my report21

Upload: manther-genx

Post on 04-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 My Report21

    1/17

    INTRODUCTION

    Formwork is a mould used to shape the concrete and support the concrete until it

    attains sufficient strength to carry its own weight. It can be visualized as a baking tin in

    which a cake is baked, the tin supports the wet dough till it is baked fully. Here the

    concrete can be compared to wet dough and formwork as the baking tin.

    ECONOMY IN FORMWORK

    The total cost of concrete construction includes the cost of formwork.

    Construction of formwork involves considerable expenditure in terms of cost of material,

    cost of labour for fabrication, erection and removal of formwork and time element. In

    case of buildings, the cost of formwork may range between 30 to 40 % of the cost of the

    concrete work. In case of special structures like bridges, tall chimneys, dams etc; the cost

    of formwork may range between 50 to 60% of the cost of the concrete work. A careful

    watch should be kept on the cost of formwork and all attempts should be made to bring

    down the cost of the formwork to a minimum so as to achieve overall economy in the

    concrete work.

    The quality of finished concrete surface depends to a great extent upon the

    quality of formwork used in the work. In case the formwork is made of rough timber and

    is not constructed properly, the resultant concrete surface will be irregular and full of

    defects. The expenditure involved in rectification of defects in such works is invariably

    more than the saving made in the cost of formwork. Thus to effect economy, the

    formwork should be made with good quality material and should be constructed properly.

    REQUIREMENTS OF FORMWORK

    1) The formwork should be constructed in such a manner that it may permit the

    removal of various parts in desired sequence without jarring or damaging the

    concrete.

    2) The material of the formwork should be cheap, easily available and should be

    suitable for re-use several times.

    1

  • 7/29/2019 My Report21

    2/17

    3) It should be strong enough to withstand all types of dead and live loads such as

    selfweight, weight of reinforcement, weight of wet concrete, loads due to workmen,

    construction equipment, other incidental loads and forces caused by placement and

    consolidation of the concrete, imposed upon it during and after casting of concrete.

    4) The inside surface of formwork should be smooth so as to turn out a good concrete

    surface. This is achieved by applying crude oil or soft soap solution to the inside

    surface of formwork. This also makes the removal of formwork easy. The material of

    the formwork should be as light as possible and should not warp or get distorted when

    exposed to sun, rain or water during concreting.

    5) It should be rigidly constructed and efficiently propped and braced (both

    horizontally and vertically) so as to retain its shape without undue deflection.

    6) The joints in the formwork should be tight against leakage of cement grout.

    7) The formwork should rest on firm base.

    CHOICE OF FORMWORK SYSTEMS

    Formwork can be divided into three approaches. They are

    1) Traditional approach.

    2) Systematic approach.

    3) Stay in place approach.

    Traditional approach: This approach is not much in use now days. The formwork is

    built on the site out of timber. It makes use of wooden posts called ballies as supports

    for shuttering and wooden planks as sheathing. This practice is labour intensive and time

    consuming especially for tall structures. It is unsafe and many a times unreliable also.

    The quality of concrete surface obtained is not good and hence plastering and rendering

    becomes a necessity. It has a very low re-use value, as the materials are not properly

    seasoned to be weatherproof. Hence it can rarely be used more than once. The following

    photo shows the Traditional Formwork approach.

    2

  • 7/29/2019 My Report21

    3/17

  • 7/29/2019 My Report21

    4/17

    very organized system of forming concrete. There are many components that combine to

    form this formwork system. These components are specifically designed to take dead

    loads and live loads. It has a very sturdy supporting system. This formwork system is

    designed keeping in mind the safety of the workmen. It might be labor intensive at times

    depending upon the structure type. The finish obtained is of high quality and needs no

    rendering or plastering unless asked for. System facilitates fixing and removal at each

    location without the use of any sophisticated tools and tackles.

    4

    Collapsibletype props (CTprops)

    A network of wooden H-beams to support thesheathing.

  • 7/29/2019 My Report21

    5/17

    Stay in place approach:In this approach the formwork stays in place after the concretehas cured to provide thermal and acoustic insulation, space to run utilities, and backing

    for finishes. It is assembled on site usually out of prefabricated, Insulating Concrete

    Forms. This formwork becomes an integral part of the concrete and is not removed.

    Hence it gets its name stay in place formwork.

    TYPES OF SYSTEM FORMWORKS

    In the early days the carpenter with available timber and nails carried out the job

    of formwork. The formwork techniques have also developed side by side along with the

    growth in the development of concrete construction. With the technological advancement

    and introduction of new materials of formwork, more rational approach is being made in

    the design of formwork. The different types of system formworks are as follows.

