multiple criteria decision analysis (mcda) to identify the ... jararaa.pdf · multiple criteria...

339
An-Najah National University Faculty of Graduate Studies Multiple Criteria Decision Analysis (MCDA) to Identify the Setting Priorities of the Sanitation Sector in the West Bank By Baraa Yaseen Jararaa Supervisor Prof. Marwan Haddad This Thesis is Submitted in Partial Fulfillment of the Requirements for the Degree of Master of Water and Environmental Engineering, Faculty of Graduate Studies, An-Najah National University, Nablus, Palestine. 2013

Upload: others

Post on 24-Mar-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

An-Najah National University

Faculty of Graduate Studies

Multiple Criteria Decision Analysis (MCDA)

to Identify the Setting Priorities of the

Sanitation Sector in the West Bank

By

Baraa Yaseen Jararaa

Supervisor

Prof. Marwan Haddad

This Thesis is Submitted in Partial Fulfillment of the Requirements for

the Degree of Master of Water and Environmental Engineering,

Faculty of Graduate Studies, An-Najah National University, Nablus,

Palestine.

2013

III

Acknowledgment I would like to express my sincere gratitude to my supervisor Dr. Prof.

Marwan Haddad for his helpful efforts, fruitful guidance, and continual

encouragement throughout the entire research. Special thanks go also to

my friends for the help in preparing the proposal of this study and guidance

during its preparation.

I would like to thanks to Palestinian Water Authority (PWA) and Austrian

project for funding my master study and helping me in providing the data.

Special thanks go to Eng. Adel Yasin, Dr. Subhi Samhan, and Eng. Hazem

Kitana.

Special thanks to my parents for help, encouragements, and patience.

My wife I love you so much, thank you for your understanding and love

during my study.

Finally, I am very grateful to all those who helped and encouraged me to

make this research possible.

IV

االقرار أنا الموقع أدناه مقدم الرسالة التي تحمل العنوان :

Multiple Criteria Decision Analysis (MCDA) to

Identify the Setting Priorities of the Sanitation

Sector in the West Bank

أقر بأن ما اشتممت عميو ىذه الرسالة إنما ىي نتاج جيدي الخاص، باستثناء ما تمت اإلشارة لم يقدم لنيل أية درجة أو لقب عممي إليو حيثما ورد، وأن ىذه الرسالة ككل، أو أي جزء منيا

أو بحثي لدى أية مؤسسة تعميمية أو بحثية أخرى .

Declaration

The work provided in this thesis, unless otherwise referenced, is the

researcher's own work, and has not been submitted elsewhere for any

other degree or qualification.

Student's Name : : اسى انطانب

Signature: : انتوقيغ

:Date : انتاريخ

V

Table of Contents Page Content No

III Acknowledgment

IV Declaration

V Table of Contents

X List of Tables

XII List of Figures

XIII Acronyms

XIV Abstract

1 Chapter 1. Introduction

1 Multi-Criteria Decision Analysis (MCDA) 1.1

2 Sanitation Sector in general 1.2

4 Research Question 1.3

4 Objectives of the Research 1.4

5 Methodology 1.5

11 Chapter 2. Literature review

11 Multi-Criteria Decision Analysis (MCDA) 2.1

11 Introduction 2.1.1

15 Multicriteria Solving Methodologies 2.1.2

15 Regulatory Uses of MCDA 2.1.3

16 U.S. Army Corps of Engineers 2.1.3.1

18 U.S. Environmental Protection Agency 2.1.3.2

20 U.S. Department of Energy 2.1.3.3

22 European Union 2.1.3.4

23 MCDA Applications for Environmental Management

and Related Uses

2.1.4

24 Application to general environmental management 2.1.4.1

32 Application to Stakeholder Involvement 2.1.4.2

35 Application to Management of Contaminated Lands 2.1.4.3

36 Sanitation Sector in Palestinian Territories 2.2

36 Introduction 2.2.1

38 Regulatory Framework 2.2.2

40 Water Law No. 3, 2002 2.2.2.1

41 Joint Water Committee 2.2.2.2

42 Environment Law No. (7) of 1999 2.2.2.3

43 National Water Plan 2.2.2.4

44 Waste Water Management Plan report (PWA

Wastewater Policies)

2.2.3

44 Wastewater Collection Policies 2.2.3.1

46 Industrial Wastewater Policies 2.2.3.2

47 Wastewater Treatment Policies 2.2.3.3

VI

49 Awareness and Stakeholders participation 2.2.3.4

49 Tariff Policy 2.2.3.5

51 Legal and Administration Policy 2.2.3.6

52 Chapter 3. Current situation of institutional

wastewater management agencies in palestine

53 National Water Council 3.1

55 The Palestinian Water Authority 3.2

56 Other Government Institutions 3.3

58 Local Committees, Municipalities, and Village Councils 3.4

58 Local NGO’s and International Organizations 3.5

60 Chapter 4. Situation of sanitation in palestine and

future plans

61 Situation of Wastewater in the Urban Area (1996-2012) 4.1

62 Situation of Wastewater in the Refugee Camps (1996-

2012)

4.2

64 Situation of Wastewater in Rural (1996-2012) 4.3

67 Situation of Wastewater in Rural (1996-2012) 4.4

71 Deficiencies and Problems 4.5

75 Driving Forces for WW Management 4.6

76 Opportunities 4.7

76 Existing and Future Plans: 4.8

76 To Stop Flowing Wastewater Toward the Green LINE

to be Treated and Reused in Palestine

4.8.1

77 Criteria for WWT Selection 4.8.2

77 Look into the Future Sustainable Planning of WWTP 4.8.3

78 Centralized WWTP (>15000 m3/day or 200,000

PE)

4.8.4

79 Look into the Future Sustainable Operation Small

WWTP

4.8.5

79 Main Cities and Urban Areas 4.8.6

80 Priorities for Selecting Wastewater Projects (Main

Cities &Urban Areas)

4.8.7

80 Semi Urban (Population 5000-10000) and Rural Areas

(Population 2000-5000)

4.8.8

80 Priorities for Selecting Wastewater Projects (Semi

Urban and Rural Areas)

4.8.9

81 Rural Areas and Small Communities (De-Centralized

(Local WWTP))

4.8.10

82 Reuse & Recycling 4.8.11

82 PWA with Cooperation and Coordination with all 4.8.12

VII

Stakeholders and Beneficiaries will do Strongly and

Effectively

83 Chapter 5. Criteria identification

83 Criteria Used in Some Countries 5.1

83 Egypt 5.1.1

85 Iraq 5.1.2

86 Libya 5.1.3

87 South Africa 5.1.4

88 Stakeholder Consultation 5.2

88 Consultation with Palestinian Ministries 5.2.1

89 Ministry of Agriculture (MoA) 5.2.1.1

91 Palestinian Water Authority (PWA) 5.2.1.2

92 Ministry of Tourism and Antiquities (MoTA) 5.2.1.3

92 Environmental Quality Authority (EQA) 5.2.1.4

93 Ministry of Local Governments (MoLG) 5.2.1.5

94 Ministry of Labor (MoL) 5.2.1.6

94 Consultation with Universities 5.2.2

95 Consultation with NGOs 5.2.3

96 Consultation with Private sector 5.2.4

97 Universal Group for Engineering & Consulting (UG) 5.2.4.1

98 Center for Engineering and Planning (CEP) 5.2.4.2

99 Consultation with Municipalities 5.2.5

99 Nablus Municipality 5.2.5.1

100 Ramallah Municipality 5.2.5.2

102 Citizens Questionnaire 5.3

102 Sample Size 5.3.1

106 Analysis of the Questionnaire 5.3.2

107 First Topic: Water Situation 5.3.2.1

107 Second Topic: Current status of sanitation and citizens'

satisfaction

5.3.2.2

108 Third Topic: Impact of wastewater on citizens 5.3.2.3

109 Fourth Topic: Economic and social aspects 5.3.2.4

110 Fifth Topic: citizens' awareness, and awareness

campaigns

5.3.2.5

110 Sixth Topic: Institutional issues 5.3.2.6

111 Seventh Topic: Decision-making 5.3.2.7

112 EQA Terms of Reference (TOR) 5.4

113 Selected Criteria Used in the Sanitation Projects (donors

criteria)

5.5

113 Wastewater Projects for USAID Funding 5.5.1

114 Assessment of Potential West Bank Water Projects for 5.5.1.1

VIII

USAID Funding

114 Identification of Potential Projects 5.5.1.1.1

115 Establishment of project selection criteria 5.5.1.1.2

116 Evaluation of Shortlisted Projects 5.5.1.1.3

118 Recommended Criteria for Prioritizing Projects 5.5.1.1.4

121 Site selection report 5.5.1.2

123 Criteria 1: Civil Administration Permitting 5.5.1.2.1

125 Criteria 2: Operational Simplicity 5.5.1.2.2

127 Criteria 3: Environmental and Health Impacts 5.5.1.2.3

129 Criteria 4: Municipal Readiness 5.5.1.2.4

131 Wastewater Projects for European Union (EU) Funding 5.5.2

133 Wastewater Projects for German Bank for

Reconstruction (KFW) Funding

5.5.3

134 Multi-Criteria Screening of Options 5.5.3.1

134 Environmental Issues 5.5.3.2

134 Socio-Economic Impact 5.5.3.2.1

134 Institutional Criteria 5.5.3.2.2

135 Wastewater Projects for Ministry of Foreign Affairs

(MFA) Republic of Finland Funding

5.5.4

135 Selection Criteria and Screening 5.5.4.1

136 Wastewater Projects for Local Finance Investment

Projects

5.5.5

136 Suitability of Land 5.5.5.1

136 Political Constraints 5.5.5.2

137 Potential Aquifer Impacts 5.5.5.3

138 Proximity of Reuse Sites 5.5.5.4

138 Proximity to Existing and/or Planned Utilities 5.5.5.5

138 Flood Plain Elevation 5.5.5.6

139 Proximity to Landfill 5.5.5.7

139 Nuisance to Surrounding Urban Areas 5.5.5.8

139 Population Served 5.5.5.9

139 Criteria Identification 5.6

141 Chapter 6. Mcda tools development

141 Normalize the Weights of Criteria 6.1

144 Carries a Value Rating for Each Criteria 6.2

144 Demography 6.2.1

144 Water Consumption / Wastewater Production 6.2.2

145 Reusing Wastewater 6.2.3

146 Environmental Factor 6.2.4

148 Operation Body 6.2.5

149 Risk for Industrial Waste 6.2.6

IX

149 Socio-Economic Factor 6.2.7

150 Geographical Factor (topography, catchment) 6.2.8

151 Political Issues 6.2.9

152 Chapter 7. Priorities settings

152 Identify Communities 7.1

163 Application of MCDA Tools 7.2

163 Carries a Value Rating for Each Criteria 7.2.1

163 Demography 7.2.1.1

164 Water Consumption / Wastewater Production 7.2.1.2

166 Reusing Wastewater 7.2.1.3

167 Environmental Factor 7.2.1.4

170 Operation Body 7.2.1.5

171 Risk for Industrial Waste 7.2.1.6

174 Socio-Economic Factor 7.2.1.7

179 Geographical Factor (topography, catchment) 7.2.1.8

181 Political Issues 7.2.1.9

182 Evaluation Measure for Each Community 7.2.2

187 Setting Priorities 7.3

188 Sensitivity and Certainty Analysis 7.4

189 Program Implementation (Case Study) 7.4.1

192 Chapter 8. Conclusions and recommendations

192 Conclusions 8.1

193 Recommendations 8.2

195 References

213 Annex

اشن ة

X

List of Tables

Page Table No.

6 Calculate normalize weights to each attributes 1.1

9 Calculate evaluation measure 1.2

28 Applications of decision support tools in environmental

management

2.1

61 Wastewater status in WB-Main Cities (WW

Departments in PWA, 2012)

4.1

62 Existing WW Treatment Plants -urban area (WW

Departments in PWA, 2012)

4.2

63 Wastewater status in WB -Refugee Camps (WW

Departments in PWA, 2012)

4.3

65 Existing Small Scale Treatment Plant-Sample 4.4

65 Existing On-site (Household level) Treatment plants 4.5

67 On-going WW Projects (WW Departments in PWA,

2012)

4.6

68 Proposed and Ongoing WW Treatment Plants (urban

area) (WW Departments in PWA, 2013)

4.7

104 Number of families in the selected communities 5.1

105 Number of samples for each community 5.2

125 Numerical Scoring Description for Criteria 1 ‐ Ease of

Civil Administration Approval

5.3

127 Numerical Scoring Description for Subcriteria 2A –

Operational Simplicity – Gravity Collection

5.4

127 Numerical Scoring Description for Subcriteria 2B –

Operational Simplicity – Wastewater Generation

5.5

128 Numerical Scoring Description for Criteria 3 –

Environmental and Health Impacts

5.6

131 Numerical Scoring Description for Criteria 3 –

Municipal Readiness

5.7

143 Calculate normalize weights to each criteria 6.1

148 Municipal ranking on the basis of performance for the

municipal development program (MDP) in MDLF

6.2

155 Communities that are expected to have a population of

more than 10,000 people in 2030

7.1

163 Demography score of each community 7.2

164 Water consumption score of each community 7.3

166 Wastewater reuse score of each community 7.4

168 Environmental factor score of each community 7.5

170 Operation body score of each community 7.6

172 Risk for Industrial Waste score of each community 7.7

XI

175 Socio-economic factor score of each community 7.8

179 Geographical factor score of each community 7.9

171 political issues score of each community 7.10

183 Calculate evaluation measure for each community 7.11

187 Setting priorities for communities 7.12

190 Setting priorities for the top ten communities according

to four various alternatives

7.13

XII

List of Figures

Page Figure No.

8 Methodological approach to characterizing and

quantifying uncertainty

1.1

10 Flowchart for research methodology 1.2

52 Water Sector Framework 3.1

53 Main stakeholders in water and sanitation sect 3.2

54 National Water Council framework 3.3

68 Existing and future WWTP Projects (WW Departments

in PWA, 2012)

4.1

108 Censorship of wastewater disposal 5.1

108 The impact of wastewater on citizens directly 5.2

109 Illustrates the problems faced by citizens because of

wastewater

5.3

111 Attention to the wastewater sector by government

institutions and civil society organizations (NGO's)

5.4

112 Management of the sanitation sector 5.5

112 Provides wastewater disposal services 5.6

145 Value agricultural land 6.1

147 Hydrogeological vulnerability of groundwater to

pollution in the West Bank

6.2

188 Program Structure (Excel Program) 7.1

XIII

Acronyms ANERA America Near East Refugee Aid

ARIJ Applied Research Institute Jerusalem

CARE Christian Action Research and Education

CEOHS Centre for Environmental and Occupational Health Sciences at

Bethlehem University

EQA Environmental Quality Authority

EU European Union

GTZ German Agency for Technical Co-operation

JICA Japanese International Cooperation Agency

JWU Jerusalem Water Undertaking

KFW German Bank for Reconstruction

MCDA Multi-Criteria Decision Analysis

MFA Ministry of Foreign Affairs, Republic of Finland

MoA Ministry of Agriculture

MoL Ministry of Labor

MoLG Ministry of Local Governments

MoTA Ministry of Tourism and Antiquities

MOU Memorandum of Understanding

PARC Palestinian Agricultural Relief Committee

PCBS Palestinian Central Bureau for Statistics

PHG Palestinian Hydrology Group

PWA Palestinian Water Authority

SCF Save the Children Federation

UNDP United Nations Development Program

UNRW

A

United Nations Relief and Works Agency for the Palestinian

Refugees in the Near East

USAID US Agency for International Development)

WB World Bank

WBG West Bank and Gaza Strip

WESI Water and Environmental Studies Institute at An-Najah National

University

WSERU Water and Soil Environmental Research Unit at Bethlehem

University

IEWS Institute of Environmental and Water Studies at Bir-Zeit

University

WW Waste Water

WWTP Waste Water Treatment Plant

XIV

Multiple Criteria Decision Analysis (MCDA) to Identify the Setting

Priorities of the Sanitation Sector in West Bank

By

Baraa Yaseen Jararaa

Supervisor

Prof. Marwan Haddad

Abstract

During the last two decades, millions of dollars have been invested in the

sanitation sector in the Palestinian lands. Nonetheless, the sanitation sector

is considered one of the sectors that have been neglected over the past

decades as only 28% to 32% of the populations are provided with sewage

systems. Such networks serve some of the main cities, camps and villages

while most of the populations get rid of wastewater via cesspits.

Many researches and studies have been conducted over the sanitation

sector in Palestine, and many plans and strategies have been developed in

this field over the past years. However, none of such researches and

strategies managed to set the priorities of the areas in need to solve the

problem of wastewater disposal.

This research aims at identifying and setting the priorities of the areas in

need to solve the problem of wastewater disposal by using Multiple

Criteria Decision Analysis (MCDA) approach in an attempt to start

projects in such areas. The research has shown that the current way they

are selecting target areas to sanitation projects are either based on the

policies of the donor or on a non-scientific method. So they do not take all

the right criteria to make the right decision.

XV

The research has shown that the criteria which significantly affect the

decision-making process in the sanitation sectors are: the demography,

water consumption - wastewater production, reusing wastewater,

environmental factor, the operation body, the risks of the industrial waste,

the socio-economic factor, the geographical factor and political issues. The

research discussed the evaluative mechanism of such criteria, and a

mathematical relationship was found between the different criteria which

facilitate identifying setting the priorities of areas.

The number of communities whose population is expected to reach up to

10 thousand in 2013 is 97 communities. There are 33 communities served

with sewage systems or in the design or implementation stages with funds

specified for these communities. On the other hand, there are 64

communities that disposed of wastewater via cesspits. According to the

PWA water sector plan for 2010-2030, the number of population of all

communities shall have reached 10 thousand, all connected and served with

a sewage system.

The Multiple Criteria Decision Analysis (MCDA) approach, developed

through this research and which is recommended to be put into use in

2010 and end by 2030 in accordance with the water sector plan, was

applied to 64 communities which consider cesspits as a means of getting

rid of wastewater. The 64 communities were ordered by priority.

The study has put forward a number of recommendations such as that the

Palestinian Water Authority set a long-term plan and a five-year plan to

serve 20 communities ordered by priority and that donating bodies abide

with this plan.

1

Chapter .1

Introductions

1.1 Multi-Criteria Decision Analysis (MCDA)

Multi-Criteria Decision Analysis (MCDA) or Multi-Criteria Decision

Making (MCDM) is a discipline aimed at supporting decision makers faced

with making numerous and sometimes conflicting evaluations. MCDA

aims at highlighting these conflicts and deriving a way to come to a

compromise in a transparent process.

Multi-criteria decision analysis has been recognized as an important tool in

environmental decision-making for formalizing and addressing the problem

of competing decision objectives (Janssen 1992, Lahdelma et al. 2000,

Linkov et al. 2006, Regan et al. 2007, Yatsalo et al. 2007).

The decision-maker’s preferences over options depend on how well they

perform according to a number of objectives or ―criteria‖ {C1…CM} that

have been identified by relevant stakeholders to be the (only) issues on

which a decision between options should be made.

Unlike methods that assume the availability of measurements,

measurements in MCDA are derived or interpreted subjectively as

indicators of the strength of various preferences. Preferences differ from

decision maker to other, so the outcome depends on who is making the

decision and what their goals and preferences are.

Here, we use MCDA method that depend on rankings of options for each

criterion, and also weightings for the criteria. We chose the method because

it has been employed widely in environmental and other decision-making

2

contexts (Janssen 1992, Lahdelma et al. 2000, Linkov et al. 2006, Regan et

al. 2007, Yatsalo et al. 2007). Our chief concern is to highlight the impact

that scoring scales and other assumptions in the process have on decision

outcomes, and to suggest some resolutions for the identified problems.

1.2 Sanitation Sector in general

The Sanitation problem is one of the problems facing communities and

environment and thus affects the lives of humans, plants, and animals not

only in Palestine but in all over the world. Therefore we need clear

comprehensive and sustainable criteria for its development.

There have been substantial developments in (waste) water management

and treatment technology worldwide during the past decades (Gijzen,

2001). In spite of that, in 1997 three billion people on earth lacked

adequate sanitation. In Africa alone, 80 million people are at risk of

cholera, and 16 million cases of typhoid infections each year are a result of

lack of clean drinking water and adequate sanitation (WHO, 1996).

According to the Kyoto summit in 2003, two billion people will not have

access to safe drinking water supplies in the year 2015. The Mediterranean

countries are among the most affected region in the world. Wastewater has

been identified as the main land-based point source pollutant causing

contamination of the (coastal) marine environment (UNEP/GPA, 2000).

The increase in population and therefore in sewage production poses a

great challenge to developing and introducing sustainable sewage

collection and treatment. The efforts in providing these essential services,

especially for poorer regions of the world, are hindered by the

3

shortcomings of the current concept of urban water management and

financial limitations.

Water is a scarce and precious resource in the Middle East. The

Mediterranean countries are among the regions of water stress in the world

(Water stress < 1700 m3/cap. year). Comparing the average international

per capita minimum need according to the WHO (2006) standards (150

l/c/d) with the actual Palestinian water consumption (82 l/c/d); the deficit

in water supply reached up to 41 million cubic meters (mcm) annually.

Population growth, rising living standards and urbanization increase the

pressure on the resource, leading to increasing costs of water supply.

Palestine is a typical example where scarce water resources are being

massively contaminated by excessive use of both fertilizer and manure in

agriculture and by uncontrolled discharge of municipal sewage into the

environment. This might seriously endanger future potable water supplies

of the population at large.

In Palestine, the only substantial water resource available is groundwater.

Presently, the application of wastewater treatment is limited due to high

costs and the technological complexity of conventional systems. Seepage

of domestic wastewater from on-site cesspits, inadequately performing

off-site sewage treatment plants, together with the excessive use of

fertilizer in agriculture has resulted in a dramatic increase of nitrate levels

in aquifers. In the West Bank, signs of nitrate pollution in some

agricultural wells and freshwater springs were reported every others, by

Alawneh and Al-Sa`ed (1997).

4

Palestine suffers from both water scarcity and water pollution; water supply

is dependent upon annual precipitation, which replenishes the aquifers,

natural springs and streams in Palestinian territories. Ground water and

rainwater collected in cisterns is exposed to severe pollution especially

from untreated wastewater.

In Palestine, domestic and industrial wastewaters are collected mainly in

cesspits or, to a much lesser extent, in sewerage networks. In some villages

and refugee camps, black wastewater is collected in cesspits (PCBS, 2007).

1.3 Research Question

The following are the research questions:

1. What are the criteria that affect the decision-making in the sanitation

sector in Palestine? And how to harmonize these criteria?

2. What are the locations of most need to solve the problem of sewage

in West Bank?

1.4 Objectives of the Research

This research aims to:

Overview and assess the sanitation sector investments, progress,

deficiencies, problems, existing and future plans.

Identify the criteria that affect the decision-making in the sanitation

sector and how to harmonize these criteria.

Develop a relationship to setting priorities of the sanitation sector

according to the various criteria obtained by MCDA.

Identify the areas which most need to solve the problem of sewage in

the West Bank.

5

1.5 Methodology The research methodology goes through five phases. Figure 1.2 shows the

relation between the phases. These phases are:

Phase 1: Data collection

A. Review the present strategy of the PWA, MEnA and the PA

environmental laws.

B. Review the available documents, papers, reports, strategy of some

countries and studies on the sanitation sector.

C. Identify the involved stakeholders in the sanitation sector such as

institutions; organizations; ministries; universities and municipalities.

D. Review the methods for determining the priorities in sanitation sector

in the ministries and relevant institutions.

E. Review the selected criteria used in the sanitation projects.

F. Review the performed projects in the sanitation sector (Investments).

G. Address the current status of sanitation in the West Bank (sewage

systems, pumps, treatment plants, cesspits).

Phase 2: Criteria Identification

A. Identify the criteria established by the laws and strategy in Palestine.

B. Identify the criteria used in some countries.

C. Stakeholder Consultation such as institutions; organizations;

ministries; universities and municipalities.

D. Questionnaire for citizens.

E. EIA Terms of Reference (TOR) of sanitation projects.

F. Determine the criteria followed by donors in the projects.

6

Phase 3: MCDA tools development

A. Realistic evaluations should take into account multiple attributes in

decision making, so, in reality we have different attributes (criteria)

that differ in importance. The ―difference in importance‖ makes it

essential to give a weight for each attribute. This is done through

consultation with stakeholders in the sanitation sector.

B. Normalize the weights by: Give a score for each attribute’s weight,

compute the summation of all the scores, and divide the score of each

attribute by the total score. See Table 1.1 and equation below:

Table 1.1 Calculate normalize weights to each attributes

Attributes Weights Normalize weight

1 W1 W1/∑W

2 W2 W2/∑W

3 W3 W3/∑W

. . .

. . .

. . .

m Wm Wm/∑W

C. Each alternative carries a value rating for each attribute. The rating of

each alternative for each attribute indicates how well the alternative

will perform as each attribute is considered. The rating will be

determined by reference to the books, references and scientific papers

and by reference to the owners of specialty in these attribute.

7

D. Managing uncertainty: The methodology for managing uncertainty

developed for characterizing and quantifying uncertainty in the

decision-making process is showing in Figure 1.1 as can be seen from

this figure, the decision-making process starts by defining the set of

options of interest (i.e. potential, alternative solutions) for the analysed

problem. At the same time, a set of criteria that will be used to

evaluate these optional solutions is identified too. This preliminary

analysis is carried out by liaising with stakeholders and supported by

the MCDA analyst. The objective is to identify/formulate planning

decisions that could be potentially used to solve the problem analysed

and, at the same time, to define the quality standards that should be

met by the implemented decision. This is an iterative process which

eventually results in a list of optional solutions to be considered and

the multiple criteria that will be used to evaluate and compare them.

8

Figure 1.1: Methodological approach to characterizing and quantifying uncertainty

Phase 4: Priorities settings

A. Identify communities. We will take the towns that have population over

10 thousand people. In accordance with the directives of the PWA to

resolve sanitation problems in the towns and villages with the population

over 10 thousand people by 2030.

B. Compile information on each community through PCBS, PWA, EQA,

various ministries, municipalities, and village councils.

C. GIS application, expected the availability of the following maps: basins

map, geological map, rainfall map, soil map, springs map, topography map,

land use map, catchment area map, built up areas map, drainage systems

map and satellite image.

9

D. Application of MCDA tools to each community.

E. Evaluation measure for each community. See in the Table below:

Table 1.2: Calculate evaluation measure Attri

bute

s

Normalize

weight

Score for each

alternative (community)

Evaluation measure for each

alternative (community)

1 2 3 n 1 2 3 n

1 W1 S11 S21 S31 W1*Sn1 W1*S11 W1*S21 W1*S31 W1*Sn1

2 W2 S12 S22 S32 W2*Sn2 W2*S12 W2*S22 W2*S32 W2*Sn2

3 W3 S13 S23 S33 W3*Sn3 W3*S13 W3*S23 W3*S33 W3*Sn3

. . . . . . . . . .

. . . . . . . . . .

. . . . . . . . . .

m Wm S1m S2m S3m Snm Wm

*S1m

Wm

*S2m

Wm

*S3m

Wm

*Snm

F. Setting priorities for each community based on evaluation measure.

Phase 5: Results and thesis writing

It will begin from the first phase and continuous through all phases and

include thesis drafting and finalizing the thesis.

10

Figure 1.2: Flowchart for research methodology

11

Chapter 2

Literature review

2.1 Multi-Criteria Decision Analysis (MCDA)

2.1.1 Introduction

Multiple criteria problems in general have received different approaches

throughout history and different authors have been using multiple

approaches and several methods for more than half a century. In that

period, multiple criteria analysis has received ―different names‖ such as

Multi-Criteria Decision Making (MCDM), Multi-Criteria Evaluation

(MCE), Multi-Attribute Utility (MAU), and Multi-Objective Programming

(MOP). Terms to describe similar decision analysis methods in the

literature vary. For example Doumpos (2002) uses the term ―multicriteria

decision aid‖ (MCDA) and Dodgson et al, use a broader term ―multicriteria

analysis‖ (MCA) which includes multicriteria decision analysis . For

purposes of this thesis, the term ―multiple criteria decision analysis‖

(MCDA) will be used for the sake of consistency.

Environmental managers of developing countries are faced with an

additional problem. The situation they often face is one of a limited budget

to implement all of their projects.

They can perform cost effectiveness analyses to determine the best

alternative and they can perform cost-benefit analyses to demonstrate that

the project benefits outweigh the costs, but the issue they often encounter is

that they have more justifiable projects than they have budget. The tools

that these managers need are those that help them to determine which of

12

these justifiable projects are the most important. In other words, ―Which

projects provide the most benefit to the successful management of their

mission?‖ To make this determination, they need a tool to prioritize their

projects in a manner, consistent with established criteria, that is satisfactory

to all stakeholders (including ultimately the public and donor countries,

which are typically the source of funding for such projects). Often the

method that environmental managers resort to is one of ad hoc decision

making. Disadvantages of this method are that such decisions are not

transparent to other stakeholders and may appear unfair. With no structured

basis for the decision process, it becomes less reliable and more difficult to

defend to others. Often times experienced mangers set the right priorities

based on ad hoc decision making, but cannot back up their decision

satisfactorily to all stakeholders. According to Satterstrom Linkov, ―A

systematic method of combining quantitative and qualitative inputs from

scientific studies of risk, cost and cost-benefit analyses, and stakeholder

views has yet to be fully developed for environmental decision making‖

(Linkov, et. al., 2006). More integrative decision analysis processes such as

multiple criteria decision analysis (MCDA) may serve environmental

managers better than the other tools.

MCDA is an ―umbrella term to describe a collection of formal approaches

which seek to take explicit account of multiple criteria in helping

individuals or groups explore decisions that matter‖ (Belton and Stuart,

2002). MCDA facilitates understanding of the problem and uses the

priorities and values of the decision makers to take the most appropriate

13

course of action. MCDA does not relieve the decision maker from the

requirement to make a difficult decision; rather, it provides a structure

within which decision makers and stakeholders express their values and

priorities to each other, resulting in a better understanding of the problem,

potential solutions, and areas in which different stakeholders agree. Many

times a course of action results from the process that was not originally

considered that reflects a compromise of the stakeholders. The MCDA

process in general includes problem identification, problem structuring,

model building, and implementation of the model to inform and challenge

thinking, followed by determination of a course of action. MCDA ―…

integrates common sense with empirical, quantitative, normative,

descriptive, and value-judgment-based analysis‖ (Haimes, 2005).

MCDA is supported by data management procedures, modeling

methodologies, optimization and simulation techniques, and decision

making approaches for the ultimate purpose of improving the decision

making process (Haimes, 2005). According to Dodgson (2000), the main

role of MCDA techniques is to ―deal with the difficulties that human

decision-makers have been shown to have in handling large amounts of

complex information in a consistent way. . . . [MCDA involves breaking a]

problem into more manageable pieces to allow [for easier analysis] and

then of reassembling the pieces to present a coherent overall picture to [aid

in thinking and decision making.] As a set of techniques, MCDA provides

different ways of disaggregating a complex problem, of measuring the

14

extent to which options achieve objectives, of weighting the objectives, and

of reassembling the pieces‖ (Dodgson et al., 2000).

A common technique in MCDA models is the use a preference matrix that

displays how each alternative under consideration compares to others in

terms of the different selection criteria established for the evaluation. In

simple applications, the analysis of the performance matrix directly may be

all that is needed to determine the best solution.

According to Dodgson (2000), in these situations one of the first steps is to

determine ―if any of the [alternatives] are dominated by others. Dominance

occurs when one option performs at least as well as another for all criteria

and is better than the other for at least one criterion‖ (Dodgson et al., 2000).

An analysis for dominance can be used to eliminate alternatives from

consideration or to review the criteria used to determine if all applicable

criteria has been included in the analysis.

In most MCDA applications, numerical analysis is conducted on the

performance matrix to determine the preferred alternative. The analysis

typically involves scoring in which a numerical score is assigned to each

alternative based on strength of preference scale for each criterion.

Weighting is also commonly used to define the relative value or importance

of each criterion. Models using this approach are referred to as

compensatory techniques since low scores on some criteria can be offset by

high scores on others. ―The most common way to combine scores on

criteria, and relevant weights between criteria, is to calculate a simple

weighted average of scores. Use of such weighted averages depends on the

15

assumption of mutual independence of preferences. This means that the

judged strength of preference for an option on one criterion will be

independent of its judged strength of preference on another‖ (Dodgson et

al., 2000).

2.1.2 Multicriteria Solving Methodologies

According to Saaty (1996), there are four major approaches or

methodologies of multicriteria.

First, the Analytic Hierarchy Process (AHP) that is a utility and value

theory of economics based on the use of lottery comparisons.

The second approach is probabilistic, based on Bayesian Theory.

Third, Outranking Method based on ordinal comparison of concordance

and discordance.

And fourth, Goal programming that is basically a modified version of

Linear Programming.

2.1.3 Regulatory Uses of MCDA

Decision process implementation is often based on the results of physical

modelling and engineering optimization schemes. Even though federal

agencies are required to consider social and political factors, the typical

decision analysis process does not provide specifically for explicit

consideration of such issues. Comparatively little effort is applied to

engaging and understanding stakeholder perspectives (including the general

public as well as potentially responsible parties and natural resource

trustees) or to provide for potential learning among stakeholders. A result

of this weakness in current and common decision models is that the process

16

tends to quickly become adversarial whereby there is little incentive to

understand multiple perspectives or to share information. However, a

review of regulatory and guidance documents reveals several programs in

the United States where regulatory agencies involved in environmental

issues are beginning to implement formal decision-analytic tools (such as

MCDA) in their decision-making process.

2.1.3.1 U.S. Army Corps of Engineers

Historically, the U.S. Army Corps of Engineers (USACE) has used

essentially a single-measure approach to civil works, planning decisions

through its Principles and Guidelines (P&G) framework (USACE 1983).

The USACE has primarily used net national economic development (NED)

benefits as the single measure to choose among different alternatives. The

P&G method makes use of a complex analysis of each alternative to

determine the benefits and costs in terms of dollars and other non dollar

measures (e.g., environmental quality and safety); the alternative with the

highest net NED benefit (i.e., with no environmental degradation) is

usually selected. The USACE uses a variety of mechanistic and

deterministic fate and transport models to provide information in

quantifying the various economic development and ecological restoration

accounting requirements as dictated by P&G procedures. The level of

complexity and scope addressed by these models is determined at the

project level by a planning team. Issues such as uncertainty and risk are

also addressed through formulation at the individual project management

level.

17

While the P&G method is not specifically required for planning efforts

related to military installation operation and maintenance, regulatory

actions or operational or maintenance dredging, it presents a general

decision approach that influences many USACE decisions. The USACE

planning approach is essentially a mono criterion approach where a

decision is based on a comparison of alternatives using 1 or 2 factors. Cost-

benefit analysis, for example, is a mono criterion approach. The P&G

approach has its challenges in that knowledge of the costs, benefits,

impacts, and interactions is rarely precisely known. This single-number

approach is limiting and may not always lead to an alternative or decision

process satisfactory to stakeholders.

In response to a USACE request for a review of P&G planning procedures,

the National Research Council (NRC 1999) provided recommendations for

streamlining planning processes, revising P&G guidelines, analyzing cost-

sharing requirements, and estimating the effects of risk and uncertainty

integration in the planning process. As an integration mechanism, the NRC

(1999) recommended that further decision analysis tools be implemented to

aid in the comparison and quantification of environmental benefits from

restoration, flood damage reduction, and navigation projects. In addition,

new USACE initiatives, such as the Environmental Operating Principles

within USACE civil works planning, dictate that projects adhere to a

concept of environmental sustainability that is defined as ―a synergistic

process, whereby environmental and economic considerations are

effectively balanced through the life of project planning, design,

18

construction, operation and maintenance to improve the quality of life for

present and future generations‖ (USACE 2003a, p. 5).

In addition, revised planning procedures have been proposed to formulate

more sustainable options through ―combined‖ economic development and

ecosystem restoration plans (USACE 2003b). While still adhering to the

overall P&G methodology, USACE (2003b) advises project delivery teams

to formulate acceptable, combined economic development and ecosystem

restoration alternatives using MCDA and trade-off methods (Males 2002).

Despite the existence of new guidance and revisions on the application of

MCDA techniques to environmental projects, there remains a need for a

systematic strategy to implement these methods within specific USACE

mission areas (e.g., navigation and restoration) as well as linkage with

existing risk analysis and adaptive management procedures.

2.1.3.2 U.S. Environmental Protection Agency

Stahl et al. (2002) and Stahl (2003) reviewed the decision analysis process

in the U.S. Environmental Protection Agency (USEPA) and observed that

although USEPA has a mandate to make decisions in the public interest

pertaining to the protection of human health and welfare, there are barriers

in current USEPA decision processes that may discourage stakeholder

participation, integration of perspectives, learning about new alternatives,

and consensus building. Similar to the USACE, the USEPA uses a variety

of modeling tools to support its current decision-making processes. The

majority of these tools are quantitative multimedia systems that assess

19

benefits and risks associated with each proposed alternative with the

objective of selecting the best option (Stahl 2003).

Several USEPA guidance documents introduce decision-analytic tools and

recommend their use. Multicriteria integrated resource assessment (MIRA)

has been proposed as an alternative framework to existing decision analysis

approaches at USEPA (Stahl et al. 2002; USEPA 2002; Stahl 2003). MIRA

is a process that directs stakeholders to organize scientific data, establishes

links between the results produced by the research community, and

organizes applications in the regulatory community. MIRA utilizes AHP-

based trade-off analysis to determine the relative importance of decision

criteria.

Multi-attribute product evaluation is inherent in the nature of life-cycle

assessment, which has rapidly emerged as a tool to analyze and assess the

environmental impacts associated with a product, process, or service

(Miettinen and Hamalainen 1997; Seppala et al. 2002). Further, the USEPA

has developed the ―Framework for Responsible Environmental Decision-

Making‖ to assist the Office of Pollution Prevention and Toxics in their

development of guidelines for promoting the use of environmentally

preferable products and services (USEPA 2000). The ―Framework for

Responsible Environmental Decision-Making‖ decision-making method

provides a foundation for linking life cycle indicator results with technical

and economic factors for decision makers when quantifying the

environmental performance of competing products.

20

2.1.3.3 U.S. Department of Energy

Similar to the USACE and USEPA, the U.S. Department of Energy

(USDOE) uses a variety of multimedia models to support its decision-

making process. A recent review (Corporate Project 7 Team 2003)

concluded that even though there are a significant number of guidance

documents, systems, and processes in use within the USDOE to determine,

manage, and communicate risk, there is a great need for comparative risk

assessment tools, risk management decision trees, and risk communication

tools that would allow site managers to reach agreement with their

regulators and other stakeholders while achieving mutual understanding of

the relationship between risk parameters, regulatory constraints, and

cleanup. Several USDOE models have been developed specifically for

dealing with radiologically contaminated sites and sites with dual (chemical

and radiological) contamination. Several of the current models are

deterministic, although probabilistic multimedia models have also been

developed and used (USDOE 2003).

Several USDOE guidance documents introduce decision-analytical tools

and recommend their use. Technical guidance developed for a wide range

of USDOE decision needs (Baker et al. 2001) segregate the decision

process into 8 sequential steps: defining the problem, determining the

requirements, establishing the goals of the project, identifying alternative

methods and products, defining the criteria of concern, selecting an

appropriate decision-making tool for the particular situation, evaluating the

alternatives against the criteria, and, finally, validating solution(s) against

21

the problem statement. Guidance also focuses on how to select a decision-

making tool from among 5 recommended evaluation methods. These

methods include pros-and-cons analysis, Kepner-Tregoe (K-T) decision

analysis, AHP, MAUT, and cost-benefit analysis.

The USDOE has developed a standard paradigm for selecting or

developing a risk-based prioritization (RBP) system (USDOE 1998). The

paradigm describes the issues that should be considered when comparing,

selecting, or implementing RBP systems. It also identifies characteristics

that should be used in evaluating the quality of a RBP system and its

associated results. The USDOE (1998) recommends the use of MAUT as

an RBP model because it is a flexible, quantitative decision analysis

technique and management tool for clearly documenting the advantages

and disadvantages of policy choices in a structured framework. The MAUT

merits special consideration because it provides sound ways to combine

quantitatively dissimilar measures of costs, risks, and benefits, along with

decision-maker preferences, into high-level, aggregated measures that can

be used to evaluate alternatives. The MAUT allows full aggregation of

performance measures into 1 single measure of value that can be used for

ranking alternatives. However, USDOE (1998) cautions that the results of

MAUT analysis should not normally be used as the principal basis for

decision making because decision making will generally require accounting

for factors that cannot be readily quantified (e.g., equity). Furthermore,

USDOE (1998) guidance states that no technique can eliminate the need to

22

rely heavily on sound knowledge, data, and judgments or the need for a

critical appraisal of results.

The USDOE has used a multi-attribute model as the core of its

Environmental Restoration Priority System for prioritizing restoration

projects developed in the late 1980s (Jenni et al. 1995). Although the

Environmental Restoration Priority System was designed to operate with

any specified set of values and tradeoffs, its use was limited to values that

were elicited from USDOE managers, including those based on risk

analysis. The USDOE has not applied the Environmental Restoration

Priority System because of stakeholder opposition, although similar

decision support systems have since been adopted for use at various

USDOE sites (CRESP 1999). The USDOE has attempted to use simple

weighting to aid program planning and budget formulation processes

(CRESP 1999).

2.1.3.4 European Union

A detailed review of the regulatory background and use of decision-

analytic tools in the European Union (EU) was recently conducted within

the EU-sponsored Contaminated Land Rehabilitation Network for

Environmental Technologies project (Bardos et al. 2002). The review

found that environmental risk assessment, cost-benefit analysis, life cycle

assessment, and MCDA were the principal analytical tools used to support

environmental decision making for contaminated land management in 16

EU countries (Austria, Belgium, Denmark, Finland, France, Germany,

Greece, Ireland, Italy, the Netherlands, Norway, Portugal, Spain, Sweden,

23

Switzerland, and the UK). Similar to the United States, quantitative

methods such as risk assessment and cost-benefit analysis are presently the

dominant decision support approaches, while MCDA and explicit tradeoffs

are used less frequently.

Pereira and Quintana (2002) reviewed the evolution of decision support

systems for environmental applications developed by the EU Joint

Research Center. The concept of environmental decision support has

evolved from highly technocratic systems aimed at improving

understanding of technical issues by individual decision makers to a

platform for helping all parties involved in a decision process engage in

meaningful debate. Applications developed in the group include water

resources management, sitting of waste disposal plants, hazardous

substance transportation, urban transportation, management, and

groundwater management.

2.1.4 MCDA Applications for Environmental Management and

Related Uses

The MCDA applications are relevant to environmental management,

stakeholder involvement, and the management of contaminated lands.

Recent publications present more comprehensive reviews of studies

relevant to management of terrestrial sites (Linkov et al. 2004) and

contaminated sediments (Linkov et al. 2005). The use of MCDA is more

strongly evident within the broad areas of environmental management and

stakeholder involvement. Fewer efforts have been made to apply MCDA to

the management of contaminated lands and risk analysis. It should be noted

24

that MCDA has also been applied in many other related policy

development areas, such as manufacturing and services; medical, military,

and public policy (Keefer et al. 2002a, 2002b); climate change (Bell et al.

2003); industrial facility sitting (Larichev and Olson 2001); energy policy

(Hobbs and Meier 2000; Keefer et al. 2002a, 2002b); agricultural resource

management (Hayashi 2000); and life-cycle assessment (Seppala et al.

2002).

2.1.4.1 Application to general environmental management

The MCDA methods have been extensively applied to a range of

environmental management challenge. Each of the examples identified in

the course of this review were classified into 1 of 5 application areas: (1)

prioritization of site/areas for industrial/military activity, (2)

environmental/remedial technology selection, (3) environmental impact

assessment, (4) stakeholder involvement, and (5) natural resource planning.

Prioritization of sites/areas for industrial/military activity—

Management of contaminated sites often requires site zoning for

remediation, restoration, or other uses. Even though applications of

MCDA methods for contaminated site zoning could not be found in

this review, the MCDA methods described in (Kiker 2009) (e.g.,

multi-attribute value theory (MAUT/MAVT), analytical hierarchy

process (AHP), and outranking) have been used, in conjunction with

geographic information system, for selection of site boundaries and

the identification of geographical areas for related uses (e.g.,

industrial or military).

25

Mendoza et al. (2002) used AHP for allocating areas for military

training exercises at Ford Hood, Texas, USA. Keisler and Sundell

(1997) and Sharifi et al. (2003) proposed a framework that integrates

MAUT and spatial analysis to determine national park boundaries.

Joerin and Musy (2000) developed a generic method to integrate

multiple considerations, such as impacts, air quality, noise,

accessibility, climate, utility networks (e.g., water, electricity), and

aesthetics related to land management. Vaillancourt and Waaub

(2002) used outranking and a geographic information system

framework to select a site for a new waste management facility in

Montreal, Quebec, Canada.

Environmental/remedial technology selection— the selection of a

feasible remedial action is usually the final stage of a contaminated

site investigation (e.g., as required under the U.S. Superfund

program). This review identified several instances in which MCDA

methods were used to select the best technology or remedial method.

For example, a MAUT-based method was applied to compare

current and alternative water control plans in the Missouri River,

USA (Prato 2003). A related problem of regulating water flow in a

river–lake system was addressed by Hamalainen et al. (2001) from

the perspectives of group decision theory and stakeholder consensus

building. Wakeman (2003) used the simple multiattribute rating

technique (SMART) (Edwards 1977) to decide which action

alternative to implement in handling the contaminated river sediment

26

at Milltown Dam, Montana, USA. Factors considered by Edwards

(1977) included availability of materials and services, ability to

construct, and reliability. One of the most advanced applications of

MCDA techniques in this area was implemented for nuclear accident

emergency management as a part of the EU-RODOS project, which

used a MAUT analysis for strategy selection for population

protection after a nuclear accident (Ehrhardt and Shershakov 1996).

Environmental impact assessment—Environmental impact

assessments (EIA) are routinely conducted for all major projects in

the United States with the potential to affect the environment. The

assessment of site contamination is often an integral part of EIA.

Janssen (2001) reviewed 21 EIAs conducted in the Netherlands in

the period 1992–2000. Most of the EIAs reviewed by Janssen (2001)

used weighted summation methods, although a few projects used

either the AHP or a MAUT-based approach.

Marttunen and Hamalainen (1995) reviewed MAUT/SMART and

the AHP methods used for decision analysis in EIAs for the

assessment of environmental impacts of a water development project

in Finland. SMART was chosen over AHP because the AHP

procedure proved to be too time consuming for stakeholders

(Marttunen and Hamalainen 1995). Ramanathan (2001)

recommended the use of AHP for considering multiple criteria and

multiple stakeholders in EIA as well as to assess the socioeconomic

impact of a proposed liquefied petroleum gas recovery plant in an

27

industrial area in India. Rogers and Bruen (1998) used Elimination

Et Choix Traduisant la Realite (ELECTRE) III (outranking)

methodology in evaluating thresholds for noise impacts from a

highway project in Ireland. Al-Rashdan et al. (1999) used Preference

Ranking Organization Method for Enrichment Evaluations

(PROMETHEE) (outranking) methodology to rank environmental

impact assessments related to wastewater projects in Jordan; the

methodology was found to be very useful in solving problems with

conflicting criteria.

Natural resource management—the management of natural

resources has involved the application of MCDA. Steiguer et al.

(2003) developed an annotated bibliography that includes 124

examples of the application of MCDA to projects ranging from

theoretical studies to real-world forest and natural resource

management situations. Steiguer et al. (2003) indicate that MCDA

constitutes a newer and, perhaps, more acceptable method for

quantifying and evaluating public preferences. Nevertheless, few

studies included empirical testing of MCDA utility or its feasibility

and, in most of the studies, researchers have used hypothetical data

or, at best, simplified decision situations; few studies were designed

to implement an MCDA-generated management strategy.

The AHP approach within MCDA has received the most attention in

natural resource management applications (Steiguer et al. 2003). The

application of AHP in natural resource planning is summarized in

28

Schmoldt et al. (2001) with Table 2.1 listing some representative

publications. Schmoldt et al. (1994) and Schmoldt and Peterson

(2001b) used AHP to address different aspects of natural park

management, including developing inventory and monitoring

programs, as well as strategic management plans. Pavlikakis and

Tsihrintzis (2003) evaluated the utility of MAUT and AHP in

selecting a technically suitable and socially acceptable management

plan for a national park in eastern Macedonia and Thrace in Greece.

Table 2.1: Applications of decision support tools in environmental

management

Applicat

ion area Method Decision context Funding agency Citation

Prioritiza

tion of

sites/area

s for

industrial

/military

activity

AHP+ GIS

Land condition

assessment for

allocation of

military training

areas

U.S. Army

Engineering

Research and

Development

Center

Mendoza et al.

(2002)

AHP+ GIS

Selection of

boundaries for

national park

International

Institute for

Geo-information

Science and

Earth

Observation,

The Netherlands

Sharifi et al.

(2002)

PROMETH

EE

Waste

management

activities in

Canada

Natural Sciences

and Engineering

Research

Council of

Canada

Vaillancourt

and Waaub

(2002)

ELECTRE +

GIS

Land

management:

Swiss National

Foundation for

Joerin and

Musy (2000)

29

Applicat

ion area Method Decision context Funding agency Citation

develop a land

suitability map

for housing in

Switzerland

Research

(FNRS)

AHP + GIS Landfill sitting Siddiqui et al.

(1996)

MAUT +

GIS

Selection of park

boundaries USDOE

Keisler and

Sundell (1997)

Environ

mental/re

medial

technolo

gy

selection

SMART

Choosing a

remedial action

alternative at

Superfund site

U.S. Army

Corps of

Engineers

Wakeman

(2003)

MAUT

Selection of

management

alternative

Missouri River

University of

Missouri—

Columbia, USA

Prato (2003)

MAUT +

AHP

Regulation of

water flow in a

lake–river

system

Academy of

Finland

Hamalainen et

al. (2001)

MAUT

Offsite

emergency

management

following a

nuclear accident

(such as the

Chernobyl

accident)

European

Commission,

Ukraine

Ehrhardt and

Shershakov

(1996);

Hamalainen et

al. (2000)

Environ

mental

impact

assessme

nt

Review

Review of

MCDA use for

EIAs in

Netherlands

Vrije University,

The Netherlands Janssen (2001)

AHP Socioeconomic

impact

Indira Gandhi

Institute of

Ramanathan

(2001)

30

assessment for a

construction

project in India

Development

Research, India

ELECTRE

Highway

environmental

appraisal in

Ireland

Dublin Institute

of Technology;

University

College Dublin,

Ireland

Rogers and

Bruen (1998)

AHP and

MAUT/SM

ART

Environmental

impact

assessment of 2

water

development

projects on a

Finnish river

Finnish

Environmental

Agency;

Helsinki

University of

Technology

Marttunen and

Hamalainen

(1995)

PROMETH

EE

Prioritization of

EIAs in Jordan

Staffordshire

University,

United Kingdom

Al-Rashdan et

al. (1999)

Natural

resource

manage

ment

AHP Natural park

management

USDA Forest

Services

Schmoldt et al.

(1994);

Peterson et al.

(1994);

Schmoldt and

Peterson

(2001b)

AHP

Management of

small forest in

North Carolina,

USA

USDA Forest

Services

Rauscher et al.

(2000)

MAUT

Management of

spruce budworm

in Canadian

forests

National Science

and Engineering

Research

Council of

Canada

Levy et al.

(2000)

AHP,

MAUT, and

outranking

Forestry

planning in

Finland

Finnish

Academy of

Sciences;

Kangas et al.

(2001)

31

Finnish Forest

Research

Institute

MAUT

Improvement of

habitat suitability

measurements

Finnish Forest

Research

Institute

Store and

Kangas (2001)

AHP

Environmental

vulnerability

assessment for

mid-Atlantic

region

USEPA/USDOE Tran et al.

(2002)

Weighting

Management of

marine protected

areas in Tobago

U.K.

Department of

International

Development

Brown et al.

(2001)

MAUT

Fisheries

management:

select among

alternative

commercial

fishery opening

days

Fisheries and

Ocean, Canada

McDaniels

(1995)

AHP,

MAUT, and

outranking

Fisheries

management

Mardle and

Pascoe (1999)

A PROMETHEE = Preference Ranking Organization Method for

Enrichment Evaluations; ELECTRE = Elimination Et Choix Traduisant la

Realite; AHP = analytical hierarchy process; GIS = geographic information

system; MAUT = multi-attribute utility theory; MCDA = multicriteria

decision analysis; EIA = environmental impact assessment; USDA = U.S.

Department of Agriculture; USDOE = U.S. Department of Energy;

SMART = simple multi-attribute rating technique.

32

Methods of MCDA have been extensively applied to a wide range of

projects in forest management; AHP was applied for a project-scale forest

management problem by Rauscher et al. (2000), and MAUT analysis was

applied to identify policy alternatives to manage a budworm outbreak in a

local site in Canada (Levy et al. 2000). Kangas et al. (2001) tested the

application of several MAUT and outranking methods for large-scale forest

policy planning in Finland. Store and Kangas (2001) used MAUT-based

methods to conduct a habitat suitability evaluation over large forested

areas. Finally, Tran et al. (2002) used AHP to assess the environmental

vulnerability of forests across the mid-Atlantic region in the United States.

The MCDA has also been applied to manage aquatic resources. Simon and

Pascoe (1999) reviewed applications of MCDA in fisheries management.

Brown et al. (2001) used weighting-based trade-off analysis to select a

management option for Buccoo Reef Marine Park in Tobago; criteria

evaluated included ecological, social, and economic factors. McDaniels

(1995) used a MAUT approach to select among alternative commercial

fishery openings involving conflicting long-term objectives for salmon

management.

2.1.4.2 Application to Stakeholder Involvement

Most of the examples presented here attempt to represent the value

judgments of a single decision maker and incorporate these value

judgments into the overall decision-making process. Stakeholder values are

often considered as 1 attribute, along with others, such as costs or risk

reduction. The MCDA can also be used as a framework that permits

33

stakeholders to structure their views about the pros and cons of different

environmental and remedial management options. Applications of MCDA

for group decision making in other areas have been reviewed by Bose et al.

(1997) and Matsatsinis and Samaras (2001).

Arvai and Gregory (2003) was the only study identified that addressed the

application of decision-analytic tools to include stakeholder involvement at

contaminated sites. Arvai and Gregory (2003) compared 2 approaches for

involving stakeholders in identifying radioactive waste cleanup priorities at

USDOE sites, (1) a traditional approach that involved communication of

scientific information that is currently in use in many USDOE, USEPA,

and other U.S. federal programs and (2) a values-oriented communication

approach that helped stakeholders make difficult trade-offs across technical

and social concerns. The 2nd approach has strong affinity to the MAUT-

based trade-offs discussed earlier in this paper. Arvai and Gregory (2003)

concluded that the incorporation of value-based trade-offs information

leads stakeholders to making more informed choices.

