
c an e to?”(Lepore & Cohen, 1999). Considering the stochastic nature and
general complexity the production line, undeniably this ability is both powerful and
desirable.
Tony Ponsonby Business Process Simulation of a Production Line
_ References
63
REFERENCES
Aguilar- a en, R. . (2004 ‘Business ocess o ellin : Re iew an f a ewo k.’
International Journal of Production Economics, 90(2) pp.129-149.
Al-Ao a , R. (2000 ‘P o uct Mix Analysis wit Disc ete E ent i ulation.’
Proceedings of the 2000 Winter Simulation Conference, Vol. 2. Orlando, Dec 2000.
pp.1385-1391
An ee a, N. (2012 ‘Lean Manufactu in Pe fo ance - Met ics an E aluation.’
XVIІI ННТКсмеждународноучастие, АДП .414-419.
An elis, J., Conti, R., Coo e , C. & Gill, C. (2011 ‘Buil in a i -commitment lean
cultu e.’ Journal of Manufacturing Technology Management,22(5) pp.569-586.
Bolden, R., Waterson, P., Warr, P., Clegg, C., Wall, T. (1997 ‘A New axono y of
Mo e n Manufactu in P actices.’ Journal of Operations & Production Management,
17(11) pp.1112-1130.
By ne, M. D. & Baki , M. A. (1999 . ‘P o uction lannin usin a yb i si ulation -
analytical a oac .’ International Journal of Production Economics, 59(1-3) pp.305-
311.
C a an, C. D. (2005 ‘Clean House Wit Lean 5 .’ Quality Progress, 38(6) pp. 27-
32.
Cuatrecasas-Arbos, L., Fortuny-Santos, J. & Vintro- anc ez, C. (2011 ‘ e
Operations-Time Chart: A graphical tool to evaluate the performance of production
syste s.’ Co ute s & In ust ial En inee in , 61(3 .663-675.
Extendsim.com (2012) Simulation Software Overview [Online]
[Accessed on 16th November 2012]
https://www.extendsim.com/sols_simoverview.html#continuous
Fearne, A. & owle , N. (2006 ‘Efficiency e sus effecti eness in const uction
su ly c ains: t e an e s of “lean” t inkin in isolation.’ Supply Chain
Management: An International Journal,11(4) pp.283-287.
Go , . J. & Mott, J. R. A. (1993 ‘Int o uction to i ulation.’ Proceedings of the
1993 Winter Simulation Conference, pp.9-17.
Goldratt, E. M. (1990) What is this Thing Called Theory of Constraints and how
should it be Implemented?. Croton-on-Hudson, NY: North River Press.
Tony Ponsonby Process Simulation of A Production Line
_ References
64
G easley, A. (2003 ‘Usin business-process simulation within a business-process
een inee in a oac .’ Business Process Management Journal, 9(4) pp.408-420.
Gu ta, M. C. & Boy , L. H. (2008 ‘ eo y of const aints: a t eo y fo o e ations
ana e ent.’ International Journal of Operations & Production Management,
28(10) pp.991-1012.
Hammer, M. & Champy, J. (2009) Reengineering The Corporation: A Manifesto for
Business Revolution. New York: HarperCollins.
Hicks, B. J. (2007 ‘Lean info ation ana e ent: Un e stan in an eli inating
waste.’ International Journal of Information Management, 27(4) pp.233-249.
highpeak.gov (2012) Planning Application Details [Online]
[Accessed on 1st December 2012].
http://planning.highpeak.gov.uk/portal/servlets/ApplicationSearchServlet?PKID=124
196
Hlu ic, V. & Robinson, . (1998 ‘Business P ocess Mo ellin an Analysis Usin
Disc ete E ent i ulation.’ Proceedings of the 1998 Winter Simulation Conference,
Medeiros, D. J., Watson E.F., Carson, J.S. and Manivannan M.S. Piscataway, NJ
pp.1363-1369.
Host, M,. Re nell, B,. Da , J N,. Ne sta , J an Nybe , C. (2001 ‘Ex lo in
bottlenecks in market-driven requirements management processes with discrete
e ent si ulation.’ Journal of Systems and Software, 59(3) pp.323-332.
Jammernegg, W. & Reiner, G. (2007 ‘Pe fo ance i o e ent of su ly c ain
ocesses by coo inate in ento y an ca acity ana e ent.’ International
Journal of Production Economics, 108(1-2) pp.183-190.
Johnson, C. D., Miranda, R., Aakre, K. T., Roberts, C. C., Patel, M. D and Krecke,
K. N. (2010 ‘P ocess I o e ent: W at Is It, W y Is It I o tant an How Is It
Done?’ American Journal of Roentgenology, 194(2) pp.461-468.
Kelton, D., Sadowski, R. P. & Sadowski, D. A. (2002) Simulation With Arena. 2nd
Edition ed. New York: Mcgraw-Hill.
Kestin , P. & Ul ø, J. P. (2010 ‘E loyee-driven innovation: extending the license
to foste inno ation.’ Management Decision, 48 (1) pp.65-84.
Ki , B. & Ki , . (2001 ‘Exten e o el fo a yb i o uction lannin
a oac .’ International Journal for Production Economics , 73(2) pp.165-173.
Tony Ponsonby Process Simulation of A Production Line
_ References
65
Kleijnen, J. P. C. (2005 ‘ u ly C ain i ulation ools an ec ni ues: A u ey.’
International Journal of Simulation and Process Modelling, 1(1) pp.82-89.
Ku a , . (2007 ‘A ofit an loss analysis fo ake-to-order versus make-to-stock
policy-a su ly c ain case stu y.’ The Engineering Economist, 52(2) pp.141-156.
Lanner.com. (2012) Simulation and Simulation Software Explained [Online]
[Accessed on 1st December 2012] http://www.lanner.com/en/simulation-
explained.cfm
Lanner. (2012) Witness-On-Line-Help System, Witness (Release 13.00)
Law, A. M. (2007) Simulation and modeling Analysis. 4th Edition ed. New York:
McGraw Hill.
Lepore, D. & Cohen, O. (1999) The Theory of Constraints and the System of
Profound Knowledge. Great Barrington, MA: North River Press.
Little, J. D. C. & Graves, S. C. (2008) Building Intuition: Insights from Basic
Operations Management Models and Principles. New York: Springer Science.
Ma ajan, P. . & In alls, R. G. (2004 ‘E aluation et o s use to etect wa -up
e io in stea y state si ulation.’ Proceedings of the 2004 Winter Simulation
Conference, Vol.1. Dec 2004. pp.663-671.
Ma kt, P. L. & Maye , M. H. (1997 ‘Witness i ulation Software - a Flexible Suite of
i ulation ools.’ Proceedings of the 1997 Winter Simulation Conference, Dec
1997. pp.711-717.
Mat u , A., Dan ayac , G. ., Mittal, M. L. & a a, M. K. (2011 ‘Pe fo ance
Measu e ent in Auto ate Manufactu in .’ Measuring Business Excellence, 15(1)
pp.78-91.
Mathwave. (2010) EasyFitXL Help Menu, EasyFitXL, Version 5.5 (Released
03/12/2012)
Me ta, A. (2000 ‘ a t Mo elin - Basic Met o olo y an A ance ools.’
Proceedings of the 2000 Winter Simulation Conference, Vol.1. pp.241-245.
Melton, . (2005 ‘ e Benefits of Lean Manufactu in : W at Lean inkin as to
ffe t e P ocess In ust ies.’ Chemical Engineering Research and Design, 83(6)
pp.662-673.
Tony Ponsonby Process Simulation of A Production Line
_ References
66
Mut ia , K. M. N. & Huan , . H. (2007 ‘ e all t ou ut effecti eness (OTE)
metric for factory-le el e fo ance onito in an bottleneck etection.’
International Journal of Production Research, 36(20) pp.4753-4769.
Öz ün, . & Ba las, Y. (2009 ‘Disc ete s. Continuous i ulation: W en Does It
Matte ?’ Proceedings of the 27th International Conference of The System Dynamics
Society, pp.1-22.
Pet o ic, D. (2001 ‘ i ulation of su ly c ain be a iou an e fo ance in an
unce tain en i on ent.’ International Journal of Production Economics, 71(1-3)
pp.429-438.
Qu, P., kinne , G. E. & Mason, . J. (2001 ‘ izin a P o uction Line Usin
i ulation.’ Proceedings of the 33nd conference on Winter simulation, pp.1188-
1193.
Ra aswa y, N. R., ella u ai, V. & Gunaseka an, A. (2002 ‘Just-in-time
implementation in small and mediu ente ises.’ International Journal of
Productivity and Performance Management, 51(2) pp.85-90.
Sanderson.com (2012) Unity ERP - Master Production Scheduling and MRP
[Online] [Accessed on 1st December 2012]
http://www.sanderson.com/sanim/MasterProductionSchedulingMaterialRequirement
Planning,10,4,797,1.html
a ent, R. G. (2010 ‘Ve ification an Vali ation of i ulation Mo els.’
Proceedings of the 2010 Winter Simulation Conference, pp.166-183.
i ons, D. & Zokaei, K. (2005 ‘A lication of lean a a i m in red meat
ocessin ’. British Food Journal, 107(4), pp.192-211.
tan i e, C. R. & Ma el, J. H. (2006 ‘W y Lean Nee s i ulation.’ Proceedings
of the 2006 Winter Simulation Conference, pp.1907-1913.
weeney, M. . & zwejczewski, M. (1996 ‘Manufacturing Strategy and
Pe fo ance.’ International Journal of Operations and Production Management,
16(5) pp.25-40.
ja jono, B. & e nán ez, R. (2008 ‘P actical a oac to ex e i entation in a
si ulation stu y’. Proceedings of the 2008 Winter Simulation Conference, pp.1981-
1988.
