Narrabri Flowlines Overview Sept 18th 2013
![Page 2: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/2.jpg)
2
Provide the necessary facilities to allow sustainable CSG production and associated produced water;
Provide a safe, fit for purpose design wellhead design;
Protect and enhance Santos’ reputation as a high quality operator and supporting positive community and stakeholder relations;
Minimise footprint;
To pay high regard to the regulator and achieve environmental and regulatory compliance in the shortest time frame possible;
Maximise value of the PEL 238 asset;
Produce CSG to meet sales gas specification; and
Prove Santos’ ability to deliver gas to the NSW market.
Project Drivers - Summary
![Page 3: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/3.jpg)
3
Dewhurst Flowlines Summary
Dewhurst 26-29 Pilot
Dewhurst Southern Flowline
Proposed to construct and operate gas and water flowlines;
These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water Transfer Facility;
- The Dewhurst Northern Water flowline will link Dewhurst 6, 13-18 and 22-25 to the Bibblewindi Water Transfer Facility;
- The Dewhurst Southern Water and Gas flowlines will link Dewhurst 26 – 29 and 30 - 31 pilot to the Bibblewindi Multi Lateral Pilot;
REF approval for flow lines has been received;
Flowlines will run parallel to existing tracks and roads as much as possible to minimise clearing (disturbance) during construction;
A ten metre construction corridor is required and will subsequently be rehabilitated to approximately a three metre operational corridor.
![Page 4: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/4.jpg)
4
Dewhurst Flowlines Route
Dewhurst 26-29 Pilot
Dewhurst Southern Flowline
![Page 5: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/5.jpg)
5
Dewhurst Flowlines Route
Dewhurst 26-29 Pilot
Dewhurst Southern Flowline
![Page 6: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/6.jpg)
6
Dewhurst Flowlines Route
Dewhurst 26-29 Pilot
Dewhurst Southern Flowline
![Page 7: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/7.jpg)
7
Dewhurst Flowlines
Dewhurst 26-29 Pilot
Dewhurst Southern Flowline
![Page 8: Narrabri Flowlines Overview - Narrabri Gas Project€¦ · These flowlines will connect the proposed new wells to the new Leewood Produced Water Facility via the Bibblewindi Water](https://reader034.vdocuments.net/reader034/viewer/2022050323/5f8a3dbd9afe0b1f8a4cbab3/html5/thumbnails/8.jpg)
8
Dewhurst Flowlines
Dewhurst 26-29 Pilot
Dewhurst Southern Flowline