navsea standard item numerical index fy-19 utilization · 009-48 pressure seal bonnet valve shop...

706
1 of 7 FY-19 NAVSEA STANDARD ITEM NUMERICAL INDEX FY-19 CH-1 ITEM NO. TITLE UTILIZATION CATEGORY DATE 009-01 General Criteria; accomplish I 01 OCT 2017 009-02 Environmental Compliance Report for Material Usage at Naval Facility; accomplish I 18 NOV 2016 009-03 Toxic and Hazardous Substance; control I 01 OCT 2017 009-04 Quality Management System; provide I 01 OCT 2017 009-05 Temporary Access; accomplish II 18 NOV 2016 009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations; accomplish I 06 MAR 2018 009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish I 01 OCT 2017 009-08 Shipboard Fire Protection and Fire Prevention; accomplish I 01 OCT 2017 009-09 Process Control Procedure (PCP); provide and accomplish II 01 OCT 2017 009-10 Asbestos-Containing Material (ACM); control I 18 NOV 2016 009-11 Insulation and Lagging; accomplish II 01 OCT 2017 009-12 Weld, Fabricate, and Inspect; accomplish II 01 OCT 2017 009-13 Meter; repair II 01 OCT 2017 009-14 Gage, Switch, and Thermometer; repair II 01 OCT 2017 009-15 Rotating Machinery; balance II 18 NOV 2016 009-16 Electronic Equipment; repair II 18 NOV 2016

Upload: others

Post on 23-Jul-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

  • 1 of 7 FY-19

    NAVSEA

    STANDARD ITEM

    NUMERICAL INDEX

    FY-19 CH-1

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-01 General Criteria; accomplish I 01 OCT 2017

    009-02 Environmental Compliance Report

    for Material Usage at Naval

    Facility; accomplish

    I 18 NOV 2016

    009-03 Toxic and Hazardous Substance;

    control

    I 01 OCT 2017

    009-04 Quality Management System;

    provide

    I 01 OCT 2017

    009-05 Temporary Access; accomplish II 18 NOV 2016

    009-06 Maintaining Protection and

    Cleanliness from Non-Radioactive

    Operations; accomplish

    I 06 MAR 2018

    009-07 Confined Space Entry,

    Certification, Fire Prevention

    and Housekeeping; accomplish

    I 01 OCT 2017

    009-08 Shipboard Fire Protection and

    Fire Prevention; accomplish

    I 01 OCT 2017

    009-09 Process Control Procedure (PCP);

    provide and accomplish

    II 01 OCT 2017

    009-10 Asbestos-Containing Material

    (ACM); control

    I 18 NOV 2016

    009-11 Insulation and Lagging;

    accomplish

    II 01 OCT 2017

    009-12 Weld, Fabricate, and Inspect;

    accomplish

    II 01 OCT 2017

    009-13 Meter; repair II 01 OCT 2017

    009-14 Gage, Switch, and Thermometer;

    repair

    II 01 OCT 2017

    009-15 Rotating Machinery; balance II 18 NOV 2016

    009-16 Electronic Equipment; repair II 18 NOV 2016

  • 2 of 7 FY-19

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-17 Rotating Electrical Equipment;

    repair

    II 01 OCT 2017

    009-18 Magnetic Material; control I 07 MAR 2017

    009-19 Provisioning Technical

    Documentation (PTD); provide

    I 30 JUL 2015

    009-20 Government Property; control I 01 OCT 2017

    009-21 Logistics and Technical Data;

    provide

    I 01 OCT 2017

    009-23 Interference; remove and install I 01 OCT 2017

    009-24 Authorization, Control,

    Isolation, Blanking, Tagging and

    Cleanliness; accomplish

    I 01 OCT 2017

    009-25 Structural Boundary Test;

    accomplish

    II 06 MAR 2018

    009-26 Deck Covering; accomplish II 01 OCT 2017

    009-27 Material Identification and

    Control (MIC) for Level I System;

    accomplish

    II 06 MAR 2018

    009-29 Cancelled 06 MAR 2018

    009-30 Boiler Sample Tube; inspect II 18 NOV 2016

    009-31 Boiler Waterjet Cleaning;

    accomplish

    II 18 JUL 2014

    009-32 Cleaning and Painting

    Requirements; accomplish

    II 07 MAR 2017

    009-33 Rotating Electrical Equipment;

    rewind

    II 01 OCT 2017

    009-34 Fire Protection of Unmanned

    Vessel at Contractor Facility;

    accomplish

    I 18 NOV 2016

    009-36 Controller; repair II 01 OCT 2017

    009-37 General Procedure for Woodwork;

    accomplish

    II 01 OCT 2017

    009-38 Boiler, Catapult Accumulator, and

    Reboiler Dry Lay-up; accomplish

    II 06 MAR 2018

  • 3 of 7 FY-19

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-39 Technical Manual Contract

    Requirement (TMCR) for a New

    Technical Manual for Commercial

    Equipment/Component; accomplish

    I 06 MAR 2018

    009-40 Contractor Crane, Multi-Purpose

    Machine and Material Handling

    Equipment at a Naval Facility;

    provide

    I 01 OCT 2017

    009-41 Cancelled II 06 MAR 2018

    009-42 Cancelled II 06 MAR 2018

    009-43 Engineering Plant Production

    Completion Date (PCD), Light-Off

    Assessment (LOA) Support; provide

    II 30 JUL 2015

    009-45 Tapered Plug Valve; repair II 06 MAR 2018

    009-46 Butterfly Valve, Synthetic and

    Metal Seated; repair

    II 06 MAR 2018

    009-47 Gate Valve; repair II 06 MAR 2018

    009-48 Pressure Seal Bonnet Valve Shop

    Repair; accomplish

    II 01 OCT 2017

    009-49 Pressure Seal Bonnet Valve In-

    line Repair; accomplish

    II 01 OCT 2017

    009-50 Horizontal Swing Check Valve;

    repair

    II 06 MAR 2018

    009-51 Cancelled 06 MAR 2018

    009-52 Relief Valve; repair II 06 MAR 2018

    009-53 Bolted Bonnet, Globe, Globe

    Angle, and Globe Stop Check

    Valve Shop Repair; accomplish

    II 06 MAR 2018

    009-54 Bolted Bonnet, Globe, Globe

    Angle, and Globe Stop Check

    Valve In-line Repair; accomplish

    II 06 MAR 2018

    009-55 Regulating/Reducing Valve; repair II 06 MAR 2018

    009-56 Main Propulsion Boiler Wet Lay-

    up; accomplish

    II 18 NOV 2016

    009-57 Reduction Gear Security;

    accomplish

    II 18 NOV 2016

  • 4 of 7 FY-19

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-58 Pump and Driver Shaft Alignment;

    accomplish

    II 01 SEP 2015

    009-59 Organotin Antifouling Material;

    control

    II 18 NOV 2016

    009-60 Schedule and Associated Reports

    for Availabilities Over 9 Weeks

    in Duration; provide and manage

    I 01 OCT 2017

    009-61 Shipboard Use of Fluorocarbons;

    control

    I 18 JUL 2014

    009-62 Boiler Handhole, Manhole Seat and

    Plate; inspect

    II 18 NOV 2016

    009-63 Lubricating Oil and Hydraulic

    Fluid; analyze

    II 18 NOV 2016

    009-64 Synthetic Fire Resistant

    Hydraulic Fluid; control

    II 18 NOV 2016

    009-65 Polychlorinated Biphenyls (PCBs);

    control

    I 01 OCT 2017

    009-67 Integrated Total Ship Testing;

    manage

    I 01 OCT 2017

    009-68 Cancelled 06 MAR 2018

    009-69 Heavy Weather/Mooring Plan;

    provide

    I 01 OCT 2017

    009-70 Confined Space Entry,

    Certification, Fire Protection,

    Fire Prevention, and Housekeeping

    for Unmanned Vessel; accomplish

    I 18 NOV 2016

    009-71 Piping System; test II 06 MAR 2018

    009-72 Physical Security at a Private

    Contractor Facility; accomplish

    I 01 OCT 2017

    009-73 Shipboard Electrical/Electronic

    Cable Procedure; accomplish

    I 01 OCT 2017

    009-74 Occupational, Safety and Health

    Plan; accomplish

    I 01 OCT 2017

    009-75 Circuit Breaker; repair II 06 MAR 2018

    009-76 Waveguide and Rigid Coaxial Lay-

    Up; accomplish

    II 18 NOV 2016

  • 5 of 7 FY-19

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-77 Cofferdam Installation;

    accomplish

    II 01 OCT 2017

    009-78 Passive Countermeasures System

    (PCMS) Material; repair

    II 18 NOV 2016

    009-79 Government Owned Material (GOM)

    Status; report

    I 18 NOV 2016

    009-80 Ship Facilities; maintain I 18 NOV 2016

    009-81 Compartment Closeout; accomplish I 06 MAR 2018

    009-82 Installation of Equal Component

    Vice Specified Component; report

    I 18 NOV 2016

    009-83 Wire Rope Assembly; fabricate II 18 NOV 2016

    009-84 Threaded Fastener Requirements;

    accomplish

    I 01 OCT 2017

    009-85 Government Sponsored Planning

    Yard/Configuration Data Manager

    (CDM) On-Site Representative

    Facility; provide

    II 19 JUL 2007

    009-86 Recovery and Turn-In of Ozone

    Depleting Substance (ODS);

    accomplish

    II 18 NOV 2016

    009-87 Chemical Disinfection Procedure;

    accomplish

    II 01 OCT 2017

    009-88 Collection, Holding and Transfer

    (CHT) and Motor Gasoline(MOGAS)