Yücesan, E. & G oote, X. (2000 ‘Lea ti es, o e elease ec anis s, an
custo e se ice.’ European Journal of Operational Research, 120(1) pp.118-130.
Tony Ponsonby Business Process Simulation of a Production Line
_ Bibliography
67
BIBLIOGRAPHY
Ál a ez, R., Cal o, R., Peña, M. M. & Do in o, R. (2009 ‘Re esi nin an
asse bly line t ou lean anufactu in tools’. International Journal of Advanced
Manufacturing Technology, 43(9-10) pp.949-958.
Kingsman, B. G. (2000 ‘Mo ellin in ut-output workload control for
yna ic ca acity lannin in o uction lannin syste s.’ International
Journal of Production Economics, 68(1) pp.73-93.
Ku a a, . & Nottesta a, D. A. (2006 ‘Inte ate i ulation A lication
Design For Short- e P o uction c e ulin .’ IIE Transactions, 38(9)
pp.737-748.
Robinson, . (2007 . ‘A statistical ocess cont ol a oac to selectin a wa -up
period for a discrete-e ent si ulation’, European Journal of Operational Research,
176 (1) pp.332-346.
o as, A. & C a entie , P. (2005 ‘Re ucin i ulation Mo els o
c e ulin Manufactu in acilities.’ European Journal of Operational
Research, 161(1) pp.111-125.
u ay, K. (1995 . ‘Business P ocess i ulation’. Proceedings of the 1995 Winter
Simulation Conference, Dec 10. pp.55-60.
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________ Appendix1
68
APPENDIX 1- SAMPLE DATA USED TO ESTABLISH CYCLE TIMES
Job
Number
Part
Number Op Description
First
Labour
Last
Labour Completed
Actual
Hours
28,746.94
A73709 836-00783 ZX064-3FoLM5K052-CRB09A1-40050 13/07/2010 10.09
836-00783 BARREL ASSY 22 Jun 10 23 Jun 10 2.67
836-00783 ZX FRAME ASSY 23 Jun 10 23 Jun 10 1.67
836-00783 CABLE ROUTING 13 Jul 10 13 Jul 10 0
836-00783 LINE PULL TEST 13 Jul 10 13 Jul 10 0
836-00783 ROPE UP BTM BLK 24 Jun 10 30 Jun 10 2
836-00783 END LINE TEST 30 Jun 10 30 Jun 10 1
836-00783 CRAB ASSY 10 Jul 10 13 Jul 10 2.75
836-00783 PACKING 13 Jul 10 13 Jul 10 0
A73710 836-00783 ZX064-3FoLM5K052-CRB09A1-40050 13/07/2010 12.59
836-00783 BARREL ASSY 22 Jun 10 23 Jun 10 2.67
836-00783 ZX FRAME ASSY 23 Jun 10 23 Jun 10 1.67
836-00783 CABLE ROUTING 24 Jun 10 24 Jun 10 2.5
836-00783 LINE PULL TEST 01 Jul 10 01 Jul 10 0.5
836-00783 ROPE UP BTM BLK 01 Jul 10 01 Jul 10 1
836-00783 END LINE TEST 02 Jul 10 02 Jul 10 1.5
836-00783 CRAB ASSY 10 Jul 10 13 Jul 10 2.75
836-00783 PACKING 13 Jul 10 13 Jul 10 0
A69957 836-00879 ZX064-3SONM4K031-LHR0002-40050 10/02/2010 10.68
836-00879 BARREL ASSY 01 Feb 10 01 Feb 10 1.59
836-00879 ZX FRAME ASSY 02 Feb 10 03 Feb 10 2
836-00879 TROLLEY ASSY 1 04 Feb 10 04 Feb 10 1
836-00879 TROL ASSY 2/3 04 Feb 10 05 Feb 10 1.09
836-00879 CABLE ROUTING 08 Feb 10 08 Feb 10 1.5
836-00879 LINE PULL TEST 08 Feb 10 08 Feb 10 0.5
836-00879 ROPE UP BTM BLK 08 Feb 10 08 Feb 10 1
836-00879 END LINE TEST 08 Feb 10 10 Feb 10 2
836-00879 PACKING 10 Feb 10 10 Feb 10 0
A70800 836-00879 ZX064-3SONM4K031-LHR0002-40050 24/02/2010 11.75
836-00879 BARREL ASSY 19 Feb 10 19 Feb 10 1.5
836-00879 ZX FRAME ASSY 19 Feb 10 19 Feb 10 2.5
836-00879 TROLLEY ASSY 1 22 Feb 10 22 Feb 10 1
836-00879 TROL ASSY 2/3 22 Feb 10 22 Feb 10 1
836-00879 CABLE ROUTING 23 Feb 10 23 Feb 10 2.75
836-00879 LINE PULL TEST 24 Feb 10 24 Feb 10 0.5
836-00879 ROPE UP BTM BLK 24 Feb 10 24 Feb 10 0.5
836-00879 END LINE TEST 24 Feb 10 24 Feb 10 2
836-00879 PACKING 24 Feb 10 24 Feb 10 0
A70080 836-00903 ZX064-3SoNM5K041-LHR0002-40050 10/02/2010 10.17
836-00903 BARREL ASSY 01 Feb 10 01 Feb 10 1.67
836-00903 ZX FRAME ASSY 02 Feb 10 02 Feb 10 2
836-00903 TROLLEY ASSY 1 04 Feb 10 04 Feb 10 1
836-00903 TROL ASSY 2/3 04 Feb 10 04 Feb 10 1
836-00903 CABLE ROUTING 05 Feb 10 05 Feb 10 1.5
836-00903 LINE PULL TEST 08 Feb 10 08 Feb 10 0.5
836-00903 ROPE UP BTM BLK 08 Feb 10 08 Feb 10 0.5
836-00903 END LINE TEST 08 Feb 10 08 Feb 10 2
836-00903 PACKING 10 Feb 10 10 Feb 10 0
A70882 836-00903 ZX064-3SoNM5K041-LHR0002-40050 05/03/2010 10.85
836-00903 BARREL ASSY 26 Feb 10 26 Feb 10 1.5
836-00903 ZX FRAME ASSY 01 Mar 10 01 Mar 10 1.5
836-00903 TROLLEY ASSY 1 01 Mar 10 01 Mar 10 1
836-00903 TROL ASSY 2/3 01 Mar 10 01 Mar 10 0.92
836-00903 CABLE ROUTING 01 Mar 10 01 Mar 10 1.59
836-00903 LINE PULL TEST 03 Mar 10 03 Mar 10 0.5
836-00903 ROPE UP BTM BLK 03 Mar 10 03 Mar 10 1
836-00903 END LINE TEST 04 Mar 10 05 Mar 10 2
836-00903 PACKING 04 Mar 10 05 Mar 10 0.84
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 2
69
APPENDIX 2 - STREET CRANE CYCLE TIME DISTRIBUTION
Figure 39 - Summary Sheet Of Distribution Data Sampling
Description Distribution Type
Hoist Type Where
Distribution Is Used
Cell Where
Distribution Is
Used
ZX10 En of Line est – All Burr ZX10 - All models 9
ZX10 Wire & Test - DT Gamma ZX10 DT 11
ZX10 Wire & Test – SS & ST Kumaraswamy ZX10 SS & ST 11
ZX10 Assembly – DT Burr ZX10 DT 11
ZX10 Assembly – SS & ST Inverse Gaussian ZX10 SS & ST 11
ZX8 Barrel Assembly Time – ZX8 CRB & FM Burr ZX8 CRB & FM 1,8 or 11
ZX8 Barrel Assembly Time – LHR General Extreme ZX8 LHR 1,8 or 11
ZX8 Frame Assembly Time – All 2/4 Fall Wakeby ZX8 All 2/4 Fall 3 or 8
ZX8 Frame Assembly Time – All 6/8 Fall Burr ZX8 All 6/8 Fall 11
ZX8 Trolley Assembly Time – LHR Log Logistic ZX8 LHR 2/4 Fall 4
ZX8 Trolley Assembly 2/3 Time – LHR Log Logistic ZX8 LHR 2/4 Fall 5
ZX8 Cable routing Time – CRB 2/4 Fall Inverse Gaussian ZX8 CRB 2/4 Fall 6
ZX8 Cable routing Time – CRB 6/8 Fall Log Logistic ZX8 CRB 6/8 Fall 11
ZX8 Cable routing Time – FM Generalised Pareto ZX8 FM 6 or 11
ZX8 Cable routing Time – LHR 2/4 Fall Burr ZX8 LHR 2/4 Fall 6
ZX8 Cable routing Time – LHR 6/8 Fall Fatigue Life ZX8 LHR 6/8 Fall 11
ZX8 Line Pull Test Time – All Log Pearson ZX8 - All models 7
ZX8 Rope-up Time – All 2 Fall General Gamma ZX8 - All 2 Fall models 7
ZX8 Rope-up Time – All 4 Fall Burr ZX8 - All 4 Fall models 7
ZX8 Rope-up Time – All 6 Fall Wakeby ZX8 - All 6 Fall models 6 or 11
ZX8 Rope-up Time – All 8 Fall Log Logistic ZX8 - All 8 Fall models 6 or 11
ZX8 End of Line Test Time – All Gamma ZX8 - All models 9
ZX8 Packing Time – All General Extreme ZX8 - All models 10
ZX8 Crab Assembly Time – CRB All Falls Wakeby ZX8 CRB All Falls 8 or 11
ZX8 Crab Assembly Time – LHR 6/8 Fall Burr ZX8 LHR 6/8 Fall 11
ZX6 Barrel Assembly Time – All General logistic ZX6 All Models 1 or 8
ZX6 Frame Assembly Time – All General Extreme ZX6 All Models 3 or 8
ZX6 Trolley Assembly Time – LHR Log Logistic ZX6 LHR 4
ZX6 Trolley Assembly 2/3 Time – LHR Log Pearson ZX6 LHR 5
ZX6 Cable Routing Time – LHR Burr ZX6 LHR 6
ZX6 Cable Routing Time – CRB Log Logistic ZX6 CRB 6
ZX6 Cable Routing Time – FM Burr ZX6 FM 6
ZX6 Line Pull Test Time – All Rice ZX6 All Models 7
ZX6 Rope-up Time – All Burr ZX6 All Models 7
ZX6 End of Line Test Time – All General Extreme ZX6 All Models 9
ZX6 Crab Assembly Time – All Johnson SB ZX6 All Models 8
ZX6 Packing Time – All Pearson 5 ZX6 All Models 10
