Investor day Naftna industrija Srbije j.s.c.. Novi Sad 17 December 2012 Pančevo Investor Relations

Upload: others

Post on 24-Jan-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Investor day

Naftna industrija Srbije j.s.c.. Novi Sad

17 December 2012Pančevo

Investor Relations

Page 2: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

2

Disclaimer

This presentation has been prepared by NIS a.d. Novi Sad (the “Company”), and comprises the slides for a presentation to investorsconcerning the Company. Presentation does not constitute or form part of any offer or invitation, or any solicitation of any offer to sellor purchase or subscribe for, any shares or other securities representing shares in the Company, nor shall it or any part of it nor thefact of its presentation or distribution form the basis of, or be relied on in connection with, any contract or investment decision.

Any viewer of this presentation considering a purchase of such securities is hereby reminded that any such sale or purchase shouldbe made solely on the basis of the information contained in other publicly available documents and will be subject to the restrictionsset out therein. No reliance may be placed for any purposes whatsoever on the information contained in this presentation, or any othermaterial discussed at any presentation or on its completeness, accuracy or fairness. The information in this presentation should not betreated as giving investment advice or recommendation. All reasonable measures are taken to ensure that the facts stated in thispresentation are accurate, and that the opinions expressed are fair and reasonable. However, the contents of this presentation havenot been adopted by the corporate body’s of Company. Accordingly, no representation or warranty, express or implied, is made orgiven by or on behalf of the Company or any of its members, directors, officers or employees or any other person as to the accuracy,completeness or fairness of the information or opinions contained in or discussed at this presentation. None of the Company or any oftheir respective members, directors, officers or employees nor any other person accepts any liability whatsoever for any losshowsoever arising from any use of this presentation or its contents or otherwise arising in connection therewith.

The information in this presentation includes forward-looking statements. These forward-looking statements include all matters thatare not historical facts, statements regarding the Company’s intentions, beliefs or current expectations concerning, among otherthings, the Company’s results of operations, financial condition, liquidity, prospects, growth, strategies, and the industry in which theCompany operates. By their nature, forward-looking statements involve risks and uncertainties, including, without limitation, the risksand uncertainties to be set in other publicly available documents, because they relate to events and depend on circumstances thatmay or may not occur in the future. The Company cautions you that forward looking statements are not guarantees of futureperformance and that its actual results of operations, financial condition and liquidity and the development of the industry in which theCompany operates may differ materially from those made in or suggested by the forward-looking statements contained in thispresentation. In addition, even if the Company’s results of operations, financial condition and liquidity and the development of theindustry in which the Company operates are consistent with the forward-looking statements contained in this presentation, thoseresults or developments may not be indicative of results or developments in future periods. The information and opinions contained inthis presentation are provided as at the date of this presentation and are subject to change without notice.

No person is under any obligation to update or keep current the information contained herein.

By attending the presentation you confirm that you have read and understood foregoing limitations.

Page 3: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

About Us

Page 4: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Quick facts about NIS

14

A joint-stock company – 56.15% of shares owned by the Russian Company

Gazprom Neft

An international company:

operating in nine countries worldwide

One of the greatest vertically integrated companies for the

production of oil and gas in the Southeastern Europe

It has about 9,000 employees

The largest tax payer in Serbia

The largest investor in Serbia in 2011

NIS meets more than 2/3 demands of the Serbian

market for petroleum products and approx. 1/5 demands of the Serbian market for natural gas

Page 5: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

5

Mission, vision and values of the company

VALUES OF THE COMPANY

MISSION

To give the people of Balkan region energy for movement towards better by responsible

use of natural resources and modern

technology.

VISION

Vertically integrated energy company NIS will become a recognized leader in Balkan

region in its industry by dynamics of sustainable

development and increase of efficiencies, demonstrating high

social and ecological responsibility and modern

standards of customer service.

EXPERTISEgaining up-to-date

knowledge for the goal of constant professional development, and the

ability to implement it in an actual business

processes.

POSITIVISM AND COOPERATION

readiness to participate in multifunctional groups and

projects, eagerness to meet demands of colleagues from other units of the company,

willingness to exchange information, ability to work in

a team.

