MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
CONTENTS
Status of NCRMP Year-1 works in Table-1 15
Spill over works statement for the Year-1 works in Table-2 16
Details of spill over works for the year-1 works in Table-3 17
A t i t d f NCRMP Y 2 k t t t i T bl 4 18
1.0 Project Background 2
2.0 Out Line of Tasks to be carried out 3
3.0 Findings of the Site Reports 4
3.0.1 Findings of Social and Environmental Engineers 6
3.1 Summary of Audit opinion 10
3.2 Corrective actions. 12
3.3 Progress of works with reference to milestones. 12
4.0 Activities of Third Party Quality Audit Consultant 14
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 3/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
1. Project Background
Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road
network in the state, the nine coastal districts cover 26,000 km of road length. Every year during the
period of April-May and September-December, cyclonic situations set in to the Bay of Bengal. With
the recent changes in climatic conditions, the catastrophic events are increasing resulting in very
devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from
1892 to 1989, there were as many as 67 cyclones within the State.
It is essential to provide safe residential accommodation to the vulnerable population during any
eventuality or disaster due to natural calamities such as cyclones and associated tidal waves and
storm surges. The project is formulated based on experiences of Government of Andhra Pradesh in
mitigating such disasters during the past and also keeping in view the existing facilities available in
the project area in Andhra Pradesh.
The Government of India has applied for a credit of US$ 255 Million equivalent from the
International Development Association (IDA) toward the cost of National Cyclone Risk Mitigation
Project (NCRMP), and it intends to apply the proceeds to payments for goods, works, related
services and consulting services under this Project.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 4/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
2. Outline of tasks to be carried outThe scopes of services for the Third Party Quality Audit (TPQA) assignment are
A. The consultant will prepare an inception report within 30 days from signing of the contract thatdetails the method agreed during negotiations to be employed in performing the services.
B. Assist SPIU in resolving issues related to Non compliances.
C. The field testing being conducted by the implementation staff will be observed and when doubtsarise in such observations another sample will be taken and will be tested independently to verifywhether it is as per the standards or not.
D. The consultant will review civil work components of the cyclone shelters and related roads & bridges of these buildings and compliances and non-compliances will be reported regularly to PIUand line department.
E. Consultants will visit the sites for each stage of work and audit
F. The consultant will visit the construction sites randomly without prior information to theimplementing agency, along with the regular site visits. The consultant will be submitting weeklyreports before the 3rd day of the following week. Monthly reports, quarterly reports, annualreports will be submitted as per the scheduled time plan. In case of noncompliance theconsultant will be reporting the same to the concerned SPIU representative along with photo
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 5/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
K. The work plans of the implementation agency will be observed and suitable modifications will besuggested basing on the past experiences in the sites.
L. The consultant will prescribe suitable formats for progress reporting and the same formats willbe used to report regularly.
M. The consultant will advise on the required site audit procedures for individual duties andresponsibilities, including detailed inspection schedules and check lists.
N. The Third Party Quality Audit will carry out additional tests, where a prime facie doubt arisesrelated to quality of works and / or compliance of standards using mobile laboratory availablewith the consultant or nearby approved laboratories. The consultant shall advise few more labsfor testing suitably, which after the approval of the SPIU / line departments, can be used fortesting.
O. Review the workers’ safety standards being followed in the construction site to avoid any typeof losses / damages, as far as possible.
P. The tests shall include all common tests as specified in Terms of Reference (ToR). Consultantwill take the samples and get it tested in accredited/approved laboratories which will be firstinspected and recommended for accrediting by Consultant under the project by SPIU. Theidentification and certification of the testing agency will be specific to the tests that can be
i d i i l l b
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 6/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
However, the progress of works need a lot of improvement in Srikakulam, East Godavari and
Guntur Districts. In the other six districts, lot of improvement is observed in the progress of works.
In Srikakulam District, number of MPCS buildings is to be constructed and hence experienced
line departmental engineers are required to supervise the works. Already, agreements were
concluded for 31 MPCS buildings and a few more are to be entrusted. Only a Deputy Executive
Engineer is holding the additional charge of the post of Executive Engineer. An experienced
Executive Engineer is necessary for proper planning and supervision of the NCRMP works inSrikakulam District. The fact was brought to the notice of the Chief Engineer, PR, NCRMP during
review meetings held in the office of SPIU. Chief engineer, PR, NCRMP camped there for 3 days to
review and improve the progress of works in Srikakulam District. Progress of works is behind
schedule in many works. PM, TPQA reviewed the situation along with SE, PR, Srikakulam on 27-12-
2013, in the presence of contractors and engineers. It was stressed that the importance of speedingup the progress to complete the works in time. There are some site problems to be resolved by the
departmental officers and in many cases; contractors need to improve the progress. Srikakulam
District requires the attention of regular review and monitoring by the higher level officers. Some
sites for some MPCS buildings in East Godavari and Guntur Districts are not yet handed over to the
contractor. These problems required to be resolved as quickly as possible. Lot of efforts and proper
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 7/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
All the details of site visits and findings etc. are given in detail in the MPRs in different
formats and work wise details are furnished in a separate check memo booklet attached to thisMonthly Progress Report. The check memo format was prepared and communicated by SPIU.
Whenever, non-compliances are noticed, Non-Compliance Reports are being issued and their
compliance is closely monitored. Suitable corrective measures are also being suggested as per the
Quality Assurance Plan. After the compliance is received, the respective NCR is being closed.
The summary of site visits, NCRs issued during the month and Quality Control Tests doneduring December 2013 are tabulated hereunder.
Sl. No. DistrictNo of Sitevisits by
TPQA
Number of NCR Issued
Quality control Testsdone
Passed Failed
1 Srikakulam 82 0 198 02 Vizianagaram 22 0 78 1
3 Visakhapatnam 6 0 4 0
4 East Godavari 50 0 178 0
5 West Godavari 41 1 111 6
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 8/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Apart from regular site visit reports, the abstract of social and environmental issues are reported
separately to the SPIU and line department for their review and immediate action. The landparticulars of the cyclone shelters are submitted to the SPIU for their necessary action.
Due to lack of awareness on safety measures among the contractors, all the safety measures are
not adopted in some works. In such cases, TPQA is issuing Non Conformance Report (NCR)s. In
Guntur district, the bridge across Pedapalli drain at Km 14/6 of chandole, proper safety measures are
not provided by the contractor. The TPQA consultant issued NCR. The contractor provided the
reflective signboards on the diversion road and painted guard stones on both sides. After the
compliances, the NCR was closed. In Srikakulam district, proper barricading is necessary for the
cyclone shelters at ch.Karrivanipalem, Ramayyapatnam, Pathadibbapalem, Bonthalakodouru,
Akkuvaram, Jaganahtapuram, Kothamukkam, Metturu, Kommaravanipeta, Chinavanka,
chinakothuru, Bypalli, Calingaptanam. In all the above mentioned sites, the first aid boxes are notprovided. Project Information boards are not erected. In Prakasam district, in the construction of
cyclone shelter in Alagayapalem, a NCR was issued due to failure to provide personal protective
equipment to the workers. The machinery engaged at the work sites are in good condition. In all
works, borrow areas are free from habitations and forest lands. In case of roads, very few local
l b d l d b h d h l b i i i li bl B
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 9/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
10. Consent/permission for water extraction/use from the concerned individuals/GP etc.,11. Traffic safety arrangements
12. Safety measures adopted at work site.
13. Control of Air Pollution during the construction
14. Measures to protect the water bodies.
15. Noise controlling measures at the work site.16. Disposal of debris /location/consent
17. Restoration and Rehabilitation of sites
18. Liabilities arising out of the contractor’s agreement with landowner/local/GP etc.,
District wise Sites Visited during December, 2013
The details of field visits done by Environment and social team of TPQA during December,2013 are summarized below:
S N Di iNo.of MPCS
Vi i d
No.of
RCS
No.of
RHBSalineE b T l
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 10/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Details of the training programs conducted by the TPQA consultant are listed in
the table here under:
S.No District Date of Training Programme
1. Krishna 02-08-2013
2. East Godavari 23-10-2013
3. West Godavari 23-10-2013
4. Prakasam 19-12-20135. Nellore 20-12-2013
6. Vizianagaram 26-12-2013
7. Srikakulam 27-12-2013
Environment Management Plans (EMPs) submitted.
The TPQA team is insisting the line department officers and contractors to submit the Social
and Environment Management Plan for all the works. In Krishna district, 31 EMPs were submitted by
the contractors. In East Godavari district, one EMP was submitted. The Contractors gave assurance
for the preparation and implementation of the SEMP in their respective works during the awareness/
workshops.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 11/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Kothapatnam reserve forest area in one stretch. The total length of the road is 5.968 Km and the
reach from Km 5/0 + 55 to 5/4 +55 (400 meters ) is falling in Kothapatnam forest area. The extentof land for which permission is required from competent authority is about 0.40 hectares. The
proposed road connects Kothapatnam, Srinivasasatram and Yamadinnepalem villages in Kota mandal
which links to Narravaripalem, Mannegunta and Varagali of Chilukur mandal. The Executive Engineer
of the PR, PIU Division, Nellore informed that the proposals were submitted in the required formats
on 24.07.2013 to Divisional Forest Officer (D.F.O), Nellore for getting the clearance. The Agreement time for the work ends by 18.06.14.
In Prakasam district, Forest department claiming that the entire stretch of the
proposed road i.e., 2040mts comes under their jurisdiction. The line department officials are
pursuing the matter with forest department for the clearance.
3.1 Summary of Audit Opinion
Engineers of TPQA consultant are visiting the NCRMP works at regular intervals and are
issuing Site Inspection Reports and Quality Control (Audit) Reports. List of all the works for which
l l d b d h
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 12/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
Summary of TPQA observations requiring attention of SPIU in Quality Audit Reports.Sl.No Description of item Remarks
1 Action Taken Reports
ATRs for QCRs are not received from line departmental officers forthe QCRs issued by TPQA consultant. Very few ATRs are receiveduntil now. Prompt submission of ATRs will serve the purpose of issuing QCR. Instructions may be issued from the E.N.C(R&B) andCE,PR, NCRMP in this regard.
2
Contractor’s work program andEnvironmental and SocialManagement Framework (ESMF)plan.
Despite requesting several times, TPQA is not receiving or shown thework program and ESMF for most of the works. TPQA supplied theblank format for ESMF plan also. Necessary guidance will beextended by TPQA in preparation of the plan if necessary. TPQA consultant has conducted training sessions at Kakinada, Amalapurm,Eluru, Vijayawada, Ongole, Nellore, Vijayanagaram and Srikakulamabout the SEMF. Now some contractors are furnishing EMP.
3 Quality control lab
Contractor is not establishing QC lab for many road works. For smallroad works, necessary field testing equipment shall be made availableat site by the contractor so that the field officers can also conduct theQC tests. One QC lab for one package of road works at a centrallocation shall be provided.
4 Site inspection register
At some places, site inspection registers are not maintained.Instructions of the inspecting officers are not being written in theregister. Some inspecting officers are issuing inspection reports.These reports are to be attached in the register.
d l l l h h
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 13/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
3.2 Corrective actions:
Corrective actions for all the likely non-compliances are suggested as per standard specificationsadopted in the contract documents in the Quality Assurance Plan submitted. Accordingly for variousnon-compliances, corrective actions are suggested and getting implemented. Some of the correctiveactions are discussed hereunder:
1. Gradation non - compliance: In collection of aggregates for GSB Granular Sub Base), WMM (WetMix Macadam), WBM (Water Bound Macadam), OGPC (Open Grade Premix Carpet), Seal Coat, SDBC
(Semi Dense Bituminous Concrete) and concrete aggregate collections. whenever gradation is notsatisfied, corrective actions were suggested by TPQA to make the gradation compliant with thespecified one. Generally, it was done by adding the missing or deficient sizes and re-breaking highersized materials.
2. Density - compliance: Whenever relative compaction is deficient in compacted layers of earthwork, shoulders, GSB layers, WBM layers or WMM layers, re-compaction is done by scarifying,
watering to OMC (Optimum Moisture Content) and compaction to achieve the specified relativecompaction
3. Deficiency in thickness: NCRs were issued when thickness of GSB, WBM, WMM or sub-grade layerthickness is found to be less than the specified thickness. After the suggested corrective action isdone, the NCR s are being closed after verification.
4. Stop work notice: Stop work notice was issued in one work, when temperature of bituminous mix
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 14/194
MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)
The progress of works with reference to mile stones, stage of work and site related problems is
described in detail in Annexure A of the MPR. Failure to furnish the contactor’s work program is nothelping our cause.
District wise Summary of Work Progress
Sl.No District Up to
10%11 to40%
41 to70%
≥ 71%
Completed
WorksNot
started
Worksdeleted
TotalNo of
works1 Srikakulam 9 20 7 2 6 14 3 61
2 Vizianagarm 2 0 1 3 0 6 0 12
3 Visakhapatnam 0 0 2 5 3 1 0 11
4 East Godavari 6 7 6 3 3 1 0 26
5 West Godavari 0 4 10 16 1 2 0 33
6 Krishna 16 14 10 20 0 23 0 83
7 Guntur 5 1 1 1 2 9 0 19
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 15/194
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 16/194
R H B
R C S
M P C S
B r i d g e s
R o a
d s
( R & B )
T o
t a l
R H B
R C S
M P C S
B r i d g e s
R o a
d s
( R & B )
T o
t a l
R H B
R C S
M P C S
B r i d g e s
R o a
d s
( R & B )
T o
t a l
1 Srikakulam 6 8 2 4 1 21 6 8 0 3 1 18 12 0 0 2 1 0 3 0
2 Vizianagaram - - - 2 1 3 0 0 0 2 1 3 3 0 0 0 0 0 0 0
3 Visakhapatnam 8 6 7 - - 21 8 6 6 0 0 20 14 0 0 0 0 0 0 1
4 East Godavari 2 8 3 - - 13 2 7 2 0 0 11 8 0 0 1 0 0 1 1
5 West Godavari 10 - - - - 10 10 0 0 0 0 10 10 0 0 0 0 0 0 0
6 Krishna 5 3 - - - 8 5 3 0 0 0 8 8 0 0 0 0 0 0 0
7 Guntur 3 12 - 2 - 17 3 12 0 1 0 16 11 0 0 0 1 0 1 0
8 Prakasham 14 7 2 1 - 24 14 7 2 1 0 24 24 0 0 0 0 0 0 0
9 Nellore 16 10 - - - 26 16 8 0 0 0 24 24 0 2 0 0 0 2 0
Total 64 54 14 9 2 143 64 51 10 7 2 134 114 0 2 3 2 0 7 2
Total No. of works entrusted in Year-1 = 143 nos No. of works deleted = 2 nos
No. of works completed by 14.04.2013 = 129 nos Spillover works in to Year – 2 = 143 – 2 – 129 = 12 nos
N o . o
f w o r k s
d e
l e t e d
N o . o
f F i n a
l R e p o r t s
S u
b m
i t t e d
Status of NCRMP Year-1 works as on 14.04.2013 TABLE - 1
S . n
oDistrict
No. of works(Under Concluded Agreements)
No. of works Completed No. of works under Progress
Page 15 of 193Page 15 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 17/194
Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works
1 Srikakulam 1 2 0 0 2 3 3 5 1 1 0 0 4 6
2 Vizianagaram 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Visakhapatnam 1 1 0 0 0 0 1 1 0 0 0 0 1 1
4 East Godavari 1 1 0 0 0 0 1 1 0 0 0 0 1 1
5 West Godavari 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6 Krishna 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Guntur 0 0 1 1 0 0 1 1 1 1 0 0 2 2
8 Prakasam 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Nellore 0 0 1 2 0 0 1 2 0 0 0 0 1 2
3 4 2 3 2 3 7 10 2 2 0 0 9 12Total
Abstract of pending Spill over (NCRMP Year-1) works (which were not completed by 14.04.2013) TABLE - 2
Sl.No.
