multi-family development forum - cps energy · juan mendez –mf designer [email protected]...

29
Multi-Family Development Forum Monday, March 20, 2017

Upload: others

Post on 21-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

Multi-Family

Development Forum

Monday, March 20, 2017

Page 2: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

AGENDA/TOPICS

• Welcome and Introductions

• “People First” Focus/Why We Are Here

• Safety Message

• Customer Growth/CSI Project Update

• Subdivision “Turnkey” Construction Process Results

• Discussion of Multi-Family Construction Options

• Explanation of Multi-Family “Turnkey” Construction

Process

• Natural Gas in Multi-Family Projects

• Q&A/Open Discussion

• Closing

2

Page 3: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

3

OUR FOCUS - PEOPLE FIRST

Page 4: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

WHY WE ARE HERE

• Growth and expansion experience

• CPS commitment to support multi-family

development and economic growth

• Purpose: Share construction options for

multi-family projects and improve

communication

4

Page 5: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

5

1. Working safe is a way of life.

2. Leaders own their team’s safety performance.

3. Leaders begin meetings with a safety message.

4. Leaders model the behavior to achieve ZERO HARM.

5. We take the time to do every job safely.

6. We keep coworkers out of harm’s way.

7. Employees are trained to work safely.

8. Employees have the right to stop any job.

9. We conduct peer to peer safety observations.

10. Taking short-cuts is prohibited.

ACTIVELY CARING FOUNDATION

Page 6: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

6

CAPITAL SPEND(CUSTOMER REQUESTS)

$0.0

$10.0

$20.0

$30.0

$40.0

$50.0

$60.0

$70.0

$80.0

2010 2011 2012 2013 2014 2015 2016

Total Capital Spend (in millions)

Residential Services

Subdivisions

Multi-Family

Commercial Services

Large Commercial

Total capital spend for electric customer requests increased from $32M to $71.2M in 6 years (123% increase).

Page 7: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

7

ELECTRIC & GAS METER SETS

Total electric meter sets increased 76% over the last 6 years (gas meter sets increased 27%)

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

2011 2012 2013 2014 2015 2016

Total Elec Single-Family Multi-Family Commercial Gas

Page 8: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

ELECTRIC & GAS METER SETS

IN 2016

8

Page 9: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

9

CONSTRUCTION SERVICE IMPROVEMENT STRATEGIC OBJECTIVES

Date Management and Customer Commitments

Scope complete, but on-going effort

- Improved OTC rate

- Reduced durations

- Notification pilot

Continue to Improve the Customer Experience and their Satisfaction with CPSE New Construction Services and Processes

• Enhanced process that incorporates the pre-application stages of the customer relationship

• Enhanced web enabled business service execution process

A Proactive, Next Generation Customer Experience for New Construction

• Proactive engagement with customers early in the new development process

• Proactive promotion of energy services and products to customers at the conceptual stage of new developments

• New solution capabilities

• On site design and estimation with the customer

Ph

ase O

ne

Inte

rim

De

livery

2016

2017

2018

Full

De

livery

Solution vendor selected

Long Term Solution Strategy Next Generation Solution Implementation

Page 10: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

10

INTERIM DELIVERY PHASE

New Web Portal

• 24/7 Project status

• Initiate applications via web

• Create Request for Service

• Grouping of work by project and customer

• Attach documents and drawings

People / Process

• Enable customer feedback channels

• Better established and documented processes

• More accurate dates for construction

Page 11: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

11

FULL DELIVERY PHASE

More Technology Enhancements

• More web portal features of work flow

• User preference & communication management on web

• Enable customers to view status via mobile

• Enable design work to be performed on-site

People / Process

• Better visibility by project and dependent tasks

• Better trained staff

• Continuous feedback from customers to prioritize process improvements

Page 12: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

SUBDIVISION TURNKEY

CONSTRUCTION PROCESS• CPS Energy began offering the subdivision turn-key

construction process through a pilot in July 2015

• The pilot was expanded as an option for all

subdivisions in June 2016

• To date, a total of 122 subdivisions have been

constructed using the turn-key construction process,

(consisting of 6,679 residential lots) in an average of

24 working days

• Today, nearly all new subdivisions are being

constructed utilizing this methodology

12

Page 13: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

CURRENT PROCESS

CPS ENERGY-MF INSTALL • CPSE Contractor installs electric primary cable and

gas infrastructure

• CPS Energy Crews:

– install OH poles, primary

– terminate primary connections (URD)

• Developer installs secondary conduits and

secondary services for electric and gas

• CPSE Service & Meter Crews terminate secondary

cable & set electric and gas meters (when customer

ready)

13

5 CONSTRUCTION MOBILIZATIONS

(4 CPSE/1 DEVELOPER)

Page 14: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

CURRENT PROCESS

MF DEVELOPER-INSTALL • Developer installs electric primary cable and gas

infrastructure

• CPS Energy Crews:

– install OH poles, primary

– terminate primary connections (URD)

• Developer installs secondary conduits and secondary

services for electric and gas

• CPSE Service & Meter Crews terminate secondary cable &

set electric and gas meters (when customer ready)

14

5 CONSTRUCTION MOBILIZATIONS

(3 CPSE/2 DEVELOPER)

Page 15: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

NEW CONTRACTOR TURNKEY

MF CONSTRUCTION• CPSE Contractor:

– installs primary cable

– Installs gas infrastructure

– installs OH poles, primary

– terminates primary connections

• Developer installs secondary conduits and secondary

services for electric and gas

• CPSE Service & Meter Crews terminate secondary

cable & set electric and gas meters (when customer

ready)

15

3 CONSTRUCTION MOBILIZATIONS

(2 CPSE/1 DEVELOPER)