    Tanks, Spaces, and Piping,

    including Sewage or MOGAS-

    Contaminated Tanks, Spaces, and

    Piping; certify

    II 18 NOV 2016

    009-89 Contractor Furnished

    Anode(Purchase and Inspection);

    accomplish

    II 06 MAR 2018

    009-90 Technical Representative; provide II 01 OCT 2017

    009-91 Propeller In-Place Inspection;

    accomplish

    II 01 OCT 2017

    009-92 Resilient Mount; install II 18 NOV 2016

  • 6 of 7 FY-19

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-93 Emergency Planning and Community

    Right-to-Know Act (EPCRA) and

    Pollution Prevention Act (PPA)

    Information; provide

    I 06 MAR 2018

    009-94 General Environmental Work at

    Contractor Facility; accomplish

    I 18 NOV 2016

    009-95 Mechanically Attached Fitting

    (MAFs); install

    II 01 OCT 2017

    009-96 Ball Valve; repair II 06 MAR 2018

    009-97 Shipbuilding and Ship Repair

    Operations National Emission

    Standard for Hazardous Air

    Pollutants (NESHAPS) for Surface

    Coating Information; provide

    I 17 JAN 2013

    009-99 Ship Departure Report; provide I 18 JUL 2014

    009-100 Ship's Stability; maintain I 06 MAR 2018

    009-101 Ship Transit and Berthing;

    accomplish

    I 18 NOV 2016

    009-102 Alteration Verification; provide I 01 OCT 2017

    009-103 Weight and Moment Change Data;

    provide

    I 18 JUL 2014

    009-104 Vibration Testing and Analysis;

    accomplish

    II 06 MAR 2018

    009-105 Thermal Sprayed Coating for

    Machinery Component Repair;

    accomplish

    II 01 OCT 2017

    009-106 Work Authorization Form

    Coordinator (WAFCOR); provide

    I 01 OCT 2017

    009-107 Piping System Cleanliness

    Restoration (Non-Nuclear);

    accomplish

    II 01 OCT 2017

    009-108 Cancelled 06 MAR 2018

    009-109 Non-SUBSAFE Work on SUBSAFE-

    Certified Vessel; accomplish

    I 01 OCT 2017

    009-110 Non-Nuclear Work on a Nuclear

    Vessel; accomplish

    I 18 NOV 2016

  • 7 of 7 FY-19

    ITEM NO.

    TITLE

    UTILIZATION

    CATEGORY

    DATE

    009-111 Schedule and Associated Reports

    for Availabilities 9 Weeks or

    Less in Duration; provide and

    manage

    I 18 NOV 2016

    009-112 Prevention of Radiographic-

    Inspection Ionizing-Radiation

    Hazard; accomplish

    II 18 NOV 2016

    009-113 Rotating Electrical Equipment

    with a Sealed Insulation System

    (SIS); rewind

    II 01 OCT 2017

    009-114 Mold Remediation; accomplish II 07 NOV 2013

    009-115 Bearing Rebabbitting; accomplish II 30 JUL 2015

    009-116 Auxiliary and Waste Heat Boiler

    Sodium Nitrite Wet Lay-up;

    accomplish

    II 30 JUL 2015

    009-117 Combat Systems Light-Off; support I 18 NOV 2016

    009-118 CG Deck Loading; accomplish I 18 JUL 2014

    009-120 Fact Finding and Critique of

    Unplanned Event; manage

    I 06 MAR 2018

    009-121 Ship Assessment/Inspection;

    accomplish

    II 18 NOV 2016

    009-122 Temporary Padeye; install and

    remove

    I 01 OCT 2017

    009-123 Fiber Optic Component; remove,

    relocate, repair, and install

    II 01 OCT 2017

    009-124 Thermal Spray NonSkid

    Application;accomplish

    06 MAR 2018

  • 1 of 9 ITEM NO: 009-01

    FY-19

    NAVSEA

    STANDARD ITEM

    FY-19

    ITEM NO: 009-01

    DATE: 01 OCT 2017

    CATEGORY: I

    1. SCOPE:

    1.1 Title: General Criteria; accomplish

    2. REFERENCES:

    2.1 Standard Items

    2.2 40 CFR Part 61, National Emission Standards for Hazardous Air

    Pollutants

    3. REQUIREMENTS:

    3.1 Report delays to the SUPERVISOR.

    3.1.1 In the event difficulty is encountered or anticipated in

    complying with the contract schedule dates, notify the SUPERVISOR immediately

    by verbal means, followed on the next work day by an original and 2 copies of

    a letter stating pertinent details. Receipt of this notification by the

    SUPERVISOR is not to be construed as a waiver of the requirements, delivery

    schedule by the Government, or waiver of rights or remedies provided by law or

    under this Job Order or any other requirements in the Job Order relating to

    jeopardy of contract schedule dates.

    3.2 Reports:

    3.2.1 When a Work Item does not require a report, and one is

    determined to be necessary in order to produce a reliable or complete repair,

    submit one legible copy, in approved transferrable media, of a report with

    supporting data as early as possible in the contract period. The goal is to

    have required work completed within the original contract period.

    3.2.2 For reports required by 2.1 or the Work Item, that could

    result in a change in work to be accomplished or additional material to be

    procured, complete the preliminary work and submit one legible copy, in

    approved transferrable media, of the report in a time frame to allow the

    SUPERVISOR to initiate early action, but no later than the first 20 percent of

    the availability.

    3.2.3 Submit one legible copy, in approved transferrable media, of

    the following to the SUPERVISOR one day prior to the weekly progress meeting:

  • 2 of 9 ITEM NO: 009-01

    FY-19

    3.2.3.1 A report listing Government Furnished Material not

    received, showing the associated Work Item number and title, material

    description, expected delivery date, required delivery date, and action

    proposed to resolve problems resulting from late delivery. Material with

    expected delivery dates before the required delivery date need not be listed

    in this report.

    3.2.3.2 A report listing late or deficient Government

    Furnished Information, showing the associated Work Item number, deficiency

    description, and proposed corrective action.

    3.2.3.3 A report of overdue contractor condition reports by

    Work Item number and expected submission date. The report shall also include

    those deficiency and condition reports for which Government response is

    outstanding.

    3.2.4 Dry dock related inspection reports shall be submitted no

    later than the first 20 percent of the scheduled docking period. Dry dock

    related reports which contain readings (final, thickness, etc.), clearances,

    alignments, test results, or other such data for work that has to be completed

    prior to pre-flood/undocking, shall be submitted to the SUPERVISOR within one

    day after recording the data but no later than 4 days prior to pre-

    flood/undocking, whichever occurs first.

    3.2.5 Reports shall contain the following information:

    3.2.5.1 Name and hull number of ship or craft, the Job Order,

    Work Item, and paragraph numbers including Standard Item paragraph number if

    applicable.

    3.2.5.2 A description of the conditions found with supporting

    data. Include annotated sketches, graphs, and photographs when necessary to

    make a report clearly understandable to the SUPERVISOR. Identify actual

    readings/dimensions taken.

    3.2.5.3 Recommendations and/or a list of material required.

    3.2.5.4 Data required by, signature, printed name, and title

    of the contractor's representative, and submission date.

    3.2.5.5 Reports written or submitted in NMD satisfy the

    requirements of 3.2.5.4.

    3.2.6 Prepare and submit one legible copy, in approved transferrable

    media, of a listing of all reports and Process Control Procedures (PCP)

    required by the CNO/CMAV Job Order to the SUPERVISOR no later than 15 days

    prior to the start of the CNO/CMAV availability. The listing shall be

    sequential by Work Item number, and include each applicable paragraph number,

    PCP/report due date, completion date, submission date, and a provision for

    adding report serial numbers from NMD. When the equivalent information is

    provided in the Test and Inspection Plan (TIP) the report may be waived.

  • 3 of 9 ITEM NO: 009-01

    FY-19

    3.2.6.1 The report shall be revised and provided weekly

    throughout the availability to include additions, deletions, modifications,

    progress, completions, and serial numbers from NMD (e.g., Contractor Furnished

    Reports (CFR)) after numbers are assigned to the reports.

    3.2.7 Where one legible copy of a report in hard copy or approved

    transferrable media is required, or where sketches, graphs, or photographs are

    required, the electronic methods and file format shall be as agreed to by the

    SUPERVISOR.

    3.2.7.1 Use NMD, or an approved web interface with NMD, for

    contracts managed in NMD.

    3.2.8 When a report is required to be submitted but no time

    requirement is specified in the Standard Item or Work Item, it shall be

    submitted no later than 4 days after completion of the event.

    3.3 Accomplish tests and checkouts.

    3.3.1 Complete work that requires tests in time to allow correction

    of deficiencies prior to dock trials, sea trials, or other applicable

    milestones established in the Job Order.

    3.3.2 Do not operate new, existing, or repaired equipment on the

    ship. Ship's Force will accomplish such operation when required for test,

    maintenance, and checkout purposes. Such requirements will be coordinated by

    the SUPERVISOR.

    3.3.2.1 Exception will be on unmanned vessels when Ship’s

    Force is not present.

    3.4 Provide labor, material, equipment, and services (such as air, power,

    water, etc.) which are required to complete the Work Item, including that

    which is indicated on drawings or test specifications as being provided by

    sources other than the contractor, unless specifically listed as Government

    Furnished Material (GFM) in paragraph 5 of the Work Items.

    3.4.1 When a performance specification (such as MIL-PRF) is

    specified, the products approved to that specification are those listed on the

    Government Qualified Products Database (QPD) for that performance

    specification. If a Type, Class, Grade or other subcategory is listed, the

    products approved for use are limited to those that meet that subcategory on

    the performance specification’s QPD.

    3.4.2 Manufacture parts that are not available from the

    vendor/manufacturer, utilizing NAVSEA approved drawings, technical manuals,

    templates, or sketches.