Several studies propose the use of MCDA tools for consensus building and

advocate the utility of this application or illustrate the value-oriented

approaches that are based on MAUT. In general, applications may include

individual surveys and workshops designed to elicit value judgment and

construct decision alternatives. Specific applications include water resource

management (McDaniels et al. 1999; Gregory et al. 2001), mining

(Gregory and Keeny 1994), wilderness preservation (McDaniels and

Roessler 1998), and estuary management (Gregory and Wellman 2001).

34

The McDaniels et al. (1999) study concludes that value-based approaches

result in a higher level of comfort for participants and are useful in

developing consensus-based management decisions. The MAUT-based

applications appear to be used in stakeholder value elicitation for regional

forest planning (Ananda and Herath 2003), air quality valuation (Kwak et

al. 2001), and agricultural applications (Gomez-Limon et al. 2003). In

addition, Schmoldt and Peterson (2001a) advocated the use of AHP as a

decision support tool in workshop settings for forest resource management.

The examples presented previously used MCDA to facilitate consensus

building. An alternative application of MCDA is in the organization of

diverse interests instead of seeking consensus-based middle ground.

Gregory and Failing (2002) argue that a clear expression of difference

facilitates development and acceptance of management plans. Another

approach to ranking risk involves soliciting the views of participants both

as individuals and in a group setting (Morgan et al. 2000; Florig et al.

2001). In this manner, decision makers can obtain information on the

rankings of options that involve multiple objectives by weighing the

attributes identified by individuals and groups developed from the 2

methods.

Mental modeling (Morgan et al. 2002) may be a promising tool for

assessing individual judgments. It involves individual, 1-on-1 interviews,

leading participants through a jointly determined agenda of topics. The

method allows free expression and encourages elaboration on topics in

order to reveal individual perspectives at considerable depth. When

35

effectively done, analysts can identify what people believe and why they

believe it. They are also able to compare analyses over time and provide

insights into why beliefs change. Environmental applications of mental

modeling include management of the Illinois River basin in eastern

Oklahoma, USA, (Focht et al. 1999; Whitaker and Focht 2001) and in

energy policy development (Gregory et al. 2003).

2.1.4.3 Application to Management of Contaminated Lands

Most applications of MCDA have been conducted by USDOE to develop

decision models to evaluate specific criteria for the selection of remediation

technologies. Grelk (1997), Grelk et al. (1998), and Parnell et al. (2001)

have developed a decision analysis value model that is based on the process

required by the legislation in the United States supporting the Superfund

program. The USDOE has also sponsored a series of studies designed to

develop decision models used to perform analysis of remedial alternatives

for a mixed-waste subsurface disposal site at Idaho National Environmental

Engineering Laboratory, USA. Ralston et al. (1996) developed a generic

model that incorporates life cycle cost and technological risk assessment

for landfill waste site remediation. Timmerman et al. (1996) proposed the

use of MAUT by USDOE for selecting technology judged to pose the

lowest level of failure or development risks. Deschaine et al. (1998) used a

MCDA simulation model based on AHP to select the most promising

remediation projects from a 114 radiological site remediation portfolio at

the USDOE Savannah River Site. Accorsi et al. (1999a, 1999b), Bonano et

al. (2000), and Apostolakis (2001) developed a methodology that uses

36

AHP, influence diagrams, MAUT, and risk assessment techniques to

integrate the results of advanced impact evaluation techniques with

stakeholder preferences.

2.2 Sanitation Sector in Palestinian Territories

2.2.1 Introduction

In 1999 the Palestinian Environmental Strategy was adopted. Its time span

was until 2010. The strategy has paid special attention to the sanitation

sector. However, a year later of the strategy adoption, the political situation

was deteriorated and the consequences were damaging the Palestinian

environmental plans and the environment as well. As a result, the

sustainable projects changed to be emergency projects that deal with the

moment situation. Although efforts have been undertaken to establish a

regional Strategy for wastewater collection, treatment and disposal, these

concepts have not been followed up on a more precise level. Such studies

have been presented municipality-wise without coordinating efforts on a

regional level.

In 1997, UNDP has sponsored a Conceptual Strategy for the sewage

disposal in the West bank Region. As a result in 1998 the Regional Plan for

West Bank Governorates Water and Wastewater has been elaborated.

The preliminary objective of this master plan was to define the existing

types of sewerage facilities and their locations; to make recommendations

for the phasing of the required works and to identify the institutional set-

ups needed to ensure efficient operation and maintenance and financial

viability of the system, with particular attention to the option of

37

transforming the Jerusalem Water Undertaking (JWU) into a regional water

and sewerage service provider.

The conceptual plan has been prepared as an integral part of necessary

measures to remedy and improve these unsatisfactory conditions included:

Physical planning for implementation of sewerage systems

Institutional plan to comparatively evaluate potentially applicable

institutional types, and to determine the most visible and efficient

institutional arrangement.

Financial and economical plans to comparatively evaluate potentially

applicable utility organizational models, and to determine the most

feasible and economically efficient model.

The Palestinian census in 2007 has revealed that only 28% of the West

Bank communities are connected to a sanitation system. In addition, only

8% of the collected wastewater is being treated. The wastewater mostly

disposed through cesspits or flow in the wadies, and though, there are

serious risks of percolation of contaminants to the groundwater which is the

main source of fresh water in the West Bank.

The uncontrolled discharge of the untreated raw wastewater to the

subsurface poses potential risks to human health and contributed to the

degradation of the environment. This ongoing practice has been responsible

for contaminating and adversely impacting the scare water resources,

particularly springs and shallow water bearing units.

During the past years, the Palestinian Water Policy and Strategy, and other

legislative regulations were not effectively enforced reflected by actual

38

facts and figures, few of them are mentioned above. Thus the Palestinian

Water Authority (PWA) recognizes that in terms of providing sustainable

Wastewater treatment facilities, it is facing a continuous battle in keeping

pace with the impacts of disengagement, unilateral actions of the Israeli

government and unfair Israeli Water Law. As the responsibility of

regulation, formulation, promotion and monitoring of sanitation services

are vested with the PA Government, Town and Village Councils and Local

Authorities, all this calls for an urgent development of a unified Palestinian

Wastewater Policy.

Nowadays, there is an increasing interest in rehabilitating and developing

the sanitation sector in the Palestinian territories.

2.2.2 Regulatory Framework

Historically, the current water legal framework has been impacted by

several administrative and political regimes. Between 1952 and 1967

Jordanian water legislations were enacted within the West Bank while the

British system found application in the Gaza Strip, which was under the

Egyptian administration. Stemmed within the Israeli Water Law of 1959,

an Israeli Military Order No. 2 of 1967 affirmed that all water resources in

the occupied Palestinian Territories as state owned by Israel. However, in

the Oslo II Accord Israel recognizes Palestinian water rights in the West

Bank and these are to be transferred once agreed in the final status

negotiations. Currently, the Article 40, the water treaty signed by the Israeli

and Palestinian sides governs the wastewater management within the West

Bank and Gaza strip. Also, the memorandum of Understanding (MoU,

39

2003), inserted updates and further rules and guidelines pertaining to

establishment of wastewater treatment facilities and reuse schemes.

The Palestinian Water Authority (PWA) was established in April 1995 by

the Palestinian Authority (PA) through Decree no. 90/1995. The PWA

derives its authority from By-law No. 2 of 1996 and Water Law No. 3 of

2002. The Water Law established the National Water Council (NWC)

consisting of representatives of the most important stakeholders in the

water sector. The Palestinian National Authority (PNA) has formulated

both a Water Policy and a Water Strategy to tackle the increased water

scarcity and to manage, protect and conserve the limited water resources

available. The strategy entailed major high politics as the Palestinian water

rights and low politics like promotion of national water regulations, build

institutional capacity, improve data, increase capital investment in water

and wastewater sectors, enforce pollution control, and promote public

participation. In addition, the Environmental Quality Authority (EQA;

formerly Ministry of Environmental Affairs, MEnA) developed a

Palestinian Environment Strategy (PES), where the overexploitation of

water resources and the degradation of water quality were identified as the

issues of highest priority. Also, an Environmental Impact Assessment

(EIA) policy was endorsed by the Legislative Council, where new

wastewater treatment facilities shall obtain an official permit for

establishment through an environmental impact assessment study.

The key regulatory documents regarding wastewater treatment and reuse in

the West Bank and Gaza are the Water Law No. (3) of year 2002; the

40

Agreements with Israel, particularly the MOU of December 2003; and the

Environmental Law No. (7) of 1999.

2.2.2.1 Water Law No. 3, 2002

Water Law No. (3) of year 2002 which stresses the overall need to secure

sustainable development of water resources in a equitable way, makes the

following key provisions with regards to the disposal, treatment and reuse

of wastewater:

Property: All water resources are considered public property (article

3);

Regulation: A license must be obtained to set up or operate a facility

for water or wastewater (article 4) in order to ensure that effluent

discharges met standards that will not pollute existing resources;

Finance: A unified water tariff system should be set (article 20) in a

fair and equitable manner in order to promote the best use of water

resources;

Institutions: The Water Authority has the juridical personality and

full responsibility for managing the water resources and wastewater

in WBG; Water utilities will be established to provide water and

wastewater services (article 25); Regional utilities and water users

associations shall set the prices of water for different usage, in

accordance with the approved tariff system (article 26);

Protection of the Environment : Special guidelines for the

Environmental Impact Assessment for any activity related to water

resources should be prepared (article 29); Anyone who causes

41

pollution in any water resource or its supply system must remove the

pollution to that source or system at his own expense (article 32).

2.2.2.2 Joint Water Committee

There are two agreements with Israel with relevance to waste water

treatment and re-use:

The Memorandum of Understanding on Guidelines and Technical

Criteria for Sewerage Projects, signed 31st December 2003, Israeli –

Palestinian Joint Water Committee; and

The Palestinian-Israeli Interim Agreement On The West Bank & The

Gaza Strip, Washington, D.C., September 28, 1995; Annex III,

Protocol Concerning Civil Affairs, ARTICLE 40: Water and

Sewerage.

The MOU is the most recent document that governs treatment and reuse

standards and will consequently drive the treatment technology and reuse

strategies that will be used in WBG. The MOU sets out agreements for the

collection systems, wastewater treatment, sludge treatment, effluent reuse

and disposal, sludge reuse and disposal and cooperation between the two

sides. The MOU’s very high standards will make implementation costly

and very difficult even though a phased implementation approach to

meeting requirements has been agreed.

The implications and requirements of the MOU of December 2003 signed

by the Israeli and Palestinian Joint Water Committee include the following

elements:

42

All sewerage projects must be complete systems – i.e. collection

systems from source, conveyance to treatment plant, treatment plant,

a plan for reuse or safe disposal, conveyance to point of reuse or

discharge, and safe reuse or disposal of sludge;

Treatment plants must be modular to allow for future expansion: In

the first phase secondary treatment must be achieved; In the second

expansion phase tertiary treatment must be achieved;

Agricultural reuse is to be the primary focus for reuse. This must

include sufficient seasonal effluent storage;

Other forms of reuse must gain mutual agreement from both parties;

Industrial wastewater must be treated separately in a pre-treatment

facility; and

Alternatives for the location of treatment plants must be presented to

both parties and the selection will be agreed in the Joint Water

Committee.

2.2.2.3 Environment Law No. (7) of 1999

The environmental law No. (7) of 1999 provides for the protection of water

resources related to treatment and reuse. The implications of the

Environment Law and effluent standards include:

The requirement to set standards and norms for collecting, treating,

reusing and disposing wastewater and storm water in a sound manner

which comply with the preservation of the environment and public

health;

43

The requirement that any solid, liquid or other substance conforms to

the conditions and standards that the competent agencies determine.

2.2.2.4 National Water Plan

It is stated in the principles of water resources management in this plan that

we should utilize all technically and economically viable alternative

sources including wastewater re-use, brackish water and rainwater

harvesting wherever, and to the extent, practical to supplement overall

supply including artificial recharge to the groundwater aquifers by

infiltration. It is stated also in this plan that farmers and relevant institutions

should plan for maximum use of wastewater re-use in future including

provision for necessary storage, health precautions and crop patterns.

The use of treated wastewater and lower quality water must form a critical

component of future agricultural strategy. The long term target is that only

minimal fresh water will be provided for soil flushing and high value crops.

Other low quality water and conservation practices, including brackish

water, storm water harvesting, blending of water and conjunctive use of

saline and non-saline water, utilized to optimal economic and practical

effect in accordance with specific targets such as utilizing of 40 million

cubic meter per year in the West Bank and 63 in Gaza of treated effluent.

2.2.3 Waste Water Management Plan report (PWA Wastewater

Policies)

These section is explain the main point contained in the Waste Water

Management Plan report was prepared to PWA by Technical Directorate

44

Research And Development Department in august 2003 which is the last

report in this field.

Management of wastewater, storm water and reuse should be administered

through regional utilities for large systems wherever possible, and through

other appropriate structures for smaller and remote areas, integrated with

other sectors in national plans, and should result in a safe, healthy, and

protected environment.

All staff must be trained according to regulations, by donor organisation for

the first phase and based on Palestinian organisations on long term basis.

As a part of all new major developments focus must be given to the

development of a Palestinian wastewater industry. Hence representatives

for consultants, manufacturers, agents, universities and the relevant

authorities must be included in the projects from the earliest preparation

stage.

According to the report some policies that have to follow the Palestinian

Water Authority:

2.2.3.1 Wastewater Collection Policies

For all projects, all elements must be included, as least taken into

consideration. The relevant elements of collection systems, like storm

water harvesting, industrial connection, rainwater collection and upgrading

of poor quality network must be addressed in any wastewater treatment

plant development. PWA must make sure these elements are discussed and

addressed in any big development project. If this is not done, the ambition

levels described in the policy and the stated goals will not be reached.

45

The starting point is to establish clear regulations, specifications and

standards for the wastewater handling, and to make sure that collection

constructions fully comply.

The collection system for wastewater from domestic use within a defined

drainage area should be collected and managed separately from storm

water, and every wastewater source within this area should be connected to

the system. Sewerage system design should be based on gravity wherever

appropriate and must include solutions for existing or potential flooding

problems.

Storm water should be collected and used as a supplementary water source.

Where direct use of storm water is not feasible, effective recharge projects

should be planned and implemented.

More rainwater must be collected directly into cistern and water tanks. The

preliminary goal for year 2010 is to triple the existing collection volume in

Palestine compared to year 2000.

Infiltration rates must be increased in areas where they are low today.

These areas should within year 2010, recharge 3 % more of the

precipitation than today (preliminary goal until more information is

collected that makes it possible to establish goals with better basics).

Flooding problems connected to storm water runoff must be identified in

detail within the year 2001, and all major ones, solved within the year

2010.

Building codes of practice must encourage collection of precipitation and

reuse in an optimum way according to the water quality.

46

For every project that involves construction of new sewerage systems or

rehabilitation of existing system, storm water must be considered in order

to separate systems, include storm water solutions in the plan and

construction in accordance with policy and goals.

Areas with low infiltration rates must be identified and studies planned

which aims to increase the rates.

Within mid 2003 the goals must be quantified for short and long terms and

divided into areas.

The sewerage system, including pumping stations, storage systems,

overflows, etc. should have a minimum negative impact on the

environment.

As long as the performances of the major treatment plants are uncertain,

septic tanks, cess- pits and local other acceptable local treatment can be

kept, as a pre-treatment or not connected. The detailed solutions will be

decided in dialogue between PWA and the plant owners.

2.2.3.2 Industrial Wastewater Policies

For all relevant development projects, industrial connections and treatment

must be addressed. PWA must, through a permit process make sure this

element is taken care of. Ministry of Industry must be involved according

to agreed procedures.

All industries should be regulated through discharge permits from PWA

and comply with other PNA regulations (municipal by-laws, Ministry of

Environmental Affairs, Ministry of Local Governance, etc). The discharge

permits should include assurances that industrial effluents must have an

47

acceptable quality and flow before being discharged into water bodies or

domestic wastewater systems, and should not be discharged with contents

of heavy metals or micro pollutants above given limits.

In approving and issuing a discharge permit, emphasis should be given to

minimising the impacts from industrial effluents through internal measures

such as recycling, clean industrial processes and pre-treatment by using the

best available technology (taking economy into consideration).

2.2.3.3 Wastewater Treatment Policies

PWA must make sure its policy and goals are implemented through the

development. Through discussions with donor countries and beneficiaries

this must be assured. Ministry of Agriculture must be involved in the

process from the beginning in order to achieve successful reuse.

All treatment and/or reuse systems will be regulated through permits from

PWA. The permit should ensure that the system design

Is planned and implemented according to approved regulations,

specifications, standards, and guidelines

Allow treatment of calculated loads and meet stated effluent quality

for the designed period

Solves identified and potential environmental and health problems

Smaller treatment plants must be of types or classes accepted by PWA

regulations and operated accordingly.

The standard treatment demands for bigger plants are described in

documents from Palestinian Standard Institution.

Low cost technology is encouraged wherever it is most feasible.

48

All wastewater treatment processes should be chosen and designed to

consume as little energy as feasible and potential energy in wastewater and

sludge must be utilised whenever appropriate. In addition, independent

alternative energy sources should be installed, if appropriate (e.g., solar

systems, battery, heating exchange pumps, etc.). Farmers should be

involved in energy recovery projects thereby benefiting from wastewater

sludge utilisation.

PWA emphasises that sludge and treated wastewater are valuable resources

that must be utilised in an optimal way. In this regard agriculture is given

priority for reuse and 65% of treated wastewater should be utilised in this

sector.

Organising reuse of treated wastewater involves many stakeholders, and

should be co-ordinated on a national level and carried out on the

appropriate local level. The Wastewater Reuse Technical coordination

committee (between PWA and MoA) will the focal point for regulation of

reuse activities.

Public participation in wastewater reuse should be ensured and carried out

according to international practice for involvement.

For the optimal use of the treated effluent, incentives need to be established

and implemented in order to encourage and promote the use of treated

wastewater in different sectors, including industry.

2.2.3.4 Awareness and Stakeholders participation

PWA must ensure that needed awareness and stakeholder involvement,

through the Department of Consumer Affairs. This must be addressed at an

49

early stage of any process. It is very important for a smooth implementation

and especially for successfully implementation of reuse schemes.

PWA recognises that accessibility for environmentally safe wastewater

services must be assured in order to achieve better social equality. In this

respect wastewater treatment and reuse policies must include stakeholders'

involvement throughout the policy and strategy formulation by awarding

and informing them, in order to create a sense of ownership and

understanding. This approach will result in transparency and build-up

credibility among the parties and facilitate a smooth implementation of the

strategies and action plans.

Vital elements of the policy can only be possible in close cooperation with

stakeholders like farmers and other affected people. Especially awareness

must be established for the utilisation of sludge and treated wastewater as

important resources and to achieve acceptance of the principle of recycling

of resources.

2.2.3.5 Tariff Policy

Through the Tariff Department, PWA must make sure all development

understand the tariff model and are capable of implementing this. This is

needed as early as possible in any project. Partly this will be achieved

through general information and communication and partly through

implementation of bigger projects.

PWA has developed a tariff model, based on parts of the general policy. It

will be very important to, monitor the experiences regarding affordability,

and including of depreciation and O&M costs to adjust the ambition levels.

50

General tariff policies are,

Make sure the projects are affordable and feasible

Overall fees for storm water handling, wastewater collection, and

treatment, storage and reuse should be calculated in order to achieve

full cost recovery of the system(s) taking overall goals into

consideration

The elements of these fees should be distributed using the Polluter

Pays Principle (PPP)

Households cannot be charged more than the defined affordability

and the government should cover the gap between full cost recovery

and affordability

The farmers must contribute for making treated wastewater available

for irrigation

To facilitate enforcement of regulations and to sustain development of the

sector, PWA will use economic incentives for polluting industries to abate

and control pollution.

2.2.3.6 Legal and Administration Policy

The established licensing system for wastewater project must be used as

soon as possible for all relevant projects. PWA must also invite other

relevant authorities to participate in these processes.

PWA is considered according to By Law No. 3 (2002) and the Water Law

of 17.07.2002, as the responsible Palestinian authority for

51

Licensing and approving all water and wastewater projects and

activities including wastewater and storm water collection, treatment,

reuse, and/or disposal

Ensuring and overseeing the efficiency and compliance of these

activities and projects initially and during operation, according to

approved regulations, specifications and standards.

Administering the construction, operation, and maintenance of wastewater

and reuse systems will be done by municipalities or regional utilities with

various levels of co-ordination and involvement of other PNA organs, such

as the Ministry of Environmental Ministry of Industry, Ministry of

Education, Ministry of Agriculture, Ministry of Local Government, and the

Palestinian Water Authority.

52

Chapter 3

Current situation of institutional wastewater management

agencies in palestine

Several institutions including mainly the National Water Council,

Palestinian Water Authority (PWA), local committees and village councils,

local and international NGO’s and institutions, work in the wastewater

sector in the Palestinian areas, the Figure 3.1 is showing the Water Sector

Framework and Figure 3.2 is showing the main stakeholders in water and

waste water sector and the relationship between it.

Figure 3.1: Water Sector Framework

53

Figure 3.2: Main stakeholders in water and sanitation sector

3.1 National Water Council

National water council is highest body responsible of water and waste

water sector; Figure 3.3 is showing national water council framework.

54

Figure 3.3: National Water Council framework

Duties and prerogatives of the National Water Council:

Sanction the general water policy;

Sanction the policy for development and utilization of water

resources and the different usage;

Ratify plans and programs aimed at organizing the usage of water,

the preventing wastage, and directing consumption;

Ratify the tariff policy;

Confirming the allocation of funds for investment in the water

sector;

Approving the periodic reports concerning the activities of the

Authority and its work;

55

3.2 The Palestinian Water Authority

Since 1996, the PWA is responsible for regulation of the Palestinian

wastewater policy, including collection, treatment, sludge handling and

reuse. It is the Palestinian legal body that is responsible of:

Licensing and approving all wastewater projects and activities

including wastewater and storm water collection, treatment, reuse,

and/or disposal

Ensuring and overseeing the efficiency and compliance of these

activities and projects initially and during operation, according to

approved regulations, specifications and standards. However, and

due to the existing complicated political circumstances in the West

Bank and the insufficient wastewater management expertise staff, the

PWA faces great challenges in enforcing its regulations.

Coordinating with relevant wastewater sector development agencies

like the NGO’s and donors is still poor. The main issues concerning

the management of wastewater such as the collection systems,

treatment plants, regulations, standards, and regulations are not

available yet.

The Palestinian Water Authority (PWA) is by its by-laws a governmental

institution with an independent status with its own budget and follows the

President of the Palestinian National Authority and has a commissioner

who is appointed by its President. PWA is responsible for the management

of the most scare and vital sources for sustaining life, for promoting

56

development, and for maintaining the environmental in Palestine. Water is

in focus of the attention in the general public and the medic.

3.3 Other Government Institutions

Several other government agencies bear or will bear responsibilities

directly related to water resources and water and wastewater services.

The Joint Water Committee (JWC) was established under the Oslo accords

as a means to share information about water issues affecting both Israel and

Palestine. As a member of the Joint Water Committee, the PWA is the

primary Palestinian contact with Israeli authorities.

The Ministry of Agriculture (MOA) is responsible for planning and policy

concerning the use of water for agriculture, including reuse of treated

wastewater. As facilities for the treatment and distribution of treated

wastewater are implemented and brought into service, the responsibility for

the conversion of farmers to more efficient irrigation and more value added

cropping will fall heavily on MOA.

The Ministry of Environmental Affairs (MEnA) is concerned with

protecting the Gaza Strip’s natural environment. This includes setting

standards related to the conservation and protection of the environment,

such as:

Minimum water requirement to preserve the environment

Disposal of treated sewage in wadis, streams, rivers, lakes and seas

Disposal of treated sewage in environments, which affects the bio-

diversity

57

Regulation of the industrial wastewater which is not treated by the

utility

Disposal of brine from the desalination plants

The Ministry of Local Government (MOLG) is responsible for the

coordination of all Gaza Strip municipalities and other forms of local

government. As such they have considerable influence in the absorption of

municipal resources into the CWMU and in the continuing provision of

water and sewer services to the population.

The Ministry of Planning (MOP) is responsible for policy development,

coordination, and planning for the overall development of Palestinian areas,

including both the water resources and agriculture sectors. Every three

years, MOP prepares a Palestinian Development Plan (PDP), comprising

sections submitted by Palestinian institutions from various sectors. PWA

prepares the section on water and wastewater.

Ministry of Health (MOH) is responsible for the protection of public health

and safety. This includes setting the standards that are related to the public

health such as:

Drinking water quality.

Disposal of treated wastewater in bathing waters.

Disposal of treated wastewater in environment which affects the

quality of some products such as fish.

Treated wastewater reuse for irrigation which may affect the

agricultural products

Disinfection and drinking water storage.

58

3.4 Local Committees, Municipalities, and Village Councils

The local bodies are managed and develop public services in the cities and

village including the supply of sanitary services. Local committees are

formed wherever a village council does not exist and in refugee camp. The

councils and committees are generally unqualified from technical,

administrative and financial viewpoints, which lead to inefficient

management.

3.5 Local NGO’s and International Organizations

Many non-governmental organizations (NGOs), scientific and technical

groups, professional and other associations working on wastewater

management in Palestine such as Palestinian Hydrology Group (PHG),

Palestinian Agricultural Relief Committee (PARC), Applied Research

Institute Jerusalem (ARIJ), House of Water and Environment (HWE),

Water and Environmental Studies Institute at An-Najah National

University (WESI), Centre for Environmental and Occupational Health

Sciences (CEOHS) and Water and Soil Environmental Research Unit

(WSERU) at Bethlehem University, Institute of Environmental and Water

Studies (IEWS) at Birzeit University, and the United Nations Relief and

Works Agency for the Palestinian Refugees in the Near East (UNRWA).

International organizations of various statuses such as United Nations

Development Program (UNDP), World Bank (WB), and German Agency

for Technical Co-operation (GTZ), US Agency for International

Development (USAID), Save the Children Federation (SCF), America

59

Near East Refugee Aid (ANERA), and (CARE) conducted some

wastewater infrastructure projects.

The aforementioned organizations and institutions operate under severe

constraints: poor capacities, high political instability and uncertainty, and

inadequate sources of funding.

Moreover, co-ordination among the institutions is poor, which result in

vagueness in their roles in the management process of the wastewater

services. Consequently, a new institutional management approach with a

clear legal framework for optimizing wastewater management in Palestine

should be developed.

60

Chapter 4

Situation of sanitation in palestine and future plans

During the occupation period, sanitation sector to be a much neglected

issue, there are collection networks in the main cities and refugee camp

(served 28-32% of population) remaining population uses cesspits.

The situation for wastewater system in Palestine (WW Departments in

PWA, 2012):

During the occupation period, wastewater sector used to be a very

neglected issue

There are collection networks in the main cities and refugee camps

(served 28-32% of population) remaining population uses cesspits

Many of these networks are old and poorly designed established before

1967 through Jordanian Administration and stayed without development

The majority of the population uses individual or communal cesspits for

temporary storage of wastewater.

Ιn refugee camps sewage flows through open drains originally

constructed to convey rainwater.

Most villages have no sewerage system and wastewater is discharged

into absorption pits.

The existing wastewater treatment plants in the West Bank are

inadequate to serve the volume of wastewater produced

The situation of the sewerage system is extremely critical. Both the

West Bank and Gaza are facing a series of wastewater and sanitation

related problems:

61

large scale discharge of untreated wastewater

leaking of collected wastewater from sewer systems and cesspits

water treatment plants that are badly functioning

uncontrolled reuse of untreated wastewater by the irrigation sector

Total production of wastewater is around 70 MCM

Only 42% of 70 MCM (30 MCM) is collected in networks

Around half of the collected (15 MCM) is discharged into wadi and

treated inside the Green Line: Jenin, Tulkarm, Nablus west, Qalqilya,

Ramallah, Hebron and Beit Jala

Only 2 MCM is treated in Al Bireh WWTP

Around 13 MCM WW is discharged into Wadis (Salfit, Bethlehem,

Nablus East)

4.1 Situation of Wastewater in the Urban Area (1996-2012)

There are collection networks in the main cities (ranges from 57% in Salfit

to 98.7% in Qalqilya) remaining population uses cesspits and septics, the

Table 4.4 is show the wastewater status in Main Cities and Table 4.2 shows

existing wastewater treatment plants in urban area.

Table 4.1: Wastewater status in WB-Main Cities (WW Departments in

PWA, 2012)

No. Main

cities

% of ww

services Treatment services

1 Jenin

City 66.5

Treatment plant Under

Rehabilitation, then treated inside

GL

2 Tulkarem

City 73.7

Primarily treatment (lagoons), then

treated inside GL

3 Qalqilya

City 98.7

No WWTP (Treated inside GL)

62

4 Nablus

City 97.2

To start construction (Nablus West

WWTP

5 Salfit

City 57.1

No WWTP (discharged into Wadi

Matwi)

6 Ramallah

City 74.6

Overload WWTP, then treated

inside GL

7 El Bireh

City 85.8

Treated in Al-Bireh TP, not reused

8 Jerusalem

City 95

Under Israeli control

9 Bethelem

(WSSA) 92.7

No WWTP (discharged into Wadi

Al-Nar)

10 Hebron

City 82.1

No WWTP (Treated inside GL)

11 Jericho Zero No WWTP (using Cesspits) –

Under construction

Table 4.2 : Existing WW Treatment Plants -urban area (WW Departments

in PWA, 2012)

No. Project Name Status

1 Existing Jenin TP Under Rehabilitation (Funded by KFW)

2 Existing Al-Bireh TP Function at 2000 (Funded by KFW)

3 Existing Ramallah City Constructed 1973, overload

4 Existing Tulkarem City Primarily treatment (lagoons)

4.2 Situation of Wastewater in the Refugee Camps (1996-2012)

Most of the refugee Camps served with Wastewater Networks

The service exceeds more than 95% of the population.

Only Jericho Camps (Aqbat Jaber and Al-Sultan) has no

Wastewater Networks)

Most WW generated from the refugee camps are connected to the

Adjacent City wastewater Network or discharged into Wadi

(Qalandia, Al Jalazon, Al-Far’a and Al’Aroob)

63

The table below is show the wastewater status in Refugee Camps.

Table 4.3: Wastewater status in WB -Refugee Camps (WW Departments

in PWA, 2012)

No. Main cities % of ww

services Treatment services

1 Jenin Refugee

Camp 97.5 Connected to Jenin

2 Tulkarem Refugee

Camp 99.9 Connected to Tulkarm

3 Nor Shams

Refugee Camp 99.5 Connected to Tulkarm

4 Askar Refugee

Camp 99.8 Connected to Nablus

5 Balata Refugee

Camp 99.9 Connected to Nablus

6 Ein Bei El-Ma

Refugee Camp 99.6 Connected to Nablus

7 Al Jalazon 93.6 Discharged into Wadi

8 Al’Amari Refugee

Camp 98.1 Connected to Al-Bireh

9 Qalandia Refugee

Camp 97.5 Connected to Ramallah

10 Qadoura Refugee

Camp 90.0 Connected to Ramallah

11 Al Sultan Zero (using Cesspits)

12 Aqbat Jaber 0 (using Cesspits)

13 Ayda Refugee

Camp 99.4

Connected to Bethlehem

14 Al’Aza Refugee

Camp 97.5

Connected to

Bethlehem

15 Al Duheisha

Refugee Camp 94.0

Connected to

Bethlehem

64

16 Al’Arroob refugee

Camp 98.6 Discharged into Wadi

17 Al Fawwar

Refugee Camp 98.5 Connected to Hebron

18 Al Far’a 17.0 Discharged into Wadi

4.3 Situation of Wastewater in Rural (1996-2012)

In rural and peri-urban communities that represent more than 60 per cent of

the total population there is no clear approach for sanitation development,

and there is a big controversial on whether using centralized or

decentralized system, where centralized system facing another challenge of

low population densities in these areas, and decentralized system still need

many studies to check its efficiency.

1.43 Million in 446 community without any Wastewater network.

Using Cesspits or septic and discharge into open areas (wadis)

Only 16 communities( 88.2 thousands) with wastewater network

covers more than 70%

Only in 13 communities (60.9 thousands) with wastewater network

covers between 40% and 70%

Only 6 communities (22.8 thousands )with wastewater network

covers less than 40%

Around 400 locations for vacuum tankers for discharging ww

Estimated wastewater collected in cesspits around 40 MCM

The Table 4.4 show the Existing Small Scale Treatment Plant-Sample in

Rural and Table 4.5 is show the No. of Existing On-site (Household

level) Treatment plants.

65

Table 4.4: Existing Small Scale Treatment Plant-Sample

No. Village /

Town Load (m

3/day) Status

1 Nuba

(Hebron) 15

2002 (Not functioning)

2 Kharas

(Hebron)

120

(40 household)

2002 (Not functioning)

3 Beit Dukko

(Jerusalem) 16

2000 (Not functioning)

4 Deir Samit

(Hebron)

15

(40 household)

2000 (Not functioning)

5 Bidya (

Salfit) 11

2007

6 Sir

(Qalqilya) 14

2006

7 Bani Zeid (

Ramallah) 50

2005 (Not functioning)

8 Zeita

(Tulkarm) 14

2008

9 Attil

(Tulkarm) 14

2007

10

Izbet

Shofeh

(Tulkarm)

15

2001 ( Not functioning)

Table 4.5: Existing On-site (Household level) Treatment plants

No. Governorate Total On-Site

1 Hebron 222

2 Bethlehem 97

3 Ramallah and Jerusalem 146

4 Salfit 10

5 Nablus 6

66

6 Jenin and Tubas 151

7 Tulkarm 6

On Going survey (through the EU & Austrian Project) to

evaluate these TPs (at least 70 % are not functioning as planned)

The Occupied Palestinian Territories are facing a rapid population growth

against a context of limited water-resources and poor wastewater

management. Most Palestinian households are internally equipped with

proper sanitation facilities (plumbed toilets, sinks, drains, etc.), but lack

means for proper collection and discharge. Only around 25 percent of

Palestinian households (35 per cent of the total population) are served by

central sewerage systems, and a further 17 per cent of the collected

municipal wastewater (from 6 per cent of the population) is partially

treated. The high percentage of unserved areas and lack of treatment plants

cause an over-reliance on traditional on-site systems for wastewater

disposal, mainly cesspits and septic tanks.

Traditionally, each household has a cesspit for the collection of excreta,

which often percolates into the surrounding soil. This is a disposal system

fraught with disadvantages, since it jeopardizes groundwater and the. In

addition, when the surrounding soil becomes saturated, cesspits require

frequent emptying using expensive private vacuum tanks, where the tanker

operators who empty the cesspits often do not follow rules and regulations

and discharge the emptied seepage within the surroundings of the

communities, especially in agricultural areas and open fields.

67

4.4 Investments and Progress in Sanitation Sector

The PWA is working to development the sanitation sector in Palestine by

construction and rehabilitation the sewer network and sewer pump station,

and by construction the WWTP. Table is showing the currently work in

wastewater projects

Table 4.6: On-going WW Projects (WW Departments in PWA, 2012)

No. Project Name Status

1 Baqa, Bart’a, Hable To start Implementation

(UNDP-Japan)

2 Misslye (collection System+TP) Funded by AFD (Under

Design)

3 Artas Collection System Funded by BTC

4 azmut and Rujib Collection

systems

Funded by MoF ( licensing

procedures)

5 Al-Tireh Collection system and

TP

Funded by moF

(Tendering Process )

6 West Bethlehem Rural

Collection system and TP

Submitted to World Bank

7 Jenin Industrial Estate Tp Funded by KFW

8 Bethlehem Industrial Estate TP Funded by AFD (need

approval JWC)

9 EU food Security (Rural Area) Call for proposal

In the WWTP project we can see the PWA is focusing to construct the

WWTP to service the main cities, Figure 4.1 and Table 4.7 show the

WWTP proposed and existing.

68

Figure 4.1:: Existing and future WWTP Projects (WW Departments in PWA, 2012)

Table 4.7 Proposed and Ongoing WW Treatment Plants (urban area)

(WW Departments in PWA, 2013)

No. Project Name Status

1 Jenin Regional TP Needs Feasibility Study

2 Tubas TP (Tayasir) Funded by AFD ( feasibility study)

3 Nablus East TP Approved and Feasibility study

finished (funded by KFW)

4 Tulkarm regional TP Funded by KFW ( Design phase)

5

Salfit TP Approved from JWC (No Fund (the

fund was reallocated to other

project by KFW

69

6 Ramallah Regional (Ein

Jaruit)

Approved and Feasibility study

finished (funded by KFW)

7 Jericho TP Under construction ( Submitted to

JICA)

8 Wadi Al-Nar (Ubeideiye)

TP

Needs Feasibility Study

9 Hebron TP Approved by JWC ( was funded by

USAID and canceled)

The following is a simple explanation for the most important projects

(WW Departments in PWA, 2012):

A. Regional Sewerage Project Jenin:

Project: Regional Sewerage Jenin

Total Investment: 40 Million USD

Donor: Germany KFW

Start Implementation: not yet

Status: TOR prepared needs approval from JWC

Obstacles: Feasibility study could not be tendered before approval

B. Regional WW Disposal Tulkarm:

Project: Regional Sewerage Tulkarm

Total Investment: 45 Million USD

Donor: Germany-KFW

Start Implementation: 2008

Period of Implementation: 3 years

Status: Feasibility Study ready

C. Sewerage Nablus West:

Project: Sewerage Nablus-west (investment/Infrastructure

restoration Measures)

70

Donor: Germany -KFW

Start Implemntation:1998

Period of Implementation: 37.8 Million USD

Status: Final Design ready

D. Ramallah Sewerage Treatment Project:

Project: Ramallah Sewerage Treatment

Donor: Germany KFW

Start Implementation: Not yet

Status: Feasibility study Ready

Obstacles: TP Location

E. Al-Bireh Wastewater Treatment Plant:

Project: Sewerage Al-Bireh

Total Investment: 12 Million USD

Donor: Germany - KFW

Start Implemntation:1998

Period of Implementation: 2.5 Years

Status: Functional TP

F. Salfeet Sewerage:

Project: Sewerage Salfeet (investment/Infrastructure restoration

Measures)

Total Investment: 11 Million USD

Donor: Germany KFW

Start Implementation: 1995

Status: postponed

71

Obstacles: JWU approval

G. Hebron WWTP:

Total Investment: 45 Million USD

Donor: USAID

Start Implementation: Not Yet

Status: Postponed

Obstacles: Regulation of USAID

H. Jericho WW collection System:

Donor: JICA

Start Implementation: Not Yet

Period of Implementation: 3 years

Status: Feasibility Study is Ready

Obstacles: Location of WWTP, JWC approval

I. Abu-Dis WW collection System:

Project: Abu-Dis, Al-Izarita & Az-Zaim WW

Total Investment: (25) Million USD

Donor: Submitted to AFD

Start Implementation: Not Yet

Status: Obstacles: Not Funded yet

Despite all what have been done, still huge efforts are needed to properly

manage the wastewater in Palestine.

4.5 Deficiencies and Problems

Palestinian Water Authority (PWA) is the main responsible for developing

the sanitation sector; PWA has an approach to provide urban areas by

72

centralized systems, but this face some challenges which are:

Challenges 1: Water Supply Priorities

Providing drinking water systems takes the priority where still more

than 220 thousands in around 220 communities without networks.

Challenges 2: Fund

Limited funding which is a major obstacle for the development and

maintenance of wastewater services. Current wastewater treatment

facilities are heavily overloaded, have inadequate maintenance and are of

low cost recovery.

Raising huge amount of fund to improve WW sector services more

than billion US Dollar are needed.

Donor regulations.

Limitation of fund and donor regulations and requirements.

Unsustainability & stability of External Donation: Donor funds only

to have sustainable & sanitation infrastructures, PWA policy and

strategies should carefully considers the affordability of

beneficiaries to pay for this service.

Challenges 3: Occupation

Some side effects of the Israeli occupation hinder the construction of

wastewater projects by Palestinians. The last 10 years, The Palestinians

allocated 250Millin USD for WWT projects but the Israelis stopped us by

one way or another.

Israeli conditions through JWC and Civil administration that

affect, postpones, stop projects for unreasonable aspects.

73

Connection of illegal Israeli Settlement effluent to Palestinian

Sewerage Systems.

Specifications and standers of effluents and treated WW imposed by

Israelis.

Security aspects.

Israeli Colonies effects on the Environment:

Israel is controlling the Palestinians for 40 years but they did

nothing to protect the environment.

Israel moved most of internationally forbidden industries to the

West Bank and disposes all toxic effluents into Palestinian land

without treatment.

95% of the industry in the Israeli settlements is considered toxic

& dangerous industries.

Total effluent sewage discharged to the Wadis by Israeli

Settlements is around 50 MCM.

Palestinian Agricultural lands around the settlements were

destroyed by untreated effluent.

Challenges 4: Selection of appropriate treatment systems and

technologies

That leads to WW management driving forces and treatment

technologies that achieve specific criteria by utilizing all type of

technologies that help to minimize the running cost, example:

produce gas CH4, incineration of sludge and available solid waste.

74

Challenge 5: Upgrading of the West Bank old urban sewage works

Odor nuisance:

Overloaded pond systems.

Misconception in design.

Land availability:

No space for extension.

Challenge 6: Final effluent disposal:

Reuse in agriculture: where, this was one of the main target of

Master Plan started in 1996.

Treated WW recycling and reuse is considered a very important

option for generating additional water resources to replace fresh

water used for agricultural and industrial purposes.

Artificial Recharge through Disposal final effluent in Wads:

environmental impact; compliance with political agreements.

Final effluent Reuse (selecting the appropriate crops and encourage

farmers to reuse the effluent).

Challenge 7: Enforcement of policy and laws:

PWA policy: Based on ―Polluter Pays Principle‖ and envisages a

full cost recovery based on affordability basis, water-tariff models

should be developed to assure cost recovery.

Palestinian Water Law: Set of regulations and rules entailing

pollution fees for environmental pollution handlings.

Challenge 8: Capacity building:

Building and maintaining a core staff for managing and regulating

75

the wastewater projects: review of documents and formulation of

future plans.

Prepare for all training and capacity building program that required

to support sustainable operation of the WWTP, and to achieve value

from reuse of the treated wastewater.

Challenge 9: On the technical and Institutional levels, still some

obstacles

Lack of technical Experience in Design, operate and maintain

WWTP

Un-defined Wastewater Reuse Strategy

Weakness of the institutions to run WW project due to:

Lack of qualified staff

Lack of financial resources

Lack of practical experience

Lack of Institutional management body and cost recovery

(affordability and sustainability).

Challenge 10: Absence of Public & Educational Awareness Strategy

Institutional level

Operators level

Farmers level

4.6 Driving Forces for WW Management

Public health risks: waterborne diseases

Environmental protection: water resources and soil

National and regional policies: standards and guidelines

76

Adequate sanitation services: life quality standards

Economical benefits: reuse and recreation

Political issues: regional stability

4.7 Opportunities

Master Plan for Water& WW is Available

Location of WWTP’s is Approximately Defined

Availability of the land for construction WWTP

Willingness of the beneficiaries to participate in implementing the

project

Availability of extended irrigable land for WW reuse

Availability of fund to start implementing the project

4.8 Existing and Future Plans:

PWA work on several plans, including (WW Departments in PWA, 2012):

4.8.1 To Stop Flowing Wastewater Toward the Green LINE to be

Treated and Reused in Palestine

Value of treated wastewater as resource

Stop deducting money by the Israeli to treat and upgrade the

treatment plant inside the green line

Centralized WWTP (>15000 m3/day) (Jenin regional, Nablus East,

and Wadi-Alnar)

Semi-Centralized WWTP (5000 – 15000 m3/day), (Tulkarm,

Nablus West, Hebron, Jericho

De-centralized (local WWTP), (Intensive with electro-mechanical

equipments-small space

77

Onsite WWTP ( extensive without electro-mechanical equipments-

large space

4.8.2 Criteria for WWT Selection

Satisfactory treatment efficiency towards: COD/BOD, suspended

solids, N, P, etc.

Robust technology: high stability towards power cut, peak loads,

toxicants, etc.

Flexible with respect to future amendments (extensions,

improvement)

Simple in operation maintenance and control and low running cost

Limited number of treatment steps

Absence of disposal problems (e.g. sludge)

No malodor nuisance

Availability of local experience

Designed for (by) product recovery

Availability of required land

Avoid of side effect problems (e.g. odour)

Availability of required spare parts

4.8.3 Look into the Future Sustainable Planning of WWTP

WW treatment facilities

Realistic planning and management?

Affordable CAPEX and OPEX?

Political issues

Sovereignty?

78

Political power?

Commitment?

Financial Resources

Effective financial management

Socio-cultural aspects

Public awareness and cleaner production tools

Institutional issues

Establishment of wastewater associations?

Private sector involvement in sanitation services

Pollution control & reuse guidelines?

Water quality & public health protection?

4.8.4 Centralized WWTP (>15000 m3/day or 200,000 PE)

The centralization can be implemented if all the following fulfilled

Adequate financial investment (at least 100 million USD)

High potential for wastewater reuse (availability of irrigable lands)

Availability of land to construct the treatment plant, to expand in the

future and to construct larges earth reservoir (at least 500,000 cubic

meter capacity or 21 days) or harvesting water dam (to store the

effluent in winter)

High well prepared institution and technically trained staff to

operate and maintain the plant adequately

Emergency plans to deal with influent in case of technical failure

Stability of financial resources

79

4.8.5 Look into the Future Sustainable Operation Small WWTP

Financial Resources

Effective financial management

Socio-cultural aspects

Public awareness and cleaner production tools

Institutional issues

Establishment of wastewater associations?

Private sector involvement in sanitation services

Pollution control & reuse guidelines?

Water quality & public health protection?

4.8.6 Main Cities and Urban Areas

Treatment Plants to serve all population within the city and adjacent

camps or communities

Network to cover 100% of the population in the city either by

gravity or by booster pumping stations.

Forbid any construction for individual sanitation ( cesspits, septic

tank or on-site treatment)

Secondary or Tertiary Treatment (BOD<20, TSS<30, N<50)

Adequate pre-treatment for industrial wastewater before dumping

into WW networks

Reuse the treated effluent in suitable crops or for artificial recharge

in Winter

To Construct Effluent reservoirs to collect the treated wastewater

for at least 30 days for sustainable reuse

80

4.8.7 Priorities for Selecting Wastewater Projects (Main Cities

&Urban Areas)

Not served cities like Jericho and adjacent camps

To follow up to implement the funded Projects ( Tulkarm, Tubas,

Nablus West and Ramalla-Beitunia)

To allocate fund to construct the approved treatment plants ( Hebron

and Salfit)

To prepare necessary feasibility studies and EIA for (Nablus-East ,

Al’UBeidiye, Abu Dis and Jenin Regional)

4.8.8 Semi Urban (Population 5000-10000) and Rural Areas

(Population 2000-5000)

To construct secondary treatment plant to serve at least the whole

community or different communities with design period 25 years

to construct wastewater networks to serve at least 80% of the

population either by gravity or by pumping stations

To construct individual sanitation (group septic tank, individual

septic tank or on-site treatment) to serve not connected population to

the collection system

Forbid using cesspits and free discharge in wadi or surroundings

Locally reuse the treated effluent in suitable crops according the

Palestinian Standards for WW reuse

4.8.9 Priorities for Selecting Wastewater Projects (Semi Urban and

Rural Areas)

Public health risks: waterborne diseases

81

Environmental protection: water resources and soil

Quantity of generated Wastewater

Availability of the land to construct treatment plant

Cropping areas for irrigation and suitable crops

Willingness of the local authority to operate and maintain the

system

Strong will to develop a sanitation project (financial and non

financial contribution)

Ability to recover water and wastewater bills

Commitment to set up a sanitation fee covering operation and

maintenance costs)

4.8.10 Rural Areas and Small Communities (De-Centralized (Local

WWTP))

Construct low cost WWTP to serve at least the whole community or

adjacent communities when topography allows.

Construct wastewater network/s to serve most of the population by

gravity and avoiding pumping station.

Construct individual sanitation (collective septic tank, individual

septic tank or household treatment (grey water) to scattered houses

that not connected to wastewater network/s

Provide vacuum tankers for evacuating the cesspits and for safe

disposal in nearby treatment plant

Forbid construct new cesspits and replace them with concrete septic

tanks

82

Forbid free discharge in wadi or surroundings

Encouraging Locally reuse the treated effluent in suitable crops

according the Palestinian Standards for WW reuse

4.8.11 Reuse & Recycling

Reuse in agriculture: where, this was one of the main targets of

Master Plan started in 1996

Treated WW recycling and reuse is considered a very important

option for generating additional water resources to replace fresh

water used for agricultural and industrial purposes

4.8.12 PWA with Cooperation and Coordination with all

Stakeholders and Beneficiaries will do Strongly and Effectively

For appropriate and realistic management and planning

For the promotion of the sustainable practices

Enforcement of policy and laws

Training and capacity building program that required to support

sustainable operation of the WWTP

83

Chapter 5

Criteria Idntification

This chapter aims to define criteria that affect the sanitation sector, which

will be done through the following:

A. Identify the criteria used in some countries.

B. Stakeholder Consultation such as institutions; organizations;

ministries; universities and municipalities.

C. Identify the criteria established by the laws and strategy in Palestine;

these criteria are shown in ‎0 and ‎0.

D. Questionnaire for citizens.

E. EQA Terms of Reference (TOR) on sanitation projects.

F. Determine the criteria followed by donors in the projects.

5.1 Criteria Used in Some Countries

5.1.1 Egypt

National Rural Sanitation Strategy was released in September 2008 is

talking about unserved areas has developed a program called (Diversion

Program).

The Diversion Program concept makes pollution abatement the first

priority in this strategy. Therefore all the municipal sewage, seepage flows,

and solid wastes of each Sanitation Service Cluster (SSC) should be

directed to a central Integrated Treatment Facility (ITF), thus eliminating

(―diverting‖) unsanitary habits of discharging liquid and solid wastes to

canals and drains in the service area. SSC treatment and conveyance

facilities are planned on the basis of an SSC’s flow composition.

84

The Diversion Program would be implemented in two stages. The first

stage would involve three types of investments:

a) Construction of a ―first-stage‖ fecal sludge/seepage treatment facility

(plus a solid waste management "SWM" facility) in each SSC

b) Reorganization (and where necessary, purchase or contracting) of SSC

seepage evacuation truck services, ensuring conveyance of all septic wastes

to the treatment facility

c) Construction of pumping stations and force mains to convey wastewater

from existing gravity sewered areas (and selected on-site systems) to the

SSC.

Ministry of Housing, Utilities, and Urban Development (MHUUD) would

undertake, through Holding Company for Water and Wastewater (HCWW)

and its affiliated companies and National Organization for Potable Water

and Sanitary Drainage (NOPWASD), all responsibilities of liquid wastes;

while Ministry of Local Development (MLD) would undertake all

responsibilities of solid wastes, through governorates and rural local units.

The second stage of the Diversion Program involves the completion of full

wastewater treatment trains in SSCs and planning and implementation of

appropriate sewerage interventions in unsewered villages or clusters of

villages. Criteria for village and community prioritization might include:

Subsurface water level

Population size and density

Water consumption levels

Ability and willingness to participate.

85

This prioritization scheme recognizes that high water table poses a serious

public health and building risk in many villages. But the treatment facilities

have the absolute priority and must be set in place first, and when funds

become available, some sewerage projects can be introduced in parallel

with ITF construction.

5.1.2 Iraq

Through my work in (Samawa Al-Soub Al-Saghir Sewerage and

Stormwater Systems Design in Iraq) there are lists of possible

environmental impacts will be analyzed selected from General directorate

of Sewage in Ministry of Municipalities &Public Works (MMPW):

The topography of the study area and flat plains.

The selected site for the planned STP and its relation with the flood

plan.

The geological formations of the project area.

The surface runoff and storm water runoff originating from urban

and rural areas.

Land use classifications within the study area and long-term planning

policies envisaged. The present main land uses within the study area

are residential, agricultural and commercial with no large industrial

enterprises.

Rain-fed and irrigated agricultural practices in the area with

prevailing crop patterns (vegetables, fruit trees and field crops).

The current main roads in the study area within the urban and rural

areas.

86

Soil investigations will be made. The natural biotic life of the study

area shows no sensitive habitats with insignificant biodiversity

relevance. A detailed EIA study shall investigate the soil type, flora

and fauna dominating in the study area.

Site Identification: The sites shall be studied carefully based on the

following site selection criteria:

Distance from the Urban Area Limits and the surrounding residential

areas.

Distance between effluent discharge point and reuse option.

Prevailing wind directions.

Topography of the project area.

Effluent discharge.

Sites accessibility.

5.1.3 Libya

The criteria presented in the following sections are provided as the standard

basis for all projects prepared for the Libya Housing and Infrastructure

Board (HIB). These criteria are mention in Guidance Document, Revision

No. 01 in 21 August 2008, Libya Housing and Infrastructure Board (HIB).

These criteria are:

Population and growth projections.

Sewage flow generation.

Sewage loadings.

Reusing wastewater.

Ground water.

87

Solve an immediate environmental problem.

Solve the problem of the dumping of waste water into the sea

(coastal areas).

5.1.4 South Africa

There are a lot of factors shared between Palestine and South Africa, the

most important of the scarcity of water and lack of sanitation systems only

in major cities.

In 1994 approved to (NATIONAL SANITATION POLICY). The most

important reportedly in the National Sanitation Policy in to identifying the

priorities of sanitation sector is:

The proposed system affordable to the user, the service supplier and

the government.

Number of people will be served compared to the cost of the project

The risks to the environment

Acceptable to people (bearing in mind the cost to them)

Water supply, Is it adequate? Can it support the proposed sanitation

system?

Also the National Sanitation Policy stipulates the following:

The design of sanitation improvement projects will ensure that the

environmental consequences are adequately considered during the

planning process. The risk of pollution through different sanitation

approaches will be assessed in order to use the option which will

minimise impacts on the environment in the most cost effective way.

The Integrated Environmental Management (IEM) Guidelines have

88

been prepared on what level of impact assessment to use for different

types of projects.

Where it is envisaged that a significant environmental change may

result, public awareness and participation is essential. Information

must be presented in an even handed manner in order to convey the

potential costs and trade-offs. For example, comparison of the costs

of avoiding pollution with those of treating the pollution after it has

happened should be accompanied by an explanation of the receiving

water quality objectives.

Environmental Impact Assessment (EIA) procedures should be

followed during the design and sitting of waste water treatment

works and waste disposal sites. As the degree of complexity may

vary according to the anticipated risk, appropriate risk assessment

procedures need to be developed.

5.2 Stakeholder Consultation

Several consultative interviews were conducted with stakeholders in the

sanitation sector such as institutions; organizations; ministries; universities

and municipalities to identify the issues and concerns to be taken into

consideration during the criteria-setting. The consulted parties, and

feedback, comments, and concerns are listed below.

5.2.1 Consultation with Palestinian Ministries

Several consultative interviews were conducted with the Palestinian

Ministries and Authorities. These included Ministry of Agriculture (MoA),

Palestinian Water Authority (PWA), Ministry of Tourism and Antiquities

89

(MoTA), Environmental Quality Authority (EQA) ), Ministry of Local

Governments (MoLG), and Ministry of Labor (MoL).

5.2.1.1 Ministry of Agriculture (MoA)

On November 22, 2012, Eng. Thaer Al- Rabi from MoA was interviewed

and he indicated the following:

• The Ministry supports the establishment of a sewage networks and

treatment plants in the west bank and they have no objection about

any projects unless inconsistent with the requirements of the

Ministry.