    1) Column/Wall formwork

    2) Flex system

    3) Beam forming supports

    4) Heavy duty tower

    5) Climbing formwork

    6) Slip formwork7) Tunnel formwork

    8) Aluminium formwork

    COLUMN / WALL FORMWORK SYSTEM: This consists of a vertical mould of the

    desired shape and size, which has to retain the wet concrete and resist the initial

    hydrostatic pressure caused by the wet concrete. The column formwork consists of a box

    prepared from four separate sides. Column forms are located at the bottom around a 75 to

    100mm high concrete plinth, which has the dual function of location and preventing grout

    loss from the bottom of the column formwork. They are used for large size-system for

    housing and business buildings, industrial construction, civil engineering works and tank

    construction. It has high strength tie system to bear large concrete pressures and to avoid

    load-bearing Struts. It hasprovision for fixing scaffolding platform and alignment units

    5

  • 7/29/2019 My Report21

    6/17

    built in. Careful planning is done to re-use the panels so as to eliminate reassembling

    them to suit different plan dimensions. These panels can be used along with climbing

    formwork systems for tall structures. Small panels are handled manually where as large

    panels are handled using cranes.

    A large column formwork with supports Wall formwork

    FLEX SYSTEM: This formwork system is used for slab and beam formwork up to floor

    heights of 4.4m. It provides the option of choosing conventional system or Beam forming

    system for beam formwork. It provides flexibility in spacing between props and

    flexibility related to heights of individual props. The components are light enough for

    erecting and dismantling the formwork. This system avoids use of many skilled laborers

    at site. It enables re-propping and frequent reuse of materials. Side forms may be

    removed as soon as practicable usually within hours of casting. This allows drying air

    movements to take place around the setting concrete. Soffit formwork may be removed

    usually within days but as a precaution some props are left in position until concrete

    member is self-supporting.

    6

  • 7/29/2019 My Report21

    7/17

    CONSTRUCTION OF RC FLOOR USING FLEX SYSTEM

    BEAM FORMING SUPPORT SYSTEM: This is a three-sided box supported and

    propped in the correct position and to the desired level. The beam formwork sides have to

    retain the wet concrete in the required shape and be able to withstand the initial

    hydrostatic pressure of the wet concrete. The formwork soffit apart from retaining the

    concrete has to support the initial load of the wet concrete and finally the set concrete

    until it has gained sufficient strength to be self-supporting. It is essential that all joints in

    the formwork be constructed to prevent the escape of grout, which could result in

    honeycombing in the cast beam. The removal time for the formwork will vary with air

    temperature, humidity and consequent curing rate. It uses standard components avoiding

    skilled laborers making them at site. Beam is provided with sheathing at the bottom

    which should be of plywood of at least 19mm or of some thicker or stiffer material. The

    arrangement on sides remains independent of beam width. This system can be easily

    assembled, aligned, fixed and dismantled.

    7

  • 7/29/2019 My Report21

    8/17

    Beam Forming Support

    HEAVY DUTY TOWER SYSTEM: This system is usedfor slab and beam formwork

    with tall staging heights and heavier loading. Additional frames can be attached to the

    tower. Height adjustment of 800mm is possible using both top and bottom tower

    spindles. Inclined decking is also possible in this system. The Individual components are

    light enough to be managed manually otherwise tower, as a whole requires a crane to

    handle it. This load-bearing tower system comprises only a few individual parts and is

    extremely versatile. Speedy assembly is possible even when the towers are high. This

    system is used whenever heavy loads are to be carried. Heavy-duty tower formwork

    system is used mainly for construction of bridges.

    CLIMBING FORMWORK SYSTEM: Climbing here means that the formwork of

    large area can be shifted in a single operation along with the decks both horizontally and

    vertically. The hydraulic jacks provide the basic climbing energy for the whole climbing

    forming. With the aid of automatic self-climbing systems, wall formwork elements are

    suspended from the platform. This makes it possible to concrete the entire core, slabs,

    and facade walls in a single pour, saving valuable time and manpower. The typical cycle

    of climbing formwork consists of stripping the formwork, lifting it to next level, laying

    rebar, setting up formwork, and then pouring concrete. Climbing formwork makes it

    possible to use the technical advantages of a large area formwork at any height with the

    same degree of safety as on the ground.

    8

  • 7/29/2019 My Report21

    9/17

    CLIMBING FORMWORK

    Features of climbing formwork:

    1) High adaptability: The formwork assembly may be integrally shifted for 600mm,

    facilitating form cleaning and bar wrapping. Flexible operation is resulted from the

    formwork assembly which may be adjusted to the left and right or up and down in

    relation to the support assembly. The crane-lifted climbing formwork can be used for

    structures of any shape and any angle of inclination.