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 3
70
APPENDIX 3 - CYCLE-TIME DISTRIBUTIONS
ZX10 End of line test - all variants
Figure 40 - PDF for all variants of ZX10 on End of Line Test
ZX10 Wire & test - DT
Figure 41 - PDF for DT variants of ZX10 on Wire and Test
ZX10 Wire & test - SS & ST
Figure 42 - PDF for SS & ST variants of ZX10 on Wire and Test
ZX10 End of Line Test - All Variants
Histogram Burr
Cycle time (hrs)
765432
f(x)
0.52
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Burr k = 1.08147 α 4.534334 β 3.505067 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank 2 Burr 0.1347304 1 0.4329841 10 1.762955 21
25 Gumbel Max 0.1411854 2 0.4121944 5 1.820167 27 40 Lognormal 0.1428626 3 0.4250525 8 1.801488 25
ZX10 Wire & Test - DT
Histogram Gamma (3P)
Cycle time (hrs)
3632282420161284
f(x)
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Distribution – Gamma α = 0.7591906 β 11.22939 γ = 2.5 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank 19 Gamma (3P) 0.1071618 1 7.548347 45 N/A 23 Gen. Pareto 0.1086214 2 0.4170786 2 0.2680201 2 29 Johnson SB 0.1104032 3 0.3838761 1 1.085856 5
ZX10 Wire & Test - SS & ST
Histogram Kumaraswamy
Cycle time (hrs)
252015105
f(x)
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Kumaraswamy α1 = 1.206512 α2 = 222.266 a = 0.7219992 b = 580.5437 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank 31 Kumaraswamy 0.0692777 1 0.5915563 1 6.950295 10 58 Weibull (3P) 0.0696535 2 0.5930856 2 6.952396 11 23 Gen. Gamma (4P) 0.0697532 3 0.5934718 3 6.952486 12
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
71
ZX10 Assembly - DT
Figure 43 - PDF for DT variants of ZX10 on Assembly
ZX10 Assembly - SS & ST
Figure 44 - PDF for SS & ST variants of ZX10 on Assembly
ZX8 Barrel assembly time - CRB & FM variants
Figure 45 - PDF for CRB & FM variants of ZX8 on Barrel Assembly
ZX10 Assembly - DT
Histogram Burr
Cycle time (hrs)
4035302520
f(x)
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Distribution – Burr k = 0.517107 α 13.73048 β 22.88117 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
2 Burr 0.079528 1 0.1944329 1 1.089862 18
37 Log-Logistic (3P) 0.081613 2 0.2041672 2 1.10868 20
3 Burr (4P) 0.0818452 3 0.2056219 3 1.108064 19
ZX10 Assembly - SS & ST
Histogram Inv. Gaussian
Cycle time (hrs)
5040302010
f(x)
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Inverse Gaussian λ = 248.8677 μ = 19.88852
# Distribution Kolmogorov Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
28 Inv. Gaussian 0.0481849 1 0.3791777 14 2.687003 16
53 Rayleigh (2P) 0.0490625 2 0.4105187 19 1.790949 8
15 Fatigue Life 0.0505466 3 0.341572 2 1.484754 7
ZX8 Barrel Assembly Time - CRB & FM Variants
Histogram Burr (4P)
Cycle time (hrs)
12108642
f(x)
0.5
0.4
0.3
0.2
0.1
0
Distribution – Burr k = 0.5280175 σ 10.77693 β 4.669118 γ -2.146674
# Distribution Kolmogorov
Smirnov
Anderson
Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
3 Burr (4P) 0.1074594 1 3.554914 1 50.23415 1
37 Log-Logistic (3P) 0.1077604 2 3.976809 4 65.63102 4
2 Burr 0.1079956 3 3.950913 2 65.69478 6
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
72
ZX8 Barrel assembly time - LHR
Figure 46 - PDF for LHR variants of ZX8 on Barrel Assembly
ZX8 Frame assembly time - CRB & FM 2/4 falls
Figure 47 - PDF for CRB & FM 2/4 Fall variants of ZX8 on Frame Assembly
ZX8 Frame assembly time - 6/8 fall all variants
Figure 48 - PDF for 6/8 Fall variants of ZX8 on Frame Assembly
ZX8 Barrel Assembly Time - LHR & LHC
Histogram Gen. Extreme Value
Cycle time (hrs)
121086420
f(x)
0.8
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – General Extreme k = 0.2397529 δ 0.3778651 μ 1.669713 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
21 Gen. Extreme Value 0.1201122 1 32.61526 21 N/A
2 Burr 0.1347907 2 9.304144 2 382.8457 2
3 Burr (4P) 0.1377839 3 9.249433 1 377.1777 1
ZX8 Frame Assembly Time - All Variants
Histogram Wakeby
Cycle time (hrs)
2015105
f(x)
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Wakeby α = 278.4285 β = 83.92139 γ 1.391011 δ 0.1258894 ζ -1.116262
# DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
60 WAKEBY 0.0700419 1 11.33769 3 N/A
3 BURR (4P) 0.0777804 2 6.865691 1 133.2115 2
2 BURR 0.0813036 3 8.858123 2 130.3759 1
ZX8 Frame Assembly Time - 6/8 Fall Variants
Histogram Burr
Cycle time (hrs)
141210864
f(x)
0.28
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Distribution – Burr k = 496.8598 α = 5.743046 β = 34.4693 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
2 BURR 0.0471006 1 0.5438014 4 8.804365 1
21 GEN. EXTREME VALUE 0.0507058 2 0.6432017 7 14.74508 20
31 JOHNSON SU 0.0544405 3 0.4967668 1 13.85122 13
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
73
ZX8 Trolley assembly time - LHR
Figure 49 - PDF for LHR variants of ZX8 on Trolley Assembly
ZX8 Trolley assembly 2/3 time - LHR
Figure 50 - PDF for LHR variants of ZX8 on Trolley Assembly 2/3
ZX8 Cable routing time - CRB 2/4 Fall
Figure 51 - PDF for CRB 2/4 Fall variants of ZX8 on Cable Routing
ZX8 Trolley Assembly Time - LHR 2/4 Fall Variants
Histogram Log-Logistic (3P)
Cycle time (hrs)
543210
f(x)
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Log-Logistic α = 4.812424 β 0.6778694 γ 0.1972457 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
34 Log-Logistic (3P) 0.1549023 1 22.44336 4 842.7591 11
6 Dagum (4P) 0.1575338 2 22.3139 3 843.7098 12
3 Burr (4P) 0.1598991 3 21.87751 1 848.6234 14
ZX8 Trolley Assembly 2/3 Time - LHC / LHR
Histogram Log-Logistic (3P)
Cycle time (hrs)
1086420
f(x)
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
Distribution – Log-Logistic α = 4.135496 β 0.8182648 γ 0.1514899 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
35 Log-Logistic (3P) 0.1428849 1 16.09746 5 617.5289 8
20 Gen. Extreme Value 0.1460525 2 20.45221 13 618.8348 10
6 Dagum 0.1487524 3 15.6568 2 617.496 6
ZX8 Trolley Assembly 2/3 Time - LHC / LHR
Histogram Inv. Gaussian
Cycle time (hrs)
2520151050
f(x)
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Distribution - Inverse Gaussian λ = 6.96671 μ 4.405886 # Distribution Kolmogorov
Smirnov
Anderson Darling
Chi-Squared
Statistic Rank Statistic Rank Statistic Rank
28 Inv. Gaussian 0.07598 1 0.6281517 15 4.32158 1
40 Lognormal (3P) 0.0774355 2 0.5433269 11 6.909811 9
29 Inv. Gaussian (3P) 0.0777099 3 0.6091184 14 7.946264 13
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
74
ZX8 Cable routing time - CRB 6/8 falls
Figure 52 - PDF for CRB 6/8 Fall variants of ZX8 on Cable Routing
ZX8 Cable routing time - FM
Figure 53 - PDF for FM variants of ZX8 on Cable Routing
ZX8 Cable routing time - LHR 2/4 falls
Figure 54 - PDF for LHR 2/4 Fall variants of ZX8 on Cable Routing
ZX8 Cable routing Time - CRB 6/8 Fall
