mvuc revised final 02

Upload: dexter-gayawet-batalao

Post on 03-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Mvuc Revised Final 02

    1/7

    Name of Project: REHABILITATION/ IMPROVEMENT ALONG LUBUAGAN-BATONG BUHAY- ABRA ROAD

    K0458+376 to K0476+238, Intermittent SectionsLUBUAGAN & PASIL KALINGA

    ITEM 505 - GROUTED RIPRAPcu.m. Quantity = 2,208.48 cu.m.

    1 cu.m./man-day Duration = 2,208.48 cu.m. =

    1.25 cu.m./hr.

    No. ofPerson

    1

    2

    8

    No. ofUnits

    0.1

    0.05

    1

    1.00 3.00 /hr

    /cu.m.

    ln.m

    sq.m

    cu.m

    cu.m.

    cu.m

    bags

    17%

    12%

    Item Cost

    Name of Project: REHABILITATION/ IMPROVEMENT ALONG LUBUAGAN-BATONG BUHAY- ABRA ROAD

    K0458+376 to K0476+238, Intermittent SectionsLUBUAGAN & PASIL KALINGA

    SPL- MOBILIZATION & DEMOBILIZATIONlot Quantity = 1.00 lot

    cu.m./man-day Duration = 4.00 hrs.

    No. ofPerson

    1

    1

    2

    No. ofUnits

    2

    1

    7

    2

    0.00 3.00 /hr

    33.00 275.00

    Gravel Fill 33.13

    8,404,162.55PhPTotal Unit Cost 3,805.41Php

    Sub - Total for 3

    9,075.00Php

    OCM/CP 1,090,283.60PhP

    VAT 900,445.99PhP

    Cement 6,625.00 295.90 1,960,337.50Php

    4,777,284.61PhP

    Direct Cost 6,413,432.96PhP

    Boulders 2,318.90 914.05 2,119,589.40Php

    Name and Specification Unit Quantity Unit Cost Amount

    3. Materials :

    Weep Holes (4" diam.) 663.00 153.33

    1,030.65 34,142.62Php

    Sand 552.12 1,000.65 552,480.09Php

    101,660.00Php

    Filter Cloth

    Sub - Total for 2 757,472.26PhpTotal (1+2) 1,636,148.35PhP

    Output per hour =

    Unit Cost = 740.85PhP

    1-Bagger Mixer 1,767 172.00PhP 303,924.00Php

    Minor tools (10% of Labor Cost) 87,867.61Php

    Name and Capacity No. of Hours Hourly Rate Amount

    Backhoe 1,767 1,537.00PhP 271,587.90Php

    Water Truck 1,767 1,065.00PhP 94,092.75Php

    2. Equipment :

    Sub - Total for 1 878,676.09PhP

    1. Labor :Construction Foreman 1,767 71.95PhP 127,135.65PhP

    Skilled 1,767 52.06PhP 183,980.04PhP

    Laborers 1,767 40.15PhP 567,560.40PhP

    Unit of Measurement =

    Output/hour =1767 hrs

    1.25cu.m./hr

    Designation No. of Hours Hourly Rate Amount

    Laborers 4 40.15PhP 321.20PhP

    1. Labor :

    Construction Foreman 4 71.95PhP 287.80PhP

    Skilled 4 52.06PhP 208.24PhP

    Unit of Measurement =

    Output/hour =

    Designation No. of Hours Hourly Rate Amount

    1,733.00PhP 6,932.00Php

    Dumptrucks 4 1,352.00PhP 37,856.00Php

    Sub - Total for 1 817.24PhP

    Name and Capacity No. of Hours Hourly Rate Amount

    2. Equipment :

    Backhoe 4 1,537.00PhP 12,296.00Php

    1-Bagger Conc. Mixer 4 172.00PhP 81.72Php

    Sub - Total for 2 57,165.72Php

    Total (1+2) 57,982.96PhP

    Output per hour =

    Pay Loader 4

  • 7/29/2019 Mvuc Revised Final 02

    2/7

    Source = From Pinagan Gravel Pit

    Hauling Distance = km. (mountainous)

    Volume = cu.m.

    1 Labor Cost

    Breaking,Picking and Stockpiling

    Labor Capacity = 1 cu.m./man-day due to multiple handling

    No. of Laborers = 50

    Total Output/day = 50 cu.m.

    No. of days = 2,434.84 cu.m./ 50 = 49.00 days

    2 Equipment Cost:

    Loading Time = 6 min.

    Unloading Time = 2 min.

    Slack Time = 6 min.

