![Page 1: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/1.jpg)
Charlie Torres, Project Manager
February 2019
Mukilteo Multimodal Project: Building a modern ferry terminal
Presentation to Puget Sound
Regional Council
![Page 2: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/2.jpg)
Building a modern ferry terminal:
• Mukilteo/Clinton route
• Costs and funding
• Project need
• Understanding place
• Partnership
• Partners
• Design
• Timeline
• Foundation
2
![Page 3: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/3.jpg)
The Mukilteo/Clinton route
The state’s busiest route for
people who drive onto the
ferry.
• carries 2.3 million
vehicles per year
• and 4.2 million riders
per year
3
![Page 4: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/4.jpg)
Cost and funding
Funding overview
• $167 million budget:
• $72.2 million in
federal funds
• $94.8 million in
state funds
4
![Page 5: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/5.jpg)
Project need
5Aerial photo from 2014
![Page 6: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/6.jpg)
6
Building a modern ferry terminal:
understanding place
![Page 7: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/7.jpg)
7
Building a modern ferry terminal:
understanding place
![Page 8: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/8.jpg)
8
Building a modern ferry terminal:
understanding place
![Page 9: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/9.jpg)
Building a modern ferry terminal:
understanding place
9
![Page 10: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/10.jpg)
Partnership: land ownership
10
![Page 11: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/11.jpg)
Forged a relationship and partnership
with our tribal communities:
• Tulalip Tribes
• Swinomish Tribe
• Suquamish Tribe
• Stillaguamish Tribe
• Snoqualmie Tribe
• Sauk-Suiattle Indian Tribe
• Samish Indian Tribe
11
Building a modern ferry terminal:
tribal partners
![Page 12: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/12.jpg)
Building a modern ferry terminal:
more partners
12
• FTA
• WSDOT
• State Historic Preservation Officer
• Advisory Council on Historic Preservation
• United States Army Corps of Engineers
• City of Mukilteo
• City of Everett
• Port of Everett
• Sound Transit
• Community Transit
![Page 13: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/13.jpg)
Design inspiration: a Longhouse
13
![Page 14: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/14.jpg)
Design inspiration: a Longhouse
14
![Page 15: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/15.jpg)
Design: cultural elements
![Page 16: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/16.jpg)
Design: cultural elements
16
![Page 17: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/17.jpg)
Design: cultural elements
17
![Page 18: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/18.jpg)
Design: cultural elements
18
![Page 19: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/19.jpg)
19
Design: light on the Earth
![Page 20: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/20.jpg)
Design: managing stormwater
• Pervious concrete
• Engineered wetlands –
rain gardens
• Capture and reuse
stormwater runoff from
buildings
Photo from Portland, Ore.
![Page 21: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/21.jpg)
Design: planning for a rising sea level
Existing storm conditions
![Page 22: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/22.jpg)
Timeline
22
![Page 23: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/23.jpg)
The foundation
23
![Page 24: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/24.jpg)
A site that once held ten fuel storage
tanks …
24
![Page 25: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/25.jpg)
… transformed into a modern
multimodal ferry terminal
25
![Page 26: Mukilteo Multimodal Project - Puget Sound Regional Council · 2/22/2019 · Charlie Torres, Project Manager February 2019 Mukilteo Multimodal Project: Building a modern ferry terminal](https://reader033.vdocuments.net/reader033/viewer/2022042809/5f94afd1b7b25a22d50cb2ec/html5/thumbnails/26.jpg)
Questions?
26