national training for commissioning, 2006 · national training for commissioning , ... in addition...
TRANSCRIPT
1
CommissioningCommissioning
National Training for Commissioning , 2006
Presented By Paul Sra and Mike Cavan
2
Scope of PresentationScope of Presentation
• Commissioning overview • Commissioning requirements for LEED
Standard• Roles and responsibilities of key persons
for projects in regard to commissioning• Commissioning process and its
deliverables• Case studies
3
What is Commissioning?What is Commissioning?
• ASHRAE defines the commissioning process as “ a quality oriented process for achieving, verifying and documenting that the perforamnce of facilities, systems and assemblies meet the defined objectives and criteria”
• Commissioning is a quality assurance process where verification against design criteria is carried out, and ensures that adequate documention and O & M training has been provided.
4
What is Commissioning?What is Commissioning?
• A planned program of activities that advances the built works from the earliest stages of the Planning Phase to a condition of full operation, meeting all objectives of commissioning as defined by the client’s functional program and the design intent. Commissioning is documenting for future operations.
5
Commissioning Requirements forLEED Standards
For any LEED project, there are 6 fundamental Cx items that must be followed to attain LEED Certification;
•Engage a Cx Manager/Commissioning Authority•Review Design Intent & other Design documentation.•Include Cx requirements in Construction Specifications•Develop & utilize a Cx Plan•Verify installation, functional performance, training & Cx documentation•Provide a final Cx report at the end of the project
6
Securing the Additional Commissioning Credit in The LEED System
In addition to fundamental building Commissioning, an additional commissioning related point could be achieved:
•Commissioning Authority independent of the design team shall conduct a peer review of the design development, construction documents and contractor’s submittals such as shop drawings.•Provide a single manual containing all information required for re-commissioning the bldg. system•Conduct a near end of warranty and plan to address occupant concerns
7
Why do we Commission?Why do we Commission?
• We Commission in order to provide a smooth transition from construction of the built works to an operational state.
8
Level /Extent of Commissioning
In order to manage the cost and result of the commissioning process, owners must consider the following three basic questions:What systems should be commissioned
What tasks should be completed in order to commission each systemWho should be responsible for each task. Other factors: Type of project- new construction, fit-up, general purpose office, laboratory, Heritage Facility
9
Level/Extent of Commissioning(cont.)
Complexity of project: Is it a Floor fit-up or Level 3 Lab - HVAC Containment /Fumehoods / Biological Safety Cabinets Profile of project LEED Certification
10
IntegratedSecurity
IndoorEnvironment
Heating &
CoolingPlant
Life SafetySystems
ElectricalDistribution
ArchitecturalRoof system, curtain wall system
IntegratedMechanical
&Electrical
BuildingEnvelope
BuildingAutomation
System(BAS)
VerticalTransportation
Facility
Commissioning of Total Building Systems
EmergencyPower
Generation
11
Benefits of Commissioning
1) Comprehensive understanding of Client’s needs (such as functional and operational requirements)
2) Reduce tenant complaints and reduce O&M costs (by providing appropriate systems & equipment considering maintainability)
3)Indoor air quality parameters verified
4) Protection of health & safety of occupants (e.g. verification of Fire protection, life safety systems, security & operation of facility)
12
Objectives ofCommissioning (Cont’d)
5) Meet established energy budgets
6) Facilitates quality of construction and
installation
7) Comprehensive training and documentation
8) Reduce risk of system failure/shutdown
13
When does Commissioning start?When does Commissioning start?
• Commissioning starts at the planning phase and continues throughout all phases of the project. Commissioning supports total quality assurance in the design and development of facilities to meet client’s needs.
14
Commissioning Activities in the PDS: Who is Involved
Commissioning involves an integrated team comprising of:•The Owner/Client
•The Project Manager
•The Commissioning Manager / Authority
•The Designer (Consultant)
•The Contractor
•Property Manager
15
Owner / Client Responsibilities
• Provides program requirements (technical & functional)
• Defines performance objectives & standards (technical data sheets)
• Sets Budgets & Schedules (milestones)
• Participates in selective Performance Tests
• Attends Training
• Participates to Interim acceptance process
16
Overall responsibility for delivery of the project (of which Commissioning is part)
• Manages:- Contracts (consultants, contractors, client).- Relationship (Professional and Technical
Services, Owner, Consultants, Commissioning Manager, Contractors, Property Manager.