INITIATIVE AND RESPONSIBILITY

finding and suggesting new solutions both in

the working environment, and in the

sphere of company interests.

COLLECTIVE RESULTS

collective effort in achieving a visible and

meaningful result, a desire to succeed and

provide each other with needed assistance.

Page 6: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Business scheme

6

NISbusiness scheme

Seismics

Exploratory well

Consumers

Production well

Gathering station

Gas refinery

RefineryTransportation

Page 7: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Business Structure Review

NIS j.s.c.

Foreign Representative OfficesExpert Services

Exploration and Production (Upstream)

Refining Oilfield Services Sales & Distribution Energy

7

Page 8: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Modernization of Refinery Units

Page 9: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Hystory of Pancevo Oil Refinery

1968Construction

of the Refinery

1979Capacity

icreased to 4.8 mln. tons per

year

1982Bitumen Production

Unit and Vacuum Distillation Unit

1985The Catalytic Cracking Unit,

FCC

1985 – 1988The Diesel

Hydrotreater Unit, theSulphuric Acid

Alkylation

1990reconstruction of a Two-Stage Thermal Cracking Unit for the

visbreaking process; the following units were put into

operation: the Unit for Extraction of Aromatic

Hydrocarbons, the Unit for Molten Sulphur Production,

truck loading/unloading facility for petroleum products

2009 – 2012Modernization –

construction of theMHC/DHT Unit

November, 1st 2012

9

Page 10: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Фазе модернизације капацитета за прерадунафте

10

First phase – meeting the requirements of modern standards for Euro 5 product quality

• an improvement of motor fuel quality• a higher conversion of high-yield products• advanced indicators of the bottom of the barrel and production of "white" petroleum products.

Second phase – development of the production chain for a wider range of products

• Reconstruction of the Novi Sad Refinery, production of high-quality base oils. • Additional reconstruction of the Pančevo Refinery, the process of heavy residue refining.

Third phase – increased bottom of the barrel

• Reconstruction of Pančevo Refinery so that it could be included in the technological chain of the process of heavy residue refining and optimization of process flows.

Page 11: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Construction of MHC/DHT ComplexEnvironmental ProgrammesFirst Phase of Reconstruction

2009

Quality• Production of petroleum products of EURO 0 quality

standard: • Production of leaded gasoline

Environment• High level of negative influence on the environment • High losses

Efficiency• Low Nelson index • Large percentage of fuel for the Company’s own

needs • Energy efficiency index is the worst in the region• Manpower index is the worst in the region

2012

Quality• Production of motor fuels of EURO 5 quality

standard only

Environment• Reconstruction of the main facilities of pollution (river

jetty, truck loading facility, rail tank car loading facility).

• Transfer to natural gas as fuel for the refineries• Smaller losses

Efficiency• Higher Nelson index• Smaller percentage of fuel for own needs • Higher index of energy efficiency • Higher index of manpower

11

Page 12: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Operation of MHC/DHT complex will enable:

• Increased production of white petroleum products

• Increased bottom of the barrel

• Higher quality of motor fuels

Changed Structure of the Production of Motor FuelsFirst Phase of Reconstruction

EURO5 BMB 95

5%

EURO5 BMB 95

100%

BMB 95; 95%

DIESEL EURO 5;

40%

DIESEL EURO 5;

100%*

DIESELD-2; 60%

PBS

EUROAUTOGAS

EN 589

Before MHC/DHT construction

After MHC/DHT construction

12 *Data for 2014 and 2015

0

1000

2009 2010 2011 2012 2013 2014 2015

Product structure(thousand tons)

Diesel euro 5 Euro BMB95Diesel 10000ppm BMB95Ethyl MB95

Page 13: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

0,0

0,5

1,0

1,5

2008 2009 2010 2011 2012

Emission of exhaust gases into the atmosphere (thousand tons)