    3.4.2.1 Verify latest revisions are correct via the

    SUPERVISOR prior to start of manufacture.

  • 4 of 9 ITEM NO: 009-01

    FY-19

    3.4.3 Submit one legible copy, in approved transferrable media, of a

    status report, listing Contractor Furnished Material (CFM) required to

    accomplish the work in Work Items that is not already on hand, to the

    SUPERVISOR not later than 30 days after the Job Order award, or 2 days after

    availability start date, whichever occurs first. Update the report and submit

    revisions to the SUPERVISOR every 14 days up to availability start date,

    within 10 days after availability start date, then monthly thereafter to End

    of Availability (EOA). The reports are to contain the following:

    3.4.3.1 Contract number

    3.4.3.2 Contractor's purchase order number

    3.4.3.3 Description of material

    3.4.3.4 Quantity ordered

    3.4.3.5 Date scheduled to be ordered

    3.4.3.6 Date ordered

    3.4.3.7 Date required to meet production schedule

    3.4.3.8 Proposed receipt date

    3.4.3.9 A summary listing any problem areas

    3.4.3.10 Date submitted to the SUPERVISOR

    3.4.3.11 Alteration number

    3.4.3.12 Drawing and piece number

    3.4.3.13 Manufacturer

    3.4.3.14 Manufacturer's part number

    3.4.3.15 Date received

    3.4.3.16 Work Item number

    3.4.4 Purchase Orders

    3.4.4.1 Maintain a file of purchase orders for CFM for review

    by the SUPERVISOR upon request.

    3.4.4.2 Submit one legible copy, in approved transferrable

    media, of selected purchase orders to the SUPERVISOR upon request.

  • 5 of 9 ITEM NO: 009-01

    FY-19

    3.5 When a Work Item references Class and Hull specific configuration and

    Ship Alteration information, planning activity shall validate that reference

    information (Ship Alteration drawings, LARS, "as built drawings", Test

    Procedures, etc.) used is correct via the assigned Class Planning Yard.

    3.6 Procure Military Specifications and Standards and Commercial

    Specifications and Standards.

    3.6.1 Procure unclassified NAVSEA Standard Plans, Military

    Specifications and Standards, and Commercial Specifications and Standards

    referenced in the Work Items.

    3.6.2 Classified Military Specifications are available at the office

    of the SUPERVISOR.

    3.6.3 Work Items will normally reference the basic Government

    Specifications, Standards, or NAVSEA Standard Plans, without suffix letters or

    numbers which identify revisions or amendments. Unless otherwise specified,

    the effective issue of these basic referenced documents, including revisions

    or amendments, shall be the most recent issue at the date of solicitation for

    a Job Order. Wherever specific dates for specifications, standards, and

    publications or amendments, revisions, or alterations thereto are specified in

    the Work Items, issues of those dates specifically shall apply in lieu of any

    other issue. Where industry standards such as ASTM and ANSI are referenced,

    the issue or revision in effect on the date specified for Government

    publication applies.

    3.7 Work Items may reference specific revision levels of equipment

    technical manuals or drawings which are not NAVSEA Standard Plans. When these

    references are listed in a Work Item without suffix letters or numbers which

    identify revisions, change notices, or amendments, unless otherwise specified,

    the effective issue of technical manuals, including revisions, change notices,

    or amendments, shall be the most recent issue at the date of solicitation for

    the Job Order.

    3.8 Submit requests for deviations to the SUPERVISOR.

    3.8.1 A deviation is defined as any action which is not in

    conformance with the Work Item requirements, including references thereto, no

    matter how minor.

    3.8.2 Deviations from Work Items and references thereto will not be

    considered by the SUPERVISOR without a written request from the contractor.

    3.8.3 Submit one legible copy, in approved transferrable media, of

    requests for deviations to the SUPERVISOR within one day of identifying the

    deviation.

    3.8.4 For technical deviations from the references of any Work Item,

    include the following minimum information:

  • 6 of 9 ITEM NO: 009-01

    FY-19

    3.8.4.1 Ship name

    3.8.4.2 Hull number

    3.8.4.3 Contractor/Subcontractor

    3.8.4.4 Name of deviation requestor

    3.8.4.5 Identification as an existing condition or result of

    repair

    3.8.4.6 Duration of repair with and without the deviation

    3.8.4.7 System, component as indicated in the applicable

    selected record drawing

    3.8.4.8 Location by compartment, frame and deck

    3.8.4.9 Description of the deviation and degree of non-

    compliance

    3.8.4.10 Document deviated from

    3.8.4.11 Technical justification for the deviation

    3.8.4.12 Alteration number if applicable

    3.8.4.13 Proposed resolution

    3.8.4.14 Date SUPERVISOR response is needed by

    3.8.5 The Government does not have an obligation to approve any

    deviation; it may elect to do so if benefit to the Government can be shown.

    Accomplish deviation only when authorized in writing by the SUPERVISOR.

    3.9 Submit documents (including procedures, required reports, plans,

    forms) requiring SUPERVISOR review, approval, acceptance or direction via an

    NMD Contractor Furnished Report (CFR) unless otherwise directed by the

    SUPERVISOR.

    3.10 Accomplish the requirements of the contract.

    3.11 Comply with security requirements.

    3.11.1 In the event that the work required by the Job Order requires

    access to spaces or equipment that are classified, or use of technical

    manuals, references, or drawings that are classified, the specific security

    clearance requirements will be identified in the individual Work Item in

    addition to the requirements provided in the Invitation for Bid/Request for

    Proposal (IFB/RFP) by the Contract Security Classification Specification (DD

    Form 254).

  • 7 of 9 ITEM NO: 009-01

    FY-19

    3.11.2 Verify that personnel, including subcontractor's personnel,

    are cleared for the required level of security classification for handling,

    repair, installation, and testing of classified equipment and for access to

    areas of the ship which require a specific security clearance.

    3.11.2.1 After selection of a subcontractor, prepare in

    triplicate a DD Form 254 for the subcontract and request the official

    designated in Paragraph 14.b of the DD Form 254 for the prime contract to

    approve and sign the DD Form 254 for the subcontract and to make the required

    distribution. In preparing the DD Form 254 for subcontracts, extract

    pertinent data from the DD Form 254 pertaining to the prime contract.

    3.11.2.2 Prior to starting work on a Work Item that requires a

    security clearance, submit a list in triplicate of the names, badge numbers or

    other identification numbers, and security clearances of contractor and

    subcontractor personnel who will require access to classified information or

    areas in order to accomplish the work.

    3.11.3 Verify that classified equipment removed from ship and

    classified documents, such as drawings, technical manuals, and test

    specifications, are marked or tagged and safeguarded at all times in

    accordance with the National Industrial Security Program Operating Manual (DOD

    5220.22-M).

    3.12 Comply with applicable federal, state, and local laws, codes,

    ordinances, and regulations in their entirety. Any reference to a specific

    portion of a federal, state, or local law, code, ordinance, or regulation in

    this or any other item shall not be construed to mean that relief is provided

    from any other sections of the law, code, ordinance, or regulation.

    3.12.1 Provide appropriate notification to regional United States

    Environmental Protection Agency (EPA) in accordance with the requirements of

    2.2. Also, comply with notification requirements of state and local air

    pollution control laws.

    3.12.2 Submit one legible copy, in approved transferrable media, of

    notification required in 3.12.1 that has been provided to any regulatory

    authority for work on board the vessel to the SUPERVISOR within 2 days of

    providing such notice to the regulatory authority.

    3.13 Maintain a current copy at the job site of the Safety Data Sheet

    (SDS) for each hazardous material that will be utilized aboard the ship and/or

    in a Navy facility during the performance of this Job Order. Submit one

    legible copy, in hard copy or approved transferrable media, to the SUPERVISOR

    upon request.

    3.13.1 Each SDS requires a one-time submittal/acceptance unless the

    SDS changes or this NAVSEA Standard Item and/or references change.

  • 8 of 9 ITEM NO: 009-01

    FY-19

    3.14 Comply with applicable federal, state, local, and foreign contractor

    host country requirements when using Nuclear Regulatory Commission (NRC)

    licensed radioactive material, Agreement State licensed radioactive material,

    and/or machine sources of ionizing radiation on Government property.

    3.14.1 Do not commence operations using radioactive material or

    machine sources of ionizing radiation on Government property until authorized

    in writing by the SUPERVISOR.

    3.14.2 Contract personnel shall not be used as operators under a Navy

    Radioactive Material Permit (NRMP) issued to a naval facility. Navy personnel

    shall not be used as operators under a Nuclear Regulatory Commission (NRC) or

    Agreement State License issued to a contractor.

    3.14.3 Submit one legible copy, in approved transferrable media, of a

    consolidated inventory of all ionizing radiation producing machines or

    material that will be utilized aboard the ship and/or naval facility during

    the performance of this Job Order to the SUPERVISOR, 5 days prior to the start

    of work.

    3.14.4 Submit one legible copy, in approved transferrable media, of

    the applicable NRC or Agreement State License including procedures regarding

    system process and operation for use of licensed radioactive material, to the

    SUPERVISOR 5 days prior to the start of work. Agreement State licensees shall

    provide evidence of NRC Form 241 (Report of Proposed Activities in a Non-

    Agreement State) with the copy of the license for Agreement State licensees.

    3.14.5 Submit one legible copy, in approved transferrable media, of

    the applicable State license, authorization, or registration for machines that

    produce ionizing radiation, to the SUPERVISOR 5 days prior to the start of

    work.

    3.14.6 Submit one legible copy, in approved transferrable media, of a

    formal Radiological Safety Plan which shall include operating and emergency

    procedures pertinent to the items listed in 3.14.3, and actions to control

    jobsite-boundary radiation exposures below those allowed for members of the

    general public under NRC and OSHA standards, to the SUPERVISOR 5 days prior to

    the start of work.