• MoA supports of the re-use of treated wastewater to irrigate crops

only if the farmers will follow the instructions of the ministry, also

they have some concerns about this matter because of the lack of

staff to control this process.

• The Agricultural Sector Strategy within the Palestinian National

Strategy (PNP) 2011-2013 emphasizes finding alternative sources for

water (treated wastewater). However, there are regulatory

instructions for using treated wastewater for agricultural purposes.

• The Palestinian Standard, PS 742, of Palestinian Standards Institute

(PSI) regulates and permits use of treated wastewater on fodder and

tree crops only.

• The ministry opposes cutting down fully protected trees, while for

the rest of the trees if there is no alternative site for the station they

will have no objection of removing and re-planting them to another

land, but only under the competent authorities supervision.

90

• Application must be submitted to the Ministry of Agriculture for the

use of agricultural lands for other purposes to be reviewed by a

specialized committee at MoA.

• He mentioned that the sewage projects are expected to contribute to

increase the agricultural production.

• He emphasized that the awareness level must be raised among the

citizens through the distribution of booklets and conducting seminars

about precautions and concerns of dealing with treated waste water.

• For crops irrigated with treated wastewater there is no problem in

changing patterns of agriculture in the region but only according to

the nature of the land and within the instruction of the ministry

taking into consideration that the farmer always seeks to increase his

agricultural production with higher benefit.

• There are mandatory instructions from the Ministry of Agriculture

about re-using the treated wastewater for all beneficiaries.

• Regarding using treated sludge as compost in agriculture,

Palestinians have no such experience. Sludge should preferably be

transferred to sanitary landfills. Main problem of sludge is the

accumulated heavy metals and chemicals rather than the organic

matter.

He mentioned that the select criteria should be sensitive to the following:

capability to re-use of treated wastewater, nature of the agricultural lands

and patterns of agriculture in the region, agricultural production.

91

5.2.1.2 Palestinian Water Authority (PWA)

On November 26, 2012, Eng. Adel Yaseen was interviewed from PWA and

he indicated the following:

• He expressed his concerns about the need for permits from the Israeli

side and difficulties to obtain them and also about farmers to accept

the possibility of reusing of treated wastewater. Also how to dispose

the treated wastewater at the time of emergency and in case of

problems in the operation.

• He emphasized the point that the PWA rejects to link settlements

with any treatment plant.

• Treated water will help to reduce the demand of drinking water used

in agriculture, and will provide additional water to increase

agricultural production.

• PWA does not mind the use of treated wastewater in groundwater

recharge in the event of the treated wastewater reached to the level of

quality permitted for use in the recharge of groundwater.

• Mechanism for addressing contingencies and emergencies must be

clarified, especially in regards to potential contamination to

groundwater resources.

• Odors and proximity to residential areas are concerns, especially in

an area that is relatively very warm in summer. Wind direction with

regard to the WWTP location from residential areas must also be

considered.

92

He mentioned that the select criteria should be sensitive to the following:

Water consumption, hydrogeological profile as well as water slopes and

vulnerability.

5.2.1.3 Ministry of Tourism and Antiquities (MoTA)

On November 14, 2012, Mr. Awni Shawamre was interviewed and

indicated the following:

• Must protect archaeological and historical sites

• It is the responsibility of the MoTA to scan the area and conduct a

field survey and facilitate in the assessment activities.

5.2.1.4 Environmental Quality Authority (EQA)

On October 30, 2012, Eng. Amjad Al Kharraz from EQA was interviewed

and he indicated the following;

• EQA supports such projects if they were built on scientific and

environmental basis.

• EQA started to support projects of sewage networks and treatment

plants in general in the West Bank because it is environmental

friendly.

• EQA has no objection of re-using treated water to irrigate crops, but

after following the Palestinian standard of water treatment in

irrigation some crops but not all of them can be irrigated by treated

wastewater, and also forest trees of various types within the

instructions of the Ministry of Agriculture.

• Regarding to solid waste that result from the process water treatment

solids (sludge) he has pointed out that at present there is only one

93

solution to the EQA which is to send the sludge to certified landfill

after treatment because there is no of a Palestinian standard for re-

using it.

• Awareness programs should be conducted for the farmers with

emphasis on limited use of treated water for irrigation certain and the

types of crops that to be irrigated by the treated wastewater

according Ministry of Agriculture.

• MoA opposes changing agricultural patterns in the Palestinian areas

randomly without a sustainable strategy in this regard.

• Alternatives should be studied in detail whether the site or the

technology used in the station and there must be an integrated plan

for the reuse of treated water.

• Several actions must be considered during the excavation and

construction process to preserve the environment during the

establishment of the sewer network in coordination with the targeted

municipalities.

He mentioned that the selected criteria should be sensitive to the

environmental issues.

5.2.1.5 Ministry of Local Governments (MoLG)

Based on previous conversations with Mr. Suleiman Abu Mfarreh, he

emphasizes the following points:

• Wastewater treatment and reuse is becoming a national priority.

• MoLG maintained that the project must be compatible with the

existing and future land uses. In addition, it should take into account

94

the political land classifications: Areas A, B, and C (Area A: Under

full Palestinian civil and military control. Area B: Under Palestinian

civil control and Israeli military control. Area C: Under full Israeli

civil and military control).

5.2.1.6 Ministry of Labor (MoL)

Based on previous conversations with Mr. Iyham Nsoor, he emphasizes the

following points:

• The sanitation projects would result in job creation at different levels

through construction and operation.

• The projects should comply with the Palestinian Labor Law No. 7

adopted in 2000. The Law provides regulations for workers' health

and safety measures, safe and healthy work conditions, life

insurance, accident insurance, working hours, and wage rates.

• Safety measures should be provided.

5.2.2 Consultation with Universities

Consultative interviews were conducted to Water and Environmental

Studies Institute (WESI) at An-Najah National University (ANU). The

Water and Environmental Studies Institute (WESI) at An-Najah National

University (ANU) was established in June 2001, as a result of upgrading

Water and Environmental Studies Center founded in 1994. The main

objective of WESI is to serve the Palestinian community's needs in terms of

studying, monitoring, describing, controlling, and following up all issues

and aspects related to the present and future state of water and environment

in Palestine.

95

Through multiple meetings with Dr. Prof. Marwan Haddad as my thesis

supervisor, and Associate Professor and Director, Water & Environmental

Studies Institute (WESI), he indicated to we should look at the following

criteria: Ground water, Amount of water consumption, Availability of

agricultural land, Collection rate for electricity and water bills, Pricing of

water, Reuse, Geographical location, Agricultural pattern, Citizens to

accept the use of treated water in agriculture, Water availability, The

existence and condition of water networks and coverage ratio, Political

Constrains, Environmental sensitivity, Social problems, Service Provider

(Municipality, Village Council, the Council of shared services, ....) and

preparations for such a project, Religious, tourist, and archaeological areas,

Water Resources, an Industrial activities and olive presses.

5.2.3 Consultation with NGOs

Consultative interviews were conducted with the House of Water and

Environment (HWE). The House of Water and Environment (HWE) is a

Palestinian not-for-profit NGO that was established in the year 2004. HWE

aims to promote practical research into the current and future state of water

resources and the environment in Palestine and across the region.

On January 26, 2013, Eng. Abdelhamid Alshami (Research Associate -

Water and Environmental engineer) was interviewed from HWE and he

indicated the following:

According to HWE experience in wastewater sector, to identify the area we

should look at the following (start from the most important factor):

96

1- In general, the areas that has open wastewater streams must have the

most priority because they have highly significant negative impact

on environment in addition to health and social impacts if these

streams flow through or near the built-up area (like salfeet

wastewater and Wadi Al zomar).

2- Vulnerability or Sensitivity of ground water.

3- Existing of agricultural lands that suffer from water shortage.

4- Existing of notable health problems due to the cesspits (if there are

reports assure that).

5- Population number.

For selecting the location of the WWTP, we should look at the following

criteria (start from the most important factor):

1- Distance to built-up area and future extension, which reflect on

residents health and their satisfaction.

2- Vulnerability or Sensitivity of ground water.

3- Existing of suitable reuse site.

4- Political Constrains, A, B, C.

5- Suitability of land (flat land or suitable slope).

6- Flood Risk.

7- Land ownership.

5.2.4 Consultation with Private sector

Consultative interviews were conducted to private sector (Companies that

have worked in the field of consulting, studies, designs and supervision in

97

the sanitation sector) like Universal Group for Engineering & Consulting

(UG) and Center for Engineering and Planning (CEP).

5.2.4.1 Universal Group for Engineering & Consulting (UG)

Universal Group for Engineering and Consulting (UG) was established in

1993 as a unique Palestinian firm with the intention to face the challenges

for the reconstruction and development of the Palestinian territories after

more than 28 years of occupation and the resulting deterioration of the

infrastructure, through offering its state-of-the art engineering and technical

services. UG is currently developing a 21st century consulting business on

the basis of a decade of engineering excellence.

UG has committed itself to high quality engineering and consulting

services with the contribution of its experienced professionals and highly

qualified and specialized experts. Since 1993, UG has grown into a

recognized leader in the consulting business in the Palestinian territories.

During this period, Universal Group for Engineering and Consulting has

become a leading multi disciplined firm known and respected for its work

and services in the planning, design, supervision, and management in the

various fields of architecture, engineering, and infrastructure.

Universal Group for Engineering and Consulting is registered as a first

grade consulting firm with the Engineers Association in the West Bank and

Gaza Strip. The Universal Group for Engineering and Consulting co-

operates with a number of leading regional and international consulting

firms.

98

On February 28, 2013, Dr. Hafez Shaheen (Associate Professor in An-

Najah National University and Water and Environmental Expert

(Backstopping) in UG) was interviewed and he indicated that the following

factors must be taken into account: demography, wastewater production,

environmental factor, Socio-economic factor, geographical factor

(topography, catchment), investment factor.

5.2.4.2 Center for Engineering and Planning (CEP)

Since its establishment in 1984, CEP has been involved in a large number

of projects both in Palestine’s Inland Region (West Bank) and Coastal

Region (Gaza Strip) and in other countries such as Iraq, United Arab

Emirates (UAE) and Libya, in the areas of town and regional planning,

socio-economic studies, housing, architecture and building engineering,

road and traffic engineering, water supply and distribution, sewage

collection, treatment and reuse, stormwater collection and drainage

systems, irrigation systems, industrial development projects and the

development of teaching and laboratory programs for academic and

technical institutions.

The professional services offered by CEP in these areas include

preliminary investigations and comprehensive research, field studies and

reports, performance evaluation studies, engineering and economic

feasibility studies, master planning, preliminary and detailed engineering

designs for buildings and infrastructure projects, the preparation of tender

documentation and the provision of construction management/quality

assurance services during project construction and operation.

99

In the area of infrastructure development, CEP has been actively involved

in the preparation of assessment and feasibility studies, master plans for

roads, water supply and distribution, sewage collection, treatment and

reuse, storm water drainage and environmental impact assessments. In the

course of these activities CEP’s staff has become very familiar with the

operational modalities of Palestinian municipalities and village councils

and has accumulated a wealth of information and data relating to the

physical, institutional, regulatory and legal aspects of infrastructure

planning and development.

On February 20, 2013, Eng. Shireen Shelleh (Manager, Design and

Studies) and Eng. Bassam Abu-Zahra (Environmental, Water, and

Wastewater Engineer) were interviewed and he indicated that the following

criteria must be taken into account: population forecast, wastewater

generation, vulnerability of ground water, reuse and agricultural lands, and

political constrains (A, B, C).

5.2.5 Consultation with Municipalities

Consultative interviews were conducted to municipalities (Specifically

large municipalities where there are sewer systems and has extensive

experience in the sanitation sector) like Nablus and Ramallah municipality.

5.2.5.1 Nablus Municipality

Nablus Municipality is a public institution with specific by-laws and

systems enacted in order to render the best quality of municipal services to

its local citizens. Nablus (177,000 inhabitants including 4 refugee camps) is

the biggest urban centre of the northern West Bank. Nablus Municipality is

100

currently implementing a western WWTP where serve around 150,000

people in 2020, and municipality is finish of the preparation of a feasibility

study for the establishment of eastern WWTP.

On January 02, 2013, Eng. Emad El Masri (Director of water and sanitation

department in the municipality) was interviewed and he indicated that the

requirements of implementing sanitation projects must be taken into

account the following: Land for the WWTP, Fund for the capital cost,

Agricultural land for reuse, Operation body, Approvals and permits,

Population density, Wastewater production.

5.2.5.2 Ramallah Municipality

Ramallah Municipality is a public institution with specific by-laws and

systems enacted in order to render the best quality of municipal services to

its local citizens. Ramallah (36,000 inhabitants) It currently serves as the de

facto administrative capital of the Palestinian National Authority. The

existing sewerage situation in Ramallah is:

Only around 65% of the urban area is connected to the sewerage

system.

Many cesspits cause flooding with related odour and hygiene

problems in developed but unconnected areas (especially Al Tireh).

Sewerage system should be a separate system, but some illegal

connections of roof gutters increase flows during rainfalls.

Industrial wastewater is not pre-treated and thus affects the

functionality of the WWTP (especially textile industries using

colorants) and sludge & treated wastewater re-use.

101

Overload of the existing WWTP, both in quantities and pollution

loads.

Effluents do not meet the Palestinian discharge standards.

Very limited extension possibilities for the existing WWTP.

WWTP very close to the city (in close vicinity to the industrial area).

Network likely to be undersized: DN 100 house connections at an

estimated rate of 80%, and maximum diameter in the network being

DN 300 (12‖).

Ramallah Municipality is currently seeking to establish a treatment

plant in Ein Jariot area funded by KFW.

On January 29, 2013, Eng. Khaled Ghazal (Director of sanitation

department in the municipality) was interviewed and he indicated that the

requirements of implementing sanitation projects must be taken into

account the following:

Demography (Population, No of Buildings, Average income).

Environmental risk (water borne disease, no of polluted springs, no

of polluted wells, No of Cesspits).

Land availability (Land for TP, Land for Future Expansion, Location

of TP, and Price of the land).

Technical implementation (Topography (Connection by Gravity),

Needs for pumping, coverage of wastewater in the first phase).

Risk of industrial Waste (No. of Olive press, No. of Stone cutting

(Quarries)).

102

Institutional Management (No. of employees, No. of technical staff,

financial stability, collection rate, cost of evacuation, cost of water,

coverage of water networks)

Reuse (Available lands for reuse, Type of crops, location for lands

downstream, availability of fresh water for irrigation, quantity of

produced ww)

5.3 Citizens Questionnaire

A questionnaire was developed for citizens in their capacity as the affected

side of the sanitation. By conducting an interview with citizens, one can

deduce a number of criteria that must be taken into account.

The questionnaire was well-developed to cover all aspects in relation to the

water sector and wastewater sector. The questionnaire and sample size

were audited by Dr. Numan Mizyed (Associate Professor, An-Najah

National University (ANU)).

The questionnaire consisted of a number of topics; these are: water

situation, current status of sanitation and citizens' satisfaction, impact of

wastewater on citizens, economic and social aspects, institutional issues,

and decision-making. See citizen’s questionnaire in Annex A.

5.3.1 Sample Size

Respondents for the questionnaire were selected randomly. The sample size

included different certain categories, e.g. gender, income level, educational

level, etc.

The alpha level used in determining sample size in most educational

research studies was either 0.05 or 0.01 (Ary, Jacobs, & Razavieh, 1996).

103

The alpha level was taken as 0.05 for sample size above 120 and as 0.01

for smaller populations less than 120 (Bartlett, Kotrlik, & Higgins, 2001).

T-value for alpha level of 0.05 was 1.96, so confidence level was 90%.

The sample was chosen to give a 90% confidence level with a confidence

interval of 5%. The required sample size was calculated according to the

Kachigan formula:

Where:

SS: Sample Size.

Z: value (1.69 for 9AYo confidence level) proportion of area under the

normal curve above the indicated values of Z.

P: Percentage of picking a choice expressed as decimal (0.5)

E: Confidence interval, expressed as decimal or maximum effort for a

given confidence level (0.05)

By substituting in the above equation:

The above equation is for an infinite population.

For a finite population, a correction factor was applied according to the

following.

Where:

Pop. is the population. Here, the number of families was used as a

population, since each questionnaire represented one family.

104

The number of families in the selected communities (see ‎CHAPTER 7) is

shown in Table 5.1.

Table 5.1: Number of families in the selected communities

No. Community No. of

families* No. Community

No. of

families*

1 Silat al

Harithiya 1,970 33

Ar Ram &

Dahiyat al

Bareed

4,370

2 Al Yamun 3,546 34 Biddu 1,446

3 Kafr Dan 1,194 35 Hizma 1,261

4 Deir Abu

Da'if 1,151 36 'Anata 2,971

5 Birqin 1,310 37 Al 'Eizariya 4,195

6 Ya'bad 2,881 38 Abu Dis 2,476

7 Qabatiya 4,126 39 As Sawahira

ash Sharqiya 1,382

8 Arraba 2,121 40 Al 'Ubeidiya 2,075

9 Kafr Ra'i 1,610 41 Husan 1,227

10 Meithalun 1,513 42 Nahhalin 1,510

11 Jaba' 1,764 43 Za'tara 1,297

12 El Far'a

Camp 1,258 44 Jannatah 1,094

13 Tammun 2,434 45 Tuqu' 1,701

14 Qaffin 1,854 46 Beit Fajjar 2,201

15 'Attil 1,883 47 Surif 2,821

16 Deir al

Ghusun 1,753 48 Beit Ummar 2,777

17 Bal'a 1,359 49 Kharas 1,220

18 'Asira ash

Shamaliya 1,750 50 Beit Ula 2,116

19 'Awarta 1,161 51 Sa'ir 3,253

20 Huwwara 1,145 52 Halhul 4,863

21 Beita 1,917 53 Ash Shuyukh 1,821

22 Jamma'in 1,260 54 Tarqumiya 2,759

23 Aqraba 1,696 55 Beit Kahil 1,239

24 Qabalan 1,487 56 Idhna 3,814

25 'Azzun 1,561 57 Taffuh 2,253

26 Biddya 1,754 58 Deir Samit 1,356

27 Sinjil 1,160 59 Bani Na'im 3,931

105

28 Shuqba 1,000 60 Beit 'Awwa 1,565

29 Qibya 993 61 Dura 6,126

30 Al Jalazun

Camp 1,624 62 Yatta 8,797

31 Kharbatha

al Misbah 1,006 63

Adh

Dhahiriya 5,521

32 Beit Liqya 1,577 64 As Samu' 3,594

* No. of families = (Projected Population 2013 / Average Size of

Household in 2007) according to the PCBS

The total numbers of family are 143,851

By substituting in the above equation

The samples were taken for each community as a proportion and fit for the

number of families as shown in Table 5.2.

Table 5.2: Number of samples for each community

No. Community No. of

samples No. Community

No. of

samples

1 Silat al

Harithiya 4 33

Ar Ram &

Dahiyat al

Bareed

8

2 Al Yamun 7 34 Biddu 3

3 Kafr Dan 2 35 Hizma 3

4 Deir Abu Da'if 2 36 'Anata 6

5 Birqin 3 37 Al 'Eizariya 8

6 Ya'bad 5 38 Abu Dis 5

7 Qabatiya 8 39 As Sawahira

ash Sharqiya 3

8 Arraba 4 40 Al 'Ubeidiya 4

9 Kafr Ra'i 3 41 Husan 2

10 Meithalun 3 42 Nahhalin 3

11 Jaba' 3 43 Za'tara 3

12 El Far'a Camp 2 44 Jannatah 2

13 Tammun 5 45 Tuqu' 3

14 Qaffin 3 46 Beit Fajjar 4

106

15 'Attil 4 47 Surif 5

16 Deir al Ghusun 3 48 Beit Ummar 5

17 Bal'a 3 49 Kharas 2

18 'Asira ash

Shamaliya 3 50 Beit Ula 4

19 'Awarta 2 51 Sa'ir 6

20 Huwwara 2 52 Halhul 9

21 Beita 4 53 Ash Shuyukh 3

22 Jamma'in 2 54 Tarqumiya 5

23 Aqraba 3 55 Beit Kahil 2

24 Qabalan 3 56 Idhna 7

25 'Azzun 3 57 Taffuh 4

26 Biddya 3 58 Deir Samit 3

27 Sinjil 2 59 Bani Na'im 7

28 Shuqba 2 60 Beit 'Awwa 3

29 Qibya 2 61 Dura 11

30 Al Jalazun

Camp 3 62 Yatta 16

31 Kharbatha al

Misbah 2 63 Adh Dhahiriya 10

32 Beit Liqya 3 64 As Samu' 7

5.3.2 Analysis of the Questionnaire

This section presents the results of the questionnaire and the main findings

of its analysis. The results were analyzed as per the different parts of the

questionnaire as follows:

1. Water Situation

2. Current status of sanitation and citizens' satisfaction

3. Impact of wastewater on citizens

4. Economic and social aspects

5. Citizens' awareness, and awareness campaigns

6. Institutional issues

7. Decision-making

107

5.3.2.1 First Topic: Water Situation

The amount of water consumption in the summer is 80 liters for each

person per day and 73 per day in the winter. The questionnaire showed

about 65% of people think the amount of water available for all uses is not

sufficient while only 45% think it is sufficient. According to the views of

respondents, there is a large deficit in the amount of water needed for

agriculture more than the amount of water needed for Industrial and

Commercial sectors, while there is no significant shortfall in domestic

water.

The questionnaire also showed that there is a small number of people

satisfied with the water services provided to them with a rate not exceeding

15%.

5.3.2.2 Second Topic: Current status of sanitation and citizens'

satisfaction

All respondents explained that they use cesspits for the disposal of

wastewater rather than using sewage systems, and they are not provided

with any services related to sanitation issues. The Figure 5.1 shows the

kind of censorship of wastewater disposal based on the opinion of the

interviewees.

108

Figure 5.1: Censorship of wastewater disposal

5.3.2.3 Third Topic: Impact of wastewater on citizens

The Figure 5.2 shows the answers of respondents to the question "Are you

already affected by the wastewater directly?". Less than 5% of respondents

said that they suffered from wastewater coming from Israeli settlements.

Figure 5.2: The impact of wastewater on citizens directly

Also, 84% of the respondents indicated that the processes of getting rid of

waste water after emptying cesspits or sewage systems are not proper. A

2%

4% 5%

8%

81%

Strongly Agree

Agree

No Opinion

Opposed

Strongly Opposed

8%

17%

6%

21%

48%

Strongly Agree

Agree

No Opinion

Opposed

Strongly Opposed

109

rate of 37% of the respondents said that the vacuum car for wastewater is

get rid near pastures while 68% reported that get rid of wastewater near the

trees and plants.

The following Figure 5.3 illustrates the problems faced by citizens because

of wastewater:

Figure 5.3: Illustrates the problems faced by citizens because of wastewater

5.3.2.4 Fourth Topic: Economic and social aspects

As far as economic and social aspects are concerned, 97% of the

respondents explained that there are no debts they accumulated as a result

of providing them with water and wastewater disposal services. 52%

indicated that they were satisfied with the price of water, compared to 46%

in addition to 2% who did not answer the question.

About 78% believed that sanitation projects would ease the financial

burden resulting from the disposal of wastewater. Moreover, 68% of the

respondents believed that the wastewater and wastewater disposal cause

social problems among citizens.

5

9

63

32

12

54

22

0 10 20 30 40 50 60 70

Contamination of drinking water

Diseases

Unpleasant odors

Harmful insects

Rats and mice

Wastewater flooding and run at in the streets

There are no problems

110

5.3.2.5 Fifth Topic: citizens' awareness, and awareness campaigns

Almost 4% of the respondents said that they attended seminars or lectures

on wastewater while the rate of respondents who attended documentary

films or TV ads on wastewater problems and methods of treatment was

about 73%, and the rate of respondents to whom leaflets or posters about

wastewater and wastewater problems were distributed was about 22%.

5.3.2.6 Sixth Topic: Institutional issues

A survey showed lack of knowledge on the part of citizens of whether or

not there is an overlap in functions and positions in government institutions

as almost 78% did not answer the question while the rate rose to reach 86%

of our questions that were answered regarding whether or not there is an

overlap in the tasks and functions between government institutions and

civil society organizations (NGO's). Figure 5.4 shows the opinion of

citizens in attention to the wastewater sector by government institutions

and civil society organizations (NGO's).

111

Figure 5.4: Attention to the wastewater sector by government institutions and civil

society organizations (NGO's)

5.3.2.7 Seventh Topic: Decision-making

The survey indicated that citizens prefer to use sewage networks to

discharge wastewater and they are willing to contribute to the creation of

sewage systems at a reasonable cost , and as demonstrated by the

questionnaire, 8% of citizens support the use of treated wastewater in

agriculture compared to 37% and 48% who agree but with some

preventive measures.

Figure 5.5 and Figure 5.6 illustrate the opinion of respondents who prefer

to carry out the management of the sanitation sector and provide

wastewater disposal services.

4

15

20

16

45

3

12

16

14

55

0 20 40 60

Strongly Agree

Agree

No Opinion

Opposed

Strongly Opposed

Attention to the wastewatersector by civil societyorganizations (NGO's)

Attention to the wastewatersector by governmentinstitutions

112

Figure 5.5 : Management of the sanitation sector

Figure 5.6 : Provides wastewater disposal services

5.4 EQA Terms of Reference (TOR)

Terms of reference (TOR) prepared by EQA were taken into account in

order to be considered during the work of environmental impact

assessment. This EIA is subject to the review and approval by several local

agencies, such as the EQA, PWA, and MoLG in order to ensure

15%

12%

9%

13% 30%

21%

PWA

MoLG

MoH

EQA

A joint committee of theministries

No Opinion

51%

22%

15%

1%

2% 1% 4%

4%

Village councils andmunicipalities

Joint services councils

Private sector

PWA

MoLG

EQA

Local committee

No Opinion

113

environmental compliance prior to project commencement and during

project implementation.

The EQA has determined that a detailed EIA study is required for all

wastewater collection and treatment systems. The EQA provides guidance

on the content and preparation of the EIA (We take Al-Yamun project for

example) as specified in the Terms of Reference (TOR) presented in Annex B

5.5 Selected Criteria Used in the Sanitation Projects (donors criteria)

The aim of this section is to review the selected criteria used in the

sanitation projects. Criteria used in the projects are normally within the

orientations of the donors and the approval of relevant government

ministries.

The methods for determining the priorities in sanitation sector in the

ministries and relevant institutions are according to the donors’ police.

There is no clear vision of how to identify priorities in sanitation sector in

the government ministries.

The following section shows the criteria used in the various projects funded

by United States Agency for International Development (USAID),

European Union (EU), German Bank for Reconstruction (KFW), Ministry

of Foreign Affairs (MFA) Republic of Finland and Local finance

investment projects.

5.5.1 Wastewater Projects for USAID Funding

The United States Agency for International Development (USAID) West

Bank and Gaza is considering wastewater sector investments in the West

Bank. USAID wishes to understand the feasibility of funding wastewater

114

sector projects by identifying potential projects and evaluating their

associated scopes, sustainability, permitting requirements, beneficiaries,

costs, implementation schedules, and other aspects. Inc. (MWH) was

selected by USAID to Assessment of Potential West Bank Water Projects

for USAID Funding, dated July 15, 2010 (Assessment). USAID has

selected Black & Veatch Company to confirming the findings of the

assessment and obtaining additional data in order to establish a

recommendation for the immediate engagement of design efforts on two of

the ten wastewater systems through the preparation of site selection report,

dated February 15, 2011.

5.5.1.1 Assessment of Potential West Bank Water Projects for USAID

Funding

The methodology developed to proceed with this investigation consisted of

the following steps:

1. Initial identification of potential projects

2. Establishment of project selection criteria

3. Development of a shortlist of projects to evaluate

4. Evaluation of shortlisted projects

5. Recommended criteria for prioritizing projects

5.5.1.1.1 Identification of Potential Projects

The initial identification of potential projects began with an examination of

documents produced by the Palestinian Water Authority (PWA) including

their Recommended Project Lists, which is updated monthly, and the

document entitled The Palestinian Water and Wastewater Sectors: Basic

115

Needs and Development Ongoing and Proposed Projects by Governorates

(October, 2009). Meetings were held with both USAID and PWA to further

discuss these documents.

Additionally, to obtain a better understanding of wastewater projects in the

West Bank, meetings were held with other organizations involved in the

West Bank wastewater sector work including:

Ministry of Local Government – Eng. Walid Halayqa

Al Bireh Municipality – Eng. Lamia Hamayel

Bir Zeit University - Dr. Omar Zimmo

KFW (German Donor Organization) – Dr. Hisham Sharabati and

Eng. Waddah Hamadalla

JICA (Japanese Donor Organization) – Dr. Abed Al-Naser

5.5.1.1.2 Establishment of project selection criteria

Establish project selection criteria based on USAID’s objectives and goals

for this effort. The identified project selection criteria included:

Project costs in the range of $10M to $15M USD

Projects that have a high likelihood of being successfully operated in

the future

Projects that have a high likelihood of being approved and permitted

Projects that solve an immediate environmental problem

Projects where the treated effluent can be used as reuse water

Projects that can be coupled with USAID water projects

Projects that are aligned with PWA’s wastewater sector goals

Projects that are not being funded by other donor agencies

116

Projects that are spread around different areas of the West Bank

The ceiling on project costs eliminated large wastewater projects, such as

Wadi Nar and Hebron City, and instead focused the search on medium-

sized projects serving communities with 2010 populations of

approximately 10,000 to 20,000 people.

5.5.1.1.3 Evaluation of Shortlisted Projects

The shortlisted projects were evaluated with the goal of providing USAID

the information needed to prioritize projects if funding becomes available.

The first step in the evaluation process was to set up meetings with the

authorities that would be involved in the potential projects. Meetings were

setup with each municipality or joint village council and were typically

attended by the mayor of the town and his key engineering and utilities

staff, as well as MWH and PWA representatives. At some meetings,

representatives from nearby towns also attended the meeting. The

authorities were provided with a list of questions prior to the meeting so

that they could be properly prepared. The information requested at each

meeting included:

1. Topographic and road maps of the area

2. Population of the town, number of households, and number of

buildings

3. Description of the municipality including number of employees,

engineers, and technicians

4. Water resources in the town, supplied quantities, and water usage

rates

117

5. Internal water network situation and its coverage area

6. Cost of water supplied to citizens

7. Percentage of water bills paid and the billing mechanism

8. Number of cesspits in town

9. Cost of emptying cesspits by vacuum tankers

10. Wastewater disposal sites

11. Social and environmental problems resulting from lack of

wastewater collection and treatment

12. Industrial activities in town especially stone cutting workshops and

olive presses

13. Disposal mechanism of stone cutting workshops and olive pressers

remnants

14. Previous studies or designs for wastewater systems

15. Status of any existing collection pipes or treatment facilities

16. Percentage of the town that could be served by a gravity collection

system

17. Availability of land to construct a wastewater treatment plant

18. Types of crops grown locally and locations where reuse water could

be utilized

19. Political areas that the system would be located in (Area A, B, or C

or a combination)

20. Potential initial service areas and future phasing opportunities

As a result of the meetings, it became very evident that all of the

municipalities and joint village councils are extremely aware of the

118

social and environmental problems caused by uncollected and

untreated wastewater and are desperate for funding for wastewater

projects. Key social and environmental issues that came up at all the

meetings included:

1. Health risks to citizens, especially children, from raw sewage

running in the streets and wadis

2. Contamination of springs and groundwater, formerly used for

water supplies, as a result of overflowing cesspits and illegal

dumping of raw sewage from tanker trucks

3. Contamination of water network piping due to overflowing

cesspits

4. Structural damage to roads and building foundations as a result

of overflowing cesspits

5. Conflicts between neighbors caused by overflowing cesspits

6. Waste of a valuable resource that could be used for irrigation or

other purposes

5.5.1.1.4 Recommended Criteria for Prioritizing Projects

The criteria listed below, are proposed for prioritizing the projects. These

criteria are based on a scoring system of 1 to 3 points. It is also

recommended that a weighting system be employed to differentiate criteria

deemed to be critical to the implementation and long-term success of the

project including those related to unit costs, existing water consumption,

sustainability, and permitting.

119

1. Demographics:

a. Initial and Ultimate Service Area Populations

1 point: <20,000

2 points: 20,000 - 30,000

3 points: >30,000

1 point: <40,000

2 points: 40,000 - 60,000

3 points: >60,000

b. Existing Water Consumption

1 point: < 50L/day/cap

2 points: 50 - 75L/day/cap

3 points: > 75 L/day/cap

c. Industries

1 point: > 10 stonecutters + olive presses

2 points: Between 5 and 10 stonecutters + olive presses

3 points: < 5 stonecutters + olive presses

2. Institutional Management (Sustainability):

a. Current Collection Rate

1 point: <50%

2 points: 50% - 75%

3 points: >75%

b. Financial Structure

120

1 point: Not tied to other utilities

2 points: Tied to other utilities - post pay system

3 points: Tied to other utilities - pre pay system

c. Management Structure

1 point: Need to form management structure

2 points: JVC

3 points: Municipality only

d. O&M Structure

1 point: Need to form O&M structure

2 points: Structure but no water staff

3 points: Structure with staff

3. Environmental Issues:

1 point: Minor

2 points: Major

3 points: Severe

4. Approvals and Permitting:

1 point: Trunk lines and/or WWTP in Area C

2 points: Project in Area A and B except road crossings in Area C

3 points: Entire project in Areas A and B

5. Technical Implementation:

a. Collection System

1 point: <50% by gravity flow

2 points: 50% to 75% by gravity flow

3 points: >75% by gravity flow

121

b. WWTP Site

1 points: Poor site

2 points: Average site

3 points: Great site (large, clear, power, no neighbors, good reuse)

c. Reuse

1 point: Minimal reuse potential near WWTP

2 points: Medium potential

3 points: Great potential

6. Project Cost per Capita:

1 point: Project Cost per capita > $600

2 points: $500 to $600

3 points: < $500

5.5.1.2 Site selection report

USAID is to design ten sewage collection and treatment systems in

medium sized communities (average current population 20,000) throughout

the West Bank. Ten municipal entities in the West Bank were previously

identified in a study entitled Assessment of Potential West Bank Water

Projects for USAID Funding. Prior to engaging in detailed design efforts,

B&V is tasked with confirming the findings of the Assessment and

obtaining additional data in order to establish a recommendation for the

immediate engagement of design efforts on two of the ten wastewater

systems.

B&V and local sub-consultants worked with Palestinian Water Authority

(PWA) staff, Ministry of Agriculture staff, the Israeli Civil Administration,

122

and the mayors and engineers of the ten municipalities to analyze the

circumstances of each proposed system. Comparisons of factors affecting

project implementation were made, some of which relied on information

presented by the municipalities themselves, others drawn from observations

and investigations made directly by B&V professionals and sub-

consultants. Where possible, the information reported by each of the ten

municipalities was cross checked with data from other sources such as

Palestinian Authority 2007 Population Census Data and PWA well

production data.

The purpose of this report is to prioritize two wastewater systems for

immediate design. A criteria based ranking system was used to score all ten

systems with recommendations for immediate design implementation going

to the top two. The evaluation and scoring is only intended for the purpose

of identifying two systems for immediate design implementation. The

evaluation and scoring is not intended as a prioritization list for all ten

projects. Nor are the criteria or ranking applicable to identifying the next

stage of construction prioritization after the first one is designed and

constructed.

Four criteria were developed for the evaluation. Where appropriate, the

criteria were further divided into sub‐criteria. A numerical scoring system

was developed to determine the overall ranking and identification of the top

two projects for immediate implementation. Each of the four criteria were

weighted and combined into a final qualitative scoring. The four criteria, in

no particular order, are:

123

1. Ease of Civil Administration Approval

2. Operational simplicity

3. Environmental and Health Impacts

4. Municipal readiness

Each criterion was given a weight of 25 percent.

5.5.1.2.1 Criteria 1: Civil Administration Permitting

The duration of the Civil Administration’s permit approval process will

drive the schedule of project implementation for those systems that impact

Area C. This can have an overriding impact on the selection of the

wastewater system that is slated for immediate implementation. At a

minimum, each project consists of the following geographical elements

which will be located in two or more of the security/administrative areas

(A, B, or C):

The geographical location of each of these permanent features will affect

the relative ease of implementation by the impact they have on Area C. In

coordination meetings with B&V, the Civil Administration has indicated

that projects that impact Area A and B only can get implemented much

faster than those that impact Area C. The Civil Administration also

distinguishes between types of construction in Area C. According to the

124

Civil Administration, approval for construction of buried pipelines in Area

C is significantly shorter (approximately six months) and a less

complicated than permanent, above‐ground structures (approximately three

years). Some Area C approvals may take a shorter time than anticipated.

Other Area C approvals may take significantly longer. In any case, the

exact duration is unknowable in advance and projects that impact Area C

are relatively risky for immediate project implementation.

However, it should be recognized that site specific issues affecting Israeli

interests are expected to have an impact on the duration of the permit

approval process. For example, the proposed wastewater systems may be

impacted by the proximity of Area C settlements. Environmental

improvements resulting from the implementation of proposed projects may

also factor into the duration of permit approvals. One example of this is the

proposed Ein Sinya wastewater treatment plant. The Civil Administration

has reportedly encouraged the development of this project by offering

financial incentives to the Palestinians to build a wastewater plant. The

existence of such a plant would improve the environmental conditions of

nearby Israeli settlements.

For the purposes of this analysis, the following numerical scoring system

was applied:

125

Table 5.3: Numerical Scoring Description for Criteria 1 ‐ Ease of Civil

Administration Approval

Score Description

10

trunks, or wastewater plants;

the catchment area;

8

trunks, or wastewater plants;

6

wastewater plants;

sewer (buried pipeline) crosses Area C;

4

wastewater plants;

pipeline) crosses Area C;

2 Permanent above grade structures (wastewater plant or

storage reservoirs) in Area C

Inadequate Area A & B land for application of reuse water;

No Israeli settlements in the catchment area

0

5.5.1.2.2 Criteria 2: Operational Simplicity

In general, service areas with full gravity collection systems are expected to

have lower operational and maintenance obligations than those requiring

lift stations. The more lift stations required for a given service area, the

greater the operational cost and complexity.

Another operational consideration is the wastewater generation per capita.

The design parameters established in the Assessment were based on the

notion that water supply and wastewater generated per capita would

126

significantly increase in the future. There is no guarantee that will be the

case in the future. Moreover, the per capita generation has significant

impacts on the wastewater treatment process selection. In general, the

lower the wastewater per capita the more concentrated the waste and the

more difficult it is to achieve reductions in effluent Nitrogen, which is

currently set at 50 mg/l in the Palestinian Standards. This is also related to

the operational costs of lime addition, which would be required to boost the

alkalinity of the wastewater in order for the required

nitrification/denitrification process to function at all.

Greater operational complexity accompanies the treatment of higher

concentrated wastes (low wastewater generation per capita). This

operational complexity results in a lower score for immediate

implementation where there is obviously a greater humanitarian need.

However, this would also suggest that efforts for the municipalities with

the lowest water consumption per capita (highest concentration wastes)

should be prioritized on increasing their water supply and distribution prior

to implementing sewage collection and treatment. In any case, for the

purposes of this evaluation, the municipalities with the lowest wastewater

generation per capita received lower scores on these subcriteria. For the

purposes of this evaluation, both subcriteria were assumed to have equal

weight. Each subcriteria carried a 12.5% impact on the final weighted

score.

127

Table 5.4: Numerical Scoring Description for Subcriteria 2A –

Operational Simplicity – Gravity Collection

Score Description

5 100% of the municipality’s service area potentially served by

a gravity collection system;

4 80% of the municipality’s service area potentially served by a

gravity collection system;

3 60% of the municipality’s service area potentially served by a

gravity collection system;

2 40% of the municipality’s service area potentially served by a

gravity collection system;

1 20% of the municipality’s service area potentially served by a

gravity collection system;

0 0% of the municipality’s service area potentially served by a

gravity collection system;

Table 5.5: Numerical Scoring Description for Subcriteria 2B –

Operational Simplicity – Wastewater Generation

Score Description

5 Estimated wastewater generation of 100 liters/per capita per day;

4 Estimated wastewater generation of 80 liters/per capita per day;

3 Estimated wastewater generation of 60 liters/per capita per day;

2 Estimated wastewater generation of 40 liters/per capita per day;

1 Estimated wastewater generation of 20 liters/per capita per day;

0 Estimated wastewater generation of 0 liters/per capita per day;

5.5.1.2.3 Criteria 3: Environmental and Health Impacts

None of the ten municipalities have usable collection systems, with the

exception of Dura. Dura has a partial collection system that was built ten

years ago. However, Dura’s partial collection system is not connected to an

outfall and has no house connections. The use of cesspits (and in some

cases, septic tanks) is widespread with some households using more than

one cesspit. Overflow and seepage problems are common to all ten

municipalities, with little distinguishable relative differences. Infiltration

and groundwater contamination from the cesspits, which are unlined, is

128

also a problem common to all ten municipalities. The installation of

collection systems and centralized treatment will have a direct benefit to

the environment from the discontinuation of unrestricted dumping of raw

sewage and the cessation of cesspit leakage.

The comparative magnitude of the resulting environmental and health

improvements can be estimated by the relative hydrologic vulnerability of

the wastewater system locations. Projects in municipalities located in

aquifer recharge areas with high infiltration rates would produce a higher

benefit than those that are located in less vulnerable areas. To make this

determination, B&V used hydrological vulnerability maps published by the

United Nations Environment Programme (UNEP) in cooperation with the

Palestinian Environmental Quality Authority from a study entitled Desk

Study on the Environment in the Occupied Palestinian Territories (2003).

The scoring system is showing in Table 5.6 below.

Table 5.6: Numerical Scoring Description for Criteria 3 – Environmental

and Health Impacts

Score Description

10 Greatest relative benefit realized by construction of collection

and centralized treatment ‐ Municipal area located in a

region of high hydrological vulnerability to groundwater

pollution as defined by UNEP.

5 Moderate relative benefit realized by construction of

collection and centralized treatment ‐ Municipal area located

in a region of medium hydrological vulnerability to

groundwater pollution as defined by UNEP.

0 Low relative benefit realized by construction of collection

and centralized treatment

‐ Municipal area located in a region of low hydrological

vulnerability to groundwater pollution as defined by UNEP.

129

Industrial waste contribution was considered as a possible sub‐criteria.

However, the amount of liquid waste generated by existing industrial

operations (stone cutting, olive press, textiles, etc) for all municipalities

appears to be low. It is assumed that direct connection of these wastes to

the collection system will not be allowed without pre‐treatment in

accordance with soon‐to‐be ratified By Laws regarding sewer discharge.

For this reason, the relative amounts of industrial wastes and their impact

on the environment and health was not considered a differentiator in the

prioritization effort.

5.5.1.2.4 Criteria 4: Municipal Readiness

All municipal mayors, council members, and staff expressed a strong desire

to have a wastewater collection, treatment, and reuse system. The residents

of these municipalities all experience similar hardships that accompany the

lack of such infrastructure. The expense of cesspit pumping, structural

issues with building foundations, contamination of cistern and groundwater

supplies from existing cesspits, and social conflicts resulting from the

spillage of wastes from cesspits, were common to all of the municipalities

visited. The problems associated with the existing situation are clear.

However, measuring the preparedness of a municipality to implement and

operate a wastewater system is less clear. Developing a scoring system and

ranking the ten municipal entities from one or two introductory meetings is

a subjective exercise. Municipal readiness is difficult to accurately

determine without having direct observation over the course of several

weeks or months.

130

Nevertheless, it is clear that as things stand today, none of the

municipalities is institutionally prepared to directly manage a new

wastewater treatment plant and reuse scheme. There is a noticeable lack of

experience and understanding of the issues associated with collection, and

treatment operations in particular.

To create a scoring system for these criteria, several indicators were

considered, including:

• The percentage of water fees collected from residents;

• The willingness of municipal leaders to combine utility bills (water

and sewer, and even electricity),

• The revenue currently generated between buying bulk water and

sales to metered users,

• The implementation of pre‐paid utility bill programs,

• Measures taken to reduce non‐payment and address water

distribution losses,

• The existence and willingness of agricultural associations to take part

in water reuse contracts,

• The ability of municipal leaders to cooperate with one another in a

regional scheme (this applies mostly to the two regional projects: Ein

Sinya and Northeast Jenin),

• The experience and capacity of the municipality to operate and

maintain its existing water infrastructure.

• The existing numbers and skill sets of the municipal operators and

engineers.

131

The scoring system is shown in Table 5.7.below.

Table 5.7: Numerical Scoring Description for Criteria 3 – Municipal

Readiness

Score Description

10 Municipality has established an independently funded

water/wastewater authority;

100% fee collection on existing water service;

Losses in the existing water distribution system are

measureable and less than 10% of the water is unaccounted for;

Municipal personnel are capable and experienced in

wastewater operations and maintenance

There is an existing, mandated agricultural association that

has produced a written commitment to purchase the treated

effluent

5 Municipality has more than 80% of consumer water fee

collection;

Municipality has already implemented a combined bill for

water/sewer on a prepaid use basis;

An agricultural association exists with or without a mandate

0 Municipality will attempt to manage the wastewater system

through the efforts of a fractioned joint service council without

a clear leader;

Municipality has less than 70% of consumer water fee

collection;

No existence of any significant agricultural associations

5.5.2 Wastewater Projects for European Union (EU) Funding

To review the EU selected criteria used in the sanitation projects we

studied last study submitted to the EU for sanitation projects, a project is

(Feasibility study and ESIA for wastewater management in Tubas, Tayasir,

'Aqqaba and Al 'Aqaba), dated January 10, 2012.

The project is divided to five components and evaluated each component

separately by various criteria. These components and criteria are:

A. Wastewater collection and conveyance networks:

132

• Investment cost

• Operation and Maintenance cost

B. Wastewater reuse

• Land suitability for irrigation and Potential areas

• Cropping patterns

• Water storage

• Investment cost

• Operation and Maintenance cost

• Irrigated area

• Irrigated water request

C. Ability to Groundwater recharge

D. WWTP sites:

• Distance to closest house

• Distance to limit of future urban area

• Nuisance to surrounding residential areas

• Potential aquifer impacts

• Location in area A, B or C

• Platform elevation

• Excavation required

• Access road

• Flooding risk

• Electrical energy supply

• Land ownership

• Reuse potential

133

E. Process selection:

• Pollution reduction

• Disinfection of treated water

• Upgradability of the process

• Footprint of the structures

• Qualification of operating staff

• Investment and operating costs

• Sludge quality

• Land requirement

5.5.3 Wastewater Projects for German Bank for Reconstruction

(KFW) Funding

To review the KFW selected criteria used in the sanitation projects we

studied last study submitted to the KFW for sanitation projects, a project is

(Consultancy Services for the Elaboration of a Feasibility Study for the

Project ―Wastewater Treatment Plant Ramallah‖), dated March 2010.

The project ―Wastewater Treatment Plant Ramallah – Feasibility Study‖

was launched by the German Government as part of the efforts undergoing

to improve the living conditions of Palestinian people. This project is

funded in the frame of the bilateral German-Palestinian Co-operation.

The Consortium of Gauff Ingenieure with ERM and Universal Group was

awarded the project; signature of the related contract was made on 19

January 2009.

134

5.5.3.1 Multi-Criteria Screening of Options

Due to the sensitivity of the project area, option comparison cannot take

into account economical items only. In addition, socio-economical and

environmental impacts have to be roughly assessed.

5.5.3.2 Environmental Issues

Environmental criteria have been introduced to compare the different

locations for the WWTP. Into account has been taken:

• Land size required for 2030;

• Availability of land for further extensions beyond 2030;

• The distance to the closest residential area;

• The connected PE until 2030;

• The requirements of having main pumping stations

• The groundwater vulnerability at the proposed sites;

• Groundwater vulnerability of the main collector routings.

5.5.3.2.1 Socio-Economic Impact

• Full Cost Recovery

• O&M Cost Recovery

5.5.3.2.2 Institutional Criteria

• Inter-Communal Co-operation

• Joint Service Council;

• Improvements in Billing

135

5.5.4 Wastewater Projects for Ministry of Foreign Affairs (MFA)

Republic of Finland Funding

The last study submitted to the MFA for sanitation projects, a project is

(Sanitation Study for Northwest Jerusalem Villages), dated March 2011.

5.5.4.1 Selection Criteria and Screening

Initial selection criteria have been applied to the proposed options. The

sorts of criteria that have been used for the initial screening process

include:

Type of Area including Oslo classification as A, B, or C

Israeli Closure Wall

Adjacent settlements

Israeli permits

Size of site (sufficient area available for extension?)

Access to site

Present land use

Distance to developed areas, wind direction and effects of odor

Approvals of Owners, PWA, JSCs and residents

-use

Facilities for storage of treated wastewater

Available agricultural area for irrigation

Options for re-use of treated wastewater

of the WWTP and Treatment method

136

Flexibility of options for future modifications

Required performance to meet the required effluent standards

Strength of sewage

Effluent quality requirements

Ambient conditions in the project area

Sewage flows and infiltration/flows

5.5.5 Wastewater Projects for Local Finance Investment Projects

Bayti real estate investment company is construction the Rawabi city,

Rawabi is new city in west bank and Rawabi is the biggest local finance

investment projects in west bank.

The criteria cover a range of technical factors that consider site and land

use issues, and community impacts including health and safety,

environmental impacts, and economic impacts. Numerical ranking was

applied to the selection criteria. These criteria were ranked by using a

scoring range of 1 to 10, with 1 equal to the least favorable rating and 10

equal to the most favorable. These criteria are briefly described below:

5.5.5.1 Suitability of Land

This criterion relates to the suitability of the site in terms of sufficient flat

area available for treatment and reuse facilities (including area for future

expansion); ease of construction in terms of site access, topography and

slope; and the cost of the land.

5.5.5.2 Political Constraints

This criterion relates to the relative ease of obtaining project approval and

permits by the Joint Water Committee. If the project site is located in

137

administrative division Area A or B as defined by the Oslo Accords,

project approval is typically much easier to accomplish than if the site is in

Area C.

5.5.5.3 Potential Aquifer Impacts

Groundwater aquifers would be impacted negatively, resulting in a threat to

public health and safety, if raw sewage were to be disposed of as a result of

a failure at the wastewater treatment (e.g., either from a spill of raw

sewage/seepage or from a treatment malfunction resulting in partially

treated effluent discharge). This criterion was evaluated based on a

vulnerability analysis. These vulnerability analyses were ranked by using a

scoring range of 1 to 10 are briefly described below:

0 the negative impact on the groundwater system is EXTREME

2.5 the negative impact on the groundwater system is HIGH

5 the negative impact on the groundwater system is MODERATE

7.5 the negative impact on the groundwater system is LOW

10 the negative impact on the groundwater system is VERY LOW

Vulnerability analysis ranked depending on:

Groundwater Divide

Springs

Wells

Wadis

Recharge Zones

Pollution by advection: Advection is the process of the movement of

pollutants with the influence of groundwater velocity in the saturated

138

zone. This is an important mechanism in the assessment of the

impact of pollution on aquifers. The mechanism is also influenced

with the direction of groundwater movement.

Karst Groundwater System

Vertical movement and travel time of pollutants

5.5.5.4 Proximity of Reuse Sites

This criterion relates to the availability of reuse sites within the proximity

to effluent discharge at minimum pumping cost, and to the suitability of the

soil for crop production.

5.5.5.5 Proximity to Existing and/or Planned Utilities

This criterion relates to the relative ease of bringing in utilities, such as

electricity and water, necessary for construction and operation of a

treatment plant.

5.5.5.6 Flood Plain Elevation

This criterion relates to potential flooding of the site during storm events.

Wastewater treatment plants are usually located in low areas that could be

subject to flooding. At sites within the flood plain, flood prevention

measures such as realignment of the wadi channel or conveyance of flood

water in a closed conduit would be necessary, significantly increasing

costs. The differentiation among sites for this criterion was based on the

relative difference in the width of the wadi where the proposed site is

located: the narrower the site width, the higher the flooding potential.

139

5.5.5.7 Proximity to Landfill

Residuals generated at wastewater treatment plants such as screenings, grit

and sludge are anticipated to be disposed of in a sanitary landfill. The

proximity of the wastewater treatment plant to a landfill site will affect the

hauling costs.

5.5.5.8 Nuisance to Surrounding Urban Areas

This criterion relates to the suitability of the site in terms of being remote

from existing and future urban areas. It is preferable to locate wastewater

treatment plants in non-urban areas, away from residences. Potential

impacts include visibility of treatment plant facilities, obstruction of natural

views, noise, odor, increased vehicular traffic, and public health and safety

concerns.

5.5.5.9 Population Served

This criterion relates to the number of residences and communities that can

be served. The site that can serve the relatively largest number of

population with reasonable length of trunk lines is preferred, as these

results in the greatest benefits versus costs.

5.6 Criteria Identification

The criteria were identified so that they are easy to measure and easy to

evaluate and based on the above, the following criteria were selected:

Demography.

Water consumption / Wastewater production.

Reusing wastewater.

Environmental factor.

140

Operation body.

Risk for Industrial Waste.

Socio-economic factor.

Geographical factor (topography, catchment).

Political Issues.

141

Chapter 6

Mcda Tools Development

6.1 Normalize the Weights of Criteria

Weights of the criteria were identified through the intergovernmental

agencies that form the Environmental Assessment Committee (see Annex A):

EQA (acting as chair of the Committee)

Ministry of National Economy (MNE)

Ministry of Local Government (MoLG)

Ministry of Transport (MoT)

Ministry of Agriculture (MoA)

Ministry of Health (MoH)

Ministry of Tourism and Antiquities (MTA)

Ministry of Planning and Administrative Development (MoPAD)

Palestinian Water Authority (PWA)

Palestinian Energy Authority (PEA)

Ministry of Public Works and Housing (MPWH)

Ministry of Labour (MoL)

Palestinian Civil Defence's (PCD)

Petroleum Authority

The EA Committee reviews the EA study and makes recommendations for

approval or denial of the project.

The weight of a criterion also comes based on the importance of 10 where

0 is not important, 5 is average importance, and 10 is very important. Each

criterion weight is given a score, and then all the scores are added up. The

142

score of each attribute is divided by the total score.

and equation below.

143

Table 6.1: Calculate normalize weights to each criteria

No. Criteria

Environmental Assessment Committee

Weights

(Wm)

Normalize

weight (from

100%) (Wm

×100/∑W)

EQ

A

MN

E

Mo

LG

Mo

T

Mo

A

Mo

H

MT

A

Mo

PA

D

PW

A

PE

A

MP

WH

Mo

L

PC

D

Petroleum

Authority

1 Demography 5 8 8 8 9 10 8 9 9 7 10 9 8 7 8.2 12.5

2

Water

consumption /

Wastewater

production

7 6 8 6 9 7 6 9 9 4 5 6 7 6 6.8 10.37

3 Reusing

wastewater 5 4 5 3 8 2 5 5 8 6 4 5 6 4 5 7.62

4 Environmental

factor 10 9 8 10 10 10 9 10 10 8 10 10 10 9 9.5 14.48

5 Operation body 10 8 8 8 9 8 8 10 9 8 9 9 8 8 8.6 13.11

6 Risk for Industrial

Waste 7 6 6 5 7 7 5 10 7 7 5 6 4 8 6.4 9.76

7 Socio-economic

factor 10 8 10 8 9 10 8 8 9 7 9 8 8 8 8.6 13.11

8 Geographical

factor 7 4 6 6 7 5 5 6 8 5 4 5 4 5 5.5 8.38

9 Political Issues 6 7 8 7 8 7 7 7 9 7 6 7 6 6 7 10.67

Total 65.60 100

144

6.2 Carries a Value Rating for Each Criteria

Each alternative carries a value rating for each attribute. The rating of each

alternative for each attribute indicates how well the alternative will perform

as each attribute is considered. The criteria listed below, are proposed for

prioritizing the projects. These criteria are based on a scoring system of 1

to 5 points.