Environmental Effects

First Phase of Reconstruction

1,54

1,26

0,82 0,78 0,78 0,74 0,7

0,20

0,40

0,60

0,80

1,00

1,20

1,40

1,60

1,80

2008 2009 2010 2011 2012 2013 2014 2015

Non-recurring losses, % of HC feed

13

Page 14: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Reconstruction of Novi Sad Refinery"Production of Base Oils" ProjectSecond Phase of Reconstruction (to be completed in 2015)

Objective

• Maximum effects from purposeful refining of oil of Velebit type and hydrocracking residue from the MHC unit

• A wider range of products and start of the production of new high-quality products

Result

• a higher profit margin, as compared to the basic variant, due to a purposeful refining of the Velebit type oil and the hydrocracking residue, in case of a variant including oil production;

• an additional profit margin due to the development of production of finished oils

• additional possibilities of potential development of other directions of business within the refinery: production of bitumen, technical liquids, lubricants, etc.;

• maximum utilization of the current fixed assets of Novi Sad Refinery, NIS j.s.c. storage, rail tank car and truck loading/unloading facility for petroleum products, river jetty for fuel bunkering;

• concentration of the entire oil business at one place will enable savings of production and logistics costs

14

Page 15: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

• Solving problems of "bottom necks" and optimization of production of petroleum products in order to meetmarket demands

• Liquidation or minimization of production of heavy fuel oil and other black petroleum products

• The quality of motor oils and mixture of propane and butane should meet the Euro standards (minimum EN-228, EN 590, EN 589);

• Meeting the EU environmental standards (including the standards related to СО2 emissions)

Optimization of Refining in Pančevo Oil Refinery (RNP)Bottom of the BarrelThird Phase of Reconstruction (to be completed in 2016)

An objective of the project

Optimization of oil refining, including refining of oil residues in NIS Refinery in Pančevo, taking intoaccount the possible interaction with production units of the Refinery in Novi Sad

15

Page 16: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Business plan2013 - 2015

Page 17: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Basic Directions of Development

Exploration and Production→ Development of the projects in Serbia, Hungary, Romania and Bosnia and Herzegovina

Sales and Distribution→ Further modernization of Pančevo Refinery – bottom of the barrel project→ Production of base oils→ Development of the markets in the Balkan region

Energy→ Development of energy in the area of renewable energy sources→ Gas monetization

17

Page 18: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Sales

Western Romania

South Hungary

Bosnia and Herzegovina

Construction/Reconstruction

Existing objects

End2012

38

14

24

Current status

24

9

15

Bulgaria, the number of retail sites

Ret

ail

Who

lesa

le

Completed transaction by acquiring depot Kostin Brod in Sofia

Purchased land for the construction of depot Timisoara

Exploration and production

Implemented 3 transactions "farm-in", signed documents on JOA. The role of the operator assigned to NIS in the largest project - East West (85% operator). Initiated 2D seismic on the project Moesia (share of NIS 50%) not the

operator of NIS. Negotiations with the owners of the remaining blocks (Zeta).

Drilling was started on the project RAG. Negotiations on greater cooperation with the company. The deal with Falcon runs expertise in the Ministry of

Finance of Hungary

Jadran-Naftagaz: End of data processing and interpretation of 2D seismic survey for the year 2012. Development of the project (by October) is to drill the first exploration wells.

Romania, the number of retail sites Bosnia, the number of retail sites30

29

125

25

36**

28

8

8

26

*Including completed or partial reconstructed objects in accordance with invest.projects** Without a possible exchange with Zarubezhneft stations

Construction/Reconstruction

Existing objects

Construction/Reconstruction

Existing objects

End2012

Current status End2012

Current status

Regional development projects status: NIS is becoming regional company with PS network in 4 countries

Page 19: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Exploration and Production (UPS) – Priorities of Development

19

A higher level of production and greater resource base.

The leader in the region in the area of reduction of hydrocarbon production costs.

High level of operational efficiency.

State-of-the-art technologies and methods for oil and gas production.

Emphasis on the basic aspect of business operations (oil and gas production).

A wider scope of business operations due to the grants (share of production due to grants minimum 30% of the total production).