    2) Short shifting times: It permits quick installation, reduces crane time because the

    entire unit repositions quickly. It offers speedy precision adjustment of the formwork in

    all directions.

    3) Safe suspension system: The platforms allow for safe and efficient work and are

    designed to carry high loads for the storage of equipment and reinforcing steel. The

    climbing formwork provides superb workplace safety.

    4) Sturdy design: They are designed to take up large loads. The embedded parts bear the

    complete lateral concrete pressure, eliminating the need for bracings and resulting in

    smooth concrete surface.

    9

  • 7/29/2019 My Report21

    10/17

    The climbing formwork is ideal for all industrial high-rise projects, bridge piers, silos,

    radio and television towers.

    SLIPFORM: Slipform means a continuously moving form, moving at such a speed that

    the concrete when exposed, has already achieved enough strength to support the vertical

    pressure from concrete still in the form as well as to withstand nominal lateral forces

    caused by jack rod, wind etc. This system is more suitable for structures with uniform

    cross-sections or uniformly varying cross-sections.

    Slipform can be classified as straight Slipform, tapering Slipform and Slipform

    for special applications. Slip Forms have been used to construct Single- cell silos, Multi

    cell silos, Piers, Towers, Water reservoirs, Chimneys, Buildings, Light House.

    Features of Slipform:

    1) It is suitable for tall structures with limited variation of shape and size in plan

    with level.

    2) Rapid construction is achieved by making use of Slipform.

    3) Slipform uses hydraulic jacks instead of cranes for lifting.

    4) Since Slipform is a continuously moving formwork; Continuous casting is done

    which avoids construction joints.

    5) It avoids expensive consumables and works out economical.

    TUNNEL FORMWORK: With the help of tunnel forms, room size walls and slabs can

    be cast together like a portal in a single pour of concrete. To facilitate removal of the

    form, block work or pre-cast walls are provided for the facade. Generally these forms are

    made of steel components and result in high productivity by repeated usage. This is

    ideally used for construction of mass system housing and tunnels. It ensures rapid

    construction. It is suitable for large repetitive projects where economy is derived from

    material and labor. Tunnel formwork requires crane for handling of formwork.

    10

  • 7/29/2019 My Report21

    11/17

    ALUMINIUM FORMWORK SYSTEM: Aluminium formwork system is to discharge

    heavy loads coming from great heights. It is the latest in technology, which is an all

    aluminium formwork system. All components except for some supporting members are

    made up of aluminium alloy.

    Features of Aluminium formwork system:

    1) It is used for concrete wall and slab type of construction.

    2) It requires not more than a hammer for its assembly and removal.

    3) It is completely self- supporting and interlocking.

    4) High speed of construction is achieved.

    5) It is Very light in weight and hence easy to handle.

    6) It is highly earth quake resistant.

    7) This system does not rely on expensive machinery or skilled workmen.

    8) The overall cost of construction is less when used for repetitive structures like

    mass housing etc.

    Limitations of Aluminium formwork system:

    1) No changes in the formwork setup can be done once it is fabricated not even

    adding conduits for services.

    2) It can be used only for superstructures; foundation needs to be done in the

    conventional way.

    3) Its initial cost is higher.

    4) It is economic only when number of repetitions of the formwork is obtained.

    FAILURE OF FORMWORK

    The safety must be the first place in the design, construction, erection and stripping of

    formwork systems. Most failures of large formwork are progressive; vertically through

    several floors or horizontally as each successive line of shoring collapses like a house of

    cards. Generally some unexpected event causes one member to fail, then others become

    overloaded or misaligned and the entire formwork structure collapses.

    11

  • 7/29/2019 My Report21

    12/17

    Failure may result in a collapse of part or all of the forms. Failure of the formwork

    causes distortion and movement of the forms, which will affect the stability of the

    structure. Such failures lead to minor or fatal accidents. Formwork collapse causes

    injuries, loss of life, property damage, and construction delays. Rectifying cost of failure

    includes removal and replacement cost of formwork, removal cost of fresh or failed

    concrete, removal of reinforcement, loss of time for rework and cost of injuries.

    To eliminate all possibility of a large costly failure, the overall formwork system

    should be reviewed before construction. Guidelines given in relevant Indian standards

    should be followed regarding the period of removal of formwork.

    CAUSES OF FAILURE OF FORMWORK

    1) If the formwork is removed too soon before the concrete has developed sufficient

    strength to support itself as well as the loads acting on it; it leads to the failure of

    formwork.

    2) Improper contact of the base and props and improper verticality of props cause

    failure.

    3) If inadequate shoring and bracing is provided it leads to failure of formwork.

    4) All loads are not considered during design.