    3.14.7 Provide the SUPERVISOR with remedies to any radiation safety

    shortcomings identified by the SUPERVISOR, to be rectified prior to commencing

    operations.

    3.15 Correct errors in record keeping by drawing a single line through the

    error, recording the correct entry, initialing, dating, and printing the name

    of the person making the correction.

    3.15.1 Corrections to records shall be made by the individual that

    made the original entry and/or signed for the accuracy and validity of the

    record. If the individual is no longer in the contractor employ or not readily

  • 9 of 9 ITEM NO: 009-01

    FY-19

    available at the time of correction the cognizant trade supervisor or

    cognizant project superintendent shall make the correction.

    3.15.1.1 Submit corrected report to SUPERVISOR.

    3.16 Record and Certification Signature Block or signature shall be

    legible and in ink. Erasures, write-overs, white-outs, ditto marks,

    continuation arrows, signature stamps, etc., are not acceptable.

    3.16.1 Copying records to "make them neat" is not allowed.

    3.16.2 Electronic records shall utilize electronic signature controls

    for certification of individual providing signature.

    3.17 Do not commence operations that could compromise watertight integrity

    during waterborne availabilities until confirmation by the SUPERVISOR that the

    ship has at least one back-up power source immediately available for providing

    power of minimum load to support firefighting and dewatering equipment in the

    event of loss of shore power.

    3.18 Protect the ship and its equipment from damage.

    4. NOTES:

    4.1 The term "day" means 24 hours prior to or after the scheduled event.

    “Business day” is used to indicate Monday through Friday, otherwise “day”

    means calendar day (Sunday through Saturday).

    4.2 Known sources for unclassified military specifications and standards

    are:

    https://mercury.tdmis.navy.mil

    https://assist.dla.mil

    http://quicksearch.dla.mil

    4.3 The term “SUPERVISOR” is defined as the local Government activity

    responsible for the execution and contract administration of Navy maintenance

    and modernization work.

    4.4 The term "Job Order" is synonymous with the term "Contract" and “Task

    Order”.

    4.5 The term “approved transferrable media” is the form, system or

    program for submitting reports required as agreed to by the SUPERVISOR.

    4.6 The term “subcontract” means any contract as defined in the FAR,

    Subpart 2.1, entered into by a subcontractor to furnish supplies or services

    for performance of a prime contract or a subcontract. It includes but is not

    limited to purchase orders, and changes and modifications to purchase orders.

    https://mercury.tdmis.navy.mil/https://assist.dla.mil/http://quicksearch.dla.mil/

  • 1 of 3 ITEM NO: 009-02

    FY-19

    NAVSEA

    STANDARD ITEM

    FY-19

    ITEM NO: 009-02

    DATE: 18 NOV 2016

    CATEGORY: I

    1. SCOPE:

    1.1 Title: Environmental Compliance Report for Material Usage at Naval

    Facility; accomplish

    2. REFERENCES:

    2.1 42 USC 7412(b), Clean Air Act, Section 112(b), List of Hazardous Air

    Pollutants

    3. REQUIREMENTS:

    3.1 Submit one legible copy, in approved transferrable media, of an

    Environmental Compliance Report for Material usage at Naval Facility as

    follows:

    3.1.1 Submit applicable permits for portable, registered, or rental

    emission units to the SUPERVISOR prior to start of work.

    3.1.2 Establish a record-keeping program to reflect the manner in

    which the material records will be maintained and submitted to the

    SUPERVISOR.

    3.1.3 Maintain facility specific records to ensure accurate

    reporting for all preservation, welding repairs, and fuel consumption for

    each individual portable internal combustion engine or portable emission

    unit. Provide the SUPERVISOR sufficient details to track usage of all

    paints, solvents, adhesives, welding rods, and fuel used for each individual

    portable internal combustion engine over 50-brake horsepower. Report any

    other materials used which contain chemicals listed in 2.1.

    3.1.4 Maintain current usage records of materials listed in 2.1.

    3.1.5 Negative reports are required.

    3.1.6 Reports shall contain the following items based upon category

    of the material.

    3.1.7 Paint, solvent, adhesive, and nonskid usage records are to be

    submitted monthly and shall include the following:

  • 2 of 3 ITEM NO: 009-02

    FY-19

    3.1.7.1 Product manufacturer, identification or color

    3.1.7.2 Net daily paint usage in gallons, paint application

    method (airless spray, HVLP, brush, or roller) per paint type, amount of

    paint disposed as hazardous waste; density of mixed paint; net daily onsite

    solvent usage in gallons used for equipment cleaning and surface preparation;

    net amount of adhesives in unit of measure (ounces, quart, gallons or pound)

    3.1.7.3 Product Safety Data Sheet (SDS), technical data

    sheet, VOC certification for paint and nonskid product

    3.1.7.4 Government site location, applicable local Air

    Pollution Control District (APCD) permit number, date, and ship's name

    3.1.8 Abrasive blast grit materials used shall be submitted monthly

    and shall include:

    3.1.8.1 Manufacturer of abrasive blast grit and SDS

    3.1.8.2 Abrasive blast grit usage certification if required

    by the cognizant state or local authorities

    3.1.8.3 Amount and hourly usage of the abrasive blast grit

    3.1.8.4 Permit associated with the abrasive blasting

    equipment if required by the cognizant state or local authorities

    3.1.9 Welding operation report shall be submitted monthly and shall

    include welding rod manufacturer, specific product used in welding

    application, SDS, usage in pounds, and type of welding application.

    3.1.10 Portable internal combustion (IC) engine greater than 50

    brake horse power operation report shall be submitted monthly and shall

    include:

    3.1.10.1 Amount of fuel used in gallons and the hours of

    operation

    3.1.10.2 IC engine permit number and site location if

    required by the cognizant state or local authorities

    3.2 Submit one legible copy, in approved transferrable media, of each

    report required by 3.1 to the SUPERVISOR no later than 10 days after the end

    of the month throughout the availability.

    4. NOTES:

    4.1 Examples of paint and nonskid manufacturers may be Ameron,

    International, American Safety Technology, or others as applicable.

  • 3 of 3 ITEM NO: 009-02

    FY-19

    4.2 Examples of American Welding Society Classifications for welding rod

    may be E316-16, E7018-AL 308-16, or others. If there is no American Welding

    Society (AWS) classification assigned, use the product name and circle the

    product on the SDS.

    4.3 Examples of welding applications may be Shielded Metal Arc Weld

    (SMAW), Gas Metal Arc Weld (GMAW), Flux Core Arc Weld (FCAW), and others.

  • 1 of 3 ITEM NO: 009-03

    FY-19

    NAVSEA

    STANDARD ITEM

    FY-19

    ITEM NO: 009-03

    DATE: 01 OCT 2017

    CATEGORY: I

    1. SCOPE:

    1.1 Title: Toxic and Hazardous Substance; control

    2. REFERENCES:

    2.1 29 CFR Part 1915, Occupational Safety and Health Standards for

    Shipyard Employment

    3. REQUIREMENTS:

    3.1 Identify materials that may contain toxic or hazardous substances as

    listed in Subpart Z of 2.1 that are to be used, removed, or disturbed during

    work operations.

    3.1.1 Conduct and document an initial determination of potential

    personnel exposure to these materials prior to the start of work.

    3.1.1.1 Provide a copy of the documentation, signed by a

    competent person as defined in 29 CFR 1915.4, to the SUPERVISOR upon request.

    3.2 Ensure that work operations comply with the requirements of 2.1 for

    the use of toxic or hazardous substances and removal or disruption of

    existing toxic or hazardous substances.

    3.3 Ensure that processes or procedures for work operations that can

    expose personnel to toxic or hazardous substances comply with the

    requirements of 2.1. At a minimum, address the following: exposure

    monitoring, method of compliance, engineering and work practice

    controls, respiratory protection, protective clothing, housekeeping, hygiene

    facilities and practices, medical surveillance, employee information and

    training, signs, and recordkeeping.

    3.3.1 Submit one legible copy of process(es) or procedure(s), in

    approved transferrable media, when requested by the SUPERVISOR.

    3.4 Provide a notice to the SUPERVISOR and to the Commanding Officer's

    designated representative at least 4 hours, but not more than 24 hours prior

    to commencement of any work operation that requires establishment of a

    regulated area in accordance with the requirements of 2.1 (i.e. cleaning of

  • 2 of 3 ITEM NO: 009-03

    FY-19

    spaces that have contained flammable or combustible liquids, lead work,

    cadmium work, asbestos work, etc.)

    3.4.1 Post the notice at the ship's Quarterdeck and at all entrances

    to spaces where work operations will be performed that require posting of

    warning signs, signs, or establishment of a regulated area.

    3.4.2 The notice shall contain the following information:

    3.4.2.1 Ship's name and hull number

    3.4.2.2 Work Item number

    3.4.2.3 Compartment or frame number

    3.4.2.4 Identification of hazard

    3.4.2.5 Date and time of work process

    3.4.2.6 Identification of engineering and work practice

    controls

    3.4.3 Deliver notification of work planned over a weekend or Monday

    following that weekend to the Commanding Officer's designated representative

    not later than 0900 on the Friday immediately preceding that weekend.

    3.4.4 Deliver notification of work planned on a Federal holiday and

    on the day following the Federal holiday to the Commanding Officer's

    designated representative not later than 0900 on the last working day

    preceding the Federal holiday.

    3.5 Provide for isolation and blanking of ship's ventilation systems in

    work areas to prevent toxic or hazardous substance contamination of

    ventilation systems or other compartments/spaces.

    3.6 Establish regulated areas for monitoring and authorized personnel

    entry whenever concentrations of the toxic or hazardous substance are in

    excess of exposure limits as listed in 2.1.