Increased investment efficiency (LC reduction, GTM optimization, application of new technologies, etc)

Greater resource base in Serbia and abroad

• The greatest international companies compensate a drop in the production in traditional regions of business with the help of CIS and the Near East.

• Smaller resource bases and more complex geological conditions of hydrocarbon deposits, higher unconventional supplies.

• Higher Lifting costs and other costs of exploration and production.

• Outsourcing of non-core business operations.

MARKET TRENDS NIS PRIORITIES

11

44

22

33

55

66

77

88

Page 20: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Exploration and Production (UPS) – Higher Scope of Production

Realized and planned scope of NIS production in the period from 2009 to 2015 .

• A further increase in trend of domestic production, but with the smaller rates of increase as compared to the previous years

• Increased production by way of active development of new fields and projects abroad.

• Increased production of natural gas by way of exploration and development of unconventional resources.

OIL AND GAS PRODUCTION, million conditional tons

20

0

1

2

3

2009 2010 2011 2012 (E) 2013 (E) 2014 (E) 2015 (E)

Domestic oil and gas Oil and gas from abroad

Page 21: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Projects at Pannonian basin and wider logisticallyavailable zone considered – potential projects ensure2020 goals achievement, after 2020 downfall is expected

Slovakia

Austria

Slovenia

Hungary*

Romania

Bulgaria

Croatia

Bosnia

Ukraine

Serbia

Czech Republic

Ascent and Dual Ex

Key prioritization of regional development projects - synergy with NIS refining and easiness ofmonetization. 2 options are planned - purchase of shares of small- and medium sized players andJVs with large companies in the region (Romania, Hungary, Bulgaria, Montenegro)

Priority 1. Pannonian basin

Priority 2. Development area allowingaccess to NIS refineries (self monetization)

Priorities of regional development:

Aspect andJKX

NIS and RAGNIS andFalcon

NIS andAscent

NIS andMoesia

NIS andMOL/expert*

NIS and East West Petroleum

NIS andNeftgazinkor

NIS and Zeta

Pannonian basin:Hungary: MOL is controlling company‟s interest in other parts of Hungary and it is not interested in cooperation, except the cooperation in terms of Expert project discussion. Negotiations are ongoing. Next license round is planned in Hungary for 2013Adriatic's:Studies were made, as well as concession negotiations held in Croatia, Montenegro and Albania.Expansion possibility study, relating to the North Africa and Mediterranean.

Considered assets/projects at Pannonian basin

MOL and Expert Petroleum

Rompetrol and Winstar

Universal Petroleum

RAG and ADX Energy

Clara Petroleum

Page 22: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Refining (REF) – Priorities of Development

Realization of modernization and reconstruction progremme.

Decreasing of losses and own consumption.

Increase of refining margins.

Improved quality of products (Euro-5, white derivatives, refining level) .

Operative improvements.

11

22

33

• Oversupply of Refining Capacities in the region.

• Lower refining margins.

• Increased competition on oil derivatives market.

• Constant changes of legislative and convergence to legislation and technical regulations in the EU.

• Required minimum share of biofuels in the EU.

• Market liberalization in RS.

MARKET TRENDS NIS’ PRIORITIES

44

55

22

Page 23: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Internal Efficiency> External Synergies and Factors>

– Sales and Trading efficiency – volume, margins, quality, standards, working capital/stocks, seasonality, etc.

– Cooperation with HIP Petrohemija.

– Energy and steam supply and cooperation with NIS Energy&Gas business unit.

– Bio-fuels – production at RNS/blending

– HSE Legislation and Technical requirements..

– Configuration of RNS and RNP;

– Feedstock crude;

– In-bound crude logistics;

– Out-bound product logistics;

– Utilization;

– Special Product Units (including bitumen, base oils, etc);

– Energy Efficiency;

– Integrity and Maintenance;

– Personnel and Efficiency;

– Infrastructure;

– OPEX efficiency, etc.

RefineryMargin

Possibilities of Improvement

Key factors, contributing to refinery cash margin

Capacity use at the level of 4.5 mln tons per year.