Histogram Log-Logistic (3P)
Cycle time (hrs)
12108642
f(x)
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Log-Logistic α = 5.243512 β 9.09024 γ -3.451846 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
36 LOG-LOGISTIC (3P) 0.0601989 1 0.282607 9 3.886376 5
7 DAGUM 0.0702104 2 0.2504889 1 6.880988 14
8 DAGUM (4P) 0.0710318 3 0.2528404 2 8.084905 26
ZX8 Cable routing Time - FM
Histogram Gen. Pareto
Cycle time (hrs)
121110987654321
f(x)
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Generalised Pareto k = -0.3291256 σ 5.223236 μ 0.8931126 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
24 GEN. PARETO 0.0730794 1 0.2020629 2 1.68992 25
30 JOHNSON SB 0.0739067 2 0.1846372 1 0.7024844 6
38 LOG-PEARSON 3 0.094907 3 0.2827201 3 0.9205102 9
ZX8 Frame Assembly Time - LHR 6/8 Fall Variants
Histogram Burr (4P)
Cycle time (hrs)
161412108642
f(x)
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Distribution – Burr k = 0.4092073 α 9.503123 β 4.464578 γ -2.098865 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
3 BURR (4P) 0.0503108 1 1.79384 1 33.15232 3
2 BURR 0.0556799 2 2.105094 2 31.33453 1
7 DAGUM 0.0587015 3 2.97295 4 64.88283 5
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
75
ZX8 Cable routing time - LHR 6/8 falls
Figure 55 - PDF for LHR 6/8 Fall variants of ZX8 on Cable Routing
ZX8 Line pull test time - all variants
Figure 56 - PDF for all variants of ZX8 on Line Pull Test
ZX8 Rope-up time - all 2 fall variants
Figure 57 - PDF for all 2 fall variants of ZX8 on Rope-up
ZX8 Cable routing Time - LHR / LHC 6/8 Fall
Histogram Fatigue Life (3P)
Cycle time (hrs)
108642
f(x)
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Fatigue Life Distribution α = 0.007506 β 307.9398 γ = -301.0421 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
16 FATIGUE LIFE (3P) 0.1078151 1 0.2531651 11 0.0739317 8
29 INV. GAUSSIAN (3P) 0.1081493 2 0.2476341 10 0.0682815 5
39 LOGISTIC 0.1091111 3 0.2669197 15 0.8406902 40
ZX8 Line Pull Test Time - All Variants
Histogram Log-Pearson 3
Cycle time (hrs)
6543210
f(x)
1.1
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
Distribution – Log-Pearson 3 Parameter α = 1.969122 β 0.2518998 γ -0.9536435 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
34 LOG-PEARSON 3 0.2650797 1 167.5913 39 N/A
14 FRECHET 0.2674476 2 84.79278 1 1185.382 2
38 NORMAL 0.270496 3 142.9538 35 3542.422 38
ZX8 Rope-Up Time - 2 Fall Variants
Histogram Gen. Gamma
Cycle time (hrs)
108642
f(x)
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – General Gamma k = 0.9778099 δ 3.025703 μ 1.387396 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
21 GEN. EXTREME VALUE 0.0505771 1 0.1603543 4 4.238572 15
40 LOGNORMAL (3P) 0.0529645 2 0.1742001 8 4.561529 21
45 PEARSON 5 (3P) 0.0531989 3 0.1588757 3 4.197518 14
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
76
ZX8 Rope-up time - all 4 fall variants
Figure 58 - PDF for all 4 fall variants of ZX8 on Rope-up
ZX8 Rope-up time - all 6 fall variants
Figure 59 - PDF for all 6 fall variants of ZX8 on Rope-up
ZX8 Rope-up time - all 8 fall variants
Figure 60 - PDF for all 8 fall variants of ZX8 on Rope-up
ZX8 Rope-Up Time - 4 Fall Variants
Histogram Burr (4P)
Cycle time (hrs)
161412108642
f(x)
0.6
0.56
0.52
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Burr k = 0.4068347 α 10.55279 β 4.890327 γ -2.56326 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
3 BURR (4P) 0.0477191 1 1.767108 1 60.80933 4
2 BURR 0.0523837 2 2.062476 2 52.41425 1
7 DAGUM 0.0554853 3 2.956326 4 60.82049 5
ZX8 Rope-Up Time - 4 Fall Variants
Histogram Wakeby
Cycle time (hrs)
108642
f(x)
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Distribution – Wakeby α = 54.26124 β 31.997 γ 7.465259 δ 0.7871496 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
61 WAKEBY 0.0610328 1 0.1362901 1 1.384995 22
31 JOHNSON SB 0.0631668 2 0.2188883 4 1.737394 24
38 LOG-PEARSON 3 0.0635461 3 0.2139905 3 1.142141 16
ZX8 Rope-Up Time - 8 Fall Variants
Histogram Log-Logistic (3P)
Cycle time (hrs)
12108642
f(x)
0.3
0.28
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Distribution – Log-Logistic α = 9.178967 β 14.59555 γ = 8.819733 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
37 LOG-LOGISTIC (3P) 0.0569572 1 0.3112037 5 7.368598 35
24 GEN. LOGISTIC 0.0593257 2 0.3235013 11 6.126104 24
61 WAKEBY 0.0640833 3 0.2639663 1 6.920481 32
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
77
ZX8 End of line test time - all variants
Figure 61 - PDF for all variants of ZX8 on End-of-Line Test
ZX8 Packing time - all variants
Figure 62 - PDF for all variants of ZX8 on Packing
ZX8 Crab assembly time - CRB all variants
Figure 63 - PDF for CRB 2/4 fall variants of ZX8 on Crab Assembly
ZX8 End of Line Test Time - All Variants
Histogram Gamma
Cycle time (hrs)
987654321
f(x)
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Distribution – Fatigue Life Distribution α = 5.856415 β 0.396903 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
19 GAMMA 0.1876646 1 84.2315 24 1924.812 30
26 GUMBEL MAX 0.1901087 2 73.96984 17 1879.493 25
40 LOGNORMAL 0.1904525 3 64.5147 9 1836.516 19
ZX8 Packing Time - All Variants
Histogram Gen. Extreme Value
Cycle time (hrs)
252015105
f(x)
1.6
1.4
1.2
1
0.8
0.6
0.4
0.2
0
Distribution – General Extreme k = 0.3637871 δ 0.332108 μ 1.108131 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
21 GEN. EXTREME VALUE 0.1764511 1 44.30887 11 1533.681 19
8 DAGUM (4P) 0.1776 2 38.65548 4 1479.531 4
15 FATIGUE LIFE 0.1779939 3 58.53319 19 1522.193 17
ZX8 Crab Assembly Time - All Variants
Histogram Wakeby
Cycle time (hrs)
108642
f(x)
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Wakeby α = 30.1711 β = 9.185647 γ = 0.7287804 δ = 0.2093373 ζ = -0.3216961
# DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
61 WAKEBY 0.1249245 1 3.451145 1 134.5576 2
4 CAUCHY 0.1275343 2 4.405837 2 51.5366 1
37 LOG-LOGISTIC (3P) 0.140773 3 8.723243 7 194.8182 20
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
78
ZX8 Crab assembly time - LHR 6/8 fall variants
Figure 64 - PDF for LHR 6/8 fall variants of ZX8 on Crab Assembly
ZX6 Barrel assembly time - all variants
Figure 65 - PDF for All variants of ZX6 on Barrel Assembly
ZX6 Frame assembly time - all variants
Figure 66 - PDF for All variants of ZX6 on Frame Assembly
ZX8 Crab Assembly Time - LHR Variants
Histogram Cauchy
Cycle time (hrs)
8.887.26.45.64.843.2
f(x)
0.56
0.52
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Cauchy σ 0.5177225 μ 5.060881 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
4 CAUCHY 0.1843189 1 0.4587954 1 0.2806318 15
33 LAPLACE 0.1850915 2 0.492071 2 3.123549 49
11 ERROR 0.1854464 3 0.4961597 3 3.123531 48
ZX6 Barrel Assembly Time - All Variants
Histogram Gen. Logistic