6.2.1 Demography

If the population grows, the priority of the establishment of a sewer project

increases. Based on that, the highest number of projected population in

2030 between communities (Ph) is given the maximum demography score

(Ds) of 5. The formula for determining the demography scores (Ds) of all

other communities is calculated as follows: Ds = 5 x P/ Ph, in which ―Ds‖

is the demography score, ―Ph‖ is the highest population, and ―P‖ is the

projected population in 2030 of the community under consideration.

6.2.2 Water Consumption / Wastewater Production

There is a positive relationship between water consumption (wastewater

production) and priority of a sewer project. Scores are distributed according

to water consumption as follows:

1 point: < 45L/day/cap

2 points: 45 - 55L/day/cap

3 points: 56 - 65L/day/cap

4 points: 66 - 90L/day/cap

5 points: > 90 L/day/cap

145

6.2.3 Reusing Wastewater

This criterion relates to the suitability of the soil for crop production. To

make this determination, we used value agricultural land map. See Figure

6.1 published by MoA. Scores are distributed as follows:

1 points: Low-value agricultural land

3 points: Medium -value agricultural land

5 points: High-value agricultural land

Figure 6.1: Value agricultural land

146

6.2.4 Environmental Factor

Two specific impacts were taken on environmental issues. The first is

hydrogeological vulnerability of groundwater to which we gave three

points while the second is the presence of springs and wells in the region to

which we gave two points.

The installation of collection systems and centralized treatment will have a

direct benefit to the environment from the discontinuation of unrestricted

dumping of raw sewage and the cessation of cesspit leakage.

The comparative magnitude of the resulting environmental and health

improvements can be estimated by the relative hydrologic vulnerability of

the wastewater system locations. Projects in communities located in aquifer

recharge areas with high infiltration rates would produce a higher benefit

than those that are located in less vulnerable areas. To make this

determination, we used hydrological vulnerability map. See Figure 6.2

published by the United Nations Environment Programme (UNEP) in

cooperation with the Palestinian Environmental Quality Authority from a

study entitled Desk Study on the Environment in the Occupied Palestinian

Territories (2002).

147

Figure 6.2: Hydrogeological vulnerability of groundwater to pollution in the West

Bank

Scores are distributed as follows:

1 point: No springs and wells in the region.

2 points: One or more springs or wells in the region.

1 point: Community located in a region of low hydrological

vulnerability to groundwater pollution as defined by UNEP.

2 points: Community located in a region of medium hydrological

vulnerability to groundwater pollution as defined by UNEP.

3 points: Community located in a region of high hydrological

vulnerability to groundwater pollution as defined by UNEP.

148

6.2.5 Operation Body

We used MoLG and Municipal Development & Lending Fund (MDLF)

ranked communities. MoLG ranked communities depend on various

standards such as the size of the community and the strength of the

operation body. MDLF ranked communities accept ―good management‖

practices according to 12 basics. Funds are allocated based on rank;

municipalities with higher rankings will be eligible for more funding than

those with lower rankings. The rankings are from A to F, with A

constituting the highest possible rank. They are based on 12 criteria

encompassing planning, management and financial accountability as shown

in Table 6.2.

Table 6.2: Municipal ranking on the basis of performance for the

municipal development program (MDP) in MDLF

Rank Performance Indicator

A

Current Account Surplus (for 2 consecutive years)

Unqualified External Audit

Integrated Financial Management System

B

Operational Account Surplus

Fixed Assets Register

Maintenance Plan in place

C

Municipal Development/Investment Plan

Financial Accounting Policies & Procedures in place

External Audit

D Capital Budget (approved and executed, properly submitted t

o MoLG)

E Recurrent Budget (approved and properly submitted to MoL

G)

F No Budgetary Information

Scores are distributed as follows:

149

MoLG

0.5 point: Village Council or Projects Committee

1 point: Rank of municipality is D.

1.5 point: Rank of municipality is C.

2 point: Rank of municipality is B.

2.5 point: Rank of municipality is A.

MDLF

0.5 point: Rank of municipality is F.

1 point: Rank of municipality is E.

1.5 point: Rank of municipality is D.

2 point: Rank of municipality is C.

2.5 point: Rank of municipality is A,B.

6.2.6 Risk for Industrial Waste

There is an impact of effluents from industrial operations (stone cutting,

olive press, textiles, etc) on the effectiveness of the treatment plants. It is

assumed that direct connection of these wastes to the collection system will

not be allowed without pre-treatment, and it is something difficult to do by

the municipalities. Scores are distributed as follows:

1 point: > 15 stonecutters + olive presses + textiles

2 points: Between 10 and 15 stonecutters + olive presses + textiles

3 points: Between 5 and 10 stonecutters + olive presses + textiles

4 points: < 5 stonecutters + olive presses + textiles

5 points: No stonecutters + olive presses + textiles

6.2.7 Socio-Economic Factor

The socio-economic factor assessment process will be on the basis of, first,

education which gives an indication of the community acceptance of the

150

project, and secondly how economically active the citizens are which gives

an indication of the ability of citizens to pay and contribute to the costs of

construction, operation and maintenance costs. Scores are distributed as

follows:

0.5 point: <= 5% of the population hold a bachelor degree or higher

of the total population aged 10 years and over.

1.5 points: 5% to 10% of the population hold a bachelor degree or

higher of the total population aged 10 years and over.

2.5 point: > 10% of the population hold a bachelor degree or higher

of the total population aged 10 years and over.

0.5 points: <= 30% of the population economically active of the

total population aged 10 years and over.

1.5 points: 30% to 35% of the population is economically active of

the total population aged 10 years and over.

2.5 points: > 35% of the population economically active of the total

population aged 10 years and over.

6.2.8 Geographical Factor (topography, catchment)

The geographical factors affect the construction of sewer systems and the

capital cost of sewer systems and if we need pumping station or not. Scores

are distributed as follows:

0.5 point: <50% by gravity flow.

1 points: 50% to 75% by gravity flow.

1.5 points: 75% to 95% by gravity flow.

2 points: > 95% by gravity flow.

151

1 point: > 2 catchment areas.

2 points: 2 catchment areas.

3 points: 1 catchment areas.

6.2.9 Political Issues

The political issues of each of these permanent features will affect the

relative ease of implementation by the impact they have on Area C. The

joint water committee (JWC) in PWA has indicated that projects that

impact Area A and B only can get implemented much faster than those that

impact Area C as it is near settlements which would delay obtaining a

license. Scores

are distributed to two points according to whether or not there are Israeli

settlements in the catchment area and according to the political land

classifications. Areas A, B, and C can be seen as follows:

1 point: One or more Israeli settlements in the catchment area

2 points: No Israeli settlements in the catchment area.

1 points: Trunk lines and/or WWTP in Area C

2 points: Entire project in Areas A and/or B

3 points: Entire project in Areas A

152

Chapter 7

Priorities Settings

7.1 Identify Communities

We will take the towns whose population is over 10 thousand people in

accordance with the directives of the PWA to resolve the problem of

sanitation in the towns and villages with the population of over 10 thousand

people by 2030. Based on the PCBS, we indicate the population numbers

for all Palestinian communities (see Annex C ‎Annex C ) according to the

census of 1997 and 2007. Communities that are expected to have a

population of more than 10,000 people in 2030 are show in Table 7.1.

From the Table 7.1, it can be seen that there are 97 communities expected

to have a population of more than 10,000 people in 2030. We except 33

communities because they contain sewage systems or in the design or

implementation stages. According to PWA Strategy a sanitation sector will

have been developed in 33 communities, and sanitation systems for 64

communities will have been found by 2030. The total current population of

64 communities is 846,705 and is expected to be 1,483,779 person in 2030.

The following communities are classified by governorates:

153

Jenin governorate (11 communities): Silat al Harithiya, Al Yamun, Kafr

Dan, Deir Abu Da'if, Birqin, Ya'bad, Qabatiya, Arraba, Kafr Ra'I,

Meithalun, and Jaba'

Tubas governorate (2 communities): El Far'a Camp, and Tammun

Tulkarem governorate (4 communities): Qaffin, 'Attil, Deir al Ghusun,

Bal'a Nablus governorate (7 communities): 'Asira ash Shamaliya, 'Awarta,

Huwwara, Beita, Jamma'in, Aqraba, and Qabalan

Qalqiliya governorate (1 community): 'Azzun

Salfit governorate (1 community): Biddya

Ramallah & Al-Bireh governorate (6 communities): Sinjil, Shuqba, Qibya,

Al Jalazun Camp, Kharbatha al Misbah, and Beit Liqya

Jericho governorate (no communities)

Jerusalem governorate (7 communities): Ar Ram & Dahiyat al Bareed, Al

Biddu, Hizma, 'Anata, Al 'Eizariya, Abu Dis, and As Sawahira ash

Sharqiya.

Bethlehem governorate (7 communities): Al 'Ubeidiya, Husan, Nahhalin,

Za'tara, Jannatah, Tuqu', and Beit Fajjar.

Hebron governorate (18 communities):Surif, Beit Ummar, Kharas, Beit

Ula, Sa'ir, Halhul, Ash Shuyukh, Tarqumiya, Beit Kahil, Idhna, Taffuh,

154

Deir Samit, Bani Na'im, Beit 'Awwa, Dura, Yatta, Adh Dhahiriya, and As

Samu'.

155

No. Locality Name

Locality code

ازجغاؿ

Actual Population

2007

Actual Populatio

n 1997

Actual Growth-

Rate (2007-1997)

Projected

Population 2010

Projected

Population 2020

Projected

Population

2030

Note

Jenin Gov.

1 Silat al Harithiya

10035 ؿ١خ

اذبعص١خ9,422 7,246 2.66 10,194 13,256 17,236 Cesspits

2 Al Yamun 10080 Cesspits 31,943 23,894 17,874 2.95 12,255 16,383 ا١ب

3 Kafr Dan 10095 10,565 7,729 5,654 3.18 3,766 5,148 وفغ صا Cesspits

4 Barta'a ash Sharqiya

10120 ثغطؼخ

الغل١خ4,176 2,814 4.03 4,701 6,976 10,353

Treated inside GL

5 Jenin 10180 85,164 60,646 43,186 3.45 27,775 39,004 ج١ Jenin TP

6 Jenin Camp

14,403 12,486 10,825 1.44 8,991 10,371 ش١ ج١ 10185Connected

to Jenin

7 Deir Abu Da'if

10215 ص٠غ أث

ضؼ١ف5,572 3,897 3.64 6,203 8,869 12,681 Cesspits

8 Birqin 10220 10,555 8,065 6,163 2.73 4,344 5,685 ثغل١ Cesspits

9 Ya'bad 10265 24,229 18,873 14,701 2.53 10,625 13,640 ٠ؼجض Cesspits

10 Qabatiya 10340 36,465 27,588 20,873 2.83 14,524 19,197 لجبط١خ Cesspits

11 Arraba 10370 18,452 14,088 10,756 2.74 7,574 9,920 ػغاثخ Cesspits

12 Kafr Ra'i 10465 12,967 10,139 7,928 2.49 5,758 7,364 وفغ عاػ Cesspits

13 Meithalu Cesspits 13,825 10,255 7,607 3.03 5,159 6,955 ١ض 10520

Table 7.1 Communities that are expected to have a population of more than 10,000 people in 2030

156

n

14 Jaba' 10605 16,222 12,243 9,240 2.85 6,409 8,492 ججغ Cesspits

Tubas Gov. 15 'Aqqaba 50535 16,468 11,028 7,385 4.09 4,385 6,548 ػمبث Tubas TP

(Tayasir) Funded by

AFD 16 Tubas 50610 34,483 24,798 17,833 3.35 11,617 16,154 طثبؽ

17 El Far'a Camp

50700 ش١

افبعػخ5,712 4,152 3.24 6,286 8,647 11,896

Collection systm-

Discharged into Wadi

18 Tammun 50755 24,642 17,212 12,022 3.65 7,540 10,795 ط Cesspits

Tulkarem Gov. 19 Qaffin 100290 15,398 11,823 9,079 2.68 6,440 8,387 لف١ Cesspits

20 'Attil 100480 13,218 11,205 9,497 1.67 7,661 9,038 ػز١ Cesspits

21 Deir al Ghusun

100530 ص٠غ

اغو8,242 6,969 1.69 8,667 10,251 12,123 Cesspits

22 Bal'a 100570 10,614 8,635 7,026 2.08 5,373 6,604 ثؼب Cesspits

23 Iktaba 100595 10,704 5,848 3,195 6.23 1,456 2,665 إوزبثب Tulkarm

regional TP (Funded by

KFW )

24 Tulkarm Camp

100635 ش١

طىغ10,641 9,948 0.68 10,858 11,615 12,424

25 Tulkarm 100645 91,038 70,944 55,285 2.53 39,977 51,300 طىغ

26 Anabta 100665 11,471 9,441 7,770 1.97 6,032 7,329 ػجزب

Nablus Gov.

157

27 'Asira ash Shamaliya

150820 ػو١غح

الب١خ7,556 5,724 2.82 8,212 10,841 14,310 Cesspits

28 Nablus 150920 219,132 172,350 135,555 2.43 99,204 126,132 بثؾ Nalus west TP (Funded

by KFW (Implement

ation process),

Nablus East TP

(Feasibility study,

Funded by KFW)

29 'Askar Camp

150930 ش١

ػـىغ11,607 9,372 2.16 12,376 15,328 18,983

30 Salim 150955 10,099 7,479 5,539 3.05 3,749 5,062 ؿب

31 Balata Camp

150960 ش١

ثالطخ15,247 13,014 1.60 15,989 18,732 21,946

32 Beit Furik 151090 20,535 15,238 11,307 3.03 7,672 10,339 ث١ذ فع٠ه

33 'Awarta 151135 10,500 8,003 6,100 2.75 4,286 5,623 ػعرب Cesspits

34 Huwwara 151185 10,237 7,857 6,030 2.68 4,275 5,570 داعح Cesspits

35 Beita 151215 19,734 14,080 10,047 3.43 6,478 9,079 ث١زب Cesspits 36 Jamma'in 151245 14,870 10,183 6,974 3.86 4,263 6,225 جبػ١ Cesspits

37 Aqraba 151270 17,693 12,651 9,046 3.41 5,849 8,180 ػمغثب Cesspits

38 Qabalan 151335 13,827 10,367 7,773 2.92 5,346 7,130 لجال Cesspits

Qalqiliya Gov.

39 Qalqiliya 201040 80,584 60,538 45,479 2.90 31,356 41,739 لم١١خ Treated

inside GL

40 'Azzun 201100 15,592 11,551 8,558 3.05 5,794 7,821 ػؼ Cesspits

158

41 Habla 201125 12,927 9,270 6,647 3.38 4,314 6,016 دجخ Implementa

tion (fund UNDP)

Salfit Gov.

42 Biddya 251305 16,028 11,890 8,820 3.03 5,982 8,064 ثض٠ب Cesspits

43 Salfit 251370 14,825 11,815 9,416 2.30 7,010 8,796 ؿف١ذ Salfit TP

(Fund KFW)

Ramallah & Al-Bireh Gov.

44 Sinjil 301500 10,414 7,723 5,727 3.03 3,883 5,236 ؿج Cesspits

45 Shuqba 301595 11,177 7,523 5,064 4.04 3,027 4,497 كمجب Cesspits

46 Qibya 301605 11,055 7,762 5,450 3.60 3,441 4,901 لج١ Cesspits

47 Al Jalazun Camp

301700 ش١

اجؼ7,813 6,064 2.57 8,430 10,862 13,994

Collection systm-

Discharged into Wadi

48 Al Bireh 301790 80,645 58,277 42,112 3.30 27,606 38,202 اج١غح Al-Bireh TP

49 Ramallah 301810 74,613 48,313 31,284 4.44 17,781 27,460 عا هللا Ramallah Regional

(Ein Jaruit) - Approved (funded by

KFW)

50 Beituniya 301825 112,050 52,694 24,780 7.84 9,293 19,761 ث١ز١ب

51 Kharbatha al

301855 سغثضب

اوجبح5,211 3,662 3.59 5,793 8,243 11,730 Cesspits

159

Misbah

52 Beit Liqya 301895 15,864 11,592 8,471 3.19 5,634 7,710 ث١ذ م١ب Cesspits

Jericho Gov.

53 'Ein as Sultan Camp

351865 ش١ ػ١

اـطب3,160 1,451 8.09 3,991 8,692 18,929

Jericho TP - Implementation ( fund

JICA)

54 Jericho (Ariha)

28,095 23,343 19,395 1.87 15,243 18,346 أع٠ذب 351920

55 Aqbat Jaber Camp

351975 ش١ ػمجخ

ججغ7,176 4,521 4.73 8,243 13,084 20,767

Jerusalem Gov.

56 Qalandiya Camp

17,081 12,822 9,625 2.91 6,629 8,831 ش١ لض٠ب 401900Connected

to Ramallah

57 Ar Ram & Dahiyat al Bareed

401945 اغا

ضبد١خ

اجغ٠ض20,359 18,719 0.84 20,878 22,708 24,697

51% Collection

systm-Discharged into Wadi

58 Biddu 401995 16,226 11,116 7,615 3.86 4,657 6,798 ثض Cesspits

59 Hizma 402005 13,739 9,769 6,947 3.47 4,459 6,271 دؼب Cesspits

60 'Anata 402040 41,509 24,243 14,159 5.53 7,037 12,049 ػبرب Cesspits

61 Al 'Eizariya

Cesspits 37,157 26,854 19,408 3.30 12,724 17,606 اؼ١ؼع٠خ 402100

160

62 Abu Dis 402120 16,945 13,921 11,437 1.99 8,858 10,782 أث ص٠ؾ Cesspits

63

As Sawahira ash Sharqiya

402145 اـادغح

الغل١خ5,800 3,810 4.29 6,579 10,016 15,247 Cesspits

Bethlehem Gov.

64 Al 'Ubeidiya

22,736 16,419 11,856 3.31 7,765 10,753 اؼج١ض٠خ 452180

Collection systm-

Discharged into Wadi

65 Beit Jala 452210 13,187 12,546 11,935 0.27- 12,079 11,758 ث١ذ جبال ww

collection system

66 Husan 452230 10,952 8,150 6,065 3.00 4,131 5,551 دؿب Cesspits

67 Bethlehem (Beit Lahm)

36,004 30,866 26,461 1.55 21,660 25,266 ث١ذ ذ 452240Bethlehem TP (Fund

AFD)

68 Beit Sahur

452255 ث١ذ

ؿبدع12,367 11,137 1.05 12,762 14,171 15,736

ww collection

system

69 Ad Doha 452265 42,726 22,478 11,825 6.63 5,131 9,753 اضدخ ww

collection system

70 Al Khadr 452270 23,136 15,907 10,937 3.82 6,720 9,774 اشضغ ww

collection

161

system

71 Ad Duheisha Camp

452275 ش١

اض١لخ8,736 6,803 2.53 9,417 12,092 15,528

Connected to

Bethlehem

72 Nahhalin 452325 16,611 11,285 7,667 3.94 4,638 6,827 ذب١ Cesspits

73 Za'tara 452360 14,242 9,982 6,997 3.62 4,408 6,289 ػػزغح Cesspits

74 Jannatah 452385 جبرخ )ث١ذ

فح(5,416 3,623 4.10 6,110 9,134 13,655 Cesspits

75 Tuqu' 452495 20,563 14,274 9,909 3.72 6,165 8,881 رمع Cesspits 76 Beit Fajjar 452525 23,609 16,941 12,156 3.37 7,896 11,004 ث١ذ فجبع Cesspits

Hebron Gov.

77 Surif 502450 29,016 20,714 14,787 3.43 9,541 13,365 هع٠ف Cesspits

78 Al 'Arrub Camp

502530 ش١

اؼغة7,941 5,933 2.96 8,667 11,600 15,526

ww collection

system

79 Beit Ummar

Cesspits 28,091 20,458 14,900 3.22 9,867 13,548 ث١ذ أغ 502540

80 Kharas 502560 12,274 9,406 7,208 2.70 5,100 6,655 سبعاؽ 50% ww

collection system

81 Beit Ula 502615 25,150 17,474 12,141 3.71 7,563 10,885 ث١ذ أال Cesspits

82 Sa'ir 502620 37,227 27,172 19,833 3.20 13,171 18,045 ؿؼ١غ Cesspits

83 Halhul 502630 49,025 34,690 24,547 3.52 15,658 22,128 دذي Cesspits 84 Ash 502635 21,437 14,564 9,894 3.94 5,986 8,811 ال١ر Cesspits

162

Shuyukh

85 Tarqumiya

Cesspits 29,868 21,721 15,796 3.24 10,441 14,357 رغل١ب 502640

86 Beit Kahil 502655 18,393 11,722 7,470 4.61 4,159 6,526 ث١ذ وبد Cesspits 87 Idhna 502685 41,207 29,438 21,030 3.42 13,582 19,012 إطب Cesspits

88 Taffuh 502750 26,924 17,950 11,968 4.14 7,065 10,597 رفح Cesspits

89 Hebron (Al Khalil)

343,950 248,692 179,815 3.30 117,962 163,146 اش١ 502780Approved by JWC (

fund USAID)

90 Deir Samit

Cesspits 16,205 10,699 7,064 4.24 4,118 6,237 ص٠غ ؿبذ 502810

91 Bani Na'im

Cesspits 50,523 33,830 22,652 4.09 13,448 20,084 ث ؼ١ 502815

92 Beit 'Awwa

Cesspits 16,391 12,041 8,846 3.13 5,924 8,064 ث١ذ ػا 502835

93 Dura 502840 72,521 48,147 31,964 4.18 18,767 28,268 صعا Cesspits

94 Al Fawwar Camp

502905 ش١

افاع6,544 4,784 3.18 7,189 9,834 13,451

Connected to Hebron

95 Yatta 503120 113,456 78,528 54,353 3.75 33,688 48,672 ٠طب Cesspits

96 Adh Dhahiriya

Cesspits 63,239 44,907 31,888 3.48 20,434 28,776 اظبغ٠خ 503245

97 As Samu' 503320 42,855 30,532 21,753 3.45 13,999 19,649 اـع Cesspits

163

7.2 Application of MCDA Tools

MCDA tools will be applied to the communities that have been selected.

First, we score for each criterion to the selected communities. Secondly, we

normalize the weights of criteria and give the score for each community.

7.2.1 Carries a Value Rating for Each Criteria

By reference to the section ‎6.2 we score for each community as follows:

7.2.1.1 Demography

According to (PCBS, 2007) the population and score of each community

are as shown in Table 7.2.

Table 7.2: Demography score of each community

No. Locality

Name

Projected

Population

2030

score No. Locality

Name

Projected

Population

2030

score

1 Silat al

Harithiya 17,236 0.76 33

Ar Ram &

Dahiyat al

Bareed

24,697 1.09

2 Al Yamun 31,943 1.41 34 Biddu 16,226 0.72

3 Kafr Dan 10,565 0.47 35 Hizma 13,739 0.61

4 Deir Abu

Da'if 12,681 0.56 36 'Anata 41,509 1.83

5 Birqin 10,555 0.47 37 Al

'Eizariya 37,157 1.64

6 Ya'bad 24,229 1.07 38 Abu Dis 16,945 0.75

7 Qabatiya 36,465 1.61 39

As

Sawahira

ash

Sharqiya

15,247 0.67

8 Arraba 18,452 0.81 40 Al

'Ubeidiya 22,736 1.00

9 Kafr Ra'i 12,967 0.57 41 Husan 10,952 0.48

10 Meithalun 13,825 0.61 42 Nahhalin 16,611 0.73

11 Jaba' 16,222 0.71 43 Za'tara 14,242 0.63

12 El Far'a

Camp 11,896 0.52 44 Jannatah 13,655 0.60

13 Tammun 24,642 1.09 45 Tuqu' 20,563 0.91

14 Qaffin 15,398 0.68 46 Beit Fajjar 23,609 1.04

164

15 'Attil 13,218 0.58 47 Surif 29,016 1.28

16 Deir al

Ghusun 12,123 0.53 48

Beit

Ummar 28,091 1.24

17 Bal'a 10,614 0.47 49 Kharas 12,274 0.54

18 'Asira ash

Shamaliya 14,310 0.63 50 Beit Ula 25,150 1.11

19 'Awarta 10,500 0.46 51 Sa'ir 37,227 1.64

20 Huwwara 10,237 0.45 52 Halhul 49,025 2.16

21 Beita 19,734 0.87 53 Ash

Shuyukh 21,437 0.94

22 Jamma'in 14,870 0.66 54 Tarqumiya 29,868 1.32

23 Aqraba 17,693 0.78 55 Beit Kahil 18,393 0.81

24 Qabalan 13,827 0.61 56 Idhna 41,207 1.82

25 'Azzun 15,592 0.69 57 Taffuh 26,924 1.19

26 Biddya 16,028 0.71 58 Deir Samit 16,205 0.71

27 Sinjil 10,414 0.46 59 Bani

Na'im 50,523 2.23

28 Shuqba 11,177 0.49 60 Beit

'Awwa 16,391 0.72

29 Qibya 11,055 0.49 61 Dura 72,521 3.20

30 Al Jalazun

Camp 13,994 0.62 62 Yatta 113,456 5.00

31 Kharbatha

al Misbah 11,730 0.52 63

Adh

Dhahiriya 63,239 2.79

32 Beit Liqya 15,864 0.70 64 As Samu' 42,855 1.89

7.2.1.2 Water Consumption / Wastewater Production

Scores of communities are distributed according to water consumption

(PWA, 2005) as follows in Table 7.3.

Table 7.3: Water consumption score of each community

No. Locality

Name

Water

consumption

(L/day/c

ap)

score No. Locality

Name

Water consumption

(L/day/cap)

scor

e

1 Silat al

Harithiya 111 5 33

Ar Ram

&

Dahiyat

al Bareed

55 2

2 Al Yamun 77 4 34 Biddu 68 4

3 Kafr Dan 57 3 35 Hizma 67 4

165

4 Deir Abu

Da'if 66 4 36 'Anata 88 4

5 Birqin 78 4 37 Al

'Eizariya 108 5

6 Ya'bad 54 2 38 Abu Dis 98 5

7 Qabatiya 68 4 39

As

Sawahira

ash

Sharqiya

102 5

8 Arraba 64 3 40 Al

'Ubeidiya 45 2

9 Kafr Ra'i 72 4 41 Husan 45 2

10 Meithalun 58 3 42 Nahhalin 55 2

11 Jaba' 64 3 43 Za'tara 40 1

12 El Far'a

Camp 45 2 44 Jannatah 45 2

13 Tammun 82 4 45 Tuqu' 50 2

14 Qaffin 85 4 46 Beit

Fajjar 60 3

15 'Attil 90 4 47 Surif 30 1

16 Deir al

Ghusun 96 5 48

Beit

Ummar 50 2

17 Bal'a 76 4 49 Kharas 42 1

18 'Asira ash

Shamaliya 65 3 50 Beit Ula 35 1

19 'Awarta 83 4 51 Sa'ir 30 1

20 Huwwara 66 4 52 Halhul 35 1

21 Beita 56 3 53 Ash

Shuyukh 45 2

22 Jamma'in 62 3 54 Tarqumiy

a 40 1

23 Aqraba 106 5 55 Beit

Kahil 50 2

24 Qabalan 33 1 56 Idhna 45 2

25 'Azzun 140 5 57 Taffuh 30 1

26 Biddya 53 2 58 Deir

Samit 55 2

27 Sinjil 46 2 59 Bani

Na'im 42 1

28 Shuqba 24 1 60 Beit

'Awwa 25 1

29 Qibya 56 3 61 Dura 50 2

30 Al Jalazun

Camp 94 5 62 Yatta 30 1

166

31 Kharbatha

al Misbah 57 3 63

Adh

Dhahiriya 55 2

32 Beit Liqya 52 2 64 As Samu' 60 3

7.2.1.3 Reusing Wastewater

Scores of communities are distributed by using value agricultural land map

as follows in Table 7.4. (See Figure 6.1 published by MoA).

Table 7.4: Wastewater reuse score of each community

No. Locality

Name

Agricultural

land value score No.

Locality

Name

Agricultural

land value score

1 Silat al

Harithiya High 5 33

Ar Ram &

Dahiyat al

Bareed

Low 1

2 Al Yamun High 5 34 Biddu Medium 3

3 Kafr Dan High 5 35 Hizma Low 1

4 Deir Abu

Da'if High 5 36 'Anata Low 1

5 Birqin Medium 3 37 Al

'Eizariya Low 1

6 Ya'bad Medium 3 38 Abu Dis Low 1

7 Qabatiya High +

Medium 4 39

As

Sawahira

ash

Sharqiya

Low 1

8 Arraba High +

Medium 4 40

Al

'Ubeidiya Low 1

9 Kafr Ra'i Low +

Medium 2 41 Husan Medium 3

10 Meithalun

Low +

Medium +

High

3 42 Nahhalin Medium 3

11 Jaba' Medium 3 43 Za'tara Low +

Medium 2

12 El Far'a

Camp High 5 44 Jannatah

Low +

Medium 2

13 Tammun Low 1 45 Tuqu' Low +

Medium 2

14 Qaffin Medium 3 46 Beit Fajjar Low +

Medium 2

15 'Attil High 5 47 Surif Low 1

167

16 Deir al

Ghusun High 5 48

Beit

Ummar

Low +

Medium 2

17 Bal'a Low +

Medium 2 49 Kharas Low 1

18 'Asira ash

Shamaliya Low 1 50 Beit Ula Low 1

19 'Awarta

Low +

Medium +

High

3 51 Sa'ir Low +

Medium 2

20 Huwwara Low +

Medium 2 52 Halhul

Low +

Medium 2

21 Beita Low +

Medium 2 53

Ash

Shuyukh Low 1

22 Jamma'in Low +

Medium 2 54 Tarqumiya Low 1

23 Aqraba Low +

Medium 2 55 Beit Kahil

Low +

Medium 2

24 Qabalan Low +

Medium 2 56 Idhna Low 1

25 'Azzun Low +

Medium 2 57 Taffuh

Low +

Medium 2

26 Biddya Low +

Medium 2 58 Deir Samit

Low +

Medium 2

27 Sinjil Low +

Medium 2 59

Bani

Na'im Low 1

28 Shuqba Low +

Medium 2 60

Beit

'Awwa

Low +

Medium 2

29 Qibya Low +

Medium 2 61 Dura Low 1

30

Al

Jalazun

Camp

Low + High 3 62 Yatta Low 1

31 Kharbatha

al Misbah Medium 3 63

Adh

Dhahiriya

Low +

Medium +

High

3

32 Beit

Liqya

High +

Medium 4 64 As Samu' Low 1

7.2.1.4 Environmental Factor Scores of communities are distributed as follows in Table 7.5.

Table .

168

Table 7.5: Environmental factor score of each community

No

. Locality Name

Springs or

wells in the

region

Hydrological

vulnerability to

Groundwater

score No

. Locality Name

Springs or wells

in the region

Hydrological

vulnerability to

Groundwater

score

1 Silat al

Harithiya No High 4 33

Ar Ram &

Dahiyat al

Bareed

High No 4

2 Al Yamun Yes Low 3 34 Biddu High No 4

3 Kafr Dan Yes Medium 4 35 Hizma High Yes 5

4 Deir Abu Da'if No High 4 36 'Anata High No 4

5 Birqin Yes Low 3 37 Al 'Eizariya Low Yes 3

6 Ya'bad Yes Medium 4 38 Abu Dis Low No 2

7 Qabatiya Yes High 5 39 As Sawahira

ash Sharqiya Low Yes 3

8 Arraba Yes Low 3 40 Al 'Ubeidiya Low No 2

9 Kafr Ra'i No Medium 3 41 Husan High Yes 5

10 Meithalun No High 4 42 Nahhalin High Yes 5

11 Jaba' Yes High 5 43 Za'tara Low Yes 3

12 El Far'a Camp Yes High 5 44 Jannatah Medium No 3

13 Tammun Yes Low 3 45 Tuqu' High Yes 5

14 Qaffin Yes Low 3 46 Beit Fajjar High Yes 5

15 'Attil Yes Medium 4 47 Surif High No 4

16 Deir al Ghusun Yes Low 3 48 Beit Ummar High Yes 5

17 Bal'a Yes Medium 4 49 Kharas High No 4

18 'Asira ash

Shamaliya No High 4 50 Beit Ula Medium No 3

169

19 'Awarta Yes Low 3 51 Sa'ir High Yes 5

20 Huwwara Yes Low 3 52 Halhul High Yes 5

21 Beita No Medium 3 53 Ash Shuyukh High Yes 5

22 Jamma'in No High 4 54 Tarqumiya High No 4

23 Aqraba Yes High 5 55 Beit Kahil High Yes 5

24 Qabalan No High 4 56 Idhna Low Yes 3

25 'Azzun Yes Medium 4 57 Taffuh High Yes 5

26 Biddya No High 4 58 Deir Samit Low No 2

27 Sinjil Yes High 5 59 Bani Na'im Low Yes 3

28 Shuqba Yes High 5 60 Beit 'Awwa Low No 2

29 Qibya No High 4 61 Dura High Yes 5

30 Al Jalazun

Camp No High 4 62 Yatta Medium Yes 4

31 Kharbatha al

Misbah No Low 2 63 Adh Dhahiriya Low No 2

32 Beit Liqya Yes Medium 4 64 As Samu' Low Yes 3

170

7.2.1.5 Operation Body

Scores of communities are distributed according to MoLG and MDLF

ranking as follows in Table 7.6.

Table 7.6: Operation body score of each community

No.

Locality

Nam

e

Ran

k

(MoL

G)

Ran

k

(MD

LF

)

score

No.

Locality

Nam

e

Ran

k

(MoL

G)

Ran

k

(MD

LF

)

score

1

Silat al

Harithi

ya

C C 3.5 33

Ar Ram &

Dahiyat al

Bareed

C C 3.5

2 Al

Yamun B C 4.0 34 Biddu C C 3.5

3 Kafr

Dan

Village

Council C 2.5 35 Hizma

Village

Council C 2.5

4

Deir

Abu

Da'if

Village

Council C 2.5 36 'Anata C E 2.5

5 Birqin C C 3.5 37 Al 'Eizariya C C 3.5

6 Ya'bad B C 4.0 38 Abu Dis C C 3.5

7 Qabati

ya B C 4.0 39

As Sawahira

ash Sharqiya C C 3.5

8 Arraba B C 4.0 40 Al 'Ubeidiya C C 3.5

9 Kafr

Ra'i C C 3.5 41 Husan

Village

Council C 2.5

10 Meithal

un C C 3.5 42 Nahhalin

Village

Council C 2.5

11 Jaba' C C 3.5 43 Za'tara C C 3.5

12 El Far'a

Camp

Projects

Commi

ttee

C 2.5 44 Jannatah D C 2.0

13 Tammu

n C C 3.5 45 Tuqu' C C 3.5

14 Qaffin C C 3.5 46 Beit Fajjar C C 3.5

15 'Attil C C 3.5 47 Surif C C 3.5

16 Deir al

Ghusun C C 3.5 48 Beit Ummar C C 3.5

17 Bal'a C C 3.5 49 Kharas C C 3.5

18

'Asira

ash

Shamal

iya

C C 3.5 50 Beit Ula C C 3.5

19 'Awarta Village

Council C 2.5 51 Sa'ir B C 4.0

171

20 Huwwa

ra C C 3.5 52 Halhul B C 4.0

21 Beita C C 3.5 53 Ash Shuyukh C C 3.5

22 Jamma'

in C C 3.5 54 Tarqumiya C C 3.5

23 Aqraba C C 3.5 55 Beit Kahil Village

Council C 2.5

24 Qabala

n C C 3.5 56 Idhna B B 4.5

25 'Azzun C C 3.5 57 Taffuh C C 3.5

26 Biddya C C 3.5 58 Deir Samit C C 3.5

27 Sinjil C E 2.5 59 Bani Na'im B C 4.0

28 Shuqba Village

Council C 2.5 60 Beit 'Awwa C C 3.5

29 Qibya Village

Council C 2.5 61 Dura B B 4.5

30

Al

Jalazun

Camp

Projects

Commi

ttee

C 2.5 62 Yatta B C 4.0

31

Kharba

tha al

Misbah

Village

Council C 2.5 63

Adh

Dhahiriya B C 4.0

32 Beit

Liqya C C 3.5 64 As Samu' B C 4.0

7.2.1.6 Risk for Industrial Waste

Scores of communities are distributed according to the number of industrial

operations (stone cutting, olive press, textiles, etc) (PCBS, 2007) as follows

in Table 7.7.

172

Table 7.7: Risk for Industrial Waste score of each community

No. Locality

Name

Olive

presses

Stonecutt

ers Textiles

Tot

al Score No.

Locality

Name

Olive

presses Stonecutters

Texti

les Total Score

1 Silat al

Harithiya 1 2 0 3 4 33

Ar Ram &

Dahiyat al

Bareed

1 4 0 5 3

2 Al

Yamun 4 3 0 7 3 34 Biddu 2 3 0 5 3

3 Kafr Dan 1 0 0 1 4 35 Hizma 0 5 0 5 3

4 Deir Abu

Da'if 1 0 0 1 4 36 'Anata 0 11 0 11 2

5 Birqin 3 0 0 3 4 37 Al

'Eizariya 0 0 1 1 4

6 Ya'bad 2 0 0 2 4 38 Abu Dis 0 0 0 0 5

7 Qabatiya 4 64 0 68 1 39

As

Sawahira

ash

Sharqiya

0 0 0 0 5

8 Arraba 5 3 0 8 3 40 Al

'Ubeidiya 0 0 0 0 5

9 Kafr Ra'i 5 1 0 6 3 41 Husan 0 0 0 0 5

10 Meithalu

n 2 2 0 4 4 42 Nahhalin 0 0 0 0 5

11 Jaba' 2 1 0 3 4 43 Za'tara 0 0 0 0 5

173

12 El Far'a

Camp 0 0 0 0 5 44 Jannatah 0 0 0 0 5

13 Tammun 0 5 0 5 3 45 Tuqu' 0 1 0 1 4

14 Qaffin 3 2 0 5 3 46 Beit Fajjar 0 182 0 182 1

15 'Attil 2 3 0 5 3 47 Surif 2 2 0 4 4

16 Deir al

Ghusun 4 1 0 5 3 48

Beit

Ummar 0 15 0 15 2

17 Bal'a 2 1 0 3 4 49 Kharas 2 2 0 4 4

18

'Asira

ash

Shamaliy

a

3 2 0 5 3 50 Beit Ula 1 0 0 1 4

19 'Awarta 2 0 0 2 4 51 Sa'ir 2 12 0 14 2

20 Huwwar

a 0 2 0 2 4 52 Halhul 0 9 0 9 3

21 Beita 5 0 0 5 3 53 Ash

Shuyukh 0 15 0 15 2

22 Jamma'in 2 30 0 32 1 54 Tarqumiy

a 1 5 0 6 3

23 Aqraba 2 2 0 4 4 55 Beit Kahil 0 0 0 0 5

24 Qabalan 3 1 0 4 4 56 Idhna 3 6 0 9 3

25 'Azzun 2 0 0 2 4 57 Taffuh 0 0 0 0 5

26 Biddya 5 0 0 5 3 58 Deir

Samit 1 0 0 1 4

27 Sinjil 0 0 0 0 5 59 Bani

Na'im 1 4 0 5 3

174

28 Shuqba 1 1 0 2 4 60 Beit

'Awwa 0 13 0 13 2

29 Qibya 0 1 0 1 4 61 Dura 1 0 0 1 4

30

Al

Jalazun

Camp

0 0 0 0 5 62 Yatta 2 9 0 11 2

31

Kharbath

a al

Misbah

2 2 0 4 4 63 Adh

Dhahiriya 2 8 0 10 2

32 Beit

Liqya 1 2 0 3 4 64 As Samu' 0 0 0 0 5

7.2.1.7 Socio-Economic Factor

Scores of communities are distributed according to percentages of the population holding a bachelor degree or a higher

degree and the percentages of the economically active citizens of the total population aged 10 years and over (PCBS, 2007)

as follows in Table 7.8.

175

Table 7.8: Socio-economic factor score of each community

No. Locality

Name

Total

populatio

n aged 10

years and

over

Ph.D Master Higher

Diploma B.Sc.

Total B.Sc.

degree or

higher

% holds a

B.Sc. or

higher

Econo

mically

active

%

Economically

active

Score

1 Silat al

Harithiya 6,640 13 27 4 356 400 6 2,042 31 3.0

2 Al Yamun 11,484 9 27 7 477 520 5 3,675 32 2.0

3 Kafr Dan 3,585 1 8

191 200 6 1,157 32 3.0

4 Deir Abu

Da'if 3,805 10 3 162 175 5 1,334 35 2.0

5 Birqin 4,159 6 20 4 336 366 9 1,518 36 4.0

6 Ya'bad 9,759 14 36 7 675 732 8 3,132 32 3.0

7 Qabatiya 13,446 10 45 12 703 770 6 3,494 26 2.0

8 Arraba 7,127 4 28 5 468 505 7 2,206 31 3.0

9 Kafr Ra'i 5,325 4 22 5 271 302 6 1,636 31 3.0

10 Meithalun 5,054 14 50 11 423 498 10 1,656 33 3.0

11 Jaba' 6,079 3 15 3 280 301 5 1,680 28 1.0

12 El Far'a

Camp 3,778 3 12 1 227 243 6 1,316 35 3.0

13 Tammun 7,651 7 35 4 570 616 8 2,586 34 3.0

14 Qaffin 6,041 3 15 1 267 286 5 1,840 30 1.0

15 'Attil 6,793 26 4 534 564 8 2,208 33 3.0

16 Deir al 6,079 7 47 13 583 650 11 2,052 34 4.0

176

Ghusun

17 Bal'a 4,756 3 15 2 225 245 5 1,474 31 2.0

18 'Asira ash

Shamaliya 5,557 12 52 11 649 724 13 2,023 36 5.0

19 'Awarta 3,982 8 1 193 202 5 1,292 32 2.0

20 Huwwara 3,948 3 20 3 221 247 6 1,201 30 2.0

21 Beita 6,198 6 33 2 383 424 7 1,902 31 3.0

22 Jamma'in 4,206 4 21 1 263 289 7 1,261 30 2.0

23 Aqraba 5,625 1 6

145 152 3 1,713 30 1.0

24 Qabalan 5,030 1 11 1 164 177 4 1,551 31 2.0

25 'Azzun 5,414 3 21 7 390 421 8 1,765 33 3.0

26 Biddya 5,563 5 41 2 377 425 8 1,791 32 3.0

27 Sinjil 3,459 5 12 4 139 160 5 1,129 33 2.0

28 Shuqba 2,929 1 6 1 105 113 4 1,014 35 2.0

29 Qibya 3,253 3

101 104 3 1,163 36 3.0

30 Al Jalazun

Camp 5,158 2 15

162 179 3 1,773 34 2.0

31 Kharbatha

al Misbah 3,478 1 7 1 106 115 3 1,091 31 2.0

32 Beit Liqya 5,226 16 1 260 277 5 1,692 32 2.0

33

Ar Ram &

Dahiyat al

Bareed

9,589 16 101 12 698 827 9 3,520 37 4.0

34 Biddu 4,303 2 10 2 193 207 5 1,420 33 2.0

35 Hizma 3,962 9 28 5 329 371 9 1,286 32 3.0

36 'Anata 6,067 9 32 12 331 384 6 2,064 34 3.0

177

37 Al

'Eizariya 8,703 18 53 10 464 545 6 2,873 33 3.0

38 Abu Dis 6,141 28 119 22 647 816 13 2,307 38 5.0

39

As

Sawahira

ash

Sharqiya

3,282 15 24 3 189 231 7 1,088 33 3.0

40 Al

'Ubeidiya 7,142 3 10 1 287 301 4 2,205 31 2.0

41 Husan 3,872 4 9 10 138 161 4 1,295 33 2.0

42 Nahhalin 4,542 11 21 12 314 358 8 1,442 32 3.0

43 Za'tara 4,209 5 17 9 305 336 8 1,316 31 3.0

44 Jannatah 3,572 2 2 98 102 3 1,023 29 1.0

45 Tuqu' 6,047 1 11 1 267 280 5 1,727 29 1.0

46 Beit Fajjar 7,517 2 17 3 264 286 4 2,387 32 2.0

47 Surif 9,381 8 31 13 789 841 9 2,198 23 2.0

48 Beit

Ummar 9,331 25 55 12 799 891 10 3,066 33 3.0

49 Kharas 4,526 3 17 4 254 278 6 1,298 29 2.0

50 Beit Ula 7,160 3 9 3 343 358 5 2,180 30 1.0

51 Sa'ir 12,046 9 24 17 540 590 5 3,608 30 1.0

52 Halhul 15,475 32 93 33 1290 1448 9 5,215 34 3.0

53 Ash

Shuyukh 5,956 2 25 5 325 357 6 1,747 29 2.0

54 Tarqumiy

a 9,978 9 31 4 651 695 7 3,089 31 3.0

178

55 Beit Kahil 4,169 1 14 6 327 348 8 1,154 28 2.0

56 Idhna 13,062 18 47 8 759 832 6 4,045 31 3.0

57 Taffuh 6,877 1 15 1 245 262 4 2,014 29 1.0

58 Deir Samit 3,999 3 5 147 155 4 1,074 27 1.0

59 Bani

Na'im 13,194 15 36 3 579 633 5 4,151 31 2.0

60 Beit

'Awwa 5,557 3 4 4 194 205 4 1,684 30 1.0

61 Dura 19,514 53 156 31 1914 2154 11 6,355 33 4.0

62 Yatta 31,541 21 60 11 1267 1359 4 9,083 29 1.0

63 Adh

Dhahiriya 19,245 14 41 25 793 873 5 6,152 32 2.0

64 As Samu' 13,116 9 33 6 734 782 6 3,447 26 2.0

179

7.2.1.8 Geographical Factor (topography, catchment)

Scores of communities are distributed according to geographical factors as

follows in Table 7.9.

Table 7.9: Geographical factor score of each community

No

.

Lo

cality N

ame

% g

ravity

flow

No

. of catch

men

ts

Sco

re

No

.

Lo

cality N

ame

% g

ravity

flow

No

. of catch

men

ts

Sco

re

1 Silat al

Harithiya

50% to

75% 2 3.0 33

Ar Ram &

Dahiyat al

Bareed

<50% > 2 1.5

2 Al

Yamun

75% to

95% 2 3.5 34 Biddu

50% to

75% 2 3.0

3 Kafr Dan > 95% 2 4.0 35 Hizma 75% to

95% 2 3.5

4 Deir Abu

Da'if > 95% 1 5.0 36 'Anata

75% to

95% 2 3.5

5 Birqin 75% to

95% 2 3.5 37

Al

'Eizariya <50% > 2 1.5

6 Ya'bad 50% to

75% 2 3.0 38 Abu Dis <50% > 2 1.5

7 Qabatiya > 95% 1 5.0 39

As

Sawahira

ash

Sharqiya

50% to

75% 2 3.0

8 Arraba <50% > 2 1.5 40 Al

'Ubeidiya <50% > 2 1.5

9 Kafr Ra'i 50% to

75% > 2 2.0 41 Husan <50% > 2 1.5

10 Meithalu

n > 95% 1 5.0 42 Nahhalin <50% > 2 1.5

11 Jaba' 75% to

95% 2 3.5 43 Za'tara

50% to

75% 2 3.0

12 El Far'a

Camp > 95% 1 5.0 44 Jannatah <50% > 2 1.5

13 Tammun 50% to

75% 2 3.0 45 Tuqu' > 95% 2 4.0

180

14 Qaffin > 95% 2 4.0 46 Beit Fajjar 50% to

75% 2 3.0

15 'Attil > 95% 2 4.0 47 Surif 50% to

75% 2 3.0

16 Deir al

Ghusun

50% to

75% 2 3.0 48

Beit

Ummar <50% > 2 1.5

17 Bal'a 75% to

95% > 2 2.5 49 Kharas > 95% 1 5.0

18

'Asira ash

Shamaliy

a

50% to

75% 2 3.0 50 Beit Ula

50% to

75% > 2 2.0

19 'Awarta 50% to

75% 2 3.0 51 Sa'ir <50% > 2 1.5

20 Huwwara > 95% 1 5.0 52 Halhul 75% to

95% > 2 2.5

21 Beita > 95% 2 4.0 53 Ash

Shuyukh

75% to

95% 2 3.5

22 Jamma'in 50% to

75% 2 3.0 54 Tarqumiya <50% > 2 1.5

23 Aqraba 50% to

75% 2 3.0 55 Beit Kahil

50% to

75% 2 3.0

24 Qabalan > 95% 2 4.0 56 Idhna <50% > 2 1.5

25 'Azzun > 95% 2 4.0 57 Taffuh 50% to

75% 2 3.0

26 Biddya 50% to

75% 2 3.0 58 Deir Samit

75% to

95% > 2 2.5

27 Sinjil > 95% 2 4.0 59 Bani Na'im <50% > 2 1.5

28 Shuqba 50% to

75% > 2 2.0 60

Beit

'Awwa

50% to

75% > 2 2.0

29 Qibya <50% > 2 1.5 61 Dura 75% to

95% > 2 2.5

30

Al

Jalazun

Camp

75% to

95% 2 3.5 62 Yatta

50% to

75% > 2 2.0

31

Kharbath

a al

Misbah

50% to

75% 2 3.0 63

Adh

Dhahiriya <50% > 2 1.5

32 Beit

Liqya > 95% 1 5.0 64 As Samu'

75% to

95% 2 3.5

182

7.2.1.9 Political Issues

Scores of communities are distributed according to political issues as

follows in Table 7.10.

Table 7.10: political issues score of each community

No

.

Lo

cality

Nam

e

Settlem

ent

in

the catch

men

t

area

Po

litical lan

d

classification

s

Sco

re

No

.

Lo

cality

Nam

e

Settlem

ent

in

the catch

men

t

area

Po

litical lan

d

classification

s

Sco

re

1 Silat al

Harithiya NO A+B 4.0 33

Ar Ram &

Dahiyat al

Bareed

YES B+C 2.0

2 Al Yamun NO A+B 4.0 34 Biddu YES B+C 2.0

3 Kafr Dan NO A+B 4.0 35 Hizma YES B+C 2.0

4 Deir Abu

Da'if NO A+B 4.0 36 'Anata YES B+C 2.0

5 Birqin NO B 4.0 37 Al

'Eizariya YES B+C 2.0

6 Ya'bad YES B+C 2.0 38 Abu Dis YES B+C 2.0

7 Qabatiya NO B 4.0 39

As

Sawahira

ash

Sharqiya

YES B+C 2.0

8 Arraba NO A+B

+C 3.0 40

Al

'Ubeidiya NO A+C 3.0

9 Kafr Ra'i NO A 5.0 41 Husan NO B+C 3.0

10 Meithalun NO A 5.0 42 Nahhalin YES B+C 2.0

11 Jaba' NO B 4.0 43 Za'tara NO A+B

+C 3.0

12 El Far'a

Camp NO A 5.0 44 Jannatah NO B+C 3.0

13 Tammun NO A+B 4.0 45 Tuqu' YES B+C 2.0

14 Qaffin NO B+C 3.0 46 Beit Fajjar NO B 4.0

15 'Attil NO B+C 3.0 47 Surif NO B+C 3.0

16 Deir al

Ghusun NO B+C 3.0 48

Beit

Ummar YES B+C 2.0

17 Bal'a NO A+B

+C 3.0 49 Kharas NO B 4.0

18 'Asira ash

Shamaliya NO A+B 4.0 50 Beit Ula NO B 4.0

182

19 'Awarta YES B+C 2.0 51 Sa'ir NO B+C 3.0

20 Huwwara NO B+C 3.0 52 Halhul NO B+C 3.0

21 Beita NO B+C 3.0 53 Ash

Shuyukh NO B+C 3.0

22 Jamma'in NO B+C 3.0 54 Tarqumiy

a YES B+C 2.0

23 Aqraba NO B+C 3.0 55 Beit Kahil NO B+C 3.0

24 Qabalan NO B 4.0 56 Idhna NO B+C 3.0

25 'Azzun YES B+C 2.0 57 Taffuh NO A+B 4.0

26 Biddya YES B+C 2.0 58 Deir

Samit NO B+C 3.0

27 Sinjil NO A+B

+C 3.0 59

Bani

Na'im NO

A+B

+C 3.0

28 Shuqba NO B+C 3.0 60 Beit

'Awwa YES B+C 2.0

29 Qibya NO B+C 3.0 61 Dura NO A+B 4.0

30 Al Jalazun

Camp YES B+C 2.0 62 Yatta NO A+B 4.0

31 Kharbatha

al Misbah NO B+C 3.0 63

Adh

Dhahiriya NO A+B 4.0

32 Beit Liqya NO B+C 3.0 64 As Samu' NO A+B 4.0

7.2.2 Evaluation Measure for Each Community

According to the previous section and normalized weight in section ‎6.1 we

calculate the evaluation measure for each community as shown in Table

7.11.

183

Table 7.11: Calculate evaluation measure for each community

No.