Crude oiltransportation

costs‟ decrease

Deep conversion

HIPP utilization Net refining margin

increase

Base oils

Key factors, ensuring the marginal revenue increase at the RNP – deep conversion, base oils and cooperation with HIP Petrohemija

Page 24: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

-3%3%

10% 7% 9% 9%4%

2% 2% 2%7%

7% 8% 7%

18%14% 13% 13%

3%

2% 2% 2%

18%

2% 2% 1%

13%

33% 33% 33%

6% 12% 12% 12%

19%17% 16% 16%

4%4% 3% 3%

2012 (E) 2013 (E) 2014 (E) 2015 (E)

Gas, Propylene

Gasoline + Gasolinecomponents for export

Naphtha

Euro diesel

Diesel fuel (D-2 and fuel oil)

Kerosine

Heavy fuel oil

Bitumen

Raffinates and other

Fuel for own consumption andlosses

Cng. in inventory ofsemiproducts

9%

24

Base oils

44% 10%Refining and processing volumeIn .000t

• Oil refining and production ofpetroleum products is planned onlyfor Pančevo Oil Refinery in 2013and 2014, due to the shut-down ofthe Novi Sad Oil Refinery for thepurpose of reconstruction.

• Higher production of motorgasolines and middle distillate fuels.

• In 2014 and 2015 the scope ofproduction will increase, and thestructure of fuel production inPančevo Oil Refinery will remainunchanged;

• a unit for the production of base oilsis expected to be commissioned inNovi Sad Refinery in 2015.

Structure of Production of Petroleum Products

Refining Pursuant to the Expected Market Demands

2.372 3.409 3.766 4.105

Page 25: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Sales and Distribution (PRO) – Priorities ofDevelopment

Development of PS network (including capital construction and regional development).

Provision of a stable share in the market for basic types of fuel by developing powerful brands.

Development of production portfolio.

Increase in the wholesale market.

Development of a logistic network in the new markets

Economic efficiency as well as themaintenance and development of competitive advantages.

• Programme• Lease of the petrol stations with

low/no cost-effectiveness

• Maintaining the high appeal of premium channel of sales and great competitiveness.

• Market liberalization (free-of-charge import of gasoline), although not many a participants in the market have the required infrastructure.

• Branded PSs are still a guarantee for fuel quality.

• The growing market is expected to make the competition between the participants be based on different positioning of company brands.

• Changes in the competitor requirements:• Additional requirement for bid

differentiation;• Increase in yields from the

accompanying goods and services;

MARKET TRENDS NIS PRIORITIES

11

22

33

44

55

66

25

Page 26: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

MARKET ACCESS TO NEARBY COUNTRIES HAS LIMITATIONS,WHILE IN MOST COUNTRIES PRICING IS BASED ON IMPORTPARITY

*All these costs do not include the cost of obligatory stock and biological components

*

Import parity. INA has about 90% marketshare. Access is further complicated by

geopolitical factors

Import parity. MOL has about 90% of themarket and the pipeline system. Access

complicated.

Import parity. The market is dividedbetween the leading retailers and

integrated players. NIS is competitive inthe western part of the country..

Import parity. The market is dividedbetween the leading retailers and

integrated players. NIS is competitive inthe eastern and northern parts of the

country.

Import parity. Themain market on thecoast. logistically,

NIS is not competitivewith Kotor (Hellenic).

Import parity.The main market on the coast.

Logistically, NIS is not competitive withimporters.

60

Danube to theBlack Sea

Import parity. NIS isnot competitive withthe Octa company

and with the importerHellenic Petroleum.

Import parity. The marketis divided between theleading retailers and

integrated players. NIS iscompetitive in thewestern part of the

country.

Black SeaFOB MED + / -FOB-MED/CIF

differentialCore region in accordancewith the approved Conceptof Regional Development

Legend:

26

Page 27: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Increased Scope of Sales and Distribution

Retail Market in Serbia

VOLUME OF NIS’ RETAIL MARKET IN SERBIA PER PETROLEUM PRODUCTS (in thousand tons)

VOLUME OF RETAIL MARKET OF MOTOR FUELS IN SERBIA(in thousand tons)

• After a drop in consumption in the market in 2013 ascompared to 2012, a gradual recovery of the market isenvisaged to occur in 2014.