Cycle time (hrs)
6.45.64.843.22.41.60.8
f(x)
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – General Logistic k = 0.3529654 σ = 0.2685148 μ = 1.423823 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
24 GEN. LOGISTIC 0.133047 1 141.5019 36 N/A
2 BURR 0.1345875 2 25.78711 2 1038.536 4
60 WAKEBY 0.1358823 3 24.79037 1 1338.58 9
ZX6 Frame Assembly Time - All Variants
Histogram Gen. Extreme Value
Cycle time (hrs)
12108642
f(x)
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – General Extreme k = 0.3023477 α 0.5467881 β 1.88475 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
21 GEN. EXTREME VALUE 0.0762871 1 36.94412 6 N/A
2 BURR 0.0770891 2 10.38397 2 526.4907 12
3 BURR (4P) 0.0778827 3 9.752139 1 503.5971 11
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
79
ZX6 Trolley assembly time - LHR
Figure 67 - PDF for LHR variants of ZX6 on Trolley Assembly 1
ZX6 Trolley assembly 2/3 time - LHR
Figure 68 - PDF for LHR variants of ZX6 on Trolley Assembly2/3
ZX6 Cable routing time - LHR
Figure 69 - PDF for LHR variants of ZX6 on Cable Routing
ZX6Trolley Assembly Time - All Variants
Histogram Log-Logistic
Cycle time (hrs)
32.521.510.5
f(x)
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Log-Logistic α = 5.610915 β 0.7961095 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
34 LOG-LOGISTIC 0.1699777 1 45.42452 6 1922.832 24
3 BURR (4P) 0.1703063 2 40.9354 1 877.1647 4
13 FATIGUE LIFE 0.1703818 3 55.01549 16 1920.795 22
ZX6 Trolley Assembly Time - LHR / LHC
Histogram Log-Pearson 3
Cycle time (hrs)
3.532.521.510.5
f(x)
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Log-Pearson 3 Parameter α = 208.9847 β = -0.0213544 γ 4.313397 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
35 LOG-PEARSON 3 0.1663461 1 44.89431 11 1936.342 14
46 PEARSON 6 (4P) 0.1668951 2 43.09965 7 1936.346 18
19 GEN. EXTREME VALUE 0.1672146 3 44.90607 12 2006.518 36
ZX6 Cable Routing Time - LHR / LHC
Histogram Burr (4P)
Cycle time (hrs)
20151050
f(x)
0.8
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Burr k = 0.4284861 α 9.707227 β 3.776739 γ -1.762133 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
3 BURR (4P) 0.0718834 1 6.002953 1 328.7607 8
2 BURR 0.0727731 2 7.159316 2 316.7859 5
7 DAGUM 0.0767745 3 8.707279 4 318.4076 7
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
80
ZX6 Cable routing time - CRB
Figure 70 - PDF for CRB variants of ZX6 on Cable Routing
ZX6 Cable routing time - FM
Figure 71 - PDF for FM variants of ZX6 on Cable Routing
ZX6 Line pull test time - all variants
Figure 72 - PDF for all variants of ZX6 on Line Pull Test
ZX6 Cable Routing Time - CRB / CRE
Histogram Log-Logistic (3P)
Cycle time (hrs)
20151050
f(x)
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Log-Logistic α = 3.634933 β 3.498207 γ -0.8902334 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
36 LOG-LOGISTIC (3P) 0.0909658 1 1.225602 2 14.76913 22
7 DAGUM 0.0985709 2 1.057907 1 4.51993 2
50 RAYLEIGH 0.1036765 3 3.344808 27 6.019246 3
ZX6 Cable Routing Time - FM
Histogram Burr (4P)
Cycle time (hrs)
108642
f(x)
0.56
0.52
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Burr k = 0.5769855 α 8.872456 β 4.690681 γ -2.617661 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
3 BURR (4P) 0.0626822 1 0.3112994 1 8.630546 5
36 LOG-LOGISTIC (3P) 0.0684314 2 0.3928862 2 8.432349 2
8 DAGUM (4P) 0.0684537 3 0.4013878 3 8.550448 4
ZX6 Line Pull Test Time - All Variants
Histogram Rice
Cycle time (hrs)
4.543.532.521.510.5
f(x)
0.88
0.8
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Rice ν = 0.4836036 σ 0.2727408 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank 50 RICE 0.3491075 1 362.963 26 5133.871 30
22 GUMBEL MAX 0.3498859 2 326.8881 23 11010.06 35
47 RAYLEIGH 0.3542044 3 383.8424 29 5348.803 31
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
81
ZX6 Rope-up time - all variants
Figure 73 - PDF for all variants of ZX6 on Rope-up
ZX6 End of line test time - all variants
Figure 74 - PDF for all variants of ZX6 on End-of-Line Test
ZX6 Crab assembly time - all variants
Figure 75 - PDF for all CRB variants of ZX6 on Crab Assembly
ZX6 Rope-up Time - All Variants
Histogram Burr (4P)
Cycle time (hrs)
1086420
f(x)
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
Distribution – Burr k = 0.4848172 α 10.50349 β 1.40639 γ -0.4657962 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
3 BURR (4P) 0.215375 1 80.93651 1 3423.532 14
22 GEN. GAMMA 0.2232415 2 141.1277 19 3604.71 21
2 BURR 0.2235395 3 81.3424 2 3419.742 13
ZX6 End of Line Test Time - All Variants
Histogram Gen. Extreme Value
Cycle time (hrs)
8.887.26.45.64.843.22.41.60.8
f(x)
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – General Extreme k = 0.0835149 δ 0.4115712 μ 1.809864 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
21 GEN. EXTREME VALUE 0.1802831 1 65.71497 8 2377.495 2
45 PEARSON 5 0.1813326 2 91.7465 26 2656.549 14
46 PEARSON 5 (3P) 0.1843568 3 113.8879 33 2555.488 6
ZX6 Crab Assembly Time - All Variants
Histogram Johnson SB
Cycle time (hrs)
43.532.521.5
f(x)
0.6
0.56
0.52
0.48
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Distribution – Johnson SB γ = 1.268061 δ 0.9716015 λ 3.756405 ξ 1.537274 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
30 JOHNSON SB 0.1948007 1 8.423895 52 N/A
24 GEN. PARETO 0.1970093 2 8.426445 53 N/A
17 FRECHET 0.2012252 3 1.184864 24 6.330685 29
Tony Ponsonby Business Process Simulation of a Production Line
__________________________________________________________Appendix 3
82
ZX6 Packing time - all variants
Figure 76 - PDF for all variants of ZX6 on packing
ZX6 Packing Time - All Variants
Histogram Pearson 5 (3P)
Cycle time (hrs)
654321
f(x)
0.8
0.72
0.64
0.56
0.48
0.4
0.32
0.24
0.16
0.08
0
Distribution – Pearson Type 5 α = 16.00812 β 19.49298 γ = -.1446756 # DISTRIBUTION KOLMOGOROV
SMIRNOV
ANDERSON
DARLING
CHI-SQUARED
Statistic Rank Statistic Rank Statistic Rank
45 PEARSON 5 (3P) 0.270043 1 151.4917 7 1873.001 2
47 PEARSON 6 (4P) 0.270477 2 151.6131 8 1873.001 1
1 BETA 0.2709203 3 183.7113 22 4926.114 18
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 4
83
APPENDIX 4 - CONFIDENCE LEVELS OF VALIDATION 2
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 5
84
APPENDIX 5 - ZERO TIME LABOUR BOOKINGS 2012
Figure 77 - 2012 Zero time labour bookings
Model Type Falls Cell Operation
Time /
Operation
Number of
Zero Time
bookings
Time Not
Booked
ZX10 DT All 11 Assembly 25.6 4 102.3
ZX10 SS/ST All 11 Assembly 19.9 1 19.9
ZX10 DT All 11 Wire & Test Time 11.0 6 66.2
ZX10 SS/ST All 11 Wire & Test Time 6.9 9 61.9
ZX10 All All 9 End Of Line Test 3.7 38 139.2
ZX10 All All 10 Packing 1.5 58 86.6
ZX6 All All 1 or 8 Barrel Assembly 1.6 26 42.5
ZX6 All All 3 or 8 Frame Assembly 2.4 45 109.8