Page 16: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

MF TURNKEY CONSTRUCTION

PROCESS

1. Identify multi-family development project as eligible for turn-key

construction process in pre-design phase (single-phase electric only)

2. Explain and discuss turn-key construction criteria with developer, project

manager and builder

3. Customer’s representative will contact the Designer to schedule a site

inspection when the turn-key construction criteria have been met

4. Site inspection will be conducted and any deficiencies identified, if needed

5. Pre-construction is held with designer, customer and contractor

6. OH construction can begin immediately, UG construction will typically

begin within 2 weeks of pre-construction meeting

16

Page 17: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

MF TURNKEY CONSTRUCTION

CRITERIA1. At least 80% of wet utilities (mains only) installed

– To reduce conflicts and damage to CPSE facilities after installation

2. Engineer/surveyor immediately available to provide center

line staking, and staking of OH poles

– For proper placement of above ground facilities at proper grade,

avoid other in-ground facilities and allow OH work to begin

immediately

3. All trench paths within 6“ of final subgrade

– To allow installation of facilities at standard/required depth

4. All trench paths cleared of obstructions

– For expedited trenching, flowable fill pouring and job completion

17

Page 18: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

MF TURNKEY CONSTR.

CRITERIA (CONT.)5. Minimal activity from other contractors on site (see flexibility slide)

– For expedited trenching, flowable fill pouring and job completion

6. All site criteria verified prior to scheduling Pre-Construction

Meeting

– To reduce the unnecessary mobilization of crews

7. Environmental approved and signed off

– Expectation for Customer Engineering to avoid delays

8. All Work Request segments approved and released to

construction

– Expectation for Customer Engineering to avoid delays and allow for

OH construction to begin immediately after per-construction meeting

18

Page 19: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

FLEXIBILITY IN TURNKEY

CONSTRUCTION PROCESS

• The Developer’s Crews can start working behind CPS

Energy Crews upon approval from the CPS Energy

Turnkey Crew Lead, typically five business days after

the CPS Energy Turnkey Crew begins work.

• CPS Energy Turnkey Crews will coordinate their work

with the Site Superintendent.

19

Page 20: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

ADDITIONAL BENEFITS OF

TURNKEY CONST. PROCESS• Construction typically completed within 15-20 working

days

• All infrastructure except service conduits installed by CPS

Energy

• Energized and ready for temporary service requests

• Reduced site congestion

• One-time CPS Energy Contractor mobilization increasing

efficiency for all developers

• OH work can start early as long as ROW paths are clear

20

Page 21: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

NATURAL GAS IN MF

DEVELOPMENT

• CPS Energy is committed to providing a

complete energy solution to meet all of your

needs.

• CPS Energy gas business continues to grow as

community see the benefits of natural gas.

21

Page 22: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

NATURAL GAS IN MF

DEVELOPMENT

• Natural Gas is a clean, reliable and domestic

energy option for achieving overall energy

efficiency and lowering overall energy costs for

developers and tenants.

• Gas appliances can be utilized in many different

types of multi-family facilities for space heating,

water heating, ranges, dryers, outdoor

appliances, backup power and many more

applications….

22

Page 23: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

NATURAL GAS IN MF DEVELOPMENT-

TYPICAL APPLICATIONS

• Natural Gas Boilers and

Furnaces can provide

heat faster and are more

economical overall.

• Natural gas water heating

can provide savings over

alternatively sourced

systems and can recover

in 1/3rd the time.

23

Page 24: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

NATURAL GAS IN MF DEVELOPMENT-

ADDITIONAL APPLICATIONS

• Natural gas fireplaces,

fire pits, patio heaters

and gas lights can

create the convenience

and ambience you want

to create.

24

Page 25: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

NATURAL GAS IN MF DEVELOPMENT-

SUPPORT APPLICATIONS

• Natural gas generators can

keep critical power on during

electric outages.

• Supplies power during outages

for designated critical

equipment such as HVAC

equipment, elevators,

refrigerators, essential lighting

or anywhere electricity is

required.

25

Page 26: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

GAS INFORMATION

• Natural Gas can be a key component of a developments

overall energy solution.

• Coordination of facilities installation done through single

point of contact.

• Support information relative to gas facility installations can

be found on-line at CPSEnergy.com within the “Summary

of Gas Service Standards Manual for Engineers, Architects,

Contractors and Developers.” https://cpsenergy.com/content/dam/corporate/en/Documents/Gas_Service_Stan

dards_CPSEnergy.pdf

• We look forward to working with you to meet all of your

energy needs.

26

Page 27: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

CONTACT INFORMATION

27

Name/Title Email Phone

Richard Rodriguez – MF Supv. [email protected] (210) 353-2366

Juan Mendez – MF Designer [email protected] (210) 353-2080

Dorothy Woodson – MF Designer [email protected] (210) 353-3592

Shawn Cobb - Manager [email protected] (210) 353-2348

Shawn Eddy – Sr. Director [email protected] (210) 353-8840

David Luschen – Sr. Director [email protected] (210) 353-4942

Page 28: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

YOUR VOICE

IS IMPORTANT TO US!

28

Join the Web Portal Input Session!

Be a part of the solution on: • Tuesday, March 28 • 2 p.m. – 4 p.m.• 17281 N. Green Mountain Rd. (Blade room)

CSI Focus Group Kickoff Schedule – March 2017• Prototypes (Demo and Functionality) – May 2017• Customer Acceptance Testing – Mid-June 2017 • Go Live – July 24, 2017

• Sign up today! http://conta.cc/2mK13VT

Page 29: Multi-Family Development Forum - CPS Energy · Juan Mendez –MF Designer jumendez@cpsenergy.com (210) 353-2080 Dorothy Woodson –MF Designer dwwoodson@cpsenergy.com (210) 353-3592

29

QUESTIONS?