• A part of quantities will be transferred from wholesale toretail channel of the corporate clients.

0

1.000

2.000

2012 (П) 2013 (П) 2014 (П) 2015 (П)

ТНГ аутогас Бензини Дизели ЕЛ

1.614 1.597 1.616 1.629

0

1.000

2012 (П) 2013 (П) 2014 (П) 2015 (П)

ТНГ аутогас Бензини Дизел (укљ. ЕЛ) Евродизел

585 637 666739

• Modernization of the retail network in Serbia• Transfer to the products of the EU quality standard

27

LPG auto gas Gasoline Diesel EL LPG auto gas Gasoline Diesel (incl. EL) Euro diesel

Page 28: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Oil Field Services (OFS) – Priorities of Development

• Increased efficiency of services.

• Increase in staff of Oil Field Services.

• Increased business revenue from the third parties.

• Meeting of internal production needs of the NIS in the area of Oil Field Services.

• Placement at the international market in order to maximize utilization of production capacities and to implement projects with a high profit marginpotential.

11

2233

• Specializing companies in specific types of services and establishing companies which are specialized in Oil Field Services.

• Regional competitiveness usually includes local, i.e. former state-owned companies with a variable level of quality and services.

• Relatively low technical level of services proposed by the regional service companies.

• Increased quality of services.

MARKET TRENDS NIS PRIORITIES

44

55

28

Page 29: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

Energy (ENR) – Priorities of Development

Implementation of projects of electric power generation based on utilization of the Company's own natural gas.

Participation in the projects in the area of alternative energy under the condition of a given Governmental support.

Optimization of utilization of thermal and electric energy, increased energy efficiency of the business.

Diverse ways of implementation of natural gas.

• Great possibility of increase in prices of electric power.

• Liberalization of market of electric power and natural gas.

• The need to compensate СО2 ratio.

• Increased share of renewable energy.

• Developed support to utilization of renewable energy sources in the region.

MARKET TRENDS NIS PRIORITIES

11

22

33

44

29

Page 30: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

2012 – first steps in implementation of strategy

First and second level priorities

CHP Novi SadIn the consortium NIS won the tender, terms of project implementation are currently under negotiation process.

GTE in SerbiaIdentified locations for the projects, on the first of them wells were tested.

CHP PancevoBasic engineering design and approval procedure with regulatory authorities of Serbia have been started.

Small cogeneration11 potential location for projects development were identified, tenders for 2 facilities building are completed.

Wind farm in SerbiaApproval of the transactions conducted in accordance with corporate procedures, the closing of the transaction by the end of 2012.

Wind farm in RomaniaThe most perspective projects in Romania were chosen, the deal is in the process of approval by BoD of NIS.

TPP KovinPermission for geological research was obtained, reserves of coal are being estimated, technical-commercial offer was submitted by EPC contractor

30

Page 31: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

0%

25%

50%

75%

100%

2012 (П) 2013 (П) 2014 (П) 2015 (П)

Head office (STS)

Energy

Oilfield Services (OFS)

Sales&Distribution (PRO)Refining (REF)

Upstream (UPS)

Financial Indicators

Expectations

31

Sales (without excise tax)(billion RSD)

DISTRIBUTION OF CAPEX PER PROFILE BLOCKS (billion RSD)

48 59 5066

0

200

400

2012 (П) 2013 (П) 2014 (П) 2015 (П)

Page 32: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

32

Dynamics of share capital and book value per share

in b

illio

n R

SD

RSD/share

Page 33: NaftnaindustrijaSrbijej.s.c.. Novi Sadir.nis.eu/fileadmin/template/nis/pdf/Reporting/...Reconstruction of Novi Sad Refinery "Production of Base Oils"Project Second Phase of Reconstruction

33

NIS a.d. Novi SadInvestor Relations Sector

Narodnog fronta 1221000 Novi Sad, Serbia

e-mail: [email protected]