    0.5 km (Gravel Pit to Highway)

    0.5 kms x 60 min/hr

    15 kms/hr

    0.5 kms x 60 min/hr

    25 kms/hr (Pinagan Highway-Dangoy, Lubuagan)

    PAVED(Mountainous) 12 km (Tomiangan to Dangoy)

    12.00 kms x 60 min/hr

    20 kms/hr

    12.00 kms x 60 min/hr

    35 kms/hr

    (Dangoy Lubuagan to Project Site)

    UNPAVED( Mountainous) 13.6 km (Dangoy to Project Site)

    13.60 kms x 60 min/hr

    15 kms/hr

    13.60 kms x 60 min/hr

    25 kms/hr

    Total Cycle Time = 160.81 min.

    8 hrs x 60 min/hr =

    mins

    Utilizing 2 Dumptrucks

    cu.m.

    2.98 trips/day x 20 cu.m.

    Dumptrucks = 2.00 DTx P10,816 /day x 39.50 days =

    Loader = 1 Loader x P13,864 /day x 39.50 days =

    Aggregate Tax = 15.00 /cu.m.

    Total Unit Cost of Boulders @ Project Site = 914.05 /cu.m.

    P854,464.00

    P547,628.00

    P1,402,092.00

    Total Cost = P2,189,056.50

    Unit Cost =P2,189,056.50

    = P899.05 /cu.m.2,434.84

    No. of Trips/day = 2.98 trips160.8114286

    No. of days Required =2,434.84

    = 40.85 say 39.5 days

    Loaded Trip = = 54.40 mins

    Unloaded Trip = = 32.64 min.

    Loaded Trip = = 36.00 mins

    Unloaded Trip = = 20.57 min.

    UNPAVED ROAD (mountainous)

    Loaded Trip = = 2.00 mins

    Unloaded Trip = = 1.20 min.

    Labor = 50 Lab. X 49.00 days x 321.21 /day = P786,964.50

    UNIT COST DERIVATION OF BOULDERS (Class "A")

    0.5

    2,318.90

  • 7/29/2019 Mvuc Revised Final 02

    3/7

    Region : CAR Roadbed Width : 4-8 m.District : Pavement Width :

    Name of Project : Rehabilitation/ Improvement along Lubuagan- Net Length : 651.50 m.: Batong Buhay-Abra Boundary Road Thickness :

    Road Section I.D. : S00562LZ Type of Structure :Section : Dangoy-Balatoc Section Type of Substructure :Location : Lubuagan & Pasil ,Kalinga No. of Spans :Appropriation : No. of Piers :

    Source of Fund : MVUC Fund Dimensions :Classification : No.of Days to Complete : 155.00 CD

    Limits : K0458+376 to K0476+238 (I.S)Starting Date :

    AVAILABLEWork Category 27: Rehabilitation plus Improvement

    Facilities for the Engineers 0.40% 2

    Provision for Safety and Health 0.35% Pay Loader 1

    Roadway Excavation (Common Earth) 0.97% Dumptrucks 7

    Structure Excavation 2.07% 1-Bagger Conc. Mixer 2

    Embankment (Selected Fill) 2.09% Bar Cutter 1

    Reinforcing Steel Bars (Grade 40) 2.96%

    Structural Concrete (Class "A") 3.65%Reinforced Concrete Pipe Culvert (910mm) 1.96%

    Grouted Riprap 84.89%

    Mobilization & Demobilization 0.66%

    100%

    UNIT COST

    Work Category 27: Rehabilitation plus ImprovementFacilities for the Engineers mos. 39,916.80

    Provision for Safety and Health lot 34,624.08

    Roadway Excavation (Common Earth) cu.m. 95,962.69

    Structure Excavation cu.m. 205,382.83

    Embankment (Selected Fill) cu.m. 206,628.39

    Reinforcing Steel Bars (Grade 40) kgs. 292,776.49

    Structural Concrete (Class "A") cu.m. 361,094.32Reinforced Concrete Pipe Culvert (910mm) ln.m. 194,528.80

    Grouted Riprap cu.m. 8,404,162.55

    Mobilization & Demobilization cu.m. 64,940.92

    Total: 9,900,017.87

    DIRECT COST1. Labor P 975,253.24

    2. Equipment P 1,073,514.79

    3. Material P 5,519,355.87

    4. Project Supervision

    Total Direct Cost P 7,568,123.91INDIRECT COST1. Mark-up (OCM, Profit) P 1,271,177.76

    2. VAT P 1,060,716.20

    3. Quality Control P

    4. Eng'g & Administrative Overhead P 100,000.00

    5. Construction Contingency P

    6. Central Office Retention P

    7. Road Right-of-Way P

    8. Soil Exploration P

    P

    Total Indirect Cost P 2,431,893.96

    TOTAL ESTIMATED PROJECT COST P 10,000,017.87

    SAY P 10,000,000.00

    Prepared by: Checked & Reviewed: Submitted by:

    1.00 34,624.08

    599.00 160.20

    %

    B.1

    B.1

    103

    T O T A L

    500a505

    704.15 291.67

    378.00 546.64

    68.39

    7,737.18

    8,105.37

    3,805.41

    64,940.92

    4,280.84

    46.67

    24.00

    A.1 7,257.60

    102a

    PROGRAM OF WORK

    Kalinga

    By Contract

    Upon Approval

    ITEM NO. ITEMS OF WORK TO BE DONE %E Q U I P M E N T

    DESCRIPTION NEEDED

    10,000,000.00PhP

    Backhoe

    Spl

    104a404a405

    5.50

    Republic of the Philippines

    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYSCordillera Administrative Region

    Office of the District Engineer

    Bulanao, Tabuk City, Kalinga

    ESTIMATED COST OF PROPOSED WORKSQUANTITY UNIT COST

    A.1

    ITEM DESCRIPTION

    2,208.48

    1.00

    102a103

    104a404a405

    500a505Spl

    24.32%

    100%

    9. Survey Plan and Preparation

    9.75%

    1.00%

    12.71%

    10.61%

    10.74%

    55.19%

    75.68%

  • 7/29/2019 Mvuc Revised Final 02

    4/7

    ADJUSTED

    COST

  • 7/29/2019 Mvuc Revised Final 02

    5/7

    Calendar Days = (given reference amount x reference duration per km. of road)

    estimated amount per km.of road

    + (duration of mob./demob. On the given reference amount)

    NOTE: For Drainage & Slope Protection (Grouted Riprap)

    Given Reference Amount = 10,000,000.00

    Reference Duration/km. of Road = 16.00

    Estimated amount per km. of road = 546,068.04

    Mobilization/Demobilization = 15 days

    (Up to P5 Million)

    Calendar Days = 10,000,000.00 x 16.00 + 15.00 days

    = 308.00 c.d.

    say 309 days(for 20M/2) = 154.50

    = 155.00 days

    Prepared by: Checked/Reviewed by:

    SAMUEL A. PAO-ITON RAFAEL L. FERNANDO

    Engineer II Chief, Planning & Design Section

    (Per D.O. No. 44, Series 2012)

    546,068.04

    COMPUTATION OF PROJECT DURATION

  • 7/29/2019 Mvuc Revised Final 02

    6/7

    Stations: K0499+900 to K0508+100

    Length : 8,200.00 m.

    12% 10%

    (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)(5)X(8) 2%((5)+(9)

    Act 309 : Other Traffic Devices

    Spl Mobilizati 1.00 lot 6,022.90 - - - - 722.75

    602a Reflectorized Thermoplastic Pavement

    Markings ( 1,933.50 sq.m. ##### ##### ##### 22% ##### #####

    602b Reflectorized Thermoplastic Pavement

    Markings ( 150.00 sq.m. ##### ##### ##### 22% ##### #####

    TOTAL = THREE MILLION, ONE HUNDRED SEVENTY THOUSAND, FOUR HUNDRED THIRTY ONE PESOS.

    PREPARED BY: Recommending Approval:

    SAMUEL EUGENE MICHAEL J. ESPITA JOEL G. BUCAO DOMIN

    OIC-Asst.

    ChairmanMem Member

    Engin Engineer II Engineer II

    Painting of Centerline and Edgelines along Kalinga-CaProject Name and Location

    ITEM NO.DESCRIPTI

    ONQty. UNIT

    ESTIMATE

    D DIRECT

    COST

    MARK-UPS IN

    PERCENTTOTAL MARK-UP

    VAT

    OCM PROFIT % VALUE

    APPROVED BUDGET FOR THE CONTRA

    Republic of the Philippines

    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

    CORDILLERA ADMINISTRATIVE REGION

    OFFICE OF THE District Engineer

    Bulanao, Tabuk City

  • 7/29/2019 Mvuc Revised Final 02

    7/7

    Contract Duration:10.00 C.D.

    (11) (12) (13) (14) (15)(9)+(10) (5)+(11) (12)/(3) (3)x(14)

    722.75 6,745.65 6,745.65 6,745.00 6,745.00

    ###### ###### 1,516.48 1,516.00 ######

    62,353.15 ###### 1,550.21 1,550.00 ######

    P #######

    APPROVED:

    O A. ENCISO

    District Engineer District Engineer

    TOTAL

    INDIRECT

    COST

    TOTAL

    COST

    UNIT

    COST

    ALEXANDER C. CASTA

    ayan Road

    ADJUSTE

    D UNIT

    COST

    ADJUSTE

    D TOTAL

    COST