multinational 225 kv guinea-mali electricity ... · v project summary 1. general project overview...

40
AFRICAN DEVELOPMENT FUND MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY INTERCONNECTION PROJECT RDGW DEPARTMENT November 2017 Translated Document Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 27-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

AFRICAN DEVELOPMENT FUND

MULTINATIONAL

225 KV GUINEA-MALI ELECTRICITY INTERCONNECTION

PROJECT

RDGW DEPARTMENT

November 2017

Translated Document

P

ubli

c D

iscl

osu

re A

uth

ori

zed

P

ubli

c D

iscl

osu

re A

uth

ori

zed

Page 2: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

TABLE OF CONTENTS

Currency equivalents, Weights and Measures, Acronyms and Abbreviations i Project Information Sheet iii

Project Summary v

Results-based Logical Framework vii

Project Implementation Schedule viii

1. STRATEGIC THRUST AND RATIONALE 1 1.1. Project Linkages to Country Strategies and Objectives 1 1.2. Rationale for Bank’s Involvement 2 1.3. Aid Coordination 2

2. PROJECT DESCRIPTION 3

2.1. Project Description and Components 3

2.2. Technical Solution Adopted and Alternatives Considered 4

2.3. Project Type 5 2.4. Project Cost and Financing Arrangements 5 2.5. Project Area and Beneficiaries 7 2.6. Participatory Approach to Project Identification, Design and Implementation 7

2.7. Bank Group Experience and Lessons Reflected in Project Design 8 2.8. Key Performance Indicators 8

3. PROJECT FEASIBILITY 9 3.1. Economic and Financial Performance 9 3.2. Environmental and Social Impact 9

4. PROJECT IMPLEMENTATION 12 4.1. Implementation Arrangements 12

4.2. Monitoring 15 4.3. Governance 16

4.4. Sustainability 16 4.5. Risk Management 17 4.6. Knowledge Development 17

5. LEGAL FRAMEWORK 18 5.1. Legal Framework 18

5.2. Conditions Associated with the Bank’s Intervention 18 5.3. Compliance with Bank Policies 19

6. RECOMMENDATION 19

Annex I: Situation of the Electricity Sub-sectors in Guinea and Mali

Annex II: Comparative Socio-economic Indicators of Guinea and Mali

Annex III: Portfolio of Current Bank Operations in Guinea and Mali Annex IV: Major Related Ongoing Projects Financed by the Bank and Other

Development Partners Annex V: Map of the Project Area

Annex VI: Rationale of request for waiver for the project to be financed over

90% by the Bank and other donors

Page 3: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

i

Currency Equivalents July 2017

UA 1 = 799.76245 XOF

UA 1 = 1.21923 EUR

UA 1 = 1.39139 USD

UA 1 = 12481.18 GNF

Fiscal Year 1 January – 31 December

Weights and Measures

1 kilometre (km) = 1,000 m

1 km² = 1,000,000 m²

1 kilovolt (kV) = 1,000 Volt (V)

1 kilovolt-Ampere (kVA) = 1,000 Volt – Ampere (VA)

1 kilowatt (kW) = 1,000 Watt

1 megawatt (MW) = 1,000,000 W = 1 000 kW

1 Gigawatt (GW) = 1,000,000 W = 1 000 kW

1 kilowatt-hour (kWh) = 1,000 Watt/hour = 3,600,000 Joules (J)

1 megawatt-hour (MWh) = 1,000,000 Wh = 1,000 kWh

1 gigawatt-hour (GWh) = 1,000,000 kWh = 1,000 MWh

1 tonne of oil equivalent (TOE) = 41,868 Joules = 11,630 kWh

1 million tonne of oil equivalent (MTOE) = 1,000,000 TOE

Acronyms and Abbreviations

ADF African Development Fund

AFIF/EU Africa Investment Facility/European Union

BD Bidding documents

CE Consultant Engineer

CNS National Monitoring Committee

CO2 Carbon Dioxide

CREDD Strategic Framework for Economic Recovery and Sustainable Development DEPI Directorate for Studies, Planning and Infrastructure

DNE National Directorate for Energy

DPD Detailed Preliminary Design

ECOWAS Economic Community of West African States

EDG Electricité de Guinée (Electricity Corporation of Guinea)

EDM-SA Energie du Mali - Ltd

ERR Economic Rate of Return

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

EUR Euro

FIRR Financial Internal Rate of Return

GDP Gross Domestic Product

GHG Greenhouse Gas

HDI Human Development Index

HV High Voltage

ICB International Competitive Bidding

IDA International Development Agency

IEC Information, Education and Communication

IMF International Monetary Fund

IsDB Islamic Development Bank

Page 4: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

ii

IUCN International Union for the Conservation of Nature

KFAED Kuwait Fund for Arab Economic Development LV Low Voltage

MDGs Millennium Development Goals

MV Medium Voltage

NCB National Competitive Bidding

NPV Net Present Value

OMVG Gambia River Basin Development Organisation

OMVS Senegal River Basin Development Organisation

PNDES Economic and Social Development Plan PRSP Poverty Reduction Strategy Paper

RBCSP Results-based Country Strategy Paper

RP Resettlement Plan

SL Short List

SME Small and Medium-sized Enterprises

SMI Small and Medium-sized Industries

SNE National Electricity Corporation

SOFRO Strategic and Operational Framework for Regional Operations

TO Turnover

TORs Terms of Reference

UA Unit of Account

WAPP West African Power Pool

Page 5: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

iii

PROJECT INFORMATION SHEET

BORROWERS : REPUBLIC OF GUINEA AND THE REPUBLIC OF MALI

DONEES : REPUBLIC OF GUINEA AND THE REPUBLIC OF MALI

EXECUTING AGENCIES : ELECTRICITE DE GUINEE ET ENERGIE DU MALI SA

Financing Plan

SOURCES AMOUNTS IN UA MILLION

INSTRUMENT GUINEA MALI TOTAL

ADF (PBA) 6.64 6.44 13.08 Loan

5.36 5.56 10.92 Grant

ADF (RO) 9.96 9.66 19.62 Loan

8.04 8.34 16.38 Grant

Total LOANS 16.60 16.10 32.70 Loan

Total GRANTS 13.40 13.90 27.30 Grant

TOTAL ADF 30.00 30.00 60.00

AFIF/EUROPEAN UNION 22.71 1.89 24.61 Grant

WORLD BANK 52.90 11.04

63.93 Loan

EBID 29.47 0.00

29.47 Loan

EIB 31.61 0.00

31.61 Loan

WADB 0.00 21.93

21.93 Loan

IsDB 57.71 0.00

57.71 Loan

REPUBLIC OF GUINEA 9.16 -

9.16

National

Development

Budget

REPUBLIC OF MALI - 1.22

1.22 National budget

TOTAL 233.55 66.09 299.63

Key Financial Information on the Bank Loan and Grant

ADF loans to Guinea and Mali ADF grants to Guinea and Mali

Loan/Grant currency Unit of Account (UA) Unit of Account (UA)

Interest Type Not applicable Not applicable

Interest rate margin Not applicable Not applicable

Service Charge 0.75% per year of the disbursed loan

amount not reimbursed Not applicable

Commitment fee

0.5% of the loan amount not disbursed

120 days after signature of the Loan

Agreement

Not applicable

Maturity 40 years Not applicable

Grace period and ADF loan repayment 10 years Not applicable

Page 6: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

iv

Timeframe – Main Milestones (expected)

Concept note approval July 2017

Project approval December 2017

Effectiveness of ADF grants December 2017

Effectiveness of ADF loans February 2018

Last disbursement of ADF resources December 2021

Completion June 2022

Final Repayment November 2061

Page 7: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

v

Project Summary

1. General Project Overview

1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011 during

an AfDB project supervision mission to Guinea, involves the construction of a double-circuit

transmission line over 714 km and associated transformer substations between the town of

N'zérékoré in Guinea and Sanankoroba (Bamako) in Mali, passing through the localities of

Beyla, Kerouane, Kankan, Fomi and Siguiri in Guinea. This transmission line is part of the

West African Power Pool (WAPP) investment programme and will be connected to other 225

kV lines being constructed in the sub-region (namely the OMVG, CLSG and OMVS lines).

Hence, it will interconnect Zone A countries (Benin, Burkina Faso, Côte d'Ivoire, Ghana,

Nigeria, Niger and Togo) to Zone B countries (The Gambia, Guinea, Guinea-Bissau, Mali,

Liberia, Senegal and Sierra Leone) of the WAPP. The project will contribute to the socio-

economic development of Mali and Guinea through community access to better quality and

affordable electricity. Costing a total of UA 200.63 million, the project will be implemented

over a five-year period (2018-2021).

1.2. The project’s direct beneficiaries are future customers of Energie du Mali (EDM-SA)

and Electricité de Guinée (EDG) in localities where the line passes in Haute Guinée, Guinée

Forestière and the Manding area in Mali as well as all current customers of EDM-SA who will

have more reliable and affordable electricity supply through the interconnected power grid.

With electricity in these areas of Guinea and Mali, it would be easy to set up new mining

companies and create sustainable jobs for the local communities whose living conditions would

improve as a result. Better energy supply to businesses (including agricultural undertakings)

would cut production costs, stimulate small-scale processing of agricultural produce and boost

agro-industry. Women and the youth in the project area would be able to develop agricultural,

trade, craft and semi-industrial and income-generating activities. The project will have a

positive impact on the schooling in the communities that will be electrified, as children would

be able to study late into the evening because their schools and homes are lit. It will contribute

to the creation of the regional electricity market and enable EDM-SA and EDG to cut their

production costs. The use of hydroelectricity will also lead to reduced consumption of

hydrocarbon products and, consequently, reduced greenhouse gas emissions, thus having an

overall positive impact on the environment. Beneficiaries will also help to strengthen project

impact through awareness campaigns to encourage good behaviour by collaborating with EDG

and EDM-SA to combat fraud and vandalism on transmission lines.

2. Needs Assessment: The inadequacies of the electricity sub-sector in both Guinea and

Mali are well known. These include: (i) a relatively low electricity access rate (18% in Guinea

and 41% in Mali) with an inordinately wide disparity between urban and rural areas; (ii) limited

production capacity relative to supply needs in Mali and limited transmission and distribution

networks in Guinea; (iii) low technical and financial capacities of national electricity companies

(EDG and EDM-SA); (iv) production costs that exceed the selling price, etc. The objective of

this project is to eliminate these constraints by focusing on building stakeholder capacity,

providing Mali with good quality and affordable energy and helping Guinea to cut its operating

costs, increase its electricity export revenue and expand its local customer base.

3. Bank’s Value-added: Fully cognizant of the relevance of the project in terms of

connectivity and integration, the Bank-financed studies in 2011 that yielded reports which were

finalised in 2017 and informed project preparation. The Bank’s involvement in the project’s

financing as lead donor designated by the recipient States, and its experience in structuring and

financing similar projects, facilitated the mobilisation of six other donors who have agreed to

participate in the funding.

Page 8: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

vi

4. Knowledge Management: As lead donor, the Bank will continue to facilitate

consultations among the technical and financial partners during project implementation;

encourage information and data sharing among donors; and organise periodic joint reviews and

project supervision missions. The success achieved and any difficulties jointly addressed by the

donor community will be used to supplement the data from the monitoring and evaluation

mechanism set up within the project management units and the monthly control and supervision

reports of the engineering consultant. The Bank will use all these data to prepare and develop

similar operations in future.

Page 9: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

vii

RESULTS-BASED LOGICAL FRAMEWORK

MULTINATIONAL - 225 kV GUINEA-MALI ELECTRICITY INTERCONNECTION PROJECT

Project Goal: To enable power-sharing between Guinea and Mali in order to improve community access to affordable electricity.

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION RISKS/

MITIGATING MEASURES Indicator (including ISCs)

Baseline

situation

(2016)

2022 Target

IMP

AC

T The living conditions of project area communities are

improved through greater access to quality and

affordable electricity.

Electricity access rate in Guinea

Electricity access rate in Mali.

18%

41%

50%

54%

- Energy ministry statistics in

Guinea and Mali;

- Activity reports of EDM-SA and

EDG and monitoring/evaluation

reports of project management

units in each of the countries.

OU

TC

OM

ES

1. Energy is effectively transmitted from Guinea to

Mali through the 225 kV line.

2. The quantity of greenhouse gases emitted in the

project area is reduced.

3. Human potential and employability in the project

area are strengthened.

4. The socio-economic conditions of women are

improved.

1 1 Quantity of electricity traded (GWh/year)

1.2 Average production cost of one kWh in Mali

(CFAF/kWh)

1.3 Number of households connected by the project

2 Quantity of CO2 avoided (t/year)

3.1 Number of jobs created

3.2 Number of young interns (M/F) trained

4.1 Number of women trained per income-generating activity

0

127

0

0

0

0

0

800 to 1500

90

18,000

including 30%

headed by

women

12,150,000 T

875 (including

15% for

women)

75 (including

50% for

women)

3000

Risks

1 Weak financial capacity of national electricity companies to ensure

the sustainability of constructed infrastructure.

2 Under-utilization of the 225 kV line due to unavailability of energy

in Guinea.

Mitigating Measures:

1 Improvement of the management of electricity companies through

reforms. The EDG currently has a management contract with an

international firm. In Mali, major reforms are envisaged for EDM-SA

in the short term.

2 The Souapiti power plant (450 MW) is under construction and the

first generator should be operational in 2020 and the entire system in

2021; the Linsan-Fomi line will also be available in 2020. Furthermore,

even with a two-year delay in Souapiti, the power generation facilities

in Guinea would produce a surplus that should satisfy all or most of the

demand in Mali during this period and the rest through the CLSG line

from other countries, including the Côte d'Ivoire.

OU

TP

UT

S

1 The interconnection line is constructed

2 HV/MV substations are constructed or reinforced

3 The institutional capacity of electricity sub-sector

stakeholders is strengthened

4 Localities situated along the 225 kV line are electrified

5 Project audit and progress reports are prepared

6 Studies for new operations are conducted.

1. 225 kV line constructed (km)

2. Number of HV/MV substations constructed

3. Number of male/female employees trained

4. Number of project area localities electrified

5. 1 Number of progress reports produced

5.2. Number of audit reports approved

6. Reports of feasibility studies and ESIAs available

0

0

0

0

0

0

0

714 km

7

60 (including

30% for

women)

201

32

10

2

Quarterly project progress reports

Monthly reports of the consulting

engineer

Project completion report, audit

reports.

Risks

Limited experience of EDM-SA and EDG in the implementation of

projects of such a scale with several TFPs

Mitigating Measures

Training of the staff of the PMUs, support of PMUs by international

experts who will be recruited. Also, a consulting engineer will be

recruited to support both PMUs. The joint funding of donors on certain

lots to reduce calls to tender is envisaged.

KE

Y A

CT

IVIT

IES

COMPONENTS

Component 1: Construction of the electricity infrastructure (225 kV line, seven MV/MV substations, electrification of localities along the 225 kV line)

Component 2: Institutional support: various training courses, logistical support, conduct of feasibility studies for priority projects.

Component 3: Project management (operation of PMUs, works control and supervision, audit, IEC-ME campaigns)

Resources: UA 299.63 million Expenditure UA 299.63 million

ADF loans and grants UA 60 million Component 1: UA 263.63 million Other Donors: UA 229.25 million Component 2: UA 8.75 million States: Guinea-UA 9.16 million/ Mali-UA 1.22 million Component 3: UA 27.25 million

Page 10: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

viii

Project Implementation Schedule

ITEM

2017 2018 2019 2020 2021

7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6

Recruitment of the key staff of the PMU

Project approval by Board

Signature of loan agreement and grant protocol

Effectiveness of grant protocol

Effectiveness of loan agreement

Lifting of the conditions precedent to first disbursement of ADF resources

First disbursement of ADF resources

A. Electricity Infrastructure

Recruitment of the consulting engineer for the line and signature of contract

Recruitment of the companies for the line works and signature of the contracts

Compensation of persons affected by the project (PAPs)

Construction of the 225 kV interconnection lines and associated stations

Monitoring and supervision of construction works on the 225 kV line

Recruitment of companies to build the grids in localities situated along the line

Construction of distribution networks in the neighbouring localities

Recruitment of the consulting engineer for the distribution networks/signature of the contract

Control and supervision of the construction of distribution networks

B. Institutional support

Miscellaneous training

Recruitment of consultants and conduct of various studies

C. Project Management

Monitoring, control and evaluation by the PMU

Audit of project accounts

Page 11: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

1

REPORT AND RECOMMENDATIONS OF MANAGEMENT TO THE BOARD OF

DIRECTORS CONCERNING FINANCING OF THE 225 KV GUINEA-MALI

ELECTRICITY INTERCONNECTION PROJECT

Management submits this report and recommendations on: (i) proposals to award ADF loans

of UA 16.6 million and UA 16.1 million to the Republic of Guinea and the Republic of Mali

respectively; (ii) proposals to award ADF grants of UA 13.4 million and UA 13.9 million to the

Republic of Guinea and the Republic of Mali respectively, to finance the 225kV Guinea-Mali

Electricity Interconnection Project.

1. STRATEGIC THRUST AND RATIONALE

1.1. Project Linkages to the Strategies and Objectives of both Countries

1.1.1. The objectives of the Guinea-Mali electricity interconnection project reflect the visions

of the governments of both countries. These visions as set out in their sector policy letters are

aimed at supplying quality and affordable electricity to the largest number of people. The

project will help to eliminate major electricity sub-sector development constraints in Mali and

Guinea, including: (i) an electricity production deficit relative to demand; (ii) the high

predominance of thermal power in the energy mix; and (iii) the low electricity access rate in

communities located along the line.

1.1.2. The project is fully consistent with the priorities of both countries as expressed in their

respective strategy documents. In Guinea, the main target of the National Economic and Social

Development Plan (PNDES 2016-2020) under its Pillar 2 (Sustainable and Inclusive Economic

Transformation) is universal, community, regular, modern and affordable energy by 2030. In

Mali, the first strategic pillar (Inclusive and Sustainable Economic Growth) of the Economic

Recovery and Sustainable Development (CREDD2016-2018) focuses on energy infrastructure

development as a priority.

1.1.3. The objectives of this project are fully consistent with the Bank’s country strategy

papers for Guinea and Mali. Indeed, Pillar 2 (Development Support Infrastructure) of Guinea's

CSP (2012-2017) is aimed at reducing the energy production deficit by developing electricity

production and interconnection infrastructure between the countries of the sub-region

consistent with the two pillars of the Bank's CSP for Mali (2015-2019) namely: "Enhancing

Governance for Inclusive Growth" and "Infrastructure Development to Support Economic

Recovery". Moreover, the project is consistent with the Bank’s Regional Integration Strategy

Paper (RISP 2011-2015 extended to 31 December 2017) for West Africa whose Pillar I focuses

on the development of regional electricity production and transmission infrastructure.

1.1.4. At the sub-regional level, the project is an integral part of the West African Power Pool

(WAPP) project which stems from the energy development strategy of the Economic

Community of West Africa States (ECOWAS).

1.2. Rationale for Bank Involvement

1.2.1 The project was identified in 2011 by the Bank, as a key link in the electricity

interconnection of the countries in the sub-region. The technical and environmental feasibility

issues of the project were financed in the same year by the Bank and the reports, finalised in

2017, were used to prepare and evaluate it.

1.2.2 Given their low national electricity access rates (41% for Mali and 18% for Guinea),

both countries have financially unprofitable electricity sub-sectors. This situation stems from

several factors, namely: (i) the lack of backbone investments in electricity infrastructure

Page 12: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

2

(production, transmission and distribution); (ii) the quality of governance; and (iii) the

applicable pricing policies. The Guinea-Mali electricity interconnection project, with its

transmission capacity of 500MW, will enable Mali to import approximately 800 GWh of

hydroelectricity annually, at an average cost of CFAF 92/kWh relative to the current production

cost of CFAF 130/kWh; cover its energy deficit (estimated at 150 MW in 2017) during at least

the first five years of operation and thus increase the national electricity access rate. The project

will help Guinea, not only to improve its export earnings but also to increase its national

electricity access rate by electrifying a significant part of the national territory (the East region

which is composed of Haute Guinée and Guinée Forestrière) which currently has irregular

power supply from generators that are costly to operate. It will also help to build backbone

electricity infrastructure at the regional level and a major regional electricity market through

the progressive interconnection of national grids into a single regional interconnected system.

Indeed, at N’Zérékoré, the project transmission line will be connected to the CLSG (Côte

d'Ivoire, Liberia, Sierra Leone and Guinea) interconnection line, and at Linsan it will be

connected to the interconnection line of OMVG countries through the Linsan-Fomi segment

(whose studies are being finalised with Bank funding and financing for the works has already

been raised from Guinea’s other technical and financial partners).

1.2.3 Several other reasons underpin the Bank’s intervention in the financing of the project,

including:

i) the consistency of certain project objectives (grid interconnection between the

two countries, raising of electricity access rates and improvement of living

conditions) with at least three of the Bank’s five key priorities (High-5s) namely:

to light up and power Africa; to integrate Africa; and to improve living

conditions for the people of Africa;

ii) the project's consistency with the Bank's energy policy which seeks to support

regional member countries in their efforts to improve access to modern, reliable

and affordable energy;

iii) the project's alignment with the 2014-2018 gender strategy, especially its

women’s empowerment pillar (multipurpose platforms will be constructed for

women’s groups in the project area); and

iv) the project's alignment with the Bank's youth employment policy (apart from

direct employment for women and the youth, during the works and operational

phases, the project will offer the first professional internship to at least 75 young

graduates) as well as its consistency with the objectives of the Bank's Ten-Year

Strategy (2013-2022) whose two strategic objectives are inclusive growth and

transition to green growth.

The Bank's intervention will help to raise project funding from resources of the EU's Africa

Investment Facility (AFIF/EU) and those of other donors.

1.3. Aid Coordination

1.3.1 The table below summarizes funding volumes to the electricity sub-sector over the

past five years in both countries. Annex 3 presents the technical and financial partners and their

respective funding volumes to the beneficiary countries of this project. These interventions are

coordinated within thematic working groups of which the Bank is an active member in each of

the countries. Furthermore, the preparation and appraisal of this project were jointly conducted

by the various donors concerned under the coordination of the WAPP Secretariat General. As

Page 13: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

3

the project’s main donor, the Bank organises a monthly conference call between donors and

WAPP to harmonise viewpoints and plan the project’s next steps.

Table 1.3:

Donor funding volume in the electricity sub-sector in Guinea and Mali

Electricity sub-sector

Volume

GDP Exports Labour

Guinea 0.58% 0% 1.0 %

Mali 0.3 % 0% 1%

Stakeholders – Annual public expenditure (2012-2016)*

Government Donors

GUINEA-UA 217 million (32%) UA 462 million (68%) ADF (6.01%), IDA (5.74%), Eximbank China (65.58%), other donors (22.67%)

MALI - UA 300.8 million (42%)

UA 415.74 million

(58%) WADB (7.5%), IsDB (4.8%), Eximbank China (14.7%), other donors (31.0%)

Aid coordination level

GUINEA MALI

Existence of thematic working groups in the sub-sector Yes Yes

Existence of a global sectoral programme Yes No

AfDB role in aid coordination Member Member

2. PROJECT DESCRIPTION

2.1. Project Description and Components

2.1.1. The main development objective of the project is to consolidate the electricity trade

between Guinea and Mali in particular, and among West African countries in general; and to

ensure the socio-economic development of both countries through greater community access to

regular and affordable electricity. More specifically, the project seeks to: (i) establish grid

interconnection between Guinea and Mali, (ii) strengthen ongoing grid interconnection works

under the CLSG, OMVS, and OMVG projects in the sub-region; and (iii) promote the

connection of households to the electricity network in both countries.

2.1.2. The project entails building a 225-kV double-circuit alternating-current transmission

line over a distance of approximately 714 km, between the town of Sanankoroba in Mali and

that of N'zérékoré in Guinea (passing through Fomi in Guinea) and the construction of

transformer substations in Siguiri, Fomi, Kankan, Kerouane, Beyla and N'Zérékoré (Guinea),

and in Sanankoroba (Mali). It comprises three main components detailed in the table below.

Page 14: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

4

Table 2.1

Project components (amounts in UA million)

No. Name of components Cost

estimate Description of components

A

Construction of

electricity infrastructure

263.63

(i) Construction of a 225 kV (alternating current) double-circuit

transmission line of 714 km between the two countries; (ii)

construction of five HV/MV transformer substations and the

extension of two other 225kV/30kV stations; (iii) electrification

of 201 localities (121 in Guinea and 80 in Mali) located near the

transmission line; and (iv) management of the environmental

and social impacts of the project.

B Institutional support

8.75

(i) Capacity building for electricity sub-sector stakeholders in

both countries (various training courses and logistical support to

national electricity corporations and national directorates for

energy) and the Secretariat of the West African Power Pool

(WAPP); (ii) conduct of feasibility studies and environmental

and social impact assessments for certain priority projects

featured in the investment plan to prepare for future donor

interventions in both countries.

C Project management 27.25

(i) Operation of the project management units (PMUs) and the

Supranational Steering Committee; (ii) works control and

supervision (225 kV line and distribution network); (iii) project

audit; (iv) energy and women's empowerment; (v) recruitment

and training of 75 interns, young graduates, comprising 30 in

Mali and 45 in Guinea.

Total project cost 299.63

2.2 Technical Solution Adopted and Alternatives Considered

2.2.1 The construction of a 225 kV (alternating current) double-circuit interconnection line was

adopted for the national electricity interconnection of Guinea and Mali. The operating voltage

of the line (225 kV) has been retained in the production and transmission master plan adopted

by ECOWAS Heads of State and Government to take account of the fact that this segment of

line will be integrated with other lines of the same voltage being constructed in the sub-region

(CLSG and OMVG interconnection lines and the OMVS network in particular) and electricity

transmission needs, not only between Guinea and Mali, but also between the other countries of

West Africa.

2.2.2 Alternatives to the abovementioned solution were studied but abandoned for the reasons

outlined in the table below:

Table 2.2

Alternative Solutions Considered and Reasons for Rejection

Alternative Solution Brief Description Reason for Rejection

Continuation of the

development of national

systems

Each of the two countries will

continue to face the challenge of

satisfying growing demand using

its own generally costly power

generation facilities

Regular supply is not guaranteed

Average production cost per kWh is higher

Higher pollution because electricity would be

generated mainly through thermal power

plants fired with petroleum products.

Cross-border medium-

voltage electrification in

Haute-Guinée, Guinée

Forestière and Koulikoro

(Mali).

Electrifying the regions through

the medium-voltage networks in

neighbouring countries,

especially Côte d'Ivoire

The electrification coverage will be very

limited because the voltage cannot cover long

distances;

The available capacity in Côte d'Ivoire will not

be able to cover the needs of all regions

concerned.

Page 15: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

5

2.3 Project Type

2.3.1 The 225 kV Guinea-Mali electricity interconnection project is an autonomous

multinational operation for the construction of an electricity transmission network linking the

two countries. The financing mechanisms proposed are ADF loans and grants that would be

awarded to Guinea and Mali in accordance with the ADF XIV lending policy and the Strategic

Framework for Regional Operations.

2.4 Project Cost and Financing Arrangements

2.4.1 The total project cost, net of taxes and customs duties, is evaluated at UA 299.63

million. This cost includes a 5% provision for physical and technical contingencies and a 5%

provision for price escalation, and will be financed up to 20% by the Bank. Project costs by

component, financing source and expenditure category are presented in Tables 2.3, 2.4 and 2.5

below:

Table 2.3

Estimated costs by component

Amount (in UA million) % Foreign

exchange Components F.E. Local

currency Total

Construction of electricity infrastructure 207.63 32.03 239.66 87%

Institutional support 5.57 2.39 7.96 70%

Project management 17.34 7.43 24.78 70%

Base Cost 230.54 41.85 272.39 85%

Physical contingencies 11.53 2.09 13.62 85%

Provision for price escalation 11.53 2.09 13.62 85%

Total project cost 253.60 46.04 299.63 85%

2.4.2 The project will be co-financed by the World Bank (WB), the European Union, IsDB,

EBID, EIB, WADB, ADF and the Governments of Guinea and Mali. The WADB approved

the project in 2016 and the EBID approved it in October 2017. The other donors intend to

submit it to their respective Boards within the first semester of 2018.

Table 2.4

Project Financing Sources

Financing Sources

Amount (in UA million)

% Total F.E.

Local

currency Total

ADF 51.26 8.74 60.00 20.0%

IsDB 51.94 5.77 57.71 19.3%

EBID 26.52 2.95 29.47 9.8%

EIB 28.45 3.16 31.61 10.5%

WADB 19.62 2.31 21.93 7.3%

EU/AFIF 20.34 4.26 24.61 8.2%

World Bank 55.10 8.83 63.93 21.3%

Government of Guinea 0.21 8.94 9.16 3.1%

Government of Mali 0.15 1.07 1.22 0.4%

Total project cost 253.60 46.04 299.63 100%

2.4.3 The ADF resources are grants and loans awarded under the conditions indicated in the

project information sheet on Page iii, which were negotiated and accepted by the two

governments (the exchange rates adopted are those that feature on Page i).

Page 16: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

6

2.4.4 Evidence of the low participation of Guinea and Mali in the project’s financing is

presented in Annex VI of this report.

2.4.5 Project cost by expenditure category is presented as follows:

Table 2.5

Project costs by expenditure category

Expenditure categories

Amount (in UA million) % Foreign

exchange F.E. Local

currency Total

Works 228.39 35.24 263.63 87%

Goods 1.62 0.69 2.31 70%

Services 13.69 5.87 19.56 70%

Operation and miscellaneous 9.90 4.24 14.14 70%

Total project cost 253.60 46.04 299.63 85%

2.4.6 The expenditure schedule by project component is as follows:

Table 2.6

Expenditure schedule by component

Components Amount (in UA million)

2,018 2,019 2,020 2,021 Total

Construction of electricity infrastructure 52.73 79.09 92.27 39.54 263.63

Institutional support 2.19 2.63 3.06 0.88 8.75

Project management 5.45 8.18 9.54 4.09 27.25

TOTAL 60.36 89.89 104.87 44.51 299.63

% Total 20.1% 30.0% 35.0% 14.9% 100.0%

2.4.7 In Guinea, ADF resources will be used to finance the total cost of the 225kV/30kV

station in Fomi, the Fomi-Kankan segment of the line (43.3 km) and part of the construction

works for the distribution networks in localities situated near the 225 kV line, institutional

support and project management. In Mali, the ADF resources will fund part of the cost of the

Sanankoroba (Mali)-Guinea/Mali border segment (125.6 km), construction works on the

distribution networks in localities along the 225 kV line, institutional support and project

management.

Table 2.7

ADF resources by expenditure category

Expenditure categories

Amount (in UA million) % Foreign

exchange F.E. Local

currency Total

Works 41.69 4.63 46.32 90%

Goods 1.62 0.69 2.31 70%

Services 5.70 2.44 8.14 70%

Operation 2.26 0.97 3.23 70%

Total 51.26 8.74 60.00 85%

2.4.8 The EU/AFIF grant resources managed by the Bank under the PAGODA agreement

will be used to finance consultancy studies for works supervision on the line and part of the

construction works in localities situated along the project line in each country. Since these

resources are grants exclusively, they will supplement the loans granted to the project by the

other donors.

Page 17: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

7

Table 2.8

AFIF/EU resources by expenditure category

Expenditure categories

Amount (in UA million) % Foreign

exchange F.E. Local

currency Total

Works 14.03 1.56 15.59 90%

Services 6.31 2.71 9.02 70%

Total 20.34 4.26 24.61 83%

2.5 Project Area and Beneficiaries

2.5.1 The project area covers two administrative regions in Guinea and one in Mali. The two

regions of Guinea are: (I) Haute Guinée with a surface area of 103,235 km² and an estimated

population of 2,645,453 inhabitants and (ii) Guinée Forestière with a surface area of 122,600

km² and a population of 1,947,191 inhabitants. These two regions comprise 7 prefectures, 21

rural council areas and 4 urban council areas. In Mali, it is the Koulikoro region, which is the

second administrative region of Mali, comprising 07 cercles and extending over 90,120 km²,

with 2 418,305 inhabitants, of which 50.4% are women.

2.5.2 The project will directly benefit, not only the two national electricity companies (EDG

and EDM-SA) which will reduce their electricity production costs, but also the 201 localities

(comprising 121 in Guinea and 80 in Mali) and their inhabitants who will have access to

electricity and thus improve their living conditions. It will improve the quality of electricity

supplied to all EDM customers though the interconnected national network and lead to the

connection of at least 18,000 households. The works phase will employ approximately 825

people, including 15% of women/girls who will hold over 50 permanent jobs during the

operational phase. As regards socio-professional integration, at least 75 young graduates, 50%

being girls, will be able to perform their first internships, thus enhancing their employability.

The project will also enable industries and businesses, especially in the mining and agricultural

sectors, to boost their activities and thus have a clear impact on employment in the sub-region.

2.6 Participatory Approach to Project Identification, Design and

Implementation

2.6.1 In accordance with AfDB and national policies, the Governments of Guinea and Mali

adopted a participatory and inclusive approach. Hence, the project was designed based on a

feasibility study conducted in collaboration with all the stakeholders (electricity companies,

energy ministries, communities located along the project line, local administrative authorities,

youth and women’s organisations, artisans’ groups, etc.). During preparation of the ESIA and

the full resettlement plan (FRP), public consultations were held in Mali and Guinea, with the

national, regional and municipal authorities and village chiefdoms to hear their expectations

on the development of the various project facilities. Furthermore, the communities and

women's groups in project area localities were consulted to determine their fears, expectations

and wishes about the project. Lastly, a survey was conducted targeting persons affected by the

project to inform them, make an inventory of their damaged property and define compensation

conditions.

2.6.2 This participatory approach will be maintained and reinforced during project

implementation in Guinea and Mali through a regional stakeholders commitment plan (SCP).

The SCP will be implemented by the PMU in close collaboration with the communities

affected by the project, local authorities and the heads of decentralised institutions. The Bank

Page 18: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

8

posted a summary of the ESIA and FRP on its website on 8 August 2017, that is, 120 days

prior to submission of the project to its Board of Directors.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 To date, the Bank’s portfolio in Guinea has had no problematic projects; it comprises

four projects for which first disbursements have not been made, although the contracts have

been awarded and disbursements will soon be made. In Mali, the portfolio has no problematic

project; one project is classified as potentially problematic and three have not yet been the

subject of any disbursements although the contracts have been signed and the first

disbursements will be made soon. However, the Bank's portfolio reviews conducted in 2016

as well as its project supervision and completion reports for these two countries have revealed

three types of recurrent project implementation problems. These are: (i) the late

commencement of projects due to insufficient ownership by the national counterpart; (ii)

procurement delays especially in the signing of contracts by national authorities; and (iii)

limited human capacity for project implementation.

2.7.2 Furthermore, the Bank's diverse experience in financing and monitoring the

implementation of multinational infrastructure projects, as evident in various supervision and

completion reports, reveals several challenges that need to be addressed to improve project

performance. These difficulties essentially stem from: (i) the multiplicity of stakeholders with

different technical and operational capabilities; (ii) poor coordination and harmonisation of

project activities in the various countries; (iii) the shortcomings of national electricity

companies (NECs) including their financial situation, no technical monitoring of the activities,

and procurement difficulties; (iv) delays in lifting fund disbursement conditions; and (v) delays

in raising government counterpart funds, which retard the compensation of project affected

persons and consequently, project commencement. Actually, the Bank has financed several

multinational and multi-donor projects in the electricity sub-sector, the most recent being the

Manantali Project of the Senegal River Basin Development Organisation (OMVS), the

NELSAP Interconnection Project, the CLSG interconnection project and the grid

interconnection project of OMVG countries.

2.7.3 The project design took into account all the elements listed above. To address noted

shortcomings, provision is made for: (a) a supranational steering committee supported by the

WAPP Secretariat General to coordinate the activities of the project management unit in each

country; (b) capacity building for national stakeholders and WAPP (training and logistical

support); (c) appointment of the key PMU staff members prior to project approval (they are

already in place and are working to prepare the relevant documents with a view to fulfilling

the conditions precedent to the first disbursement of ADF resources); (d) the use of advance

procurement action to gain time and (e) sensitisation of both governments on the need to

schedule national counterpart funds in their 2018 budgets.

2.8 Key Performance Indicators

2.8.1 Project performance will be measured through performance indicators detailed in the

results-based logical framework. The project’s main performance indicators are: (i) the

quantity of energy exchanged through the interconnected network; (ii) the decline in the

average production cost per kWh in Mali; (iii) the electricity access rate in the project area;

(iv) the volume of greenhouse gases avoided per year; and (iv) the number of direct and

indirect jobs by gender created. The project outputs are: (i) the operation of a 225-kV

transmission line; (iii) the construction of 5 new substations; and (iv) the reinforcement of two

transformer stations.

Page 19: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

9

2.8.2 The data on these performance indicators will be provided through quarterly project

progress reports produced by the PMUs and monthly reports of the engineering consultant, the

reports of the joint supervision missions of donors, including the Bank, and project completion

reports (of the Borrowers and the Bank).

3 PROJECT FEASIBILITY

3.1 Economic and Financial Performance

Table 3.1

Key Economic and Financial Data of the Project

Baseline Scenario ERR 21.28% % ENPV EUR 312 million

3.1.1 Economic Performance of the Project: The project’s economic performance was

analysed based on the economic rate of return (ERR) generated from a comparison of updated

costs (investment and operation of the electricity systems) in both countries in the “no project”

(two separate and autonomous grids) and “project” situations. The economic costs used to

calculate the economic rate of return (ERR) and the economic net present value (ENPV) are

project costs net of taxes and the provision for price escalation, adjusted with the appropriate

conversion factor for equipment, works, services and labour. Maintenance costs and the other

operating costs were processed in the same manner. This comparative analysis showed that the

project generates a substantial economic rate of return compared to the "no project" situation

and therefore constitutes the most advantageous situation (see technical annex in Table B.7).

3.1.2 Financial Performance of the Project: The project impact analysis was limited to

economic impacts. Indeed, financial analysis of the project based on the rates currently

applicable in Guinea and Mali could lead to the conclusion that the project is not financially

profitable for both companies. Indeed, the current average rates charged to customers by EDM-

SA and EDG do not cover the average production cost per kWh and it is a well-known fact that

an increase in rates is necessary to ensure that both companies are in a comfortable financial

situation. The argument for building an interconnection line despite the lack of immediate

financial profitability at current rates is that, apart from its obvious economic profitability, the

project will greatly improve electricity supply in the regions concerned at an affordable cost

and thus facilitate the subsequent application of rate increase measures. Besides, future use of

the line by neighbouring countries that will be interconnected subsequently, will increase transit

income for EDG and EDM-SA and improve their respective financial situations.

3.1.3 Sensitivity Analysis of Project Performance The project was analysed in terms of: (i)

a 10% increase in investment costs; (ii) a 10% increase in operating expenses; and (iii) a two-

year delay in the operation of the line. The analysis revealed that the economic rate of return,

though highly sensitive to late implementation of the project, remained higher than the

economic cost of capital estimated at 10% in both countries, thus confirming the economic

viability of the project.

3.2 Environmental and Social Impact

3.2.1 Environment

The 225 kV Guinea-Mali Electricity Interconnection Project is classified in category 1, from

the environmental and social standpoints. Hence, its design included a complete environmental

and social impact assessment (ESIA), an Environmental and Social Management Plan (ESMP)

and a full resettlement plan (FRP) for persons affected by the project. The ESIA, ESMP and

the FRP were validated in each country and by the Bank and the relevant summaries were

Page 20: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

10

posted on the Bank’s website on 8 August 2017 in accordance with the applicable requirements.

An environmental and social analysis of the project is presented in Technical Annex B8.

3.2.1.1 Negative Impact

The most significant negative impacts expected during construction of the line relate to the loss

of land, vegetation and wildlife habitat. The project will have a negative impact on: (i) the

diversity of plant ecology and local flora; (ii) the bird life, primate population and other fauna

as well as the fragmentation of their environments; (iii) the ecosystem services of the wetlands

and alluvial valleys of the Tinkisso, Niger and Milo rivers; (iv) the ecosystem services of the

humid agro-forests in Guinea Forestière; and (v) the crossing of RAMSAR sites. It will also

lead to deforestation owing to the clearing of an eight-metre-wide strip (included in the 40-

metre corridor), free of any crops and trees and sometimes skirting classified forests, to build

the interconnection line. Its impact is also evident in: (vi) the clearing of 2,842 ha of forest land,

comprising 598 ha of wooded savannah in Mali, and 1,119 ha of wooded savannah, 916 ha of

woodlands and 209 ha of rain forest in Guinea. It will also affect (vii) 2,022 people, including

1,686 in Guinea and 336 in Mali.

In the operational phase, the main impacts on air quality will relate to transport and traffic,

periodic clearing of the right-of-way and access to the 225 kV lines. Maintenance work on the

rights of way is likely to: (i) disrupt or destroy wildlife and their habitats by opening up easy

access through the right-of-way. Impacts related to the presence of equipment, include: (i) risk

of electrical accidents for the local population, (no exploitation of the farmland beneath the

lines, near the transformer substations and in the permanent access areas.

3.2.1.2 Positive Impact

During the construction phase, the project will create a number of economic opportunities (jobs,

boosting of local production) that may not, however, equitably benefit the poor. The human

development impacts are: (i) improvement of the socio-economic conditions of the local

communities through the monetary benefits earned from construction workers paying for

sundry services; (ii) collection of felled trees by the local population for other uses (wood fuel,

charcoal, carpentry, etc.); (iii) creation of direct temporary jobs and indirect jobs during

construction; (iv) development of new access roads; and (v) the fact that the 40-metre cleared

corridor would serve as a barrier against bush fires.

The most significant positive impact is the electrification of the villages along the transmission

line. This will (i) improve quality of life for almost 1,220,000 inhabitants; (ii) boost the

productivity of enterprises, create new income-generating activities and extend the working day

thanks to street lighting (opening of new services, sale of frozen products, opening of

workshops, etc.); (iii) improve the quality of public services, including health and education

and expand access to information and entertainment technologies; (iv) offer periodic

employment opportunities to project area youth through maintenance works (cleaning of the

line corridor) and (v) boost the productivity and competitiveness of women entrepreneurs in the

electrified localities who operate in the services sector where they are often better represented

than men.

3.2.1.3 Mitigation and Land Improvement Programme

Mitigation of the negative effects identified during the implementation phase will mainly

depend on the organisation of work, as recommended in the terms of reference for companies.

This organisation is based on binding clauses for companies and the Consultant Engineer, the

Page 21: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

11

obligation to have a Health, Safety and Environmental Plan that includes emergency provisions,

as well as an environmental protection plan for sensitive environments.

In all, the specific and mitigating measures are: (i) a reforestation programme (based on the

principle of planting 2 units for 1 unit deforested; it will involve NGOs, regional and local

relays of the Guinean and Malian Ministries for women's empowerment, and the local water

and forestry services; (ii) a specific wildlife management plan, with biodiversity/fragmentation

monitoring and wildlife protection components; (iii) a communication plan; (iv) a conservation

and cultural heritage conservation plan; and (v) an employment plan.

Organisational responsibilities will be exercised by: the Project Management Units (PMUs) in

each country, together with the consulting engineer (same firm for the whole project), and in

case of complaints, the Conciliation and Monitoring Committees (CCS). These structures will

be supported by the steering committee which will play an advisory role and interact primarily

with the WAPP Secretariat General. The ESMP will be regularly monitored to ensure that any

negative effects are mitigated. It has defined the objectives to be attained and outlined the

prevention and intervention plans for project implementation and operation. These plans take

into account the environmental situation (soil, water, key site, etc.) and its interaction with

project activities. The ESMP will be updated in cases where certain unidentified impacts were

either not taken into account or were under-estimated. Its total budget, net of taxes, is EUR

10,674,987, representing 3% of the total project budget.

3.2.2 Climate Change

3.2.2.1. The risk of natural disasters is high in Guinea. Floods, landslides and earthquakes have

become a concern. The sites particularly exposed are: (i) the banks of the Niger and Milo rivers.

(ii) rugged terrain, especially between the Simandou and Going mountains. In Mali, the rivers

are prone to seasonal flash floods and, consequently, bank erosion and river-bed sedimentation.

3.2.2.2. Erodible and rugged areas, as well as erosion of the banks of watercourses located

within the right-of-way were taken into account such that construction of the line was designed

to incorporate preventive measures for adapting to these risks. As a result, less than 30% of the

line alignment passes through such areas. The related costs are included. Implementation

studies will fine-tune the construction arrangements and set out the final design, which will

include: (i) installing and building pylon base structures outside floodplains; (ii) installing

substations outside flood-prone/erodible areas, and with backfilling; (iii) sizing pylon

foundations taking into account the average speeds of dominant winds.

3.2.2.3. Regarding mitigation, provision has been made for a compensatory reforestation plan

to ensure a positive net gain relative to the vegetation cover destroyed. This surplus will

contribute to carbon sequestration. Furthermore, with respect to GHG emissions, the following

parameters were considered: (i) the manufacture of construction materials; (ii) transportation of

such materials; (iii) deforestation of the 40-metre corridor in preparation for the various sites;

(iv) clearing of the corridor; (v) operation of the facilities with a life expectancy of 40 years,

calculated based on the projected export of 800 to 1120 GWh of hydroelectricity per year from

Guinea to Mali by 2030. This will make it possible to avoid emissions equivalent to 12,150,450

metric tonnes of CO2, which is a substantial positive impact.

3.2.3 Gender

3.2.3.1. The population that has no access to energy includes a large number of women. Yet,

women are primarily responsible for providing energy to households through the collection and

use of traditional fuels. Furthermore, in the absence of modern energy, women are expected to

Page 22: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

12

execute all manual production and processing activities; which further increases their workload.

They are also the first victims of health impacts linked to the use of inappropriate energies and

fuels. A detailed gender analysis per country is presented in the technical annexes (B. 10) of

the project.

3.2.3.2. To remedy the situation, it was agreed that the following activities be implemented by

the Ministry in charge of gender in each country: (i) organising awareness campaigns on

rational energy use, prevention of electricity accidents, gender-based violence (GBV),

HIV/AIDS and rational access to basic social services (Guinea and Mali); (ii) supporting

women operating income-generating activities through training and guidance in various trades

(Guinea); (iii) supporting the operationalization of four GBV counselling centres in the

prefectures of Siguiri, Kankan, Kerouane and N'Zérékoré (in Guinea); and (iv) getting women’s

and youth groups in the project area to carry out reforestation actions that will improve the

environment and boost the incomes of women in such areas (in Mali). It has also been agreed

that a gender and socio-economic expert will be recruited into the project team. The total

estimated budget for the implementation of these activities is USD 413,000 for Guinea and

USD 205,000 for Mali.

3.2.4 Employment

3.2.4.1. During construction of the electrical infrastructure, the project will create over 825

direct, skilled and unskilled jobs, including at least 15% for women to the extent possible.

During the operational phase, approximately 50 permanent jobs will be created.

3.2.4.2. To promote employability, the project will recruit and train 45 young graduates in

Guinea and 30 in Mali, with at least 50% of them being women. The recruitment will be done

in three stages during project implementation for a period of 6 months, renewable once.

3.2.4.3. The social mitigation measures to be developed in the ESMP and FRP will facilitate

the promotion of income-generating activities for at least 3,000 women and girls/boys.

Furthermore, the project will stimulate the development of additional income-generating

activities by supplying energy for small businesses operated by women, girls and the youth

(mills, improved woodstoves, shops, hairdressing salons, welding workshops, etc.). Finally, the

construction of this electricity network and rural electrification will benefit small and medium-

sized enterprises and businesses.

3.2.5 Forced Resettlement

The project will affect 1,686 people in Guinea and 336 in Mali, located within its right-of-way,

with the expropriation of agricultural or residential land, the loss of miscellaneous property and

socio-economic damage. Accordingly, and in keeping with the Bank's requirements, an

approved and published full resettlement plan (FRP) has been submitted by each country,

setting out the appropriate measures to be taken in favour of persons affected by the project.

Women's groups will be consulted in decision-making on the distribution of compensation to

affected persons.

4 PROJECT IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Project Implementation: The Ministries in charge of energy, through their respective

National Directorates for Energy in each country, shall be responsible for project control and

supervision. The latter will be delegated to the national electricity companies (Electricité de

Page 23: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

13

Guinée (EDG) and Energie du Mali (EDM-SA) to which the ADF resources will be transferred

by the two governments. Within each company, a Project Management Unit (PMU) will be set

up to ensure the technical, administrative, accounting and financial management of the project

segment on each national territory for all financing provided by the various project donors. The

key PMU staff is composed of: one project manager, three electrical engineers, one

administrative and accounting officer, one procurement expert, one monitoring and evaluation

expert and one environmentalist. The complete staff list of each PMU is presented in the Annex.

4.1.2 For the PMU in Guinea, three international experts will be recruited (one procurement

expert, one sub-station electrical engineer and one transmission line electrical engineer) to

manage all project procurements, lend their expertise to the PMU and train national staff in

their respective specialties. The other PMU staff members shall be appointed by the Guinean

Government and their CVs shall be submitted to the Bank for prior approval. The project

manager must be freed from all other activities and be assigned exclusively to the project. An

international procurement expert will be recruited for the PMU in Mali to manage the

procurements of this project and of another mini hydroelectricity power station project also

financed by the Bank. Since Mali has extensive experience in the operation and maintenance

of 225 kV lines, EDM-SA has qualified engineers to monitor the construction of 225 kV lines

and substations. In each country, the Project Manager will ensure the implementation and

regular monitoring of project activities as well as the management of individual contracts. He

shall be provided with all the technical and managerial resources needed to supply all the

services required for the technical, administrative and financial management of the project.

Each country has already appointed its Project Manager following the Bank's formal approval

of their CVs. Apart from the staff to be recruited, Mali has already provided the Bank with the

CVs of the other PMU staff members. Guinea should do same before the project is submitted

to the Board of Directors.

4.1.3 A consultancy firm (CF) will also be recruited to monitor and supervise all

construction works on the 225 kV line, as well as the ESMP on both territories and two

consulting engineers will also be recruited to supervise construction work on the distribution

networks in project area localities. Recruitment of the CF responsible for works control on the

225 kV line will be entrusted to the WAPP Secretariat General. Furthermore, a Supranational

Steering Committee (SSC) will be set up to provide strategic guidelines on the coordination and

alignment of the activities of both PMUs. The SSC will be composed of 11 officials from both

countries (five per country) and from the WAPP Secretariat General. The Guinean members of

the SSC are: the National Director for Energy, the National Director for Public Investments,

the General Manager of EDG, the General Manager of the Guinean Bureau of Studies and

Environmental Assessments (BGEEE) and the General Manager of the Major Projects and

Public Procurement Administration and Control Authority (ACGPMP). On the Malian side, the

members of the SSC are: the National Director for Energy, the National Director for Sanitation

and Pollution Control (DNACPN), the National Director for Development Planning, the

Director General for Public Debt and the General Manager of EDM-SA. WAPP will be

represented by its Secretary General.

4.1.4 The facilities constructed shall be operated and maintained by EDG and EDM-SA, on

their respective national territories.

4.1.5 Procurement Arrangements: In Guinea, Bank-financed goods under the project

(including services other than those of consultants) shall be procured in accordance with the

Procurement Framework for Bank Group-funded Operations, October 2015 edition, and in

accordance with the provisions set out in the Financing Agreement. More specifically,

procurements will be done according to the Bank's Procurement Methods and Procedures

(BPM) based on the standard bidding documents (SBD) for goods, works and consultancy

Page 24: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

14

services for which the BPM is deemed to be best adapted. Indeed, an analysis of the

procurement system in Guinea, as presented in Technical Annex B5, has resulted in

classification of the procurement risk as substantial. Accordingly, during project

implementation, the Bank's procurement procedures and methods will be used with the

understanding that a capacity development action plan will be discussed with Guinean

authorities to enable the rapid use of the national procurement system after implementation of

the necessary reforms.

4.1.6 In Mali, works on the 225 kV line are jointly financed by the Bank and WADB which

agreed that that the Bank’s procurement rules and procedures should be applied. Since EDM-

SA which controls the project is not subject to national procurement procedures, it was agreed

that Bank-financed goods, works and consultancy services be procured in accordance with the

“Procurement Policy and Methodology for Bank Group-Funded Operations” dated October

2015. They will also comply with the provisions that will be set out in the financing agreement,

using the Bank's procurement methods and procedures (BPM) and the relevant standard

bidding documents (SBDs). Procurements will be effected by the PMU to be established

within the Directorate for Studies and Strategic Planning of EDM-SA and staffed with an

international procurement expert. The expert will be responsible for all planned project

procurements and will be supported in his tasks by a procurement assistant, the competent

technical services and partners involved in the project as well as the Procurement Directorate

of EDM-SA.

4.1.7 Risk and procurement capacity assessment (RPCA): Risks at the country, sector and

project levels as well as the procurement capacity of the executing agency (EA) were assessed

and the results were used to determine the Bank’s procurement methods and procedures needed

for all scheduled project activities. The appropriate risk mitigation measures have been included

in the PERCA action plan presented in Annex B5. The detailed procurement arrangements and

project procurement plans in each country are also presented in Technical Annex B5.

4.1.8 Given the urgent need to implement the project for both countries and to mitigate

procurement delay risks, the Governments have sought the Bank's agreement in principle to use

advance procurement actions (APA) for the construction of the 225 kV line and the recruitment

of the engineering consultancy firm that will conduct works control and supervision. This

authorisation was sought pursuant to Article 11.2 of the Procurement Policy for Bank Group-

Funded Operations.

4.1.9 Financial Arrangements: In Guinea, the assessment of the financial management

components and the other project implementation units hosted by EDG is satisfactory,

although some adjustments need to be made. Project counterpart funds, essentially composed

of compensation for affected persons and PMU office rental costs, must be included in the

State budget for FY2018. With regard to internal control, since the project is funded by several

donors, a procedures manual will be prepared based on the provisions of the procedures

manuals existing in the Implementation Unit for Bank-funded Projects; the Internal Audit Unit

of the EDG shall periodically audit the operations of the PMU. Accounting software will also

be procured for project management. The PMU will produce quarterly financial monitoring

reports for the Bank and annual financial statements for submission to an annual financial and

accounting audit. Lastly, training on the financial management requirements of Bank-financed

projects will be provided to PMU staff when the project is launched. Implementation of the

action plan agreed upon and detailed in the annex should lead to proper project commencement

and ensure the effective operation of financial management components.

Page 25: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

15

4.1.10 In Mali, EDM-SA is responsible for the administrative, financial and accounting

management of the project through the Directorate of Studies and Strategic Planning within

which the project management unit (PMU) will be established. The capacity assessment of

EDM-SA has highlighted its strengths and weaknesses detailed in Technical Annex B6 of the

appraisal report. EDM-SA already has: (i) staff capable of managing a project; and (ii)

experience in managing projects financed by multilateral partners. However, it does not have

integrated accounting and financial management software adapted to development projects.

Indeed, the company's accounts are managed with Oracle software whose “project

management” module was not procured. Furthermore, EDM-SA does not have an

administrative, accounting and financial procedures manual. Consequently, multi-project,

multi-user, multi-donor and multi-site integrated accounting and financial management

software adapted to development projects will have to be procured under the project as well as

a manual of administrative, accounting and financial procedures. Financial management staff

will have to be trained to use the software and the procedures manual. Moreover, guidance

(assistance) should be provided by the software supplier until the first comprehensive annual

financial statements to be audited are produced.

4.1.11 In both countries, project accounts will be kept using private sector accounting

standards and the abovementioned integrated software. The accounting plan will be developed

based on the accounting law standards of the Uniform Act of the Organisation for the

Harmonisation of Business Law in Africa (OHADA), applicable in both countries. Moreover,

a work plan and annual budget (WPAB) will be prepared in each country, as well as quarterly

financial management reports in which a clear analysis must be made between budget

estimates and actual expenditure for the quarter. Any discrepancies should be analysed and

explained. Whenever necessary, the internal auditors of EDM-SA and EDG must be involved

in the development of the work plan, the analysis and explanation of discrepancies and the

various transactions executed under the project in each country must be reviewed periodically.

The financial management details of the project can be found in Technical Annex B4.

4.1.12 Disbursement Arrangements: The ADF funds will be disbursed through: (i) the

special account method; (ii) the direct payment method; and (iii) the reimbursement method.

A special account in local currency will be opened in each country to receive ADF resources.

These methods are detailed in the technical annexes of this appraisal report.

4.1.13 External Audit Arrangements: The financial statements of the project in each country

will be audited annually by independent audit firms. The audit terms of reference shall be

approved by the Bank in advance and the audit firms shall be recruited within six months

following the commencement of project activities. The audit contract will be concluded for a

non-renewable period of three years. Continuation of the contract for another two years shall

be predicated on the Bank's approval of the audit report of the first year. The audit reports must

reach the Bank no later than six months following the end of the fiscal year.

4.2 Monitoring

4.2.1 The monitoring and evaluation experts in the PMUs shall each submit periodic reports

on the progress of project indicators. The reports of joint periodic supervision missions of

donors, the engineering consultant responsible for works control and supervision as well as

project audit will be used to monitor implementation and the attainment of set objectives.

Project progress reports, prepared by each PMU on a quarterly basis, shall be submitted to the

Bank. All of the abovementioned reports will make it possible to identify constraints or delays,

where appropriate, and to take suitable actions that ensure implementation of the project within

the prescribed timeframe and the achievement of its overall objectives.

Page 26: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

16

4.2.2 The Bank’s project monitoring activities are summed up in the table below. They will

be conducted following the project implementation schedule found in page (vi). At least two

joint project supervision missions by donors will be conducted per year. At the end of the

project, both PMUs shall prepare and submit a completion report to the Bank. The Bank will

also prepare its own completion report and a project performance evaluation report.

Table 4.2

Monitoring of project activities / Feedback loop

Period Stages Monitoring activities/Feedback loop

December 2017-

February 2018

Project approval and

effectiveness of ADF loans and

grants

- Board approval

- Notification to Governments

- Signing of ADF loan and grant agreements

- Effectiveness of the grants and loans

- Lifting of conditions precedent to effectiveness and first

disbursement of ADF loans and launch of the project

August 2017 to

February 2018

Recruitment of international

experts, consulting engineers

and construction contractors

- Notice for expressions of interest, consultancy files

- Approval of the file and bid evaluation

- Recruitment of consultants and works contractors

March 2018 to

December 2018

Recruitment of the external

auditor and other consultants

- Notice for expressions of interest, consultancy files

- Approval of the file and bid evaluation

- Recruitment of the audit firm and other consultants

March 2018 to

December 2018

Electricity infrastructure

construction works

- Supply and installation of equipment

- Control and supervision (consulting engineer)

- Joint project supervision missions/ESMP monitoring

June 2019 Joint mid-term review by

donors

- Joint mid-term review mission by all donors and the Bank

December 2020

to June 2021 Project completion

- Project completion report by Borrowers

- The Bank’s project completion report

4.3 Governance

4.3.1 In such a large-scale project funded by several donors, governance issues, including

fraud and corruption may arise during the procurement. Since the evaluation of national

procurement systems was inconclusive, it was decided to use AfDB procurement rules and

procedures which require the prior approval of the Bank at each stage of the procurement

process. With regard to administrative and financial management, there are plans to develop

administrative, accounting and financial procedures manuals, keep a separate accounting for

the project, and use the appropriate management software and independent external auditors

who will perform financial and operational audits of the project. All these provisions will ensure

that project resources are used efficiently and for their intended purpose.

4.4 Sustainability

4.4.1 The project's sustainability is underpinned by the stated willingness of the Malian and

Guinean Governments to develop electricity trade between the two countries. Indeed, a

Memorandum of Understanding on electricity between the two countries was signed on

21/06/2017. The physical sustainability of the project and its outcomes are also predicated on

good governance in the electricity sub-sector in each country and a better financial situation for

the national electricity companies (EDG and EDM-SA) to ensure proper maintenance of the

structures. In Guinea, the Government has initiated reforms, since 2011, which have placed

EDG under a management contract in order to ensure its good governance and improve its

technical, commercial and financial performance. However, it has been proven that all efforts

would go in vain if the applicable rates remain below the production cost per kWh. The

government has, therefore, requested the Bank (which has accepted) to finance a pricing study

Page 27: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

17

and a physical/financial equilibrium model; these are being prepared by a consultant expected

to submit the first reports in the first quarter of 2018. The Government will undertake, within

the framework of this financing, to implement the relevant recommendations of these studies.

Similarly, a pricing study is underway in Mali and reforms are being considered which could

lead to the splitting of EDM-SA into two separate entities, namely: an asset management

company and an operating company. Pending the recommendations of the pricing study, the

Malian Government has since 2015 pledged to raise the rates annually by 3% until 2018 to

reduce or even eliminate the operating subsidies.

4.4.2 Furthermore, this project will increase the export revenue and domestic sales of EDG

and significantly reduce the kWh cost of electricity sold by EDM-SA by replacing highly

expensive thermal energy with affordable hydroelectricity. In short, the project should help to

improve the financial situation of the two electricity companies, putting them in an ideal

situation for appropriate monitoring and adequate maintenance of the facilities, everything else

being equal.

4.5 Risk Management

4.5.1 The potential risks identified for the project are:(i) the non-availability of energy in

Guinea leading to under-utilization of the 225 kV line; (ii) the low financial capacity of the

national electricity companies (EDG and EDM-SA) to honour their commitments and maintain

the facilities; and (iii) the limited experience of national electricity companies to execute large-

scale projects funded by several donors.

4.5.2 The mitigating measures for these risks are: (i) the energy in Guinea should come mainly

from the hydroelectric power plants of Kaléta (240 MW) and Souapiti (450 MW) during the

first years of operation of the line. The Kaléta power plant has been operational since 2015

and the Souapiti plant is already under construction, and its first generators are expected to

go operational by the end of 2020 and the entire plant by 2021. Furthermore, the portion of

the 225 kV Linsan-Fomi line which will transmit this energy from the western to the eastern

part of Guinea, and subsequently to Mali will be available in 2021 at the latest, because the

Government has already secured the funding from Chinese cooperation and work is expected

to start during the first quarter 2018. Moreover, even with a pessimistic hypothesis of a 2-

year delay in the availability of the Souapiti plant, the power generation facilities envisaged

by Guinea (ongoing rehabilitation of the current hydroelectric plants, planned construction of

other small hydropower plants, etc.) would generate a surplus that will satisfy all or most of

Malian demand until 2024 and the rest could be imported from Côte d’Ivoire through the

CLSG line; (ii) reorganisation of the management and improvement of the financial situation

of the electricity companies through ongoing reforms in both countries and the application of

rates that accurately reflect production costs; and (iii) capacity building for stakeholders

involved in the sub-sector, including the national electricity companies, the national

directorates for energy departments and the project management units (PMU) through specific

training for their staff, and the hiring international experts in key positions to support the

PMUs.

4.6 Knowledge Building

4.6.1 Apart from the knowledge on best practices that will be shared among donors during

the supervision missions and joint project reviews, the Bank could also deepen its knowledge

through the results of three types of specific activities identified during project

implementation. These are: (i) training during project implementation for young

inexperienced employees of the national electricity companies serving as assistants, by

experienced professionals recruited to serve within the project management units; such

Page 28: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

18

trained young employees will constitute the group of experts capable of successfully

managing the PMUs of future operations in the sub-sector and in the country; (ii)

implementation of the “Energy and women’s empowerment, information, education and

communication” component by women's groups specialized in this kind of communication

and having experience in the project area, under the supervision of the ministry in charge of

women's and children's affairs in each country; and (iii) internships for 75 young graduates

(50% being girls) who, thanks to the project, will have their first professional experience for

a duration of six months, renewable once.

4.6.2 The monitoring and evaluation system instituted in each PMU; the project's half-yearly

financial reports, interim financial reports and annual external audit reports; and the

supervision missions following which lessons will be learnt, will all constitute information

sources on the project. The publication of project completion and performance appraisal

reports will help to disseminate knowledge to Bank staff and the public. The lessons learnt

will enhance the design of similar future Bank operations.

5. LEGAL FRAMEWORK

5.1 Legal Instrument

5.1.1 The ADF will award grants and loans from its routine resources to the Republics of

Guinea and Mali as its funding quota for the project, as well as grants from the resources of

the Africa Investment Facility of the European Union (AFIF/EU) which it administers under

this project.

5.2 Conditions Associated with the Bank’s Involvement

A. Conditions Precedent to Effectiveness of the Grants and Loans

(i) The effectiveness of ADF grants shall be subject to signature by the parties

concerned of the relevant grant agreement protocols;

(ii) The effectiveness of ADF loans shall be subject to the Borrowers’ fulfilment of

the conditions provided for in Section 12.01 of the Fund’s General Conditions

for Loan Agreements and Guarantee Agreements.

B. Conditions Precedent to First Disbursement of ADF Resources

5.2.1 Apart from effectiveness of the grant agreement protocols, first disbursement of ADF

resources shall be subject to fulfilment by the Donee/Borrower to the satisfaction of the

Fund of the following conditions:

5.2.1.1 Conditions precedent to first disbursement of ADF grants and loans awarded to the

national electricity companies (EDG and EDM-SA)

(i) Each State must provide the Bank/Fund with proof of signature of an agreement

transferring the received funds to its national electricity company under terms

acceptable to the Bank/Fund;

(ii) Provide the Bank/Fund with proof of appointment of the key staff members of

the Project Management Unit including the project manager, the administrative

and accounting officer, the monitoring and evaluation expert, and the

environmentalist.

Page 29: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

19

5.2.1.2 Conditions precedent to first disbursement of the resources of the Africa Investment

Facility of the European Union (AFIF/EU) transferred to WAPP for the recruitment

of a Consulting Engineer for project works control and supervision

The Republic of Guinea and the Republic of Mali will have to provide the Bank/Fund with

proof of signature of an agreement transferring the funds received from AFIF/EU for project

works control and supervision to the WAPP General Secretariat, under terms acceptable to the

Bank/Fund.

C. Other Conditions

Each State shall:

(i) Provide the Bank/Fund with proof of approval by the other donors of their share

of project financing, prior to commencement;

(ii) Provide the Bank/Fund with proof of the opening of a special account by the

national electricity company in a bank acceptable to the Bank/Fund, to receive

AfDB/ADF funds;

(iii) Forward to the Fund, at the latest before the beginning of works in the area

concerned: (a) proof of the procurement of land or of compensation of project

affected persons (PAPs), in accordance with the Bank's rules and procedures,

especially its involuntary population resettlement policy, its integrated

safeguards system, the Environmental and Social Management Plan (ESMP), the

full resettlement plan (FRP) and the applicable national regulations; or (b),

where such acquisition or compensation of certain PAPs is impossible, proof of

deposit into an escrow account satisfactory to the Fund, of financial resources to

be used for the procurement of land or compensation of such persons; in

accordance with the abovementioned rules and procedures.

(iv) Establish, no later than 6 (six) months after the first disbursement, a performance

contract between the national electricity company and its technical supervisory

Ministry.

D. Commitments

5.2.2 The Government of Guinea, as Borrower/Donee, undertakes to:

(i) finalise the drafting and ensure the adoption of the new electricity law no later

than the end of 2018;

(ii) implement the recommendations of the pricing study with a view to achieving

the financial equilibrium of the sub-sector over the next five years;

(iii) implement the project, the Environmental and Social Management Plan (ESMP)

and the full resettlement plan (FRP) and have them implemented by its

contractors in accordance with national laws, recommendations, prescriptions

and procedures contained in the ESMP and the FRP, and with the applicable

rules and procedures of the Bank/Fund; and

(iv) provide the Fund with quarterly reports on the implementation of the project,

ESMP and FRP, and with any document that is reasonably necessary for

monitoring project implementation.

Page 30: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

20

5.2.3 The Government of Mali, as Borrower/Donee, undertakes to:

(v) implement the recommendations of the pricing study with a view to achieving

the financial equilibrium of the electricity sub-sector over the next five years;

(vi) continue electricity sub-sector reforms with a view to improving its technical

and financial performance;

(vii) implement the project, the Environmental and Social Management Plan (ESMP)

and the full resettlement plan (FRP) and have them implemented by its

contractors in accordance with national laws, recommendations, prescriptions

and procedures contained in the ESMP and the FRP, and with the applicable

rules and procedures of the Bank/Fund;

(viii) provide the Fund with quarterly reports on the implementation of the project,

ESMP and FRP, and with any document that is reasonably necessary for

monitoring project implementation.

5.3 Compliance with Bank policies

5.3.1 The project is in compliance with all the Bank’s applicable policies.

6. RECOMMENDATION

Management recommends that the Board of Directors approves the proposal to award a loan of

UA 16.6 million and a grant of UA 13.4 million to the Republic of Guinea as well as the

proposal to award a loan of UA 16.1 million and a grant of UA 13.9 million to the Republic of

Mali, to finance the 225kV Guinea-Mali Electricity Interconnection Project, under the

conditions set out in this report.

Page 31: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

I

Annex I.1- Situation of the Electricity Sub-sector in Guinea

Annex I.2- Situation of the Electricity Sub-Sector in Mali

The electricity sub-sector situation in Guinea, detailed in Technical Annex A, can be summarized as follows:

Guinea is a country in West Africa with an estimated population of 12.9 million inhabitants (2016), of which 36.8%

live in urban areas. It has one of the lowest human development indices in the world, with 73% of the population

earning less than two US dollars a day.

The electricity sub-sector remains poorly developed. Only 29% of the population has access to electricity and only

18% are formally and legally connected to the grid. In rural areas, only 2% have formal access to electricity.

The installed production capacity as of end-September 2017 was 629.97 MW, of which one third was the own facilities

of the State-owned Electricité de Guinée (EDG). The installed capacity is dominated by hydroelectricity

(approximately 59% or 367.37 MW), thanks to commissioning of the Kaléta dam in 2015 (240 MW), which has helped

to resolve the capacity deficit on the interconnected network during the rainy season. The Souapiti hydropower plant

(450 MW) is under construction and its first generator will be commissioned in 2021. The country's total hydro-

electricity potential is estimated at 6,000 MW. A hydroelectricity mapping is being prepared with funding from one

of Guinea’s technical and financial partners to facilitate the identification of potential useable sites. Moreover, Guinea

is located at the centre of the West African Power Pool (WAPP) and will therefore be crisscrossed by transmission

lines interconnecting the countries of the Economic Community of West Africa States (ECOWAS) by 2025. Indeed,

the interconnection line of the networks of OMVG and CLSG countries, which are being built with financing from

TFPs of Guinea including the Bank, will reach the localities of Linsan and Nzérékoré in Guinea. The Guinea-Mali

interconnection line targeted by this project will join the other two lines to connect Guinea to at least 11 countries of

the sub-region.

One of the Government's main development objectives, as set out in the National Economic and Social Development

Plan (PNDES) is to increase access to electricity. Indeed, a vast electricity sub-sector investment programme (which

includes this project) is being developed to achieve universal access by 2030. This objective is consistent with the

commitments of the SE4ALL initiative which the Government joined in 2012 and entails reaching 1.7 million

connections. In addition to the benefits that it brings to households, the programme will substantially improve the

quality of public services through the electrification of schools as well as administrative and health centres.

At the institutional level, EDG which is a public corporation, has a monopoly on electricity transmission and

distribution nationwide; while production is left to private independent producers. The electricity law is being

reviewed by a Bank-funded consultant to adapt it to current realities. Since 2015, the EDG has been under a four-year

performance contract managed by the VEOLIA-SEURECA Group in order to streamline its technical, financial and

commercial performance. The financial situation of the EDG over the last five years is characterized by a growing

deficit and a severe financial imbalance. The company's solvency is weakened, although it continues to honor its

medium and long-term financial commitments.

The current interconnection project with Mali will enable the EDG to sell electricity to EDM-SA at a substantial profit,

and to supply electricity to a region of the country that has hitherto had virtually no supply or been powered by small

costly generators (which will no longer be used). These actions are expected to improve nation-wide electricity supply

and the financial situation of the company. However, such improvement of the financial situation of EDG remains

contingent on the application of realistic rates. Actually, the average electricity rate at end-2016 was GNF 778 while

the production cost was GNF 1,571, excluding energy supply from Kaléta; and GNF 890 for energy from the Kaléta

plant whose output is currently supplied free of charge to EDG. A pricing study was launched in the first half of 2017

with Bank funding. The study results expected in the first half of 2018, will determine the rates needed to ensure the

sector’s financial balance and the Government will take appropriate decisions, either by adjusting the rates or

committing to pay adequate operating subsidies.

Page 32: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

II

The electricity sub-sector situation in Mali, detailed in Technical Annex A, can be summarized as follows:

Mali is a country in West Africa with an estimated population of 18.1 million inhabitants (2016), of which 37.6% live

in urban areas. It has one of the lowest human development indices in the world (41.9% at end-2014), with 91% of

the population earning less than two US dollars per day.

The electricity sub-sector is relatively less developed with a national electricity access rate of 41%. In rural areas, only

17% of the people have formal access to electricity, relative to 66.8% in urban areas. The total installed production

capacity in end-September 2017 was 556.2 MW, of which 486.2 MW came from the interconnected network. The

composition of the production facilities on the interconnected network are 37.7% for hydropower and 62.3% for

thermal power. Owing to the obsolescence and unavailability of certain power plants, EDM-SA is unable to satisfy

the needs of all its customers and continues to engage in load shedding despite imports from Côte d'Ivoire

(approximately 50 MW) and the purchase of energy from independent producers (approximately 98 MW in 2016).

Furthermore, the predominance of thermal energy in the energy mix is detrimental to EDM-SA which regularly

records a deficit because of the very high energy production costs. This makes the sub-sector highly dependent on

hydrocarbons products whose import volume is rising steadily to meet the demands of a rapidly growing population

(doubling every 20 years) and economic growth. Consequently, the Malian economy as a whole is vulnerable to oil

price volatility. Yet, the opportunities to develop renewable energy sources (hydro, solar, and wind) are not fully

tapped. For instance, only 250 MW of hydroelectric power potential of 1000 MW in the Niger and Senegal rivers is

currently tapped. The country could become a major producer of solar energy since it receives 7 to 10 hours of

sunshine per day throughout the year (with average irradiation of 5 to 7 kWh/m2/day, relative to an estimated global

average of 4-5 kWh/m2/day).

Accordingly, the Malian Government, through the first strategic pillar of its Strategic Framework for Economic

Recovery and Sustainable Development (CREDD 2016-2018) entitled “inclusive and sustainable economic growth”

which has prioritised energy infrastructure development, decided that production facilities had to be diversified, which

implies developing the country's hydroelectricity potential; exploring the options offered by solar, biofuel and wind

energies; and increasing the interconnection rate to the sub-regional power pool.

From the institutional standpoint, EMD-SA, which is a semi-public company in which the State of Mali has a 66%

stake, with the remaining capital (34%) held by IPS WA (Industrial Promotion Services West Africa), is the main

concessionaire for electricity supply in Mali. It is responsible for the generation, transmission and distribution of

electricity in the country on the interconnected network and in major cities. Power generation is open to private entities

and the monopoly on wholesale purchase of electricity enjoyed by EDM-SA since 2000, ended on 31 December 2010,

thus opening up the possibility for third parties to gain access to the network.

Moreover, although the price of electricity is relatively high (CFAF 97/kWh on average at end-2016), it is still

insufficient to cover the production costs of the electricity distributed (CFAF 130/kWh). The current regulatory

framework is not conducive enough to private investment in the energy sector, despite the strong private sector

involvement in rural electrification over the last five years. In recent years, EDM-SA has recorded accumulating losses

that have undermined its financial position. The company's solvency is affected and if timely action is not taken, it

may not be able to keep honouring its medium and long-term financial commitments. The 225 kV Guinea-Mali

Electricity Interconnection Project which will enable EDM-SA to import electricity at a price significantly lower than

the current production cost per kWh, offers some hope for the improvement of its financial situation. However, this

remains predicated on the application of realistic rates or payment by the State of sufficient subsidies to ensure the

financial balance of the sub-sector.

Page 33: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

III

Annex II. Comparative Socio-economic Indicators

Year Guinea Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 246 30 067 97 418 36 907Total Population (millions) 2016 12,9 1 214,4 6 159,6 1 187,1Urban Population (% of Total) 2016 36,8 40,1 48,7 81,1Population Density (per Km²) 2016 52,7 41,3 65,1 33,8GNI per Capita (US $) 2015 470 2 153 4 509 41 932Labor Force Participation *- Total (%) 2016 82,3 65,7 63,5 60,0Labor Force Participation **- Female (%) 2016 79,4 55,7 48,9 52,1Sex Ratio (per 100 female) 2016 100,6 100,1 106,0 105,0Human Dev elop. Index (Rank among 187 countries) 2015 183 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2012 35,3 ... 14,6 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 2,7 2,5 1,3 0,6Population Grow th Rate - Urban (%) 2016 3,8 3,6 2,4 0,8Population < 15 y ears (%) 2016 42,4 40,9 27,9 16,8Population 15-24 y ears (%) 2016 19,9 19,3 16,9 12,1Population >= 65 y ears (%) 2016 3,1 3,5 6,6 17,2Dependency Ratio (%) 2016 83,4 79,9 54,3 52,0Female Population 15-49 y ears (% of total population) 2016 23,3 24,0 25,7 22,8Life Ex pectancy at Birth - Total (y ears) 2016 59,6 61,5 69,9 80,8Life Ex pectancy at Birth - Female (y ears) 2016 60,1 63,0 72,0 83,5Crude Birth Rate (per 1,000) 2016 35,9 34,4 20,7 10,9Crude Death Rate (per 1,000) 2016 9,4 9,1 7,6 8,6Infant Mortality Rate (per 1,000) 2015 61,0 52,2 34,6 4,6Child Mortality Rate (per 1,000) 2015 93,7 75,5 46,4 5,5Total Fertility Rate (per w oman) 2016 4,9 4,5 2,6 1,7Maternal Mortality Rate (per 100,000) 2015 679,0 476,0 237,0 10,0Women Using Contraception (%) 2016 7,8 31,0 62,2 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2005-2015 9,7 41,6 125,7 292,2Nurses and midw iv es (per 100,000 people) 2005-2015 ... 120,9 220,0 859,4Births attended by Trained Health Personnel (%) 2010-2015 39,3 53,2 69,1 ...Access to Safe Water (% of Population) 2015 76,8 71,6 89,4 99,5Access to Sanitation (% of Population) 2015 20,1 39,4 61,5 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2015 1,6 3,4 ... ...Incidence of Tuberculosis (per 100,000) 2015 177,0 240,6 166,0 12,0Child Immunization Against Tuberculosis (%) 2015 72,0 81,8 ... ...Child Immunization Against Measles (%) 2015 52,0 75,7 83,9 93,9Underw eight Children (% of children under 5 y ears) 2010-2015 16,3 18,1 15,3 0,9Prev alence of stunding 2010-2014 35,8 33,3 25,0 2,5Prev alence of undernourishment (% of pop.) 2015-2016 16,4 16,2 12,7 ...Public Ex penditure on Health (as % of GDP) 2014 2,7 2,6 3,0 7,7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2016 91,3 101,2 104,9 102,4 Primary School - Female 2010-2016 83,8 98,4 104,4 102,2 Secondary School - Total 2010-2016 38,8 52,6 71,1 106,3 Secondary School - Female 2010-2016 30,7 50,2 70,5 106,1Primary School Female Teaching Staff (% of Total) 2010-2016 30,0 47,1 59,8 81,0Adult literacy Rate - Total (%) 2010-2015 30,5 66,8 82,3 ...Adult literacy Rate - Male (%) 2010-2015 38,1 74,3 87,1 ...Adult literacy Rate - Female (%) 2010-2015 22,9 59,4 77,6 ...Percentage of GDP Spent on Education 2010-2015 3,2 5,0 4,0 5,0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2014 12,6 8,7 11,2 10,3Agricultural Land (as % of land area) 2014 59,0 41,7 37,9 36,4Forest (As % of Land Area) 2014 26,0 23,2 31,4 28,8Per Capita CO2 Emissions (metric tons) 2014 0,2 1,1 3,5 11,0

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Guinea

June 2017

0

20

40

60

80

100

120

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

Guinea Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

GNI Per Capita US $

Guinea Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Guinea Africa

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

Guinea Africa

Page 34: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

IV

Year Mali Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 1 240 30 067 97 418 36 907Total Population (millions) 2016 18,1 1 214,4 6 159,6 1 187,1Urban Population (% of Total) 2016 37,6 40,1 48,7 81,1Population Density (per Km²) 2016 14,9 41,3 65,1 33,8GNI per Capita (US $) 2015 790 2 153 4 509 41 932Labor Force Participation *- Total (%) 2016 66,3 65,7 63,5 60,0Labor Force Participation **- Female (%) 2016 50,3 55,7 48,9 52,1Sex Ratio (per 100 female) 2016 102,0 100,1 106,000 105,000Human Dev elop. Index (Rank among 187 countries) 2015 175 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2009 49,3 ... ... ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 3,0 2,5 1,3 0,6Population Grow th Rate - Urban (%) 2016 5,2 3,6 2,4 0,8Population < 15 y ears (%) 2016 47,4 40,9 27,9 16,8Population 15-24 y ears (%) 2016 19,3 19,3 16,9 12,1Population >= 65 y ears (%) 2016 2,5 3,5 6,6 17,2Dependency Ratio (%) 2016 99,8 79,9 54,3 52,0Female Population 15-49 y ears (% of total population) 2016 21,9 24,0 25,7 22,8Life Ex pectancy at Birth - Total (y ears) 2016 59,0 61,5 69,9 80,8Life Ex pectancy at Birth - Female (y ears) 2016 58,8 63,0 72,0 83,5Crude Birth Rate (per 1,000) 2016 42,3 34,4 20,7 10,9Crude Death Rate (per 1,000) 2016 9,8 9,1 7,6 8,6Infant Mortality Rate (per 1,000) 2015 74,5 52,2 34,6 4,6Child Mortality Rate (per 1,000) 2015 114,7 75,5 46,4 5,5Total Fertility Rate (per w oman) 2016 6,1 4,5 2,6 1,7Maternal Mortality Rate (per 100,000) 2015 587,0 476,0 237,0 10,0Women Using Contraception (%) 2016 12,0 31,0 62,2 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2005-2015 8,5 41,6 125,7 292,2Nurses and midw iv es (per 100,000 people) 2005-2015 44,3 120,9 220,0 859,4Births attended by Trained Health Personnel (%) 2010-2015 58,6 53,2 69,1 ...Access to Safe Water (% of Population) 2015 77,0 71,6 89,4 99,5Access to Sanitation (% of Population) 2015 24,7 39,4 61,5 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2015 1,3 3,4 ... ...Incidence of Tuberculosis (per 100,000) 2015 57,0 240,6 166,0 12,0Child Immunization Against Tuberculosis (%) 2015 79,0 81,8 ... ...Child Immunization Against Measles (%) 2015 76,0 75,7 83,9 93,9Underw eight Children (% of children under 5 y ears) 2010-2015 ... 18,1 15,3 0,9Prev alence of stunding 2010-2014 ... 33,3 25,0 2,5Prev alence of undernourishment (% of pop.) 2015-2016 5,0 16,2 12,7 ...Public Ex penditure on Health (as % of GDP) 2014 1,6 2,6 3,0 7,7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2016 75,8 101,2 104,9 102,4 Primary School - Female 2010-2016 72,1 98,4 104,4 102,2 Secondary School - Total 2010-2016 41,3 52,6 71,1 106,3 Secondary School - Female 2010-2016 36,8 50,2 70,5 106,1Primary School Female Teaching Staff (% of Total) 2010-2016 30,0 47,1 59,8 81,0Adult literacy Rate - Total (%) 2010-2015 33,1 66,8 82,3 ...Adult literacy Rate - Male (%) 2010-2015 45,1 74,3 87,1 ...Adult literacy Rate - Female (%) 2010-2015 22,2 59,4 77,6 ...Percentage of GDP Spent on Education 2010-2015 3,6 5,0 4,0 5,0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2014 5,3 8,7 11,2 10,3Agricultural Land (as % of land area) 2014 33,8 41,7 37,9 36,4Forest (As % of Land Area) 2014 3,9 23,2 31,4 28,8Per Capita CO2 Emissions (metric tons) 2014 0,1 1,1 3,5 11,0

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Mali

June 2017

0

20

40

60

80

100

120

140

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

Mali Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

GNI Per Capita US $

Mali Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Mali Africa

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

Mali Africa

Page 35: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

V

Annex III.1 Portfolio of Current Bank Operations in Guinea as of 31/07/17

Projects Status Approval

date

Closing

date

Disb.

Rate

Amount

approved Balance Sector

1 PPF - Support for the

transformation of Guinean

agriculture - youth

entrepreneurship component

OnGo 03/08/2016 30 June

2018

7.59% 990,000 914,859 Agriculture

2 Rural Electrification Project OnGo 21/01/2011 30/11/2017 69.92% 14,960,000 4,499,968 Energy

3 Second Electricity Network

Rehabilitation and Extension

Project

OnGo 11/09/2013 31/12/2017 46.91% 11,000,000 5,839,803 Energy

4 CLSG Interconnection Project OnGo 06/11/2013 31/12/2018 0.00% 28,910,000 28,910,000 Energy

5 Energy Project - OMVG

GUINEA

OnGo 30/09/2015 31

December

2020

0.00% 46,250,000 46,250,000 Energy

6 Financial Sector

Modernization Support Project

APVD 15/03/2017 31/12/2017 0.00% 2,400,000 2,400,000 Financial

7 Economic Planning and

Governance Support Project

OnGo 10/07/2013 30

September

2017

82.88% 11,380,000 1,948,256 Governance

8 Administrative Capacity

Building Support Project

APVD 15/07/2016 30/06/2020 6.09% 6,000,000 5,634,600 Governance

9 Economic and Financial

Reform Support Programme

APVD 13/07/2016 31/12/2017 100.00% 10,520,000 0 Governance

10 Road Development and

Facilitation Programme

APVD 18/12/2014 30/06/2020 0.00% 33,173,000 33,173,000 Transport

21.75% 165,583,000 129,570,486

Page 36: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

VI

Appendix III.2 Portfolio of Current Bank Operations in Mali as of 31/07/2017

Sector

Project Approval date Date of Ist

actual disbursement

Closing date

Approved amount

(UA million)

Disbursement rate

1

Agriculture

Bani Basin and Sélingué Irrigation Development Programme

27/05/2009 21/01/2010 31/12/2018 44 49.3%

2 Project for Food Security Consolidation through Development of Irrigation Farming

03/12/2013 20/04/2015 31/12/2019 36 22%

3 Mali – Food and Nutrition Security Support Project in Koulikoro

17/09/2014 05/03/2015 31/12/2019 36 17.0%

4 Programme to Build Resilience to Food and Nutrition Insecurity in the Sahel

15/10/2014 23/10/2015 30/06/2020 36.4 1.0%

5 Agro-industry Project for Diversification of the Activities of “Moulin Moderne de Mali” - M3 (private sector)

17/09/2014 03/06/2015 10/11/2020 13.3 9.1%

6 Water and sanitation

Bamako Drinking Water Supply Project

09/10/2013 15 December

2014 31/12/2018 50 13.0%

7 Bamako City Sanitation Project 11/01/2017 Not yet 31 December

2020 30 0.0%

8 Transport Mali-Côte d'Ivoire Transport Development and Facilitation Project

26/11/2015 Not yet 31/12/2019 70.8 12.9%

Sector Project Approval date Date of Ist

actual disbursement

Closing date Approved amount

(UA)

Disbursement Rate

9

Governance

Economic Governance Support Project 01/07/2013 08/05/2015 31/12/2017 10 39.0%

10 Economic Governance Reform Support Programme II - Budget Support

14/12/2016 Not yet 31/12/2017 23.15 0.0%

11 Land-use Management Master Plan 28/02/2017 Not yet 30/06/2018 1 0.0%

12 Finance Line of Credit to Banque Malienne de Solidarité

06/07/2011 05/03/2015 30/09/2018 4.4 100%

13

Energy

Ségou Solar Power Plant Project 31 October

2016 Not yet 30/06/2020 24.9 0.0%

14 Study on the Development of Mini and Micro Hydropower Plants

19/04/2013 11/02/2016 30/06/2017 1.8 16.9%

15 Renewable Energy Promotion Support Project

22/10/2014 22/09/2015 31/01/2019 1.5 6.0%

16 Climate Change Accelerating the construction of a green economy resilient to climate change

17/08/2015 Not yet 31/12/2017 0.3 0.0%

17

Social

Capacity building for the National Centre for Documentation and Information on Women and Children (CNDIFE)

15/03/2016 15/02/2017 30/06/2017 0.08 50.0%

18 Socio-economic Reintegration Support Project for Communities in Northern Mali

30/11/2016 Not yet 31

December 2020

10.5 0.0%

19 Youth Forum on Employment and Peace by GYIN- Global Youth Innovation Network

15/02/2017 Not yet 30

September 2017

0.06 0.0%

Total/Average 394.2 19%

Page 37: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

VII

Annex IV. 1

Major Related Ongoing Projects Financed by the Bank and Other Development Partners in Guinea

Donors Amount

Million F.E. Projects Status

World Bank 37.30 USD Improvement of energy sector efficiency - 2006

Implemented up to

70%

4.10 USD Decentralised rural electrification - 2002 Fully executed

African Development

Fund

12.00 UA

Conakry Electricity Network Rehabilitation and

Extension Project (PREREC 1) - 2008 completed

14.96 UA Rural Electrification Project – 2011 Ongoing

1.66 UA Guinea - Mali Interconnection Line Study - 2011 completed

11 million

Second Conakry Electricity Network Rehabilitation and

Extension Project (PREREC 2) - 2013 In process

40.80 UA CLSG interconnection line - 2013 Ongoing

46.25 million Interconnection of OMVG Networks - 2015 Ongoing

Islamic Development

Bank 11.50 USD

Conakry Electricity Network Rehabilitation and

Extension Project (PREREC 1) - 2008

Implemented up to

80%

17.45 USD Rehabilitation of the Kombo power plants - 2012 Starting-up

ECOWAS Bank for

Investment and

Development

30.0 USD Rehabilitation of the networks of four regional capitals -

2008 Ongoing

ECOWAS Commission 10.0 USD Rehabilitation of power plants -2011 Ongoing

ECOWAS Commission 20.0 USD Procurement of fuel oils and spare parts-2011 Ongoing

French Development

Fund 1.0 EUR Energy Sector Studies and Capacity Building Fund - 2012 Ongoing

Eximbank China 334.5 USD Kaléta Hydropower Plant Development - 2012 Ongoing

Annex IV. 2

Major Related Projects Financed by the Bank and Other Development Partners of Mali

Projects

Donors Cost Period

Construction of the National Control Centre of

Bamako and Doubling of the Capacity of the

Sotuba II Hydroelectric Power Station

WADB and gov't Mali 22494 MXOF 2010-2018

Construction of the Ségou-Markala-Niono HV 63

kV line

WADB and gov't Mali 12000 MXOF

Energy Sector Support Project (PASE) World Bank USD 120

million

2009-2014

Extension of the IsDB Balingué Power Plant

(additional 23 MW)

IsDB 197000 MXOF 2013-2015

Construction of the Sikasso and Bamako 225 kV

line

BIMC-EXIM Bank and Gov't

of Mali

USD 100

million

2012-2016

Hydroelectricity dam in Taoussa Kuwaiti Fund; IsDB;

WADB; Saudi Fund; OPEC;

ABEDA; EBID; Abu Dhabi

Fund and Gov't of Mali

XOF 130000

million

Page 38: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

VIII

Annex V Map of the Programme Area

The staff of the African Development Bank Group (AfDB) have provided this map for the exclusive use of

readers of this report to which it is appended. The appellations and the demarcations on this map do not imply

any judgment on the part of the ADB Group and its members concerning either the legal status of a territory or

the approval or acceptance of its boundaries.

Page 39: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

IX

Annex VI

Rationale for Requesting a Waiver for the Project to be financed over 90% by the Bank

and other Donors

The purpose of this note is to justify a waiver for financing of the 225kV Guinea-Mali Electricity

Interconnection Project with ADF resources in accordance with the policy governing expenditure

eligible for Bank Group funding (ADB/BD/WP/2007/106/Rev.2- ADF/BD/wp/207/72/Rev.2 of 2 May

2008).

I. GUINEA

The Guinean Government requested a waiver to be exempted from providing the maximum

counterpart contribution to the project’s financing. The Government hopes that its counterpart

contribution will be limited to a maximum of UA 9.16 million, representing 3.1% of the total

project cost, which is below the 10% required by the Policy on Expenditure Eligible for Bank

Group Financing under the ADF window. The justification of the request is based on the

following three criteria.

1.1 The Country’s Commitment to implement its General Development Programme

In recent years, although the margin of progress has remained significant, road infrastructure

remains inadequate and deficient even though the country has spent over 10% of its budget on

such infrastructure. This has enabled it, under a five-year road plan (2012-2016), to: (i) build

450.2 km of prefectural roads; (ii) rehabilitate 612.8 km of prefectural and community roads;

(iii) build 176.6 km of road network; (iv) rehabilitate 15 km of road network; (v) pave 522 km

of national roads; and (vi) build 352 linear metres of major facilities. During implementation

of PNDES 2016-20, which has a pillar on infrastructure, Guinea plans to take up this major

challenge in an environment constrained by a shortage of concessional resources to address its

significant infrastructure funding needs. In this regard, discussions with development partners

revolve around boosting domestic revenue collection by speeding up reforms stalled by the

Ebola epidemic, and engaging in greater and deeper financial engineering to finance this costly

infrastructure while maintaining sustainable debt levels.

1.2 Financing Allocated by the Country to Sectors Targeted by Bank Assistance

In this context, the Government, which is already focusing on road infrastructure in its strategic

guidelines and budget, intends to increase allocations to this sector even above the statutory

10%.

1.3 Budget Situation and Debt Level of the Country

The advent of the Ebola virus disease (EVD) from 2014 to 2016 undermined the macro-budget

fundamentals of the country. The EVD slowed down the reforms that had been underway up to early

2013 (Mining Code, Investment Code, Petroleum Code, new public finance organic law, public

governance instrument, new public procurement code, electricity management, etc.). The initiation of

these reforms had enabled the country to reach the completion point of the Heavily-Indebted Poor

Countries Initiative (HIPCI) in 2012. Indeed, growth was 1.1% in 2014 and 0.1% in 2015, and the budget

deficit rose to 7% of GDP in 2015, compared to 3% in the previous years. The decline in economic and

financial activities, revenue and international reserves, as well as significant capital investment from the

2015 presidential elections, impacted on macroeconomic management. The country proposed a major

budget adjustment (reduce the deficit from 7% of GDP in 2015 to 0.4% of GDP in 2016) which enabled

it to conclude, for the 1st time in its history, a full programme with the IMF. This adjustment has helped

to freeze over 90% of infrastructure costs, including for roads. This highly severe budget adjustment

helped to contain the budget deficit to below 3% in 2016, and the government intends to maintain this

level. The outlook remains optimistic, with growth recovery estimated at 6.7% in 2016 and projected at

6% in 2017, driven by an increase in production and investment in the mining sector, robust agricultural

performance, and partial data update in the national accounts. Debt levels remained sustainable at 26%

of GDP in 2016. However, although this economic recovery and the more pronounced resumption of

fiscal reforms are significant, their impact on the expansion of fiscal space will only be felt within the

Page 40: MULTINATIONAL 225 KV GUINEA-MALI ELECTRICITY ... · v Project Summary 1. General Project Overview 1.1. The 225 kV Guinea-Mali Electricity Interconnection Project identified in 2011

X

next two to three years. In the interim, the Government is seeking budget support from its development

partners, including the Bank.

In light of the foregoing, it is clear that the Government of Guinea is determined to implement its

development agenda and to give priority to the transport sector, even though with difficulties in raising

domestic revenue as capital. On that basis, and at the request of the Government, it is proposed that the

counterpart contribution be reduced for the ADF window.

II. MALI

Preparation of the project and its future implementation are characterized by the fact that Mali has been

hard hit by impact of the security, political, economic and social crises that have rocked the country.

The pressure on State resources is enormous: the Agreement for Peace and Reconciliation in Mali signed

between the Government and the armed movements in May and June 2015 is in the implementation

phase with increased expenditure on security, the social sectors, poverty reduction, rehabilitation and

reconstruction.

The total cost of the 225kV Guinea-Mali Electricity Interconnection Project is UA 299.63 million. It

will be financed with a grant of UA 13.90 million and a loan of UA 16.10 million from the African

Development Fund (ADF); grants and loans from other donors amounting to UA 229.25 million; a

Guinean Government contribution of UA 9.16 million; and a Malian Government contribution of UA

1.22 million. Thus, over 90% of the project cost will be financed with donor resources, including those

of the ADF, given the fragile economic and financial situation in Guinea and Mali.

Mali is committed to the implementation of its development programme. The Strategic Framework

for Economic Recovery and Sustainable Development (CREDD) 2016-2018 is in its second year of

implementation. It is built on two preliminary pillars, three strategic pillars and thirteen priority areas.

The preliminary pillars are: (i) peace and security; and (ii) macroeconomic stability; and the three

strategic pillars are: (i) inclusive and sustainable economic growth; (ii) social development and access

to basic social services; and (iii) institutional development and governance.

There is still a sustained effort to allocate substantial resources to the project's focus area. In the

appropriation directions for CREDD 2016, the amount of own resources allocated to the specific

objective “Developing renewable energies and increase access to low-cost electricity for rural and urban

communities” was CFAF 9.9 billion, whereas external assistance is estimated at CFAF 67.9 billion, or

82.9% of the total resources earmarked for the energy sector. Energy sector needs remain significant in

light of the effects of the crisis, and the resumption of economic growth. However, the energy needs in

the context of economic recovery and implementation of the Agreement for Peace and Reconciliation

in Mali are significant.

In 2016, the Government implemented a cautious fiscal policy geared towards economic recovery. The overall budget deficit (cash basis, including grants) was 4.3% of GDP. It is expected to drop to

approximately 4% of GDP in 2017. In the supplementary budget of 2017, the increased expenditure

stems from additional expenses generated by the programming law for internal security for the 2017-

2021 period; regional, local and communal elections and the referendum; the provision for new projects

and the allocation (through a special Treasury account) of 0.4% of GDP to start the Sustainable

Development Fund (SDF) set up in 2017 under the peace agreement to finance the special development

strategy for the regions in North Mali. The last debt sustainability analysis indicated a moderate

debt distress risk for Mali. However, debt sustainability is threatened by shocks resulting from the

concentration of exports on gold, the decrease in remittances and foreign direct investment as well as

the hardening of financial conditions. Therefore, the Government must continue its efforts to control the

external debt by resorting mainly to grants and concessional loans with a minimum grant element of

35%. Mali’s public debt stock represents 36.6% of GDP and while its external debt accounts for

24.1% of GDP. As of 31 December 2016, Mali had no external public debt servicing arrears.