Construction Timeline
2010 Football
Design Phase Review, Bid, Contract
& Order MaterialsConstruction Phase
Aug 2011Mar 2010 Jan 2011
2011 Football
Nov 2010
FF&E
/IT
Complete Design Nov 2010
Order Materials ahead of Construction
Start Construction following
2010 Season
Finish Construction ahead of
2011 Season