    5) If the strength of shoring materials is insufficient to take up the loads.

    DESIGN OF FORMWORK

    Several failures of formwork have focused attention on the need for guidelines in

    the design and construction of formwork so as to achieve safety, reliability and economy

    in concrete construction. The importance of formwork at times is not appreciated well.

    Formwork shall be designed to meet the requirement of the permanent structure using

    relevant Indian Standards for materials selected for formwork. The design should take

    into account the conditions of materials to be actually used for the formwork,

    environment and site consideration. Before proceeding to the design, all the relevant

    design information should be obtained from the relevant sources. The design information

    12

  • 7/29/2019 My Report21

    13/17

    includes the site investigation report, expected loading scheme of load transfer, sequence

    of erection and releasing, procedure of concreting and time frame. When the material for

    formwork have been chosen, and the anticipated loading estimated, a form should be

    designed strong enough to carry the anticipated loads safely, and stiff enough to hold its

    shape under full load. Under-designing can result in failure of the forms and Over-

    designing will result in an excessive cost.

    Loads on Formwork and Combination of Loads

    Formwork shall be designed to resist the expected dead load, imposed load, construction

    load and environmental load. Loads on formwork are any combinations of the following:

    1) Dead loads,

    2) Imposed loads,

    3) Environmental loads,

    4) Incidental loads during erection and operation,

    5) Lateral pressure.

    DEAD LOAD: Dead loads shall include:

    Formwork structure, self weight of formwork and any ancillary temporary work

    connected or supported by formwork, and weight of freshly placed concrete for the

    permanent structure directly supported by the formwork. The unit weight of wet concrete

    including reinforcement shall be taken as 26 kN/m. Actual load of formwork shall be

    evaluated for use in design. However, in absence of the data, load may be assumed as 500

    N/m2 for the purpose of initial calculations.

    IMPOSED LOAD: Loads during constructional operation shall constitute the imposed

    loads for formwork design. Such loads may occur due to construction personal, plant and

    equipments, vibration and impact of machine delivered concrete, lateral pressure of fresh

    concrete, unsymmetrical placement of concrete, concentrated load and storage of

    construction materials. The concrete should not be dropped from a free height greater

    than 11 m if it be necessary to exceed these limitations, allowances for the additional

    13

  • 7/29/2019 My Report21

    14/17

    loading should be made in design. Where allowance has only to be made for access and

    inspection purposes, a loading of750N/m2 should be adequate.

    ENVIRONMENTAL LOADS: These loads include:

    1) Wind or seismic loads,

    2) Earth pressure,

    3) Water pressure,

    4) Snow loads or ice loads, and

    5) Thermal load, etc.

    LATERAL PRESSURE (due to fresh concrete): The lateral pressure due to fresh

    concrete depends on the temperature of concrete as placed, the rate of placing of concrete

    and the concrete mix proportion. A set of curves giving typical values of pressurePmax

    for unit height, on formwork are given in Fig 3 for guidance. The pressure distribution

    varies along the height of formwork. For normal concrete, the maximum pressure may

    occur at a height h,below the top as given by the following formula:

    hm = Pmax/d

    Where

    hm, is in m,Pmax is in kN/m2, and

    dis density of fresh concrete in kN/m3.

    STABILTY: The formwork shall be designed to check against overturning and sliding.

    A factor of safety of 1.5 may be used in design against overturning and sliding.

    14

  • 7/29/2019 My Report21

    15/17

    Deflection limit

    The formwork shall be designed so as to remain sufficiently rigid during placing and

    compaction of concrete. The total calculated deflection of formwork including the initial

    imperfection in the members should not exceed the following:

    For beam span < 3 000 mm,

    < 3mm

    For beam length > 3 000 m

    is the least of 30 mm OR L/l 000

    15

  • 7/29/2019 My Report21

    16/17

    CONCLUSION

    Formwork is base for any concrete structure.No desirable structure can be built withoutthe use of formworks.

    Unfortunately very little attention is being paid to formwork design or its usage in India

    even though formwork accounts for a large part of the cost of concrete work in a project.

    Formwork can increase or decrease the cost of the project as under design & over design

    will increase the cost of the project to considerable limits. Under-designing can result in

    failure of the forms and Over-designing will result in an excessive cost. The formwork

    design requires the same skill and attention to details as the design of permanent

    structures. Formwork collapse causes injuries, loss of life, property damage, and

    construction delays.

    There has been a considerable advancement in Formwork recently worldwide. There are

    lot of software tools for fast work preparation, planning and material allocation and

    design. Summarizing, the goal of this study was to provide a comprehensible discussion

    of the concepts and importance of formwork

    16

  • 7/29/2019 My Report21

    17/17

    17