ZX6 LHR All 4 Trolley Assembly 1 0.9 15 13.0
ZX6 LHR All 4 Trolley Assembly 2/3 0.9 15 13.7
ZX6 CRB All 6 Cable Routing 3.1 4 12.2
ZX6 FTM All 6 Cable Routing 2.9 10 28.6
ZX6 LHR All 6 Cable Routing 3.0 25 75.5
ZX6 All All 7 Line Pull 0.6 67 38.2
ZX6 All All 7 Rope Up 1.2 64 78.2
ZX6 All All 9 End Of Line Test 2.1 19 39.6
ZX6 CRB All 8 Crab Assembly 2.5 97 241.4
ZX6 All All 10 Packing 1.2 97 112.7
ZX8 CRB /FM All 8 or 11 Barrel Assembly 3.3 101 330.9
ZX8 LHR All 1 or 11 Barrel Assembly 2.0 22 44.1
ZX8 All 2&4 1 or 8 Frame Assembly 3.8 20 75.1
ZX8 All 6&8 11 Frame Assembly 11.2 8 89.8
ZX8 LHR All 4 Trolley Assembly 1 1.0 20 19.5
ZX8 LHR All 4 Trolley Assembly 2/3 1.1 16 17.4
ZX8 CRB 2&4 6 Cable Routing 4.4 0 0.0
ZX8 CRB 6&8 11 Cable Routing 6.1 1 6.1
ZX8 FM All 6 or 11 Cable Routing 4.8 64 308.7
ZX8 LHR 2&4 6 Cable Routing 3.8 13 49.2
ZX8 LHR 6&8 6 or 11 Cable Routing 6.9 6 41.3
ZX8 All All 7 Line Pull 0.7 150 105.4
ZX8 All 2&4 7 Rope Up 3.8 13 49.9
ZX8 All 6&8 7 Rope Up 6.2 62 385.7
ZX8 All All 9 End Of Line Test 2.4 21 49.4
ZX8 All All 10 Packing 1.5 17 25.4
ZX8 CRB All 6 or 11 Crab Assembly 3.6 37 133.8
Total Not Booked 1171 3013.2
Tony Ponsonby siness Process Simulation of a Production Line
Appendix 6
85
APPENDIX 6 - EXPERIMENT 2 TOP 40 SCENARIOS
Sce
nar
io
Me
an Q
uan
tity
Dis
pat
che
d
Ce
ll1
Qu
anti
ty
Ce
ll3
Qu
anti
ty
Ce
ll4
Qu
anti
ty
Ce
ll6
Qu
anti
ty
Ce
ll8
Qu
anti
ty
Ce
ll9
Qu
anti
ty
Ce
ll1
1 Q
uan
tity
Ce
ll1
0 Q
uan
tity
Ce
ll7
_R
op
eU
p Q
uan
tity
Ge
ne
rato
r U
tili
sati
on
90
% M
in
90
% M
ax
95
% M
in
95
% M
ax
99
% M
in
99
% M
ax
248 976.2 3 4 3 6 1 4 6 4 4 98.6 945.5 1006.9 936.1 1016.3 909.9 1042.5
1094 970.7 4 4 3 5 1 4 5 3 4 98.4 935.3 1006.2 924.5 1017.0 894.2 1047.3
486 969.1 4 4 2 5 1 4 5 4 4 98.6 942.4 995.8 934.2 1003.9 911.4 1026.7
1118 968.7 4 4 3 6 2 4 5 3 4 98.4 915.4 1022.1 899.1 1038.4 853.4 1084.1
824 968.3 3 4 3 6 1 4 6 3 4 98.6 945.3 991.3 938.2 998.3 918.6 1017.9
1144 968.1 4 4 4 6 1 4 6 3 4 98.8 936.6 999.6 927.0 1009.2 900.1 1036.1
462 967.6 4 3 4 5 2 4 5 4 4 97.8 925.8 1009.4 913.0 1022.2 877.3 1057.9
1126 966.9 4 4 4 5 1 4 5 3 4 98.6 934.0 999.8 924.0 1009.8 895.9 1037.9
264 965.6 3 4 4 5 1 4 6 4 4 98.6 929.9 1001.3 919.0 1012.2 888.4 1042.8
792 965.6 3 4 2 6 1 4 6 3 4 98.6 922.6 1008.6 909.5 1021.7 872.7 1058.5
1096 964.9 4 4 3 5 1 4 6 3 4 98.4 940.4 989.5 932.8 997.0 911.8 1018.0
808 964.8 3 4 3 5 1 4 6 3 4 98.2 930.6 999.0 920.1 1009.4 890.9 1038.6
544 964.6 4 4 3 6 2 4 6 4 4 98.6 918.8 1010.5 904.8 1024.4 865.6 1063.6
1120 963.3 4 4 3 6 2 4 6 3 4 98.6 951.4 975.1 947.8 978.7 937.7 988.9
782 962.3 3 4 2 5 2 4 5 3 4 98.2 931.5 993.1 922.1 1002.5 895.8 1028.8
512 962.1 4 4 2 6 2 4 6 4 4 98.6 907.2 1017.0 890.5 1033.8 843.6 1080.7
214 961.5 3 4 2 6 1 4 5 4 4 98.6 935.1 987.8 927.1 995.8 904.6 1018.3
286 960.5 3 4 4 6 2 4 5 4 4 98 924.9 996.1 914.0 1006.9 883.6 1037.3
1008 960.3 4 3 3 5 2 4 6 3 4 98.4 937.5 983.1 930.5 990.1 911.0 1009.6
816 960.0 3 4 3 5 2 4 6 3 4 98.4 940.5 979.5 934.5 985.4 917.9 1002.1
552 957.8 4 4 4 5 1 4 6 4 4 99 949.3 966.3 946.7 968.9 939.4 976.2
520 957.7 4 4 3 5 1 4 6 4 4 98.6 946.9 968.4 943.6 971.7 934.4 980.9
174 957.2 3 3 4 5 2 4 5 4 4 98.2 938.1 976.2 932.3 982.0 916.0 998.3
550 957.2 4 4 4 5 1 4 5 4 4 98 934.7 979.6 927.8 986.5 908.6 1005.7
864 956.8 3 4 4 6 2 4 6 3 4 98.4 924.9 988.8 915.1 998.5 887.9 1025.8
534 956.7 4 4 3 6 1 4 5 4 4 98.4 917.8 995.5 905.9 1007.4 872.7 1040.6
830 956.5 3 4 3 6 2 4 5 3 4 98.8 913.5 999.5 900.4 1012.6 863.7 1049.3
1078 956.2 4 4 2 6 1 4 5 3 4 99 920.4 991.9 909.5 1002.8 879.0 1033.4
1134 956.0 4 4 4 5 2 4 5 3 4 98.4 923.7 988.3 913.9 998.1 886.3 1025.7
126 955.3 3 3 2 6 2 4 5 4 4 98 917.3 993.4 905.7 1005.0 873.1 1037.5
206 955.2 3 4 2 5 2 4 5 4 4 98.6 911.9 998.4 898.7 1011.6 861.8 1048.6
1088 955.2 4 4 2 6 2 4 6 3 4 98.8 911.0 999.4 897.5 1012.9 859.7 1050.7
510 954.8 4 4 2 6 2 4 5 4 4 98.2 900.1 1009.6 883.4 1026.3 836.6 1073.0
518 954.5 4 4 3 5 1 4 5 4 4 98.6 907.2 1001.8 892.8 1016.2 852.4 1056.6
528 954.5 4 4 3 5 2 4 6 4 4 98.4 905.7 1003.3 890.8 1018.2 849.1 1060.0
568 954.3 4 4 4 6 1 4 6 4 4 98.2 942.6 966.1 939.0 969.7 928.9 979.8
774 953.8 3 4 2 5 1 4 5 3 4 98.6 916.2 991.5 904.7 1003.0 872.6 1035.1
270 953.5 3 4 4 5 2 4 5 4 4 98.6 911.1 995.9 898.2 1008.8 862.0 1045.0
110 953.2 3 3 2 5 2 4 5 4 4 98.4 930.6 975.7 923.8 982.6 904.5 1001.9
1128 952.9 4 4 4 5 1 4 6 3 4 99 929.0 976.7 921.7 984.0 901.2 1004.5
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 7
86
APPENDIX 7 - EXPERIMENT 3 RESULTS
Scenario
Mean Hoists Shipped
Generator Quantity
Cell7 LinePull Quantity
Generator Utilisation (%)
ZX6 Throughput Efficiency (%)
ZX8 Throughput Efficiency (%)
ZX10 Throughput Efficiency (%)
Line Pull Utilisation (%)
Combined Average Total Time
Combined Average Process Time
Combined Average Wasted Time
Combined TE
Combined Arrival Rate (Hoists/Hour)
Combined Avg WIP
Combined Hoists / m² of building
90% Min
90% Max
95% Min
95% Max
99% Min
99% Max
De
lay1
1968.31
193.7%
3.6%6.%
4.%51.5
41819
3994.5%
0.22594.0
41935
20021927
20101909
2028
De
lay2
1991.91
296.2%
3.7%6.%
4.%25.4
41319
3944.5%
0.22793.9
41968
20161962
20211949
2034
De
lay3
2006.41
396.9%
3.9%6.%
4.1%17
41019
3924.5%
0.22994.0
41970
20431961
20511942
2071
De
lay4
2284.92
154.5%
4.%6.%
5.%60.5
35618
3385.2%
0.26192.9
42278
22912277
22932273
2297
De
lay5
2293.22
254.7%
4.%6.%
5.%29.8
35618
3385.2%
0.26293.2
42284
23022282
23042278
2309
De
lay6
2289.42
354.8%
4.%6.%
5.%19.9
35618
3375.2%
0.26193.0
42280
22992278
23012273
2306
De
lay7
2293.43
137.%
4.%6.%
5.%60.4
35618
3385.2%
0.26293.3
42286
23012284
23032280
2307
De
lay8
2289.33
236.7%
4.%6.%
5.%29.5
35618
3385.2%
0.26193.1
42282
22972280
22992276
2303
De
lay9
2292.73
336.6%
4.%6.%
5.%19.8
35618
3385.2%
0.26293.2
42284
23022281
23042276
2309
De
lay10
2285.54
127.4%
4.%6.%
5.%60.2
35718
3385.2%
0.26193.0
42279
22922277
22942273
2298
De
lay11
2286.24
227.3%
4.%6.%
5.%29.7
35618
3385.2%
0.26193.0
42279
22932277
22952274
2299
De
lay12
2290.14
326.9%
4.%6.%
5.%19.8
35618
3375.2%
0.26193.0
42282
22982280
23002276
2304
No
De
lay1
2044.41
195.1%
4.8%23.9%
5.8%52.9
30018
2826.1%
0.23370.1
42008
20811999
20901979
2109
No
De
lay2
2212.81
298.9%
5.5%22.4%
5.3%28.2
26817
2516.4%
0.25367.8
42144
22822128
22982091
2335
No
De
lay3
2319.91
399.%
6.1%21.9%
5.8%19.7
23716
2216.9%
0.26562.7
42270
23692259
23812232
2408
No
De
lay4
3144.62
173.9%
8.%24.3%
9.9%82.9
18218
1649.8%
0.35965.3
63109
31803101
31893081
3208
No
De
lay5
3386.52
281.%
9.%23.4%
13.1%44.3
15618
13811.5%
0.38760.1
63371
34023367
34063359
3414
No
De
lay6
3259.62
375.3%
9.1%23.9%
12.3%28.1
14917
13211.5%
0.37255.6
63233
32863227
32923213
3306
No
De
lay7
3421.23
154.7%
9.%24.5%
13.4%91
15318
13511.7%
0.39159.8
73404