Locality Name

Criteria Score for each community

Criteria Score × Normalize

weight (500)

Score for each

community (100)

Dem

ograp

hy

Water

con

sum

ptio

n/

Wastew

ater

pro

du

ction

Reu

sing

waste

water

Enviro

nm

enta

l factor

Op

eration

b

od

y

Risk fo

r In

du

strial

Waste

Socio

-

econ

om

ic facto

r

Geo

graph

ical facto

r

Po

litical

Issues

Normalize weight 12.5 10.37 7.62 14.48 13.11 9.76 13.11 8.38 10.67

1 Silat al

Harithiya 0.76 5 5 4 3.5 4 3.0 3 4.0 349.5 69.9

2 Al Yamun 1.41 4 5 3 4 3 2.0 4 4.0 320.5 64.1

3 Kafr Dan 0.47 3 5 4 2.5 4 3.0 4 4.0 320.5 64.1

4 Deir Abu Da'if 0.56 4 5 4 2.5 4 2.0 5 4.0 323.5 64.7

5 Birqin 0.47 4 3 3 3.5 4 4.0 4 4.0 323 64.6 6 Ya'bad 1.07 2 3 4 4 4 3.0 3 2.0 292 58.4

7 Qabatiya 1.61 4 4 5 4 1 2.0 5 4.0 320.5 64.1

8 Arraba 0.81 3 4 3 4 3 3.0 2 3.0 297.5 59.5

9 Kafr Ra'i 0.57 4 2 3 3.5 3 3.0 2 5.0 308.5 61.7

10 Meithalun 0.61 3 3 4 3.5 4 3.0 5 5.0 322.5 64.5

11 Jaba' 0.71 3 3 5 3.5 4 1.0 4 4.0 305.5 61.1 12 El Far'a Camp 0.52 2 5 5 2.5 5 3.0 5 5.0 337 67.4

13 Tammun 1.09 4 1 3 3.5 3 3.0 3 4.0 288.5 57.7

14 Qaffin 0.68 4 3 3 3.5 3 1.0 4 3.0 283 56.6

15 'Attil 0.58 4 5 4 3.5 3 3.0 4 3.0 325 65

184

16 Deir al Ghusun 0.53 5 5 3 3.5 3 4.0 3 3.0 325 65

17 Bal'a 0.47 4 2 4 3.5 4 2.0 3 3.0 314.5 62.9

18 'Asira ash Shamaliya

0.63 3 1 4 3.5 3 5.0 3 4.0 313 62.6

19 'Awarta 0.46 4 3 3 2.5 4 2.0 3 2.0 271 54.2

20 Huwwara 0.45 4 2 3 3.5 4 2.0 5 3.0 287 57.4

21 Beita 0.87 3 2 3 3.5 3 3.0 4 3.0 280.5 56.1 22 Jamma'in 0.66 3 2 4 3.5 1 2.0 3 3.0 251.5 50.3

23 Aqraba 0.78 5 2 5 3.5 4 1.0 3 3.0 317.5 63.5

24 Qabalan 0.61 1 2 4 3.5 4 2.0 4 4.0 278.5 55.7

25 'Azzun 0.69 5 2 4 3.5 4 3.0 4 2.0 312.5 62.5

26 Biddya 0.71 2 2 4 3.5 3 3.0 3 2.0 263.5 52.7

27 Sinjil 0.46 2 2 5 2.5 5 2.0 4 3.0 287.5 57.5 28 Shuqba 0.49 1 2 5 2.5 4 2.0 2 3.0 267.5 53.5

29 Qibya 0.49 3 2 4 2.5 4 3.0 2 3.0 283 56.6

30 Al Jalazun

Camp 0.62 5 3 4 2.5 5 2.0 4 2.0 299 59.8

31 Kharbatha al

Misbah 0.52 3 3 2 2.5 4 2.0 3 3.0 244.5 48.9

32 Beit Liqya 0.70 2 4 4 3.5 4 2.0 5 3.0 299.5 59.9

33 Ar Ram & Dahiyat al

Bareed 1.09 2.00 1.00 4.00 3.50 3.00 4.00 1.50 2.00 278 55.6

34 Biddu 0.72 4.00 3.00 4.00 3.50 3.00 2.00 3.00 2.00 279 55.8

35 Hizma 0.61 4.00 1.00 5.00 2.50 3.00 3.00 3.50 2.00 281 56.2

185

36 'Anata 1.83 4.00 1.00 4.00 2.50 2.00 3.00 3.50 2.00 272 54.4

37 Al 'Eizariya 1.64 5.00 1.00 3.00 3.50 4.00 3.00 1.50 2.00 298.5 59.7

38 Abu Dis 0.75 5.00 1.00 2.00 3.50 5.00 5.00 1.50 2.00 308.5 61.7

39 As Sawahira ash Sharqiya

0.67 5.00 1.00 3.00 3.50 5.00 3.00 3.00 2.00 292 58.4

40 Al 'Ubeidiya 1.00 2.00 1.00 2.00 3.50 5.00 2.00 1.50 3.00 252 50.4

41 Husan 0.48 2.00 3.00 5.00 2.50 5.00 2.00 1.50 3.00 291 58.2 42 Nahhalin 0.73 2.00 3.00 5.00 2.50 5.00 3.00 1.50 2.00 296.5 59.3

43 Za'tara 0.63 1.00 2.00 3.00 3.50 5.00 3.00 3.00 3.00 268 53.6

44 Jannatah 0.60 2.00 2.00 3.00 2.00 5.00 1.00 1.50 3.00 249.5 49.9

45 Tuqu' 0.91 2.00 2.00 5.00 3.50 4.00 1.00 4.00 2.00 272.5 54.5

46 Beit Fajjar 1.04 3.00 2.00 5.00 3.50 1.00 2.00 3.00 4.00 281.5 56.3

47 Surif 1.28 1.00 1.00 4.00 3.50 4.00 2.00 3.00 3.00 260 52 48 Beit Ummar 1.24 2.00 2.00 5.00 3.50 2.00 3.00 1.50 2.00 279.5 55.9

49 Kharas 0.54 1.00 1.00 4.00 3.50 4.00 2.00 5.00 4.00 261.5 52.3

50 Beit Ula 1.11 1.00 1.00 3.00 3.50 4.00 1.00 2.00 4.00 275.5 55.1

51 Sa'ir 1.64 1.00 2.00 5.00 4.00 2.00 1.00 1.50 3.00 265 53

52 Halhul 2.16 1.00 2.00 5.00 4.00 3.00 3.00 2.50 3.00 316 63.2

53 Ash Shuyukh 0.94 2.00 1.00 5.00 3.50 2.00 2.00 3.50 3.00 265.5 53.1

54 Tarqumiya 1.32 1.00 1.00 4.00 3.50 3.00 3.00 1.50 2.00 257.5 51.5 55 Beit Kahil 0.81 2.00 2.00 5.00 2.50 5.00 2.00 3.00 3.00 283.5 56.7

56 Idhna 1.82 2.00 1.00 3.00 4.50 3.00 3.00 1.50 3.00 283.5 56.7

57 Taffuh 1.19 1.00 2.00 5.00 3.50 5.00 1.00 3.00 4.00 288.5 57.7

58 Deir Samit 0.71 2.00 2.00 2.00 3.50 4.00 1.00 2.50 3.00 241.5 48.3

59 Bani Na'im 2.23 1.00 1.00 3.00 4.00 3.00 2.00 1.50 3.00 258.5 51.7

186

60 Beit 'Awwa 0.72 1.00 2.00 2.00 3.50 2.00 1.00 2.00 2.00 210 42

61 Dura 3.20 2.00 1.00 5.00 4.50 4.00 4.00 2.50 4.00 371.5 74.3

62 Yatta 5.00 1.00 1.00 4.00 4.00 2.00 1.00 2.00 4.00 299.5 59.9

63 Adh Dhahiriya 2.79 2.00 3.00 2.00 4.00 2.00 2.00 1.50 4.00 277.5 55.5 64 As Samu' 1.89 3.00 1.00 3.00 4.00 5.00 2.00 3.50 4.00 305 61

187

7.3 Setting Priorities

Communities were arranged based on the score of each community as

shown in Table 7.12.

Table 7.12: Setting priorities for communities

No

.

Lo

calit

y

Nam

e

Sco

re

No

.

Lo

calit

y

Nam

e

Sco

re

No

.

Lo

calit

y

Nam

e

Sco

re

1 Dura 74.3 23 Al Jalazun

Camp 59.8 45

Adh

Dhahiriya 55.5

2 Silat al

Harithiya 69.9 24 Al 'Eizariya 59.7 46 Beit Ula 55.1

3 El Far'a

Camp 67.4 25 Arraba 59.5 47 Tuqu' 54.5

4 'Attil 65 26 Nahhalin 59.3 48 'Anata 54.4

5 Deir al

Ghusun 65 27 Ya'bad 58.4 49 'Awarta 54.2

6 Deir Abu

Da'if 64.7 28

As Sawahira

ash Sharqiya 58.4 50 Za'tara 53.6

7 Birqin 64.6 29 Husan 58.2 51 Shuqba 53.5

8 Meithalun 64.5 30 Tammun 57.7 52 Ash

Shuyukh 53.1

9 Al Yamun 64.1 31 Taffuh 57.7 53 Sa'ir 53

10 Kafr Dan 64.1 32 Sinjil 57.5 54 Biddya 52.7

11 Qabatiya 64.1 33 Huwwara 57.4 55 Kharas 52.3

12 Aqraba 63.5 34 Beit Kahil 56.7 56 Surif 52

13 Halhul 63.2 35 Idhna 56.7 57 Bani Na'im 51.7

14 Bal'a 62.9 36 Qaffin 56.6 58 Tarqumiya 51.5

15 'Asira ash

Shamaliya 62.6 37 Qibya 56.6 59 Al 'Ubeidiya 50.4

16 'Azzun 62.5 38 Beit Fajjar 56.3 60 Jamma'in 50.3

17 Kafr Ra'i 61.7 39 Hizma 56.2 61 Jannatah 49.9

18 Abu Dis 61.7 40 Beita 56.1 62 Kharbatha al

Misbah 48.9

19 Jaba' 61.1 41 Beit Ummar 55.9 63 Deir Samit 48.3

20 As Samu' 61 42 Biddu 55.8 64 Beit 'Awwa 42

21 Beit Liqya 59.9 43 Qabalan 55.7

22 Yatta 59.9 44

Ar Ram &

Dahiyat al

Bareed

55.6

188

7.4 Sensitivity and Certainty Analysis

Weights of the criteria in this research work were identified through

qualitative interview with the intergovernmental agencies that form what so

called the Environmental Assessment Committee. These weights were

subjected to change of time and space due to various socio-economic

political and developmental changes and conditions. In order to conduct

sensitivity and certainty analysis of data related, a specific case, an excel

program relating the assigned criteria, and priorities were developed.

Program output would rearrange priorities according to the changes

occurred in the assigned criteria. Figure 7.1 shows the program structure.

Figure 7.1: Program Structure (Excel Program)

The program consists of four sheets, first rating for each criteria, second

normalized weights sheet which is input data for the program and it is an

adjustable sheet, the third and the fourth sheets are output data of the

program which represent the results.

Rating each

criteria Sheet

Program Structure

(Excel Program)

Normalized weights

Sheet

Evaluation measure

Sheet

Setting

up

priorities

Show the

rating for

each criterion

Adjustable

Show the

normalized

weights

Adjustable

Evaluation

measures for

each

community

based on

rating for each

Arranging

the

communiti

es based

on the

189

7.4.1 Program Implementation (Case Study):

For the sensitivity analysis a fewer alternatives were assumed, with four

main assumptions as follow:

A. Political Solution Occurred: The political conflict will affect the ease

of implementation of sanitation projects. Projects in areas which are

classified as (A and B only can get relatively faster implementation process

than those areas which classified as (C) since they are near settlements

which would delay obtaining permits from the Israeli side. Occurrence of a

political solution thus becomes a political factor without significance.

B. An Increase in Water Consumption: There is a positive relationship

between water consumption (therefore wastewater production) and the

priority of a sewer project. In this alternative the assumption of an increase

in water consumption was taken, by finding new water sources (wells,

additional quantities from Mekerot, seawater desalination plants, brackish

water desalination in Jordan Valley, etc.) then equitable distribution of

water quantities between the localities, thus the water consumption

/wastewater production becomes as a factor without significance.

C. Capacity Building: Sanitation projects need a strong and effective

operation body to manage such projects, due to the sensitivity of sanitation

projects and, high capital cost, operation and maintenance costs and efforts.

In this alternative the assumption that PWA, stakeholders and donors will

conduct capacity building for the municipalities benefiting from projects

and find qualified staffs in municipalities to manage sanitation projects was

taken. Thus this factor of operation body becomes without significance.

190

D. Control of Industrial Wastes: There is an impact of effluents from

industrial operations (stone cutting, olive press, textiles, etc) on the

effectiveness of the sanitation projects specifically on treatment plants. It is

assumed that direct connection of these wastes to the collection system will

not be allowed without a pre-treatment. In this alternative the assumption

that a control of industrial wastes was obtained by enactment of laws and

find mitigation measures to reduce the negative effect of industrial waste to

sanitation projects. Thus this factor of risk from industrial wastes becomes

without significance.

The sensitivity program was run for the selected alternative criteria as listed

in Annex B.

Table 7.13.below shows the setting of priorities for the top ten

communities.

Table 7.13: Setting priorities for the top ten communities according to

four various alternatives

No. of

Setting

priorities for

communities

Alternatives

A B C D

1 Dura Dura Dura Dura

2 Silat al

Harithiya El Far'a Camp El Far'a Camp Qabatiya

3 'Attil Halhul Silat al

Harithiya

Silat al

Harithiya

4 Deir al

Ghusun

Silat al

Harithiya

Deir Abu

Da'if 'Attil

5 'Azzun Meithalun Kafr Dan Deir al Ghusun

6 Abu Dis Yatta 'Attil Al Yamun

7 Aqraba Kafr Dan Deir al

Ghusun El Far'a Camp

8 El Far'a

Camp 'Attil Birqin Halhul

9 Halhul Deir Abu Da'if Meithalun Deir Abu Da'if

10 Bal'a 'Asira ash Aqraba Birqin

191

Shamaliya

The sensitivity program results shows that the setting priorities for

communities are changed when we changed the alternative criteria

(political solution occurred, increase in water consumption, capacity

building, and control of industrial wastes). Therefore PWA and

interested/related stakeholders need to expect future changes in identified

priorities depending on changes in alternative criteria (See Table ).

192

Chapter 8

Conclusione and Recommendayions

8.1 Conclusions

In light of the results, observations and outcomes from research, the

following are the main conclusions:

The current way they are selecting target areas to sanitation projects

are either based on the policies of the donor or on a non-scientific

method. So they do not take all the right criteria to make the right

decision.

Research shows that almost 56% of the population suffers from

problems of wastewater. The 78% believed that sanitation projects

would ease the financial burden resulting from the disposal of

wastewater.

As evidenced by the research, citizens prefer to use sewage networks

to discharge wastewater and they are willing to contribute to the

costs of creating sewage systems at a reasonable cost. Also, as

demonstrated in the research, 8% of citizens support the use of

treated wastewater in agriculture compared to 37% and 48% who

agree but with some preventive measures.

Communities that are expected to have a population of more than

10,000 people in 2030 are 97 communities. There are 33 community

containing sewage systems or in the design or implementation stage.

According to PWA Strategy, a sanitation sector will have been

193

developed in 33 communities and sanitation systems to 64

communities will have been found by 2030.

Multi-criteria decision analysis is an important tool in environmental

decision-making for formalizing and addressing the problem of

competing decision objectives. Characterized the MCDA

undemanding and accuracy method.

The criteria that affect the decision-making process in the sanitation

sector the most are: Demography, Water consumption / Wastewater

production, Reusing wastewater, Environmental factor, Operation

body, Risk of Industrial Waste, Socio-economic factor, Geographical

factor, and Political Issues.

The top ten communities which most need to solve the problem of

sewage, ordered according to importance, are: Dura, Silat al

Harithiya, El Far'a Camp, 'Attil, Deir al Ghusun, Deir Abu Da'if,

Birqin, Meithalun, Al Yamun, Kafr Dan, and Qabatiya

8.2 Recommendations

The recommendations listed herein support the future studies and address

the following issues regarding the management of the sanitation sector:

The Palestinian Water Authority should start to identify target areas

to sanitation projects by taking all the right criteria to make right

decision and oblige donors on it.

We recommend the Palestinian Water Authority use the MCDA

method to Identify the Setting Priorities of the Sanitation Sector in

the West Bank

194

The Palestinian Water Authority should benefit from the

mathematical relationships and MCDA that have been working in

this research in order to set priorities of the sanitation sector.

The Palestinian Water Authority should start to plan to develop

sanitation sectors in 33 communities and find sanitation systems to

64 communities by 2030.

The Palestinian Water Authority should start putting a long-term

plan and a five-year plan that would include serving 20 communities

whose population is of more than 10 thousand people every 5 years.

The Palestinian Water Authority should start preparing feasibility

studies and master plans that contain estimated costs to the

communities whose population is more than 10 thousand people and

do not contain sewage systems.

195

Referances

– Accorsi R, Apostolakis GE, Zio E. 1999a. Prioritizing stakeholder

concerns in environmental risk management. Journal of Risk

Research 2:11–29.

– Accorsi R, Zio E, Apostolakis GE. 1999b. Developing utility

functions for environmental decision-making. Prog Nucl Energy

34:387–411.

– Alawneh, M. and Al-Sa’ed, R. M. (1997). Review on water quality in

Palestine. Groundwater and surface water. Proceedings of the 2nd

Conference on Energy and Environment, An-Najah University,

Nablus, Palestine.

– Al-Rashdan D, Al-Kloub B, Dean A, Al-Shemmeri T. 1999. Theory

and methodology environmental impact assessment and ranking the

environmental projects in Jordan. European Journal of Operational

Research 118:30–45.

– Ananda J, Herath G. 2003. Incorporating stakeholder values into

regional forest planning: A value function approach. Ecological

Economics 45:75–90.

– Apostolakis GE. 2001. Assessment and management of

environmental risks. In: Linkov I, Palma-Oliveira J, editors.

Assessment and management of environmental risks. Boston (MA),

USA: Kluwer. p 211–220.

– Arvai J, Gregory R. 2003. Testing alternative decision approaches for

identifying cleanup priorities at contaminated sites. Environ Sci

196

Technol 37:1469–1476.

– Ary, D., Jacobs, L. C., & Razavieh, A., 1996, Introduction to research

in education. Fort Worth, TX: Harcourt Brace College Publishers.

– Baker D, Bridges D, Hunter R, Johnson G, Krupa J, Murphy J,

Sorenson K. 2001.

– Bardos P, Lewis A, Nortcliff S, Matiotti C, Marot F, Sullivan T. 2002.

CLARINET report: Review of decision support tools for

contaminated land management, and their use in Europe. Vienna:

Austrian Federal Environment Agency.

– Bartlett, J., Kotrlik, J., & Higgins, C., Information Technology,

Learning, and Performance Journal, Vol. 19, No. 1, Spring 2001.

– Bell M, Hobbs BF, Ellis H. 2003. The use of multi-criteria decision-

making methods in the integrated assessment of climate change:

Implications for IA practitioners. Socio-Economic Planning Sciences

37:289–316.

– Belton V, Steward T. 2002. Multiple criteria decision analysis: An

integrated approach. Boston (MA), USA: Kluwer.

– Belton, V. and Stewart, T., 2002. Multiple Criteria Decision

Analysis: An Integrated Approach. Boston, MA: Kluwer Academic

Publishers, Boston/Dordrecht/London.

– Bonano EJ, Apostolakis GE, Salter PF, Ghassemi A, Jennings S. 2000.

Application of risk assessment and decision analysis to the

evaluation, ranking and selection of environmental remediation

alternatives. J Hazard Mater 71:35–57.

197

– Bose U, Davey AM, Olson DL. 1997. Multi-attribute utility methods

in group decision-making: Past applications and potential for

inclusion in GDSS.

– Brown B, Neil-Adger W, Tompkins E, Bacon P, Shim D, Young K.

2001. Trade-off analysis for marine protected area management.

Ecological Economics 37:417–434.

– Consortium for Risk Evaluation with Stakeholder Participation

(CRESP). 1999. Peer review of the U.S. Department of Energy use of

risk in its prioritization process.

– Corporate Project 7 Team. 2003. Assessment report. Corporate project

7: A cleanup program driven by risk-based end states. Washington

DC: U.S. Department of Energy.

– Deschaine LM, Breslau B, Ades MJ, Selg RA, Saaty TL. 1998.

Decision support software to optimize resource allocation: Theory

and case history. Society for Computer Simulation, Simulators

International XV. Boston (MA), USA: Society for Modeling

Simulations. p 139–144.

– Dodgson, John, Michael Spackman Alan Pearman, and Lawrence

Phillips, 2000. Department of Transport, Local Government and the

Regions, (DTLR). ―Multicriteria Analysis Manual.‖ National

Economic Research Associates, London. December, 2000. Available

on line at http://www.communities.gov.uk/index.asp?id=1142253.

Viewed November 18, 2006.

– Doumpos, Michael, 2002. Multicriteria Decision Aid Classification

198

Methods. Kluwer Academic Publishers, Secaucus, NJ.

– Edwards W. 1977. How to use multi-attribute utility measurement

for social decision-making. IEEE (Inst Electr Electron Eng) Trans

Biomed Eng 7:326–340.

– Ehrhardt J, Shershakov VM. 1996. Real-time on-line decision

support systems (RODOS) for off-site emergency management

following a nuclear accident.

– Final Report. Luxemburg: European Commission.

– Florig HK, Morgan MG, Morgan KM, Jenni KE, Fischoff B,

Fischbeck PS, DeKay ML. 2001. A deliberative method for ranking

risks (I): Overview and test bed development. Risk Analysis 21:913–

922.

– Focht W, DeShong T, Wood J, Whitaker K. 1999. A protocol for the

elicitation of stakeholders’ concerns and preferences for

incorporation into policy dialogue.

– Gijzen H.J. (2001a). Aerobes, anaerobes and phototrophs: a winning

team for wastewater management. Water Science and Technology,

44(8): 123-132.

– Gomez-Limon JA, Arriaza M, Riesgo L. 2003. An MCDM analysis of

agricultural risk aversion. European Journal of Operational

Research 151:569–585.

– Gregory R, Failing L. 2002. Using decision analysis to encourage

sound deliberation: Water use planning in British Columbia, Canada.

Journal of Policy Analysis and Management 21:492–499.

199

– Gregory R, Fischhoff B, Thorne S, Butte G. 2003. A multi-channel

stakeholder consultation process for transmissionderegulation.

Energy Policy 31:1291–1299.

– Gregory R, Keeney RL. 1994. Creating policy alternatives using

stakeholder values. Management Science 40:1035–1048.

– Gregory R, McDaniels T, Fields D. 2001. Decision aiding, not dispute

resolution: Creating insights through structured environmental

decisions. Journal of Policy Analysis and Management 20:415–432.

– Gregory R, Wellman K. 2001. Bringing stakeholder values into

environmental policy choices: A community-based estuary case

study. Ecological Economics 39:37–52.

– Grelk B, Kloeber JM, Jackson JA, Deckro RF, Parnell GS. 1998.

Quantifying CERCLA using site decision maker values. Remediation

8:87–105.

– Grelk BJ. 1997. A CERCLA-based decision support system for

environmental remediation strategy selection [thesis]. Colorado

Springs (CO): U.S. Department of the Air Force, Air University, Air

Force Institute of Technology.

– Guidebook to decision-making methods. Washington DC: U.S.

Department of Energy. WSRC-IM-2002-00002.

– Haimes, Yacov Y., 2005. Risk Modeling, Assessment, and

Management. John Wiley & Sons Incorporated, Hoboken, NJ.

– Hamalainen RP, Kettunen E, Ehtamo H. 2001. Evaluating a

framework for multistakeholder decision support in water resources

200

management. Group Decision and Negotiation 10:331–353.

– Hamalainen RP, Lindstedt M, Sinkko K. 2000. Multi-attribute risk

analysis in nuclear emergency management. Risk Analysis 20:455–

468.

– Hartman DH, Goltz MN. 2001. Application of the analytic hierarchy

process to select characterization and risk-based decision-making

and management methods for hazardous waste sites. Environmental

Engineering and Policy 3:1–7.

– Hayashi K. 2000. Multi-criteria analysis for agricultural resource

management: A critical survey and future perspectives. European

Journal of Operational Research 122:486–500.

– Hobbs BF, Meier P. 2000. Energy decisions and the environment: A

guide to the use of multi-criteria methods. Boston (MA), USA:

Kluwer.

– In: Proceedings of the third workshop in the environmental policy and

economics workshop series: Economic research and policy concerning

water use and watershed management.Washington DC:

Environmental Law Institute. p 1–24.

– International Journal of Management Sciences 25:691–706.

– Janssen R. 2001. On the use of multi-criteria analysis in

environmental impact assessment in the Netherlands. Journal of

Multi-Criteria Decision Analysis 10:101–109.

– Janssen, R. (1992). Multiobjective Decision Support for

201

Environmental Management. Dordrecht, Kluwer Academic

Publishers.

– Jenni KE, Merkhofer MW, Williams C. 1995. The rise and fall of a

risk-based priority system: Lessons from DOE’s environmental

restoration priority system. Risk Analysis 15:397–410.

– Joerin F, Musy A. 2000. Land management with GIS and multi-

criteria analysis. International Transactions in Operational Research

7:67–78.

– Kane Driscoll SB, Wickwire WT, Cura JJ, Vorhees DJ, Butler CL,

Moore DW, Bridges TS. 2002. A comparative screening-level

ecological and human health risk assessment for dredged material

management alternatives in New York /New Jersey Harbor.

International Journal of Human and Ecological Risk Assessment

8:603–626.

– Kangas J, Kangas A, Leskinen P, Pykalainen J. 2001. MCDM methods

in strategic planning of forestry on state-owned lands in Finland:

Applications and experiences. Journal of Multi-Criteria Decision

Analysis 10:257–271.

– Keefer D, Kirkwood CW, Corner JL. 2002a. Perspective on decision

analysis applications, 1990–2001. Decision Analysis 1: (online

supplement).

– Keefer D, KirkwoodCW, Corner JL. 2002b. Summary of decision

analysis applications in the operations research literature, 1990–

2001. Tucson (AZ), USA: Technical Report Department of Supply

202

Chain Management, Arizona State University.

– Keisler JM, Sundell RC. 1997. Combining multi-attribute utility and

geographic information for boundary decisions: An application to

park planning. Journal of Geographic Information and Decision

Analysis 1:101–118.

– Kwak SJ, Yoo SH, Kim TY. 2001. A constructive approach to air-

quality valuation in Korea. Ecological Economics 38:327–344.

– Lahdelma, R., P. Salminen, et al. (2000). "Using Multicriteria

Methods in Environmental Planning and Management."

Environmental Management 26(6): 595–605.

– Larichev OI, Olson DI. 2001. Multiple criteria analysis in strategic

siting problems. Boston (MA), USA: Kluwer. Levy J, Hipel K,

Kilgour DM. 2000. Using environmental indicators to quantify the

robustness of policy alternatives to uncertainty. Ecol Model 130:79–

86.

– Linkov I, Sahay S, Seager TP, Kiker G, Bridges T. 2005. Multi-

criteria decision analysis: Framework for applications in remedial

planning for contaminated sediments. In: Proth JM, Levner E,

Linkov I, editors. Strategic management of marine ecosystems.

Amsterdam, The Netherlands: Kluwer.

– Linkov I, Varghese A, Jamil S, Seager TP, Kiker GA, Bridges TS.

2004. Multi-criteria decision analysis: Framework for applications

in remedial planning for contaminated sites. In: Linkov I, Ramadan

203

A, editors. Comparative risk assessment and environmental decision

making. Amsterdam, The Netherlands: Kluwer. p 15–54.

– Linkov, I., F. K. Satterstrom, et al. (2006). "From comparative risk

assessment to multi criteria decision analysis and adaptive

management: Recent developments and applications." Environment

International 32: 1072–1093.

– Linkov, I., Satterstrom, F.K., Kiker, G., Seager, T.P., Bridges. T.,

Gardner, K.H., Rogers, S.H., Belluck, D.A., Meyer, A., 2006.

“Multicriteria Decision Analysis: A Comprehensive Decision

Approach for Management of Contaminated Sediments.” Risk

Analysis, Vol. 26, No. 1.

– Mahmoud N, Zimmo O., Zeeman G., Lettinga G. and Gijzen H (2004).

Perspectives for Integrated Sewage Management in Palestine/ the

Middle East. Water 21.

– Mahmoud N. (2002). Anaerobic pre-treatment of sewage under low

temperature (15oC) conditions in an integrated UASB-digester

system. PhD. Thesis, Wageningen University, The Netherlands.

– Mahmoud N., Amarneh M., Al-Sa’ed R., Zeeman G., Gijzen H. And

Lettinga G. (2003). Sewage characterization as a tool for the

application of anaerobic treatment in Palestine. Environmental

Pollution, 126(1): 115-122.

204

– Males RM. 2002. Beyond expected value: Making decisions under risk

and uncertainty. RMM Technical Services, under contract to

Planning and Management Consultants Ltd. Prepared for U.S. Army

Corps of Engineers, Institute for Water Resources. IWR Report 02-R-

4. www.iwr.usace.army.mil/ iwr/pdf/02r4bey_exp_val.pdf. Accessed

24 December 2012.

– Marttunen M, Hamalainen RP. 1995. Decision analysis interviews in

environmental impact assessment. European Journal of Operational

Research 87:551–563.

– Matsatsinis NF, Samaras AP. 2001. MCDA and preference

disaggregation in group decision support systems. European Journal

of Operational Research 130:414–429.

– McDaniels TL, Gregory RS, Fields D. 1999. Democratizing risk

management: Successful public involvement in local water

management decisions. Risk Analysis 19:497–510.

– McDaniels TL, Roessler C. 1998. Multi-attribute elicitation of

wilderness preservation benefits: A constructive approach.

Ecological Economics 27:299–312.

– McDaniels TL. 1995. Using judgment in resource management: A

multiple objective analysis of a fisheries management decision.

Operations Research 43:415–426.

– Mendoza GA, Anderson AB, Gertner GZ. 2002. Integrating multi-

criteria analysis and GIS for land condition assessment: Part 2—

Allocation of military training areas. Journal of Geographic

205

Information and Decision Analysis 6:17–30.

– Miettinen P, Hamalainen RP. 1997. How to benefit from decision

analysis in environmental life cycle assessment (LCA). European

Journal of Operational Research 102:279–294.

– Morgan MG, Fischhoff B, Bostrom A, Atman C J. 2002. Risk

communication. Boston (MA), USA: Cambridge University Press.

– Morgan MG, Florig HK, DeKay ML, Fischbeck PS. 2000.

Categorizing risks for risk ranking. Risk Analysis 20:49–58.

– National Research Council [NRC]. 1999. New directions in water

resources planning for the U.S. Army Corps of Engineers.

Washington DC: National Academy Press.

– New Brunswick (NJ), USA: CRESP.

– Niemczynowics J. (1997). The water profession and agenda 21. Wat.

Qual. Int. 2: 9-11.

– Palestinian Environmental Law (7), (1999).

– Palestinian National Authority (1999) Environmental Law Number 7.

Palestine Liberation Organization, PNA, Albireh, Palestine.

– Palestinian Water Authority (2003), WasteWater Management Plan.

– Palestinian Water Law (3), 2002.

– Palestinian-Israeli Agreements (2003).

– Parnell GS, Frimpon M, Barnes J, Kloeber JM Jr, Deckro RF, Jackson

JA. 2001.

– Pavlikakis GE, Tsihrintzis VA. 2003. A quantitative method for

206

accounting human opinion, preferences, and perceptions in

ecosystem management. J Environ Manag 68:193–205.

– PCBS, Palestinian Central Bureau for Statistics (2007). Population

census for Palestine, Albireh, West Bank, Palestine

– PECDAR, (2001) Palestinian Water Strategic Planning Study.

– Pereira AG, Quintana SC. 2002. From technocratic to participatory

decision support systems: Responding to the new governance

initiatives. Journal of Geographic Information and Decision Analysis

6:95–107.

– Peterson D, Silsbee D, Schmoldt D. 1994. A case study of resources

management planning with multiple objectives and projects.

Environ Manag 18:729–742.

– Prato T. 2003. Multiple-attribute evaluation of ecosystem

management for the Missouri River system. Ecological Economics

45:297–309.

– PWA data, 2012

– PWA, (2000) National Water Plan.

– Ralston BE, Jackson JA, Kloeber JM Jr, Deckro RF. 1996.

Development of a decision support system for the Department of

Energy selection of waste remediation technologies. Wright Patterson

Air Force Base, USA: Center for Modeling, Simulation, and Analysis.

Technical report 96-02:1–123.

– Ramanathan R. 2001. A note on the use of the analytical hierarchy

process for environmental impact assessment. J Environ Manag

207

63:27–35.

– Rauscher HM, Lloyd FT, Loftis DL, Twery MJ. 2000. A practical

decision-analysis process for forest ecosystem management. Comput

Electron Agric 27:195–226.

– Regan, H. M., F. W. Davis, et al. (2007). "Comprehensive criteria for

biodiversity evaluation in conservation planning." Biodiversity

Conservation 16: 2715–2728.

– Rogers M, Bruen M. 1998. Choosing realistic values of indifference,

preference and veto thresholds for use with environmental criteria

within ELECTRE. European Journal of Operational Research

107:542–551.

– Saaty, & Thomas L. (1996). Mathematics and Multicriteria Decision

Making. Mathematics Awareness week. University of Pittsburgh.

– Safety risk analysis of an innovative environmental technology. Risk

Analysis 21:143–155.

– Schmoldt D, Peterson D, Silsbee D. 1994. Developing inventory and

monitoring programs based on multiple objectives. Environ Manag

18:707–727.

– Schmoldt D, Peterson D. 2001b. Strategic and tactical planning for

managing national park resources. In: Name, editors. The analytical

hierarchy process in natural resource and environmental decision-

making. Amsterdam, The Netherlands: Kluwer. p 67–79.

– Schmoldt DL, Kangas J, Mendoza GA, Pesonen M. 2001. The

analytic hierarchy process in natural resource and environmental

208

decision making. Amsterdam, The Netherlands: Kluwer.

– Schmoldt DL, Peterson DL. 2001a. Efficient group decision making

in workshop settings. In: Name, editors. The analytical hierarchy

process in natural resource and environmental decision-making.

Amsterdam, The Netherlands: Kluwer. P 97–114.

– Seppala J, Basson L, Norris GA. 2002. Decision analysis frameworks

for life-cycle impact assessment. J Ind Ecol 5:45–68.

– Sharifi MA, van den Toorn W, Rico A, Emmanuel M. 2003.

Application of GIS and multicriteria evaluation in locating

sustainable boundary between Tunari National Park and

Cochabamba City (Bolivia). Journal of Multi-Criteria Decision

Analysis 11:151–164.

– Siddiqui M, Everett J, Vieux B. 1996. Landfill siting using

geographic information systems: A demonstration. Journal of

Environmental Engineering 122:515–523.

– Simon M, Pascoe S. 1999. A review of applications of multiple

criteria decisionmaking techniques to fisheries. Marine Resource

Economics 14:41–63.

– Stahl CH, Cimorelli AJ, Chow AH. 2002. A new approach to

environmental decision analysis: Multi-criteria integrated resource

assessment (MIRA). Bulletin of Science, Technology and Society

22:443–459.

209

– Stahl CH. 2003. Multi-criteria integrated resource assessment

(MIRA): A new decision analytic approach to inform

environmental policy analysis [thesis]. Wilmington (DE), USA:

University of Delaware.

– Steiguer JE, Liberti L, Schuler A, Hansen B. 2003. Multi-criteria

decision models for forestry and natural resources management:

An annotated bibliography.

– Store R, Kangas J. 2001. Integrating spatial multi-criteria evaluation

and expert knowledge for GIS-based habitat suitability modeling.

Landsc Urban Plann 55:79–93.

– Timmerman TJ, Kloeber JM Jr, Jackson JA, Deckro RF. 1996.

Selecting remediation technologies through a technical risk index:

An application of multi-attribute utility theory. Wright Patterson Air

Force Base, USA: Center for Modeling, Simulation, and Analysis.

Technical report 96–01.

– Tran L, Knight CG, O’Neill R, Smith E, Ritters K, Wickham J. 2002.

Environmental assessment fuzzy decision analysis for integrated

environmental vulnerability assessment of the mid-atlantic region.

Environ Manag 29:845–859.

– U.S. Army Corps of Engineers (USACE). 1983. The economic and

environmental principles and guidelines for water and related land

resources implementation. Engineering Regulation (ER) 105-2-100.

210

– U.S. Army Corps of Engineers (USACE). 2003a. Environmental

operating principles and implementation guidance. www.hq.usace.

army.mil/CEPA/7%20Environ%20Prin%20web%20site/Page1.html.

Accessed 20 December 2012.

– U.S. Army Corps of Engineers (USACE). 2003b. Planning civil

works projects under the environmental operating principles.

Circular 1105-2-404. www.usace.army.mil/inet/usace-docs/eng-

circulars/ec1105-2-404/entire.pdf. Accessed 18 December 2012.

– U.S. Department of Energy (USDOE). 1998. Guidelines for risk-

based prioritization of DOE Activities. Washington, DC: USDOE.

DOE-DP-STD-3023–98.

– U.S. Department of Energy (USDOE). 2003. Washington, DC:

USDOE-RESRAD Environmental Assessment Division.

http://web.ead.anl.gov/resrad/home2. Accessed 14 December 2012.

– U.S. Environmental Protection Agency (USEPA). 2000. Framework

for responsible environmental decision-making (FRED): Using life

cycle assessment to evaluate preferability of products. Washington,

DC: USEPA. EPA/600/R-00/095.

– U.S. Environmental Protection Agency (USEPA). 2002. Consistency

and transparency in determination of USEPA anticipated ozone

designations. Special Review. Washington, DC: USEPA, Office of

Inspector General. Report 2002-S-00016.

– UNEP/GPA (2000). Strategy options for sewage management to

protect the marine environment. Report produced by IHE-Delft for

211

UNEP/GPA, November 2000. pp102.

– Vaillancourt K, Waaub JP. 2002. Environmental site evaluation of

waste management facilities embedded into EUGENE model: A

multi-criteria approach. European Journal of Operational Research

139:436–448.

– Voogd, H. (1983). Multicriteria Evaluation for Urban Regional

Planning. Great Britain, London.

– Wakeman JS. 2003. Milltown reservoir sediment/Clark Fork River

superfund sitefocused feasibility study.

ww.epa.gov/region8/superfund/sites/mt/milltowncfr/home.html.

Accessed 24 December 2012.

– Washington, DC: U.S. Department of Agriculture, Forest Service.

General technical report NE-307.

– Wastewater Departments in PWA data, 2012

– Whitaker K, Focht W. 2001. Expert modeling of environmental

impacts. OPS Special Issue: Environmental Policy in Oklahoma

10:179–186.

– WHO (1996). Water supply and sanitation sector monitoring. Report

1996: ―Sector status as of 31 December 1994‖. In WHO/EOS/96.15.

Geneva, Switzerland.

– WHO, (2006). Guideline for drinking-water quality. World Health

Organization, Geneva, Switzerland, 1: 52-53.

– Yatsalo, B., G. A. Kiker, et al. (2007). "Application of Multicriteria

Decision Analysis Tools to Two Contaminated Sediment Case

212

Studies." Integrated Environmental Assessment and Management 3(2):

223–233.

– Yoe C. 2002. Trade-off analysis planning and procedures guidebook.

http://www.iwr.usace.army.mil/iwr/pdf/tradeoff.pdf. Accessed 24

December 2012.

213

ANNEX

214

ANNEX A

CITIZENS QUESTIONNAIRE

215

الرحيمبسم هللا الرحمن

اؿزج١ب ػ اط١ دي ضع ا١ب اؼبصخ اوغف اوذ ف اضفخ اغغث١خ

ف ضؿخ ا١ب اج١ئخ جبؼخ اجبح ثؼ عؿبخ بجـز١غ ذوي ػ كبصح ابجـز١غ( ثغاء جغاعػ)٠م اجبدش

زذض٠ض ( MCDA)رذ١ امغاعاد زؼضصح اؼب١٠غ )بخ اط١خ ثبزؼب غ ؿطخ ا١ب افـط١١خ، د١ش رزض اغؿ

ثئكغاف اضوزع غا دضاص، ػ أ أ رـب ظا اغؿبخ ف ( أ٠بد ضغ لطبع اوغف اوذ ف اضفخ اغغث١خ

١ب ثى صلخ د رشف١ف لبو ا١ب اؼبصخ ف فـط١، ظا ز اإلجبثخ ػ ج١غ األؿئخ از ؿزطغح ف ظا االؿزج

.ى جؼ٠ الىغ

طوغ : اجؾ. 3........................... ىب اـى . 2:.............. اؼغ. 1

أض

: ػضص أفغاص األؿغح از رؼ١ق ف١ب. 5أسغ زؼط أػؼة : اذبخ االجزبػ١خ. 4

......................

كبصاد و١خ أ جبؼخ إػضاص صب رؼ١ اثزضائ أ :اذبخ ازؼ١١خ. 6

ػ١ب

عثخ ث١ذ ظف اؼعاػخ اوبػخ اذغف ط ػ اؼ ػب : اؼ. 7

غ١غ طه

ج١ض زؿظ ؿ١ئ :اضغ االلزوبص ؼبئخ. 8

ؼبعى ال عأ افك افك جضا األؿئخ اغلؼبعى

ثلضح

انحور األول: انوضغ انائي

1.1 ا١ب همضاع ا١ب ازبدخ

ىوبف١خ ىبفخ اؿزشضابر

1.2

مضاع ا١ب اشووخ أج

اإلؿزشضا اؼ وبف١خ رـض

برىدبج

1.3 مضاع ا١ب اشووخ أج

اؼعاػخ وبف١خ

1.4

مضاع ا١ب اشووخ أج

اإلؿزشضابد اوبػ١خ ازجبع٠خ

وبف١خ

1.5 أذ عاى ػ سضبد ا١ب امضخ

ه

3 ---------------ف الزبء 3 ---------------١ب ف او١ف ثلى رمغ٠ج مضاع إؿزالن 1.6

216

.)ى كغ(

1.7

ا١ب ازبدخ ه وبصعب الدظبرى ػ

.......................................................................................................:.دب١ب

...........................................................................................................................

.................................................

رضا انواطنينو انحور انثاني: انوضغ انحاني نهياه انؼادية

2.1 رم ثزوغ٠ف ا١ب اؼبصخ ف

كجىبد اوغف اوذ

2.2 أذ عاى ػ سضبد اوغف

اوذ امضخ ه

2.3 ف ج١ض اوغف اوذ لطبع

طمزه

2.4 رشضغ ػ١بد ازشن ا١ب

اؼبصخ أل ع اغلبثخ

2.5

اؼبصخ از رم ا١بب الدظبرى ػ ػ١بد روغ٠ف

............................................................................ثبؿزشضاب:.

...........................................................................................................................

.................................................

آثر انياه انؼادية ػهى انواطنين: انحور انثانث

3.1 اؼبصخ ؿجك أ رضغعد ا١ب

ثلى جبكغ

3.2 رؼب ا١ب اؼبصخ امبصخ

اـزطبد اإلؿغائ١١خ

3.3

رؼزمض أ ػ١خ ازشن ا١ب

اؼبصخ ثؼض رفغ٠غ اذفغ االزوبه١خ

أ كجىبد اوغف اوذ رز

ثلى هذ١خ

3.4 ٠ز ازشن ا١ب اؼبصخ ثبمغة

ف طمزه اغاػ

3.5 ٠ز ازشن ا١ب اؼبصخ ثبمغة

ف طمزه األكجبع اجبربد

3.6

رس ١ب الغة. : اجبع() رؼب ب ثـجت ا١ب اؼبصخأ البو ازب١خ

. دلغاد ضبعح . عائخ وغ٠خ ازلبع األغاى سوهب اؼ٠خ ب.

غ١غ . ال ٠جض لبو ف١ضب ا١ب اؼبصخ جغ٠بب ف الاعع. . فئغا جغطا

طه: ..................................

3.7

و١ف رغ ضغ طمزى اوذ بد١خ لىخ ا١ب

..........................................................................................:.اؼبصخ

...........................................................................................................................

.................................................

اننواحي االقتصادية واالجتاػية: انحور انرابغ

4.1 رىفخ ازغ اىؼت ا١ب ف

ج١ض طمزه

4.2 ٠جض ص٠ زغاوخ ػ١ه ز١جخ

رؼ٠ضن ثب١ب

4.3 رىفخ رشوه ا١ب اؼبصخ ف

ج١ضح طمزه

4.4 ٠جض ص٠ زغاوخ ػ١ه ز١جخ

رشوه ا١ب اؼبصخ

217

4.5 ض إؿزؼضاص إلؿزشضا ا١ب اؼبجخ

ف اؼعاػخ مبث عؿ

4.6

أدضصذ ا١ب اؼبصخ طغق ازشن

ب لبو اجزبػ١خ ث١ ااط١

ف طمزه

4.7 أدضصذ ا١ب اؼبصخ طغق ازشن

ب لبو ث١ ااط١ اجض٠خ

وػي انواطنين، وحالت انتوػية: انحور انخايس

5.1 ا١ب اؼبصخ رؼزجغ أوضغ

دـبؿ١خ جزغااض١غ

5.2

د لىخ ا١ب اؼبصخ ؿف ٠ؼ٠ض

عفب١خ اـىب ٠غفغ ـز

ؼ١لز

5.3

د لىخ ا١ب اؼبصخ ؿف ٠ى

آصغ ث١ئ هذ إجزبػ

إ٠جبث ػ ااط١

5.4 ضاد أ ذبضغاد ػ ر ػمض

ا١ب اؼبصخ

5.5 رزذضس ادأ ثؿزغ ادلغر رػ٠غ

ػ ا١ب اؼبصخ لبوب

5.6

دضغد ف صبئم أ إػال

رفؼ٠ ػ ا١ب اؼبصخ لبوب

طغق ؼبجزب

القضايا المؤسساتية: انحور انسادس

6.1 بن ازب لج اؤؿـبد

اذى١خ ثمطبع ا١ب اؼبصخ

6.2 رضاس ف اب اظبئف ف بن

اؤؿـبد اذى١خ

6.3

بن ازب لج اؤؿـبد اغ١غ

دى١خ اظبد األ١خ ثمطبع

ا١ب اؼبصخ

6.4

بن رضاس ف اب اظبئف ث١

اؤؿـبد اذى١خ اظبد

األ١خ

6.5

أز عاض ػ أصاء مض سضبد

روغ٠ف ا١ب اؼبصخ ف طمزه

)ثض٠بد، جبؾ لغ٠خ، جبؾ

سضبد لزغوخ، ....(

218

المحور السابع: المشاركة باتخاذ القرارات

طرق تصريف المياه العادمة ومعالجتها وإعادة استخدامها: ( أ

دفغ ازوبه١خ كجىبد هغف هذ فض ذ لىخ ا١ب اؼبصخ: رأ األع ازب١خ

غ١غ طه: بجخ ؼ١خ ذطبد ؼ

..............................................................................................................................

أ كجىبد ـزمخ زوغ٠فب. غ كجىبد اوغف اوذ. :بع رؤ٠ض روغ٠ف ١ب األط

ال أػ. ال ٠ز روغ٠فب.

:أافك أافك ثلضح ب عأ٠ه ف ػ١خ إػبصح اؿزشضا ا١ب اؼبصخ ف اؼعاػخ ثؼض ؼبجزب

طه أػبعى

.......................................................................................................................................

...........................

التكاليف: ( ب

اؼبئخ ـزؼضح ـبخ ف د لىخ ا١ب اؼبصخ )رىفخ إلبء كجىبد هغف هذ ذطبد

ال، طه ثـجت ؼ، مضاع اـبخ: ................... ؼبجخ(

.................................................................

:اؼبئخ ـزؼضح ـبخ ف صفغ وفخ او١بخ ازلغ١ لجىبد اوغف اوذ ذطبد اؼبجخ

ال، طه ثـجت ؼ، مضاع اـبخ: ........................ / كغ

.................................................................

أفض اطغق از ٠ى إرجبػب أج رغط١خ رىب١ف رلغ١ كجىبد ذطبد اوغف اوذ: ب

...............................

.......................................................................................................................................

...........................

219

إدارة قطاع المياه العادمة: ( ج

:ؿطخ جصح اج١ئخ ؿطخ ا١ب أ ا٢ر رفض أ ٠م ثئصاعح لطبع اوغف اوذ

خ اػاعاد، بطا:جخ لزغو ػاعح اوذخ ػاعح اذى اذ

......................................................................................

.......................................................................................................................................

...........................

اجبؾ امغ٠خ اجض٠بد سضبد روغ٠ف ا١ب اؼبصخ: ٠مضثزأ ا٢ر رفض أ ٠م

ؿطخ جصح اج١ئخ ؿطخ ا١ب كغوبد امطبع اشبم جبؾ سضبد لزغوخ

جخ ذ١خ، بطا: ..... ػاعح اذى اذ

.......................................................................................................................................

...........................

ألع اإلجغاءاد از رفض إرجبػب ػض إصاعح ا١ب اؼبصخ: ب ا

.........................................................................

.......................................................................................................................................

...........................

اقتراحات: ( د

بد١خ إصاع٠خ رظ١١خ الزغادبد رذج أ رؤسظ ثؼ١ االػزجبع ذ لىخ ا١ب اؼبصخ

...............................................

.......................................................................................................................................

...........................

الزغادبد رذج أ رؤسظ ثؼ١ االػزجبع ذ لىخ ا١ب اؼبصخ ف فـط١ ثلى ػب

....................................................

.......................................................................................................................................

...........................

220

ANNEX B

EQA TERMS OF REFERENCE (TOR)

221

222

223

224

225

226

227

228

229

230

231

ANNEX C

POPULATION PROJECTION

232

Locality

Nam

e

Locality

code

Male

Fem

ale

Total

No. o

f Housin

g

Units

No. o

f Build

ings

No. o

f

Estab

lishm

ents

Averag

e Size

of H

ouseh

old

No. o

f

Househ

old

s

جغؿ از

ا

Actu

al

Populatio

n 2

007

Actu

al

Populatio

n 1

997

Com

men

t No.*

Actu

al Gro

wth

-Rate

(2007-1

997)

Actu

al Gro

wth

-Rate

(2007-1

997)

Pro

jected

Populatio

n 2

010

Pro

jected

Populatio

n 2

020

Pro

jected

Populatio

n 2

030

Jenin Gov.