District
PR R&B I & CADTOTAL
MPCS RCS RHB TOTAL Bridges Saline Embankment
Page 16 of 193Page 16 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 18/194
Sl.No
DistrictCateg
oryPackages allotted under
Phase - 1s.no Names of works under each package
Agreement No./ Date
Work Status
1 1Road from R&B road Mobagam toDuubakavanipeta via Gajapathinagaram
/2010-11, Dt.30.04.2011
completed
2 2 Road from Talasamudram to Dola Regulator /2010-11, Dt.
30.04.2011completed
3 NCRMP/B-W/AP/RHB/PRED/01/Polaki/005 3 Road from R&B road Edulavalasa - Killam toJonnam via Talasamudram /2011-12, Dt.30.04.2011 completed
4R&B
bridgeNCRMP/B-W/AP/Br/R&B/
01/Uppugedda/0024
Construction of High level bridge acrossUppugedda at KM 7/6 of Srikakulam muncipallimits to Pukkalapeta via Killipalem
47/2010-11,Dt17.12.2010
completed
5 5 Construction of Cyclone shelter at KollipaduG.o rt No 451 dt
06.04.2010completed
6 6 Construction of Cyclone Shelter at RunkuG.o rt No 451 dt
06.04.2010completed
7 Visakhapatnam MPCSNCRMP/B-W/AP/MPCS/PRED/
03/Rambilli/0041 Construction of CS at Venkayyapalem
/2011-12, Dt.03.10.2011
Completed
8 East Godavari MPCSNCRMP/B-W/AP/MPCS/PRED/
04/ Uppalaguptam/0021
Construction of CS at Pedaraghavulapeta of Uppalaguptam Mandal
78/2011-12Dt:17.10.2011
Completed
9 BridgesNCRMP/B-W/AP/Br/R&B/
07/Bapatla/0114
Reconstruction of HLB @Km2/4 of Bapatla -Pandurangapuram Road across perali drain
78/2010-111.12.2010
Completed
10 RCSNCRMP/B-W/AP/RCS/PRED/
07/PV Palem/0016 Road from R&B Road Alluru to Yadavapalem
2011-20121.11.2011
completed
11 3Road from @ 56/8 to C.K road to Periyavettukuppam CS
14.09.2012 completed
12 2Providing BT road to Pedapannamgadu in TadaMandal
14.09.2012 completed
NCRMP/B-W/AP/RCS/PRED/09/Tada/009
RCSSPSR Nellore
STATUS OF SPILL OVER (NCRMP YEAR-1) WORKS AS ON 31.12.2013 TABLE - 3
Srikaulam
RHB
NCRMP/B-W/AP/RHB/PRED/01/Polaki/006
MPCSNCRMP/B-W/AP/MPCS/PRED/
01/Santhabommalli/005
Guntur
Page 17 of 193Page 17 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 19/194
Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works
1 Srikakulam 12 25 6 15 6 15 24 55 0 0 0 0 24 55
2 Vizianagaram 3 4 1 5 3 3 7 12 0 0 0 0 7 12
3 Visakhapatnam 1 1 3 4 3 5 7 10 0 0 0 0 7 10
4 East Godavari 3 5 6 9 5 8 14 22 3 3 0 0 17 25
5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33
6 Krishna 5 9 10 30 15 42 30 81 1 1 1 1 32 83
7 Guntur 5 8 2 3 2 4 9 15 2 2 0 0 11 17
8 Prakasam 6 11 4 12 11 30 21 53 1 1 0 0 22 54
9 Nellore 0 0 11 19 9 19 20 38 1 1 0 0 21 39
35 63 47 106 62 150 144 319 8 8 1 1 153 328
Details of Agreements Communicated by SPIU to TPQA Consultant to the end of December 2013 TABLE - 4
R&B I & CADTOTAL
MPCS RCS RHB
PR
TOTAL Bridges Saline EmbankmentDistrictSl.No.
Total
Page 18 of 193Page 18 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 20/194
TABLE - 5
Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works Packages Works
1 Srikakulam 13 27 6 15 7 18 26 60 1 1 0 0 27 61
2 Vizianagaram 3 4 1 5 3 3 7 12 0 0 0 0 7 12
3 Visakhapatnam 2 2 3 4 3 5 8 11 0 0 0 0 8 11
4 East Godavari 4 6 6 9 5 8 15 23 3 3 0 0 18 26
5 West Godavari 0 0 4 9 8 24 12 33 0 0 0 0 12 33
6 Krishna 5 9 10 30 15 42 30 81 1 1 1 1 32 83
7 Guntur 5 8 3 4 2 4 10 16 3 3 0 0 13 19
8 Prakasam 6 11 4 12 11 30 21 53 1 1 0 0 22 54
9 Nellore 0 0 12 21 9 19 21 40 1 1 0 0 22 41
38 67 49 109 63 153 150 329 10 10 1 1 161 340Total
RCS RHB
Details of Agreements Communicated by SPIU to TPQA Consultant to the end of December 2013 + Spill over works of Year-1
Sl.No.
District
PR I & CADTOTAL
MPCSSaline
Embankment
R&B
TOTAL Bridges
Page 19 of 193Page 19 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 21/194
P R
R & B -
B r i d g e s
I & C A D D
S t a r t e d
N o
t s t a r t e d
P r o g r e s s
C o m p
l e t e d
D e l e
t e d
C i v i l E n g
i n e e r s
v i s i t s
E n v
& S o c
i a l
v i s i t s
E l e c t r i c a l E n g g
v i s i t s
T o
t a l V i s i t s
I s s u e d
C l o s e d
P e n
d i n g
C i v i l A u d
i t
R e p o r t s
S o c i a
l & E n v
A u
d i t r e p o r t s
E l e c t r i c a l A u
d i t
r e p o r t s
1 Srikakulam 60 1 0 49 44 14 38 6 3 442 61 15 518 832 15 12 3 58 61 9
2 Vizianagaram 12 0 0 6 6 6 6 0 0 93 9 1 103 222 3 3 0 14 9 1
3 Visakhapatnam 11 0 0 11 10 1 7 3 0 187 9 14 210 611 10 2 8 31 9 14
4 East Godavari 23 2 0 25 25 1 22 3 0 216 20 10 246 753 1 1 0 26 20 9
5 West Godavari 33 0 0 33 31 2 30 1 0 320 41 0 361 588 21 20 1 43 42 0
6 Krishna 81 1 1 50 60 23 60 0 0 432 33 0 465 600 12 6 6 76 32 0
7 Guntur 16 3 0 9 10 9 8 2 0 237 3 0 240 101 3 3 0 11 6 0
8 Prakasam 53 1 0 35 35 19 32 3 0 466 38 0 504 1536 23 20 3 83 36 0
9 Nellore 40 1 0 39 40 1 40 0 0 406 40 0 446 1783 18 16 2 76 39 0
329 9 1 257 261 76 243 18 3 2799 254 40 3093 7026 106 83 23 418 254 33Total
ABSTRACT STATUS OF NCRMP WORKS PROGRESS AS ON 31.12.2013 TABLE - 7
Cummulative Visits of TPQACummulative AuditReports submitted
by TPQA
Sl.
No.District
Work Entrusted Status of Works
T o
t a l N o . o
f Q C t e s t s
c o n d
u c t e d
NCRs By TPQA
R e v i e w o
f C o n
t r a c t
D o c u m e n
t
Page 20 of 193Page 20 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 22/194
Annexure - A
Status of Works
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 23/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 40 11 to 40% 57
41 to 70% 52
≥ 71% 94
Completed 18
Works Not Started 76
Deleted 3
Total No of Works 340
Consolidated Abstract Status of NCRMP Works as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 24/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 2
11 to 40% 7
41 to 70% 4
≥ 71% 19
Completed 3
Works Not Started 19
Total No of works 54
Abstract Status of NCRMP Works in Prakasam District as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 25/194
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 26/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work Value of
work done in
% of work done
for thework
15 Y 2 - 3
8 7
R&B Road toPulavaripalem 600 36.71 GSB, CC Completed,
Shoulders in Progress 35.00 95%
16 Y 2 - 3
8 8
Road from ChinnaganjamRly gate to Bapaiahnagar 5577 187.50 175.50 93.6%
17 Y 2 - 3 8 9 Road from R & B road to
Kothaplem 1925 83.06 77.98 94%
18 Y 2 - 3
9 0
Motupalli R & B Road toKrishna Nagar 360 23.37 GSB Completed, CC
Pavement Completed 21.81 93%
19 Y 2 - 3
9 1
Road from R & B Road to Yanadi Sangam 850 48.19
GSB,CC,WBM Gr-II & III,OGPC + SC Completed,Shoulders in Progress
44.82 93%
20 Y 2 - 3
9 2 Jeedichetlapalem R&B
road toKunkuduchetlapalem
2170 126.27GSB Completed, CC
Pavement in progress for340m
4.16 3%
21 Y 2 - 3
9 3
Road from R&B road toNayuripally - - - Work Not Started - - - - - -
22 Y 2 - 3 9
4Road from R & B Road to
Sai Nagar - - - Work Not Started - - - - - -
23 Y 2 - 3
9 5 Road from Utukuru
Subbaiahpalem toTenkayachetlapalem
- - - Work Not Started - - - - - -
24 Y 2 - 3
9 6
Road from R & B road toKothaplem - - - Work Not Started - - - - - -
25 Y 2 - 3
9 7
KEM R&B road toChinapattapupalem 900 43.13 40.63 94%
26 Y 2 - 3
9 8 Salt Road from Madnur ZP
road toPedapattapupalem
973 53.69 50.92 94.8%
27 Y 2 - 3 9 9
Madnur ZP road toSwarnandhrapattapupalem 800 43.11 40.88 95%
28 Y 2 - 4
0 0
Madnur ZP road toBapujiyanadi colony 285 16.57 GSB, CC Completed,
Shoulders in Progress 15.71 95%
29 Y 2 - 4
0 1 Salt Road from Madnur ZP
road to Namburi yanadicolony
975 47.89 45.25 94%
30 Y 2 - 4
0 2 Salt Road from Madnur ZP
road to Thotaguntayanadi colony
1100 51.75 48.77 94%
10.02.13WBM, CD & CC works
(54%)
10.06.14BT & RoadFurniture(100%) 2
4 . 0
3 . 1
3
288.48 94%
70.79 36%
For thepackage
Progress of works are as
per Milestone
GSB, CC, WBM Gr-II & III, OGPC + SC
Completed, Shoulders inProgress
7
NCRMP/B-W/ AP/RHB/PRED/08/
Chinaganjam /013
R H B 197.00 /
19.03.13 18.03.14
18.08.13Earth work
& GSB(26%)
18.12.13WBM, CDWorks &
CC (44%)
18.03.14BT & RoadFurniture(100%) 1
5 . 0
5 . 1
3
6
NCRMP/B-W/ AP/RHB/PRED/08/
Chinaganjam
/012
R H B 307.00 /
11.03.13 10.06.14
10.09.13,Earth Work
& GSB(32%)
For thepackage
Progress of works are
slow and notas per
Milestone
8
NCRMP/B-W/AP/RHB/PR
ED/08/Vetapalem& Chirala/015
R H B
Agreement Concluded, but not submitted to TPQA
9NCRMP/B-W/ AP/RHB/
PRED/08/Kothapatnam/0
20
R H B 256.00 /
11.03.13 10.09.1410.11.13
Earth work,GSB (47%)
10.04.14WBM Gr-II,WBM Gr-III
& CDWorks(65%)
10.09.14CC,
Shoulders,BT & RoadFurniture(100%)
2 0
. 0 3
. 1 3
GSB, CC, WBM Gr-II & III, OGPC + SC
Completed, Shoulders inProgress
242.16 95%For thepackage
Progress of works are asper Milestone
GSB, CC, WBM Gr-II & III, OGPC + SC
Completed, Shoulders inProgress
Page 25 of 193Page 25 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 27/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work Value of
work done in
% of work done
for thework
10
NCRMP/B-W/ AP/RHB/PRED/08/
Tangutur/021 R H B 143.00 /
02.04.13 01.04.1410.09.13
Earth work,GSB (20%)
10.01.14WBM, CDWorks &
CC (55%)
01.04.14Shoulders,BT & RoadFurniture(100%)
31 Y 2 - 4
0 3 Road from Tangutur to
Tallapalem (via) Velagapudi (Km 4/5 to
7/465)
2965 143.00 0 5
. 0 4
. 1 3 GSB, CC & WBM Gr-II
Completed & WBM Grade-III in progress
90.38 63% 90.38 63%Progress of
work is as perMilestone
11
NCRMP/B-W/ AP/RHB/PRED/08/
Tangutur/022 R H B 131.00 /
14.03.13 13.03.14 13.08.13Earth work,GSB (20%)
13.12.13
WBM Gr-II,CD Works& CC
(55%)
13.03.14
Shoulders,BT & RoadFurniture(100%)
32 Y 2 - 4 0
4Road from Tangutur-Ravivaripalem road @1/2KM to Pasukuduru.