34393399
34433390
3453
No
De
lay8
3412.63
255.2%
9.1%24.4%
14.1%44.9
14518
12612.5%
0.39056.3
73396
34293392
34333383
3442
No
De
lay9
3411.33
355.2%
9.7%24.6%
14.4%30
14418
12612.5%
0.38956.0
73395
34273391
34313383
3440
No
De
lay10
34254
141.9%
9.%24.4%
14.%91
14818
13012.2%
0.39157.9
73409
34413406
34443397
3453
No
De
lay11
3415.74
241.3%
9.4%24.6%
14.5%45
14318
12512.6%
0.39056.0
73400
34313396
34353388
3444
No
De
lay12
3406.84
341.%
9.5%24.7%
14.5%29.9
14318
12512.6%
0.38955.7
63393
34203390
34233383
3431
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 8
87
APPENDIX 8 - IUNIFORM DISTRIBUTIONS GOVERNING HOIST ATTRIBUTES
Table 18 - Iuniform Data to Assign Hoist Model Attribute
Table 19 - Iuniform Data to Assign ZX6 Attributes
Table 20 - Iuniform Data to Assign ZX8 Attributes
Table 21 - Iuniform Data to Assign ZX10 Attributes
Hoist
Model
Qty in
2012
Iuniform
from (>)
Iuniform
to (<=) % Split
ZX10 60 0 60 3.77
ZX6 863 60 923 54.28
ZX8 667 923 1590 41.95
Total 1590
Barrel
Length
No
Of
Falls
CRB
QTY
Iuniform
from (>)
Iuniform
to (<=)
FTM
QTY
Iuniform
from (>)
Iuniform
to (<=)
LHR
QTY
Iuniform
from (>)
Iuniform
to (<=) Total
2 1 0 1 6 1 7 34 7 41
4 9 41 50 29 50 79 45 79 124
2 1 124 125 1 125 126 24 126 150
4 86 150 236 52 236 288 575 288 863
2 1 863 864 17 864 881 51 881 932
4 49 932 981 49 981 1030 1206 1030 2236
Total 147 154 1935 2236
ZX6 Hoist Configurations
E
L
N
Barrel
Length
No
Of
Falls
CRB
QTY
Iuniform
from (>)
Iuniform
to (<=)
FTM
QTY
Iuniform
from (>)
Iuniform
to (<=)
LHR
QTY
Iuniform
from (>)
Iuniform
to (<=) Total
2 2 0 2 1 2 3 21 3 24
4 20 24 44 14 44 58 36 58 94
6 28 94 122 6 122 128 5 128 133
8 110 133 243 8 243 251 12 251 263
2 263 263 4 263 267 14 267 281
4 92 281 373 41 373 414 157 414 571
6 24 571 595 7 595 602 3 602 605
8 32 605 637 3 637 640 3 640 643
2 13 643 656 3 656 659 44 659 703
4 202 703 905 54 905 959 670 959 1629
6 16 1629 1645 1645 1645 5 1645 1650
8 1 1650 1651 1651 1651 1 1651 1652
Total 540 141 971 1652
ZX8 Hoist Configurations
N
L
E
Barrel
Length
ZX10
Configuration
CRB
QTY
Iuniform
from (>)
Iuniform
to (<=)
FTM
QTY
Iuniform
from (>)
Iuniform
to (<=) Total
E SS 0 0 0 2 0 2
DT 14 2 16 2 16 18
SS 8 18 26 3 26 29
ST 9 29 38 38 38
DT 3 38 41 41 41
SS 30 41 71 3 71 74
ST 3 74 77 77 77
SS 12 77 89 5 89 94
ST 0 94 94 94 94
DT 16 94 110 1 110 111
SS 1 111 112 1 112 113
ST 12 113 125 125 125
Total 108 17 125
ZX10 Hoist Configurations
S
V
L
N
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 9
88
APPENDIX 9 - HOIST SIZE LOOK-UP TABLE
Ho
ist
Mo
de
l
Ho
ist
De
sign
Fall
s
Bar
rel
Len
gth
Co
de
Are
a m
²
Wid
th (
m)
De
pth
(m
)
Ho
ist
Mo
de
l
Ho
ist
De
sign
Fall
s
Bar
rel
Len
gth
ZX1
0
Co
nfi
gura
tio
n
Co
de
Are
a m
²
Wid
th (
m)
De
pth
(m
)
ZX6 CRB 2 E ZX6CRB2E 2.20 1.80 1.22 ZX8 FM 6 E ZX8FM6E 2.39 2.64 0.90
ZX6 FM 2 E ZX6FM2E 3.45 2.40 1.44 ZX8 LHR 6 E ZX8LHR6E 6.36 3.14 2.03
ZX6 LHR 2 E ZX6LHR2E 1.92 1.68 1.15 ZX8 CRB 6 L ZX8CRB6L 3.86 2.02 1.92
ZX6 CRB 2 L ZX6CRB2L 1.77 1.45 1.22 ZX8 FM 6 L ZX8FM6L 3.45 2.40 1.44
ZX6 FM 2 L ZX6FM2L 1.92 1.68 1.15 ZX8 LHR 6 L ZX8LHR6L 5.21 2.57 2.03
ZX6 LHR 2 L ZX6LHR2L 1.52 1.33 1.15 ZX8 CRB 6 N ZX8CRB6N 3.73 1.95 1.92
ZX6 CRB 2 N ZX6CRB2N 1.62 1.33 1.22 ZX8 FM 6 N ZX8FM6N 3.08 2.14 1.44
ZX6 FM 2 N ZX6FM2N 1.52 1.33 1.15 ZX8 LHR 6 N ZX8LHR6N 4.68 2.31 2.03
ZX6 LHR 2 N ZX6LHR2N 1.26 1.10 1.15 ZX8 CRB 8 E ZX8CRB8E 4.95 2.59 1.92
ZX6 CRB 4 E ZX6CRB4E 2.20 1.80 1.22 ZX8 FM 8 E ZX8FM8E 2.39 2.64 0.90
ZX6 FM 4 E ZX6FM4E 3.45 2.40 1.44 ZX8 LHR 8 E ZX8LHR8E 6.91 3.41 2.03
ZX6 LHR 4 E ZX6LHR4E 1.92 1.68 1.15 ZX8 CRB 8 L ZX8CRB8L 3.86 2.02 1.92
ZX6 CRB 4 L ZX6CRB4L 1.77 1.45 1.22 ZX8 FM 8 L ZX8FM8L 3.45 2.40 1.44
ZX6 FM 4 L ZX6FM4L 1.92 1.68 1.15 ZX8 LHR 8 L ZX8LHR8L 5.21 2.57 2.03
ZX6 LHR 4 L ZX6LHR4L 1.52 1.33 1.15 ZX8 CRB 8 N ZX8CRB8N 3.73 1.95 1.92
ZX6 CRB 4 N ZX6CRB4N 1.62 1.33 1.22 ZX8 FM 8 N ZX8FM8N 3.08 2.14 1.44
ZX6 FM 4 N ZX6FM4N 1.52 1.33 1.15 ZX8 LHR 8 N ZX8LHR8N 4.68 2.31 2.03
ZX6 LHR 4 N ZX6LHR4N 1.26 1.10 1.15 ZX10 CRE 6 E SS ZX10CREESS 8.39 4.10 2.04
ZX8 CRB 2 E ZX8CRB2E 3.97 2.35 1.69 ZX10 FM 6 E SS ZX10FMESS 3.62 2.94 1.23
ZX8 FM 2 E ZX8FM2E 2.25 2.51 0.90 ZX10 CRE 6 L SS ZX10CRELSS 8.15 3.99 2.04
ZX8 LHR 2 E ZX8LHR2E 3.45 2.40 1.44 ZX10 FM 6 L SS ZX10FMLSS 3.37 2.74 1.23
ZX8 CRB 2 L ZX8CRB2L 3.01 1.78 1.69 ZX10 CRE 6 N SS ZX10CRENSS 6.85 3.33 2.06
ZX8 FM 2 L ZX8FM2L 3.45 2.40 1.44 ZX10 FM 6 N SS ZX10FMNSS 2.88 2.34 1.23
ZX8 LHR 2 L ZX8LHR2L 2.64 1.84 1.44 ZX10 CRE 6 S SS ZX10CRESSS 5.48 2.66 2.06
ZX8 CRB 2 N ZX8CRB2N 2.57 1.52 1.69 ZX10 FM 6 S SS ZX10FMSSS 2.39 1.94 1.23
ZX8 FM 2 N ZX8FM2N 2.64 1.84 1.44 ZX10 CRE 6 V SS ZX10CREVSS 10.06 4.89 2.06
ZX8 LHR 2 N ZX8LHR2N 2.27 1.58 1.44 ZX10 FM 6 V SS ZX10FMVSS 4.24 3.44 1.23
ZX8 LHR 2 V ZX8LHR2V 4.03 2.80 1.44 ZX10 CRE 12 L ST ZX10CRELST 7.58 3.33 2.28
ZX8 CRB 4 E ZX8CRB4E 3.97 2.35 1.69 ZX10 FM 12 L ST ZX10FMLST 5.04 3.39 1.49
ZX8 FM 4 E ZX8FM4E 2.25 2.51 0.90 ZX10 CRE 12 L DT ZX10CRELDT 8.60 3.77 2.28
ZX8 LHR 4 E ZX8LHR4E 3.45 2.40 1.44 ZX10 FM 12 L DT ZX10FMLDT 5.63 3.77 1.49
ZX8 CRB 4 L ZX8CRB4L 3.01 1.78 1.69 ZX10 CRE 12 N ST ZX10CRENST 6.21 2.73 2.28
ZX8 FM 4 L ZX8FM4L 3.45 2.40 1.44 ZX10 FM 12 N ST ZX10FMNST 4.14 2.79 1.49
ZX8 LHR 4 L ZX8LHR4L 2.64 1.84 1.44 ZX10 CRE 12 N DT ZX10CRENDT 7.23 3.17 2.28
ZX8 CRB 4 N ZX8CRB4N 2.57 1.52 1.69 ZX10 FM 12 N DT ZX10FMNDT 4.74 3.17 1.49
ZX8 FM 4 N ZX8FM4N 2.64 1.84 1.44 ZX10 CRE 12 V DT ZX10CREVDT 10.88 4.77 2.28
ZX8 LHR 4 N ZX8LHR4N 2.27 1.58 1.44 ZX10 FM 12 V DT ZX10FMVDT 7.13 4.77 1.49
ZX8 LHR 4 V ZX8LHR4V 4.03 2.80 1.44 ZX10 CRE 16 V ST ZX10CREVST 9.15 4.33 2.12
ZX8 CRB 6 E ZX8CRB6E 4.95 2.59 1.92 ZX10 FM 16 V ST ZX10FMVST 6.51 4.39 1.49
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 10
89
APPENDIX 10 - EXPERIMENT 4 RESULTS
Scenario
Mean Hoists Shipped
Cell1 Quantity
Cell3 Quantity
Cell4 Quantity
Cell6 Quantity
Cell8 Quantity
Cell9 Quantity
Cell11 Quantity
Cell10 Quantity
Cell7 Rope-Up Quantity
Generator Quantity
Cell7 LinePull Quantity
Generator Utilisation (%)
ZX6 Throughput Efficiency (%)
ZX8 Throughput Efficiency (%)
ZX10 Throughput Efficiency (%)
Line Pull Utilisation (%)
ZX6QTY
ZX8QTY
ZX10QTY
90% Min
90% Max
95% Min
95% Max
99% Min
99% Max
183890.1
44
36
34
64
44
247.1
923.4
1451.4
2210.81561.1
118.13875
39053872
39083864
3916
63890.2
34
36
34
64
44
247.1
923
1451.6
2206.61565.3
118.33878
39023875
39053869
3912
243884.9
44
46
34
64
44
246.9
923
1451.5
2209.51557.1
118.63873
38973870
39003864
3906
123888.1
34
46
34
64
44
246.8
923.1
1451.4
2205.31564.5
118.63872
39043868
39083860
3916
223710.1
44
46
24
64
44
245.1
9.424.1
14.249.1
21251466.4
118.53693
37273689
37313680
3740
43705.8
34
36
24
64
44
245.1
9.324
14.749.1
2115.31471.9
118.43687
37253682
37293672
3739
163711.9
44
36
24
64
44
244.8
9.323.9
14.249.1
2127.91465.7