Zububa 10005 958 976 1,93

4 1,564 1,934 ػثث 359 5.4 62 406 425

2.15 2.15 2,061 2,549 3,152

Rumma

na 10010

1,61

2

1,52

8

3,14

0 بخ 596 5.3 68 579 642 2,483 3,140 ع

2.38 2.38 3,369 4,261 5,388

Ti'innik 10015 477 523 1,00

0 806 1,000 رؼه 178 5.6 23 192 216

2.18 2.18 1,067 1,324 1,642

At

Tayba 10020

1,11

1

1,04

4

2,15

5 1,757 2,155 اط١جخ 416 5.2 72 477 487

2.06 2.06 2,291 2,810 3,447

Arabbu

na خ 160 5.1 40 168 186 810 400 410 10025 630 810 ػغث

2.54 2.54 873 1,123 1,444

Al

Jalama 10030

1,03

4

1,02

6

2,06

0 خ 413 5 84 402 490 1,697 2,060 اج

1.96 1.96 2,183 2,650 3,217

Silat al

Harithi

ya

10035 4,87

7

4,54

5

9,42

2

1,86

7 1,600 244 5.6 1,669

ؿ١خ

اذبعص١خ9,422 7,246

2.66 2.66 10,194 13,256 17,236

As

Sa'aida ؼب٠ضح 13 5.4 5 21 14 70 38 32 10040 ـ 94 70 ا

-2.90 0.50 71 75 79

'Anin 10045 1,93

4

1,75

7

3,69

1 2,739 3,691 ػب١ 658 5.6 93 565 793

3.03 3.03 4,037 5,440 7,330

233

'Arrana 10050 1,03

7 959

1,99

6 اخ 367 5.4 70 397 415 1,579 1,996 ػغ

2.37 2.37 2,141 2,707 3,422

Deir

Ghazal

a

10055 456 439 895 203 175 51 5.1 177 ص٠غ

غؼاخ895 629

3.59 3.59 995 1,416 2,014

Faqqu'a 10060 1,77

2

1,69

5

3,46

7 ػخ 689 5 145 716 753 6,517 4,953 3,764 2.78 2.78 1 2,635 3,467 فم

Khirbet

Suruj 10070 32 24 56 9 19 9 6.2 9

سغثخ

ؿغط56 35

4.81 4.81 64 103 165

Al

Yamun 10080

8,30

2

8,08

1

16,3

83

3,50

1 2,672 485 5.5 2,965 ا١ب

16,38

3

12,25

5 2.95 2.95 17,874 23,894 31,943

Umm

ar

Rihan

10085 197 173 370 76 66 3 5.7 65 أ

اغ٠ذب370 275

3.01 3.01 404 544 732

Kafr

Dan 10095

2,65

1

2,49

7

5,14

8

1,08

7 3,766 5,148 وفغ صا 981 5.2 188 1,048

3.18 3.18 5,654 7,729 10,565

Khirbet

'Abdall

ah al

Yunis

10105 84 54 138 32 40 1 4.2 33

سغثخ

ػجض هللا

ا١ؾ

138 104

2.87 2.87 150 199 264

Dhaher

al

Malih

10115 115 83 198 40 45 14 5 40 ظغ

ابخ198 160

2.15 2.15 211 261 323

Barta'a

ash

Sharqiy

a

10120 2,19

7

1,97

9

4,17

6 873 894 440 5.1 817

ثغطؼخ

الغل١خ4,176 2,814 2 4.03 4.03 4,701 6,976 10,353

Al

'Araqa 10125

1,12

9

1,03

2

2,16

1 1,564 2,161 اؼغلخ 367 5.9 70 387 431

3.29 3.29 2,381 3,290 4,546

Al 10135 18 14 32 5 3 0 6.4 5 اج١ال 32 27

1.71 1.71 34 40 47

234

Jameela

t

د

Beit

Qad 10140 731 716

1,44

7 3,424 2,355 1,619 3.82 3.82 3 995 1,447 ث١ذ لبص 265 5.5 71 308 296

Tura al

Gharbi

ya

10145 491 427 918 245 272 60 4.7 197 طعح

اغغث١خ918 817

1.17 1.17 951 1,068 1,200

Tura

ash

Sharqiy

a

10150 84 90 174 37 43 14 5 35 طعح

الغل١خ174 133

2.72 2.72 189 247 323

Al

Hashim

iya

10155 519 532 1,05

1 696 1,051 ابك١خ 186 5.7 17 202 205

4.21 4.21 1,189 1,796 2,712

Nazlat

ash

Sheikh

Zeid

10165 371 333 704 164 135 24 5.9 119

ؼخ

ال١ز

ػ٠ض

704 537

2.74 2.74 764 1,001 1,312

At

Tarem 293 369 اطغ 70 5.3 10 78 83 369 185 184 10170

2.33 2.33 395 498 627

Khirbet

al

Muntar

al

Gharbi

ya

10175 11 11 22 6 6 2 3.7 6

سغثخ

اطبع

اغغث١خ

22 25

-1.27 0.50 22 23 25

Jenin 10180 19,7

66

19,2

38

39,0

04

9,21

5 5,392

3,1

00 ج١ 7,609 5.1

39,00

4

27,77

5 4 3.45 3.45 43,186 60,646 85,164

Jenin

Camp 10185

5,10

4

5,26

7

10,3

71

2,31

8 1,196 262 5.1 2,039

ش١

ج١

10,37

1 8,991

1.44 1.44 10,825 12,486 14,403

235

Jalbun 10190 1,22

5

1,16

5

2,39

0 1,836 2,390 جج 463 5.2 157 500 523

2.67 2.67 2,587 3,367 4,383

'Aba 10195 105 99 204 37 36 7 5.7 36 122 204 ػبثب

5.28 5.28 238 398 666

Khirbet

Mas'ud 10200 26 21 47 14 11 0 4.3 11

سغثخ

ـؼص

)ػغاق

اضاع(

47 46

0.22 0.22 47 48 49

Khirbet

al

Muntar

ash

Sharqiy

a

10205 3 4 7 9 5 2 3.5 2

سغثخ

اطبع

الغل١خ

7 13

-6.00 0.50 7 7 8

Kafr

Qud 10210 531 612

1,14

3 2,712 1,863 1,279 3.83 3.83 5 785 1,143 وفغ لص 215 5.3 49 211 239

Deir

Abu

Da'if

10215 2,77

7

2,79

5

5,57

2

1,05

0 1,101 338 6 935

ص٠غ أث

ضؼ١ف5,572 3,897

3.64 3.64 6,203 8,869 12,681

Birqin 10220 2,86

3

2,82

2

5,68

5

1,25

9 4,344 5,685 ثغل١ 1,115 5.1 271 1,001

2.73 2.73 6,163 8,065 10,555

Umm

Dar 429 557 أ صاع 108 5.2 41 138 115 557 280 277 10225

2.65 2.65 602 782 1,015

Al

Khuljan 358 509 اشجب 88 5.8 45 113 99 509 250 259 10230

3.58 3.58 566 804 1,144

Wad ad

Dabi' 10235 213 198 411 72 71 3 6 69

اص

اضجغ411 272

4.21 4.21 465 703 1,062

Dhaher

al

'Abed

10240 189 174 363 67 71 5 5.6 65 ظغ

اؼجض363 273

2.89 2.89 395 526 699

Zabda 10245 487 457 944 194 174 14 5.1 184 1,812 1,365 1,028 2.88 2.88 6 711 944 ػثضح

236

Ya'bad 10265 6,86

1

6,77

9

13,6

40

3,01

7 ٠ؼجض 2,486 5.5 499 2,284

13,64

0

10,62

5 2.53 2.53 14,701 18,873 24,229

Kufeirit 10275 1,24

8

1,15

8

2,40

6 1,801 2,406 وف١غد 433 5.6 84 409 528

2.94 2.94 2,624 3,506 4,684

Imreiha 10285 199 224 423 87 94 13 5 85 314 423 إغ٠ذخ

3.02 3.02 463 623 839

Umm

at Tut 738 989 أ ازد 169 5.9 35 182 195 989 494 495 10295

2.97 2.97 1,080 1,447 1,939

Ash

Shuhad

a

10300 865 883 1,74

8 1,280 1,748 الضاء 319 5.5 92 344 363

3.17 3.17 1,919 2,621 3,579

Jalqam

us 10305

1,00

1 991

1,99

2 1,375 1,992 جمؽ 343 5.8 74 362 391

3.78 3.78 2,226 3,225 4,673

Al

Mugha

yyir

10310 1,23

0

1,19

0

2,42

0 1,649 2,420 اغ١غ 404 6 58 393 478

3.91 3.91 2,715 3,985 5,848

Al

Mutilla 193 295 اطخ 57 5.2 12 57 57 295 147 148 10315

4.33 4.33 335 512 783

Bir al

Basha 10320 692 615

1,30

7 260 232 14 6 217

ث١غ

اجبكب1,307 962

3.11 3.11 1,433 1,947 2,645

Al

Hafira 10335 30 28 58 15 13 0 4.5 13

اذف١غح

)دف١غح

ػغاث(

58 57

0.17 0.17 58 59 60

Qabatiy

a 10340

9,73

9

9,45

8

19,1

97

3,90

5 لجبط١خ 3,495 5.5 679 3,393

19,19

7

14,52

4 7 2.83 2.83 20,873 27,588 36,465

Arraba 10370 4,96

6

4,95

4

9,92

0

2,06

6 18,452 14,088 10,756 2.74 2.74 8 7,574 9,920 ػغاثخ 1,811 5.5 407 1,669

Telfit 10385 119 119 238 74 41 32 4.1 58 1,128 573 292 7.00 7.00 9 121 238 رف١ذ

Mirka 10395 825 786 1,61

1 1,145 1,611 غوخ 284 5.7 52 251 288

3.47 3.47 1,785 2,511 3,533

Wadi 10400 63 60 123 21 26 2 7.2 17 اص 123 87

3.52 3.52 136 193 273

237

Du'oq صػق

Fahma

al

Jadida

10401 179 190 369 71 77 8 5.7 65 فذخ

اجض٠ضح369 258

3.64 3.64 411 588 840

Raba 10405 1,57

9

1,56

6

3,14

5 2,270 3,145 عاثب 548 5.7 140 558 598

1

0 3.31 3.31 3,468 4,805 6,657

Al

Mansur

a

10410 94 79 173 31 36 1 6 29 او

عح173 111

4.54 4.54 198 308 480

Misliya 10415 1,23

2

1,15

6

2,38

8 1,658 2,388 ـ١خ 440 5.4 79 429 491

3.72 3.72 2,664 3,837 5,527

Al

Jarba 54 63 اجغثب 13 4.8 10 19 15 63 30 33 10430

1.55 1.55 66 77 90

Az

Zababi

da

10435 1,89

1

1,77

4

3,66

5

1,31

0 2,844 3,665 اؼثبثضح 826 4.4 268 844

2.57 2.57 3,955 5,096 6,568

Fahma 10445 1,28

5

1,20

1

2,48

6 1,796 2,486 فذخ 432 5.8 66 451 440

3.30 3.30 2,741 3,794 5,251

Az

Zawiya 517 770 اؼا٠خ 111 6.9 15 140 136 770 366 404 10460

4.06 4.06 868 1,292 1,925

Kafr

Ra'i 10465

3,70

4

3,66

0

7,36

4

1,55

9 1,296 228 5.3 1,385

وفغ

عاػ7,364 5,758

2.49 2.49 7,928 10,139 12,967

Al

Kufeir 48 43 اىف١غ 8 5.4 2 22 20 43 22 21 10485

-1.09 0.50 44 46 48

Sir 10495 377 367 744 179 192 22 5.4 137 585 744 ه١غ 1

1 2.43 2.43 800 1,017 1,293

'Ajja 10500 2,58

3

2,47

2

5,05

5 3,790 5,055 ػجخ 897 5.6 178 875 998

2.92 2.92 5,511 7,351 9,804

'Anza 10505 941 932 1,87

3 1,477 1,873 ػؼح 395 4.7 53 476 499

2.40 2.40 2,011 2,551 3,234

238

Sanur 10510 2,07

4

1,99

3

4,06

7 3,139 4,067 هبع 698 5.8 119 735 832

2.62 2.62 4,396 5,695 7,379

Ar

Rama 664 964 اغاخ 172 5.6 14 181 206 964 468 496 10515

3.80 3.80 1,078 1,565 2,272

Meithal

un 10520

3,59

6

3,35

9

6,95

5

1,43

2 5,159 6,955 ١ض 1,258 5.5 249 1,258

3.03 3.03 7,607 10,255 13,825

Al

Judeida 10565

2,37

7

2,36

1

4,73

8

1,01

7 3,592 4,738 اجض٠ضح 923 5.1 157 953

2.81 2.81 5,148 6,791 8,958

al

'Asa'asa 10585 232 232 464 62 57 7 7.3 64

اؼوبػ

هخ464 343

3.07 3.07 508 687 930

Al

'Attara 10590 608 551

1,15

9 790 1,159 اؼطبعح 199 5.8 36 228 228

3.91 3.91 1,300 1,908 2,799

Siris 10600 2,49

3

2,39

3

4,88

6 3,714 4,886 ؿ١غ٠ؾ 812 6 123 800 939

2.78 2.78 5,305 6,979 9,181

Jaba' 10605 4,31

1

4,18

1

8,49

2

1,76

4 6,409 8,492 ججغ 1,498 5.7 293 1,485

2.85 2.85 9,240 12,243 16,222

Al

Fandaq

umiya

10615 1,74

9

1,65

2

3,40

1 689 556 88 5.7 596

افضل

٠خ3,401 2,476

3.23 3.23 3,741 5,138 7,058

Silat

adh

Dhahr

10625 2,93

7

2,85

7

5,79

4

1,22

3 996 265 6.1 946

ؿ١خ

اظغ5,794 4,609

2.31 2.31 6,206 7,801 9,807

Total

Jenin

Gov.

130,

328

126,

291

256,

619

55,2

76

44,35

0

11,

133 5

47,43

7

يجوع

يحافظة

جنين

256,6

19

192,7

13 3.01 279,832 374,234 502,050

Tubas Gov.

Bardala 50420 816 821 1,63

7 1,139 1,637 ثغصخ 271 6 17 261 286

3.69 3.69 1,825 2,623 3,770

'Ein el

Beida 50450 599 564

1,16

3 205 185 17 5.9 197

ػ١

اج١ضب1,163 781

4.06 4.06 1,311 1,952 2,906

239

Kardala 50455 166 141 307 52 39 3 6.3 49 210 307 وغصخ 1

2 3.87 3.87 344 503 735

Ibziq 50490 108 103 211 37 36 1 6.6 32 43 211 إثؼ٠ك

17.2

4

17.2

4 340 1,669 8,188

Salhab 50525 24 21 45 8 8 6 9 5 53 45 ؿذت

-1.62 0.50 46 48 50

'Aqqab

a 50535

3,42

6

3,12

2

6,54

8

1,20

7 4,385 6,548 ػمبث 1,127 5.8 193 1,033

4.09 4.09 7,385 11,028 16,468

Tayasir 50550 1,30

0

1,18

9

2,48

9 1,731 2,489 ر١بؿ١غ 467 5.3 49 420 496

3.70 3.70 2,776 3,991 5,739

Al

Farisiya 154 151 افبعؿ١خ 29 5.2 0 28 28 151 70 81 50551

-0.20 0.50 153 161 169

Al

'Aqaba 85 104 اؼمجخ 23 4.5 5 27 20 104 50 54 50560

2.04 2.04 110 135 165

Ath

Thaghr

a

187 546 اضغغح 100 5.5 16 121 126 546 261 285 50575

11.3

1

11.3

1 753 2,199 6,419

Al

Malih 149 370 ابخ 58 6.4 0 57 57 370 180 190 50580

9.52 9.52 486 1,207 2,997

Tubas 50610 8,13

5

8,01

9

16,1

54

3,50

8 طثبؽ 2,933 5.5 699 2,657

16,15

4

11,61

7 3.35 3.35 17,833 24,798 34,483

Kashda 50650 34 37 71 10 12 5 8.9 8 29 71 ولضح

9.37 9.37 93 227 557

Khirbet

Yarza 50656 22 17 39 13 13 5 4.9 8

سغثخ

٠غػح39 23

5.42 5.42 46 77 131

Ras al

Far'a 50670 360 346 706 140 109 24 5.6 125

عاؽ

افبعػخ706 506

3.39 3.39 780 1,089 1,519

El Far'a

Camp 50700

2,85

6

2,85

6

5,71

2

1,14

8 706 162 5.5 1,048

ش١

افبعػخ5,712 4,152

3.24 3.24 6,286 8,647 11,896

Khirbet

ar Ras

al

50720 110 69 179 30 30 0 5.1 35

سغثخ

اغاؽ

األدغ

179 62

11.1

8

11.1

8 246 710 2,051

240

Ahmar

Wadi al

Far'a 50740

1,41

0

1,32

0

2,73

0 516 553 119 5.8 474

اص

افبعػخ2,730 1,691

4.91 4.91 3,152 5,088 8,215

Tammu

n 50755

5,40

2

5,39

3

10,7

95

2,23

5 ط 1,965 5.5 329 1,911

10,79

5 7,540

3.65 3.65 12,022 17,212 24,642

Khirbet

'Atuf 50790 91 80 171 34 37 20 6.1 28

سغثخ

ػبطف171 76

8.45 8.45 218 491 1,104

Khirbet

Humsa 50871 64 69 133 22 22 0 6 22

سغثخ

دوخ133 149

1

3 -1.13 0.50 135 142 149

Total

Tubas

Gov.

25,5

33

24,7

28

50,2

61

10,1

78 8,265

1,6

70 5.6 9,004

يجوع

يحافظة

طوباس

50,26

1

34,76

2 3.76 6.25 56,340 83,997 132,355

Tulkarem Gov.

Akkaba 10025

0 192 254 ػىبثخ 41 6.2 18 69 46 254 131 123

2.84 2.84 276 365 483

Qaffin 10029

0

4,34

5

4,04

2

8,38

7

1,78

3 6,440 8,387 لف١ 1,587 5.3 236 1,474

2.68 2.68 9,079 11,823 15,398

Nazlat

'Isa

10033

0

1,20

8

1,12

6

2,33

4 482 431 50 5.3 440

ؼخ

ػ١ـ2,334 1,844

2.38 2.38 2,505 3,171 4,013

An

Nazla

ash

Sharqiy

a

10034

5 803 711

1,51

4 313 263 23 5.5 277

اؼخ

الغل١خ1,514 1,214

2.23 2.23 1,618 2,017 2,516

Baqa

ash

Sharqiy

a

10035

0

2,10

3

1,99

8

4,10

1 923 768 144 5.4 762

ثبلخ

الغل١خ4,101 3,159

1

4 2.64 2.64 4,435 5,757 7,474

An

Nazla

10035

5 174 166 340 81 82 12 4.6 74

اؼخ

اؿط340 306

1.06 1.06 351 390 433

241

al

Wusta

An

Nazla

al

Gharbi

ya

10038

0 484 453 937 177 187 17 6 156

اؼخ

اغغث١خ937 652

3.69 3.69 1,045 1,501 2,158

Zeita 10042

5

1,38

2

1,47

0

2,85

2 2,315 2,852 ػ٠زب 560 5.1 86 506 630

2.11 2.11 3,036 3,740 4,608

Seida 10044

0

1,52

3

1,40

6

2,92

9 2,267 2,929 ه١ضا 568 5.2 79 601 624

2.60 2.60 3,163 4,087 5,280

'Illar 10047

5

3,15

5

3,03

5

6,19

0

1,36

2 5,068 6,190 ػالع 1,142 5.4 173 1,198

2.02 2.02 6,573 8,028 9,805

'Attil 10048

0

4,58

7

4,45

1

9,03

8

2,00

8 7,661 9,038 ػز١ 1,720 5.3 373 1,672

1.67 1.67 9,497 11,205 13,218

Deir al

Ghusun

10053

0

4,19

8

4,04

4

8,24

2

1,77

2 1,313 237 5.2 1,578

ص٠غ

اغو8,242 6,969

1.69 1.69 8,667 10,251 12,123

Al

Jarushi

ya

10054

5 462 470 932 213 191 33 5.1 183

اجبع

ك١خ932 668

3.39 3.39 1,030 1,437 2,005

Al

Masquf

a

10055

5 124 136 260 52 50 5 5.5 47

اـم

فخ260 156

5.24 5.24 303 505 842

Bal'a 10057

0

3,35

2

3,25

2

6,60

4

1,40

4 5,373 6,604 ثؼب 1,202 5.5 262 1,375

2.08 2.08 7,026 8,635 10,614

Iktaba 10059

5

1,38

9

1,27

6

2,66

5 1,456 2,665 إوزبثب 463 5.8 49 551 490

6.23 6.23 3,195 5,848 10,704

Nur

Shams

Camp

10062

0

3,28

2

3,19

7

6,47

9

1,33

6 761 179 5.3 1,216

ش١

ع

كؾ

6,479 5,814

1.09 1.09 6,693 7,458 8,312

242

Tulkar

m

Camp

10063

5

5,28

5

5,35

6

10,6

41

2,09

7 1,146 245 5.4 1,962

ش١

طىغ

10,64

1 9,948

0.68 0.68 10,858 11,615 12,424

Tulkar

m

10064

5

25,8

17

25,4

83

51,3

00

12,2

37 7,143

2,9

21 طىغ 9,877 5.2

51,30

0

39,97

7

1

5 2.53 2.53 55,285 70,944 91,038

Anabta 10066

5

3,62

5

3,70

4

7,32

9

1,78

8 6,032 7,329 ػجزب 1,440 5.1 274 1,460

1

6 1.97 1.97 7,770 9,441 11,471

Kafr al

Labad

10069

0

2,06

3

2,01

1

4,07

4 3,076 4,074 وفغ اجض 693 5.9 99 747 757

1

7 2.85 2.85 4,432 5,870 7,775

Kafa 10071

0 257 404 وفب 75 5.4 7 77 87 404 186 218

4.63 4.63 463 727 1,143

Al

Haffasi

10071

5 76 81 157 31 32 3 5.8 27

اذفبه

157 118

2.90 2.90 171 228 303

Ramin 10073

0 889 917

1,80

6 1,547 1,806 عا١ 353 5.1 42 369 390

1.56 1.56 1,892 2,209 2,578

Far'un 10073

5

1,54

9

1,55

1

3,10

0 2,351 3,100 فغػ 633 4.9 83 507 752

2.80 2.80 3,368 4,441 5,856

Shufa 10076

0

1,14

1

1,05

3

2,19

4 1,650 2,194 كفخ 400 5.5 97 465 475

1

8 2.89 2.89 2,390 3,178 4,225

Khirbet

Jubara

10078

0 143 150 293 67 64 12 4.7 63

سغثخ

ججبعح293 241

1.97 1.97 311 378 459

Saffarin 10079

5 764 760 ؿفبع٠ 136 5.6 16 149 153 760 383 377

-0.05 0.50 771 811 852

Beit

Lid

10080

0

2,49

6

2,49

8

4,99

4

1,01

1 4,354 4,994 ث١ذ ١ض 947 5.3 150 954

1.38 1.38 5,204 5,969 6,846

Ar Ras 10081

5 373 540 اغاؽ 96 5.6 9 106 111 540 265 275

3.77 3.77 603 874 1,265

Kafr

Sur

10084

5 565 552

1,11

7 263 262 63 5 222

وفغ

هع1,117 924

1.92 1.92 1,182 1,429 1,728

Kur 10087 239 262 وع 54 4.9 8 72 69 262 139 123

0.92 0.92 269 295 324

243

0

Kafr

Zibad

10089

5 522 556

1,07

8 261 251 34 5.2 208

وفغ

ػ٠جبص1,078 962

1.14 1.14 1,115 1,250 1,401

Kafr

Jammal

10090

0

1,22

7

1,19

7

2,42

4 510 441 68 5.3 455

وفغ

جبي2,424 1,882

2.56 2.56 2,615 3,368 4,338

Kafr

'Abbus

h

10091

5 721 736

1,45

7 346 355 43 5.2 281

وفغ

ػجف1,457 1,096

2.89 2.89 1,587 2,110 2,804

Total

Tulkar

em

Gov.

79,8

06

78,1

82

157,

988

35,1

01

26,09

2

6,1

50 5.3

29,93

8

يجوع

يحافظة

طونكرو

157,9

88

127,3

45 2.50 168,779 211,355 266,817

Nablus Gov.

Bizzari

ya

15066

0

1,18

0

1,07

2

2,25

2 1,587 2,252 ثؼاع٠خ 380 5.9 84 442 413

3.56 3.56 2,501 3,549 5,037

Burqa 15068

0

1,87

4

1,79

6

3,67

0 2,987 3,670 ثغلخ 733 5 134 792 925

1

9 2.08 2.08 3,904 4,797 5,893

Yasid 15069

5

1,06

1

1,02

3

2,08

4 1,690 2,084 ٠به١ض 349 6 56 391 430

2.12 2.12 2,219 2,737 3,375

Beit

Imrin

15070

5

1,40

3

1,41

8

2,82

1 616 471 101 5.3 528

ث١ذ

إغ٠2,821 2,121

2.89 2.89 3,073 4,087 5,436

Nisf

Jubeil

15074

5 195 199 394 104 90 17 4.7 83

وف

جج١394 373

0.55 0.55 401 423 447

Sabasti

ya

15076

5

1,30

6

1,30

8

2,61

4 2,143 2,614 ؿجـط١خ 515 5.1 95 523 615

2.01 2.01 2,775 3,384 4,128

Ijnisiny

a

15077

0 413 505 إجـ١ب 106 4.8 15 140 135 505 252 253

2.03 2.03 536 656 802

Talluza 15077

5

1,20

6

1,16

9

2,37

5 1,977 2,375 طػح 429 5.5 72 440 507

1.85 1.85 2,509 3,015 3,621

An 15078 800 745 1,54 1,223 1,545 ابلعح 290 5.3 44 278 327

2.36 2.36 1,657 2,094 2,645

244

Naqura 5 5

Al

Badhan

15080

5

1,27

3

1,21

2

2,48

5 1,786 2,485 اجبطا 447 5.6 87 441 514

3.36 3.36 2,744 3,818 5,312

Deir

Sharaf

15081

0

1,22

2

1,23

8

2,46

0 578 446 85 5.3 464

ص٠غ

كغف2,460 2,035

1.91 1.91 2,604 3,148 3,805

'Asira

ash

Shamal

iya

15082

0

3,82

7

3,72

9

7,55

6

1,84

5 1,367 276 5.1 1,490

ػو١غح

الب١خ7,556 5,724

2.82 2.82 8,212 10,841 14,310

An

Nassari

ya

15082

5 785 800

1,58

5 304 286 60 6.1 259

اوبع

٠خ1,585 999

4.72 4.72 1,820 2,888 4,582

Zawata 15083

5 953 922

1,87

5 1,401 1,875 ػارب 360 5.2 59 317 459

2.96 2.96 2,046 2,739 3,665

Al

'Aqraba

niya

15084

0 494 507

1,00

1 196 204 28 6.4 157

اؼمغثب

٠خ1,001 703

2

0 3.60 3.60 1,113 1,585 2,256

Qusin 15085

5 866 843

1,70

9 1,279 1,709 له١ 300 5.7 60 319 339

2.94 2.94 1,864 2,491 3,328

Beit Iba 15086

0

1,59

0

1,56

0

3,15

0 2,410 3,150 ث١ذ إ٠جب 628 5 134 626 847

2.71 2.71 3,413 4,462 5,832

Beit

Hasan

15086

5 563 558

1,12

1 206 174 42 5.9 190

ث١ذ

دـ1,121 879

2.46 2.46 1,206 1,538 1,961

Beit

Wazan

15087

5 518 539

1,05

7 267 199 27 5.1 207

ث١ذ

ػ1,057 826

2.50 2.50 1,138 1,456 1,864

'Ein

Beit el

Ma

Camp

15088

0

2,03

2

1,94

7

3,97

9 810 404 72 5.2 769

ش١

ػ١ ث١ذ

ابء

3,979 3,715

0.69 0.69 4,062 4,350 4,660

'Ein 15088 ػ١ 57 5.9 16 75 76 335 171 164 335 146

8.66 8.66 430 986 2,263

245

Shibli 5 كج

'Azmut 15091

0

1,31

8

1,33

2

2,65

0 2,009 2,650 ػؼط 449 5.9 61 453 553

2.81 2.81 2,880 3,798 5,010

Nablus 15092

0

63,6

88

62,4

44

126,

132

32,0

18

10,41

5

7,7

87 5

25,10

4 بثؾ

126,1

32

99,20

4

2

1 2.43 2.43 135,555 172,350 219,132

'Askar

Camp

15093

0

5,80

8

5,79

9

11,6

07

2,32

7 1,096 268 5.5 2,114

ش١

ػـىغ

11,60

7 9,372

2.16 2.16 12,376 15,328 18,983

Deir al

Hatab

15093

5

1,09

3

1,12

0

2,21

3 430 329 30 6 368

ص٠غ

اذطت2,213 1,665

2.89 2.89 2,410 3,203 4,258

Sarra 15095

0

1,31

4

1,24

8

2,56

2 2,133 2,562 هغح 463 5.5 82 422 499

1.85 1.85 2,707 3,251 3,905

Salim 15095

5

2,48

8

2,57

4

5,06

2 3,749 5,062 ؿب 841 6 117 779 923

3.05 3.05 5,539 7,479 10,099

Balata

Camp

15096

0

7,48

9

7,75

8

15,2

47

3,17

3 1,512 416 5.5 2,759

ش١

ثالطخ

15,24

7

13,01

4 1.60 1.60 15,989 18,732 21,946

'Iraq

Burin

15097

5 401 367 768 161 170 13 5.2 147

ػغاق

ثع٠768 568

3.06 3.06 841 1,137 1,537

Tell 15099

0

2,18

7

2,15

7

4,34

4 3,496 4,344 ر 778 5.6 152 770 869

2.20 2.20 4,636 5,761 7,159

Beit

Dajan

15100

0

1,75

3

1,73

2

3,48

5 740 613 98 5.4 640

ث١ذ

صج3,485 2,647

2.79 2.79 3,785 4,983 6,560

Rujeib 15101

0

2,17

1

2,03

1

4,20

2 2,888 4,202 عج١ت 770 5.5 120 631 869

3.82 3.82 4,702 6,842 9,955

Kafr

Qallil

15102

5

1,23

5

1,21

6

2,45

1 1,838 2,451 وفغ ل١ 423 5.8 16 338 475

2.92 2.92 2,672 3,563 4,752

Furush

Beit

Dajan

15103

0 417 352 769 177 167 50 6.4 121

فغف

ث١ذ

صج

769 855

-1.05 0.50 781 821 862

Madam

a

15105

0 872 882

1,75

4 1,223 1,754 بصب 325 5.4 41 289 387

3.67 3.67 1,954 2,803 4,020

246

Burin 15108

0

1,15

5

1,15

4

2,30

9 1,898 2,309 ثع٠ 429 5.4 70 472 539

1.98 1.98 2,449 2,979 3,624

Beit

Furik

15109

0

5,24

7

5,09

2

10,3

39

2,22

9 1,982 384 5.2 1,999

ث١ذ

فع٠ه

10,33

9 7,672

3.03 3.03 11,307 15,238 20,535

'Asira

al

Qibliya

15109

5

1,19

7

1,16

9

2,36

6 476 391 99 6 392

ػو١غح

امج١خ2,366 1,686

3.45 3.45 2,619 3,676 5,158

'Awarta 15113

5

2,89

5

2,72

8

5,62

3

1,11

8 4,286 5,623 ػعرب 992 5.7 105 890

2.75 2.75 6,100 8,003 10,500

'Urif 15116

0

1,53

0

1,39

1

2,92

1 2,094 2,921 ػع٠ف 493 5.9 73 512 552

3.38 3.38 3,228 4,502 6,281

Odala 15118

0 567 568

1,13

5 798 1,135 أصال 173 6.6 35 196 194

3.59 3.59 1,262 1,794 2,552

Huwwa

ra

15118

5

2,78

3

2,78

7

5,57

0

1,13

0 4,275 5,570 داعح 971 5.7 284 888

2.68 2.68 6,030 7,857 10,237

'Einabu

s

15119

5

1,21

2

1,12

8

2,34

0 1,637 2,340 ػ١جؽ 421 5.6 65 428 479

3.64 3.64 2,605 3,723 5,322

Yanun 15120

0 113 102 ٠ب 19 5.4 9 36 28 102 48 54

-1.02 0.50 104 109 114

Beita 15121

5

4,71

5

4,36

4

9,07

9

1,72

4 6,478 9,079 ث١زب 1,566 5.8 290 1,599

3.43 3.43 10,047 14,080 19,734

Ar

Rajman

15122

0 29 15 اغجب 4 3.8 0 16 14 15 7 8

2

2 -6.38 0.50 15 16 17

Zeita

Jamma'

in

15123

0

1,11

0

1,00

5

2,11

5 351 375 46 6.8 309

ػ٠زب

جبػ١2,115 1,447

3.87 3.87 2,370 3,464 5,063

Jamma'

in

15124

5

3,16

9

3,05

6

6,22

5

1,17

0 4,263 6,225 جبػ١ 1,010 6.2 283 1,112

3.86 3.86 6,974 10,183 14,870

Osarin 15126

5 818 794

1,61

2 1,201 1,612 أهغ٠ 288 5.6 31 330 319

2.99 2.99 1,761 2,363 3,172

247

Aqraba 15127

0

4,19

8

3,98

2

8,18

0

1,75

7 5,849 8,180 ػمغثب 1,389 5.9 293 1,573

3.41 3.41 9,046 12,651 17,693

Za'tara 15128

5 43 44 ػػزغح 10 4.4 0 10 15 44 22 22

0.23 0.23 44 45 46

Tall al

Khasha

ba

15131

1 13 13 26 16 15 0 5.2 5

ر

اشلجخ26 3

24.1

0 2.86 28 38 50

Yatma 15132

5

1,42

5

1,42

8

2,85

3 2,199 2,853 ٠زب 517 5.5 79 491 563

2.64 2.64 3,085 4,002 5,193

Qabala

n

15133

5

3,66

5

3,46

5

7,13

0

1,52

6 5,346 7,130 لجال 1,250 5.7 308 1,481

2.92 2.92 7,773 10,367 13,827

Jurish 15134

5 710 690

1,40

0 1,020 1,400 جع٠ق 222 6.3 36 253 267

3.22 3.22 1,540 2,113 2,900

Qusra 15136

5

2,23

1

2,14

6

4,37

7 3,276 4,377 لوغح 674 6.5 169 803 777

2.94 2.94 4,774 6,379 8,523

Talfit 15137

5

1,42

6

1,39

8

2,82

4 2,206 2,824 رف١ذ 420 6.7 65 448 481

2.50 2.50 3,041 3,893 4,984

As

Sawiya

15138

0

1,22

8

1,16

5

2,39

3 1,697 2,393 اـب٠خ 383 6.2 52 447 478

3.50 3.50 2,653 3,741 5,275

Majdal

Bani

Fadil

15138

5

1,23

3

1,14

9

2,38

2 457 394 68 5.9 404

جضي

ث

فبض

2,382 1,611

3.99 3.99 2,679 3,960 5,856

Al

Lubban

ash

Sharqiy

a

15140

5

1,24

3

1,22

2

2,46

5 453 390 57 6 410

اج

الغل١خ2,465 1,844

2.95 2.95 2,689 3,595 4,806

Qaryut 15141

0

1,16

7

1,15

4

2,32

1 1,846 2,321 لغ٠د 396 5.9 61 387 431

2

3 2.32 2.32 2,486 3,126 3,930

Jalud 15142 334 464 جبص 85 5.5 5 91 94 464 235 229

3.34 3.34 512 711 988

248

0

'Ammu

riya

15143

5 231 302 ػع٠خ 48 6.3 5 62 58 302 151 151

2.72 2.72 327 428 559

Duma 15144

5

1,04

1

1,05

8

2,09

9 1,643 2,099 صب 341 6.2 80 403 389

2

4 2.48 2.48 2,259 2,886 3,687

Total

Nablus

Gov.

162,

241

158,

589

320,

830

72,1

99

42,88

4

13,

867 5.4

59,66

3

يجوع

يحافظة

نابهس

320,8

30

248,1

03 2.60 2.86 346,862 451,018 588,897

Qalqiliya Gov.

Falamy

a

20090

5 495 633 فال١خ 114 5.6 20 133 122 633 325 308

2.49 2.49 681 871 1,114

Kafr

Qaddu

m

20092

5

1,48

9

1,41

9

2,90

8 564 520 64 5.9 490

وفغ

لض2,908 2,450

1.73 1.73 3,061 3,634 4,313

Jit 20094

5

1,11

2

1,08

5

2,19

7 1,627 2,197 ج١ذ 375 5.9 52 306 409

3.05 3.05 2,404 3,246 4,384

Baqat

al

Hatab

20096

5 891 753

1,64

4 331 348 80 5.5 297

ثبلخ

اذطت1,644 1,226

2.98 2.98 1,795 2,407 3,228

Hajja 20097

0

1,10

1

1,04

7

2,14

8 1,773 2,148 دجخ 389 5.5 89 450 472

1.94 1.94 2,275 2,756 3,340

Jayyus 20098

5

1,47

3

1,42

1

2,89

4 2,319 2,894 ج١ؽ 538 5.4 105 515 555

2.24 2.24 3,093 3,860 4,817

Khirbet

Sir

20099

5 232 215 447 120 117 24 4.9 92

سغثخ

ه١غ447 380

2

5 1.64 1.64 469 552 649

'Arab ar

Ramadi

n ash

Shamal

i

20100

5 44 37 81 18 37 19 5.1 16

ػغة

اغبض

٠

الب

81 51

4.73 4.73 93 148 235

249

Far'ata 20101

5 461 642 فغػزب 101 6.4 15 120 112 642 301 341

3.37 3.37 709 987 1,375

Immati

n

20102

0

1,22

1

1,16

7

2,38

8 1,718 2,388 إبر١ 433 5.5 71 448 479

3.35 3.35 2,636 3,664 5,093

Al

Funduq

20103

5 462 756 افضق 149 5.1 91 160 165 756 357 399

5.05 5.05 876 1,434 2,347

Qalqili

ya

20104

0

21,2

55

20,4

84

41,7

39

8,68

0 5,219

1,9

25 لم١١خ 7,844 5.3

41,73

9

31,35

6 2.90 2.90 45,479 60,538 80,584

An

Nabi

Elyas

20105

5 600 571

1,17

1 226 185 94 5.4 216

اج

إ١بؽ1,171 852

3.23 3.23 1,288 1,771 2,433

Kafr

Laqif

20106

5 427 429 856 187 170 42 5.5 157

وفغ

اللف856 690

2.18 2.18 913 1,133 1,405

'Arab

Abu

Farda

20107

0 56 60 116 24 37 1 4.8 24

ػغة

أث فغصح116 77

4.18 4.18 131 198 298

'Izbat at

Tabib

20107

5 114 117 231 46 62 29 5.8 40

ػؼثخ

اطج١ت231 167

2

6 3.30 3.30 255 352 487

Jinsafut 20108

5

1,07

6

1,04

3

2,11

9 384 348 90 6 351

جوبف

ط2,119 1,599

2.86 2.86 2,306 3,056 4,049

'Azzun 20110

0

4,02

7

3,79

4

7,82

1

1,43

4 5,794 7,821 ػؼ 1,309 6 339 1,225

3.05 3.05 8,558 11,551 15,592

'Arab ar

Ramadi

n al

Janubi

20110

5 118 104 222 40 54 9 5.6 40

ػغة

اغبض

٠

اجث

222 136

5.02 5.02 257 420 685

'Isla 20111

5 622 855 ػـخ 137 6.2 27 124 141 855 394 461

3.23 3.23 941 1,293 1,777

Arab

Al-

20111

6 14 11 25 9 10 1 4.2 6

ػغة

اشخ25 4,314

-

40.20.50 25 27 28

250

Khoule

h

5

Wadi ar

Rasha

20112

0 85 70 155 23 18 4 6.7 23

اص

اغكب155 76

7.39 7.39 192 391 798

Habla 20112

5

3,09

4

2,92

2

6,01

6

1,13

9 4,314 6,016 دجخ 1,062 5.7 215 707

3.38 3.38 6,647 9,270 12,927

Ras at

Tira

20113

0 210 184 394 70 74 9 6.7 59

عاؽ

اط١غح394 278

3.55 3.55 437 620 879

Ras

'Atiya

20115

5 781 741

1,52

2 292 244 71 5.7 269

عاؽ

ػط١خ1,522 1,121

3.11 3.11 1,668 2,265 3,075

Ad

Dab'a

20117

0 189 335 اضجؼخ 57 5.9 8 57 59 335 165 170

5.89 5.89 398 705 1,250

Kafr

Thulth

20117

5

1,96

6

1,95

5

3,92

1 3,060 3,921 وفغ صش 696 5.6 172 669 747

2.51 2.51 4,224 5,412 6,935

'Izbat

Jal'ud

20119

0 64 48 112 22 27 4 5.1 22

ػؼثخ

جؼص112 100

1.14 1.14 116 130 145

Al

Mudaw

war

20120

5 155 271 اضع 43 6.3 15 53 44 271 130 141

5.75 5.75 320 560 980

'Izbat

Salman

20121

0 373 349 722 138 114 30 5.6 130

ػؼثخ

ؿب722 451

4.82 4.82 831 1,331 2,131

'Izbat al

Ashqar

20122

5 169 146 315 61 67 13 6.3 50

ػؼثخ

األكمغ315 293

0.73 0.73 322 346 372

Beit

Amin

20125

5 534 476

1,01

0 174 169 18 6 168

ث١ذ

أ١1,010 804

2.31 2.31 1,082 1,359 1,707

Sanniri

ya

20126

0

1,48

5

1,29

5

2,78

0 2,095 2,780 ؿ١غ٠ب 476 5.8 68 493 532

2.87 2.87 3,026 4,016 5,329

'Azzun

'Atma

20128

0 933 838

1,77

1 309 311 65 5.7 310

ػؼ

ػزخ1,771 1,171

4.22 4.22 2,005 3,032 4,586

Total

46,7 44,4 91,2 18,1 13,59 3,8 5.5 16,48 يجوع 91,21 72,67

3.34 99,515 133,336 179,348

251

Qalqili

ya

Gov.

يحافظة 3 79 1 28 17 53 64

قهقيهية

7 6

Salfit Gov.

Deir

Istiya

25125

0

1,58

2

1,56

4

3,14

6 707 618 105 5.3 592

ص٠غ

إؿز١ب3,146 2,818

2

7 1.11 1.11 3,252 3,630 4,053

Qarawa

t Bani

Hassan

25127

5

2,00

5

1,79

6

3,80

1 732 792 134 5.7 669

لغاح

ث

دـب

3,801 2,668

3.60 3.60 4,227 6,022 8,579

Qira 25129

0 575 568

1,14

3 743 1,143 ل١غح 176 6.5 31 167 206

4.40 4.40 1,301 2,001 3,078

Kifl

Haris

25129

5

1,61

3

1,63

5

3,24

8 704 630 122 5.4 599

وف

دبعؽ3,248 2,323

3.41 3.41 3,592 5,022 7,021

Marda 25130

0 991

1,00

1

1,99

2 1,589 1,992 غصا 348 5.7 36 318 382

2.29 2.29 2,132 2,672 3,350

Biddya 25130

5

4,13

4

3,93

0

8,06

4

1,66

8 5,982 8,064 ثض٠ب 1,471 5.5 404 1,577

3.03 3.03 8,820 11,890 16,028

Haris 25131

0

1,54

5

1,56

7

3,11

2 2,205 3,112 دبعؽ 534 5.8 81 445 614

2

8 3.51 3.51 3,451 4,870 6,874

Yasuf 25131

5 829 792

1,62

1 1,265 1,621 ٠بؿف 312 5.2 53 311 374

2.51 2.51 1,746 2,238 2,867

Mas-ha 25132

0

1,00

5 998

2,00

3 1,423 2,003 ـذخ 384 5.2 181 508 544

3.48 3.48 2,219 3,124 4,397

Iskaka 25133

0 789 912 إؿىبوب 155 5.9 34 161 193 912 420 492

1.46 1.46 953 1,101 1,273

Sarta 25134

0

1,33

9

1,19

1

2,53

0 1,875 2,530 هغطخ 466 5.4 64 513 515

3.04 3.04 2,768 3,735 5,040

'Izbat

Abu

Adam

25135

5 8 3 11 2 2 0 11 1

ػؼثخ

أث آص11 35

-

10.9

3

0.50 11 12 12

252

Az

Zawiya

25136

0

2,39

2

2,36

2

4,75

4 3,647 4,754 اؼا٠خ 888 5.4 136 938 992

2.69 2.69 5,147 6,710 8,747

Salfit 25137

0

4,40

2

4,39

4

8,79

6

2,11

1 7,010 8,796 ؿف١ذ 1,840 4.8 436 1,590

2.30 2.30 9,416 11,815 14,825

Rafat 25139

5 975 886

1,86

1 1,448 1,861 عافبد 344 5.4 38 361 363

2.54 2.54 2,007 2,579 3,314

Bruqin 25140

0

1,66

5

1,57

1

3,23

6 2,624 3,236 ثغل١ 564 5.7 85 604 627

2.12 2.12 3,446 4,250 5,241

Farkha 25141

5 693 673

1,36

6 1,100 1,366 فغسخ 222 6.2 27 247 265

2.19 2.19 1,458 1,810 2,248

Kafr ad

Dik

25142

5

2,28

9

2,26

4

4,55

3 990 830 132 5.2 884

وفغ

اض٠ه4,553 3,708

2

9 2.07 2.07 4,842 5,946 7,301

Deir

Ballut

25143

0

1,62

1

1,57

4

3,19

5 703 592 66 5.2 609

ص٠غ

ثط3,195 2,645

1.91 1.91 3,381 4,084 4,934

Khirbet

Qeis

25144

0 120 106 226 54 53 3 5 45

سغثخ

ل١ؾ226 182

2.19 2.19 241 299 372

Total

Salfit

Gov.

30,2

75

29,2

95

59,5

70

12,7

46

11,25

7

2,1

68 5.4

11,10

3

يجوع

يحافظة

سهفيث

59,57

0

46,07

9 2.62 64,409 83,809 109,553

Ramallah & Al-Bireh Gov.

Qarawa

t Bani

Zeid

30145

5

1,50

3

1,41

2

2,91

5 530 444 73 5.8 504

لغاح

ث ػ٠ض2,915 1,932

4.20 4.20 3,298 4,976 7,507

Bani

Zeid

ash

Sharqiy

a

30146

0

2,60

6

2,47

7

5,08

3 962 887 140 5.7 888

ث ػ٠ض

الغل١خ5,083 3,825

3

0 2.88 2.88 5,536 7,356 9,776

Kafr

'Ein

30147

0 875 868

1,74

3 1,272 1,743 وفغ ػ١ 341 5.1 36 329 379

3.20 3.20 1,916 2,625 3,597

253

Bani

Zeid

30148

0

2,81

1

2,70

4

5,51

5

1,17

6 4,298 5,515 ث ػ٠ض 1,094 5 133 937

2.52 2.52 5,943 7,626 9,786

'Abwei

n

30148

5

1,55

2

1,56

7

3,11

9 2,399 3,119 ػج٠ 572 5.5 81 572 574

2.66 2.66 3,375 4,387 5,704

Turmus

'ayya

30149

0

1,82

0

1,91

6

3,73

6 3,106 3,736 رغـؼ١ب 625 6 127 840 935

1.86 1.86 3,949 4,750 5,713

Al

Lubban

al

Gharbi

30149

5 709 767

1,47

6 261 202 42 6 248

اج

اغغث1,476 1,054

3.42 3.42 1,633 2,287 3,202

Sinjil 30150

0

2,56

8

2,66

8

5,23

6

1,02

9 3,883 5,236 ؿج 965 5.4 127 806

3.03 3.03 5,727 7,723 10,414

Deir as

Sudan

30150

5

1,00

8 983

1,99

1 347 288 20 6.1 326

ص٠غ

اـصا1,991 1,521

2.73 2.73 2,159 2,826 3,699

Rantis 30151

5

1,36

7

1,16

7

2,53

4 2,020 2,534 عز١ؾ 421 6 60 385 446

2.29 2.29 2,712 3,403 4,268

Jilijliya 30152

0 714 741 جج١١ب 154 4.8 9 225 222 741 390 351

0.37 0.37 749 778 807

'Ajjul 30152

5 636 601

1,23

7 1,013 1,237 ػجي 220 5.6 16 206 227

2.02 2.02 1,313 1,604 1,958

Al

Mugha

yyir

30153

0

1,22

0

1,14

8

2,36

8 1,683 2,368 اغ١غ 376 6.3 61 439 414

3.47 3.47 2,623 3,691 5,194

'Abud 30153

5

1,06

5

1,01

9

2,08

4 1,716 2,084 ػبثص 419 5 55 353 452

1.96 1.96 2,209 2,683 3,258

An

Nabi

Salih

30154

0 286 248 534 101 96 11 5.9 91

اج

هبخ534 366

3.85 3.85 598 873 1,273

Khirbet

Abu

30154

5

2,03

6

1,96

0

3,99

6 718 612 98 6.4 620

سغثخ

أث فالح3,996 2,863

3.39 3.39 4,416 6,164 8,603

254

Falah

Umm

Safa

30155

0 503 612 أ هفب 114 5.4 19 100 119 612 298 314

1.98 1.98 649 790 961

Al

Mazra'a

ash

Sharqiy

a

30155

5

2,22

8

2,26

7

4,49

5

1,06

6 958 140 5.7 792

اؼعػخ

الغل١خ4,495 3,612

2.21 2.21 4,800 5,973 7,433

Deir

Nidham

30156

0 635 879 ص٠غ ظب 139 6.3 8 105 136 879 412 467

3.31 3.31 969 1,341 1,857

'Atara 30156

5

1,13

1

1,13

9

2,27

0 1,640 2,270 ػطبعح 413 5.5 39 421 495

3.30 3.30 2,503 3,464 4,795

Deir

Abu

Mash'al

30157

0

1,79

4

1,72

8

3,52

2 703 613 97 5.2 672

ص٠غ أث

لؼ3,522 2,402

3.90 3.90 3,951 5,793 8,494

Jibiya 30157

5 112 148 ج١ج١ب 26 5.7 4 28 33 148 77 71

2.83 2.83 161 213 281

Burham 30158

5 395 616 ثغب 120 5.1 5 99 130 616 310 306

4.54 4.54 704 1,098 1,712

Kafr

Malik

30159

0

1,36

6

1,42

1

2,78

7 664 631 127 5 561

وفغ

به2,787 2,220

3

1 2.30 2.30 2,984 3,746 4,703

Shuqba 30159

5

2,30

2

2,19

5

4,49

7 3,027 4,497 كمجب 793 5.7 164 684 883

4.04 4.04 5,064 7,523 11,177

Kobar 30160

0

1,88

5

1,79

2

3,67

7 2,563 3,677 وثغ 668 5.5 72 630 707

3.68 3.68 4,097 5,878 8,433

Qibya 30160

5

2,54

5

2,35

6

4,90

1 3,441 4,901 لج١ 803 6.1 126 776 838

3.60 3.60 5,450 7,762 11,055

Silwad 30161

0

3,07

2

3,05

1

6,12

3

1,68

3 5,064 6,123 ؿاص 1,237 4.9 191 1,197

1.92 1.92 6,482 7,837 9,476

Yabrud 30161 481 644 ٠جغص 111 5.8 9 102 136 644 307 337

2.96 2.96 703 941 1,260

255

5

AL-

Itihad

30162

0

3,52

1

3,28

2

6,80

3

1,10

1 4,853 6,803 االرذبص 1,055 6.4 115 887

3

2 3.44 3.44 7,528 10,554 14,794

Shabtin 30162

5 610 844 كجز١ 149 5.7 8 108 157 844 395 449

3.30 3.30 930 1,287 1,781

Bir Zeit 30163

5

2,26

1

2,26

8

4,52

9

1,77

2 4,625 4,529 ث١غػ٠ذ 1,005 4.5 262 841

-0.21 0.50 4,597 4,832 5,080

AL-

Doha

30163

6 40 50 اضدخ 10 5 0 52 29 50 19 31

2.26 2.26 53 67 84

'Ein

Siniya

30164

0 349 362 711 169 190 19 5.2 136

ػ١

ؿ١١ب711 526

3.06 3.06 778 1,052 1,422

Silwad

Camp

30164

5 215 167 382 71 61 14 5.6 68

ش١

ؿاص382 296

2.58 2.58 412 532 687

Deir

Jarir

30165

0

1,97

7

2,00

9

3,98

6 838 487 95 5.3 750

ص٠غ

جغ٠غ3,986 3,004

2.87 2.87 4,339 5,757 7,639

Deir

'Amma

r Camp

30166

0 931 903

1,83

4 359 252 55 5.9 311

ش١

ص٠غ

ػبع

1,834 1,556

1.66 1.66 1,927 2,271 2,677

Budrus 30166

5 690 709

1,39

9 1,056 1,399 ثضعؽ 236 5.9 23 225 273

2.85 2.85 1,522 2,017 2,672

AL-

Zaytou

neh

30167

0

3,20

5

2,98

5

6,19

0

1,19

8 4,263 6,190 اؼ٠زخ 1,027 6 103 1,084

3

3 3.80 3.80 6,923 10,052 14,596

Jifna 30167

5 860 856

1,71

6 948 1,716 جفب 378 4.5 48 366 470

6.11 6.11 2,050 3,711 6,718

Dura al

Qar'

30168

0

1,42

8

1,46

9

2,89

7 640 360 47 5.4 541

صعا

امغع2,897 1,913

4.24 4.24 3,281 4,969 7,525

At

Tayba

30168

5 692 760

1,45

2 1,484 1,452 اط١جخ 333 4.4 87 376 442

-0.22 0.50 1,474 1,549 1,628

Al 30170 3,94 3,87 7,81 1,54 ش١ 1,401 5.6 197 908 7,813 6,064

2.57 2.57 8,430 10,862 13,994

256

Jalazun

Camp

اجؼ 5 3 1 2 0

Abu

Qash

30170

5 707 697

1,40

4 1,092 1,404 أث لق 273 5.1 66 290 401

2.54 2.54 1,514 1,947 2,503

Deir

Qaddis

30171

0

1,00

6 936

1,94

2 397 290 50 5.6 345

ص٠غ

لض٠ؾ1,942 1,374

3.52 3.52 2,154 3,045 4,304

Ni'lin 30171

5

2,31

9

2,25

4

4,57

3 3,317 4,573 ؼ١ 869 5.3 217 686 979

3.26 3.26 5,035 6,942 9,571

'Ein

Yabrud

30172

0

1,42

7

1,57

2

2,99

9 852 629 103 5.2 577

ػ١

٠جغص2,999 2,483

1.91 1.91 3,174 3,833 4,630

Kharbat

ha Bani

Harith

30172

5

1,47

7

1,36

9

2,84

6 519 453 88 5.8 487

سغثضب

ث

دبعس

2,846 2,029

3.44 3.44 3,150 4,418 6,198

Ras

Karkar

30173

0 850 813

1,66

3 308 219 30 5.8 288

عاؽ

وغوغ1,663 1,325

2.30 2.30 1,780 2,234 2,804

Surda 30173

5 507 524

1,03

1 993 1,031 هغصا 214 4.8 17 204 288

0.38 0.38 1,043 1,083 1,124

Al

Janiya

30174

0 581 582

1,16

3 817 1,163 اجب١خ 180 6.5 14 142 209

3.59 3.59 1,293 1,841 2,620

Al

Midya

30174

5 666 635

1,30

1 911 1,301 اض٠خ 216 6 16 153 224

3.63 3.63 1,448 2,068 2,953

Rammu

n

30175

0

1,28

8

1,33

8

2,62

6 2,241 2,626 ع 468 5.6 67 470 594

1.60 1.60 2,754 3,227 3,781

Kafr

Ni'ma

30175

5

1,88

8

1,86

2

3,75

0 770 690 91 5.3 709

وفغ

ؼخ3,750 2,704

3.32 3.32 4,137 5,737 7,956

Bil'in 30176

0 889 812

1,70

1 1,226 1,701 ثؼ١ 307 5.5 51 350 350

3.33 3.33 1,877 2,604 3,612

Beitin 30176

5

1,01

5

1,12

8

2,14

3 2,131 2,143 ث١ز١ 440 4.9 70 410 717

0.06 0.06 2,147 2,159 2,171

'Ein 30177 ػ١ 130 6.2 6 108 137 812 399 413 812 564

3.71 3.71 906 1,304 1,878

257

Qiniya 0 ل١١ب

Badiw

al

Mu'arra

jat

30177

5 407 346 753 110 108 5 6.7 112

ثض

اؼغجب

د

753 558

3.04 3.04 824 1,112 1,500

Deir

Ibzi'

30178

0

1,05

5

1,01

4

2,06

9 362 335 41 5.8 354

ص٠غ

إثؼ٠غ2,069 1,452

3.60 3.60 2,301 3,279 4,672

Deir

Dibwan

30178

5

2,41

3

2,83

9

5,25

2

1,34

3 1,233 201 5.3 990

ص٠غ

صثا5,252 4,837

0.83 0.83 5,383 5,845 6,347

Al

Bireh

30179

0

19,1

34

19,0

68

38,2

02

12,0

87 3,781

2,2

45 اج١غح 7,917 4.8

38,20

2

27,60

6 3.30 3.30 42,112 58,277 80,645

'Ein

'Arik

30180

0 772 795

1,56

7 307 228 48 5.5 287

ػ١

ػغ٠ه1,567 1,190

2.79 2.79 1,702 2,241 2,951

Saffa 30180

5

1,90

4

1,89

8

3,80

2 2,822 3,802 هفب 651 5.8 152 620 759

3.03 3.03 4,158 5,601 7,547

Ramall

ah

30181

0

13,6

14

13,8

46

27,4

60

8,47

7 3,046

3,0

86 عا هللا 6,083 4.5

27,46

0

17,78

1 4.44 4.44 31,284 48,313 74,613

Burqa 30181

5 995

1,09

5

2,09

0 1,618 2,090 ثغلخ 314 6.7 40 278 375

2.59 2.59 2,257 2,915 3,766

Beit 'Ur

at

Tahta

30182

0

2,24

3

2,12

9

4,37

2 882 715 122 5.4 804

ث١ذ

ػع

ازذزب

4,372 3,081

3.56 3.56 4,856 6,891 9,778

Beituni

ya

30182

5

10,0

47

9,71

4

19,7

61

5,05

3 ث١ز١ب 3,901 5.1 480 1,588

19,76

1 9,293

3

4 7.84 7.84 24,780 52,694 112,050

Al

Am'ari

Camp

30183

0

2,58

3

2,43

1

5,01

4

1,02

9 554 93 5.5 906

ش١

األؼغ5,014 3,993

2.30 2.30 5,368 6,741 8,465

Qaddur

a Camp

30183

5 604 604

1,20

8 289 119 70 5.2 233

ش١

لضعح1,208 1,088

1.05 1.05 1,247 1,384 1,537

Beit 30185 1,43 1,31 2,74 ث١ذ 493 5.6 61 381 564 2,749 1,984

3.31 3.31 3,032 4,200 5,820

258

Sira 0 4 5 9 ؿ١غا

Kharbat

ha al

Misbah

30185

5

2,66

3

2,54

8

5,21

1 924 669 110 6.4 815

سغثضب

اوجبح5,211 3,662

3.59 3.59 5,793 8,243 11,730

Beit 'Ur

al

Fauqa

30186

0 438 426 864 185 179 26 4.9 178

ث١ذ

ػع

افلب

864 647

2.93 2.93 942 1,258 1,680

At Tira 30189

0 661 697

1,35

8 1,148 1,358 اط١غح 246 5.5 22 231 282

1.69 1.69 1,428 1,689 1,998

Beit

Liqya

30189

5

3,91

1

3,79

9

7,71

0

1,47

0 5,634 7,710 ث١ذ م١ب 1,302 5.9 230 1,224

3.19 3.19 8,471 11,592 15,864

Beit

Nuba

30192

5 134 115 249 31 23 4 7.8 32

ث١ذ

ثب249 204

2.01 2.01 264 323 394

Total

Ramall

ah &

Al-

Bireh

Gov.

140,

827

138,

903

279,

730

66,7

04

40,56

8

11,

085 5.3

52,83

4

يجوع

يحافظة

راو هللا

279,7

30

202,8

03 2.94 309,532 440,661 645,152

Jericho Gov.