    3.7 Monitor the affected areas during work operations to ensure

    compliance with 2.1. Monitoring shall include adjacent spaces to ensure the

    work area containments and work practices are effective. Results of

    surveillance shall be documented and documentation shall be made available to

    the SUPERVISOR.

    4. NOTES:

    4.1 The term "hazardous substance" means a substance, which by reason of

    being explosive, flammable, poisonous, corrosive, oxidizing, irritant, or

    otherwise harmful is likely to cause injury.

  • 3 of 3 ITEM NO: 009-03

    FY-19

    4.2 Consider ventilation cleaning debris to contain toxic or hazardous

    substances.

  • 1 of 11 ITEM NO: 009-04

    FY-19

    NAVSEA

    STANDARD ITEM

    FY-19

    ITEM NO: 009-04

    DATE: 01 OCT 2017

    CATEGORY: I

    1. SCOPE:

    1.1 Title: Quality Management System; provide

    2. REFERENCES:

    2.1 Standard Items

    2.2 ANSI/ISO/ASQ Q9001-2015, Quality Management Systems – Requirements

    2.3 ANSI/NCSL Z540-3, Requirements for the Calibration of Measuring and

    Test Equipment

    2.4 ISO/IEC 17025, General Requirements for the Competence of Testing

    and Calibration Laboratories

    2.5 NAVSEA 04-4734, Navy and Marine Corps Calibration Laboratory

    Audit/Certification Manual

    2.6 SSPC QP1 Application, Instructions, and Program Rules

    2.7 NAVSEA OD 45845, Metrology Requirements List (METRL)

    3. REQUIREMENTS:

    3.1 Establish, document, implement, and maintain a Quality Management

    System (QMS) as a means of ensuring that product conforms to specified

    requirements.

    3.2 A written QMS Manual addressing all elements of 2.2 and

    supporting documented procedures shall be submitted to the SUPERVISOR for

    review and acceptance. Subsequent to SUPERVISOR acceptance, the written

    QMS Manual is acceptable in each geographic location in which the

    contractor maintains the same QMS. The contractor shall have an accepted

    QMS, in accordance with this Standard Item, in place to receive an award of

    a Job Order. Include the following documented procedures:

    3.2.1 Support: Address all areas of Paragraphs 7.1.5, 7.2 and 7.5

    of 2.2.

  • 2 of 11 ITEM NO: 009-04

    FY-19

    3.2.1.1 Calibration laboratories shall be accredited to

    either 2.3 or 2.4 by a Commercial Accreditation Activity, or certified by a

    Navy Certification Activity to 2.5, and the scope of accreditation must

    cover the appropriate measurement parameters and ranges of the calibrations

    performed.

    3.2.1.2 Calibration intervals assigned to Measuring and

    Test Equipment used by the contractor for acceptance testing shall meet

    those recommended in 2.7 unless alternate calibration intervals are

    established in accordance with 2.3.

    3.2.2 Operation: Address all areas of Paragraphs 8.2, 8.4, 8.5,

    8.6, 8.7 of 2.2

    3.2.2.1 Verification of Purchased Product: Identify, in

    the purchasing documents, verification arrangements at the subcontractor or

    vendor location/premises. Purchasing documents shall contain the following

    statement when the SUPERVISOR requests government inspection: "Government

    Inspection is required prior to shipment from your plant. Upon receipt of

    this order, promptly notify and furnish a copy to the Government

    representative who normally services your plant so that appropriate

    planning for government inspection can be accomplished. In the event the

    government representative or office cannot be located, our purchasing agent

    shall be notified immediately.

    3.2.2.2 Unless otherwise specified in a higher tier

    document, Receipt Inspection of contractor furnished materials shall be

    based on supplier performance history and one or more of the following:

    certificate of compliance, vendor material test certification data,

    manufacturer's mill certificate, or testing using sampling techniques.

    3.2.3 Performance evaluation: Address all areas of Paragraphs 9.2

    and 9.3 of 2.2

    3.2.4 Improvement: Address all areas of Paragraph 10.2 of 2.2.

    3.2.5 The documented QMS shall include a matrix listing the

    correlation between 2.2, 3.2 and the submitted documents.

    3.3 The QMS shall be subject to audits by the SUPERVISOR throughout the

    contract. Retain documented information to demonstrate the processes are

    carried out as planned.

    3.4 Submit one legible copy, in hard copy or approved transferrable

    media, of any revisions to the accepted QMS identified in 3.2 to the

    SUPERVISOR within 7 days of contractor approval.

    3.5 Submittal of procedures and Process Control Procedures (009-09 of

    2.1) invoked by NAVSEA Standard Items, MIL-STDs, drawings, technical

    publications, and specifications, although an integral part of the QMS, shall

    be submitted to and approved by the SUPERVISOR independent of the QMS a

  • 3 of 11 ITEM NO: 009-04

    FY-19

    minimum of 14 days prior to start of required process for planned

    availabilities, or as otherwise approved by SUPERVISOR.

    3.6 The corrective action program shall require that a copy of the

    written responses to contractor generated corrective actions will be provided

    to the SUPERVISOR when requested.

    3.7 Respond in writing to each SUPERVISOR issued Method B/C/D Corrective

    Action (CA) within 3 business days unless otherwise specified by the

    SUPERVISOR. Initial response shall include immediate corrective action taken

    and a plan of action for CA completion. Final response shall include

    preventive action for recurrence of identified nonconformance, root cause

    analysis and Objective Quality Evidence (OQE) for corrective action

    completed. All follow up responses shall be as specified by the SUPERVISOR.

    3.7.1 Inform the SUPERVISOR when corrective actions are complete for

    each SUPERVISOR issued Method A Corrective Action (CA). Response required

    within 72 hours unless otherwise specified by the SUPERVISOR. Response shall

    state that the non-conformance has been corrected.

    3.7.2 Use NMD, or approved Web interface, to perform all CAR

    functions for contracts managed in NMD.

    3.8 Attend fact-finding/investigative meetings when requested by the

    SUPERVISOR. (See 4.4)

    3.9 Develop a Test and Inspection Plan (TIP) incorporating each Work

    Item in the job order, LOA Chits or Statements of Work (SOW). The initial

    TIP shall include all inspections and tests required by zero-tier references

    and first tier references, as well as symbols (I)(V)(Q) test/inspections and

    (G) government notification identified in the Work Item, and any additional

    tests and inspections the contractor deems necessary to substantiate product

    conformance.

    3.9.1 Submit one legible copy, in hard copy or approved

    transferrable media, of initial copy of the TIP to the SUPERVISOR prior to

    start of productive work for non-CNO availabilities and no later than 5

    days prior to the availability start date for CNO availabilities.

    3.9.1.1 Submit one legible copy, in hard copy or approved

    transferrable media that can be sorted (e.g., Excel spreadsheet) of an

    updated TIP when requested by the SUPERVISOR.

    3.9.2 A TIP shall:

    3.9.2.1 Be revised prior to the start of productive work and

    updated as work proceeds on each Work Item. It shall be available upon

    request by the SUPERVISOR. Supporting data for tests and inspections

    requiring government notification (G), including accept/reject criteria,

    shall be available at the location of each test and inspection. Include

  • 4 of 11 ITEM NO: 009-04

    FY-19

    provisions for documenting the date, time, and identification of the

    SUPERVISOR's representative notified and government representative attending

    each (G)-Point on the TIP. The TIP shall annotate the relationship to a

    specific key event. The following key events shall be considered at a

    minimum (as applicable): Undocking, Production Completion Date (PCD),

    Command, Control, Communications, Computer, Combat Systems, and Intelligence

    (C5I) Light-Off (C5ILO), Dock Trials (DT), Fast Cruise (FC), Sea Trials (ST),

    and Availability Completion (AC).

    3.9.2.2 Each test and inspection shall be identified by its

    respective Work Item number and Work Item paragraph number, including

    Standard Item paragraph number, and shall include inspection symbols (I)(Q)

    and (V), and the government notification (G) Point symbol where applicable.

    3.9.2.3 Provide identification of the item to be inspected by

    name, number, and location (e.g., number 3 main feed pump, 5-180-0-E).

    3.9.2.4 Provide identification of each characteristic of the

    items to be inspected and provide the criterion for acceptance for each

    characteristic (e.g., air test; 2 PSIG for 10 minutes; no drop).

    3.10 Test and Inspection records shall:

    3.10.1 Include the ship's name and hull number, Job Order and Work

    Item number, applicable PCP number, paragraph number, component

    identification, accept/reject criteria, date, time, and signature of the

    contractor's authorized representative who witnessed or performed the test or

    inspection. The signature occurs after the checkpoint is determined to be

    satisfactory or unsatisfactory and any exceptions are documented.

    3.10.2 Be maintained at a contractor location accessible to the site

    of the work required by the Job Order.

    3.10.3 Be documented within one day of accomplishment or prior to the

    subsequent tests or inspections, whichever is less. The records shall

    indicate the results of the test and or inspection accomplished. Records

    shall be incorporated into the TIP within 4 days after completion of each

    test or inspection.

    3.10.3.1 For tests and inspections involving (G)-points,

    records shall be documented upon acceptance or rejection and a hard copy (or

    electronic copy as authorized by the SUPERVISOR) provided to the SUPERVISOR

    at the conclusion of each (G)-Point. For tests and inspections utilizing

    Coating QA Tool Kit (CQATK) paperless QA program in accordance with 009-32 of

    2.1, the data must be downloaded into the computer at the time and location

    of inspection. (See 4.5)

    3.10.4 Required reports resulting from tests or inspections shall

    include the appropriate design criterion for each attribute or measurement

    required by the Work Item.

  • 5 of 11 ITEM NO: 009-04

    FY-19

    3.11 The SUPERVISOR will consider the Work Item incomplete if the

    contractor's documentation and records are not complete.

