MTA CAPITAL PROGRAM MILESTONES as of December 31, 2014

Upload: vuthu

Post on 11-Dec-2016

222 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: MTA CAPITAL PROGRAM MILESTONES

MTA CAPITAL PROGRAM MILESTONES

as of December 31, 2014

Page 2: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead MTA Agency Milestones January 2015 - December 2016 MTA Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

TABLE OF CONTENTS

AGENCY Page Number MTA NEW YORK CITY TRANSIT, including MTA BUS COMPANY 1 MTA LONG ISLAND RAIL ROAD 14 MTA METRO-NORTH RAILROAD 22 MTA BRIDGES AND TUNNELS 29 MTA CAPITAL CONSTRUCTION 44

Basics of Report:

Additional project-specific detail for each milestone can be found on the MTA Capital Program Dashboard:

http://web.mta.info/capitaldashboard/CPDHome.html

Timeline: Consists of 6 months of historical events and 24 months planned.

Symbols: “Star” depicts a completion milestone. “Square” is for a progress milestone (starts and interim accomplishments).

2010-2014 Milestones are tracked using colors:

GGrreeeenn:: on-time (early or within 0-3 months), YYeellllooww:: 4-6 months late, RReedd:: > 6 months late

2005-2009 Capital Program milestones are shown, but not tracked using colors

For projects reaching completion, photos can be found on the MTA Capital Program Dashboard.

Page 3: MTA CAPITAL PROGRAM MILESTONES

MTA NEW YORK CITY TRANSIT, including MTA BUS COMPANY

Page 1 as of December 31, 2014

Page 4: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Subway Cars January 2015 – December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Cars are purchased to replace older vehicles based on reliability, usage, and age, or alternatively to grow the fleet in response to increased ridership. New cars come equipped with improved passenger amenities and run substantially longer without failure. All new cars come CBTC-ready and can be equipped for CBTC operation.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 2 as of December 31, 2014

Page 5: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Buses January 2015 - December 2016 NYCT/MTA Bus Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Buses are replaced at the end of their useful service life of 12 years as experience has shown this to generally be when it becomes impractical to maintain them in service any further. To improve the environmental impacts of operating the buses, NYCT has a diverse fleet of Compressed Natural Gas (CNG), Hybrid-Electric, and clean-diesel buses, and will continue to implement a broad spectrum of clean fuel technologies into our everyday business practices.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Articulated Buses

Express Buses

Standard Buses

Page 3 as of December 31, 2014

Page 6: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Bus Service Enhancements January 2015 – December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Bus service enhancements are meant to significantly improve the attractiveness and performance of the bus network for our customers. NYC Transit and NYC DOT will continue to work together to implement the remaining Select Bus Service (SBS) routes along the seven Phase 1 Bus Rapid Transit corridors located throughout the city. Lane enforcement cameras will help to ensure buses on select routes will be free of impedances and thus reduce travel times. MTA / NYC Transit is also deploying bus customer information systems (CIS) to provide customers real-time service status updates via the web, smartphones and 3rd party apps.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

NOTE: 7 Planned SBS Routes: (1) Fordham Road – Bronx, (2) 34th St – Manhattan, (3) 1st/2nd Avenues – Manhattan, (4) Nostrand Avenue – Brooklyn, (5) Hylan Boulevard – Staten Island, (6) Webster Avenue – Bronx, (7) LaGuardia Airport – Manhattan Traffic Signal Priority, Phase 2 – 4 Additional Corridors: (1) Hylan Boulevard (S79) – Staten Island, (2) Webster Avenue (Bx41) – Bronx, (3) Nostrand Avenue (B44) – Brooklyn, (4) Utica Avenue (B46) – Brooklyn Purchase of articulated buses for use on SBS routes is presented on “Buses” page.

Page 4 as of December 31, 2014

Page 7: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Station Rehab & Renewal January 2015 - December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: NYCT plans to eliminate station component defects rated Condition 4 or worse (on a 1-good to 5-bad scale) within the 2010-2014 Capital Program. The methods of work to address defects have expanded to include component campaigns for identified defects and a re-focused comprehensive treatment of defects at an identified station (“Renewal”).

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 5 as of December 31, 2014

Page 8: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Station Component January 2015 - December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: NYCT plans to eliminate station component defects rated Condition 4 or worse (on a 1-good to 5-bad scale) within the 2010-2014 Capital Program. The methods of work to address defects have expanded to include component campaigns for identified defects and a re-focused comprehensive treatment of defects at an identified station (“Renewal”).

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary:

Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 6 as of December 31, 2014

Page 9: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead ADA Accessibility January 2015 - December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: NYC Transit plans to make 100 key stations fully compliant with the Americans with Disabilities Act by 2020. Compliant stations generally include elevators to move between levels and other improved elements such as platform edges and Braille signage. NYC Transit has completed 80 of the 100 key stations, and has additionally made 19 non-key stations at least partially accessible.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 7 as of December 31, 2014

Page 10: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Fare Payment Systems January 2015 – December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Fare payment systems encompass the development, installation, renewal, and maintenance of both the current MetroCard system and the next generation New Fare Payment System in development.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

NOTE:

New Fare Payment System (NFPS) – A consultant with expertise in contactless payment systems has been retained to assist NYCT in the development of comprehensive specifications to meet agency needs. In addition, the consultant will provide assistance through the evaluation process related to acquiring a NFPS system integrator. Once a system integrator has been selected an implementation schedule will be developed, and related milestones will be reported.