Marj

Na'ja

35104

5 359 356 715 145 136 10 6.2 116

غط

ؼجخ715 547

2.71 2.71 775 1,013 1,324

Az

Zubeid

at

35111

0 729 692

1,42

1 955 1,421 اؼث١ضاد 199 7.1 13 140 199

4.05 4.05 1,601 2,382 3,544

Marj al

Ghazal

35111

6 97 106 203 50 68 5 4.7 43

غط

اغؼاي203 274

-2.95 0.50 206 217 228

Al

Jiftlik

35114

0

1,85

7

1,85

7

3,71

4 3,136 3,714 اجفزه 578 6.4 129 716 692

1.71 1.71 3,907 4,628 5,480

Fasayil 35151 541 537 1,07 641 1,078 فوب٠ 190 5.7 8 214 202

5.34 5.34 1,260 2,119 3,563

259

0 8

Al

'Auja

35169

0

2,05

8

2,06

2

4,12

0 2,858 4,120 اؼجب 674 6.1 112 711 721

3.73 3.73 4,598 6,628 9,555

An

Nuwei'

ma

35184

0 593 652

1,24

5 830 1,245 ا٠ؼخ 213 5.8 21 274 243

4.14 4.14 1,406 2,109 3,164

'Ein ad

Duyuk

al

Fauqa

35184

5 409 412 821 156 175 21 6 137

ػ١

اض٠ن

افلب

821 580

3.54 3.54 911 1,290 1,826

'Ein as

Sultan

Camp

35186

5

1,59

2

1,56

8

3,16

0 653 707 67 5.4 589

ش١

ػ١

اـطب

3,160 1,451

8.09 8.09 3,991 8,692 18,929

Jericho

(Ariha)

35192

0

9,14

5

9,20

1

18,3

46

4,54

9 أع٠ذب 3,510 5.2 668 3,386

18,34

6

15,24

3

3

5 1.87 1.87 19,395 23,343 28,095

Deir al

Qilt

35197

0 4 0 4 1 1 0 4 1

ص٠غ

امظ4 2

7.18 7.18 5 10 20

Aqbat

Jaber

Camp

35197

5

3,63

0

3,54

6

7,17

6

1,36

9 1,420 151 5.5 1,298

ش١

ػمجخ

ججغ

7,176 4,521

4.73 4.73 8,243 13,084 20,767

Deir

Hajla

35202

1 6 2 8 1 1 0 8 1

ص٠غ

دجخ8 5

4.81 4.81 9 15 24

An

Nabi

Musa

35207

5 167 142 309 65 91 22 4.7 66

اج

ؿ309 45

21.2

5

21.2

5 551 3,782 25,970

Total

Jericho

Gov.

21,1

87

21,1

33

42,3

20

9,04

6 8,040

1,2

27 5.6 7,615

يجوع

يحافظة

أريحا

42,32

0

31,08

8 5.63 46,858 69,310 122,488

Jerusalem Gov.

Rafat 4018 1,20 1,17 2,37 1,553 2,374 عافبد 420 5.7 49 319 455

4.34 4.34 2,696 4,122 6,301

260

70 3 1 4

Mikhmas 4018

85 677 770

1,44

7 1,374 1,447 شبؽ 312 4.6 39 404 503

0.52 0.52 1,470 1,548 1,630

Qalandiy

a Camp

4019

00

4,57

4

4,25

7

8,83

1

1,70

3 934 160 5.4 1,625

ش١

لض٠ب8,831 6,629

2.91 2.91 9,625 12,822 17,081

Jaba'

(Tajamm

u'

Badawi)

4019

10 35 37 72 19 31 15 4.5 16

ججغ

)رجغ

ثض(

72 46

4.58 4.58 82 129 202

Qalandiy

a

4019

15 573 606

1,17

9 844 1,179 لض٠ب 214 5.5 8 150 220

3.40 3.40 1,303 1,821 2,543

Beit

Duqqu

4019

30 830 791

1,62

1 1,170 1,621 ث١ذ صل 308 5.3 21 268 370

3.31 3.31 1,788 2,477 3,431

Jaba' 4019

35

1,65

5

1,52

8

3,18

3 2,369 3,183 ججغ 462 6.9 41 399 557

3.00 3.00 3,478 4,673 6,279

Al

Judeira

4019

40

1,13

8

1,13

8

2,27

6 1,551 2,276 اجض٠غح 410 5.6 46 255 482

3.91 3.91 2,554 3,747 5,499

Ar Ram

&

Dahiyat

al Bareed

4019

45

10,4

81

9,87

8

20,3

59

7,53

0 2,285 921 4.9 4,149

اغا

ضبد١خ

اجغ٠ض

20,35

9

18,71

9 0.84 0.84 20,878 22,708 24,697

Beit

'Anan

4019

50

1,98

5

1,99

5

3,98

0 843 604 79 5.2 764

ث١ذ

ػب3,980 3,119

2.47 2.47 4,282 5,464 6,972

Al Jib 4019

55

2,13

7

2,08

3

4,22

0

1,01

5 3,395 4,220 اج١ت 719 5.9 68 544

2.20 2.20 4,505 5,599 6,960

Bir

Nabala

4019

60

2,40

2

2,41

5

4,81

7

2,05

5 4,454 4,817 ث١غ جبال 944 5.1 170 792

0.79 0.79 4,932 5,333 5,768

Beit Ijza 4019

65 383 315 698 146 104 11 5.8 120

ث١ذ

إجؼا698 490

3.60 3.60 776 1,106 1,575

Al 4019 1,61 1,55 3,17 1,513 3,172 امج١جخ 555 5.7 132 491 628

7.68 7.68 3,961 8,304 17,409

261

Qubeiba 80 6 6 2

Kharayib

Umm al

Lahim

4019

85 177 186 363 55 44 3 6.8 53

سغائت

أ اذ363 272

2.93 2.93 396 528 705

Biddu 4019

95

3,51

4

3,28

4

6,79

8

1,17

9 4,657 6,798 ثض 1,157 5.9 267 760

3.86 3.86 7,615 11,116 16,226

An Nabi

Samwil

4020

00 136 122 258 41 27 2 6 43

اج

هئ١258 160

4.89 4.89 298 480 774

Hizma 4020

05

3,11

0

3,16

1

6,27

1

1,28

4 4,459 6,271 دؼب 1,027 6.1 152 730

3.47 3.47 6,947 9,769 13,739

Beit

Hanina

al Balad

4020

10 550 521

1,07

1 409 233 19 5.9 181

ث١ذ

د١ب

اجض

1,071 1,014

0.55 0.55 1,089 1,150 1,215

Qatanna 4020

15

3,24

2

3,21

6

6,45

8

1,15

7 5,482 6,458 لطخ 1,069 6 64 894

1.65 1.65 6,783 7,991 9,414

Beit

Surik

4020

20

1,94

6

1,94

1

3,88

7 649 415 59 6.2 629

ث١ذ

ؿع٠ه3,887 2,792

3.36 3.36 4,293 5,976 8,320

Beit Iksa 4020

25 963 932

1,89

5 424 326 29 5.2 362

ث١ذ

إوـب1,895 1,148

5.14 5.14 2,202 3,636 6,001

'Anata 4020

40

6,09

1

5,95

8

12,0

49

2,65

0 ػبرب 2,168 5.6 288 1,250

12,04

9 7,037

5.53 5.53 14,159 24,243 41,509

Al

Ka'abina

(Tajamm

u'

Badawi)

4020

45 339 355 694 171 171 36 5.7 122

اىؼبث

)رجغ

ثض(

694 714

-0.28 0.50 704 740 778

Az

Za'ayye

m

4020

65

1,76

3

1,63

9

3,40

2

1,06

1 1,798 3,402 اؼػ١ 695 4.9 73 368

6.58 6.58 4,119 7,794 14,747

Al 4021 8,89 8,70 17,6 5,20 17,60 اؼ١ؼع٠خ 3,429 5.1 971 2,430 12,72

3.30 3.30 19,408 26,854 37,157

262

'Eizariya 00 7 9 06 7 6 4

Abu Dis 4021

20

5,57

9

5,20

3

10,7

82

2,87

8 أث ص٠ؾ 2,215 4.9 297 1,518

10,78

2 8,858

1.99 1.99 11,437 13,921 16,945

'Arab al

Jahalin

4021

25 364 357 721 96 114 3 7.1 101

ػغة

اجب١721 881

-1.98 0.50 732 769 809

As

Sawahira

ash

Sharqiya

4021

45

2,92

6

2,87

4

5,80

0

1,28

8 914 78 5.4 1,077

اـادغ

ح

الغل١خ

5,800 3,810

4.29 4.29 6,579 10,016 15,247

Ash

Sheikh

Sa'd

4021

60 941

1,00

8

1,94

9 518 437 16 5.1 385

ال١ز

ؿؼض1,949 1,760

1.03 1.03 2,010 2,225 2,464

Total

Jerusale

m J2

70,2

27

68,0

06

138,

233

35,5

93

18,21

1

4,1

28 5.4

25,73

1

يجوع

انقذس

j2

138,2

33

Total

Jerusale

m J1

114,

743

110,

673

225,

416 - - - 5

44,70

3

يجوع

انقذس

j1

225,4

16

Total

Jerusale

m Gov.

184,

970

178,

679

363,

649

35,5

93

18,21

1

4,1

28 5.2

70,43

4

يجوع

يحافظة

انقذس

363,6

49

104,7

92 3.29 151,098 207,060 292,398

Bethlehem Gov.

Al

Walaja

45217

0

1,04

1

1,00

0

2,04

1 1,227 2,041 اجخ 390 5.2 24 280 388

5.22 5.22 2,378 3,955 6,579

Battir 45217

5

1,99

2

1,97

5

3,96

7 3,054 3,967 ثز١غ 798 5 85 663 981

2.65 2.65 4,291 5,574 7,240

Al

'Ubeidi

ya

45218

0

5,45

6

5,29

7

10,7

53

1,86

5 اؼج١ض٠خ 1,703 6.3 131 1,257

10,75

3 7,765

3

6 3.31 3.31 11,856 16,419 22,736

'Ayda 45218 1,31 1,31 2,63 ش١ 509 5.2 43 288 564 2,631 2,360

1.09 1.09 2,718 3,030 3,378

263

Camp 5 8 3 1 ػب٠ضح

Khallet

an

Nu'man

45219

0 80 93 173 35 30 1 6 29

سخ

اؼب173 143

1.92 1.92 183 222 268

Al 'Aza

Camp

45219

5 786 743

1,52

9 275 142 38 5.2 292

ش١

اؼؼح1,529 1,262

1.94 1.94 1,620 1,962 2,377

Al

Khas

45220

0 250 394 اشبم 77 5.1 5 84 91 394 194 200

4.65 4.65 452 712 1,122

Al

Haddad

iya

45220

5 49 54 اذضاص٠خ 10 5.4 0 12 13 54 24 30

0.98 0.98 56 61 68

Khallet

Hamam

eh

45220

8 694 721

1,41

5 335 167 16 5 285

سخ

دبخ1,415 1,150

2.10 2.10 1,506 1,853 2,280

Bir

Onah

45220

9 331 341 672 149 102 5 4.7 144

ثئغ

ػ672 472

3.60 3.60 747 1,064 1,514

Beit

Jala

45221

0

5,83

4

5,92

4

11,7

58

3,43

3 ث١ذ جبال 2,664 4.4 571 1,911

11,75

8

12,07

9 -0.27 0.50 11,935 12,546 13,187

Dar

Salah

45222

5

1,71

5

1,65

8

3,37

3 685 656 68 5.4 625

صاع

هالح3,373 2,183

3

7 4.45 4.45 3,843 5,938 9,176

Husan 45223

0

2,94

2

2,60

9

5,55

1

1,19

5 4,131 5,551 دؿب 1,028 5.4 168 928

3.00 3.00 6,065 8,150 10,952

Wadi

Fukin

45223

5 588 580

1,16

8 244 180 12 5.4 217

اص

فو١1,168 869

3.00 3.00 1,276 1,716 2,306

Bethleh

em

(Beit

Lahm)

45224

0

12,7

53

12,5

13

25,2

66

6,70

9 3,107

1,8

60 ث١ذ ذ 5,211 4.8

25,26

6

21,66

0 1.55 1.55 26,461 30,866 36,004

Beit

Sahur

45225

5

6,20

2

6,16

5

12,3

67

3,51

7 2,145 656 4.5 2,775

ث١ذ

ؿبدع

12,36

7

11,13

7 1.05 1.05 12,762 14,171 15,736

264

Ad

Doha

45226

5

4,95

0

4,80

3

9,75

3

2,22

0 5,131 9,753 اضدخ 1,849 5.3 429 1,002

6.63 6.63 11,825 22,478 42,726

Al

Khadr

45227

0

5,05

6

4,71

8

9,77

4

1,90

1 6,720 9,774 اشضغ 1,722 5.7 255 1,106

3.82 3.82 10,937 15,907 23,136

Ad

Duheis

ha

Camp

45227

5

4,42

6

4,31

0

8,73

6

1,90

5 1,170 253 5.1 1,698

ش١

اض١لخ8,736 6,803

2.53 2.53 9,417 12,092 15,528

Hindaz

a

45228

0

2,41

6

2,38

3

4,79

9 2,621 4,799 ضاػح 794 6 56 805 899

3

8 6.24 6.24 5,754 10,535 19,290

Ash

Shawa

wra

45228

5

1,91

5

1,82

2

3,73

7 771 760 56 5.4 694

الاع

ح3,737 2,715

3

9 3.25 3.25 4,113 5,661 7,792

Artas 45230

0

1,87

7

1,78

6

3,66

3 2,651 3,663 إعطبؽ 603 6.1 40 535 755

3.29 3.29 4,036 5,577 7,706

Nahhali

n

45232

5

3,54

2

3,28

5

6,82

7

1,35

2 4,638 6,827 ذب١ 1,204 5.7 182 1,117

3.94 3.94 7,667 11,285 16,611

Beit

Ta'mir

45233

5 654 575

1,22

9 242 200 13 6.1 200

ث١ذ

رؼغ1,229 840

3.88 3.88 1,378 2,016 2,949

Khallet

al

Louza

45234

5 290 288 578 104 191 4 6.2 93

سخ

اػح578 324

5.96 5.96 688 1,227 2,188

Al Jab'a 45235

5 643 896 اججؼخ 140 6.4 11 137 153 896 416 480

3.37 3.37 990 1,379 1,922

Za'tara 45236

0

3,21

5

3,07

4

6,28

9

1,08

0 4,408 6,289 ػػزغح 1,046 6 85 1,049

4

0 3.62 3.62 6,997 9,982 14,242

Jannata

h

45238

5

2,75

4

2,66

2

5,41

6 913 851 52 6.3 860

جبرخ

)ث١ذ

فح(

5,416 3,623 4

1 4.10 4.10 6,110 9,134 13,655

Wadi 45240 764 655 1,41 اص 278 5.1 22 272 301 1,419 872 4 4.99 4.99 1,642 2,672 4,349

265

Rahhal 0 9 2 عدبي

Jubbet

adh

Dhib

45240

5 81 81 162 27 23 5 6 27

ججخ

اظ٠ت162 93

5.71 5.71 191 333 581

Khallet

Sakariy

a

45241

5 97 88 185 36 33 2 5.4 34

سخ

ؿىبع٠ب185 195

4

3 -0.53 0.50 188 197 207

Khallet

al

Haddad

45243

0 220 187 407 79 74 4 5.6 73

سخ

اذضاص407 303

2.99 2.99 445 597 802

Al

Ma'sara

45244

0 429 374 803 136 137 10 6.2 129

اؼوغ

ح803 572

3.45 3.45 889 1,248 1,752

Wadi

an Nis

45244

5 394 378 772 132 103 10 6.5 119

اص

ا١ن772 538

3.68 3.68 860 1,235 1,771

Jurat

ash

Sham'a

45246

0 797 694

1,49

1 269 202 43 6 250

جعح

الؼخ1,491 1,085

3.23 3.23 1,640 2,254 3,097

Khallet

'Afana

45246

5 0 0 0 12 15 4 0 0

سخ

ػفبخ0 4

-

100.

00

0.50 0 0 0

Marah

Ma'alla

45247

0 373 312 685 106 104 14 6.9 99

غاح

ؼال685 446

4.38 4.38 779 1,197 1,838

Umm

Salamu

na

45248

0 475 470 945 144 128 20 6.8 139

أ

ؿخ945 584

4.93 4.93 1,092 1,767 2,859

Al

Manshi

ya

45249

0 263 433 ال١خ 57 7.6 5 45 57 433 221 212

5.11 5.11 503 828 1,363

Tuqu' 45249

5

4,55

5

4,32

6

8,88

1

1,44

4 6,165 8,881 رمع 1,368 6.5 169 1,311

4

4 3.72 3.72 9,909 14,274 20,563

266

Marah

Rabah

45250

0 690 630

1,32

0 177 158 32 7.8 169

غاح

عثبح1,320 822

4.85 4.85 1,522 2,443 3,924

Beit

Fajjar

45252

5

5,63

4

5,37

0

11,0

04

2,04

2 1,561 400 6.1 1,808

ث١ذ

فجبع

11,00

4 7,896

3.37 3.37 12,156 16,941 23,609

Al

Maniya

45253

5 509 503

1,01

2 651 1,012 ا١خ 157 6.4 18 147 153

4

5 4.51 4.51 1,155 1,796 2,792

Kisan 45256

5 288 454 و١ـب 76 6 3 75 77 454 228 226

4.66 4.66 520 820 1,293

'Arab ar

Rashayi

da

45266

0 750 703

1,45

3 291 301 5 6.5 224

ػغة

اغكب٠ضح1,453 947

4

6 4.37 4.37 1,652 2,535 3,889

Total

Bethle

hem

Gov.

89,7

43

86,4

92

176,

235

38,2

57

25,56

4

5,8

85 5.4

32,66

7

يجوع

يحافظة

بيث نحى

176,2

35

132,6

32 2.88 3.69 193,202 266,648 377,357

Hebron Gov.

Khirbet

ad Deir

50243

5 127 137 264 48 50 1 5.6 47

سغثخ

اض٠غ264 212

2.22 2.22 282 351 437

Surif 50245

0

6,74

8

6,61

7

13,3

65

2,35

1 2,242 306 6.2 2,151

هع٠

ف

13,36

5

9,54

1 3.43 3.43 14,787 20,714 29,016

Al

'Arrub

Camp

50253

0

4,02

5

3,91

6

7,94

1

1,42

0 977 184 5.8 1,358

ش١

اؼغة7,941

5,93

3 2.96 2.96 8,667 11,600 15,526

Beit

Ummar

50254

0

6,90

9

6,63

9

13,5

48

2,73

9 2,266 364 5.9 2,306

ث١ذ

أغ

13,54

8

9,86

7 47 3.22 3.22 14,900 20,458 28,091

Jala 50254

5 180 249 جبال 40 6.2 2 64 47 249 138 111

3.30 3.30 274 380 525

Hitta 50255

0 511 891 دزب 114 7.8 16 129 121 891 450 441

5.72 5.72 1,053 1,836 3,201

Shuyuk 50255 822 728 1,55 ك١ر 257 6 41 284 287 1,550 978

4.71 4.71 1,780 2,820 4,470

267

h al

'Arrub

اؼغة 0 5

Kharas 50256

0

3,47

2

3,18

3

6,65

5

1,18

2 6,655 سبعاؽ 1,042 6.4 130 1,091

5,10

0 48 2.70 2.70 7,208 9,406 12,274

Umm

al Butm

50257

5 58 71 أ اجط 11 6.5 0 10 12 71 35 36

2.04 2.04 75 92 113

Hamrus

h

50258

0 39 53 دغف 7 7.6 3 12 8 53 22 31

3.11 3.11 58 79 107

Nuba 50258

5

2,21

8

2,11

8

4,33

6 4,336 ثب 730 5.9 92 757 817

3,17

8 3.16 3.16 4,760 6,494 8,860

Beit

Ula

50261

5

5,55

5

5,33

0

10,8

85

1,94

9 ث١ذ أال 1,712 6.4 271 1,847

10,88

5

7,56

3 49 3.71 3.71 12,141 17,474 25,150

Sa'ir 50262

0

9,12

9

8,91

6

18,0

45

3,05

9 ؿؼ١غ 2,699 6.7 418 3,043

18,04

5

13,1

71 50 3.20 3.20 19,833 27,172 37,227

Halhul 50263

0

11,2

74

10,8

54

22,1

28

4,55

0 دذي 3,961 5.6 638 3,555

22,12

8

15,6

58 51 3.52 3.52 24,547 34,690 49,025

Ash

Shuyuk

h

50263

5

4,50

3

4,30

8

8,81

1

1,75

4 8,811 ال١ر 1,438 6.1 278 1,468

5,98

6 52 3.94 3.94 9,894 14,564 21,437

Tarqum

iya

50264

0

7,39

8

6,95

9

14,3

57

2,49

2 رغل١ب 2,284 6.3 347 2,356

14,35

7

10,4

41 53 3.24 3.24 15,796 21,721 29,868

Beit

Kahil

50265

5

3,36

4

3,16

2

6,52

6

1,08

4 964 120 6.9 948

ث١ذ

وبد6,526

4,15

9 4.61 4.61 7,470 11,722 18,393

Beit

'Einun

50268

0 930 879

1,80

9 360 310 42 6.4 282

ث١ذ

ػ١1,809

1,73

1 0.44 0.44 1,833 1,916 2,002

Qla’a

Zeta

50268

1 456 447 903 194 103 8 5.7 158

لالع

ػ٠زب903 705

2.51 2.51 973 1,246 1,596

Idhna 50268

5

9,72

3

9,28

9

19,0

12

3,46

3 إطب 3,118 6.1 611 3,626

19,01

2

13,5

82 54 3.42 3.42 21,030 29,438 41,207

Taffuh 50275 5,38 5,21 10,5 1,94 10,59 رفح 1,759 6 254 1,432 7,06 55 4.14 4.14 11,968 17,950 26,924

268

0 5 2 97 8 7 5

Beit

Maqdu

m

50276

5

1,26

7

1,30

1

2,56

8 521 484 55 5.9 432

ث١ذ

مض2,568

1,86

7 56 3.24 3.24 2,826 3,887 5,346

Al

Baqa

50277

8 612 606

1,21

8 1,218 اجمؼ 193 6.3 2 155 244

1,05

2 1.48 1.48 1,273 1,474 1,706

Hebron

(Al

Khalil)

50278

0

84,2

23

78,9

23

163,

146

34,1

06

17,59

3

7,3

64 5.7

28,56

3 اش١

163,1

46

117,

962 57 3.30 3.30

179,81

5 248,692 343,950

Al

Bowere

h

(Aqabat

Injeleh)

50278

1 358 336 694 122 117 3 6.5 106

اج٠غ

)ػمجخ

اج١(

694 472

3.93 3.93 779 1,146 1,684

Khallet

Edar

50278

2

1,11

1

1,07

5

2,18

6 366 304 18 6.9 316

سخ

اضاع2,186

1,57

2 3.35 3.35 2,413 3,356 4,667

Deir

Samit

50281

0

3,16

6

3,07

1

6,23

7

1,18

3 1,028 134 5.9 1,057

ص٠غ

ؿبذ6,237

4,11

8 58 4.24 4.24 7,064 10,699 16,205

Bani

Na'im

50281

5

10,0

74

10,0

10

20,0

84

3,45

2 ث ؼ١ 3,067 6.5 429 3,333

20,08

4

13,4

48 59 4.09 4.09 22,652 33,830 50,523

Khallet

Al

Masafe

r

50283

0 96 121 217 38 38 0 5.6 39

سخ

اـبفغ217 166

2.72 2.72 235 307 402

Beit

'Awwa

50283

5

3,99

8

4,06

6

8,06

4

1,35

5 8,064 ث١ذ ػا 1,295 6.2 354 1,390

5,92

4 3.13 3.13 8,846 12,041 16,391

Dura 50284

0

14,3

63

13,9

05

28,2

68

5,57

1 صعا 4,832 5.9 994 4,557

28,26

8

18,7

67 60 4.18 4.18 31,964 48,147 72,521

Qalqas 50285

5 584 565

1,14

9 644 1,149 لمؾ 159 7.2 18 166 172

5.96 5.96 1,367 2,439 4,351

269

Sikka 50286

0 1,468 1,160 917 2.38 2.38 61 676 855 ؿىخ 149 5.7 20 158 162 855 453 402

Khirbet

Salama

50286

5 183 188 371 63 69 3 5.8 64

سغثخ

ؿالخ371 239

4.50 4.50 423 657 1,020

Wadi

'Ubeid

50287

0 64 66 130 20 24 3 6.2 21

اص

ػج١ض130 107

1.97 1.97 138 167 203

Fuqeiqi

s

50287

5 227 271 فم١م١ؾ 42 6.5 7 35 44 271 138 133

1.79 1.79 286 341 407

Khursa 50289

5

1,73

3

1,70

7

3,44

0 3,440 سغؿب 554 6.2 82 567 599

2,43

8 3.50 3.50 3,814 5,382 7,594

Tarram

a

50290

0 399 631 طغاخ 106 6 8 115 121 631 331 300

4.69 4.69 724 1,145 1,811

Al

Fawwar

Camp

50290

5

3,35

4

3,19

0

6,54

4

1,09

2 762 191 6.4 1,029

ش١

افاع6,544

4,78

4 3.18 3.18 7,189 9,834 13,451

Al

Majd

50291

0 970 955

1,92

5 1,925 اجض 315 6.1 57 333 335

1,49

3 62 2.57 2.57 2,078 2,679 3,454

Marah

al

Baqqar

50291

5 101 114 215 50 46 1 5.4 40

غاح

اجمبع215 139

4.46 4.46 245 379 586

Hadab

al

Fawwar

50292

0 964 954

1,91

8 347 262 24 6.2 308

دضة

أفاع1,918

1,31

5 3.85 3.85 2,148 3,133 4,570

Deir al

'Asal at

Tahta

50292

5 266 289 555 111 100 12 6.2 89

ص٠غ

اؼـ

ازذزب

555 433

2.51 2.51 598 766 982

Al

Heila

50293

5 641 636

1,27

7 707 1,277 اذ١خ 169 7.6 3 186 173

6.09 6.09 1,525 2,754 4,975

Wadi

ash

50294

0 361 354 715 122 109 6 5.9 121

اص

البجخ715 451 63 4.72 4.72 821 1,302 2,063

270

Shajina

As Sura 50295

0 975 950

1,92

5 1,925 اوغح 293 6.6 52 299 323

1,26

7 4.27 4.27 2,182 3,316 5,038

Deir

Razih

50295

5 135 133 268 50 47 2 6.2 43

ص٠غ

عاػح268 233

1.41 1.41 279 321 370

Ar

Rihiya

50296

0

2,06

6

1,88

3

3,94

9 3,949 اغ٠ذ١خ 511 7.7 36 472 519

2,47

4 4.79 4.79 4,544 7,253 11,577

Zif 50296

5 648 848 ػ٠ف 98 8.7 4 117 114 848 423 425

2.73 2.73 919 1,203 1,574

Deir al

'Asal al

Fauqa

50297

0 782 816

1,59

8 282 246 19 6.5 244

ص٠غ

اؼـ

افلب

1,598 1,31

3 1.98 1.98 1,695 2,063 2,511

Khallet

al

'Aqed

50297

5 141 131 272 54 62 7 6.5 42

سخ

اؼمض272 148

6.27 6.27 326 600 1,103

Imreish 50298

0 830 835

1,66

5 1,665 إغ٠ق 281 5.9 20 305 298

1,16

1 64 3.67 3.67 1,855 2,661 3,816

Al

Buweib

50300

5 381 607 اج٠ت 76 8 2 159 152 607 316 291

4.77 4.77 698 1,112 1,772

Beit ar

Rush at

Tahta

50301

0 187 186 373 74 74 11 6 62

ث١ذ

اغف

ازذزب

373 352

0.58 0.58 380 402 426

Hadab

al

'Alaqa

50304

0 309 332 641 119 124 20 5.8 111

دضة

اؼمخ641 381

5.34 5.34 749 1,261 2,121

Beit

Mirsim

50307

5 160 158 318 77 85 5 5.5 58

ث١ذ

غؿ318 238 65 2.94 2.94 347 463 619

Beit ar

Rush al

Fauqa

50309

0 519 460 979 158 162 15 6.5 151

ث١ذ

اغف

افلب

979 685

3.64 3.64 1,090 1,557 2,226

271

Karma 50309

5 721 665

1,38

6 966 1,386 وغخ 239 5.8 15 228 255

3.68 3.68 1,545 2,216 3,180

Beit

'Amra

50310

0

1,11

6

1,04

9

2,16

5 293 295 13 7.5 289

ث١ذ

ػغح2,165

1,20

6 6.03 6.03 2,580 4,632 8,316

Om

Adaraj

(Arab

Al

Ka’abn

eh)

50310

5 420 393 813 116 126 0

10.

7 76

أ اضعط

)ػغة

اىؼبث(

813 417

6.90 6.90 993 1,937 3,776

Wadi al

Kilab

50311

0 26 21 47 15 19 1 7.8 6

اص

اىالة47 23

7.41 7.41 58 119 243

Om

Ashoqh

an

50311

1 152 144 296 62 70 1 7.2 41

أ

المذب296 172

5.58 5.58 348 599 1,032

Khallet

al

Maiyya

50311

5 722 690

1,41

2 188 205 10 7.6 187

سخ

ا١خ1,412 900

4.61 4.61 1,616 2,536 3,978

Kheros

hewesh

Wal

Hadede

yah

50311

6 177 202 379 67 90 0 6.5 58

س١غك

٠ف

اذض٠ض

٠خ

379 245

4.46 4.46 432 668 1,034

Om Al

Amad

(Sahel

Wadi

Elma)

50311

7 83 69 152 38 50 2 5.2 29

أ اؼض

)ؿ

اص

ابء(

152 102

4.07 4.07 171 255 380

Yatta 50312

0

24,6

14

24,0

58

48,6

72

7,82

8 ٠طب 7,077 6.9 931 7,455

48,67

2

33,6

88 66 3.75 3.75 54,353 78,528 113,456

272

Ad

Deirat

50312

5 2,207 1,416 908 4.54 4.54 67 510 795 اض٠غاد 98 8.1 10 115 104 795 408 387

Khashe

m

Adaraj

(Al-

Hathale

en)

50312

6 309 297 606 113 112 0 6.5 93

سل

اضعط

)اظا١

)

606 467

2.64 2.64 655 850 1,103

Kurza 50313

5 554 771 وغػح 137 5.6 12 127 138 771 388 383

3.36 3.36 851 1,185 1,649

Rabud 50314

5

1,11

4

1,14

8

2,26

2 2,262 عاثص 372 6.1 18 360 385

1,62

0 68 3.39 3.39 2,500 3,491 4,875

Umm

Lasafa

50315

0 398 853 أ وفب 110 7.8 1 152 142 853 415 438

7.92 7.92 1,072 2,298 4,925

Al Burj 50317

0

1,30

7

1,27

1

2,57

8 2,578 اجغط 418 6.2 49 452 486

1,97

0 69 2.73 2.73 2,795 3,657 4,786

Um Al-

Khair

50321

0 319 516 ا اش١غ 69 7.5 3 100 102 516 260 256

4.93 4.93 596 964 1,560

Al

Karmil

50321

5

1,89

7

1,84

4

3,74

1 3,741 اىغ 552 6.8 36 726 673

2,08

2 6.04 6.04 4,460 8,014 14,400

Khallet

Salih

50322

5 563 530

1,09

3 206 222 2 6.6 166

سخ

هبخ1,093 592 70 6.32 6.32 1,314 2,426 4,478

Adh

Dhahiri

ya

50324

5

14,5

81

14,1

95

28,7

76

4,89

0 4,552 829 6.4 4,469

اظبغ

٠خ

28,77

6

20,4

34 71 3.48 3.48 31,888 44,907 63,239

At

Tuwani

50325

5 1,652 816 403 7.31 7.31 72 161 326 ازا 52 6.3 2 77 76 326 155 171

Ma'in 50326

0 169 459 ؼ١ 58 7.9 1 85 72 459 240 219

10.5

1 7.50 570 1,175 2,422

An 50326 463 441 419 0.50 3.47- 73 588 413 اجبصح 51 8.1 2 96 104 413 196 217

273

Najada 5

'Anab

al

Kabir

50329

5 162 173 335 59 63 0 6.7 50

ػبة

اىج١غ335 218

4.39 4.39 381 586 900

Khirbet

Asafi

50330

5 53 42 95 13 13 0 9.5 10

سغثخ

اهف95 73

2.67 2.67 103 134 174

Mantiq

at Shi'b

al Batin

50331

0 71 66 137 29 29 0 6 23

طمخ

كؼت

اجط

137 33

15.3

0 7.50 170 351 723

As

Samu'

50332

0

9,96

3

9,68

6

19,6

49

3,22

0 اـع 2,950 6.7 372 3,019

19,64

9

13,9

99 74 3.45 3.45 21,753 30,532 42,855

Wadi

Al

Amayer

50332

1 245 236 481 71 73 6 8.3 58

اص

اؼب٠غ481 378

2.44 2.44 517 658 837

Khirbet

Tawil

ash

Shih

50332

5 100 82 182 28 31 0 7.6 24

سغثخ

ط٠

ال١خ

182 133

3.19 3.19 200 274 374

Ar

Ramadi

n

50333

5

1,62

5

1,65

6

3,28

1 561 566 22 6.7 487

اغبض

٠ 3,281

2,17

9 4.18 4.18 3,710 5,586 8,411

Magha

yir al

'Abeed

50334

5 2 2 4 2 2 0 4 1

غب٠غ

اؼج١ض4 27

-

17.3

8

0.50 4 4 4

Khirbet

al

Fakheit

50335

0 114 117 231 57 57 0 5.6 41

سغثخ

افش١ذ231 42 75

18.5

9 7.50 287 591 1,219

Khirbet

Bir al

'Idd

50336

0 65 54 119 40 41 0 5.2 23

سغثخ

ث١غ اؼض119 178 76 -3.95 0.50 121 127 133

274

Khirbet

Zanuta

50337

5 32 28 60 16 16 0 4.6 13

سغثخ

ػرخ60 6

25.8

9 7.50 75 154 317

Imneizi

l

50338

0 190 390 إ١ؼي 49 8 0 55 59 390 186 204

7.46 7.46 484 993 2,039

'Arab al

Fureijat

50340

5 260 312 572 104 100 2 6.7 85

ػغة

افغ٠جب

د

572 338 77 5.40 5.40 670 1,133 1,918

Total

Hebro

n Gov.

281,

570

270,

594

552,

164

103,

086

80,44

8

16,

447 6.1

89,91

9

يجوع

يحافظة

انخهيم

552,1

64

389,

716 3.88

613,53

8 874,304

1,251,9

89

Total

West

Bank

1,19

3,24

4

1,15

7,33

9

2,35

0,58

3

456,

314

319,2

70

77,

639 5.5

427,0

97

يجوع

انضفة

انغربية

2,350

,583

1,58

2,70

9

2,329,

965

3,195,7

33

4,468,4

05

275

* Comment on Community:

Comment No.

Community Code

Community Name

Actual Population 1997

اؿ ازجغ

1

Population of Faqqu'a in 2007 include

10,060 Faqqu'a 2,570 فمػخ

10,065 Khirbet Abu 'Anqar 11 سغثخ أث ػمغ

10,100 Barghasha 54 ثغغلخ

Total 2,635 اجع

2

Population of Barta'a ash Sharqiya in 2007 include

10,120 Barta'a ash Sharqiya

ثغطؼخ الغل١خ 2,653

10,130 Khirbet ash Sheikh Sa'eed

161 سغثخ ال١ز

ؿؼ١ض

Total 2,814 اجع

3

Population of Beit Qad in 2007 include

10,140 Beit Qad 642 ث١ذ لبص

10,160 Umm Qabub 68 أ لبثة

10,110 Mashru' Beit Qad 285 لغع ث١ذ لبص

Total 995 اجع

4

Population of Jenin in 2007 include

10,180 Jenin 26,332 ج١

10,075 Dahiyat Sabah al Kheir

1,073 ضبد١خ هجبح

اش١غ

10,270 'Arab as Suweitat 370 ػغة

اـ٠طبد

Total 27,775 اجع

5

Population of Kafr Qud in 2007 include

10,210 Kafr Qud 668 وفغ لص

10,260 Al Manshiya 117 ال١خ

Total 785 اجع

6

Population of Zabda in 2007 include

10,245 Zabda 612 ػثضح

10,255 Qeiqis 99 ل١من

)اموع(

Total 711 اجع

7

Population of Qabatiya in 2007 include

10,340 Qabatiya 14,502 لجبط١خ

10,280 Khirbet Sab'ein 22 سغثخ ؿجؼ١

Total 14,524 اجع

8

Population of Arraba in 2007 include

10,370 Arraba 7,356 ػغاثخ

10,365 Ad Damayra 218 اضب٠غح

Total 7,574 اجع

276

9

Population of Telfit in 2007 include

10,385 Telfit 82 رف١ذ

10,325 Tannin 39 ر١

Total 121 اجع

10

Population of Raba in 2007 include

10,405 Raba 2,237 عاثب

10,375 Khirbet Marah ar Raha

10 سغثخ غاح

اغ

10,390 Khirbet Kharruba 23 سغثخ سغثخ

Total 2,270 اجع

11

Population of Sir in 2007 include

10,495 Sir 566 ه١غ

10,540 Mantiqat al Heish 19 طمخ ا١ق

Total 585 اجع

12

Population of Kardala in 2007 include

50,455 Kardala 119 وغصخ

50,470 Khirbet Tell el Himma

سغثخ ر اذخ 91

Total 210 اجع

13

Population of Khirbet Humsa in 2007 include

50,871 Khirbet Humsa 17 سغثخ دوخ

50,851 Al Hadidiya 132 اذض٠ضح

Total 149 اجع

14

Population of Baqa ash Sharqiya in 2007 include

100,350 Baqa ash Sharqiya 3,015 ثبلخ الغل١خ

100,360 Nazlat Abu Nar 144 ؼخ أث بع

Total 3,159 اجع

15

Population of Tulkarm in 2007 include

100,645 Tulkarm 33,505 طىغ

100,640 Dhinnaba 6,215 طبثخ

100,675 Khirbet at Tayyah 257 سغثخ اط١بح

Total 39,977 اجع

16

Population of Anabta in 2007 include

100,665 Anabta 5,391 ػجزب

100,630 Kafr Rumman 641 عبوفغ

Total 6,032 اجع

17

Population of Kafr al Labad in 2007 include

100,690 Kafr al Labad 2,970 وفغ اجض

100,655 'Izbat Abu Khameish

37 ػؼثخ أث

س١ق

100,685 'Izbat al Khilal 69 ػؼثخ اشالي

Total 3,076 اجع

18 Population of Shufa in 2007 include

100,760 Shufa 924 كفخ

277

100,725 'Izbat Shufa 726 ػؼثخ كفخ

Total 1,650 اجع

19

Population of Burqa in 2007 include

150,680 Burqa 2,973 ثغلخ

150,750 Al Mas'udiya 14 اـؼص٠خ

Total 2,987 اجع

20

Population of Al 'Aqrabaniya in 2007 include

150,840 Al 'Aqrabaniya 660 اؼمغثب١خ

150,850 Kirbet Tall al Ghar 9 سغثخ ر اغبع

150,940 Shihda wa Hamlan 34 كذض ال

Total 703 اجع

21

Population of Nablus in 2007 include

150,920 Nablus 98,919 بثؾ

150,890 Al Juneid 285 اج١ض

Total 99,204 اجع

22

Population of Al Ar Rajman in 2007 include

151,220 Ar Rajman 1 اغجب

151,176 Khirbet Tana 15 سغثخ طبب

151,235 Jafa an Nun 13 جفب ا

151,240 Ad Dawa 0 اضا

Total 29 اجع

23

Population of Qaryut in 2007 include

151,410 Qaryut 1,821 لغ٠د

151,450 Khirbet Sarra 25 سغثخ هغح

Total 1,846 اجع

24

Population of Duma in 2007 include

151,445 Duma 1,637 صب

151,465 Khirbet al Marajim 6 سغثخ اغاد

Total 1,643 اجع

25

Population of Khirbet Sir in 2007 include

200,995 Khirbet Sir 377 سغثخ ه١غ

200,980 'Izbat Abu Hamada 3 ػؼثخ أث دبصح

Total 380 اجع

26

Population of 'Izbat at Tabib in 2007 include

201,075 Izbat at Tabib 148 ػؼثخ اطج١ت

201,060 Mahattat Tahseen Mansur

19 رذـ١ ذطخ

وع

Total 167 اجع

27

Population of Deir Istiya in 2007 include

251,250 Deir Istiya 2,766 ص٠غ إؿز١ب

251,150 Wadi Qana 52 اص لبب

Total 2,818 اجع

28 Population of Haris in 2007 include

251,310 Haris 2,201 دبعؽ

278

251,350 Dar Abu Basal 4 صاع أث ثو

Total 2,205 اجع

29

Population of Kafr ad Dik in 2007 include

251,425 Kafr ad Dik 3,698 وفغ اض٠ه

251,390 Khirbet Susa 10 سغثخ ؿؿخ

Total 3,708 اجع

30

Population of Bani Zeid ash Sharqiya in 2007 include

301,460 Mazari' an Nubani 1,753 ؼاعع اثب

301,475 'Arura 2,072 ػبععح

Total 3,825 اجع

31

Population of Kafr Malik in 2007 include

301,590 Kafr Malik 2,098 وفغ به

301,580 'Ein Samiya 122 ػ١ ؿب١خ

Total 2,220 اجع

32

Population of AL-Itihad in 2007 include

301,620 Beitillu 2,152 ث١ز

301,630 Jammala 1,015 جبال

301,655 Deir 'Ammar 1,686 ص٠غ ػبع

Total 4,853 اجع

33

Population of AL-Zaytouneh in 2007 include

301,695 Al Mazra'a al Qibliya

اؼعػخ امج١خ 2,964

301,670 Abu Shukheidim 1,299 أث كش١ض

Total 4,263 اجع

34

Population of Beituniya in 2007 include

301,825 Beituniya 9,268 ث١ز١ب

301,795 Khirbet Kafr Sheiyan

سغثخ ومغ ك١ب 25

Total 9,293 اجع

35

Population of Jericho (Ariha) in 2007 include

351,920 Jericho (Ariha) 14,551 أع٠ذب

351,880 Deir Quruntul 3 ص٠غ امغط

351,905 'Ein ad Duyuk at Tahta

689 ػ١ اض٠ن

ازذزب

Total 15,243 اجع

36

Population of Jericho (Ariha) in 2007 include

452,180 Al 'Ubeidiya 6,195 اؼج١ض٠خ

452,215 Wadi al 'Arayis 1,570 اص اؼغا٠ؾ

Total 7,765 اجع

37

Population of Dar Salah in 2007 include

452,225 Dar Salah 721 صاع هالح

452,220 Al Hujeila 74 اذج١١خ

452,245 Juhdum 1,007 جض

452,250 Umm al Qasseis 264 أ امـ١ؾ

279

452,260 Umm 'Asla 117 ػـخ أ

Total 2,183 اجع

38

Population of Hindaza in 2007 include

452,280 Hindaza 1,555 ضاػح

452,315 Khallet Hamad 344 سخ دض

452,320 Bureid'a 240 ثغ٠ضؼخ

452,310 Wadi Umm Qal'a 192 اص أ لؼخ

452,305 Dhahrat an Nada 290 ظغح اض

Total 2,621 اجع

39

Population of Ash Shawawra in 2007 include

452,285 Ash Shawawra 1,912 الاعح

452,290 Ras al Wad 569 عاؽ ااص

452,330 Al Khushna 49 اشلخ

452,295 Fakht al Jul 185 فشذ اجي

Total 2,715 اجع

40

Population of Za'tara in 2007 include

452,360 Za'tara 3,890 ػػزغح

452,375 Al Fureidis 518 فغ٠ضؽ

Total 4,408 اجع

41

Population of Jannatah in 2007 include

452,385 Jannatah

368 جبرخ )ث١ذ

فح(452,350 Rakhme 671 عسخ

452,365 Al 'Asakira 724 اؼـبوغح

452,395 Khallet al Qaranin 101 سخ امغا١

452,410 Al 'Iqab 645 اؼمبة

452,420 Harmala 548 دغخ

452,425 Abu Nujeim 566 أث ج١

Total 3,623 اجع

42

Population of Wadi Rahhal in 2007 include

452,400 Wadi Rahhal 413 اص عدبي

452,380 Al Beida 253 اج١ضب

452,370 Ath Thabra 179 اضجغح

452,340 Khirbet an Nahla 27 سغثخ اذخ

Total 872 اجع

43

Population of Khallet Sakariya in 2007 include

452,415 Khallet Sakariya 72 سخ ؿىبع٠ب

452,390 Khallet al Balluta 123 سخ اجطخ

Total 195 اجع

44

Population of Tuqu' in 2007 include

452,495 Tuqu' 4,827 رمع

452,455 Khirbet ad Deir 1,132 سغثخ اض٠غ

452,475 Al Halqum 130 اذم

452,520 Khirbet Tuqu' 76 سغثخ رمع

280

Total 6,165 اجع

45

Population of Al Maniya in 2007 include

452,535 Al Maniya 564 ا١خ

452,510 Wadi Muhammad 87 اص ذض

Total 651 اجع

46

Population of 'Arab ar Rashayida in 2007 include

452,660 Arab ar Rashayida 777 ػغة اغكب٠ضح

452,670 Al 'Azazima 59 اؼؼاػخ

452,715 Ar Rawa'in 111 اغاػ١

Total 947 اجع

47

Population of Beit Ummar in 2007 include

502,540 Beit Ummar 8,987 ث١ذ أغ

502,485 Safa 785 هبفب

502,505 Khirbet al Mantara 95 سغثخ اطغح

Total 9,867 اجع

48

Population of Kharas in 2007 include

502,560 Kharas 5,056 سبعاؽ

502,515 Khirbet Mushrif 44 سغثخ لغف

)ػظاة(Total 5,100 اجع

49

Population of Beit Ula in 2007 include

502,615 Beit Ula 6,726 ث١ذ أال

502,570 Qila 651 ل١ال

502,600 Ras al Jora 186 عاؽ اجعح

Total 7,563 اجع

50

Population of Sa'ir in 2007 include

502,620 Sa'ir 9,545 ؿؼ١غ

502,590 'Irqan Turad 361 ػغلب طغاص

502,595 Kuziba 338 وػ٠جب

502,610 Shamaliyyat al Hawa

كب١خ ا 67

502,665 Ras at Tawil 470 عاؽ اط٠

502,690 Ad Duwwara 1,196 اضاعح

502,725 Wadi ar Rim 68 اص اغ٠

502,735 Qinan an Namir 80 لب اغ

502,720 Al 'Uddeisa 1,046 اؼض٠ـخ

Total 13,171 اجع

51

Population of Halhul in 2007 include

502,630 Halhul 15,477 دذي

502,605 Al Baqqar 27 اجمبع

502,675 Khirbet al Hasaka 154 سغثخ اذـىخ

Total 15,658 اجع

52 Population of Ash Shuyukh in 2007 include

502,635 Ash Shuyukh 5,063 ال١ر

281

502,650 Qafan al Khamis 923 لفب اش١ؾ

Total 5,986 اجع

53

Population of Tarqumiya in 2007 include

502,640 Tarqumiya 10,429 رغل١ب

502,625 Khirbet Jamrura 12 سغثخ جغعح

Total 10,441 اجع

54

Population of Idhna in 2007 include

502,685 Idhna 13,364 إطب

502,645 Bir Musallam 135 ث١غ ـ

502,730 Suba 83 ؿثب

Total 13,582 اجع

55

Population of Taffuh in 2007 include

502,750 Taffuh 6,962 رفح

502,710 Al Khamajat 103 اشجبد

Total 7,065 اجع

56

Population of Beit Maqdum in 2007 include

502,765 Beit Maqdum 507 ث١ذ مض

502,770 Al Kum 945 اى

502,795 Al Muwarraq 415 اعق

Total 1,867 اجع

57

Population of Hebron (Al Khalil) in 2007 include

502,780 Hebron (Al Khalil) 117,839 اش١

502,880 Birin 123 ث١غ٠

Total 117,962 اجع

58

Population of Idhna in 2007 include

502,810 Deir Samit 4,066 ص٠غ ؿبذ

502,800 Tarusa 39 طبعؿخ

502,785 Humsa 13 دوخ

Total 4,118 اجع

59

Population of Bani Na'im in 2007 include

502,815 Bani Na'im 13,404 ث ؼ١

502,705 Jurun al Louz 44 جغ اػ

Total 13,448 اجع

60

Population of Dura in 2007 include

502,840 Dura 15,300 صعا

502,820 Rafada 303 عفبصح

502,845 Wadih 48 اضخ

502,850 At Tabaqa 1,018 اطجمخ

502,805 Kureise 1,616 وغ٠ـخ

502,885 Al Hijra 482 اجغح

Total 18,767 اجع

61

Population of Sikka in 2007 include

502,860 Sikka 572 ؿىخ

502,890 Tawas 104 طاؽ

282

Total 676 اجع

62

Population of Al Majd in 2007 include

502,910 Al Majd 1,292 اجض

502,930 Khirbet Abu Hamid 83 سغثخ أث دبض

502,985 Iskeik 118 إؿى١ه

Total 1,493 اجع

63

Population of Wadi ash Shajina in 2007 include

502,940 Wadi ash Shajina 404 اص البجخ

503,015 Khirbet Bism 47 سغثخ ثـ

Total 451 اجع

64

Population of Imreish in 2007 include

502,980 Imreish 880 إغ٠ق

503,000 'Abda 126 ػجضح

503,025 Al 'Alaqa al Fauqa 67 اؼمخ افلب

503,050 Al 'Alaqa at Tahta 88 ازذزباؼمخ

Total 1,161 اجع

65

Population of Beit Mirsim in 2007 include

503,075 Beit Mirsim 204 ث١ذ غؿ

503,055 Abu Suhweila 34 أث ؿذ١خ

Total 238 اجع

66

Population of Yatta in 2007 include

503,120 Yatta 30,420 ٠طب

502,995 Biyar al 'Arus 650 ث١بع اؼغؽ

503,020 Ad Duweir 490 اض٠غ

503,060 Qinan an Najma 114 لب اجخ

503,070 Qurnet ar Ras 194 لغخ اغاؽ

503,085 Khurisa 29 سغ٠ـخ

503,175 Al Muntar 283 اطبع

503,190 I'zeiz 507 إػؼ٠ؼ

503,030 Wadi as Sada 156 اـبصحاص

503,035 Khallet 'Arabi 137 سخ اؼغث

502,990 Hureiz 708 دغ٠ؼ

Total 33,688 اجع

67

Population of Ad Deirat in 2007 include

503,125 Ad Deirat 279 اض٠غاد

503,080 Ar Rifa'iyya 231 اغفبػ١خ

Total 510 اجع

68

Population of Rabud in 2007 include

503,145 Rabud 433 عاثص

503,160 Abu al Ghuzlan 402 أث اغؼال

503,155 Abu al 'Asja 443 أث اؼـجب

503,185 Abu al 'Urqan 342 أث اؼغلب

Total 1,620 اجع

69 Population of Al Burj in 2007 include

283

503,170 Al Burj 1,749 اجغط

503,165 Al Bira 221 اج١غح

Total 1,970 اجع

70

Population of Khallet Salih in 2007 include

503,225 Khallet Salih 300 سخ هبخ

503,220 Qinan Jaber 292 لب ججغ

Total 592 اجع

71

Population of Adh Dhahiriya in 2007 include

503,245 Adh Dhahiriya 20,279 اظبغ٠خ

503,270 Khirbet Deir Shams

42 سغثخ ص٠غ

الؾ

503,285 Khirbet Shuweika 86 سغثخ ك٠ىخ

503,195 Juwai & Kafr Jul 0 ج وفغجي

503,235 Somara 27 ؿغح

Total 20,434 اجع

72

Population of At Tuwani in 2007 include

503,255 At Tuwani 76 ازا

503,280 Ar Rakeez 0 اغو١ؼ

503,315 Qawawis 37 لا٠ؾ

503,290 Khirbet Sarura 48 سغثخ هبععح

Total 161 اجع

73

Population of An Najada in 2007 include

503,265 An Najada 168 اجبصح

503,130 Khashem al Karem 420 اىغ سل

Total 588 اجع

74

Population of As Samu' in 2007 include

503,320 As Samu' 12,743 اـع

503,230 As Simiya 1,210 اـ١١ب

503,385 Khirbet al Kharaba 2 سغثخ اشغاثخ

503,395 Khirbet Ghuwein al Fauqa

44 سغثخ ػ٠

افلب

Total 13,999 اجع

75

Population of Khirbet al Fakheit in 2007 include

503,350 Khirbet al Fakheit 20 سغثخ افش١ذ

503,330 Khirbet at Tabban 22 سغثخ ازجب

503,340 Khirbet al Majaz 0 سغثخ اجبػ

Total 42 اجع

76

Population of Khirbet Bir al 'Idd in 2007 include

503,360 Khirbet Bir al 'Idd 104 سغثخ ث١غ اؼض

503,355 Khirbet at Tawamin

سغثخ ازا١ 24

503,365 Haribat an Nabi 50 غ٠جخ اج

Total 178 اجع

77 Population of 'Arab al Fureijat in 2007 include

284

503,405 Arab al Fureijat 302 افغ٠جبدػغة

503,400 Khirbet ar Rahwa 36 سغثخ اغح

Total 338 اجع

285

ANNEX A

MEMBERS OF THE ENVIRONMENTAL ASSESSMENT COMMITTEE

286

ANNEX B

EXCEL PROGRAM RESULTS

287

Rating for each criteria Sheet:

No. Locality Name

Demography Water consumption

Actual Population

2007

Actual Population

1997*

Actual Growth-Rate

(2007-1997)**

Projected Population

2030***

score

Water consumption (L/day/cap)*

score

1 Silat al Harithiya 9,422 7,246 2.66 17,236 0.76 111 5

2 Al Yamun 16,383 12,255 2.95 31,943 1.41 77 4

3 Kafr Dan 5,148 3,766 3.18 10,565 0.47 57 3

4 Deir Abu Da'if 5,572 3,897 3.64 12,681 0.56 66 4

5 Birqin 5,685 4,344 2.73 10,555 0.47 78 4

6 Ya'bad 13,640 10,625 2.53 24,229 1.07 54 2

7 Qabatiya 19,197 14,524 2.83 36,465 1.61 68 4

8 Arraba 9,920 7,574 2.74 18,452 0.81 64 3

9 Kafr Ra'i 7,364 5,758 2.49 12,967 0.57 72 4

10 Meithalun 6,955 5,159 3.03 13,825 0.61 58 3

11 Jaba' 8,492 6,409 2.85 16,222 0.71 64 3

12 El Far'a Camp 5,712 4,152 3.24 11,896 0.52 45 2

13 Tammun 10,795 7,540 3.65 24,642 1.09 82 4

14 Qaffin 8,387 6,440 2.68 15,398 0.68 85 4

15 'Attil 9,038 7,661 1.67 13,218 0.58 90 4

16 Deir al Ghusun 8,242 6,969 1.69 12,123 0.53 96 5

17 Bal'a 6,604 5,373 2.08 10,614 0.47 76 4

18 'Asira ash Shamaliya 7,556 5,724 2.82 14,310 0.63 65 3

19 'Awarta 5,623 4,286 2.75 10,500 0.46 83 4

20 Huwwara 5,570 4,275 2.68 10,237 0.45 66 4

288

21 Beita 9,079 6,478 3.43 19,734 0.87 56 3

22 Jamma'in 6,225 4,263 3.86 14,870 0.66 62 3

23 Aqraba 8,180 5,849 3.41 17,693 0.78 106 5

24 Qabalan 7,130 5,346 2.92 13,827 0.61 33 1

25 'Azzun 7,821 5,794 3.05 15,592 0.69 140 5

26 Biddya 8,064 5,982 3.03 16,028 0.71 53 2

27 Sinjil 5,236 3,883 3.03 10,414 0.46 46 2

28 Shuqba 4,497 3,027 4.04 11,177 0.49 24 1

29 Qibya 4,901 3,441 3.60 11,055 0.49 56 3

30 Al Jalazun Camp 7,813 6,064 2.57 13,994 0.62 94 5

31 Kharbatha al Misbah 5,211 3,662 3.59 11,730 0.52 57 3

32 Beit Liqya 7,710 5,634 3.19 15,864 0.70 52 2

33 Ar Ram & Dahiyat al

Bareed 20,359 18,719 0.84 24,697 1.09

55 2

34 Biddu 6,798 4,657 3.86 16,226 0.72 68 4

35 Hizma 6,271 4,459 3.47 13,739 0.61 67 4

36 'Anata 12,049 7,037 5.53 41,509 1.83 88 4

37 Al 'Eizariya 17,606 12,724 3.30 37,157 1.64 108 5

38 Abu Dis 10,782 8,858 1.99 16,945 0.75 98 5

39 As Sawahira ash

Sharqiya 5,800 3,810 4.29 15,247 0.67

102 5

40 Al 'Ubeidiya 10,753 7,765 3.31 22,736 1.00 45 2

41 Husan 5,551 4,131 3.00 10,952 0.48 45 2

42 Nahhalin 6,827 4,638 3.94 16,611 0.73 55 2

43 Za'tara 6,289 4,408 3.62 14,242 0.63 40 1

44 Jannatah 5,416 3,623 4.10 13,655 0.60 45 2

45 Tuqu' 8,881 6,165 3.72 20,563 0.91 50 2

289

46 Beit Fajjar 11,004 7,896 3.37 23,609 1.04 60 3

47 Surif 13,365 9,541 3.43 29,016 1.28 30 1

48 Beit Ummar 13,548 9,867 3.22 28,091 1.24 50 2

49 Kharas 6,655 5,100 2.70 12,274 0.54 42 1

50 Beit Ula 10,885 7,563 3.71 25,150 1.11 35 1

51 Sa'ir 18,045 13,171 3.20 37,227 1.64 30 1

52 Halhul 22,128 15,658 3.52 49,025 2.16 35 1

53 Ash Shuyukh 8,811 5,986 3.94 21,437 0.94 45 2

54 Tarqumiya 14,357 10,441 3.24 29,868 1.32 40 1

55 Beit Kahil 6,526 4,159 4.61 18,393 0.81 50 2

56 Idhna 19,012 13,582 3.42 41,207 1.82 45 2

57 Taffuh 10,597 7,065 4.14 26,924 1.19 30 1

58 Deir Samit 6,237 4,118 4.24 16,205 0.71 55 2

59 Bani Na'im 20,084 13,448 4.09 50,523 2.23 42 1

60 Beit 'Awwa 8,064 5,924 3.13 16,391 0.72 25 1

61 Dura 28,268 18,767 4.18 72,521 3.20 50 2

62 Yatta 48,672 33,688 3.75 113,456 5.00 30 1

63 Adh Dhahiriya 28,776 20,434 3.48 63,239 2.79 55 2

64 As Samu' 19,649 13,999 3.45 42,855 1.89 60 3

113,456

290

Note

* From PCBS

* Water consumption (PWA, 2005)

** Actual Growth-Rate= (population 2007 / Population 1997)(1/10) - 1

*** Expected population in (2030) = Population

in (2007)* (1+r)^23

Rating-Equation

>=L/day/cap score

adjustable

Ds = 5 x P/ Ph (highest population)

0 1

45 2

56 3

66 4

91 5

Rating 1 point: < 45L/day/cap

2 points: 45 - 55L/day/cap

3 points: 56 - 65L/day/cap

4 points: 66 - 90L/day/cap

5 points: > 91 L/day/cap

291

No. Locality Name

Reuse Environmental factor

Agricultural land value* score

Hydrological vulnerability to Grounwater*

score

springs or wells in the

region** score

Total Score

1 Silat al Harithiya High 5 High 3 No 1 4

2 Al Yamun High 5 Low 1 Yes 2 3

3 Kafr Dan High 5 Medium 2 Yes 2 4

4 Deir Abu Da'if High 5 High 3 No 1 4

5 Birqin Medium 3 Low 1 Yes 2 3

6 Ya'bad Medium 3 Medium 2 Yes 2 4

7 Qabatiya Medium+High 4 High 3 Yes 2 5

8 Arraba Medium+High 4 Low 1 Yes 2 3

9 Kafr Ra'i Low+Medium 2 Medium 2 No 1 3

10 Meithalun low+Medium+High 3 High 3 No 1 4

11 Jaba' Medium 3 High 3 Yes 2 5

12 El Far'a Camp High 5 High 3 Yes 2 5

13 Tammun Low 1 Low 1 Yes 2 3

14 Qaffin Medium 3 Low 1 Yes 2 3

15 'Attil High 5 Medium 2 Yes 2 4

16 Deir al Ghusun High 5 Low 1 Yes 2 3

17 Bal'a Low+Medium 2 Medium 2 Yes 2 4

18 'Asira ash Shamaliya

Low 1

High 3 No 1 4

19 'Awarta Low+Medium+High 3 Low 1 Yes 2 3

20 Huwwara Low+Medium 2 Low 1 Yes 2 3

21 Beita Low+Medium 2 Medium 2 No 1 3

22 Jamma'in Low+Medium 2 High 3 No 1 4

23 Aqraba Low+Medium 2 High 3 Yes 2 5

292

24 Qabalan Low+Medium 2 High 3 No 1 4

25 'Azzun Low+Medium 2 Medium 2 Yes 2 4

26 Biddya Low+Medium 2 High 3 No 1 4

27 Sinjil Low+Medium 2 High 3 Yes 2 5

28 Shuqba Low+Medium 2 High 3 Yes 2 5

29 Qibya Low+Medium 2 High 3 No 1 4

30 Al Jalazun Camp Low+High 3 High 3 No 1 4

31 Kharbatha al

Misbah Medium

3 Low 1 No 1 2

32 Beit Liqya Medium+High 4 Medium 2 Yes 2 4

33 Ar Ram & Dahiyat al

Bareed Low

1 High 3 No 1 4

34 Biddu Medium 3 High 3 No 1 4

35 Hizma Low 1 High 3 Yes 2 5

36 'Anata Low 1 High 3 No 1 4

37 Al 'Eizariya Low 1 Low 1 Yes 2 3

38 Abu Dis Low 1 Low 1 No 1 2

39 As Sawahira ash

Sharqiya Low

1 Low 1 Yes 2 3

40 Al 'Ubeidiya Low 1 Low 1 No 1 2

41 Husan Medium 3 High 3 Yes 2 5

42 Nahhalin Medium 3 High 3 Yes 2 5

43 Za'tara Low+Medium 2 Low 1 Yes 2 3

44 Jannatah Low+Medium 2 Medium 2 No 1 3

45 Tuqu' Low+Medium 2 High 3 Yes 2 5

46 Beit Fajjar Low+Medium 2 High 3 Yes 2 5

47 Surif Low 1 High 3 No 1 4

48 Beit Ummar Low+Medium 2 High 3 Yes 2 5

293

49 Kharas Low 1 High 3 No 1 4

50 Beit Ula Low 1 Medium 2 No 1 3

51 Sa'ir Low+Medium 2 High 3 Yes 2 5

52 Halhul Low+Medium 2 High 3 Yes 2 5

53 Ash Shuyukh Low 1 High 3 Yes 2 5

54 Tarqumiya Low 1 High 3 No 1 4

55 Beit Kahil Low+Medium 2 High 3 Yes 2 5

56 Idhna Low 1 Low 1 Yes 2 3

57 Taffuh Low+Medium 2 High 3 Yes 2 5

58 Deir Samit Low+Medium 2 Low 1 No 1 2

59 Bani Na'im Low 1 Low 1 Yes 2 3

60 Beit 'Awwa Low+Medium 2 Low 1 No 1 2

61 Dura Low 1 High 3 Yes 2 5

62 Yatta Low 1 Medium 2 Yes 2 4

63 Adh Dhahiriya Low+Medium+High 3 Low 1 No 1 2

64 As Samu' Low 1 Low 1 Yes 2 3

Note

* Agricultural land map (published by MoA)

* hydrological vulnerability map (published by UNEP in cooperation with the EQA, 2002)

** GIS database

Rating-Equation

Agricultural land value score Hydrological

vulnerability to Grounwater

score springs or

wells in the region

score

adjustable Low 1 Low 1 No 1

Low+Medium 2 Medium 2 Yes 2

Medium 3 High 3

Low+Medium+High 3

Low+High 3

Medium+High 4

High 5

294

Rating 1 points: Low-value agricultural land 1 point: No springs and wells in the region

3 points: Medium -value agricultural land 2 points: >= 1 springs or wells in the region

5 points: High-value agricultural land 1 point: Low hydrological vulnerability

2 points: Medium hydrological vulnerability

3 points: High hydrological vulnerability

No. Locality Name

Operation body Risk for Industrial Waste

Rank of municipality-

MoLG* score

Rank of municipality-

MDLF** score

Total Score

olive presses

*

stonecutters*

textiles*

Total score

1 Silat al Harithiya C 1.5 C 2 3.5 1 2 0 3 4

2 Al Yamun B 2 C 2 4 4 3 0 7 3

3 Kafr Dan Village Council 0.5 C 2 2.5 1 0 0 1 4

4 Deir Abu Da'if Village Council 0.5 C 2 2.5 1 0 0 1 4

5 Birqin C 1.5 C 2 3.5 3 0 0 3 4

6 Ya'bad B 2 C 2 4 2 0 0 2 4

7 Qabatiya B 2 C 2 4 4 64 0 68 1

8 Arraba B 2 C 2 4 5 3 0 8 3

9 Kafr Ra'i C 1.5 C 2 3.5 5 1 0 6 3

10 Meithalun C 1.5 C 2 3.5 2 2 0 4 4

11 Jaba' C 1.5 C 2 3.5 2 1 0 3 4

12 El Far'a Camp Projects Committee 0.5 C 2 2.5 0 0 0 0 5

13 Tammun C 1.5 C 2 3.5 0 5 0 5 3

14 Qaffin C 1.5 C 2 3.5 3 2 0 5 3

15 'Attil C 1.5 C 2 3.5 2 3 0 5 3

16 Deir al Ghusun C 1.5 C 2 3.5 4 1 0 5 3

17 Bal'a C 1.5 C 2 3.5 2 1 0 3 4

18 'Asira ash Shamaliya

C 1.5 C 2 3.5

3 2 0 5 3

19 'Awarta Village Council 0.5 C 2 2.5 2 0 0 2 4

295

20 Huwwara C 1.5 C 2 3.5 0 2 0 2 4

21 Beita C 1.5 C 2 3.5 5 0 0 5 3

22 Jamma'in C 1.5 C 2 3.5 2 30 0 32 1

23 Aqraba C 1.5 C 2 3.5 2 2 0 4 4

24 Qabalan C 1.5 C 2 3.5 3 1 0 4 4

25 'Azzun C 1.5 C 2 3.5 2 0 0 2 4

26 Biddya C 1.5 C 2 3.5 5 0 0 5 3

27 Sinjil C 1.5 E 1 2.5 0 0 0 0 5

28 Shuqba Village Council 0.5 C 2 2.5 1 1 0 2 4

29 Qibya Village Council 0.5 C 2 2.5 0 1 0 1 4

30 Al Jalazun Camp Projects Committee 0.5 C 2 2.5 0 0 0 0 5

31 Kharbatha al

Misbah Village Council 0.5 C 2 2.5

2 2 0 4 4

32 Beit Liqya C 1.5 C 2 3.5 1 2 0 3 4

33 Ar Ram & Dahiyat

al Bareed C 1.5 C 2 3.5

1 4 0 5 3

34 Biddu C 1.5 C 2 3.5 2 3 0 5 3

35 Hizma Village Council 0.5 C 2 2.5 0 5 0 5 3

36 'Anata C 1.5 E 1 2.5 0 11 0 11 2

37 Al 'Eizariya C 1.5 C 2 3.5 0 0 1 1 4

38 Abu Dis C 1.5 C 2 3.5 0 0 0 0 5

39 As Sawahira ash

Sharqiya C 1.5 C 2 3.5

0 0 0 0 5

40 Al 'Ubeidiya C 1.5 C 2 3.5 0 0 0 0 5

41 Husan Village Council 0.5 C 2 2.5 0 0 0 0 5

42 Nahhalin Village Council 0.5 C 2 2.5 0 0 0 0 5

43 Za'tara C 1.5 C 2 3.5 0 0 0 0 5

44 Jannatah D 1 C 2 3 0 0 0 0 5

45 Tuqu' C 1.5 C 2 3.5 0 1 0 1 4

296

46 Beit Fajjar C 1.5 C 2 3.5 0 182 0 182 1

47 Surif C 1.5 C 2 3.5 2 2 0 4 4

48 Beit Ummar C 1.5 C 2 3.5 0 15 0 15 2

49 Kharas C 1.5 C 2 3.5 2 2 0 4 4

50 Beit Ula C 1.5 C 2 3.5 1 0 0 1 4

51 Sa'ir B 2 C 2 4 2 12 0 14 2

52 Halhul B 2 C 2 4 0 9 0 9 3

53 Ash Shuyukh C 1.5 C 2 3.5 0 15 0 15 2

54 Tarqumiya C 1.5 C 2 3.5 1 5 0 6 3

55 Beit Kahil Village Council 0.5 C 2 2.5 0 0 0 0 5

56 Idhna B 2 B 2.5 4.5 3 6 0 9 3

57 Taffuh C 1.5 C 2 3.5 0 0 0 0 5

58 Deir Samit C 1.5 C 2 3.5 1 0 0 1 4

59 Bani Na'im B 2 C 2 4 1 4 0 5 3

60 Beit 'Awwa C 1.5 C 2 3.5 0 13 0 13 2

61 Dura B 2 B 2.5 4.5 1 0 0 1 4

62 Yatta B 2 C 2 4 2 9 0 11 2

63 Adh Dhahiriya B 2 C 2 4 2 8 0 10 2

64 As Samu' B 2 C 2 4 0 0 0 0 5

Note * http://www.molg.pna.ps/LGU.aspx

* From municipalities and Village councils

**http://www.mdlf.org.ps/Details.aspx?LangID=En&PageID=49&mi

d=22

Rating-Equation

Rank of municipality-

MoLG score

Rank of municipality-

MDLF score

>= score

adjustable Village Council 0.5 F 0.5

16 1

Projects Committee 0.5 E 1

10 2

D 1 D 1.5

5 3

297

C 1.5 C 2

1 4

B 2 B 2.5

0 5

A 2.5 A 2.5

Rating

0.5 point: Village Council or

Projects Committee

0.5 point: F

1 point: > 15 stonecutters +

olive presses + textiles

1 point: E

2 points: Between 10 and 15

1 point: D 1.5 point: D

3 points: Between 5 and 10

1.5 point: C 2 point: C

4 points: < 5

2 point: B 2.5 point: A,B

5 points: No stonecutters +

olive presses + textiles

2.5 point: A

298

No. Locality Name

Socio-economic factor

Total population aged 10 years

and over*

Ph.D*

Master*

Higher

Diploma*

Bachelor*

Total bachelor degree

or higher*

% holds a B.Sc.

or higher*

score

Economically

Active*

% Economicall

y Active*

score Total Score

1 Silat al Harithiya 6,640 13 27 4 356 400 6 1.5 2,042 31 1.5 3.0

2 Al Yamun 11,484 9 27 7 477 520 5 0.5 3,675 32 1.5 2.0

3 Kafr Dan 3,585 1 8 191 200 6 1.5 1,157 32 1.5 3.0

4 Deir Abu Da'if 3,805 10 3 162 175 5 0.5 1,334 35 2.5 3.0

5 Birqin 4,159 6 20 4 336 366 9 1.5 1,518 36 2.5 4.0

6 Ya'bad 9,759 14 36 7 675 732 8 1.5 3,132 32 1.5 3.0

7 Qabatiya 13,446 10 45 12 703 770 6 1.5 3,494 26 0.5 2.0

8 Arraba 7,127 4 28 5 468 505 7 1.5 2,206 31 1.5 3.0

9 Kafr Ra'i 5,325 4 22 5 271 302 6 1.5 1,636 31 1.5 3.0

10 Meithalun 5,054 14 50 11 423 498 10 1.5 1,656 33 1.5 3.0

11 Jaba' 6,079 3 15 3 280 301 5 0.5 1,680 28 0.5 1.0

12 El Far'a Camp 3,778 3 12 1 227 243 6 1.5 1,316 35 1.5 3.0

13 Tammun 7,651 7 35 4 570 616 8 1.5 2,586 34 1.5 3.0

14 Qaffin 6,041 3 15 1 267 286 5 0.5 1,840 30 1.5 2.0

15 'Attil 6,793 26 4 534 564 8 1.5 2,208 33 1.5 3.0

16 Deir al Ghusun 6,079 7 47 13 583 650 11 2.5 2,052 34 1.5 4.0

17 Bal'a 4,756 3 15 2 225 245 5 1.5 1,474 31 1.5 3.0

18 'Asira ash Shamaliya 5,557 12 52 11 649 724 13 2.5 2,023 36 2.5 5.0

19 'Awarta 3,982 8 1 193 202 5 1.5 1,292 32 1.5 3.0

20 Huwwara 3,948 3 20 3 221 247 6 1.5 1,201 30 1.5 3.0

21 Beita 6,198 6 33 2 383 424 7 1.5 1,902 31 1.5 3.0

22 Jamma'in 4,206 4 21 1 263 289 7 1.5 1,261 30 0.5 2.0

299

23 Aqraba 5,625 1 6 145 152 3 0.5 1,713 30 1.5 2.0

24 Qabalan 5,030 1 11 1 164 177 4 0.5 1,551 31 1.5 2.0

25 'Azzun 5,414 3 21 7 390 421 8 1.5 1,765 33 1.5 3.0

26 Biddya 5,563 5 41 2 377 425 8 1.5 1,791 32 1.5 3.0

27 Sinjil 3,459 5 12 4 139 160 5 0.5 1,129 33 1.5 2.0

28 Shuqba 2,929 1 6 1 105 113 4 0.5 1,014 35 1.5 2.0

29 Qibya 3,253 3 101 104 3 0.5 1,163 36 2.5 3.0

30 Al Jalazun Camp 5,158 2 15 162 179 3 0.5 1,773 34 1.5 2.0

31 Kharbatha al

Misbah 3,478 1 7 1 106 115 3 0.5 1,091 31 1.5 2.0

32 Beit Liqya 5,226 16 1 260 277 5 1.5 1,692 32 1.5 3.0

33 Ar Ram & Dahiyat al

Bareed 9,589 16 101 12 698 827 9 1.5 3,520 37 2.5 4.0

34 Biddu 4,303 2 10 2 193 207 5 0.5 1,420 33 1.5 2.0

35 Hizma 3,962 9 28 5 329 371 9 1.5 1,286 32 1.5 3.0

36 'Anata 6,067 9 32 12 331 384 6 1.5 2,064 34 1.5 3.0

37 Al 'Eizariya 8,703 18 53 10 464 545 6 1.5 2,873 33 1.5 3.0

38 Abu Dis 6,141 28 119 22 647 816 13 2.5 2,307 38 2.5 5.0

39 As Sawahira ash

Sharqiya 3,282 15 24 3 189 231 7 1.5 1,088 33 1.5 3.0

40 Al 'Ubeidiya 7,142 3 10 1 287 301 4 0.5 2,205 31 1.5 2.0

41 Husan 3,872 4 9 10 138 161 4 0.5 1,295 33 1.5 2.0

42 Nahhalin 4,542 11 21 12 314 358 8 1.5 1,442 32 1.5 3.0

43 Za'tara 4,209 5 17 9 305 336 8 1.5 1,316 31 1.5 3.0

44 Jannatah 3,572 2 2 98 102 3 0.5 1,023 29 0.5 1.0

45 Tuqu' 6,047 1 11 1 267 280 5 0.5 1,727 29 0.5 1.0

46 Beit Fajjar 7,517 2 17 3 264 286 4 0.5 2,387 32 1.5 2.0

47 Surif 9,381 8 31 13 789 841 9 1.5 2,198 23 0.5 2.0

48 Beit Ummar 9,331 25 55 12 799 891 10 1.5 3,066 33 1.5 3.0

300

49 Kharas 4,526 3 17 4 254 278 6 1.5 1,298 29 0.5 2.0

50 Beit Ula 7,160 3 9 3 343 358 5 1.5 2,180 30 1.5 3.0

51 Sa'ir 12,046 9 24 17 540 590 5 0.5 3,608 30 0.5 1.0

52 Halhul 15,475 32 93 33 1290 1448 9 1.5 5,215 34 1.5 3.0

53 Ash Shuyukh 5,956 2 25 5 325 357 6 1.5 1,747 29 0.5 2.0

54 Tarqumiya 9,978 9 31 4 651 695 7 1.5 3,089 31 1.5 3.0

55 Beit Kahil 4,169 1 14 6 327 348 8 1.5 1,154 28 0.5 2.0

56 Idhna 13,062 18 47 8 759 832 6 1.5 4,045 31 1.5 3.0

57 Taffuh 6,877 1 15 1 245 262 4 0.5 2,014 29 0.5 1.0

58 Deir Samit 3,999 3 5 147 155 4 0.5 1,074 27 0.5 1.0

59 Bani Na'im 13,194 15 36 3 579 633 5 0.5 4,151 31 1.5 2.0

60 Beit 'Awwa 5,557 3 4 4 194 205 4 0.5 1,684 30 1.5 2.0

61 Dura 19,514 53 156 31 1914 2154 11 2.5 6,355 33 1.5 4.0

62 Yatta 31,541 21 60 11 1267 1359 4 0.5 9,083 29 0.5 1.0

63 Adh Dhahiriya 19,245 14 41 25 793 873 5 0.5 6,152 32 1.5 2.0

64 As Samu' 13,116 9 33 6 734 782 6 1.5 3,447 26 0.5 2.0

Note

* Census Final Results – Summary, (Population, Buildings, Housing, Establishments) Census 2007, 2008-2009

Rating-Equation

score

score

adjustable

> 10 2.5 > 35 2.5

>= 5 1.5 > 30 1.5

>= 0 0.5 >= 0 0.5

301

Rating

0.5 point: <= 5% of the population hold a bachelor degree or higher of the total population aged 10 years and

over

1.5 points: 5% to 10% of the population hold a bachelor degree or higher of the total population aged 10 years

and over

2.5 point: > 10% of the population hold a bachelor degree or higher of the total population aged 10 years and

over

0.5 points: <= 30% of the population economically active of the total population aged 10 years and over

1.5 points: 30% to 35% of the population economically active of the total population aged 10 years and over

2.5 points: > 35% of the population economically active of the total population aged 10 years and over

No. Locality Name

Geographical factor Political Issues

% gravity

flow* score

No. of catchments*

score Total Score

settlement in the catchment

area* score

Political land classifications*

score Total Score

1 Silat al

Harithiya 50% to

75% 1 2 2

3 NO 2 A+B 2 4.0

2 Al Yamun

75% to 95%

1.5 2 2 3.5

NO 2 A+B 2 4.0

3 Kafr Dan > 95% 2 2 2 4 NO 2 A+B 2 4.0

4 Deir Abu Da'if > 95% 2 1 1 3 NO 2 A+B 2 4.0

5 Birqin

75% to 95%

1.5 2 2 3.5

NO 2 B 2 4.0

6 Ya'bad

50% to 75%

1 2 2 3

YES 1 B+C 1 2.0

302

7 Qabatiya > 95% 2 1 1 3 NO 2 B 2 4.0

8 Arraba <50% 0.5 > 2 3 3.5 NO 2 A+B+C 1 3.0

9 Kafr Ra'i

50% to 75%

1 > 2 3 4

NO 2 A 3 5.0

10 Meithalun > 95% 2 1 1 3 NO 2 A 3 5.0

11 Jaba'

75% to 95%

1.5 2 2 3.5

NO 2 B 2 4.0

12 El Far'a Camp > 95% 2 1 1 3 NO 2 A 3 5.0

13 Tammun

50% to 75%

1 2 2 3

NO 2 A+B 2 4.0

14 Qaffin > 95% 2 2 2 4 NO 2 B+C 1 3.0

15 'Attil > 95% 2 2 2 4 NO 2 B+C 1 3.0

16 Deir al Ghusun

50% to 75%

1 2 2 3

NO 2 B+C 1 3.0

17 Bal'a

75% to 95%

1.5 > 2 3 4.5

NO 2 A+B+C 1 3.0

18 'Asira ash Shamaliya

50% to 75%

1 2 2 3

NO 2 A+B 2 4.0

19 'Awarta

50% to 75%

1 2 2 3

YES 1 B+C 1 2.0

20 Huwwara > 95% 2 1 1 3 NO 2 B+C 1 3.0

21 Beita > 95% 2 2 2 4 NO 2 B+C 1 3.0

22 Jamma'in

50% to 75%

1 2 2 3

NO 2 B+C 1 3.0

23 Aqraba

50% to 75%

1 2 2 3

NO 2 B+C 1 3.0

24 Qabalan > 95% 2 2 2 4 NO 2 B 2 4.0

25 'Azzun > 95% 2 2 2 4 YES 1 B+C 1 2.0

303

26 Biddya

50% to 75%

1 2 2 3

YES 1 B+C 1 2.0

27 Sinjil > 95% 2 2 2 4 NO 2 A+B+C 1 3.0

28 Shuqba

50% to 75%

1 > 2 3 4

NO 2 B+C 1 3.0

29 Qibya <50% 0.5 > 2 3 3.5 NO 2 B+C 1 3.0

30 Al Jalazun

Camp 75% to

95% 1.5 2 2

3.5 YES 1 B+C 1 2.0

31 Kharbatha al

Misbah 50% to

75% 1 2 2

3 NO 2 B+C 1 3.0

32 Beit Liqya > 95% 2 1 1 3 NO 2 B+C 1 3.0

33 Ar Ram & Dahiyat al

Bareed <50% 0.5 > 2 3

3.5 YES 1 B+C 1 2.0

34 Biddu

50% to 75%

1 2 2 3

YES 1 B+C 1 2.0

35 Hizma

75% to 95%

1.5 2 2 3.5

YES 1 B+C 1 2.0

36 'Anata

75% to 95%

1.5 2 2 3.5

YES 1 B+C 1 2.0

37 Al 'Eizariya <50% 0.5 > 2 3 3.5 YES 1 B+C 1 2.0

38 Abu Dis <50% 0.5 > 2 3 3.5 YES 1 B+C 1 2.0

39 As Sawahira ash Sharqiya

50% to 75%

1 2 2 3

YES 1 B+C 1 2.0

40 Al 'Ubeidiya <50% 0.5 > 2 3 3.5 NO 2 A+C 1 3.0

41 Husan <50% 0.5 > 2 3 3.5 NO 2 B+C 1 3.0

42 Nahhalin <50% 0.5 > 2 3 3.5 YES 1 B+C 1 2.0

43 Za'tara 50% to 1 2 2 3 NO 2 A+B+C 1 3.0

304

75%

44 Jannatah <50% 0.5 > 2 3 3.5 NO 2 B+C 1 3.0

45 Tuqu' > 95% 2 2 2 4 YES 1 B+C 1 2.0

46 Beit Fajjar

50% to 75%

1 2 2 3

NO 2 B 2 4.0

47 Surif

50% to 75%

1 2 2 3

NO 2 B+C 1 3.0

48 Beit Ummar <50% 0.5 > 2 3 3.5 YES 1 B+C 1 2.0

49 Kharas > 95% 2 1 1 3 NO 2 B 2 4.0

50 Beit Ula

50% to 75%

1 > 2 3 4

NO 2 B 2 4.0

51 Sa'ir <50% 0.5 > 2 3 3.5 NO 2 B+C 1 3.0

52 Halhul

75% to 95%

1.5 > 2 3 4.5

NO 2 B+C 1 3.0

53 Ash Shuyukh

75% to 95%

1.5 2 2 3.5

NO 2 B+C 1 3.0

54 Tarqumiya <50% 0.5 > 2 3 3.5 YES 1 B+C 1 2.0

55 Beit Kahil

50% to 75%

1 2 2 3

NO 2 B+C 1 3.0

56 Idhna <50% 0.5 > 2 3 3.5 NO 2 B+C 1 3.0

57 Taffuh

50% to 75%

1 2 2 3

NO 2 A+B 2 4.0

58 Deir Samit

75% to 95%

1.5 > 2 3 4.5

NO 2 B+C 1 3.0

59 Bani Na'im <50% 0.5 > 2 3 3.5 NO 2 A+B+C 1 3.0

60 Beit 'Awwa

50% to 75%

1 > 2 3 4

YES 1 B+C 1 2.0

61 Dura 75% to 1.5 > 2 3 4.5 NO 2 A+B 2 4.0

305

95%

62 Yatta

50% to 75%

1 > 2 3 4

NO 2 A+B 2 4.0

63 Adh Dhahiriya <50% 0.5 > 2 3 3.5 NO 2 A+B 2 4.0

64 As Samu'

75% to 95%

1.5 2 2 3.5

NO 2 A+B 2 4.0

306

Note

* Have been identified from the contour maps

* GIS database

Rating-Equation

% gravity

flow score

No. of catchments

score

settlement in

the catchment area

score Political land classifications

score

adjustable <50% 0.5 1 1

YES 1 C 1

50% to

75% 1 2 2

NO 2 B+C 1

75% to

95% 1.5 > 2 3

A+C 1

> 95% 2

A+B+C 1

B 2

A+B 2

A 3

Rating 0.5 point: <50% by gravity flow 1 point: >=1 settlements in the catchment area

1 points: 50% to 75% by gravity

flow

2 points: No settlements in the catchment area

1.5 points: 75% to 95% by

gravity flow

1 points: Trunk lines and/or WWTP in Area C

2 points: > 95% by gravity flow

2 points: Entire project in Areas A and/or B

1 points: > 2 catchment areas

3 points: Entire project in Areas A

2 points: 2 catchment areas

3 point: 1 catchment areas

307

Normalize weights Sheet:

No. Criteria Environmental Assessment Committee

EQA National

Economy MoLG Transport Agriculture Health

Tourism

and

Antiquities

Planning and

Administrative

Development

PWA

1 Demography 5 8 8 8 9 10 8 9 9

2 Water consumption /

Wastewater

production

7 6 8 6 9 7 6 9 9

3 Reusing wastewater 5 4 5 3 8 2 5 5 8

4 Environmental factor 10 9 8 10 10 10 9 10 10

5 Operation body 10 8 8 8 9 8 8 10 9

6 Risk for Industrial

Waste 7 6 6 5 7 7 5 10 7

7 Socio-economic factor 10 8 10 8 9 10 8 8 9

8 Geographical factor 7 4 6 6 7 5 5 6 8

9 Political Issues 6 7 8 7 8 7 7 7 9

Can Change Directly

Weights of the criteria were identified through the intergovernmental agencies

308

No. Criteria Palestinian

Energy Authority

Public Works

and Housing

Labour Civil

defense

Petroleum

Authority

Weights

(Wm)

from 10

Normalize weight

(from 100%)

(Wm×100/∑W)

1 Demography 7 10 9 8 7 8.2 12.5

2 Water consumption /

Wastewater

production

4 5 6 7 6 6.8 10.37

3 Reusing wastewater 6 4 5 6 4 5 7.62

4 Environmental factor 8 10 10 10 9 9.5 14.48

5 Operation body 8 9 9 8 8 8.6 13.11

6 Risk for Industrial

Waste 7 5 6 4 8 6.4 9.76

7 Socio-economic factor 7 9 8 8 8 8.6 13.11

8 Geographical factor 5 4 5 4 5 5.5 8.38

9 Political Issues 7 6 7 6 6 7 10.67

309

Evaluation measure Sheet:

No.

Locality Name

Criteria Score for each community Score for

each community

Demography

Water consumptio

n

Reusing wastewate

r

Environmental factor

Operation body

Risk for Industrial

Waste

Socio-economic

factor

Geographical factor

Political Issues

Normalize weight 12.5 10.37 7.62 14.48 13.11 9.76 13.11 8.38 10.67

1 Silat al

Harithiya 0.76 5 5 4 3.5 4 3 3 4 69.9

2 Al Yamun 1.41 4 5 3 4 3 2 3.5 4 64.1

3 Kafr Dan 0.47 3 5 4 2.5 4 3 4 4 64.1

4 Deir Abu Da'if 0.56 4 5 4 2.5 4 3 3 4 64.7

5 Birqin 0.47 4 3 3 3.5 4 4 3.5 4 64.6

6 Ya'bad 1.07 2 3 4 4 4 3 3 2 58.4

7 Qabatiya 1.61 4 4 5 4 1 2 3 4 64.1

8 Arraba 0.81 3 4 3 4 3 3 3.5 3 59.5

9 Kafr Ra'i 0.57 4 2 3 3.5 3 3 4 5 61.7

10 Meithalun 0.61 3 3 4 3.5 4 3 3 5 64.5

11 Jaba' 0.71 3 3 5 3.5 4 1 3.5 4 61.1

12 El Far'a Camp 0.52 2 5 5 2.5 5 3 3 5 67.4

13 Tammun 1.09 4 1 3 3.5 3 3 3 4 57.7

14 Qaffin 0.68 4 3 3 3.5 3 2 4 3 56.6

15 'Attil 0.58 4 5 4 3.5 3 3 4 3 65

16 Deir al Ghusun 0.53 5 5 3 3.5 3 4 3 3 65

17 Bal'a 0.47 4 2 4 3.5 4 3 4.5 3 62.9

18 'Asira ash Shamaliya

0.63 3 1 4 3.5 3 5 3 4 62.6

19 'Awarta 0.46 4 3 3 2.5 4 3 3 2 54.2

20 Huwwara 0.45 4 2 3 3.5 4 3 3 3 57.4

310

21 Beita 0.87 3 2 3 3.5 3 3 4 3 56.1

22 Jamma'in 0.66 3 2 4 3.5 1 2 3 3 50.3

23 Aqraba 0.78 5 2 5 3.5 4 2 3 3 63.5

24 Qabalan 0.61 1 2 4 3.5 4 2 4 4 55.7

25 'Azzun 0.69 5 2 4 3.5 4 3 4 2 62.5

26 Biddya 0.71 2 2 4 3.5 3 3 3 2 52.7

27 Sinjil 0.46 2 2 5 2.5 5 2 4 3 57.5

28 Shuqba 0.49 1 2 5 2.5 4 2 4 3 53.5

29 Qibya 0.49 3 2 4 2.5 4 3 3.5 3 56.6

30 Al Jalazun

Camp 0.62 5 3 4 2.5 5 2 3.5 2 59.8

31 Kharbatha al

Misbah 0.52 3 3 2 2.5 4 2 3 3 48.9

32 Beit Liqya 0.70 2 4 4 3.5 4 3 3 3 59.9

33 Ar Ram & Dahiyat al

Bareed 1.09 2 1 4 3.5 3 4 3.5 2 55.6

34 Biddu 0.72 4 3 4 3.5 3 2 3 2 55.8

35 Hizma 0.61 4 1 5 2.5 3 3 3.5 2 56.2

36 'Anata 1.83 4 1 4 2.5 2 3 3.5 2 54.4

37 Al 'Eizariya 1.64 5 1 3 3.5 4 3 3.5 2 59.7

38 Abu Dis 0.75 5 1 2 3.5 5 5 3.5 2 61.7

39 As Sawahira ash Sharqiya

0.67 5 1 3 3.5 5 3 3 2 58.4

40 Al 'Ubeidiya 1.00 2 1 2 3.5 5 2 3.5 3 50.4

41 Husan 0.48 2 3 5 2.5 5 2 3.5 3 58.2

42 Nahhalin 0.73 2 3 5 2.5 5 3 3.5 2 59.3

43 Za'tara 0.63 1 2 3 3.5 5 3 3 3 53.6

311

44 Jannatah 0.60 2 2 3 3 5 1 3.5 3 49.9

45 Tuqu' 0.91 2 2 5 3.5 4 1 4 2 54.5

46 Beit Fajjar 1.04 3 2 5 3.5 1 2 3 4 56.3

47 Surif 1.28 1 1 4 3.5 4 2 3 3 52

48 Beit Ummar 1.24 2 2 5 3.5 2 3 3.5 2 55.9

49 Kharas 0.54 1 1 4 3.5 4 2 3 4 52.3

50 Beit Ula 1.11 1 1 3 3.5 4 3 4 4 55.1

51 Sa'ir 1.64 1 2 5 4 2 1 3.5 3 53

52 Halhul 2.16 1 2 5 4 3 3 4.5 3 63.2

53 Ash Shuyukh 0.94 2 1 5 3.5 2 2 3.5 3 53.1

54 Tarqumiya 1.32 1 1 4 3.5 3 3 3.5 2 51.5

55 Beit Kahil 0.81 2 2 5 2.5 5 2 3 3 56.7

56 Idhna 1.82 2 1 3 4.5 3 3 3.5 3 56.7

57 Taffuh 1.19 1 2 5 3.5 5 1 3 4 57.7

58 Deir Samit 0.71 2 2 2 3.5 4 1 4.5 3 48.3

59 Bani Na'im 2.23 1 1 3 4 3 2 3.5 3 51.7

60 Beit 'Awwa 0.72 1 2 2 3.5 2 2 4 2 42

61 Dura 3.20 2 1 5 4.5 4 4 4.5 4 74.3

62 Yatta 5.00 1 1 4 4 2 1 4 4 59.9

63 Adh Dhahiriya 2.79 2 3 2 4 2 2 3.5 4 55.5

64 As Samu' 1.89 3 1 3 4 5 2 3.5 4 61

312

Setting priorities Sheet:

No. Locality Name Score No. Locality Name Score No. Locality Name

Score

1 Dura 74.3 23 Al Jalazun Camp 59.8 45 Adh Dhahiriya

55.5

2 Silat al Harithiya 69.9 24 Al 'Eizariya 59.7 46 Beit Ula 55.1 3 El Far'a Camp 67.4 25 Arraba 59.5 47 Tuqu' 54.5

4 'Attil 65 26 Nahhalin 59.3 48 'Anata 54.4

5 Deir al Ghusun 65 27 Ya'bad 58.4 49 'Awarta 54.2

6 Deir Abu Da'if 64.7 28 As Sawahira ash Sharqiya

58.4 50 Za'tara 53.6

7 Birqin 64.6 29 Husan 58.2 51 Shuqba 53.5 8 Meithalun 64.5 30 Tammun 57.7 52 Ash Shuyukh 53.1

9 Al Yamun 64.1 31 Taffuh 57.7 53 Sa'ir 53

10 Kafr Dan 64.1 32 Sinjil 57.5 54 Biddya 52.7

11 Qabatiya 64.1 33 Huwwara 57.4 55 Kharas 52.3 12 Aqraba 63.5 34 Beit Kahil 56.7 56 Surif 52

13 Halhul 63.2 35 Idhna 56.7 57 Bani Na'im 51.7

14 Bal'a 62.9 36 Qaffin 56.6 58 Tarqumiya 51.5

15 'Asira ash Shamaliya 62.6 37 Qibya 56.6 59 Al 'Ubeidiya 50.4 16 'Azzun 62.5 38 Beit Fajjar 56.3 60 Jamma'in 50.3

17 Kafr Ra'i 61.7 39 Hizma 56.2 61 Jannatah 49.9

18 Abu Dis 61.7 40 Beita 56.1 62 Kharbatha al Misbah

48.9

19 Jaba' 61.1 41 Beit Ummar 55.9 63 Deir Samit 48.3

20 As Samu' 61 42 Biddu 55.8 64 Beit 'Awwa 42

313

21 Beit Liqya 59.9 43 Qabalan 55.7

22 Yatta 59.9 44 Ar Ram & Dahiyat al Bareed

55.6

314

Alternative A

Normalize weights to each criteria

No. Criteria Weights

(Wm)

Normalize

weight

1 Demography 8.2 13.99

2 Water consumption / Wastewater production 6.8 11.6

3 Reusing wastewater 5 8.53

4 Environmental factor 9.5 16.21

5 Operation body 8.6 14.68

6 Risk for Industrial Waste 6.4 10.92

7 Socio-economic factor 8.6 14.68

8 Geographical factor 5.5 9.39

9 Political Issues 0 0

58.6 100

Setting priorities for communities

No. Locality

Name Score No.

Locality

Name Score

No

.

Locality

Name Score

1 Dura 73.6 23 Beit Liqya 59.8 45 Taffuh 55

2 Silat al

Harithiya 68.7 24 Arraba 59.5 46 Biddya 54.3

3 'Attil 65.6 25 Jaba' 58.8 47 Beit

Fajjar 53.5

4 Deir al

Ghusun 65.6 26 As Samu' 58.8 48 Za'tara 52.9

5 'Azzun 65.2 27 Hizma 58.2 49 Tarqumi

ya 52.9

6 Abu Dis 64.3 28 Husan 58 50 Qabalan 52.8

7 Aqraba 63.9 29 Beit Ummar 57.8 51 Shuqba 52.8

8 El Far'a

Camp 63.5 30 Biddu 57.7 52

Adh

Dhahiriy

a

52.6

9 Halhul 63.5 31 Yatta 57.5 53 Ash

Shuyukh 52.3

10 Bal'a 63.2 32

Ar Ram &

Dahiyat al

Bareed

57.5 54 Beit Ula 52.2

315

11 Deir Abu

Da'if 62.9 33 Kafr Ra'i 57.2 55 Sa'ir 52.2

12 Birqin 62.8 34 Sinjil 57.2 56 Surif 51.1

13 Al Yamun 62.2 35 Huwwara 57.1 57 Bani

Na'im 50.7

14 Kafr Dan 62.2 36 Beit Kahil 56.3 58

Al

'Ubeidiy

a

49.3

15 Qabatiya 62.2 37 Idhna 56.3 59 Jamma'i

n 49.1

16 Al Jalazun

Camp 62.1 38 Tuqu' 56.3 60 Kharas 49

17 Al

'Eizariya 62 39 Qaffin 56.2 61 Jannatah 48.7

18 Nahhalin 61.7 40 Qibya 56.2 62

Kharbath

a al

Misbah

47.6

19 Ya'bad 60.6 41 'Anata 56.2 63 Deir

Samit 46.9

20

As

Sawahira

ash

Sharqiya

60.6 42 'Awarta 55.9 64 Beit

'Awwa 42.3

21 'Asira ash

Shamaliya 60.5 43 Beita 55.7

22 Meithalun 60.2 44 Tammun 55

316

Alternative B

Normalize weights to each criteria

No. Criteria Weights (Wm) Normalize weight

1 Demography 8.2 13.95

2 Water consumption /

Wastewater production 0 0

3 Reusing wastewater 5 8.5

4 Environmental factor 9.5 16.16

5 Operation body 8.6 14.63

6 Risk for Industrial Waste 6.4 10.88

7 Socio-economic factor 8.6 14.63

8 Geographical factor 5.5 9.35

9 Political Issues 7 11.9

58.8 100

Setting priorities for communities

No. Locality

Name Score No.

Locality

Name Score No.

Locality

Name Score

1 Dura 78.3 23 Qabalan 59.8 45 Bani Na'im 55.4

2 El Far'a

Camp 70.6 24 Kafr Ra'i 59.6 46 Tarqumiya 55.2

3 Halhul 68.2 25 Arraba 59.5 47 Al Jalazun

Camp 55.1

4

Silat al

Harithiy

a

66.4 26 Sinjil 59.5 48 Tammun 55.1

5 Meithalu

n 65 27 Aqraba 59.3 49 Al 'Eizariya 55

6 Yatta 64.6 28 Beit Ula 59.2 50 Huwwara 54.8

7 Kafr

Dan 64.5 29

Beit

Kahil 58.6 51 Ash Shuyukh 54.6

8 'Attil 63.2 30 Idhna 58.6 52 Biddya 54.2

9

Deir

Abu

Da'if

62.9 31 'Azzun 58.2 53 Qaffin 53.9

10

'Asira

ash

Shamali

ya

62.9 32 Beit

Ummar 57.7 54

As Sawahira

ash Sharqiya 53.5

11 Birqin 62.8 33 Za'tara 57.5 55 Hizma 53.5

12 Al

Yamun 62.3 34

Ar Ram

&

Dahiyat

57.4 56 Biddu 53

317

al

Bareed

13 Qabatiya 62.3 35 Shuqba 57.4 57 Al 'Ubeidiya 51.6

14 Beit

Liqya 62.2 36 Abu Dis 57.3 58 'Anata 51.5

15 Taffuh 62 37

Adh

Dhahiriy

a

57.3 59 'Awarta 51.3

16 Nahhali

n 61.6 38 Sa'ir 56.8 60 Jannatah 51

17 Jaba' 61.2 39 Qibya 56.2 61 Deir Samit 49.3

18 As

Samu' 61.2 40 Tuqu' 56.2 62 Jamma'in 49.2

19 Deir al

Ghusun 60.9 41 Kharas 56.1 63

Kharbatha al

Misbah 47.6

20 Bal'a 60.9 42 Beit

Fajjar 55.9 64 Beit 'Awwa 44.6

21 Ya'bad 60.6 43 Beita 55.7

22 Husan 60.3 44 Surif 55.7

318

Alternative C

Normalize weights to each criteria No. Criteria Weights (Wm) Normalize weight

1 Demography 8.2 14.39

2 Water consumption /

Wastewater production 6.8 11.93

3 Reusing wastewater 5 8.77

4 Environmental factor 9.5 16.67

5 Operation body 0 0

6 Risk for Industrial Waste 6.4 11.23

7 Socio-economic factor 8.6 15.09

8 Geographical factor 5.5 9.65

9 Political Issues 7 12.28

57.0 100

Setting priorities for communities

No. Locality

Name Score No.

Locality

Name Score No.

Locality

Name Score

1 Dura 72 23 Sinjil 58.6 45 Qabalan 53.5

2 El Far'a

Camp 70.1 24 Beit Liqya 58.3 46

Ar Ram &

Dahiyat al

Bareed

53.5

3 Silat al

Harithiya 69.9 25 As Samu' 58.2 47 Beit Ula 52.9

4 Deir Abu

Da'if 66.9 26 Al 'Eizariya 58.1 48 Tuqu' 52.2

5 Kafr Dan 66.2 27 Beit Kahil 57.7 49 Adh

Dhahiriya 51.8

6 'Attil 64.2 28 Qibya 57.6 50 Idhna 51.7

7 Deir al

Ghusun 64.2 29 Hizma 57.2 51 Za'tara 51.1

8 Birqin 63.8 30 Yatta 56.9 52 Ash

Shuyukh 50.6

9 Meithalun 63.6 31

As

Sawahira

ash

Sharqiya

56.6 53 Biddya 50.1

10 Aqraba 62.5 32 Arraba 56.4 54 Kharas 49.7

11 Qabatiya 61.8 33 Tammun 55.8 55 Surif 49.3

12 Bal'a 61.8 34 Taffuh 55.8 56 Sa'ir 48.9

13 Al Yamun 61.7 35 Huwwara 55.5 57 Kharbatha

al Misbah 48.8

14 'Asira ash 61.5 36 Ya'bad 55.2 58 Tarqumiya 48.7

319

Shamaliy

a

15 'Azzun 61.4 37 'Anata 55.1 59 Jannatah 48.4

16

Al

Jalazun

Camp

61.2 38 'Awarta 54.9 60 Al

'Ubeidiya 47.5

17 Nahhalin 60.8 39 Qaffin 54.6 61 Bani Na'im 47.4

18 Halhul 60.6 40 Beit Fajjar 54.2 62 Jamma'in 47.3

19 Kafr Ra'i 60.5 41 Beita 54.1 63 Deir Samit 45.1

20 Abu Dis 60.5 42 Shuqba 54.1 64 Beit 'Awwa 37.8

21 Jaba' 59.7 43 Beit

Ummar 53.7

22 Husan 59.5 44 Biddu 53.7

320

Alternative D

Normalize weights to each criteria No. Criteria Weights (Wm) Normalize weight

1 Demography 8.2 13.85

2 Water consumption /

Wastewater production 6.8 11.49

3 Reusing wastewater 5 8.45

4 Environmental factor 9.5 16.05

5 Operation body 8.6 14.53

6 Risk for Industrial

Waste 0 0

7 Socio-economic factor 8.6 14.53

8 Geographical factor 5.5 9.29

9 Political Issues 7 11.82

59.2 100

Setting priorities for communities

No. Locality

Name Score No.

Locality

Name Score No.

Localit

y Name Score

1 Dura 73.7 23 Abu Dis 57.6 45 Jamma'

in 53.6

2 Qabatiya 68.9 24 Beit

Ummar 57.6 46 Taffuh 53.1

3 Silat al

Harithiya 68.8 25 Al 'Eizariya 57.5 47

Qabala

n 53.1

4 'Attil 65.5 26 Tammun 57.4 48 Sinjil 52.9

5 Deir al

Ghusun 65.5 27

Adh

Dhahiriya 57.2 49

Beit

Ula 52.5

6 Al Yamun 64.6 28 As Samu' 56.8 50 Beit

Kahil 52

7 El Far'a

Camp 63.9 29 Idhna 56.3 51 Biddya 52

8 Halhul 63.5 30 Qaffin 56.3 52 Tuqu' 51.8

9 Deir Abu

Da'if 63 31 Ya'bad 56.1 53 'Awarta 51.5

10 Birqin 62.9 32 'Anata 56 54 Bani

Na'im 50.8

11 'Asira ash

Shamaliya 62.9 33 Hizma 55.8 55 Shuqba 50.7

12 Meithalun 62.8 34 Beita 55.7 56 Tarqum

iya 50.6

13 Kafr Dan 62.3 35 Al Jalazun

Camp 55.4 57 Kharas 49.3

14 Yatta 62.1 36 Biddu 55.4 58 Surif 49

15 Kafr Ra'i 61.9 37 Ar Ram & 55.2 59 Za'tara 48.6

321

Dahiyat al

Bareed

16 Aqraba 61.7 38 Nahhalin 55 60

Kharba

tha al

Misbah

45.6

17 Bal'a 61 39 Huwwara 55 61

Al

'Ubeidi

ya

45.1

18 'Azzun 60.7 40 Ash

Shuyukh 54.5 62

Deir

Samit 44.9

19 Beit Fajjar 60.2 41 Sa'ir 54.4 63 Jannata

h 44.5

20 Arraba 59.5 42 Qibya 54 64 Beit

'Awwa 42.2

21 Jaba' 59 43

As

Sawahira

ash

Sharqiya

53.9

22 Beit Liqya 57.7 44 Husan 53.7

جامعة النجاح الوطنية كمية الدراسات العميا

تحديد أولويات قطاع الصرف الصحي في الضفة الغربية (MCDAبإستخدام طريقة تحميل القرار متعدد المعايير )

إعداد براء ياسين عبد الفتاح جرارعو

إشراف مروان حدادد. أ.

المياه والبيئة بكمية ىندسةفي الماجستيرقدمت ىذه االطروحة استكماال لمتطمبات نيل درجة الدراسات العميا في جامعة النجاح الوطنية في نابمس، فمسطين.

3102

ب

تحميل القرار متعدد تحديد أولويات قطاع الصرف الصحي في الضفة الغربية بإستخدام طريقة (MCDA) المعايير

إعداد براء ياسين عبد الفتاح جرارعو

إشراف.مروان حدادد

الممخص

األراضيي فيي الصييي الصير قطياع فيي الدوالرات ماليين استثمار تم األخيرين، العقدين خالل فييعتبر قطياع الصير الصييي مين القطاايات المخملية خيالل العقيود الماضيية ذلك، ومع. الفلسطينية

% فقييط مين السيبان بتيببات صير صييي وبيذت التييببات 32-22ييي ييتم خدمية ميا نسيبت بيين تخيييدم بعيييض الميييدن الرميسيييية والمخيميييات والقيييرا فيميييا ييييتخلص معظيييم السيييبان مييين المييييات العادمييية

بواسطة اليفر اإلمتصاصية.

تم امل العديد من األبيا والدراسات الي قطياع الصير الصييي فيي فلسيطين وتيم وضيع العدييد مييين بيييذت األبييييا خيييالل السيينوات الماضيييية لبييين يييا ميين الخطيييط واإلسيييتراتيهيات فييي بيييذا المهيييال

واإلستراتيهيات لم ييدد ولويات المناطق التي بياهة ليل متبلة الصر الصيي.

يخد البي لتيديد ولويات المناطق التي بياهة ليل متبلة الصر الصيي لعمل متياريع فيخيا اليالييية الطريقيية(، يييي ظخيير البييي ن MCDAبإسييتخدام طريقيية تيليييل القييرار متعييدد المعييايير

سيلو و الميانيين سياسيات سياس الي إميا المتياريع بيذت من المستخدفة المناطق تيديد يتم التي .الصييح القرار التخاذ والعلمية الصييية المعايير هميع تأخذ ال نخاأل ذلك المي غير

بيي الصييي الصير قطياع فيي القيرار صينع الي بتبل ببيير تؤثر التي المعايير ن ظخر البي المييييات، اسيييتخدام إاييياد ،المنتهييية الصييييي الصييير مييييات/ المييييات اسيييتخالك اليييديموغرافيا،: القضيييايا

-اإلقتصييياد عاميييلال الصييينااية، لنفايييياتالناتهييية اييين ا المخييياطر الهسيييم المتييي ل، ،يالبيمييي عاميييلال

ت

وقييد نيياقش البييي قلييية تقييييم بييذت المعييايير وتييم .السياسييية والقضييايا اله رافييي، العامييل ،اإلهتمييااي يهاد االقة رياضية تربط بين المعايير المختلفة مما يسخل املية تيديد ولويات المناطق.إ

قال نسييمة فييي اييام 10 ظخيير البييي ن اييدد التهمعييات المتوقييع ن يبليي اييدد سييبانخا بثيير ميين تهميع مخييدوم بتيببات صير صييي و قييد التنفييذ و فييي 33تهميع، يوهيد منخيا 79بيي 2030

تهميع ييتم اليتخلص مين المييات العادمية 44وقد تم تخصيص تمويل لخا، بينما بناك مريلة التصميم التييي تييم املخييا ميين 2030-2010بواسييطة اليفيير اإلمتصاصييية. ويسيي الخطيية القطااييية للميييات

يهي ن تبيون بيل التهمعيات التيي يبلي اييدد 2030قبيل سيلطة المييات الفلسيطينية فإني بيليول اييام نسمة مربوطة بنظام صر صيي.قال 10سبانخا بثر من

( التيي تيم تطويربيا خيالل بيذا البيي اليي MCDAتيم تطبييق طريقية تيلييل القيرار متعيدد المعييايير تهمييع يييتم الييتخلص ميين الميييات العادميية فيخييا بواسييطة اليفيير اإلمتصاصييية والتييي سييتخدم بيلييول 44 مع يس األولوية.ته 44يس الخطة القطااية للميات، وقد تم ترتي ال 2030اام

وخطية األهيل طويلية خطة وضعخرهت الدراسة بعدد من التوصيات من بينخا ن تبد سلطة الميات بلزام الهخات المانية بخذت الخطة. 20 خدمة تتمل خمسية تهمع يس األولوية وا