    3.12 Accomplish (I), (V) and (Q) tests/inspections that do not have

    associated (G)-points, with qualified and/or currently certified personnel

    where required by the technical documents (e.g., NBPI, NACE, nondestructive

    testing, electrical cableway inspection, etc.) as follows:

    3.12.1 (I) inspections require verification and documentation by a

    separate individual, other than the person who has accomplished the work, who

    is qualified as an inspector.

    3.12.2 (V) inspections require verification and documentation by the

    qualified tradesperson, trade supervisor, or inspector.

    3.12.3 (Q) inspections require verification and documentation by a

    qualified Technical Representative in accordance with 009-90 of 2.1 and

    associated PCP requirements.

    3.12.4 The authority to accomplish, document, accept and reject (I)

    and (V) inspections may be delegated to qualified subcontractor personnel,

    without regards to geographical location, subject to SUPERVISOR approval.

    3.13 Accomplish (G)-Point (government notification) as follows:

    3.13.1 (G) is a symbol inserted in a Work Item to establish a point

    in the sequence of accomplishment of work at which time the SUPERVISOR shall

    be notified by the prime contractor in all cases to permit observation of a

    specific test or inspection (I)(V) by the government. When the symbol (G)

    precedes tests or inspections in a Work Item which are applicable to more

    than one action, the symbol (G) shall identify the action required, e.g., (G)

    "HYDROSTATIC TEST". When more than one unit is involved, the (G)

    notification requirement applies to each unit. Pre-inspection by the

    contractor prior to a (G)–Point is neither required nor desired.

    3.13.2 Notify the SUPERVISOR's designated representative via FAX,

    hard copy, or by electronic method, as directed by the SUPERVISOR.

    3.13.2.1 Notify the SUPERVISOR during normal day shift working

    hours, at least 4 hours, but not more than one day, prior to commencing the

    specific requirements in the paragraph annotated with the symbol (G). Notify

    the SUPERVISOR to cancel a scheduled test or inspection as soon as known, but

    no later than 30 minutes prior to the scheduled event.

    3.13.2.2 Notify the SUPERVISOR not later than 4 hours before

    the end of the last preceding day shift when tests or inspections following a

    (G) Point are scheduled after normal day shift working hours, on a weekend,

    or on a federal holiday.

  • 6 of 11 ITEM NO: 009-04

    FY-19

    3.13.2.3 Notify the SUPERVISOR at least 48 hours, but not more

    than 72 hours, prior to commencing (G)-Points at contractor's/subcontractor's

    plants located in excess of 50 miles by the most direct roadway nearest to

    the place of performance of the contract. Document the date, time, and

    identification of the SUPERVISOR's representative notified.

    3.13.2.4 For (G)-Points scheduled after normal day shift

    working hours, on a weekend, or a Federal holiday, notify the SUPERVISOR to

    cancel a scheduled test or inspection as soon as known, but no later than 2

    hours prior to the scheduled event.

    3.13.3 Proceed with the test or inspection if the SUPERVISOR is not

    present, provided the required advance notice has been furnished to the

    SUPERVISOR and the contractor has completed and documented the preceding

    tests and inspections.

    3.13.4 A partial test or inspection requiring (G) notification may be

    accomplished in the event that all work cannot be completed and work progress

    would be delayed in waiting for total completion of work. Comply with the

    requirements of 3.13.2 when the incomplete work is completed and ready for

    the remainder of the test or inspection. Note partial inspections on the

    test or inspection form.

    3.13.5 Invoke (G) notification requirements for tests or inspections

    involving a subcontractor in purchase orders such that the requirements of

    3.13.2 are met.

    3.13.6 A qualified contractor representative shall be present to

    accomplish, accept or reject and document tests or inspections associated

    with the symbol (G).

    3.13.6.1 The authority to witness or perform, document and

    accept/reject (I)(G), (Q)(G), and (V)(G) tests and inspections is a prime

    contractor's responsibility but, subject to SUPERVISOR approval within a 50-

    mile radius of the contractor’s plant nearest to the place of performance of

    the contract, may be delegated to subcontractors who are MSRA or ABR

    agreement holders, SSPC QP1 certified, NDT certified, or have a current QMS

    accepted by the SUPERVISOR.

    3.13.6.2 The contractor may delegate responsibility to

    subcontractors to perform, document and accept/reject (I)(G) and (V)(G) tests

    and inspections performed at plants located outside a 50-mile radius of the

    contractor's plant nearest to the place of performance of the contract

    subject to SUPERVISOR prior approval.

    3.13.6.3 Associated (G)-Point notification requirements shall

    not be delegated.

    3.14 For work being performed outside a 50-mile radius of the place of

    contract performance, the prime contractor shall submit one legible copy, in

  • 7 of 11 ITEM NO: 009-04

    FY-19

    hard copy or approved transferrable media, of purchase orders to the

    SUPERVISOR within 2 days or otherwise as directed by the SUPERVISOR, prior to

    issue of purchase order and shipment of equipment. For contractors who do not

    utilize purchase orders as a vehicle for accomplishing work within their

    company, a report identifying the delineation of the specific Work Item

    requirements, in lieu of the purchase order shall be submitted to the

    SUPERVISOR.

    3.15 Maintain a current list for reference by the SUPERVISOR, designating

    the contractor's qualified and currently certified inspectors who witness or

    perform and sign for symbol (I) inspections, indicating the type of tests and

    inspections for which each inspector is qualified and currently certified.

    When subcontractors are delegated responsibility, the subcontractor's

    qualified and currently certified inspectors shall be included on this list.

    3.16 Submit one legible copy, in hard copy or approved transferrable

    media, of the most recent contractor's/subcontractor's SSPC QP-1 audit

    results to the SUPERVISOR, no later than 10 days after

    contractor's/subcontractor's receipt of the final audit report.

    3.17 Contractor/subcontractor shall notify the SUPERVISOR within one day

    when aware of any preliminary SSPC audit findings for critical audit items

    that result in a rating of one (1) (i.e., major CAR or deficiency) as

    referenced in 2.6. These notifications shall be submitted, as required, in

    addition to the final SSPC audit report.

    3.18 Certify to the SUPERVISOR that work is completed technically correct

    with all required OQE. All supporting documentation shall be submitted in

    support of the following Key Events: Undocking (if applicable), PCD, C5ILO,

    |DT, FC, ST, and CA.

    3.18.1 As required by 009-60 of 2.1, each Work Item to be

    accomplished during the availability shall be evaluated and properly tied to

    the appropriate Key Event in a predecessor/successor methodology and

    documented in the Integrated Production Schedule (IPS) and tracked via the

    Event Readiness List. Key Event ties shall also be annotated for each item

    in the TIP as required by 3.9.2.1.

    3.18.2 Notify the SUPERVISOR of the condition and status of each

    individual Work Item in the availability within 3 days of Work Item

    completion or a minimum of 5 days prior to the scheduled Key Event to which

    that item is tied, whichever occurs first, by either of the following

    methods:

    3.18.2.1 Completion and submission of one legible copy of

    Attachment A, in hard copy or approved transferrable media. Submission

    of Event Readiness List (ERL) may substitute for Attachment A when authorized

    by the SUPERVISOR.

    3.18.2.2 Signature on a centralized signature sheet or record

    book maintained by the SUPERVISOR if Work Item is complete. If work is

    incomplete or complete with discrepancies, supporting rationale and impact

  • 8 of 11 ITEM NO: 009-04

    FY-19

    statement with recovery plan shall be provided to the SUPERVISOR via

    submission of one legible copy of Attachment A, in hard copy or approved

    transferrable media. Upon completion of work or correction of discrepancies,

    a revised Attachment A with the updated status shall be submitted to the

    SUPERVISOR in hard copy or approved transferrable media.

    4. NOTES:

    4.1 ANSI/ISO/ASQ Q9001:2015 commercial third party registrar certification

    is not required.

    4.2 The QMS submitted in 3.2 requires a one-time submittal/acceptance unless this NAVSEA Standard Item and/or references change or contractor's

    status changes.

    4.3 A "zero-tier reference" is a specification, standard, drawing, test

    memo, planning/design memo that is cited in the contract (including its

    attachments). A "first-tier reference" is either: (1) a specification,

    standard, or drawing cited in a zero-tier reference, or (2) a specification

    cited in a first tier drawing. All zero-tier and first tier references are

    mandatory for use. All lower tier references shall be used for guidance

    only.

    4.4 Contractor-run critiques or fact findings are accomplished in

    accordance with 009-120 of 2.1.

    4.5 A partial (G)-point may be accomplished for a fraction of the work

    specification components. When elected, the contractor is responsible to

    account for the inspection status of each component. A final (G)-point is

    required for the last remaining component(s).

    4.6 ISO compliant Quality Management Systems typically follow a 4-tiered

    hierarchy comprised of:

    a. The “first-tier” document related to the QMS is the Quality Manual,

    which is the high-level document that is authored and approved by

    upper management of the organization and is the guiding

    organizational document for which all subsequent tiers within the

    system should be aligned with.

    b. The “second-tier” documents are the Quality Procedures making up the

    center of the documentation system. These procedures span all the

    required processes and practices within the organization and should

    include references both upward to the Quality Manual and downward to

    the Work Instructions associated with each process.

    c. The “third-tier” documents are Work Instructions comprised of

    instructions that describe the specific actions required to achieve

    a quality product.

  • 9 of 11 ITEM NO: 009-04

    FY-19

    d. The “fourth-tier” documents are the Quality Records which capture

    all the data, information, records, forms and become the objective

    evidence which will prove the QMS is being executed per procedure.