Page 8 as of December 31, 2014

Page 11: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Signals January 2015 - December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of signal investments is to eliminate overage signals and unmodernized interlockings, some of which date back to the original construction of the subway system and the failure of which remains one of the largest causes of train service delays. Types of investment include modernization of conventional fixed block signals and interlockings, and migration to new technology Communications-Based Train Control (CBTC) signals.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 9 as of December 31, 2014

Page 12: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Subway Customer Information January 2015 – December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Install public address systems and customer information screens (PA/CIS) and provide automated real-time train arrival information (audio and text) at all subway stations. Additionally, provide immediate access to assistance and information through Help Point intercoms located in passenger stations, which debuted at two stations in Spring of 2012.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

NOTE: Canarsie line: Entire line already has PA/CIS and real-time information – Total of 24 stations. A-Division Projects: Real-time information is now available at 153 stations on the lines. The remaining three stations include two at the Fulton Street

Complex () and the Cortlandt St station (), which will provide real-time information following their reconstruction – Total of 156 stations. Train Arrival time is available on both mta.info site and mobile apps including the NYCT developed SubwayTimeTM.

B-Division Projects: Beyond the Canarsie line, 44 stations have next train arrival: Queens Boulevard Line (11), 8th Avenue Line (19), 4th Ave Line (1), and Flushing Line (13), which is considered B-Division here because it was not included in the “PACIS at 156 Stations” project. Eventually all stations on the lettered lines and the Flushing line will have next train information – Total of 288 stations.

Page 10 as of December 31, 2014

Page 13: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Line Structures January 2015 - December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Rehabilitate line structures to address deficiencies, and repaint steel elevated structures within a targeted timeframe of every 15 years.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Structure Rehabilitation

Structure Painting

Page 11 as of December 31, 2014

Page 14: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Maintenance Facilities January 2015 - December 2016 NYCT Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Cost-effective investments are planned for shops, yards and depots that are aimed at keeping these facilities in good repair. Component-based or phased projects are favored; complete facility reconstructions are used only in select cases.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary: Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 12 as of December 31, 2014

Page 15: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Superstorm Sandy January 2015 - December 2016 NYCT/MTA Bus Capital Program Recovery / Resiliency

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Repair/replacement of storm-damaged equipment at nine under-river tubes, four yards, and various other locations system-wide. Asset types include signals, cables, track/switches, line equipment, traction power equipment, communication equipment, and station components. In addition, resiliency measures will be implemented to better prepare the system for future storms and reduce impacts to service.

Prior 6 months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Milestone Type: Completion Progress Color coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital program

Milestone Under Development

Summary:

Previous 6 Months:

0-6 Months:

7-12 Months:

13-24 Months:

Page 13 as of December 31, 2014

Page 16: MTA CAPITAL PROGRAM MILESTONES

MTA LONG ISLAND RAIL ROAD

Page 14 as of December 31, 2014

Page 17: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Rolling Stock January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: As part of its fleet modernization and expansion effort, the LIRR will initiate the first phase of its M-9 procurement. This effort is required to support the East Side Access (ESA) project and to replace the aging M-3 cars, which utilize decades old technology. The M-9 car will incorporate the popular and successful features which are part of the M-7, while also utilizing the latest technology. Future M-9 purchase options will allow the LIRR to expand the size of its electric fleet to accommodate systemwide ridership growth.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)

Ongoing M9 Fleet Procurement

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Rolling StockRolling Stock

Summary: Previous 6 Months:

Ongoing M9 Fleet Procurement Contract - Begin delivery of Pilot cars by end of 2016

0-6 Months:

7-12 Months:

13-24 Months:

Page 15 as of December 31, 2014

Page 18: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Stations January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Station investments work to improve ADA access and customer safety by installing new elevators, platform lighting, ADA-compliant platform handrails, station platforms, and other station components.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)( ) ( ) ( ) ( )

Construction Completion - Massapequa Station Platform Replacement

Design Complete - Nostrand Ave Station

Design Completion - Wantagh Station Platform ReplacementConstruction Start - Wantagh Station Platform Replacement

Construction Completion - Elevator Replacement Program

Construction Start - Escalator Replacement Program

Construction Completion - Wyandanch Parking Facility

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Stations

Summary: Previous 6 Months:

Begin construction Escalator replacement program

0-6 Months: Complete platform design at 2 stations

7-12 Months: Complete platform construction at 1 station

13-24 Months: Begin Platform replacement at 1 station

Complete Construction - Elevator Replacement program

Complete Construction - Wyandanch Parking Facility

Page 16 as of December 31, 2014

Page 19: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Track / Line Structures January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The LIRR’s Track and Line Structures investment program provides for cyclical replacement of asset components to ensure service reliability and on-time performance and compliance with FRA track standards.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)

Beneficial Use - 2014 Annual Track Program

Design / Build Completion - Jamaica Capacity Improvements - Johnson Ave. Yard

Construction Completion - 150th St. Bridge Structure Rehab

Beneficial Use - Jamaica /Lefferts Blvd. Bridge Structure Rehabilitation

Design Complete-Jamaica Capacity Improvements - Platform 'F'

Design Complete - Jamaica Capacity Improvements Phase I

Award Platform F Construction

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Line Structures

Track

Summary: Previous 6 Months: Complete 2014 Annual Track Program Complete design - JCI Platform 'F'

0-6 Months:

7-12 Months: Complete rehabilitation of 150th St. Bridge Structure Complete rehabilitation of Jamaica/Lefferts Blvd. bridge structure Complete design for JCI Phase I Award construction JCI – Platform F