2900 131.00 1 4
. 0 4 . 1 3 GSB, CD Works, CC,
WBM Gr-II completed.WBM Grade-III in
progress
94.06 72% 94.06 72% Progress of work is as perMilestone
33 Y 2 - 4
0 5
Road from Kanuparthy toKukkalavaripalem 800 39.55 GSB & WBM Grade-II
Completed for 500m 10.78 27%
34 Y 2 - 4
0 6
Road from Kanuparthy to Yanadi Sangam 1500 71.83 GSB Completed & WBM
Grade-II Completed 28.99 40%
35 Y 2 - 4
0 7
Road from Kanuparthy toMS Pattapupalem 2300 118.31
GSB, WBM Grade-IICompleted & WBM Grade-
III in progress54.89 46%
13
NCRMP/B-W/ AP/RHB/PRED/
08/S.Konda/
018
R H B
36 Y 2 - 4
0 8
Road from PR Road toDevalampallipalem - - - Work Not Started - - - - - -
37 Y 2 - 4
0 9 Road from KEM R&B Road
to Vajjireddypalem -Pattapupalem
1185 58.50GSB,CC,WBM Gr-II & III,
OGPC+SC Completed,Shoulder in Progress
49.45 85%
38 Y 2 - 4
1 0
KEM R & B road toPinnivaripalem 1650 62.08
GSB,CC,WBM Gr-II & III,OGPC+SC Completed,Shoulder in Progress
58.32 94%
39 Y 2 - 4
1 1 Salt Road from Madnur ZP
road toChinnapattapupalem
800 33.89GSB,CC,WBM Gr-II & III,
OGPC+SC Completed,Shoulder in Progress
31.84 94%
40 Y 2 - 4
1 2
KEM R & B road to E.Pallipalem 650 29.20 GSB, CC Completed,
Shoulders in Progress 29.00 99%
41 Y 2 - 4
1 3 Road from KEM R & B
road toChenchupapayapalem
1550 56.72GSB,CC,WBM Gr-II & III,OGPC + SC Completed,Shoulders in Progress
53.17 94%
15
NCRMP/B-W/ AP/RHB/PRED/08/Ulavapadu
/016
R H B 359 /
11.03.13 10.03.1410.08.13
Earth work,GSB (12%)
10.12.13WBM Gr-II,WBM Gr-III
& CDWorks(64%)
10.03.14CC-
Shoulders,BT & RoadFurniture(100%)
42 Y 2 - 4
1 4 Road From M.C road to
West ST colony of Veerapalli
5380 359.00 2 0
. 0 3
. 1 3 GSB,CC,WBM Gr-II & III,
OGPC+SC Completed,Shoulder in Progress
349.88 97% 349.88 97%
For thepackage
progress of work is as per
Milestone
94.66 41%
For thepackage
Progress of works are asper Milestone
12
NCRMP/B-W/ AP/RHB/
PRED/08/ NGPadu/011
R H B 229.00 /
20.03.13 19.06.1419.09.13
Earth work,GSB (25%)
19.01.14WBM Gr-II,WBM Gr-III
& CDWorks(49%)
19.06.14CC,
Shoulders,BT & RoadFurniture(100%)
0 9
. 0 4
. 1 3
Agreement Concluded, but not submitted to TPQA
14
NCRMP/B-W/ AP/RHB/PRED/08/
Kothapatnam /019
R H B 240.00 /
15.03.13 14.06.1414.09.13
Earth work,GSB (29%)
14.02.14WBM Gr-II,WBM Gr-II,CC-50% & CD Works
(35%)
14.06.14CC-50%,
Shoulders,BT & RoadFurniture(100%)
2 0
. 0 3
. 1 3
221.78 92%
For thepackage
Progress of works are asper Milestone
Page 26 of 193Page 26 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 28/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work Value of
work done in
% of work done
for thework
16
NCRMP/B-W/ AP/Br/R&B/08/
Ongole/023 B r i d g e
372.00 /12.04.13 11.09.14
11.08.13Completion
of Foundations upto Sill
Level(35%)
11.12.13Completionupto belowDeck Salb
(47%)
11.04.14Completion
of entirework
includingapproaches
(100%)
43 Y 2 - 4
5 5 Reconstruction of High
level bridge at Km. 11/10of Ongole - Kothapatnam
road
4 ventsof 16mspan
372.00 2 0
. 0 4
. 1 3
Work Stopped 37.00 10% 37.00 10%
For thepackage
progress of work is as per
Milestone
17
NCRMP/B-W/ AP/MPCS/PRED/08/
S.Konda/002 M P C S
44 Y 2 - 1
0 2 Construction of B type CS
in Pakala Main, S.Kondamandal,Prakasam District
Type-B - - Excavation in Progress - - - - - -
18
NCRMP/B-W/ AP/MPCS/PRED/08/
Chirala/004 M P C S
45 Y 2 - 1
0 3
Construction of CS inOdarevu (Type D)
46 Y 2 - 1
0 4
Construction of CS in K.Pallipalem (Type D)
47 Y 2 - 1
0 5
Construction of CS inMotumala (Type D)
48 Y 2 - 1 0 6
Construction of CS inPadarthy (Type D) Type-D - - Excavation in Progress - - - - - -
49 Y 2 - 1
0 7
Construction of CS inRangaipalem (Type D) Type-D - - Excavation in Progress - - - - - -
50 Y 2 - 1
0 8
Construction of CS inGamallapalem (Type B)
51 Y 2 - 1
0 9
Construction of CS inMadanur (Type D)
21
NCRMP/B-W/AP/MPCS/P
RED/08/Ulavapadu/
007
M P C S
52 Y 2 - 1
1 1 Construction of CS in
Peddapallipalem of Karedu(Type C)
Type-C - - Excavation Completed & PCC in Progress - - - - - -
53 Y 2 - 1
1 2 Construction of CS in
Alagayapalem of Karedu(Type B)
Type-B - - Excavation & FoundationCompleted. - - - - - -
54 Y 2 - 1
1 3 Construction of CS in
Kothapallipalem of Karedu(Type C)
Type-B - - Excavation Completed & Foundation in Progress - - - - - -
Agreement Concluded, but not submitted to TPQA
Agreement Concluded, but not submitted to TPQA Work Not Started
19
NCRMP/B-W/AP/MPCS/P
RED/08/Kothapatna
m/005
M P C S
Agreement Concluded, but not submitted to TPQA
Work Not Started
20
NCRMP/B-W/AP/MPCS/P
RED/08/Kothapatna
m/006
M P C S
Agreement Concluded, but not submitted to TPQA Work Not Started
Agreement Concluded, but not submitted to TPQA
22
NCRMP/B-W/AP/MPCS/P
RED/08/Ulavapadu/
008
M P C S
Agreement Concluded, but not submitted to TPQA
Page 27 of 193Page 27 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 29/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 0
11 to 40% 4
41 to 70% 11
≥ 71% 25
Completed 0
Works Not Started 1
Total No of works 41
Abstract Status of NCRMP Works in SPSR Nellore District as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 30/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Y 2 - 2
4 0 Road from @ 56/8 to
C.K road to Periyavettukuppam CS
1910 71.83Earth work, GSB and
WBM Gr-II ,Gr-III & BTare completed.
70 97%
2 Y 2 - 2
4 1 Providing BT road to
Pedapannamgadu inTada Mandal
1015 32.47Earth work, GSB WBM Gr-
II & III and BTcompleted.
32 99%
2
NCRMP/B-W/ AP/RCS/PRED/09/
Alluru/012 R C S 24.39
18.03.2013 17.09.13
17.06.13Earthwork, CD
Works, andGSB (9%)
17.08.13 CCPavement &
Shoulders(90%)
17.09.13Road
furniture.(100%)
3 Y 2 - 2
4 2
Approach road toLabbipalem 420 24.39 01.05.13 GSB and CC pavement
are completed 21 86% 21 86%
3
NCRMP/B-W/ AP/RCS/PRED/09/Bogole/013
R C S 58.99
20.03.2013 19.12.13
19.07.13Earthwork,
and GSB(35%)
19.10.13WMM, CDWorks andShoulders
(73%)
19.12.13BT andRoad
furniture.(100%)
4 Y 2 - 2
4 3
Road from R & B roadto Pathakadapalem 1400 58.99 01.05.13
Earth work for wideningis done. GSB &WMM
completed43 73% 43 73%
5 Y 2 - 2
4 4 Road from
Ramudupalem on R&Broad to Pallipalem
3600 209.93Earth work, GSB, WMMand CC pavement are
completed.178 85%
6 Y 2 - 2
4 5
Road from Korutur toPattapupalem 2250 159.58
Earth work, CD works,SG,GSB, WMM & CC road
completed142 89%
5
NCRMP/B-W/ AP/RCS/PRED/09/Kavali/020
R C S 166.89
28.02.2013 27.02.14
27.07.135Months: Earth
Work, GSB(24%)
27.11.139 Months:WMM, CD
works(72%)
27.02.1412 Months:BT & RoadFurniture
of all works(100%)
7 Y 2 - 2
4 6 Road from 230/6 Km of
M.C Raod toPedapattapupalem
6200 166.89 01.03.13
Earth work for widening,vented road dam GSBcompleted.WMM is in
progress
110 66% 110 66%
Pogress of work is within the milestones as pervalue of work done.
8 Y 2 - 2
4 7 Road from R&B road to
Utukuru Pallipalem 3800 143.3 Earth work, GSB & WMMare completed. CC road
progress114 80%
9 Y 2 - 2
4 8 Road Ponnapudi R&B
Road to
Ramachendrapuram.
2230 123.8 Earth work, GSB, WMM,CC road are completed. 107 86%
10 Y 2 - 2
4 9 Ponnapudi R&B road to
Busagadipalem 2000 98 Earth work GSB & CCroad are completed. 57 58%
11 Y 2 - 2
5 0 Road from Ponnapudi
R&B Road toLakshimipuram
1.115 54 Earth work GSB & CCroad are completed. 35 65%
12 Y 2 - 2
5 1
Road from R&B Road toRamalingapuram 2193 72
Earth work, GSB & CCroad (from km0.151 to0.365) are completed.
WMM is progress.
40 56%
Status of NCRMP works in SRSP Nellore District as on 31.12.2013
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets (%)Sl.No
of work
P r o j e c t c o d e
Name of the Work
1
NCRMP/B-W/ AP/RCS/
PRED/09/Tada/009
R C S 104.300
14.09.201213.09.13
13.2.13Earthwork,
Pipe culverts,
GSB & CCpavement
(49%)
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
13.06.13WBM Gr-II,Gr-III andShoulders
(86%)
13.09.13BT andRoad
furniture.(100%)
15.09.12 102 98%
Progress of work is notwithin the
mile stonesas per value
of work done.Extension of time has to
be taken
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work
Valueof
work done
in
% of work done
for thework
6
NCRMP/B-W/ AP/RCS/PRED/09/
Vidavaluru /021
R C S 497.800
20.03.2013 19.06.14
19.09.136Months: Earth
Work, GSB(21%)
19.02.1411 Months:WMM, CC
Pavement of all works,CD works
(78%)
Progress of work is within the mile
stones as pervalue of work
done.
4
NCRMP/B-W/ AP/RCS/PRED/09/ I.Pet/018
R C S 369.51
20.03.2013 19.06.14
19.09.13Earthwork, CD
Works, CCPavement and
GSB (54%)
19.02.14WMM, andShoulders
(74%)
19.06.14BT and
Roadfurniture(100%)
21.03.13
19.06.1415 Months:BT & RoadFurniture
of allworks.
(100%)
01.04.13 353 71%
Progress of work is within the mile
stones as pervalue of work
done.
320 87%
Progress of work is within the mile
stones as pervalue of work
done.
Page 29 of 193Page 29 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 31/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets (%)Sl.No
of work
P r o j e c t c o
d e
Name of the Work Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work
Valueof
work done
in
% of work done
for thework
7
NCRMP/B-W/ AP/RCS/PRED/09/Chillakur/ 014
R C S 293.28
21.03.2013 20.03.14
20.09.13Earthwork,and GSB.
(39%)
20.12.13WMM, CDWorks, CC
Pavement & Shoulders
(84%)
19.03.14BT andRoad
furniture.(100%)
13 Y 2 - 2
5 2 Road from R&B Road
Lingavaram toNarravaripalem
6808 293.28 22.03.13
Earth work for wideningis completed.GSB
Completed.WMM is inProgress
134.5 46% 135 46%
8
NCRMP/B-W/ AP/RCS/PRED/09/Chillakur/015
R C S 112.77
21.03.2013 20.03.14
20.08.13Earthwork,and GSB.
(38%)
20.12.13WMM, CDWorks, CC
Pavement & Shoulders
(82%)
20.03.14BT andRoad
furniture(100%)
14 Y 2 - 2
5 3 Road from R&B road
(via) Narravaripalrm toSrinivasa Satram
2260 112.77 01.04.13
Earth work for wideningis completed.GSB
Completed.WMM is inProgress
88 78% 88 78%
9
NCRMP/B-W/ AP/RCS/PRED/09/Kota/016
R C S 157.200
20.03.2013 19.03.14
19.08.13Earthwork,and GSB.
(21%)
18.12.13WMM,CD
Works, CCPavement &
Shoulders(56%)
19.03.14BT andRoad
furniture(100%)
15 Y 2 - 2
5 4 Road from R&B Road to
Doruvukatta road (via) Allmpadu, Deyyaladibba
4320 157.2 21.03.13
Earth work for widening,GSB, CC pavement ,CDworks , WMM and BT
completed.
151 96% 151 96%
16 Y 2 - 2
5 5 Road from Kotha Kudur
– Katepalli road toPatha Pattapupalem
600 25.67 GSB and CC road iscompleted 23 90%
17 Y 2 - 2
5 6
Road from C.S. Puramto Edurupalem 2200 74.31
From km 0.0 to km 1.2Earth work, GSB, WMM ,
BT completed34 46%
18 Y 2 - 2
5 7 Mahlakshmi puram to
Sagara Sangamam (via)MuthyalathopuPattapupalem
2600 65.66 Earth work for widening,WMM and BT Completed.
CD works completed.63 96%
19 Y 2 - 2
5 8 Road from R&B road
Nelaturu to Ananthavaram CS
100 7.24 GSB & CC arecompleted 6.3 87%
11
NCRMP/B-W/ AP/RCS/PRED/09/Tada/024
R C S 97.55
22.03.2013 21.03.14
21.07.13Earthwork,and GSB.
(35%)
21.10.13WMM, CDWorks, CC
Pavement & Shoulders
(79%)
21.12.13BT andRoad
furniture(100%)
20 Y 2 - 2
5 9 Road from @ Km 65/4
of CK Road to TadaKuppam CS
1900 97.55 23.03.13
Earth work forwidening,CD, GSB and
WMM and BTcompleted.
96 98% 96 98%
progress of work is within the mile
stones as pervalue of work
done.
12
NCRMP/B-W/ AP/RCS/PRED/09/Chittamur/010
R C S 172.82
12.08.2013 11.11.14
11.02.14Earthwork,and GSB.
(27%)
11.07.2014,wmm, 75%
of cdwork,cc
pavement,schoulder
77%
11.11.2014BT 25% of CD Work and Roadfurniture
100%
21 y 2 - 4
5 9
Road from NidigurthiR&B road toMukkidipalem viagollapalem and to CS of Chittamur mandal inNellore dist
3075 172.82 12.08.13
Earth wok, Sub gradeand CD works
completed.GSBcompleted
95 55% 95 55%
progress of work is within the mile
stones as pervalue of work
done.
Progress of work is within the mile
stones as pervalue of work
done.
17.02.1411 Months:WMM, CDworks, CCPavement
(76%)
17.06.1415 Months:
BT andRoad
Furniture(100%)
01.07.13 126.3 73%
progress of work is within the mile
stones as pervalue of work
done.
10
NCRMP/B-W/ AP/RCS/PRED/09/T.P.Gudur & Muthukur /019
R C S 172.98
18.03.2013 17.06.14
17.09.136Months: Earth
Work, GSB(17%)
Page 30 of 193Page 30 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 32/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets (%)Sl.No
of work
P r o j e c t c o
d e
Name of the Work Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work
Valueof
work done
in
% of work done
for thework
13
NCRMP/B-W/ AP/RHB/PRED/09/
Allur/018 R H B 120.86
18.03.2013 17.03.14
17.08.13Earthwork,
andGSB.(16%)
17.12.13WMM, CDWorks, CC
Pavement & Shoulders
(77%)
17.03.14BT andRoad
furniture.(100%)
22 Y 2 - 4
1 9 Road from R.I Road to
C.R. Palem (via)Sambhunipalem
4000 160.0 01.06.13
Cause way in km 0/4,Slab culvert in km 2/4and CC road from km
0.00 to 0.195 and 0.636to 1.0 is completed. From1.00 to 1.481 CC road is
progress
63 39% 63 39%
Progress of work isslightly
behind themile stonesas per value
of work done.