    4.7 NAVSEA 04RM3 Approved list of Accrediting Bodies (AB).

    . ANSI-ASQ National Accreditation Board (ANAB), http://anab.org/

    . Laboratory Accreditation Bureau (L-A-B), http://l-a-b.com/

    . Perry Johnson Registrars (PJLA), http://www.pjr.com/

    . The American Association for Laboratory Accreditation (A2LA),

    https://www.a2la.org/

    . National Voluntary Laboratory Accreditation Program (NVLAP),

    https://www.nist.gov/nvlap

    . International Accreditation Service (IAS), http://www.iasonline.org

    Contact NAVSEA 04RM3 for information on commercial accreditation in

    accordance with 2.3 and 2.4 by NAVSEA approved commercial Accrediting Bodies

    (AB).

  • 10 of 11 ITEM NO: 009-04

    FY-19

    Attachment A

    Work Completion Certification

    SHIP’S NAME : HULL NO.:

    WORK ITEM NO: SSP NO.:

    KEY EVENT:

    Undocking (UD)

    Production Completion Date (PCD)

    Dock Trials (DT)

    Fast Cruise (FC)

    Sea Trials (ST)

    Availability Completion (AC)

    Command, Control, Communications, Computer, Combat

    Systems, and Intelligence Light-Off (C5ILO)

    Other ______________________

    1) All contracted production work (original, new and growth) has been

    satisfactorily reviewed, accurate and complete. All non-conformances have

    been corrected and corrective action request (CAR) are at an acceptable level

    of completion.

    RESULTS/STATUS:

    Complete

    Complete w/ Discrepancies

    Incomplete

    Note: If work is incomplete or complete with discrepancies, supporting

    rational and impact statement with recovery plan in the Comments block below.

    Comments:

    Print and Sign

    Name: Date:

    Position and

    Responsibility:

    2) All Tests and Inspections have been completed satisfactorily reviewed,

    accurate, complete and properly documented in the T&I Plan.

  • 11 of 11 ITEM NO: 009-04

    FY-19

    RESULTS/STATUS:

    Complete

    Complete w/ Discrepancies

    Incomplete

    Note: If work is incomplete or complete with discrepancies, supporting

    rational and impact statement with recovery plan in the Comments block below.

    Comments:

    Print and Sign

    Name: Date:

    Position and

    Responsibility:

    3) All required reports and all accompanying required data have been

    submitted, reviewed, accurate, complete and satisfactory.

    RESULTS/STATUS:

    Complete

    Complete w/ Discrepancies

    Incomplete

    Note: If work is incomplete or complete with discrepancies, supporting

    rational and impact statement with recovery plan in the Comments block

    below.

    Comments:

    Print and Sign

    Name: Date:

    Position and

    Responsibility:

  • 1 of 5 ITEM NO: 009-05

    FY-19

    NAVSEA

    STANDARD ITEM

    FY-19

    ITEM NO: 009-05

    DATE: 18 NOV 2016

    CATEGORY: II

    1. SCOPE:

    1.1 Title: Temporary Access; accomplish

    2. REFERENCES:

    2.1 Standard Items

    2.2 MIL-STD-1689, Fabrication, Welding, and Inspection of Ships

    Structure

    2.3 29 CFR 1915, Occupational Safety and Health Standards for Shipyard

    Employment

    3. REQUIREMENTS:

    3.1 Submit one legible drawing or sketch of each proposed temporary

    access cut to the ship structure or engine enclosure and a list of each

    proposed bolted/riveted access removal to the SUPERVISOR 3 days prior to

    making the cuts or removing the bolted/riveted access. For a nuclear-powered

    vessel, submit drawing/sketch of each proposed temporary access cut to the

    SUPERVISOR 5 days prior to making cut or removing the bolted/riveted access.

    3.1.1 Submittal of drawing or sketch is not required for those

    access cuts authorized on a NAVSEA-approved drawing.

    3.1.2 The drawing or sketch shall include, as a minimum, the

    following information:

    3.1.2.1 A plan and elevation view specifying the location of

    the access by deck, frame, and distance from the center line or deck edge and

    showing location of adjacent penetrations, bulkheads, framing, welds, and

    riveted joints within 12 inches of the proposed cut.

    3.1.2.2 Location and number of previous cuts visible in each

    plate and the cutback of existing welds as required by 2.2.

    3.1.2.3 Temporary structural reinforcement required to

    prevent distortion of ship structure.

  • 2 of 5 ITEM NO: 009-05

    FY-19

    3.1.2.4 Thickness and type of material of plating and

    structural members to be cut. Include source or document/drawing number

    which identifies material requirements.

    3.1.2.5 A description of the temporary access closure or

    enclosure.

    3.1.2.6 Include a copy of the weld procedure or approved

    weld procedure number with the proposed access sketch.

    3.1.3 List of bolted/riveted access covers shall include location,

    designation, and classification as identified on ship's damage control book.

    3.1.4 Provide all drawing titles and numbers (including applicable

    sub-tier), and technical documentation used to accomplish the requirements of

    3.1.

    3.1.5 Temporary accesses include access plates, small access

    plates, and closure plates as defined in Paragraph 3.33 of 2.2.

    3.2 Ensure that access cut boundaries conform to the requirements of 2.2

    and the following:

    3.2.1 Boundaries may extend across one or more frames as required

    for size of opening.

    3.2.2 Are sized and located to accomplish the requirements of the

    Job Order.

    3.2.2.1 Verify access requirements on NAVSEA drawings

    conform to these same requirements.

    3.2.3 Weld riveted plates using a single V-weld with glass cloth

    conforming to MIL-C-24576, Type One, Class One, to prevent fusion between

    backing member and plate.

    3.2.3.1 Remove existing rivets within 6 inches of a cut and

    install new rivets in accordance with 2.2.

    3.2.3.2 Round patches 2 feet in diameter or less shall be

    dished 1/16-inch to 1/8-inch.

    3.2.4 Minimum width of small access plates shall be at least 4 times

    the material thickness of the plate being cut or 3 inches, whichever is

    greater.

    3.2.5 Corners of small access plates between 3 inches minimum to 6

    inches maximum in width shall have a radius of one-half the width. Exception

    to this corner radius criterion is where a boundary terminates on an existing

    hull longitudinal seam or transverse butt joint.

  • 3 of 5 ITEM NO: 009-05

    FY-19

    3.2.6 Corners of small access plates greater than 6 inches in width

    shall have a radius of 2 times the material thickness of the plate being cut

    or 3 inches, whichever is greater. Exception to this corner radius criterion

    is where a boundary terminates on an existing hull longitudinal seam or

    transverse butt joint.

    3.2.7 Corners of access plates shall have a minimum radius of 6

    inches. Exception to this corner radius criterion is where a boundary

    terminates on an existing hull longitudinal seam or transverse butt joint.

    3.2.8 Utilize the same boundaries as used for prior cuts unless the

    requirements of this Standard Item have been violated.

    3.2.8.1 Annotate violations on the drawing or sketch

    required by 3.1.

    (V)(G) "INSPECT LAY OUT"

    3.3 Lay out access on both sides of the structure to be cut, in

    accordance with the approved drawing or sketch.

    3.4 Prior to cutting access in the ship/vessel's structure and after

    layout checkpoint, accomplish positive verification by drilling a pilot hole

    in the path of the cut to be accomplished.

    3.5 Center punch access layout upon completion of verification in 3.4.

    3.6 Accomplish the requirements of 2.3 for guarding of access openings.

    3.6.1 Remove temporary guarding after installation of access

    plates. Chip and grind surfaces flush in way of removals.

    3.7 Install a temporary coaming with a minimum height of 4 inches around

    access cuts through decks. Tack-weld the coaming to the deck and seal the

    deck joint with caulking compound.

    3.7.1 Remove the temporary coaming after installation of access

    plate. Chip and grind surfaces flush in way of removals.

    3.8 Cut access in accordance with the approved drawing or sketch.

    3.9 Remove bolted/riveted access.

    3.9.1 Clean and preserve gasket faying surfaces.

    3.9.2 Chase and tap exposed threaded areas.

    3.10 Protect ship from weather and contamination.

  • 4 of 5 ITEM NO: 009-05

    FY-19

    3.10.1 Fabricate temporary closures using fire retardant material,

    prior to removing plates or cutting access openings.

    3.10.1.1 Closures shall be constructed to protect the access

    from inclement weather and entry of contaminants.

    3.10.1.2 Horizontal deck closures shall support a minimum of

    150 pounds per square foot.

    3.10.1.3 Closures shall be fitted with fasteners that permit

    rapid installation and removal.

    3.10.2 Install closures whenever access is not in use.

    3.11 Maintain watertight integrity of waterborne ship.

    3.11.1 Fabricate and install watertight enclosures prior to removing

    plates or cutting access openings that do not provide a minimum of 4 feet of

    freeboard.

    3.11.1.1 Maintain watertight integrity to a level 4 feet

    above the maximum calculated draft.

    3.12 Maintain watertight integrity of ship in dry dock.

    3.12.1 Provide temporary access closure plates and fasteners prior

    to removing plates or cutting access openings below 4 feet of waterborne

    freeboard.

    3.12.1.1 Closure plates shall be available on short notice

    for emergency sealing of the temporary access openings.

    3.12.2 Seal access openings with closure plates when conditions

    warrant.

    3.12.3 Secure openings at the end of each shift not immediately

    followed by another shift engaged in dry dock work.

    3.13 Remove the temporary closures when no longer required.

    3.14 Reinstall the temporary access removed in 3.8 in accordance with the

    approved drawing or sketch.

    3.14.1 Accomplishment of welding, fabrication, and inspection

    requirements to support installation of a temporary access shall be in

    accordance with NAVSEA Standard Items (See Note 4.2)

    3.14.2 Install the bolted/riveted access.

    3.14.2.1 Use new gasket material conforming to MIL-PRF-900.

  • 5 of 5 ITEM NO: 009-05

    FY-19

    3.14.2.2 Install new rivets for riveted access plates in

    accordance with 2.2.