- All funding.
Project Manager Responsibilities
17
• Coordinates Commissioning activities with the project team
• Carries out Quality Assurance on behalf of the Owner / Investor, Project Manager & Property Manager
• Reviews “Commissioning Plan” to ensure that plan is
tailored to facility requirements
• Manages Commissioning process.
Commissioning Manager / AuthorityResponsibilities
18
Commissioning Manager / AuthorityResponsibilities (Cont’d)
Reviews:• and accepts Designer developed Cx specifications which include check sheets and functional performance tests.
• Design Intent & Concept drawing• Design progress drawings
(33%,66%,99%,100% & tender drawings)• O&M Manuals• Witnessing of equipment, system &
Integrated & system performance tests
19
Design ConsultantResponsibilitiesDesign ConsultantResponsibilities
• Liable and accountable• Develops the “Commissioning Plan”• Produces the Commissioning manual and Design Intent• Develops the “Commissioning Specifications” • Develops the “Training Plan”• Develops the Commissioning forms (PI/PV & checklists)• Develops and certifies the functional performance tests
20
Design Consultant Responsibilities (Cont’d)
•Administers and reports on the commissioning process with the Contractor
•Provides approvals on verifications and testing
•Witnesses testing (as required)•Assists in documentation turnover
21
• Accountable contractually
• Executes the commissioning deliverables as defined in the contract documents
• Develops the Commissioning schedule • Refines the Commissioning Plan• Executes & documents the functional performance
(tests)• Prepares & submits the O&M manual, training, as-builts,
warranties
General Contractor Responsibilities
22
Property Manager Responsibilities
• Receives the facility once project is complete
• Receives all documents required for operation
• Manages the facility
• Implements the Management Plan (BMP, MMS, Service contracts)
• Operates the facility through out its useful life
23
The Commissioning Process-1 *The Commissioning Process-1 *
The Commissioning Process is based on the National Project Management System (NPMS)• Project Inception Stage-Definition phase
• Project Identification Stage
Initiation phase
Feasibility phase
Analysis phase
Identification Close -out phase
24
The Commissioning Process-2 *The Commissioning Process-2 *
The Commissioning Process is based on the National Project Management System (NPMS)
• Project Delivery stage
Planning phase
Design phase
Implementation phase
Delivery Close-out phase
25
Commissioning Activities in the NPMS
Project inception/Project identification stage
• Owner identifies the project’s operational and functional requirements as well as sets budgets and milestones
• Establishes Commissioning needsProject Inception
StageProject Identification
StageProject Delivery
Stage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design Implementation Close-out
Project Management
Commissioning Process
26
Commissioning Activities in the NPMS
Project Delivery Stage- Planning phase
• A list of Commissioning deliverables is identified and is included in the consultant brief (RFP, scope of work)
• This includes definition of building O&M and user requirements
• A Commissioning Manager (for the project) is appointedProject Inception
StageProject Identification
StageProject Delivery
Stage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design Implementation Close-out
Project Management
Commissioning Process
27
Commissioning Activities in the NPMS
Project Delivery stage – Design phase• Develop design intent• Preliminary O&M and energy budget• Prepare “Preliminary Commissioning Plan” to
meet facility requirements & users needs within the facility
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design Implementation Close-out
Project Management
Commissioning Process
28
Commissioning Activities in the NPMS
Project Delivery stage – Implementation phase
• Develop Building Management Manual• Review design to ensure facility needs have
been addressed
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
29
Commissioning Activities in the NPMS
Project Delivery stage – Implementation phase
• Finalize commissioning plan• Develop specification and performance
verification forms to permit effective Commissioning of the facility.