13-24 Months: Complete construction JCI – Johnson Ave Yard

Page 17 as of December 31, 2014

Page 20: MTA CAPITAL PROGRAM MILESTONES

Communications and Signals 24 Month Look-ahead January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: To increase safety and comply with a federal mandate, a Positive Train Control (PTC) system will be installed throughout LIRR territory in New York State (in coordination with Metro-North Railroad). To facilitate compliance with PTC an Automatic Speed Control (ASC) signal system will be installed from Speonk to Montauk. Contracts to advance both projects were awarded late in 2013 and completions are forecast beyond the 24 month outlook. The LIRR is also continuing work on the construction of a Centralized Train Control Facility.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)

Ongoing PTC ImplementationOngoing Speonk to Montauk Signalization

Construction Completion - Centralized Train Control Facility

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Communications and Signals

Summary: Previous 6 Months: Ongoing PTC Development & Implementation Ongoing Speonk to Montauk Signalization

0-6 Months: Complete Construction – Centralized Train Control Facility

7-12 Months:

13-24 Months:

Page 18 as of December 31, 2014

Page 21: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Shops and Yards January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The Mid-Suffolk Yard project includes the construction of a new electric train storage yard. Based on the projected demand for future services, expansions of electric train storage yard facilities are required. The need was identified to increase electric train storage yard capacity on the Main Line Branch.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)

Design Complete-Mid-Suffolk Yard

Construction Start - Mid Suffolk Yard

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Shops & Yards

Summary: Previous 6 Months:

0-6 Months: Complete Mid-Suffolk yard design

7-12 Months:

13-24 Months: Construction Start - Mid-Suffolk yard

Page 19 as of December 31, 2014

Page 22: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Main Line Corridor - Near Term Capacity Improvements

Program Description: Capital improvements over the next five years for key parts of LIRR's Main Line between Mineola and Hicksville. This critical stretch of track carries trains from five branches, serves nearly 40% of total daily ridership and will play an extremely important part in the success of East Side Access. The investments include the rehabilitation of Hicksville Station as well as adjacent track and signal modernization as well as the demolition and reconstruction and widening of the Ellison Avenue Bridge in Westbury.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)

Construction Start - Ellison Ave Bridge Construction CompleteConstruction Start - Hicksville Station Ellison Ave Bridge

Design Complete - Hicksville Station

Design Complete - Hicksville North Siding

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

MLC - Near Term Capacity Improvements

Summary: Previous 6 Months: Construction Start - Ellison Ave Bridge

0-6 Months: Design Complete - Hicksville Station & Hicksville North Siding

7-12 Months: Construction Start – Hicksville Station

13-24 Months: Construction Complete – Ellison Ave Bridge

Page 20 as of December 31, 2014

Page 23: MTA CAPITAL PROGRAM MILESTONES

Super Storm Sandy 24 Month Look-ahead Recovery / Resiliency January 2015 – December 2016 LIRR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Repair/replacement of storm-damaged equipment and infrastructure focus on four key areas: Long Beach Branch, Long Island City Yard, West Side Yard, and the East River Tunnels. Early repair efforts are focused on the Long Beach Branch systems and power infrastructure and the Long Island City (LIC) Yard, followed by West Side Yard and the East River Tunnels. In addition, resiliency projects are under development and will be implemented to better prepare the system for future storms and reduce impacts to service. These projects will be added to this Milestone report as their scopes and schedules are developed.

Prior 6 Months Current (01/2015) 6 Mo (07/2015) 12 Mo (01/2016) 24 Mo (12/2016)

Design Complete -Wreck Lead Bridge Systems

Construction Start - Long Beach Branch Systems - Signal System

Third Party Design Complete - Long Beach BranchSubstation Replacement

Third Party Design Complete - Long Island City Yard RestorationConstruction Start - Long Island City Yard Restoration

Construction Start - First Avenue Substation Restoration Construction Completion - First Avenue Substation Restoration

Design Complete - Infrastructure / System Upgrades (Various Locations)Construction Start - Infrastructure / System Upgrades (Various Locations)

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Long Island City Yard

Wreck Lead Bridge

Long Beach Branch System

First Avenue Substation

Various Infrastructure / Systems Upgrades

Long Beach Branch Substations

Summary: Previous 6 Months:

Begin Construction - 1st Ave Substation

0-6 Months: Complete design of Wreck Lead Bridge Systems Begin Construction - Long Beach Branch System Complete Design of LIC Yard Restoration Begin Construction - Infrastructure / System Upgrades (Various Locations)

7-12 Months: Complete design Long Beach Substation Begin Construction of LIC Yard Restoration

13-24 Months: Complete Construction - 1st Ave Substation Complete design Infrastructure / Systems Upgrades (Various Systems)

Page 21

as of December 31, 2014

Page 24: MTA CAPITAL PROGRAM MILESTONES

MTA METRO-NORTH RAILROAD

Page 22 as of December 31, 2014

Page 25: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Rolling Stock January 2015 – December 2016 MNR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Design, Manufacture, Test and Deliver new M-8 electric cars for New Haven Line revenue service. The base contract for 210 cars and the first option for 90 additional cars were awarded on August 21, 2006; two additional options for 42 and 38 cars respectively were subsequently elected.

Prior 6 Months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

M8 Car ProcurementPilot Testing of M-8 Cars for Shoreline East Service

Acceptance of original order of 380 M-8 Cars for New Haven Line Service

Acceptance of 25 single car configuration Deliver remaining three M-8 Cars

Milestone Type: Completion Progress 2010-2014 Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

0-6 Months: Acceptance of original order of 380 M-8 Cars for New Haven Line Service Acceptance of 25 single car configuration

7-12 Months: Pilot Testing of M-8 Cars for Shoreline East Service

13-24 Months: Deliver remaining 3 M-8 Cars

Page 23 as of December 31, 2014

Page 26: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Stations January 2015 – December 2016 MNR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Station rehabilitation work focuses on components in need of investment, so it varies by station. Work may include overpass replacement, platform replacement, canopy replacement, lighting, public address system, visual information system, tactile warning strips, parking expansion, guardrail, domestic water system, fire suppression system and other improvements.

Prior 6 Months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

New Haven Line Stations Phase IIComplete Construction

Fordham Station Complete ConstructionCapacity Improvements- Platform Widening

Poughkeepsie Station: Complete Poughkeepsie DesignStation Building Improvements

Harlem Line Stations Renewal Complete Harlem Line Stations Renewal Ph 1 Design(Phase 1)

Award Ph 1 Construction

GCT Domestic Water System Complete Construction Domestic Water System

GCT Fire Suppression System Award Fire Suppression System Construction

GCT Trainshed/Tunnel Structure

Award Trainshed/Tunnel Repairs Construction

Milestone Type: Completion Progress 2010-2014 Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Complete 1 Construction Award 1 Construction

0-6 Months: Complete 1 Design Complete 1 Construction

7-12 Months: Complete 1 Design Award 1 Construction

13-24 Months: Award 1 Construction Complete 1 Construction

Note: Guardrail Replacement Mentoring Project – Only Mount Vernon Station was complete; the contract was terminated before the completion of the Pelham and New Rochelle Stations.

Page 24 as of December 31, 2014

Page 27: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Track and Structures January 2015 – December 2016 MNR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The Structures program features concrete repairs of pier foundations, replacement of bearings and superstructure repairs at Moodna Viaduct. At the Woodbury Viaduct the repairs consist of reconstruction of the east abutment back wall and the pedestals supporting the superstructure. The annual track program focuses on installation of new ties as well as track resurfacing east of Hudson River.

Prior 6 Months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Moodna / WoodburyViaduct Priority Repairs

Complete Repairs for Woodbury Viaduct

2013 Track ProgramComplete installation 20k ties and surface 125 miles

2014 Track ProgramAward 2014 Track Program Complete 2014 Track Program

Milestone Type: Completion Progress 2010-2014 Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Complete 1 Construction

0-6 Months: Complete 2013 Track Program Commence 2014 Track Program

7-12 Months:

13-24 Months: Complete 2014 Track Program

Page 25 as of December 31, 2014

Page 28: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Communications and Signals January 2015 – December 2016 MNR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: To increase safety and comply with federal mandates, a Positive Train Control (PTC) system will be installed throughout Metro-North territory in New York State (in coordination with LIRR). West of Hudson Signal Improvements will install a cab signal system including Positive Train Control for the Port Jervis Line, similar to MNR East of Hudson territory.

Initiate early Design efforts for the Customer Service Initiatives (CSI) program to provide real-time customer information to new and existing Visual Information Displays at all East of Hudson stations through the installation of new train information and public address system field equipment to provide departure time and destination, status, and track information to customers and employees. Ethernet-based network connectivity at each station will support the new system, provide ticket selling machine data communication upgrades, provide new ticket office workstations at key stations, and allow capability for remote CCTV and elevator monitoring/control.

Prior 6 Months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Positive Train Control Complete PTC Systems Integrator Contract Part 1

West of Hudson SignalImprovements Complete Design Build for Cab Signal System Houses

Communication/Connectivity Award DesignImprovement (CECCI)

Milestone Type: Completion Progress 2010-2014 Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Award 1 CECCI Design

0-6 Months: Complete 1 Design Build

7-12 Months: Complete PTC Systems Part1

13-24 Months:

Page 26 as of December 31, 2014

Page 29: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Shops and Yards January 2015 – December 2016 MNR Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: At Croton-Harmon continue with the Harmon Shop Improvements Program, with focus on maintaining the integrity of the existing facilities and yard which includes repairs and upgrades. In addition perform preliminary engineering for the first stage of design to replace the existing Electric Car Facility.

Prior 6 Months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Harmon Shop Improvements

Design - Build Award Construction of the Consist ShopPhase V (Stage 1)

Milestone Type: Completion Progress 2010-2014 Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Start Design/Build

0-6 Months:

7-12 Months:

13-24 Months:

Page 27 as of December 31, 2014

Page 30: MTA CAPITAL PROGRAM MILESTONES

Super Storm Sandy

24 Month Look-ahead Recovery / Resiliency January 2015 – December 2016 MNR Capital Program

 

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/ 

Program Description: Repair/replacement of storm-damaged equipment and infrastructure includes Rolling Stock Restoration, Right of Way Restoration, Power Infrastructure Restoration, and Communications and Signals (C&S) Infrastructure Equipment Replacement. In addition, resiliency projects are under development and will be implemented to better prepare the system for future storms and reduce impacts to service. These projects will be added to this Milestone report as their scopes and schedules are developed.

Prior 6 Months Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Right of Way RestorationComplete Construction-Tree Removal Shoreline Restoration Construction Complete

Power & C&S Infrastucture Design Build StartRestoration PH I

Prelim. Design Complete

C&S Infrastucture Equipment Replacement

Complete Impedance Bond Study

Power InfrastructureSubstations Construction 3 Substations Start

Prelim. Design Complete

Power Infrastructure Construction HRLB Facility Houses CompleteHarlem River Lift Bridge (HRLB)

Construction HRLB Facility Houses Start

Milestone Type: Completion Progress 2010-2014 Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior Capital Program  

Summary:

Previous 6 Months: Complete 2 Prelim. Designs Complete Impedance Bond Study Start Construction HRLB Facility House

0-6 Months: Commence 1 Design-Build Start Construction 3 Substations Complete HRLB Facility House Construction

7-12 Months:

13-24 Months: Complete Shoreline Restoration Complete Tree Removal

Page 28 as of December 31, 2014

Page 31: MTA CAPITAL PROGRAM MILESTONES

MTA BRIDGES AND TUNNELS

Page 29 as of December 31, 2014

Page 32: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Throgs Neck Bridge January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Throgs Neck Bridge Rehabilitation Program is to address the facility’s structural needs in order to maintain a state of good repair while also upgrading the bridge elements to current standards. Major work planned includes the replacement of roadway decks on the suspended span and approaches, rehabilitation of structural steel on suspended span and approaches, rehabilitation of the Bronx and Queens tower fender systems and painting of the approaches and tower fender systems.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Rehabilitation of Orthotropic Deck on Approach Spans and Painting of Bronx Approach Spans

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Complete Rehabilitation of Orthotropic Deck on Approach Spans and Painting of Bronx Approach Spans (December 2014)

0-6 Months:

7-12 Months:

13-24 Months:

Page 30 as of December 31, 2014

Page 33: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Bronx-Whitestone Bridge January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Bronx-Whitestone Bridge Rehabilitation Program is to perform work needed to maintain the bridge elements in a state of good repair and integrating the latest design standards in order to meet current and future capacity demand. Work planned at this facility will focus on the complete replacement of the Bronx and Queens Approaches including roadway deck slabs and superstructures, piers and pile foundation, repair of anchorages, and installation of necklace lighting.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Necklace Lighting Installation

Complete Bronx Anchorage Concrete Repairs

Complete Replacement of the Queens Approach

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program Summary: Previous 6 Months:

Complete Bronx Anchorage Concrete Repairs (August 2014)

0-6 Months: Complete Queens Approach Replacement (January 2015)

7-12 Months: Complete Necklace Lighting Installation (July 2015)

13-24 Months:

Page 31

as of December 31, 2014

Page 34: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Verrazano-Narrows Bridge January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Verrazano-Narrows Bridge Rehabilitation Program is to maintain the facility in a state of good repair by addressing ongoing structural needs of the facility and planning for the appropriate timing for improvements to be carried out. Work planned at this facility includes the replacement of the roadway deck on the suspended span, upgrade of toll plazas, and painting of the towers.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Staged Replacement of Eastbound Toll Plaza Ramps and Eastbound Staten Island Expressway Rehabilitation

Complete Substation #1 Rehabilitation

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program Summary: Previous 6 Months:

Complete Staged Replacement of East End Toll Plaza Ramps and E/B Staten Island Expressway Rehabilitation (November 2014)

0-6 Months:

7-12 Months:

13-24 Months: Complete Substation #1 Rehabilitation (June 2016)

Page 32 as of December 31, 2014

Page 35: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Robert F. Kennedy Bridge January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Robert F. Kennedy Bridge Rehabilitation Program is to continue efforts begun in 1995 to ensure that the facility and bridge elements are in a state of good repair. As a critical part of the regional network, continuous rehabilitation and maintenance of the bridge structure and upgrade of elements must be carried out to meet current standards and future demand in order to maintain a high level of service to customers. The most significant work planned at this facility includes the rehabilitation and reconstruction of the Bronx and Manhattan Toll Plazas, Manhattan Approach Ramps and replacement of the bridge deck’s wearing surface.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Deck Replacement of Manhattan-Queens Ramp

Start Deck Replacement and Painting of Bronx-Manhattan Ramps and Toll Plaza

Start Miscellaneous Rehabilitation of Manhattan Approach Ramps

Start Miscellaneous Structural Repair

Complete Design/Build Maintenance Facility

Start Painting of Plaza and Approach Ramps

Start Interim Repairs to Toll Plaza - Phase II

Complete Installation of CCTV & Fiber Optic Cable

Complete Design / Build Training Facility

Complete Miscellaneous Structural Repair

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program Summary: Previous 6 Months:

Complete Deck Replacement of Manhattan-Queens Ramp (August 2014) Start Deck Replacement and Painting of Bronx-Manhattan Ramps and Toll Plaza (December 2014) Start Miscellaneous Rehabilitation of Manhattan Approach Ramps (December 2014) Start Miscellaneous Structural Repair (December 2014) Complete Design/Build Maintenance Facility (August 2014) Start Painting of Plaza and Approach Ramps (September 2014) Start Interim Repairs to Toll Plaza – Phase II (October 2014)

0-6 Months:

7-12 Months: Complete Installation of CCTV & Fiber Optic Cable (April 2015) Complete Design/Build Training Facility (December 2015)

13-24 Months: Complete Miscellaneous Structural Repair (August 2016)

Page 33 as of December 31, 2014

Page 36: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Cross Bay and Marine Parkway Bridges January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the rehabilitation programs at the Cross Bay and Marine Parkway Bridges is to maintain the bridge structure and elements in a state of good repair. The ongoing needs of these facilities are carefully planned to minimize inconvenience to customers while ensuring proper coordination between the two bridges since they serve a common corridor. Major work planned at these facilities includes the rehabilitation of the Superstructure and Substructure elements of the Cross Bay and Marine Parkway Bridges.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Substructure and Underwater Scour Protection for Marine Parkway Bridge

Start Programmable Logic Controller & Mechanical Rehabilitation

Start Design/Build Rehabilitation of Rockaway Point Blvd Overpass

Complete Design/Build Rehabilitation of Rockaway Point Blvd Overpass

Start Design/Build Generator

Start Miscellaneous Steel Repairs & Structural Rehabiliation andPaint at Marine Parkway Bridge

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program Summary: Previous 6 Months:

0-6 Months: Start Design/Build Rehabilitation of Rockaway Point Blvd (January 2015) Start Miscellaneous Steel Repairs & Structural Rehabilitation and Paint at Marine Parkway Bridge (June 2015)

7-12 Months: Complete Substructure and Underwater Scour Protection Work for Marine Parkway Bridge (July 2015) Start Design/Build Generator (September 2015)Start Programmable Logic Controller & Mechanical Rehabilitation (November 2015)

13-24 Months: Complete Design/Build Rehabilitation of Rockaway Point Blvd (June 2016)

Page 34 as of December 31, 2014

Page 37: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Henry Hudson Bridge January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Henry Hudson Bridge Rehabilitation Program is to maintain the bridge elements in a state of good repair while minimizing inconvenience to the traveling public. B&T plans to continue these efforts by addressing rehabilitation needs of the upper level roadway deck and toll plaza area. In addition, the pilot project for All Electronic Tolling (AET) will be carried out at this facility.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Replacement of Toll Plazas and Southbound Approach

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Start Replacement of Toll Plazas and Southbound Approach (December 2014)

0-6 Months:

7-12 Months:

13-24 Months:

Page 35 as of December 31, 2014

Page 38: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Hugh L. Carey Tunnel January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Brooklyn Battery Tunnel (Hugh L. Carey Tunnel) Rehabilitation Program is to rehabilitate or replace deteriorated or outdated components of the facility and coordinating a sequence of projects that systematically address the needs of the various tunnel systems and elements while allowing for efficient tunnel operations. The most significant work planned at this facility includes the replacement of the electrical power system and rehabilitation of the tunnel roadway, wall, and ceiling.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Service Building Rehabilitation

Start Miscellaneous Repairs at Battery Parking Garage

Complete Replacement of Electrical Switchgear and Equipment

Start Replacement of Brooklyn Plaza Structural Slab

Start Rehabilitation of Walls, Roadway, Firelines and Ceiling Repair

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Start Service Building Rehabilitation (July 2014)Complete Replacement of Electrical Switchgear and Equipment (September 2014) Start Replacement of Brooklyn Plaza Structural Slab (December 2014) Start Rehabilitation of Walls, Roadway, Firelines and Ceiling Repair (December 2014)

0-6 Months: Start Miscellaneous Repairs at Battery Parking Garage (January 2015)

7-12 Months:

13-24 Months:

Page 36 as of December 31, 2014

Page 39: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Queens Midtown Tunnel January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of the Queens Midtown Tunnel Rehabilitation Program is to maintain the facility in a state of good repair while upgrading tunnel elements to current standards. Work planned at this facility will focus on mechanical and electrical needs, including the upgrade of the tunnel ventilation system.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Queens Service Building Garage Renovations

Start Entrance and Exit Plazas Structural Rehabilitation - Phase 1

Start Tunnel Wall and Ceiling Repairs and Leak Control - Phase 1

Complete Queens Service Building Garage Renovations - Phase 1

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program Summary: Previous 6 Months:

Start Queens Service Building Garage Renovations (October 2014)

0-6 Months: Start Entrance and Exist Plazas Structural Rehabilitation – Phase 1 (April 2015) Start Tunnel Wall and Ceiling Repairs and Leak Control – Phase 1 (April 2015)

7-12 Months:

13-24 Months: Complete Queens Service Building Garage Renovations (October 2016)

Page 37 as of December 31, 2014

Page 40: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Intelligent Transportation System Program January 2015 – December 2016 B&T Capital Program

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The goal of B&T’s ITS Program is to ensure that the systems and equipment used to support basic needs and services such as traffic management, safety, toll collection, and facility operations, are continuously improved and updated. As part of its on-going effort to enhance and implement the ITS Program, B&T will install and replace variable message signs (VMS) and upgrade toll systems and equipment based on established planned replacement intervals.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Installation of 2 VMS at Bronx-Whitestone Bridge

Complete Installation of 5 VMS at Verrazano-Narrows Bridge

Complete Installation of 2 VMS at Robert F. Kennedy Bridge

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

Complete Installation of 2 VMS at Bronx-Whitestone Bridge (September 2014)

0-6 Months: Complete Installation of 5 VMS at Verrazano-Narrows Bridge (April 2015)Complete Installation of 2 VMS at Robert F. Kennedy Bridge (April 2015)

7-12 Months:

13-24 Months:

Page 38 as of December 31, 2014

Page 41: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Super Storm Sandy Restoration Program January 2015 – December 2016 B&T Capital Program Verrazano-Narrows Bridge

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Restoration of MTA Bridges and Tunnels facilities affected by Super Storm Sandy.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Complete Restoration of Tower Base Electrical/Lighting Systems and Pedestrian Access Bridge

Start Restoration of Backup Communication Room

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program Summary: Previous 6 Months:

0-6 Months: Complete Restoration of Tower Base Electrical/Lighting Systems and Pedestrian Access Bridge (May 2015) Start Restoration of Backup Communication Room (May 2015)

7-12 Months:

13-24 Months:

Note: Milestones shown in the previous quarterly update but not shown in this update have been accomplished via Operating Budget.

Page 39 as of December 31, 2014

Page 42: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Super Storm Sandy Restoration Program January 2015 – December 2016 B&T Capital Program Marine Parkway Bridge

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Restoration of MTA Bridges and Tunnels facilities affected by Super Storm Sandy.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Design/Build Replacement of Marine Parkway Bridge Electrical Equipmentat North Abutment

Complete Replacement of Marine Parkway Bridge Lighting Systems

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months: Complete Replacement of Marine Parkway Bridge Lighting Systems (November 2014)

0-6 Months:

7-12 Months: Start Design/Build Replacement of Marine Parkway Bridge Electrical Equipment at North Abutment (September 2015)

13-24 Months:

Note: Milestones shown in the previous quarterly update but not shown in this update have been accomplished via Operating Budget.

Page 40 as of December 31, 2014

Page 43: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Super Storm Sandy Restoration Program January 2015 – December 2016 B&T Capital Program Hugh L. Carey Tunnel

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Restoration of MTA Bridges and Tunnels facilities affected by Super Storm Sandy.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Restoration of HCT (BBT) Structural

Start Restoration of HCT (BBT) Roadway

Start Restoration of HCT (BBT) Utilities

Start HCT (BBT) Environmental Cleanup-Construction Phase II

Start Construction of Tunnel Ventilation Door

Start Construction of Generator at Governor's Island

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months: Start Restoration of HCT (BBT) Structural (December 2014) Start Restoration of HCT (BBT) Roadway (December 2014) Start Restoration of HCT (BBT) Utilities (December 2014) Start BBT (HCT) Environmental Cleanup-Construction Phase II (December 2014)

0-6 Months: Start Construction of Tunnel Ventilation Door (February 2015) Start Construction of Generator at Governor’s Island Vent Building (June 2015)

7-12 Months:

13-24 Months:

Note: Milestones shown in the previous quarterly update but not shown in this update have been accomplished via Operating Budget.

Page 41 as of December 31, 2014

Page 44: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Super Storm Sandy Restoration Program January 2015 – December 2016 B&T Capital Program Cross Bay Bridge

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Restoration of MTA Bridges and Tunnels facilities affected by Super Storm Sandy.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Replacement of Cross Bay Bridge Mechanical and Electrical Equipmentin South Abutment and Service Building

Start Phase 2A of Restoration of Cross Bay Service Building

Start Phase 3 of Restoration of Cross Bay Service Building

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

0-6 Months:

7-12 Months: Start Replacement of Cross Bay Bridge Mechanical and Electrical Equipment in South Abutment and Service Building (September 2015) Start Phase 2A of Restoration of Cross Bay Service Building (September 2015) Start Phase 3 of Restoration of Cross Bay Service Building (September 2015)

13-24 Months:

Note: Milestones shown in the previous quarterly update but not shown in this update have been accomplished via Operating Budget.

Page 42 as of December 31, 2014

Page 45: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Super Storm Sandy Restoration Program January 2015 – December 2016 B&T Capital Program Queens Midtown Tunnel

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: Restoration of MTA Bridges and Tunnels facilities affected by Super Storm Sandy.

Prior 6 months Current (1/2015) 6Mo (7/2015) 12Mo (1/2016) 24 Mo (12/2016)

Start Remove Ceiling Tiles

Start Restoration of QMT Control/Communication Systems, CCTV and Traffic Signals

Start Environmental Cleanup - Construction Phase II

Start Restoration of QMT - Structural

Start Restoration of QMT Roadway

Start Backflow Preventer Installation

Milestone Type: Completion Progress Color Coding: 0-3 Mo Late 4-6 Mo Late >6 Mo Late Prior Capital Program

Summary: Previous 6 Months:

0-6 Months: Start Removing Ceiling Tiles (Feb 2015) Start Restoration of QMT Control/Communication Systems, CCTV and Traffic Signals (April 2015) Start Environmental Cleanup - Construction Phase II (April 2015) Start Restoration of QMT – Structural (April 2015) Start Restoration of QMT Roadway (April 2015) Start Backflow Preventer Installation (May 2015)

7-12 Months:

13-24 Months:

Note: Milestones shown in the previous quarterly update but not shown in this update have been accomplished via Operating Budget.

Page 43 as of December 31, 2014

Page 46: MTA CAPITAL PROGRAM MILESTONES

MTA CAPITAL CONSTRUCTION

Page 44 as of December 31, 2014

Page 47: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead

East Side Access January 2015 – December 2016 MTA Capital Construction

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The East Side Access Project will connect the Long Island Rail Road (LIRR) to Grand Central Terminal (GCT) in Manhattan. The scope of the project includes new tunnels in Manhattan and Queens, new tracks, crossovers, and bypasses within Harold Interlocking in Queens, a new terminal station underneath and within Grand Central Terminal, new street entrances, and new shops and yards. The new connection will increase the LIRR’s capacity to Manhattan, and dramatically shorten travel time for Long Island and eastern Queens commuters traveling to the east side of Manhattan.

Prior 6 Mo (7/2014) Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

NTP Issued for System Package 4 – Traction Power Procurement and Installation (CS084)Complete Construction of 44th St Vent Building in Manhattan (CM004)

NTP for GCT Concourse & Cavern Finishes (CM014B)Complete Construction of 55th Street Vent Facility (CM013A)Complete Harold Structures Part 2A (CH054A)

Complete Construction of GCT Concourse in Manhattan (CM014A)Complete Harold Structures Part 1 and GO2 Substation (CH053)

NTP to construct Harold Structures Part 3 (CH057)NTP Issued to construct Manhattan Cavern Structures and Fit-Out (CM007)

NTP Issued to Construct Harold Structures Part 3B & East Bound Reroute (CH058) Complete Construction of Manhattan South Structures (CM005)

Complete Plaza Substation & Queens Structures Construction (CQ032)Complete Construction of West Bound Bypass (CH057A)

Complete Construction of Manhattan North Structures (CM006)

Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior capital program

Summary:

Previous 6 Months: NTP Issued for Traction Power Systems; Complete Construction of 44th Street Vent Building in Manhattan

0-6 Months: NTP for GCT Concourse & Cavern; Complete Construction of GCT Concourse; Complete Construction of 55th Street Vent Facility; Complete Harold Structures Part 2A; Complete Harold Structures Part 1; NTP to Construct Harold Structures Part 3

7-12 Months: NTP to Construct Harold Structures Part 3; NTP for Manhattan Cavern Structures and Fit-Out

13-24 Months: NTP for East Bound Reroute; Complete Manhattan South Structures; Complete Plaza Substation & Queens Structures; Completion of West Bound Bypass; Complete Manhattan North Structures

Contract Descriptions: CM004 – 44th St Demolition, Construct Fan Plant

Structure & 245 Park Ave Entrance CM005 – Manhattan South Structures CM006– Manhattan North Structures CM007 – Manhattan Cavern Structures and Fit-Out CM013A – 55th Street Vent Facility in Manhattan CM014A – GCT Concourse CM014B – GCT Concourse & Cavern Finishes

CH053 – Harold Structures 1 CH054A – Harold Structures 2A CH057 – Harold Structures 3A & West Bound Bypass CH057A – West Bound Bypass Early Work CH058 – Harold Structures 3B & East Bound Reroute CQ032 – Plaza Substation & Queens Structures CS084 – System Package 4 – Traction Power Procurement and Installation

VS086 – Signal Systems Procurement

Page 45 as of December 31, 2014

Page 48: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Second Avenue Subway January 2015 – December 2016 MTA Capital Construction

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The Second Avenue Subway includes tunnels from 105th Street and Second Avenue to 63rd Street and Third Avenue, with new stations along Second Avenue at 96th, 86th and 72nd Streets and new entrances to the existing Lexington Avenue/63rd Street Station at 63rd Street and Third Avenue. This project will reduce congestion on the Lexington Avenue line and improve access to mass transit for residents of the far East Side of Manhattan. Stations will have elevator connections from street-level to station mezzanine to platforms in compliance with the Americans with Disabilities Act.

Prior 6 Mo (7/2014) Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Complete 86th Street Station Structure Contract (C-26008)

Complete 63rd Street Station Upgrade (C-26006)

Complete 86th Street Station Finishes Contract (C-26012)

Complete 72nd Street Station Finishes Contract (C-26011)

Complete Systems Contract (C-26009)

Complete 96th Street Station Finishes Contract (C-26010)

SAS (Phase 1) - Revenue Service

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior capital program

Summary: Previous 6 Months: Complete 86th Street Station Structure Contract

0-6 Months:

7-12 Months: Complete 63rd St Station Upgrade Contract

13-24 Months: Complete 72nd Street Station, 86th Street Station, and 96th Street Station Finishes Contracts; Complete Systems Contract; SAS (Phase 1) – Revenue Service

Contract Descriptions: C-26006 – 63rd Street Station Upgrade C-26008 – 86th Street Station Mining & Lining C-26009 – Systems C-26010 – 96th Street Station Finishes C-26011 – 72nd Street Station Finishes C-26012 – 86th Street Station Finishes

Page 46 as of December 31, 2014

Page 49: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead 7 Line Extension January 2015 – December 2016 MTA Capital Construction

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The 7 Line Extension will extend the existing 7 Line from its current terminal at Times Square to 11th Avenue and 34th Street. The scope of the project includes construction of over a mile of new tunnels and a new terminal station at 34th Street and 11th Avenue. The project will support planned development on the far west side of Manhattan and provide improved transit access to the Javits Convention Center.

Prior 6 Mo (7/2014) Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Complete - Canopy at Site J Main Entrance

Complete Systems & Finishes - Revenue Service

Complete - Site P - Secondary Station Entrance

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior capital program Summary: Previous 6 Months:

Complete Canopy at Site J Main Entrance

0-6 Months: Complete Systems & Finishes Contract – Revenue Service

7-12 Months:

13-24 Months: Complete Site P Contract

Page 47 as of December 31, 2014

Page 50: MTA CAPITAL PROGRAM MILESTONES

24 Month Look-ahead Fulton Center January 2015 – December 2016 MTA Capital Construction

Note: Further information on capital project milestones can be found on the MTA Capital Program website: http://web.mta.info/capital/

Program Description: The Fulton Center project at the corner of Fulton Street and Broadway will improve connections to the Lower Manhattan stations of existing subway lines: 4/5, A/C, J/Z, 2/3, R, 1 and E. The project will include a new Fulton Center building, underground passageways, improved mezzanine and platform access and improved American with Disabilities access. These investments will improve travel for hundreds of thousands of daily commuters, Lower Manhattan residents and visitors and better connect the subway with the World Trade Center site, PATH transit services and the World Financial Center.

Prior 6 Mo (7/2014) Current (1/2015) 6 Mo (7/2015) 12 Mo (1/2016) 24 Mo (12/2016)

Turnover Dey Street Concourse (4E)

Opening of new escalator to John Street (4G)

Opening of Corbin Building (4G)

Opening of Transit Center Building (4F)

Milestone Type: Completion Progress Color Coding: On-Time 4-6 Mo Late >6 Mo Late Prior capital program Summary:

Previous 6 Months: Turnover Dey Street Concourse; Opening of new escalator to John Street; Opening of Corbin Building; Opening of Transit Center Building

0-6 Months:

7-12 Months:

13-24 Months:

Contract Descriptions: 4E – Dey Street and R Underpass Finishes 4F – Transit Center Building 4G – Corbin Building Reconstruction

Page 48 as of December 31, 2014