23 Y 2 - 4
2 0 Salt Road from Iskapalli
to Salt fields at KothaKurrupattapupalem
3000 134Earth work, GSB & WMMare completed. CD works
completed.105 78%
24 Y 2 - 4
2 1
Road from R&B road toZuvvagu Lakshmipuram 1800 84 Earth work for widening
done. GSB in progress 12 14%
25 Y 2 - 4
2 2
Road from R&B Road toZuvvagu 2100 31.24
Earth work, GSB, WMM,CD works and CC Road
are completed.23 74%
26 Y 2 - 4
2 3 Annagaripalem R&B
road to PedanattuPattapupalem
2100 57.28Earth work for widening
done. GSB, WMMProgress
40 70%
27 Y 2 - 4
2 4
Pedapattapupalem toNandempuram 2844 77.17 Earth work, GSB and
WMM is completed 57 74%
28 Y 2 - 4
2 5 Ponnapudi-Utukur roadto Pattapupalem 2700 137
Earth work for wideningand GSB completed.
WMM progress60 44%
29 Y 2 - 4
2 6
Road from R&B road to Venkatareddypalem 1100 58.63 Sub Grade in progress 15 26%
30 Y 2 - 4
2 7
Ponnapudi R&B road to Anjanayapuram 950 52 Earth work for widening
and GSB is completed 21 40%
31 Y 2 - 4
2 8
Ponnapudi – Utukurroad to Srigowripuram 1100 68.44
Earth work and CCcompleted. GSB is in
progress.30 44%
32 Y 2 - 4
2 9
Ponnapudi – UtukurR&B road To Kothuru 1080 59.43
Earth work ,GSB & WMMis completd. CC road is
progress41 69%
33 Y 2 - 4 3
0Road from Ponnapudi –Utukur R&B road toPrasanthi giri colony
1200 65.79 Earth work for widening,GSB,CC road WMM & BTare completed.
65 99%
34 Y 2 - 4
3 1
Ponnapudi R&B road to Venkatanarayanapuram 1352 67.87
Earth work for widening,GSB,CC road WMM & BT
are completed.67 99%
35 Y 2 - 4
3 2
Road from PonnapudiR&B road to Ponnapudi 500 33.22 Earth work, GSB & CC
pavement are completed 31.7 95%
140 56%
Progress of work is within the mile
stones as pervalue of work
done.
14
NCRMP/B-W/ AP/RHB/PRED/09/
Allur/019 R H B 249.24
18.03.2013 17.03.14
17.08.13Earthwork,
and GSB(24%).
15
NCRMP/B-W/ AP/RHB/PRED/09/Kavali/024
R H B 134.45
04.03.2013 03.03.14
3.08.135Months: Earth
Work, GSB(32%)
17.12.13WMM, CDWorks, CCPavement
andShoulders
(49%)
17.03.14BT andRoad
furniture.(100%)
19.03.13
3.12.139 Months:WMM, CD
works,shoulders
(69%)
. .12 Months:BT & RoadFurniturecompleteof work.100%
01.06.13 97 72%
Progress of
work is within the milestones as pervalue of work
done.
20.12.139 Months:WMM, CC
Pavement of all works,CD works,
(84%)
20.03.1412 Months:BT & RoadFurniture
of allworks.
(100%)
21.03.13 96 39%
17
NCRMP/B-W/
AP/RHB/PRED/09/ Vidavaluru /026
R H B 294.86
21.03.2013 19.06.14
20.09.136Months: Earth
Work, GSB(23%)
20.02.1411 Months:
WMM, CCPavement of all works,CD works,
(88%)
19.06.1415 Months:
BT andRoad
Furnitureof all
works.(100%)
21.03.13
16
NCRMP/B-W/ AP/RHB/PRED/09/
Vidavaluru /025
R H B 247.63
21.03.2013 20.03.14
20.08.135Months: Earth
Work, GSB(27%)
234.7 80%
Progress of work is within the mile
stones as pervalue of work
done.
Page 31 of 193Page 31 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 33/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets (%)Sl.No
of work
P r o j e c t c o
d e
Name of the Work Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservation
Stage of work
Valueof
work done
in
% of work done
for thework
36 Y 2 - 4
3 3
Mypadu R&B Road toKollimittapalem 2328 129.94
Earth work for widening,GSB and WMM
completed109.53 84%
37 Y 2 - 4
3 4 Nellore – Mypadu R&B
Road to WestPattapupalem
900 56.28 Earth work , GSB & CCroad is completed 53 94%
19
NCRMP/B-W/ AP/RHB/PRED/09/
V.Chalam/021 R H B 69.400
08.02.2013 07.11.13
7.07.135Months: Earth
Work, GSB(22%)
7.11.139 Months:WMM, CD
works,(82%)
7.02.1412 Months:BT & RoadFurniture(100%).
38 Y 2 - 4
3 5 Road from
ThirumalammapalemR&B Road to GajulapalliKoneru
2400 69.4 09.02.13
From km 0/0 to km 2.00,Earth work, GSB, CD
works, WMM & BT arecompleted. From Km 2.0to 2.4 work could not becompleted due to court
case.
65 94% 65 94%
20
NCRMP/B-W/ AP/RHB/PRED/09/Kota/022
R H B 252.640
19.03.2013 18.06.14
18.09.136Months: Earth
Work, GSB(23%)
18.02.135 Months:WMM, CD
works,(82%)
18.06.144 Months:BT & RoadFurnitureremainingall items.(100%)
39 Y 2 - 4
3 6 Road from R&B road
Kothapatnam to Yamadinnepalem (via)Srinivasasatram
5968 252.64 20.03.13
Earth work for wideningand GSB ,cc road are
completed. WMM work isin progress.
190 75% 190 75%
21NCRMP/B-W/
AP/RHB/PRED/09/Kota/023
R H B 53.87
08.02.2013 07.11.1307.06.13
4Months: EarthWork, GSB
(24%)
07.09.133 Months:WMM, CD
works,(81%)
07.11.132 Months:BT & RoadFurniture(100%)
40 Y 2 - 4
3 7 Road from at km 22/5
of Yamadinne palemroad to Gunnampadia
1320 53.87 09.02.13
Earth work forwidening, GSB, CD
works, WMM and BTCompleted. CC pavement
completed.
53 98% 53 98%
Progress of
work is aheadof the milestones as pervalue of work done.
22
NCRMP/B-W/ AP/Br/R&B/09/Juvvaladine/02
5 B r i d g e
41 Y 2 - 4
5 5
Construction of HLB atKm 7/2 of road from MC
road Juvvaladinne viaMungamur in Nellore
District
Work not Started
18
NCRMP/B-W/ AP/RHB/PRED/09/I.Peta/027
R H B 186.24
21.03.2013 20.03.14
20.08.135Months: Earth
Work, GSB(20%)
20.12.139 Months:WMM, CD
works,(89%)
Agreements concluded , Estimate copies and Drawings not givenby Line Deparment
20.03.1412 Months:BT & RoadFurnitureremainingall items.(100%)
21.03.13 162.53 87%
Progress of work is within the mile
stones as pervalue of work
done.
Progress of work is within the mile
stones as pervalue of work
done.
Page 32 of 193Page 32 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 34/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 0
11 to 40% 0
41 to 70% 2
≥ 71% 5
Completed 3
Works Not Started 1
Total No of works 11
Abstract Status of NCRMP Works in Visakhapatnam District as on31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 35/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1
NCRMP/B-W/ AP/MPCS/PRED/03/
Rambillii/004 M P C S 75.06
03.10.2011
02.07.12EOAT
approvedup to
25.07.13
02.01.12GroundFloorPlinth
Leve
02.04.12Casting of all slabs
02.07.12Completio
n of allitems of
work
1 Y 2 - 0
4 8 Construction of
cyclone shelter at Venkayyapalem
75.06
Re startafter gettingapproval of foundation
re design on29.06.12
All slabs, brick work,plastering, wood
joinery, flooring,plumbing, painting
completed.
75.06 100% 75.06 100%
Completed. Workingestimate
preparation/approval is awaiting.
2
NCRMP/B-W/ AP/MPCS/PRED/03/ SRayavaram
/009
M P C S 129.92
20.04.2013 19.04.13
19.09.13GroundFloorPlinthLevel
19.01.14Casting of all floors
19.04.13Completio
n of allitems of
work
2 Y 2 - 0
5 7 Construction of CS at
Bangarampalem I & IIH/o Vakadu. (Type D)
129 .9 2 2 0. 04. 13
Earthwork excavationstarted and stop due tosite dispute. Alternatesite is identified andapproval is pending.
0.00 0% 0 0%
The villageproposed to be
aquired for navelbase purpose.Hence the field
officers areinformed to higher
otherties forcancellation of the
work
3 Y 2 - 1
6 5 Road from R&B road
toChinanagamayyapalem
CS
1525 47.29 11.03.13
WBM Gr-II & III andOGPC +Seal coat fromKM 0.000 to 0.800, 3
nos CD works,Shoulders completed.
28.35 60%
45% value of work is not able to do
due to site disputewith forest dept.@
4 Y 2 - 1
6 6
Road from R&B roadto Annavaram CS 1100 31.15 11.03.13
WBM Gr-II & III, OGPC+ Seal coat from km0.00 to 1.057 and CCRoad work from km
1.057 to 1.107,Shoulders completed.
30.5 98%
4
NCRMP/B-W/ AP/RCS/
PRED/03/ SRayavaraam
/006
R C S 56.46
07.03.2013 06.12.13
06.07.13Earth
work, CCroad
(29.28%)
06.10.13CC Road(67.18%)
06.12.13Shoulders
, Roadfurniture
& CC road(100%)
5 Y 2 - 1
6 7
Road from R&B roadto Revupolavaram CS 1065 56.46 07.03.13
Earth work forwidening, CC Road
work, shoulder worksare completed from KM
0.000 to 0.8548 andfrom KM 0.885 to 1.072
56 99% 56 99%
5
NCRMP/B-W/ AP/RCS/PRED/03/
Rambilli/007 R C S 38.78
11.03.2013 10.09.13
10.06.13Earthwork
, GSB (15%)
10.08.13CC Road( 89.45)
10.09.13
Wearingcoat,shouldersand Roadfurniturecomplete( 100%)
6 Y 2 - 1
6 8
Road from R&B roadto Kothapatnam CS 650 38.78 11.03.13
Earth work, subgrade,GSB, shoulders
and CC Road work completed from KM0.000 to KM 0.610.
39 101% 38.7 100% Completed
10.12.133
NCRMP/B-W/ AP/RCS/PRED/03/
Bheemili/005 R C S 78.44
11.03.2013
10.07.13Earthwork
, Pipeculverts of
allworks(10
%)
Reasonsfor non-startedworks
TPQA observation Value of
work done in
% of work
done forthe work
Status of NCRMP works in Visakhapatnam District as on 31.12.2013
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t e
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o d e
Name of the Work Stage of work
10.10.13WBMGr-II,
Gr-III andCC
pavementof allwork
(54.76%)
10.12.13BT,
Shoulders
and Roadfurniturecomplete
of allworks
(100%)
58.85 75%
Length(Mts)
AGG Valueof work (Lakhs)
Date of commence
ment of work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Page 34 of 193Page 34 of 193
e Mil t / Fi i l T t T l
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 36/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Reasonsfor non-startedworks
TPQA observation Value of
work done in
% of work
done forthe work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t e
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work Stage of work Length(Mts)
AGG Valueof work (Lakhs)
Date of commence
ment of work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
7 Y 2 - 2
8 0
Road from R&B roadto Rajavaram 425 14.38 07.03.13
One pipe culvert, WBMGr-II, Gr-III and OGPC
seal coat Work iscompleted from KM 0.0
to 0.425
14 94%
6.4% value of Onepipe culvert work isnot executed as the
field officersproposed that it is
not required.
8 Y 2 - 2
8 1 Road from Rajala R&B
Road toRajaraidupalem
1764 65.34 07.03.13
Sub grade with selectedearth (Gravel): from km0.640 to 0.750, from km
1.190 to 1.764, earthwork & WBM Gr-IIcompleted from km
0.000 to 0.012 & fromkm 0.030 to 1.764, GSB: 1488 Meters from km
0.030 to 0.094, from km0.340 to 1.764, CDworks (4 nos) and
retaining wallcompleted. WBM Gr-III
Rolling is progress.
32 49%
9 Y 2 - 2
8 2 Road from R&B road
to Gajareddipalem via Venkaypalem
2614 109.87 07.03.13
4 Nos pipe culverts,
from Km 0/106 to 1/600and from km 2/0 to
2/620 GSB, WBM Gr-II& III, OGPC + Seal
coat, from km 1.600 to2.000 and from KM2.620 to 2.720 GSB
work completed.
92 84%
7
NCRMP/B-W/ AP/RHB/PRED/03/
Payakaraopeta
/008
R H B 62.04
07.03.2013 06.12.13
06.07.13Earth,GSB,Retaining
wall (
22%)
06.10.13CC Road(86%)
06.12.13CC drain,CD works,Shouldersand Roadfurniturecomplete(100%)
10 Y 2 - 2
8 3 Road from Z.P Road
Palmanpeta toKorlayyapeta
1110 62.04 07.03.13
One single row and onetwo row pipe culvert
works completed.Retaining wall work completed for 62.55
Meters (62.55m in km0/600). Earth work, GSB
and CC pavement
from Km 0/0323 to Km0/4021, from Km 0/689
to 0/9294 and CrossRoad from Km 0/328 to
0/498 Completed
60 96% 60 96%
CC drain, body wallsand parapet wallsfor one CD work is
not done.
8
NCRMP/B-W/ AP/RHB/PRED/03/
Atchutapuram /009
R H B 26.09
07.03.2013 06.09.13
06.06.13Earth
work,CCRoad
(26.22%)
06.08.13CC Road(70.81%)
06.09.13Shouldersand Roadfurniture
11 Y 2 - 2
8 4
Road from R&B Roadto Vadapalem 450 26.09 07.03.13
Shoulders and CC Roadcompleted from KM0.000 to KM 0.4244
26 100% 26 100% Completed
138 73%
06.10.13Earthwork
,Pipeculver
ts,GSB( 35.8%)
06.04.14WBM Gr-II,Gr-III
andshoulders
& CCPavement( 72.6%)
06.06.14BT andRoad
furniture( 100%)
6
NCRMP/B-W/ AP/RHB/PRED/03/
Payakaraopeta /005
R H B 189.59
07.03.2013 06.06.14
Page 35 of 193Page 35 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 37/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 9
11 to 40% 20
41 to 70% 7
≥ 71% 2
Completed 6
Works Not Started 14
Works Deleted 3
Total No of works 61
Abstract Status of NCRMP Works in Srikakulam Districtas as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 38/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Y 2 - 0
0 1
Construction of CS atKollipadu 112.03 Completed 112 100%
2 Y 2 - 0
0 2
Construction of CS at
Runku112.03 Completed 112 100%
3 Y 2 - 0
0 5
Construction of MPCSin Amalapadu
Resanctioned, Notstarted 0
4 Y 2 - 0
0 6
Construction of MPCSin Angavanipeta 86.4 SBC sample
collected for testing 0 0%
5 Y 2 - 0
0 7
Construction of MPCSin Ch.Batasalavanipeta DELETED
6 Y 2 - 0
0 8
Construction of MPCSin Chintavanipeta DELETED
7 Y 2 - 0
0 9
Construction of MPCSin U.Narisingapally 86.4 Not started 0 0%
8 Y 2 - 0
1 0 Construction of MPCS
in Bypalli(Type C)
117.38
PCC for Footings,footings, pedestalsand columns up to
bottom of plinthbeam are
completed, Back filling in foundation
is in progress.
25 21%
9 Y 2 - 0
1 1 Construction of MPCS
in Chinavanka(Type C)
119.1
PCC, Footings,Columns below
plinth levelcompleted.
Backfilling infoundation is in
progress.
19 16%
10 Y 2 - 0
1 2 Construction of MPCS
in Chinakotturu(Type A)
89.21
PCC, Footingscompleted. Columns
upto stilt floorcompleted. Plinth
beam reinforcementand back filling is in
progress.
14.5 16%
11 Y 2 - 0
1 3 Construction of CS in
Chinajuttuvanipalem(Type A)
DELETED
3
NCRMP/B-W/ AP/MPCS/PRED/01/
V.Kotturu/004 M P C S 422.27
9.03.13 8.09.14
Progress of work is behind the mile
stones.Contractor has to
speed up thework to achivethe progress.
8.11.13Ground
Floor PlinthLevel of all
works
(24.34%)
8.04.14Casting of all slabs of all works
(59.64% )
8.09.14Competitionof all works
(100% )
58.5 18%
100%
2
NCRMP/B-W/ AP/MPCS/PRED/01/
V.Kotturu/003 M P C S 475.07
09.03.13 08.09.14
08.11.13Ground
Floor PlinthLevel of all
works(28.72%)
08.04.14Casting of all slabs of all works
(65.27% )
08.09.14Competitionof all works
(100% )
0 0%
1
NCRMP/B-W/ AP/MPCS/PRED/01/
Santhabommali
/005
M P C S 224.07
17.10.11
EOATapproved
up to04.09.13
16.03.12Ground
Floor PlinthLevel of all
works
Length(Mts)
AGG of work
(Lakhs)
Date of commencementof work
16.08.12Casting of first floorroof slabs
of all works
16.01.13Competitionof all works
(100% )
Nov-11
Status of NCRMP works in Srikakulam District as on 31.12.2013
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t e
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o d e
Name of the Work
Total of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons fornon-started
works
TPQAobservation
Stage of work
of work done
in
% of work done
for thework
224.00
Page 37 of 193Page 37 of 193
te Milestone/ Financial Targets
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 39/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG of work
(Lakhs)
Date of commencementof work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t e
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work
Total of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons fornon-started
works
TPQAobservation
Stage of work
of work done
in
% of work done
for thework
4
NCRMP/B-W/ AP/MPCS/PRED/01/
Ranastalam /008
M P C S 88.75
15.03.13 14.03.14
14.09.13Ground
Floor PlinthLevel of all
works(21%)
14.2.14Casting of all slabs of all works(67% )
14.06.14Competitionof all works
(100% )
12 Y 2 - 0
1 8 Construction of MPCS
in Kommaravanipeta(Type A)
88.75 15.03.13
Earth work excavation, PCC,
footings, Columnsup to bottom
completed. Sand fillin foundation is in
progress
14 16% 13 15%
Site is handedover to thecontractor. Butthe he started theearth work excavation in themonth of August.
Progress of work is behind the milestones.Contractor has tospeed up thework to achivethe progress.
13 Y 2 - 0
1 9 Construction of MPCS
in CH.Kovvada(Type C)
121.73 Not started 0 0%
14 Y 2 - 0
2 0 Construction of MPCS
in Donipeta(Type A)
90.23
Earth work excavation
completed, PCC forfootings is in
progress.
1.85 2%
15 Y 2 - 0
2 1 Construction of MPCS
in Pothayyapeta(Type B)
84.67Earth work
excavation is inprogress.
0.6 1%
6
NCRMP/B-W/ AP/MPCS/PRED/01/Kavati/011
M P C S 80.83
20.03.13 19.03.14
19.08.13Ground
Floor Plinth
Level(28.51%)
19.12.13Casting of all slabs.
(60.23% )
19.03.14Competitionof all works
(100% )
16 Y 2 - 0
2 3 Construction of MPCS
in Ch.Karrivanipalem
(Type B)
80.83 15.08.13 Earth work is inprogress 1 1% 1 1%
Site is handedover to thecontractor. Butthe her started
the earth work excavation in themonth of August.
Progress of work is behind the milestones.Contractor has to
speed up thework to achivethe progress.
7
NCRMP/B-W/ AP/MPCS/PRED/01/
Sompeta/012 M P C S 88.78
15.03.13 14.03.14
19.08.13Ground
Floor PlinthLevel
(33%)
19.12.13Casting of all slabs.(67% )
19.03.14Competitionof all works
(100% )
17 Y 2 - 0
2 4 Construction of MPCS
in Ramayyapatnam(Type B)
88.78 15.03.13
PCC completed,Footings completed,
Columns uptobottom of plint
beam and sand fillin foundation is in
progress.
12 14% 5.5 6%
Progress of work is behind the milestones.Contractor has tospeed up thework to achivethe progress.
18 Y 2 - 0
2 5
Construction of MPCSin Metturur (Type D) 119.775 15.03.13
PCC for Footings,footings, pedestalsand columns up to
bottom of plinthbeam are
completed, Back filling in foundationand RR Masonary is
in progress.
23 19%
19 Y 2 - 0
2 6 Construction of MPCS
in Nuvvalarevu (TypeD)
119.775 Not started 0 0%
Site is handedover to the
contractor. Thecontractor has tostart the work.
8NCRMP/B-W/ AP/MPCS/
PRED/01/ V.Kotturu / 013
M P C S 239.55
15.03.13 14.06.14
14.09.13
GroundFloor PlinthLevel of all
works(22.97%)
14.02.14Casting of all slabs of all works(52.58%)
14.06.14Competitionof all works
(100%)
23 10%
Progress of behind the mile
stones.Contractor has to
speed up thework to achivethe progress.
2.45 1%5
NCRMP/B-W/ AP/MPCS/PRED/01/
Ranasthalam/009
M P C S 300.24
26.10.13 25.01.15
25.04.14Ground
Floor PlinthLevel of all
works
25.09.13Casting of all slabs of all works
(% )
25.01.15Competitionof all works
(% )
Page 38 of 193Page 38 of 193
t e Milestone/ Financial Targets e
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 40/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG of work
(Lakhs)
Date of commencementof work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work
Total of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons fornon-started
works
TPQAobservation
Stage of work
of work done
in
% of work done
for thework
9
NCRMP/B-W/ AP/MPCS/PRED/01/
Santhabommalli /014
M P C S 116.89
20.03.13 19.03.14
19.08.13Ground
Floor PlinthLevel
(21%)
19.12.13Casting of all slabs.
(% )
19.03.14Competitionof all works
(100% )
20 Y 2 - 0
2 7 Construction of MPCS
in R.Sunnapally(Type C)
116.89 20.03.13 Earth work is inprogress 2 2% 2 2%
The contractorstarted the earthwork excavationin the month of July.
21 Y 2 - 0
2 8 Construction of MPCS
in Calingapatnam(Type D)
125.78 15.03.13
Stilt floor slab andColumns below 1st
floor slab arecompleted,
reinforcement for1st floor is in
progress.
52 41%
22 Y 2 - 0
2 9 Construction of MPCS
in Bandaruvanipeta(Type D)
125.78 15.03.13
Stilt floor slab andColumns below 1st
floor slab arecompleted.
45 36%
11
NCRMP/B-W/ AP/MPCS/PRED/01/Polaki/018
M P C S 92.48
15.03.13 14.03.14
14.08.13Ground
Floor PlinthLevel
(15%)
14.12.13Casting of all slabs of all works(68% )
14.03.14Competitionof all works
(100% )
23 Y 2 - 0
3 0 Construction of MPCS
in Akkuvaram (TypeC)
92.48 15.03.13
PCC completed,footings completed,Columns upto plintbeam is completed.Reinforcement forplinth beam is in
progress.
20 22% 20 22%
Progress of work is behind the milestones.Contractor has tospeed up thework to achivethe progress.
24 Y 2 - 0
3 1 Construction of MPCS
in Jaganadhapuram(Type B)
89.43 15.03.13
PCC, Footings & columns below
plinth beam and RR masonry underplinth beam are
completed and back filling is in progress.
21.5 24%
25 Y 2 - 0
3 2 Construction of MPCS
in Kottamukkam (Type A)
88.72 15.03.13
PCC, Reinforcement,footings, columnsupto stilt floor, RR
Masonary work andplinth beamcompleted.
26 29%
26 Y 2 - 0 3 6 Construction of MPCS
in Patadibbalapalem(Type A)
89.91
Footings, columns
below plinth beamcompleted. Filling in
foundation is inprogress.
19 21%
27 Y 2 - 0
3 7 Construction of MPCS
in Bontalakoduru(Type B)
86.87 Earth work Completed 2 2%
12%
Progress of work is behind the mile
stones.Contractor has to
speed up thework to achivethe progress.
39%
12
NCRMP/B-W/ AP/MPCS/PRED/01/
Ranastalam /016
M P C S 178.26
15.03.13 14.06.14
Progress of work is behind the mile
stones.Contractor has to
speed up thework to achivethe progress.
13
NCRMP/B-W/ AP/MPCS/PRED/01/
Etcherla/017A M P C S 176.94
03.04.13 02.07.14
02.10.13Ground
Floor PlinthLevel of all
works(29.19%)
02.03.14Casting of all slabs of all works
(63.11% )
02.07.14Competitionof all works
(100% )
03.04.13
14.09.13Ground
Floor PlinthLevel of all
works(26.01%)
14.2.14Casting of all slabs of all works
(58.56% )
14.06.14Competitionof all works
(100% )
47.50 27%
Site is handedover to the
contractor. Butthe contractor
started the earthwork excavationin the month of
June
21
10
NCRMP/B-W/ AP/MPCS/PRED/01/Gara/015
M P C S 251.57
15.03.13 14.06.14
14.09.13Ground
Floor PlinthLevel of all
works(28.43%)
14.2.14Casting of all slabs of all works
(59.88% )
14.06.14Competitionof all works
(100% )
97
Page 39 of 193Page 39 of 193
t t e Milestone/ Financial Targets e l f ff
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 41/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG of work
(Lakhs)
Date of commencementof work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t
DFC
esto e/ a c a a gets(%)
Sl.Noof
work P r o j e c t c o
d e
Name of the Work
Total of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons fornon-started
works
TPQAobservation
Stage of work
of work done
in
% of work done
for thework
14
NCRMP/B-W/ AP/RCS/PRED/01/
Santhabommali /003B
R C S 87.34
19.10.13 18.10.14
18.03.14Earth work,GSB,Bridgefoundation
18.07.14WMM, CCroad & Bridge substrecture
18.10.14BT, road
furnishes,Bridge superstructure & Approach
Slabs. 100%
28 Y 2 - 1
4 4 Road from NH5 to
T.Sasanam inSanthabommali (M) inSrikakulam District
87.34 Work not started 0 0% 0 0%
29 Y 2 - 1
4 5 Road from
Chinnavanka toGopaladavooru
3675 63.32 Earth work completed 1 2%
30 Y 2 - 1
4 6 Road from MN peta
Road to Kondavooruand to CS
500 23.50 Earth work completed 1 4%
31 Y 2 - 1
4 7
Road from R&B Roadto S.J. Puram 265 19.13
Earth work, GSB & Keywalls completed,Concreting for road
is in progress.`
3 16%
32 Y 2 - 1
4 8
Road from KothapetaRoad to Sainooru CS 785 30.10
Earth work completed, CD
Works completed.5 17%
16
NCRMP/B-W/
AP/RCS/PRED/01/Santhabommali
/008
R C S 93.09
15.03.13 14.12.13
14.07.13Earth work,GSB(18.18%)
14.10.13WBM GR-II
&III, CDworks andCCpavement(81.46%)
14.12.13 BT
and roadfurnishes allworks
(100% )
33 Y 2 - 1 5
0Borubhadra -Meghavaram Road toM. Maruvada
2000 93.09 15.03.13
Earth work & Culverts, GSB, CCroad , WBM Gr-IILayer completed
50 54% 50 54%
Progress of work is behind the mile
stones.Contractor has tospeed up the
work to achivethe progress.
34 Y 2 - 1
5 1 Road from R&B road
to Kothapalem cycloneshelter
35 Y 2 - 1
5 2 Road from NABARD
road to Pukkalapalemin Kavity mandal inSrikakulam district
36 Y 2 - 1
5 3 Road from
Kusumapuram toKalingapatnam
37 Y 2 - 1 5 4 Yeeramukkam – Rati
R&B road toDunnavooru
350 18.79 4 21%
38 Y 2 - 1
5 5 Road from
Yeeramukkam – RatiR&B road Geddavooru
600 34.96 8 23%
39 Y 2 - 1
5 6 Road from R&B road
Ganguwada to road toSigalaputtuga
875 39.19 5 13%
40 Y 2 - 1
5 7
Road from R&B roadto Akkuvaram 585 30.41
CC road completed,Graverl shoulder
laying in progress29.5 97%
Work not started
46.5 38%
Progress isbehined the
approved milestones.
Road widening is inprogress, earth
work, culverts is inprogress.
17
NCRMP/B-W/ AP/RCS/PRED/01/
Mandasa/009 R C S 200.18
19.10.13 18.10.14
18.03.14Earth work,GSB 50%,CD works
of all works
18.07.14WMM, CC
road,remaining50% of CDworks, of all works
14.03.14 BTand road
furnishes allworks
(100% )
15
NCRMP/B-W/ AP/RCS/PRED/01/
V.Kottoru/001 R C S 136.07
15.03.13 14.03.14
14.08.13Earth work,
Pipeculverts,GSB and CC
Pavementsof all works(44.97%)
14.12.14WBM Gr-II,Gr-III, CDworks andshoulders
of all works(70.33% )
14.03.14 BTand Road
furniture of all works(100% )
15.03.13 10 7%
Working estimateis prepared forchanging theWBM layer toWMM layer,approval isawaiting.
18
NCRMP/B-W/ AP/RCS/PRED/01/
Mandasa/010 R C S 123.36
15.03.13 14.03.14
14.08.13Earth work,GSB of all
works(20.72%)or 12.15%
14.12.14WMM, CCPavement
& CDworks,
shouldersfor allworks
(88.36% )or 38.09%
14.03.14 BTand road
furnishes allworks
(100% )
15.03.13
Page 40 of 193Page 40 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 42/194
t t e Milestone/ Financial Targetsde Total of % of% of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 43/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG of work
(Lakhs)
Date of commencementof work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y
A g r e e m e n
t
A m o u n
t
( L a k h s ) /
D a t
DFC
(%)Sl.No
of work
P r o j e c t c o
d e
Name of the Work
Total of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons fornon-started
works
TPQAobservation
Stage of work
of work done
in
% of work done
for thework
23
NCRMP/B-W/ AP/RHB/PRED/01/
Santhabommali /001B
R H B 216.17
23.03.13 22.09.14
22.10.13Earth work,GSB,Bridgefoundation.(53.16%)
22.04.14WBM Gr-II& III,Bridge Substructure(79.89%)
22.09.14 BTraod
furnishesBridge superstructure & Approach
slabs (100%)
53 Y 2 - 2
7 0 Road from DPN road
to Gangaram Villagevia Palatalagam,Srikrishnapuram
3700 216.17 23.03.13
Road widening & Subgrade from
0/000 to Km 3/200,Bridge execavation
completed, CDworks in progress.
42 19% 42 19%Bridge re design
approval isawaiting.
24
NCRMP/B-W/AP/RHB/PR
ED/01/Polaki/005
R H B 75.15
30.04.11
29.10.12(31.05.13
)
29.07.11Earth work & CDworks
29.10.11WBM Gr-II,Gr-III andshouldersworks
29.01.12 BTraodfurnishes allworks(100% )
54 Y 2 - 2
7 1 Road from R&B road
Edulavalasa – Killam toJonnam viaTalasamudram
2700 76.10 30.04.11 Completed 0% 100% Completed
55 Y 2 - 2
7 2 R&B road Mobagam to
Dubbakavanipeta viaGajapathinagaram
2750 100.40 30.04.11 Completed 0% 100% Completed
56 Y 1 - 0
9 8 Road from
Talasamudram to DolaRegulator
1600 43.00 30.04.11 Completed 0% 100% Completed
57 Y 2 - 2
7 3 DPN road to DL Puram
jn. via Koduru,Magathapadu,
Guppidipeta
2350 108.92
l , -II completed, CCRoad of length
150mts is inr r
53 49%
58 Y 2 - 2
7 4
Guppidipeta road toChinnakoviripeta 1340 55.97
Culverts, WBM GR-II completed. WBMGR-III collection is
in progress.
24.5 44%
59 Y 2 - 2
7 5 K.C. Road to
Rajarampuram via Ampalem Revuamplam
0.9 57.13
Culverts, WBM GR-II laying
completed. CC Roadis in progress.
21 37%
60 Y 2 - 2
7 6
KC road to Amplam(via) Urjam, Nandigam 1.6 49.73
Culverts, CCpavement, WBM Gr-
II completed16 32%
28
NCRMP/B-W/ AP/Br/R&B/01/Uppugedda
/002 R
& B -
B r
119.5617.12.10
16.06.2012 EOAT
approvedup to
30.07.13
Completionof
foundationup to sill
level.6 Months
Completionupto below
the deck slab. 12Months
Completionof entire
work includingapproaches18 Months
61 Y 2 - 4 3 8
Construction of Highlevel bridge acrossUppugedda at KM 7/6
of Srikakulammuncipal limits toPukkalapeta viaKillipalem
119.56 Aug-12 Completed 119.5 100% 119.5 100% Completed
25
NCRMP/B-W/AP/RHB/PR
ED/01/Polaki/006
14530.04.11
29.04.12(31.05.13
)
4 monthsEarth work,GSB & CD
works
29.12.11WBM Gr-II,Gr-III andshouldersw
orks
29.04.11 BTraod
furnishes allworks
(100% )
26
NCRMP/B-W/
AP/RHB/PRED/01/Polaki/007
R H B 164.92
20.03.13 19.03.14
19.08.13Earth work,GSB of all
works(13.15%)
19.12.13WBM Gr-II& III, CDworks, CCpavement
of all works(78.91%)
19.03.14 BTraod
furnishesBridge super
structure(100% )
R H B
20.3.13 77.5 47%
Progress of work
is behind theapproved mile
stone.
27
NCRMP/B-W/ AP/RHB/PRED/01/Polaki/008
R H B 106.67
25.03.13 24.03.14
24.08.13Earth work,GSB of all
works(7.3%)
24.12.13WBM Gr-II& III, cd
works, CCpavement
of all works(80.45%)
24.03.14 BTraod
furnishesBridge super
structure(100% )
25.03.13 37 35%
Progress of work is behind the
approved milestone.
Page 42 of 193Page 42 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 44/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 6
11 to 40% 7
41 to 70% 6
≥ 71% 3
Completed 3
Works Not Started 1
Total No of works 26
Abstract Status of NCRMP Works in East Godavari as on 31.12.2013
Status of NCRMP works in East Godavari as on 31 12 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 45/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1
NCRMP/B-W/ AP/MPCS/PRED/04/
Uppalaguptam /002
M P C S 105.65
17.10.2011 16.07.13 1 Y 2 - 0
6 2 Construction of CS at
Pedaraghavulapeta of Uppalaguptam Mandal
CycloneShelter 105.65 24.02.12 Completed 95 90% 95 90%
Workingestimate is
beingprepared.
2 Y 2 - 0
7 4 Construction of CS at
Kesavadasupalem(Type D)
CycloneShelter 120 No jungle Clerence
Completed. 3.6 3%
Site is handed over on29-06-13. Contractorhas not started the
work until now.
3 Y 2 - 0
7 5
Construction of CS atPallipalem (Type D)
CycloneShelter 120 12.07.13
Gravel collected forcattle
ramp,cement andsteel procured.
10 8%
4 Y 2 - 0
7 6 Construction of CS at
Padamatapalem (TypeD)
CycloneShelter 107 21.06.13
first floor roof slabcompleted,
columns work is inprogress.
49.2 46%
5 Y 2 - 0
7 7
Construction of CS atKesanapalli (Type D)
CycloneShelter 107 No jungle Clerence
Completed. 2 2%
4
NCRMP/B-W/ AP/MPCS/PRED/04/
Mamidikuduru /012
M P C S 94.00
22.04.2013 21.04.14
21.09.13GroundFloorPlinth
Level of All Works
(27%)
21.01.14Casting of
All Slabs of All Works.
(67%)
21.04.14Completion
of Allworks
(100%)
6 Y 2 - 0
7 8
Construction of CS atKaravaka (Type B)
CycloneShelter 94 No Not Yet Started Nil Nil Nil Nil
Original site isidentified in
Indiramma colony. Thevillagers wanted the
MPCS to beconstructed in place of
community hall indilapidated condition.The villagers promised
to dismantle thebuilding and hand overthe site for MPCS. But
so far, it was notdismantled. District
Collector has seen the
site and agreed inprinciple.
Suitable actionis to be takento hand over
the site.
5
NCRMP/B-W/ AP/RCS/
PRED/04/ UKothapalli /002
R C S 9.00
26.03.2013 25.12.13
25.07.13Earth
Work & CD Works
(19%)
25.10.13GSB & CCPavement
(76%)
25.12.13Shoulders
& RoadFurniture(100%)
7 Y 2 - 1
6 9 Road from R&B road
to SamanthkurruPallepalem CS
120 9 06.07.13Carting Earth
Completed.GSB isin progess
4 44% 4 44% Wok is inprogess
21.10.13GroundFloorPlinth
Level of All Works
(27%)
21.03.14Casting of
All Slabs of All Works.
(67%)
21.07.14Completion
of Allworks
(100%)
51.2 24% Work is inprogess
21.03.14Casting of
All Slabs of All Works.
(67%)
21.07.14Completion
of Allworks
(100%)
13.6 6%Progress of
work notsatisfactory
3
NCRMP/B-W/ AP/MPCS/PRED/04/
Malikipuram /011
M P C S 214.00
22.04.2013 21.07.14
21.10.13GroundFloorPlinth
Level of All Works
(27%)
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work
2
NCRMP/B-W/ AP/MPCS/PRED/04/
Sakhinetipally /010
M P C S 240.00
23.04.2013 22.07.14
Status of NCRMP works in East Godavari as on 31.12.2013
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o d e
Name of the Work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasons for non-started works
TPQAobservation
Valueof work done in
% of work done
for thework
Page 44 of 193Page 44 of 193
Milestone/ Financial Targetsd e Total
% of% of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 46/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
(%)Sl.No
of work
P r o j e c t c o
d
Name of the Work
Value of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons for non-started works
TPQAobservation
Valueof work done in
% of work done
for thework
8 Y 2 - 1
7 0 Approach Road from R
& B Road toTurupupalem CS
100 7.5 No work is not inprogess. 0.5 7%
This road is very near b
9 Y 2 - 1
7 1 Road from R & B Road
to Kesanapalli (New)CS
100 7 No Carting Earth is inprogess 1 14%
10 Y 2 - 1 7 2 Road from R & B Road
to Padamatipalem CS 1880 70.5 14.06.13
GSB and WBM Gr-II Completed.
WBM Gr-III is inprogress
54 77%
11 Y 2 - 1
7 3 Road from R & B Road
to Katrenipadu LankaCS
640 20.5 08.06.13
Road A) OGPC +Seal coat
completed fromKm. 0.000 to
0.500. Road B)GSB and CCPavement
Completed FromKm.0.000 to 0.210.
21 100%
12 Y 2 - 1 7 4 Road from R & B road
to Kesavadasupalem(New) CS
430 29.5 16.07.13
Road A) GSB andCC Pavement
completed from
Km 0.000 to 0.320.Road B) GSB andCC Pavement
completed fromKm.0.000 to 0.110.
30 100%
8
NCRMP/B-W/ AP/RCS/PRED/04/
Mamidikuduru /013
R C S 33.00
08.03.2013 07.09.13
07.05.13Earth
Work & GSB
(21%)
07.08.13CD Works &
CCPavement
(72%)
07.09.13Road
Furniture& GSB
(100%)
13 Y 2 - 1
7 5
Road from R&B roadto Karavaka CS 800 33 18.06.13
2no. Pipe CulvertCompleted. EW,Selected earth
completed fromKm.0.500 to
Km0.800
14.5 44% 14.5 44% Villagers stopthe work
9
NCRMP/B-W/ AP/RCS/PRED/04/
Katrenikona /015
R
C S 29.00
08.03.201307.09.14
07.05.13EarthWork,
GSB & CDWorks(27%)
07.08.13CC
Pavement(68%)
07.09.13Road
Furniture(100%)
14 Y 2 - 1
7 6 CC Road from main
proposed road to
Neellarevu II CS inNeellarevu
540 29 06.07.13
GSB and CCPavement
Completed fromKm. 0.000 to Km.
0.490.
29 100% 29 100%Progress of work behind
the mile stone
10
NCRMP/B-W/ AP/RCS/PRED/04/
Allavaram/016 R C S 41.00
29.04.2013 30.09.13
30.05.13Earth
Work & GSB
(27%)
30.08.13WBM & CCPavement
(68%)
30.09.13BT & RoadFurniture(100%)
15 Y 2 - 1
7 7
Road from R&B roadto Samanthakurru CS 380 41 02.06.13
Retaining wall andGSB Completed.CCRoad is in pogess
32 78% 32 78% Wok is inprogess
30.05.13Earth
Work & GSB
(21%)
30.08.13WBM & CCPavement
(81%)
30.09.13BT & RoadFurniture(100%)
50 100.00%
Progress of work is well
ahead of milestones
03.01.14WBM & CCPavement
(52%)
03.04.14BT & RoadFurniture(100%)
55.5 67% Wok is inprogess
7
NCRMP/B-W/ AP/RCS/PRED/04/Razole &
Sakhinetipalli /010
R C S 50.00
29.04.2013 30.09.13
6
NCRMP/B-W/ AP/RCS/PRED/04/
Malikipuram/00
9
R C S 85.00
04.04.2013 03.04.14
03.09.13EarthWork,GSB
(17%)
Page 45 of 193Page 45 of 193
flMilestone/ Financial Targets
(%) d e Totall f
% of% of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 47/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
(%)Sl.No
of work
P r o j e c t c o
d
Name of the Work
Value of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons for non-started works
TPQAobservation
Valueof work done in
% of work done
for thework
29.08.13Earth
Work & GSB
(23%)
29.12.13WBM, CD
Works & CCPavement
(76%)
29.03.14BT & RoadFurniture(100%)
16 Y 2 - 2
8 9 Road from R&B road
to KorukondavariGroup
1000 44.5 06.06.13 GSB completed 13.5 30%
29.08.13EarthWork &
GSB(23%)
29.12.13WBM, CDWorks & CCPavement
(76%)
29.03.14BT & RoadFurniture(100%)
17 Y 2 - 2
9 0
Road from R&B roadto Gondi Kodapa 830 49.5 12.06.13 GSB is in Progress. 14.5 29%
29.08.13Earth
Work & GSB
(17%)
29.12.13WBM, CC
Pavement & CD Works.
(58%)
29.03.13BT & RoadFurniture(100%)
18 Y 2 - 2
9 3 BT road from
Komaragiripatnam toKadadari and to CS
3500 93 09.07.13
Road A) WBM Gr-III completed
from Km 0.000 to1.050. Road B)
EW, Selected earthand GSB, WBM Gr-
III completed
42 45%
29.08.13Earth
Work & GSB(17%)
29.12.13WBM, CC
Pavement & CD Works.(58%)
29.03.13BT & RoadFurniture(100%)
19 Y 2 - 2
9 4 Road from R&B road
Samanthakurru toChakkavaripetaRameswaram
880 55 14.07.13 GSB is in Progress. 6 11%
26.09.13Earth
Work & GSB
(18%)
26.01.14WBM, CC
Pavement & CD Works.
(61%)
26.04.14BT & RoadFurniture(100%)
20 Y 2 - 2
9 5
Road from Guthenadeevi to Gogullanka 1920 94 No Sub. Grade is in
Progress. 11 12%
26.09.13Earth
Work & GSB
(18%)
26.01.14WBM, CC
Pavement & CD Works.
(61%)
26.04.14BT & RoadFurniture(100%)
21 Y 2 - 2
9 6 Road from R&B road
to RamalayampetaPallamkurru (v)
1350 61 No Sub. Grade is inProgress. 10 16%
14
NCRMP/B-W/ AP/RHB/PRED/04/
Katrenikona /016
R H B 157.00
30.03.2013 29.03.14
29.08.13EarthWork &
GSB(31%)
29.11.13WBM & CD
Works.(72%)
29.03.14BT & RoadFurniture(100%)
22 Y 2 - 2
9 7 Road from N.
Kothapalli to G.Pora inKatrenikone (v)
3500 157 No Sub. Grade is inProgress. 5 3% 5 8%
15
NCRMP/B-W/ AP/RHB/PRED/04/
Razole/020 R H B 13.00
25.03.2013 24.09.13
24.05.13Earth
Work & WBM
(100%)
24.09.13BT & RoadFurniture.(100%)
_ 23 Y 2 - 2
9 8
Road from R&B roadto Aravapalem 740 13 04.07.13 WBM Grade III
completed. 4.5 35% 4.5 35%
As per MileStone work isnot completed Agreement
period is over.
14% Progress isslow13
NCRMP/B-W/ AP/RHB/PRED/04/
Katrenikona /014
R H B 155.00
27.04.2013 26.04.14 21
30% Progress of work is slow.
12
NCRMP/B-W/ AP/RHB/PRED/04/
Allavaram/012 R H B 148.00
30.03.2013 29.03.14 48 45% Progress of work is slow
11
NCRMP/B-W/ AP/RHB/PRED/04/
Sakhinetipalli /008
R H B 94.00
30.03.2013 29.03.14 28
Page 46 of 193Page 46 of 193
AGG D fSl y AMilestone/ Financial Targets
(%) d e TotalV l f
% of % of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 48/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
(%)Sl.No
of work
P r o j e c t c o
d
Name of the Work
Value of Work
done forpackage(Lakhs)
work done for
thePackage
Reasons for non-started works
TPQAobservation
Valueof work done in
work done
for thework
16
NCRMP/B-W/ AP/Br/R&B/04/Upputeru
/014
B r i d g e
236.5925.03.2013 24.09.14
24.12.13Completio
n of Foundatio
n up to
WellCapping.(36%)
24.05.14Completionup to below
the Deck slab &
Earth work
Formationfor Approaches
.(87%)
24.09.14Completion
of entirework
includingapproaches (100%)
24 Y 2 - 4
4 3
Construction of Bridgeat Km 9/4 of
Vakalapudi - Edatamroad across Uppeteru
Yeru vagu in EGDistrict.
25 .3 4 23 6.5 9 20 .05 .1 3 Abutement
1,2,Well curb is inprogess
12 5% 12 3%Progress of
work is as permilestone
17
NCRMP/B-W/ AP/Br/R&B/04/ Pampa
Yeru-1 /015 B r i d g e
505.0026.03.2013 25.09.14
24.12.13Completio
n of Foundatio
n up toWell
Capping.(36%)
24.05.14Completionup to below
the Deck slab &
Earth work Formation
for Approaches
. (87%)
24.09.14Completion
of entirework
includingapproaches (100%)
25 Y 2 - 4
4 4
Construction of Bridgeat Km 43/10 of
Vakalapudi - Edatamroad across Pampa
Yeru in EG District.
83.74 505 13.04.13
Abutement A1,A2,Pier P1 Top well
pluging is inprogess.Pier p3,p4
Bottom wellpluging is in
progess Pier p2Well shinking is in
progess
223 44% 223 44%Progress of
work is as permilestone
18
NCRMP/B-W/ AP/Br/R&B/
04/Pampa Yeru-2 /016
B r i d g e
355.0025.03.2013 24.09.14
24.12.13Completio
n of Foundatio
n up toWell
Capping.(36%)
24.05.14Completionup to below
the Deck slab &
Earth work Formation
for Approaches
.(87%)
24.09.14Completion
of entirework
includingapproaches (100%)
26 Y 2 - 4
4 5
Construction of Bridgeat Km 43/6 of
Vakalapudi - Edatamroad across Pampa
Yeru in EG District.
50.54 355 20.05.13
Abutement 1,2,Topwell pluging is inprogess. Pier 1,2
Bottom wellpluging is in
progess
152 43% 152 43%Progress of
work is as permilestone
Page 47 of 193Page 47 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 49/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 16
11 to 40% 14
41 to 70% 10
≥ 71% 20
Completed 0
Works Not Started 23
Total No of works 83
Abstract Status of NCRMP Works in Krishna District as on 31.12.2013
Status of NCRMP works in Krishna District as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 50/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Y 2 - 1
8 9
Road from R&B roadto CS @ Ullipalem 690 43.25 28.05.13 41.00 95%
2 Y 2
- 1 9 0 Road from R & B Road
to CS atJaruguvanipalem
500 31.08 22.07.13 27.78 89%
3 Y 2 - 1
9 1
Road from R&B roadto CS @ Utagundam 290 23.00 22.07.13 21.60 94%
4 Y 2 - 1
9 2 Road from R&B road
to CS @ Ramakrishnapuram
390 21.39 28.05.13 20.80 97%
5 Y 2 - 1
9 3
Road from R&B roadto CS @ Chintakolla 1950 95.16 20.07.13 Earthwork, GSB WMM,
SDBC completed. 94.00 99%
6 Y 2 - 1
9 4 Road from R&B road
to CS @Padalavaripalem
510 30.15 04.06.13Earthwork, GSB WMM,SDBC and all CD works
completed.29.50 98%
7 Y 2 - 1
9 5
Road from R&B roadto CS @ Mandapakala 590 34.55 04.06.13
Earthwork, GSB WMM,SDBC and all CD works
completed.
33.50 97%
8 Y 2 - 1
9 6 Road from R&B road
to Ramakrishna puramR & B Road viaPathaupakali
3300 179.04 29.07.13Earthwork, GSB WMM,SDBC and all CD works
completed.163.00 91%
9 Y 2 - 1
9 7
R & B Road to CS atKothaupakali 510 39.26 29.07.13
Earthwork, GSB WMM,SDBC and all CD works
completed.38.0 97%
10 Y 2 - 1
9 8
Road from Uppu Canaldrain to CS at Nali 630 33.90 29.07.13 1000mm dia
compelted in KM 0/4. 3.0 9%
11 Y 2 - 1
9 9
Road from Nali R & BRoad to Barrankula CS 2430 99.78 29.07.13
Earth work,All CDworks,GSB ,WMM and
SDBC completed.75.0 75%
12 Y 2 - 2 0 0
From R&B road toBhavadevarapalli 230 29.85 29.07.13
Earth work,CDworks,GSB completed
from KM 0.00 to0.145.
4.9 16%
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
Milestone/Financial Targets (%)Sl.No
of work
P r o j e c t c o d e
Name of the Work
Total Value of
Work done forpackage(Lakhs)
% of work
done forthe
Package
Reasonsfor non-startedworks
TPQAobservatio
n
1
NCRMP/B-W/ AP/RCS/PRED/06/
Koduru/001 R C S 115.88
21.03.2013 20.06.14
20.09.13Jungle
clearance,earth work,scarifying,GSB,Sub
grade(25%)
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work Value of
work done in
% of work done
for thework
For thepackage,
progress of works is wellahead asper mile
stone
2
NCRMP/B-W/ AP/RCS/PRED/06/
Koduru/002 R C S 159.86
21.03.2013 20.06.14
20.09.13earth work (raod waycutting),
scarifying,GSB (27%)
20.02.14WMM, CD
works(68%)
20.06.14 Earthwork, prime coat,Tack coat, SDBC,shoulders, Roadfurniture (100%)
157.0
20.02.14WMM, CD
works(64%)
20.06.14 Earth
work, prime coat,Tack coat, SDBC,Shoulders, Roadfurniture (100%)
Earthwork, GSB WMM,SDBC completed. 111.2 96%
98%
For thepackage,
progress of works is well
ahead asper mile
stone
3
NCRMP/B-W/ AP/RCS/PRED/06/
Nagayalanka /003
R C S 211.30
23.03.2013 20.03.1420.08.13
Earth work,GSB (25%)
20.12.13WMM, CD
works(69%)
20.03.14Embankment,
Earth work, primecoat, Tack coat,
SDBC, shoulders,Road furniture
(100%)
201.0 95%
For thepackage,
progress of works is well
ahead asper mile
stone
4
NCRMP/B-W/ AP/RCS/PRED/06/
Nagayalanka /004
R C S 163.53
25.03.2013 24.06.14
For thepackage,
progress of works is asper secondmile stone
24.09.13Earth work,GSB (14%)
24.02.14WMM, CD
works(66%)
24.06.14 Earthwork, prime coat,Tack coat,SDBC,shoulders, Roadfurniture (100%)
82.9 51%
Page 49 of 193Page 49 of 193
Sl y AgreementMilestone/Financial Targets (%)
o d e Total
Value of% of
ReasonsAGG Date of% of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 51/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFCSl.No
of work
P r o j e c t c o
Name of the Work
Value of Work
done forpackage(Lakhs)
work done for
thePackage
Reasonsfor non-startedworks
TPQAobservatio
n
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work Value of
work done in
work done
for thework
13 Y 2 - 2
0 1
Road from R&B roadto CS at Pedapalem 570 37.23 29.07.13 14.0 38%
14 Y 2 - 2
0 2 Road from
Gullalamoda R&B roadto Etimoga
183 19.65 27.07.13 9.5 48%
15 Y 2 - 2
0 3
Road from R&B to CSat China Etimoga 210 33.79 25.05.13 17.0 50%
16 Y 2 - 2
0 4 Road from R & B Road
to CS at ChinaKammavaripalem
300 26.51 27.07.13 6.6 25%
17 Y 2 - 2
0 5 Road from China
Zinkapalem toGollamanda via Peda
Zinkapalem
2030 103.90 01.08.13Jungle clearance done,
No further work isgoing on.
0.5 0%
18 Y 2 - 2
0 6
Road from R&B roadto CS at Gollamanda 900 47.92 01.08.13 0.5 1%
19 Y 2 - 2
0 7
Road from ZP Road toCS at Natchugunta 300 17.31 01.08.13 0.5 3%
20 Y 2 - 2 0
8Road from KrishnaRiver to Elichetladibba
CS720 58.85 01.08.13 0.5 1%
R C S
17.10.14 21 Y 2 - 2
0 9 Road from
Domalagondi toNidamarru HW
1800 118.09 - Work not started 0.0 0%
22 Y 2 - 2
1 0
Road from R&B toInteru Cyclone Shelter 265 24.86 - Work not started 0.0 0%
23 Y 2 - 2
1 1
Road fromKammavanicheruvu
R&B road to Venkatadurgambapuram in
Machilipatnam Mandal
4100 203.77 13.04.13Earth work, GSB,WMM and SDBC
completed.180.0 88%
24 Y 2 - 2
1 2 Road from R&B RoadPedayadara toHarijanawada
1100 66.33 02.07.13 Earth work completed,CD works in progress. 7.0 11%
R C S
25 Y 2 - 2
1 3 Road from R&B Road
to Giripuram viaSathenapalem
2460 142.31 - Work not started 0.0 0%
26 Y 2 - 2
1 4
Road from R&B toGollagudem 1400 82.05 - Work not started 0.0 0%
6
NCRMP/B-W/ AP/RCS/PRED/06/
Nagayalanka /006
R C S 227.981
22.03.2013 21.06.1421.09.13
Earth work (3%)
5
NCRMP/B-W/ AP/RCS/PRED/06/
Nagayalanka /005
R C S 117.18
20.03.2013 19.06.14
19.09.13Earth work,CD works
(24%)
19.02.14Earthwork,Sub Grade,
GSB,WMM, CCpavement,CD works
(85%)
19.06.14 Earthwork, clearance,prime coat, Tack
coat,SDBC,shoulders, Roadfurniture (100%)
sub grade, all CDworks completed. GSB
work is in progress.
21.02.14Earth work,
GSB, subgrade(24%)
21.06.14 Barrowedearth, WMM,prime
coat, Tack coat,SDBC,pipe
culverts, shoulders,Road furniture
(100%)
2.0 1%
For thepackage
progress of works isslow and
behind thefirst mile
stone
Jungle clearance done,No further work going
on.
47.1 40%
For thepackage
progress of works slow
and behindthe first milestone
8
NCRMP/B-W/ AP/RCS/PRED/06/
Machilipatnam
/008
R C S 270.096
22.03.2013 21.03.14
21.08.13Earth work,
GSB,Subgrade
(13%)
7
NCRMP/B-W/ AP/RCS/PRED/06/
Kruthivennu /007
142.9418.10.2013
17.03.14Clearing
andGrubing,
Earth work.(28%)
21.12.13Earth work,GSB, Sub
grade
(23%)
21.03.14 Barrowedearth,WMM, prime
coat, Tack coat,SDBC, pipe
culverts, shoulders,RF (100%)
187.0 69%
For thepackage,
progress of works is asper secondmile stone
0 0%
17.07.14WWM,CD
work,600mm dia
pipeculverts(37%)
17.10.14 CCroad, shoulders,
Roadfurniture(100%)
25.10.14 Primecoat, Tack coat,SDBC,Shoulders,Road furniture.
(100%)
0.0 0%9
NCRMP/B-W/ AP/RCS/PRED/06/
Machilipatnam /009
224.36418.10.2013 25.10.14
25.02.14Clearing & Grubing,
Earth work,GSB (22%)
25.06.14WMM, CD
works(32%)
Page 50 of 193Page 50 of 193
Sl r y AgreementMilestone/Financial Targets (%)
o d e Total
Value of% of
ReasonsAGG Date of% of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 52/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o ry Agreement
Amount(Lakhs)/
Date
DFCSl.No
of work
P r o j e c t c o
Name of the Work
Value of Work
done forpackage(Lakhs)
work done for
thePackage
Reasonsfor non-startedworks
TPQAobservatio
n
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work Value of
work done in
work done
for thework
27 Y 2 - 2
1 5 Road from R&B Road
Karagraharam toPallipalem
630 41.49 08.08.13Earthwork, All CDworks, GSB WMM,SDBC completed.
40.0 96%
28 Y 2 - 2
1 6 Road from R&B Road
Kammavaricheruvu toKPT palem
820 62.74 08.08.13 0.5 1%
29 Y 2 - 2
1 7 Road from R&B Road
Kammavaricheruvu toMalakayalanka
450 32.50 08.08.13 0.5 2%
30 Y 2 - 2
1 8 Road from R&B Road
Pallithumalapalem toNelithippa
245 17.48 08.08.13600mm dia pipeculvert and GSB
completed.7.0 40%
11
NCRMP/B-W/ AP/RHB/PRED/06/
Koduru/004 R H B 155.096
22.03.2013 21.03.1421.08.2013Earth work,GSB (10%)
21.12.2013scarifying,clearing
andgrubbing,
GSB (18%)
21.03.2014Barrowed
earth,WMM, Primecoat, Tack coat,
SDBC, shoulders,CD works, Roadfurniture (100%)
31 Y 2 - 3
2 8
Road from R&B Roadto Narsimhapuram 3550 155.10 19.04.13
Earthwork, shoulderrs,GSB WMM ,SDBC and
all CD workscompleted.
153.5 99% 153.5 99%
Progress of work is
ahead of themile stone
32 Y 2 - 3
2 9
Road from R&B Road
to Krishnapuram2530 118.60 25.07.13
Earth work,Subgrade,GSB, all CD
works,WMM,SDBCcompleted.
100.0 84%
33 Y 2 - 3
3 0
Road from R&B roadto Pedagudumotu 1850 87.40 17.05.13
All CD works,GSB,WMM and SDBC
completed.85.0 97%
34 Y 2 - 3
3 1 Road from R&B Road
to Venugopalapuramvia Salempalem
3510 179.51 18.10.13 Jungle cleareancecompleted. 0.5 0%
R H B
35 Y 2 - 3
3 2 Road from
Salempalem R&B Roadto Gaba
1580 111.82 18.10.13 Jungle cleareancecompleted. 0.5 0%
36 Y 2 - 3
3 3
Road From Pittalankato Bavisettivaripalem 560 28.81 - Work not started 0.0 0%
14
NCRMP/B-W/ AP/RHB/PRED/06/
Koduru/007 R H B 277.29
18.10.13 17.10.14
17.03.14Jungle
clearance,earth work,
GSB,CDworks,Dia
pipe (15%)
17.07.14WMM, GSB(48.46%)
17.10.14 Earthwork, Prime coat,
Tack coat,SDBC,Shoulders,ro
ad furniture.(100%)
37 Y 2 - 3
3 4
Road from R&B Roadto Basavanipalem 5370 277.29 18.10.13 Earth work,GSB and all
CD works completed. 75.0 27% 75.0 27%
For thepackage,
progress of works is as
per first milestone
10
NCRMP/B-W/ AP/RCS/PRED/06/
Machilipatnam /010
R C S 154.21
04.06.2013 01.09.14
For thepackage,
progress of works is asper secondmile stone
Jungle clearancecompleted.Scariying
work is in progress
12NCRMP/B-W/
AP/RHB/PRED/06/
Koduru/005 R H B 206.00
22.03.2013 21.03.1421.08.13
Earth work,GSB (20%)
21.12.13WMM,CD
works(68%)
21.03.14 Earth
work, Prime Coat,Track coat, SDBC,
Shoulders,RF,GSB,CD works
(100%)
03.12.13Earth work,
GSB (7%)
03.05.14Grade III,WMM, CD
works(61%)
01.09.14 primecoat, Tack coat,SDBC,
shoulders, CCpavement, Roadfurniture (100%)
48.0 31%
185.0 90%
For thepackage,
progress of works is well
ahead asper mile
stone
13
NCRMP/B-W/ AP/RHB/PRED/06/
Koduru/006
291.0018.10.2013 17.01.15
17.04.14Jungle
clearance,scarifying,
earth work,GSB,CD
works RCCslab.