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
30
Commissioning Activities in the NPMS
Project Delivery Stage-Implementation phase • Develop a “Training Plan” to meet the requirements of the facility operators.•Provide input to requirements for the construction phase andestablishes an O&M budget
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
31
Commissioning Activities in the NPMS
Project Delivery Stage-implementation phase•Provide input to requirements for the construction phase andestablishes an O&M budget
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
32
Commissioning Activities in the NPMS
• Project Delivery stage –implementation
• Review the Building System Shop Drawings for O&M
• Develop the Commissioning Schedule• Finalize the “Commissioning Plan”
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
33
Commissioning Activities in the NPMS
• Project Delivery stage –implementation phase
• Completion of Product Information/ Performance Verification(PI/PV) forms
• Site Co-ordination Meetings
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
34
Commissioning Activities in the NPMS
Project Delivery stage –implementation phase
• Complete the installation checklist• O&M Manuals• As-Built drawings• Warranties
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
35
Commissioning Activities in the NPMS
• Equipment, systems and integrated systems commissioning tests are performed and witnessed
• Operational and Maintenance Manual(s) are completed• Finalize Building Management Manual• Ensure Commissioning deliverables are provided• Interim acceptance is recommended to the Project
Manager• Ensure training of O&M staff is completed
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design ImplementationClose-out
Project Management
Commissioning Process
36
Commissioning Activities in the NPMS
Project Delivery stage –closeout phase -1
• Complete all deferred commissioning tests & activities• Assist in the fine tuning of systems• Complete all outstanding design and construction
(contractual) deficiencies relating to O & M issues• Recommend final acceptance to the project manager
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design Implementation Close-out
Project Management
Commissioning Process
37
Commissioning Activities in the NPMS
Project Delivery stage–closeout phase-2• Project Team evaluation of lessons learned
• Assist the project manager in preparation of the final evaluation report
Project InceptionStage
Project IdentificationStage
Project DeliveryStage
Definition Initiation Feasibility Analysis IdentificationClose-out
Planning Design Implementation Close-out
Project Management
Commissioning Process
38
Summary - Commissioning Deliverables
Summary - Commissioning Deliverables
• Commissioning Plan
• Design reviews for O&M impacts
• Design Intent / System Operating Manual
• Commissioning Specifications
39
Summary - Commissioning Deliverables (Cont’d)
• Commissioning Performance testing (PI/PV & checklists)
• Commissioning schedule
• Training
• Operation and Maintenance manuals(O&M)
• As-Built drawings
• Warranty (Documentation)
40
Commissioning: Return on Investment
Commissioning: Return on Investment
•Can reduce operational & maintenance costs(through effective recommendation in the selection ofequipment)
•Results in a product delivery with fewer deficiencies•Reduces tenant complaints•Reduces operational surprises•Operational savings offset commissioning costs in one to two years
•Extended lifecycle on equipment•Reduces changes during and after construction
43
Retro Commissioning
• EMCS & Lighting Systems• Objectives;
– Identify energy deficiencies– Optimization of systems– Identify HVAC IAQ
issues
44
Retro Commissioning
•Constructed early 70’s
•Existing mechanical systems
•EMCS approx. 10 years old
•Lighting system approx. 6 years old
45
Retro Commissioning
• Involved Operations Staff• Involved the EMCS / Lighting
Service providers• Involved the field device
maintainer• Will involve an Energy Engineer
46
Retro Commissioning
Verifications performed on EMCS;• Field sensors and devices• Sequence of operations under normal /
Emer. procedures.• Trending of systems
47
Retro Commissioning
Key EMCS Issues Identified;• Damper performance / calibrations• VSD’s @ 100% most of the time• Induction units – 27% failure rate.• Pneumatic devices / transducer
compatibility – 34% failure rate • Operator Training
48
Retro Commissioning
Major Building Issues;• Stack effect• Age of existing equipment• Change in occupancy (space optimization)• Minor fit-ups in building over the years
49
Retro Commissioning
Lighting System; Areas of Interest• Review current system operation and
documentation• Identify Maintenance Issues• Identify energy saving potentials• Cx of lighting system controls and devices