Project Progress – 06thJan,2014
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 06.01.14
1.1st To 14th Floor Slabs : Completed2.15th Floor Slab : Flat No 1 & 2 flats Slab Completed, 4 & 5 flats Slab Bar Bending Completed ,3rd flat
Shuttering Completed. 3.Brick Work: 10th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 06.01.14
1.1st To 14th Floor Slabs : Completed2.15th Floor Slab : Flat No 1 & 2 flats Slab Completed, 4 & 5 flats Slab Planning Today ,3rd flat Slab Bar Bending
Progress . 3.Brick Work: 10th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 06.01.14
1.1st To 11th Floor Slabs : Completed
2.12th Floor Slab : Flat No 01 Completed ,Flat No 02 Bar bending In Finishing Stage
2. Brick Work: 9th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 06.01.14
1.1st To 15th Floor Slabs : Completed2.16th Floor Slab : Flat No 1 and 2 Bar Bending Completed ,Flat No : 4 and 5 shuttering Work Started 3rd Flat Columns work
Progress 3.Brick Work: 11th Floor External walls in Progress
STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 06.01.13
1.1st To 15th Floor Slabs : Completed2.16th Floor Slab : Flat No 1&2 Slab Completed , 4 & 5 flats Shuttering work Progress, 3rd Flat Columns work In
Progress 3. Brick Work: 11th Floor External walls in Progress