118.33692
37323687
37373676
3748
103700.6
34
46
24
64
44
244.7
9.224.2
14.949
2108.71473.7
118.23683
37193678
37233669
3733
33658.6
34
36
24
64
44
144.1
924
12.397.3
2160.31380.7
117.83647
36703644
36733638
3679
93650
34
46
24
64
44
143.9
924.1
12.297.3
21601371.8
118.33640
36603638
36623633
3667
213650.8
44
46
24
64
44
143.8
924
11.997.3
2159.71372.4
118.73637
36653634
36683626
3675
153656.9
44
36
24
64
44
143.8
924.1
12.197.3
2161.61376.8
118.23646
36683643
36703638
3676
113674
34
46
34
64
44
143.6
8.824.1
10.897.9
2217.11338.2
118.63665
36833662
36863657
3691
233668.1
44
46
34
64
44
143.4
8.324.2
10.297.8
22241326.1
118.13655
36813652
36843645
3691
173668.6
44
36
34
64
44
143.4
8.524.1
10.397.6
2222.11328.1
118.53656
36813653
36843646
3691
53669
34
36
34
64
44
143.2
8.724.2
10.697.7
2221.61329.2
118.33658
36803655
36833649
3689
13425
34
36
14
64
44
141.9
924.4
1491
20031303.4
118.33409
34413406
34443397
3453
203417.4
44
46
14
64
44
241.5
1024.4
1445
1991.51307.7
118.23404
34313401
34343394
3441
73424.6
34
46
14
64
44
141.3
924.6
1491.1
20051301.8
1183410
34393406
34433398
3451
23415.7
34
36
14
64
44
241.3
9.424.6
14.545
1978.61319.2
117.93400
34313396
34353388
3444
133428.7
44
36
14
64
44
141.2
924.3
1491.1
2018.81292.1
117.83410
34473406
34523396
3462
193422.8
44
46
14
64
44
141.2
924.4
1491
2008.41296.2
118.13409
34373405
34403397
3448
143415.8
44
36
14
64
44
241.1
9.824.7
14.144.9
1989.31308.5
118.33401
34303398
34343390
3441
83416.9
34
46
14
64
44
240.9
9.624.4
14.244.9
1982.71316.3
1183402
34323398
34363390
3444
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 11
90
APPENDIX 11 - HEALTH AND SAFETY ASSESSMENT
The MANCHESTER METROPOLITAN UNIVERSITY
Faculty of Science and Engineering
RISK ASSESSMENT COVER SHEET
SCHOOL: Science and Engineering
TITLE OF WORK: Process Simulation of a Production Line
LOCATION OF WORK: John Dalton E345 & E328
If off-site give contact details: NA
INTENDED ACTIVITIES: Simulation of business processes using Witness simulation
software within the MMU computer laboratory.
PERSONS AT RISK: Tony Ponsonby
HAZARDS: Prolonged exposure to display screen equipment.
Are these hazards necessary in order to achieve the objectives of the activity? Yes
Hazard Rating: Low
HAZARDOUS SUBSTANCES/MATERIALS USED AND HAZARD CLASSIFICATION: None ALL CONTAINERS OF HAZARDOUS SUBSTANCES SHOULD BEAR CORRECT HAZARD
WARNING LABELS.
NAME OF MATERIAL N/A
HAZARD CLASS
HAZARD LABEL
DISPOSAL N/A
PROCEDURE FOR EMERGENCY SHUT-DOWN: N/A
IF OFF-SITE INDICATE ANY OTHER ISSUES (e. . associate wit : in i i ual’s health and dietary requirements (obtain off-site health forms for all participating individuals and indicate where this information will be located); social activities, transportation, ID requirements; permissions for access and sampling).
NAME STAFF/STUDENT No. DATE
Originator Tony Ponsonby 02968984 16/11/12
Supervisor Mohammed Latif
Technical Manager - - -
Divisional / School Health and Safety Coordinator (p.p. HoS)
DATE TO BE REVIEWED BY:
Tony Ponsonby Business Process Simulation of a Production Line
Appendix 12
91
APPENDIX 12 - ETHICS CHECK FORM
Before completing the Ethics Check Form the person undertaking the activity should consider the following:
YES NO N/A
1. Is the size of sample proposed for any group enquiry larger than justifiably necessary?
N/A
2 Will any lines of enquiry cause undue distress or be impertinent?
N/A
3 Has any relationship between the researcher(s) and the participant(s), other than that required by the academic activity, been declared?
N/A
4 Have the participants been made fully aware of the true nature and purpose of the study? If NO is there satisfactory justification (such as the likelihood of the end results being affected) for withholding such information? (Details to be provided to the person approving the proposal).
N/A
5 Have the participants given their explicit consent? If NO is there satisfactory justification for not obtaining consent? (Details to be provided to the person approving the proposal).
N/A
6 Have the participants been informed at the outset that they can withdraw themselves and their data from the academic activity at any time?
N/A
7 Are due processes in place to ensure that the rights of those participants who may be unable to assess the implications of the proposed work are safeguarded?
N/A
8 Have any risks to the researcher(s), the participant(s) or the University been assessed? If YES to any of the above is the risk outweighed by the value of the academic activity?
YES
NO
9 If any academic activity is concerned with studies on activities which themselves raise questions of legality is there a persuasive rationale which demonstrates to the satisfaction of the University that: i the risk to the University in terms of external (and internal) perceptions of the worthiness of the work has been assessed and is deemed acceptable;
N/A
YES
ii arrangements are in place which safeguard the interests of the researcher(s) being supervised in pursuit of the academic activity objectives;
YES
iii special arrangements have been made for the security of related documentation and artifacts.
N/A
10 Have the ethical principles and guidelines of any external bodies associated with the academic activity been considered?
N/A
Tony Ponsonby Process Simulation of a Production Line
Appendix 12
92
Faculty of Science and Engineering Department of Engineering and Technology
Ethics Check Form
1 Name(s) of Applicant: Tony Ponsonby 2 Department: Engineering and Technology 3 Name of Supervisor: Dr Muhammad Latif 4 Title of Project: Business Process Simulation of a Production Line 5 Resume of ethical issues: 6 Does the project require the approval of any external agency?
YES If YES has approval been granted by the external agency? YES
7 Statement by Applicant
I confirm that to the best of my knowledge, I have made known all relevant information, and I undertake to inform my supervisor of any such information, which subsequently becomes available whether before or after the research has begun
Signature of Applicant:
Date: 6/12/12
8 Statement by Supervisor
Approval for the above named proposal is granted I confirm that there are no ethical issues requiring further consideration. (Any subsequent changes to the nature of the project will require a review of the ethical considerations): Signature of Supervisor: Date: I confirm that any issues identified overleaf as requiring further consideration have been satisfactorily addressed: Signature of Supervisor: Date:
Approval for the above named proposal is not granted I confirm that there are ethical issues requiring further consideration and will refer the project proposal to the appropriate Committee** Signature of Supervisor: Date: