Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager

Upload: clancy

Post on 23-Feb-2016

46 views

Category:

Documents


0 download

DESCRIPTION

Mu2e WGM. 2/22/2011 R. Ray Mu2e Project manager. CD-1. Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be ready for the review we must complete the following: Cost and Schedule, BOEs CDR Other Project Documentation Development of cost range - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Mu2e WGM

Mu2e WGM

2/22/2011

R. RayMu2e Project manager

Page 2: Mu2e WGM

R. Ray - Mu2e WGM 2

CD-1

• Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5.

• To be ready for the review we must complete the following: Cost and Schedule, BOEs CDR Other Project Documentation Development of cost range Respond to recommendations from Independent Design Review Prepare presentation materials

• A lot of work still remains to be ready.

Page 3: Mu2e WGM

R. Ray - Mu2e WGM 3

Cost & Schedule Development

WBS &WBS DictionaryResources:

•Labor hours•Materials FY12$

Schedule:•Activities•Durations •Predecessors

Primavera P6 Schedule

Timephase activities, resources

Cobra Cost ProcessorRate TablesPrice Resources

ResourcesActivities, Durations

Burdened/Escalated Cost

Page 4: Mu2e WGM

R. Ray - Mu2e WGM 4

Cost, Schedule, BOEs

• Likely to come down to the wire.• Change of resource names set us back. Still trying to catch up on BOEs.• Costs entered into P6 in $FY12. Labor entered in hours. 1 FTE = 1768 hrs.• Off project tasks will be tracked in Mu2e schedule using milestones.• Calorimeter scope divided between INFN and DOE (~85/15)

DOE pays for ~20% of crystals, FEE and calibration system. Track INFN work using milestones Most likely cost is the cost for the DOE scope (fully loaded including contingency) Low end of the range is 0 High end of the range is full cost to build the calorimeter in the US.

• Initial set of milestones identified and split into tiers. Still have to look at the distribution in time and will likely identify a few more.

• Still need Milestone Dictionary.

Page 5: Mu2e WGM

R. Ray - Mu2e WGM 5

CDR Requirements (from DOE O 413.3b)

A Conceptual Design Report (CDR) shall be developed that includes: • A clear and concise description of the alternatives analyzed, the basis for the alternative

selected, how the alternative meets the approved mission need • the functions and requirements that define the alternative and demonstrate the capability

for success, Programmatic requirements discussed in Acquisition Strategy and referenced in CDR chapter 2. Description of how design flows from Mission Need to requirements documents and the

alternative analysis Discussion of alternative analysis, selection and satisfaction of requirements in subsystem

chapters.

Mission Need

Statement

Mu2e Scientific Proposal

Subsystem Definition Requirements

Evaluate Alternatives

Set of Selected

Alternatives

Design Reviews

Simulations

Page 6: Mu2e WGM

R. Ray - Mu2e WGM 6

CDR Requirements

• Facility performance requirements Included in the Conventional Construction chapter

• Planning standards and life-cycle cost assumptions. Mu2e-doc-524. Recently updated for new scope. Summarized in CDR. Includes

power, cryogens, maintenance, D&D.• The CDR should also clearly and concisely describe the KPPs that will form

the basis of the PB at CD-2. Included in PEP and CDR 

o Capability to slow extract 8 GeV protons from the Debuncher Ring and transport them through the Muon Campus External Beamline to the Mu2e Production Target.

o Solenoid system has been cooled down, powered and demonstrated to run at nominal field strength.

o Tracks from cosmic ray muons have been observed in the detector and recorded by the data acquisition system.

Page 7: Mu2e WGM

R. Ray - Mu2e WGM 7

CDR

• Mature draft was shown to the IDR team in May.

• Significant scope changes result in necessary changes to CDR in many places.

Solenoid and Accelerator chapters essentially being re-written

Significant changes to conventional construction Smaller number of changes to other sections

• Solenoid fields have changed a little, so we are re-running backgrounds and sensitivities.

Page 8: Mu2e WGM

R. Ray - Mu2e WGM 8

CDR Scope DescriptionNew front end of the CDR describes the scope of the Mu2e project and the scope of off project contributions that are required by Mu2e

Page 9: Mu2e WGM

R. Ray - Mu2e WGM 9

CD-1 Requirements

• Approve an Acquisition Strategy with endorsement from OECM Draft sent to Headquarters for comment

• Approve a preliminary Project Execution Plan (PEP) Draft set to Headquarters for comment

• Establish and charter an Integrated Project Team Established over a year ago. Meets regularly.

• Comply with the One-for-One Replacement legislation Space offset received in 2009 (Mu2e-doc-1051). Enough for Mu2e but not

enough for Muon Campus. Planned demolition before Mu2e construction begins will make up for shortfall.

• Identify general Safeguards and Security requirements for the recommended alternative.

Security Vulnerability Assessment document (Mu2e-doc-676). o Theft, vandalism, computer security are the primary issues.

Page 10: Mu2e WGM

R. Ray - Mu2e WGM 10

CD-1 Requirements

• Document High Performance and Sustainable Building provisions and Sustainable Environmental Stewardship considerations in the Conceptual Design Report, Acquisition Strategy, and/or PEP, as appropriate.

Strategy described in PEP and CDR. Because facility will generally be unoccupied we don’t have to comply with LEED Gold standard. Will instead comply with LEED Guiding Principles.

• Conduct a Design Review of the conceptual design with reviewers external to the project.

IDR completed in May. Subsystems with significant technical changes due to scope reduction will be reviewed for technical feasibility as part of Directors Review in April.

• Complete a Conceptual Design Report. Nearly there.

Page 11: Mu2e WGM

R. Ray - Mu2e WGM 11

CD-1 Requirements - Risk

• Develop a Risk Management Plan (RMP) and complete an initial risk assessment of a recommended alternative.

Risk Management Plan completed over a year ago. Detailed Risk registry exists. Undergoing final update before review. Includes information that will be used to generate cost range.

From DOE Risk Management Guide - DOE G 413.3-7

Page 12: Mu2e WGM

R. Ray - Mu2e WGM 12

CD-1 Requirements - Safety

• An Integrated Safety Management System (ISMS) must be in place to ensure that potential hazards are identified and appropriately addressed throughout the project (refer to DOE P 450.4). It will be used to systematically integrate safety into management and work processes at all levels.

Project ES&H coordinator appointed. Oversight by Divisions & Sections Safety integrated into Lab management at all levels.

o Project embedded in Lab’s line Management • Prepare a Preliminary Hazard Analysis Report

Done. Updated for new scope. Under review by FSO. • Establish a Quality Assurance Program

Mu2e-doc-677 Custom QA/QC plan tailored to each L2 subsystem discussed in CDR

subsystem chapters

Page 13: Mu2e WGM

R. Ray - Mu2e WGM 13

Fermilab Integrated Safety Management for Mu2e Project

Define Work Scope

Provide Feedback

Perform Work Within

Controls

Develop & Implement

Hazard Controls

Analyze Hazards

• Encompasses R&D, safety, environment, security, quality, cyber security

• Makes ES&H and quality intrinsic to every job and project

• NEPA process for Mu2e addresses potential impacts of project execution and subsequent operation

• Preliminary Hazard Analysis Report catalogues hazards in all phases of project, and provides a solid basis for project design, planning, and execution

Page 14: Mu2e WGM

R. Ray - Mu2e WGM 14

Additional DocumentsDocument Current Status Notes

CDR Revisions nearly done

Acquisition Strategy Being reviewed by Headquarters

Project’s part complete. DOE’s document now

Project Execution Plan Being reviewed by Headquarters

Still have to agree on change control thresholds

RLS In progress Will be tight for April 3.

Draft Configuration Management Plan

Done Good enough for CD-1

Project Management Plan Almost done Needs input from cost & schedule.

Preliminary Hazard Analysis Updated for new scope Under review by FSO

WBS dictionary Out-of-date draft

Risk Management Plan Done

Risk registry Working on final updates

Need one more cycle through with L2 managers and Risk manager

QA Plan Done Good enough for CD-1. Significant revision expected fro CD-2

Security Vulnerability Assessment

Done

Page 15: Mu2e WGM

R. Ray - Mu2e WGM 15

Cost Range

• We will use our Risk/Opportunity register to generate a cost range

Risks∑High End = Most likely cost + Cost

Opportunities∑Low End = Most likely cost + Cost

• This approach approved by Lehman’s Office• However, we have many more threats than opportunities, so most likely cost

will be closer to low end than high end in this approach.• Need to work harder to identify more opportunities

Most likely cost = base + contingency

Page 16: Mu2e WGM

R. Ray - Mu2e WGM 16

Examples

From the Mu2e Risk Registry• Potential Problem:

Tevatron HTS leads in storage do not work • Cause:

HTS leads, in storage for the past 10 years, no longer function• Consequence:

Worst case, would be if the power leads failed to perform. In which case the leads would have be redesigned and fabricated

• Mitigation: We will test all of the leads early to assure that the leads in fact do work.

• Probability/Impact/Risk Low/High/High

• Cost Impact: $1M

Page 17: Mu2e WGM

R. Ray - Mu2e WGM 17

Examples

From the Mu2e Risk Registry• Potential Opportunity:

DOE advances project funding profile, providing money sooner than anticipated. • Cause:

Decision by DOE based on requirement to manage their entire program in response to funding changes, changes in priority, delays in other projects, etc.

• Consequence/Benefit: Overall schedule is accelerated, which has the potential to reduce costs and add

flexibility to the project. • Mitigation:

Always have a plan for advancing the schedule if money is available sooner. • Probability/Impact/Risk

Moderate/Moderate/Moderate• Cost Impact:

Burn rate is about $800k/month. Assume a 3 month schedule advance. $2400k

Page 18: Mu2e WGM

R. Ray - Mu2e WGM 18

Schedule to get to CD-1

We are hereMaterials posted by March 16

Page 19: Mu2e WGM

R. Ray - Mu2e WGM 19

RLS Schedule