    (V) "CHALK TEST"

    3.15 Accomplish a chalk test on structural closure in way of temporary

    access. Chalk imprint shall be centered with 100-percent contact.

    3.16 Accomplishment of structural boundary testing (e.g., cofferdam,

    vacuum box, air hose, water hose) of each watertight/airtight temporary

    access closure shall be in accordance with NAVSEA standard items (See Note

    4.3).

    4. NOTES:

    4.1 Maximum Calculated Draft (MCD) – The maximum draft, calculated

    during the period in which ship’s draft is affected due to evolutions which

    add, remove, or change weight. It represents the “worst case” cumulative

    effect at any one time on trim, list, or draft for the proposed weight

    changes throughout the period that hull penetrations are in a non-standard

    configuration. MCD shall be known and utilized by the SUPERVISOR and Ship’s

    Force in scheduling work and testing during waterborne maintenance periods.

    4.2 If welding, fabrication, or inspection for installation of a

    temporary access of 3.14.1 is required; the use of Category II Standard Item

    009-12 “Welding, Fabrication, and Inspection Requirements; accomplish” of 2.1

    will be specified in the Work Item.

    4.3 If a structural boundary test (e.g., cofferdam, vacuum box, air

    hose, water hose) to support testing of a watertight/airtight temporary

    access closure is required; the use of Category II Standard Item 009-25

    “Structural Boundary Test; accomplish” of 2.1 will be specified in the Work

    Item.

  • 1 of 5 ITEM NO: 009-06

    FY-19 CH-1

    NAVSEA

    STANDARD ITEM

    FY-19 CH-1

    ITEM NO: 009-06

    DATE: 06 MAR 2018

    CATEGORY: I

    1. SCOPE:

    1.1 Title: Maintaining Protection and Cleanliness from Non-Radioactive

    Operations; accomplish

    2. REFERENCES:

    2.1 Standard Items

    2.2 MIL-STD-1623, Fire Performance Requirements and Approved

    Specifications for Interior Finish Materials and Furnishings (Naval

    Shipboard Use)

    2.3 NFPA Standard 701, Standard Methods of Fire Tests for Flame

    Propagation of Textiles and Films

    3. REQUIREMENTS:

    3.1 Observe the following requirements, in addition to the specific

    requirements of the Job Order, for maintaining protection and cleanliness

    from non-radioactive operations on the ship, ship's equipment, components,

    and spaces for the duration of the availability.

    3.1.1 Accomplish an inspection of the work area prior to

    installation of protective covering to identify the current condition of

    equipment, systems, and components, including any exposed cables,

    penetrations, stuffing tubes, bolted cover plates, and antennas.

    3.1.1.1 Submit one legible copy, in hard copy or approved

    transferrable media, of a report listing results of the requirements of 3.1.1

    to the SUPERVISOR.

    3.2 Prevent contamination and damage of the ship's equipment,

    components, and spaces during contamination-producing operations.

    3.2.1 Plug, blank, wrap, cover, seal, and mask equipment,

    components, cables, wireways, boots, and openings using fire retardant/water

    repellent material, and prevent entry of contaminants to components, systems

    and equipment.

  • 2 of 5 ITEM NO: 009-06

    FY-19 CH-1

    3.2.1.1 Ensure plugging and blanking does not result in

    flooding or damage to ship's equipment.

    3.2.1.2 Install Herculite or canvas covering conforming to

    A-A-55308, and/or fire retardant plywood conforming to Category 2, Type II,

    of MIL-L-19140, or other NAVSEA-approved fire retardant industrial protective

    material.

    3.2.2 Install fire retardant industrial filter material meeting the

    minimum requirements of UL 900 Class 1, non-fire contributing material, on

    the intake of supply and exhaust end of ventilation systems that will be in

    use.

    3.2.2.1 Remove existing and install new filter or clean the

    filter material when air flow is restricted.

    (V) "VERIFY PROTECTIVE MEASURES"

    3.2.3 All protective measures are to be in place prior to start of

    any contamination-producing operations and shall remain in place until the

    contamination-producing operations are complete.

    3.2.4 Install double curtain baffles at the entrance of each access

    door where airborne contamination could occur during contamination-producing

    operations. Install a dirt collecting mat on the deck directly inside each

    door. The SUPERVISOR will select a maximum of 4 doors. Secure and mark

    doors not designated for access.

    3.2.5 Temporary coverings shall not be removed during

    contamination-producing operations without permission of the SUPERVISOR.

    (V) "INSPECT PROTECTIVE COVERING"

    3.3 Inspect the integrity of the protective covering at the beginning of

    each shift in which contamination-producing operations will be accomplished.

    Ensure that equipment and machinery have not been infiltrated by

    contaminants. Notify the SUPERVISOR immediately by verbal means, followed on

    the next day in writing, if contamination or surface damage has occurred.

    Reseal to prevent further entry of contaminants or surface damage.

    3.4 Maintain cleanliness of the work site, including bilges, free from

    accumulation of industrial debris caused by contractor and/or subcontractor

    employees on a continuous basis throughout the availability. Work spaces

    include those areas immediately under and adjacent, and those areas where

    service lines are run, and bilge areas in vicinity of the work site.

    3.4.1 Cleaning shall be accomplished no later than at the end of

    each shift at a minimum, on a daily basis.

    3.4.2 Remove and dispose of industrial debris from the ship at the

    end of each shift at a minimum, on a daily basis.

  • 3 of 5 ITEM NO: 009-06

    FY-19 CH-1

    3.4.3 Vacuum cleaners shall be emptied of all debris at the end of

    each shift at a minimum, on a daily basis.

    3.4.3.1 Use metal canister vacuum cleaners aboard the ship,

    except those used for regulated and controlled radiological and hazardous

    waste or hazardous material.

    3.4.3.2 Permanently and legibly mark each vacuum cleaner

    with a company name or unique identifier.

    3.4.4 Plastic trash cans are prohibited for trash collection

    onboard in spaces where industrial work is being performed. Plastic trash

    bags may be used onboard as a liner for metal trash cans.

    |

    (V)(G) "FINAL CONTAMINATION/DAMAGE INSPECTION"

    3.5 Remove protective covering installed in 3.2 upon completion of

    contamination-producing operations. Accomplish a final inspection of the

    work area to identify the presence of contamination and/or damage created by

    contamination-producing operations. Contamination/damage shall be documented

    on the inspection record.

    3.5.1 Presence of contamination and/or damage created by

    contamination-producing operations is unacceptable and shall be corrected.

    3.6 Remove from the ship and dispose of debris and foreign matter

    generated as a result of work being accomplished at the end of each shift at

    a minimum, on a daily basis. Comply with the requirements of federal, state,

    and local laws, codes, ordinances, and regulations or as specified elsewhere

    in the Job Order.

    3.7 Non-fabric material used onboard for containment or as protective

    coverings shall be in accordance with 2.2. Fabrics used onboard for

    containment or as protective coverings shall be tested in accordance with and

    meet the requirements of 2.3 or be listed as an acceptable "Drapery or

    Curtain" in 2.2.

    4. NOTES:

    4.1 Definitions:

    4.1.1 Cleanliness means the removal of all industrial debris

    (industrial trash, waste material, weld rods/tips, fasteners, rags, lagging

    waste, job scrap, wire, litter, rubbish, etc.) at the end of each shift,

    leaving the areas broom clean and electronic spaces vacuum clean.

    Adjacent/surrounding machinery, equipment, etc., shall be cleaned free of all

    resulting debris.

    4.1.2 Daily means at least once per every calendar day.

  • 4 of 5 ITEM NO: 009-06

    FY-19 CH-1

    4.1.3 Non-radioactive operations include but are not limited to:

    4.1.3.1 Operations liable to produce particulates to become

    airborne during accomplishment of the work scope, i.e., abrasive blasting,

    mechanical cleaning, spray painting, hot work operations, and air blowdowns.

    4.1.3.2 Operations liable to produce fluid contamination of

    equipment as a result of external leakage of piping systems during testing.

    4.1.3.3 Operations liable to produce fluid contamination of

    equipment as a result of external leakage of piping systems during

    waterjetting.

    4.1.3.4 Operations liable to produce industrial debris such

    as, but not limited to, industrial trash, waste material, weld rods/tips,

    fasteners, rags, lagging waste, job scrap, wire, litter, rubbish, etc.

    4.2 The SUPERVISOR will coordinate operation of ventilation systems, as

    requested by the contractor, to maintain a positive pressure within the

    vessel's envelope and to create an outward flow of air through crevices or

    around penetrations.

    4.3 The cleanliness goal is to turn over all areas of the ship in the

    same condition or better as at beginning of the availability.

    4.4 Ship's Force responsibility:

    4.4.1 Ship's Force is responsible for dust that collects as a

    matter of course throughout the availability and for any Ship's Force job

    site maintenance including monitoring job sites being worked by intermediate

    maintenance activities, Alteration Installation Teams (AIT), and any

    contractor services that the ship has arranged.

    4.4.2 Ship's Force is responsible to maintain cleanliness of their

    areas of responsibility broom clean at the end of each shift, on a daily

    basis.

    4.4.3 Ship's Force will report cleanliness concerns to the

    SUPERVISOR for contractor responsible areas.

    4.4.4 Ship's Force will work continually throughout the

    availability to keep bilges and other general areas of the ship clean where

    the Contractor is not working.

    4.5 Ship's Force and the Contractor will familiarize each other with

    their scope of work (any other work being performed on board the ship not

    pursuant to contractor authorized work under the Job Order is considered

    Ship's Force work). The affected locations and aspects of the work and/or

    ship co