(38%)
17.09.14WMM, GSB
(79.6%)
17.01.15 Earthwork, Prime coat,
Tack coat,SDBC,Shoulders,
RF (100%)
1.0 0.34%
Page 51 of 193Page 51 of 193
Sl. r y AgreementMilestone/Financial Targets (%)
l o d e Total
Value of% of
kReasonsAGG Date of
l f% of
k
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 53/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Sl.No.of
Pkg
Package Nos.
c a t a g o ry Agreement
Amount(Lakhs)/
Date
DFCSl.No
of work
P r o j e c t c o
Name of the Work
Value of Work
done forpackage(Lakhs)
work done for
thePackage
Reasonsfor non-startedworks
TPQAobservatio
n
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work Value of
work done in
work done
for thework
38 Y 2 - 3
3 5
Road from R&B Roadto Parra chivara 800 51.58 17.07.13 39.50 77%
39 Y 2 - 3
3 6
Road from R&B roadto Pedagowdapalem 810 54.90 17.07.13 36.00 66%
40 Y 2 - 3
3 7
Road from R&B Roadto Mulapalem 660 36.05 17.07.13 31.00 86%
41 Y 2 - 3
3 8 Ganapeswaram R&B
Road toPullaiahgaridibba
1810 139.16 17.07.13
Earth work,GSB,all CDworks,WMM,SDBC
completed. CCpavement in progress.
92.0 66%
42 Y 2 - 3
3 9 Road from R&B Road
to Kammanamolu Village
530 63.75 - Work not started 0.0 0%
R H B 336.13
18.10.2013 17.01.15 43 Y 2 - 3
4 0 Road from R&B Road
to Dhanunjaya Colonyto Krishnapuram
1800 113.47 - Work not started 0.0 0%
44 Y 2 - 3
4 1
Road from R&B Roadto Nandyalavaridibba 1320 101.71 - Work not started 0.0 0%
45 Y 2 - 3 4
2Road from R&B RoadtoPedakammavaripalem
630 57.20 - Work not started 0.0 0%
46 Y 2 - 3
4 3 Road from R & B Road
to Indiramma Tank inGullalamoda
1600 114.24 29.07.13 Jungle clearance work is in progress 0.5 0.44%
47 Y 2 - 3
4 4 Construction of road
from ST colony toUppu drain in Dindi.
1260 104.43 29.07.13pipe culverts,
Subgrade,GSB work isin progress.
32.5 31%
48 Y 2 - 3
4 5
Road from Z.P.road toSorlagondi 1380 110.23 29.07.13
CD works,Earth work,SubGrade completed,GSB,WMM,SDBC From
km 0.00 to 0.860completed.
51.0 46%
49 Y 2 - 3
4 6 Road from R & B road
to MPUP School inSangameswaram
610 44.21 29.07.13
Earth work,All CDworks,GSB WMM
Completed. SDBC is inprogress.
43.0 97%
15
NCRMP/B-W/ AP/RHB/PRED/06/
Nagayalanka /008
R H B 274.69
25.03.201324.06.14
24.09.13Earth work,
GSB(20%)
For thepackage,
progress of works is well
ahead asper mile
stone
16
NCRMP/B-W/ AP/RHB/PRED/06/
Nagayalanka /009
17.04.14Jungle
clearance,scarifying,
earth work,GSB,CD
works RCCslab,Dia pip
e( 33%)
17.09.14WMM, GSB
(77%)
17.01.15 Earthwork, Prime coat,
Tack coat,SDBC,Shoulders,ro
ad furniture.(100%)
0.0 0%
24.02.13WMM,CD
works(74%)
24.06.14 Earthwork, Prime coat,track coat, SDBC,
Shoulders, roadfurniture, GSB(100%)
Earth work,GSB,all CDworks,WMM,SDBC
completed.198.5 72%
21.12.14Grade III,WMM,CDworks ,
Retainingwall (61%)
21.06.14 Primecoat, tack coat,
SDBC, CCpavement,
Shoulders, roadfurniture (100%)
127.0 34%
For thepackage,
progress of works is asper secondmile stone
17
NCRMP/B-W/ AP/RHB/PRED/06/
Nagayalanka /010
R H B 373.11
22.03.2013 21.06.1421.09.13
Earth work,GSB (7%)
Page 52 of 193Page 52 of 193
Sl. r y AgreementMilestone/Financial Targets (%)
Sl N o d e Total
Value of % of
kReasons
TPQA AGG Date of
V l f% of
k
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 54/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g o r g
Amount(Lakhs)/
Date
DFCSl.No
of work
P r o j e c t c o
Name of the Work Work
done forpackage(Lakhs)
work done for
thePackage
for non-startedworks
TPQAobservatio
n
Length(Mts)
Valueof work (Lakhs)
commencementof work
Stage of work Value of
work done in
work done
for thework
50 Y 2 - 3
4 7 Road from Matlam Z.P
road toGovindarajuladibba inKruthivennu mandal
1320 72.94 20.05.13
In KM 1/0 600mm diapipe culvert
completed, Earthwork is in progress.
13.0 18%
51 Y 2 - 3
4 8 Road from R&B road
to Amudalapalli(Pennamdibba) in
Kruthivennu mandal
2000 118.63 01.04.13 All CD works,GSB andWMM completed. 60.0 51%
52 Y 2 - 3
4 9 Seethannapalli R&B
Road to Gollagudem inKruthivennu mandal
720 51.83 01.04.13Earth work,All CDworks,GSB ,WMM
completed.25.0 48%
53 Y 2 - 3
5 0 Road from R&B Road
to Bolugondi inKruthivennu mandal
1200 77.44 01.04.13 All CD work,Earth
work,Sub gradecompleted.
28.0 36%
54 Y 2 - 3
5 1
Road from R&B Roadto Ramapuram 1370 96.05 9.11.13
CD workscompleted.Sub grade
work is in progess.17.0 17.70%
55 Y 2 - 3
5 2 Road from
Chinapandraka R&BRoad to Uppuluru
3920 271.11 9.11.13 CD works completed.GSB work in progress. 35.0 12.91%
56 Y 2 - 3
5 3
Road from B.L road toMatlam 1950 152.00 17.06.13Subgrade completed,CD and GSB works is
in progress15.0 10%
57 Y 2 - 3
5 4
Road from Interu R&Broad to Parvathipuram 3054 309.90 20.08.13 Earthwork completed 22.0 7%
58 Y 2 - 3
5 5 Road from R&B road
Thallapalem toPallipalem
850 335.16 20.12.13 jungle cleareance,earth work GSB is in
progress.9.0 3%
59 Y 2 - 3
5 6 Road from R&B road
at Satravapalem toJonnalavarimodi
3000 170.58 20.12.13
jungle,earth work Scrifying Material
collected for CD works,10, 20 & 40mm
Gradiation test done.
7.0 4%
13.02.14 ,GSB,WMM
, CD works,earthwork,prime coat,
tack coat,SDBC,
shoulders,retaining
wall (85%)
13.06.2014earthwork, primecoat, tack coat,
SDBC, shoulders,road furniture
(100%)
126.0 39%
Over allpackage of
works is
behind thesecond mile
stone
18
NCRMP/B-W/ AP/RHB/PRED/06/
Kruthivennu /011
R H B 320.861
14.3.201313.06.14
13.09.13Earth work,
GSB, WMM(21%)
17.02.14WMM, CCpavement
(44%)
17.06.14 Barrowedearth, shoulders,
road furniture,Prime coat, Tack coat, SDBC , CCpavement, CDworks (100%)
52.0 14%
Over allpackage of works is as
per first milestone
19
NCRMP/B-W/ AP/RHB/PRED/06/
Kruthivennu /013
R H B 376.164
18.03.2013 17.06.14
17.09.13Earth work,Sub grade,Barrowed
earth, GSB(12%)
25.02.14Sub gradeGSB, CC
Pavement(83%)
25.06.14 Earthwork, shoulders,road furniture,
Prime coat, Tack coat, SDBC 100%
37.0 8%
Over allpackage of
works isbehind thefirst mile
stone
20
NCRMP/B-W/ AP/RHB/PRED/06/
Kruthivennu /014
R H B 461.90
26.03.2013 25.06.14
25.09.13Earth work,
CD work (26%)
21
NCRMP/B-W/ AP/RHB/PRED/06/
Machilipatnam
/016
R H B 505.81
18.10.13 18.04.15
18.05.14clearance,scarifying,embanckm
et,Earthwork,Bored
cast,HYSDsteel infoundation.
(29%)
18.11.14Embankme
t Sub-gread,
GSB,WMM,Sand filling,
M20levellingcourse,
piles caps,
Abutments,Piers, Bedblocks etc,HYSD Steel
in substruture.(68%)
18.04.15 Primecoat, Tack coat,
SDBC, Shoulders,walls, pedestals,T.beam & slab,approach slab,
Wearing course,Revetment, Masticpad, Filter media,
Abutments, Weep
holes, HYSD Steelin super struture,Postts,painting,sto
ne revetment,Neoprene
bearings, CDworks. (100%)
16.0 3%
Over allpackage of
works isbehind thefirst mile
stone
Page 53 of 193Page 53 of 193
Sl. r y AgreementMilestone/Financial Targets (%)
Sl No o d e Total
Value of % of
orkReasons
TPQA AGG Date of
Val e of% of
ork
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 55/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g o r g
Amount(Lakhs)/
Date
DFCSl.No
of work
P r o j e c t c o
Name of the Work Work
done forpackage(Lakhs)
work done for
thePackage
for non-startedworks
TPQAobservatio
n
Length(Mts)
Valueof work (Lakhs)
commencementof work
Stage of work Value of
work done in
work done
for thework
60 Y 2 - 3
5 7
Road from R&B roadto Kamsalipalem 1155 67.80 11.12.13
Scarifying, earthwork is in progress, GSB
Gradiation test done,Rcc pipes collected.
Material 20mm
30.0 44%
R H B
61 Y 2 - 3
5 8 Road from Gokavaram
R&B road tosathenapalem
1200 64.49 12.12.13 Work not started 20.0 31%
62 Y 2 - 3
5 9 Road from R&B road
Jonnalavanipalemvuchalvanipalem via
Thallapalem
1200 55.07 12.12.13 Jungle cleareancecompleted. 0.5 1%
63 Y 2 - 3
6 0 Road from
Pedapatnam R&B roadto Sajjalavaripalem
910 70.34 12.12.13 Jungle cleareancecompleted. 0.0 0%
R H B
64 Y 2 - 3
6 1 Road from
Thallapalem R&B roadto Beach area
1200 83.84 12.12.13Jungle
cleareance,Scarifyingwork completed.
1.0 1%
65 Y 2 - 3
6 2 Road from
Pedapatnam R&B roadThallapalem
600 48.84 12.12.13 Jungle cleareancecompleted. 0.0 0%
66 Y 2 - 3 6 3 Road from R&B
Potlapalem Road toChinapothepalli
455 37.25 27.11.13
Material test done for10 & 20mm, sand andGSB. GSB work is in
progress.5.0 13%
R H B
17.01.15 67 Y 2 - 3
6 4
Road from R&B roadto Marridibba 2200 119.60 27.11.13 GSB, 600mm dia pipe
culvert is in progress. 10.0 8%
68 Y 2 - 3
6 5 Pedapatnam R&B
road to Vannaruvillage
1800 67.21 - Work not started 0.0 0%
69 Y 2 - 3
6 6 Road from Gokavaram
R&B road to Vodarevupalem
1060 50.90 25.07.13
Earthwork,All CDworks, GSB, WMM,SDBC, CC pavment
Completed.
48.6 95%
70 Y 2 - 3 6 7 Road from Gokavaram
R & B road toBaduguvaripalem 470 35.07 25.07.13
Earthwork,All CDworks,GSB WMM
Completed from km
0.312 to 0.470 and CCpavment work is inprogress from km
0.312 to 0.470
21.6 62%
71 Y 2 - 3
6 8 Road from R&B Road
Thallapalem toRayapalli
470 29.49 25.07.13
Earth work,GSB,450mm pipe culver
completed and WMM2nd layer in progress.
15.8 53%
72 Y 2 - 3
6 9 Manginapudi R&B
Road toPathareddypalem
515 39.55 25.07.13Earthwork, All CDworks,GSB,WMM,SDBC completed.
31.7 80%
22
NCRMP/B-W/ AP/RHB/PRED/06/
Machilipatnam /017
187.3518.10.2013 17.01.15
17.04.14Clearing & Grubbing,Earth work,
GSB.(10%)
17.09.14Grade III,WMM,CD
works, Diapipe
culverts,span RCC box
culvert.(69%)
17.01.15 Primecoat, Tack coat,SDBC,shoulders,road furniture.
(100%)
50.5 27%
Over allpackage of works is as
per first milestone
0.49%202.803
18.10.2013 17.01.15
24
NCRMP/B-W/ AP/RHB/PRED/06/
Machilipatnam /019
224.07918.10.2013
17.04.14Jungle
clearance,scarifying,
earth work,GSB. (5%)
17.09.14Grade III,WMM,CD
works, Diapipe
culverts(22%)
23
NCRMP/B-W/ AP/RHB/PRED/06/
Machilipatnam /018
17.04.14Clearing & Grubbing,Earth work,
GSB.(11%)
. .Gr-III,
WMM,CDworks, Dia
pipeculverts,
span RCCbox
culvert.59%
17.01.15 Primecoat, Tack coat,
SDBC,CCpavement,
shoulders, roadfurniture. (100%)
1.0
17.01.15 Primecoat, Tack coat,SDBC,shoulders,road furniture.
(100%)
15.0 7%
Over allpackage of works is as
per first milestone
25
NCRMP/B-W/ AP/RHB/PRED/06/
Machilipatnam /020
R H B 155.06
18.03.2013 16.04.14
For thepackage,
progress of works is well
ahead asper mile
stone
17.09.13Embankme
nt (2%)
17.02.14GSB (11%)
16.04.14Embankment, GSB,
WMM, prime coat,Track coat, SDBC,Shoulders, CCpavement, CDWorks, Road
furniture (100%)
117.6 76%
Page 54 of 193Page 54 of 193
Sl. r y AgreementMilestone/Financial Targets (%)
Sl No c o d e Total
Value of % of work
ReasonsTPQA
AGG Date of Value of
% of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 56/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g o r
Amount(Lakhs)/
Date
DFCSl.No
of work
P r o j e c t c
Name of the Work Work
done forpackage(Lakhs)
work done for
thePackage
for non-startedworks
TPQAobservatio
n
Length(Mts)
Valueof work (Lakhs)
commencementof work
Stage of work Value of
work done in
work done
for thework
26
NCRMP/B-W/ AP/MPCS/PRED/06/
Kruthivennu /001
M P C S 93.39
18.10.2013 17.10.14
17.03.14Earth work,
PCC M20
foundation,sand filling,
Brick masonary,c
oursedrubblestone
masonary.(20%)
17.07.14 VCC
columnsand lintels,
roof
beams,roof
slab,sunshaddes &
lofts, steps,bed blocks,
Brick masonary,
gradesteel.(61%)
17.10.14 Sumpand septic tank,
base slab,wall,plasttering
ceiling,coat,flooring, flooring
with polished
tandur stones,internal walls,ceramic tiles,
dadooring to walls,RCM walls,
platform, cubes,Gravel back,
pitching slopes,providing doors,
windows,ventilators,MS
railing, paintingsurface, (100%)
73 Y 2 - 0
8 5 Construction of
Cyclone Shelter atIntheru in Kruthivennu
Mandal (Type-B)
93.39 02.12.13SBC sample
collected.Exacavationwork is in progress.
2.00 2% 2.00 2.14
Progress of work is pooras per firstmile stone
27
NCRMP/B-W/ AP/MPCS/PRED/06/
Kruthivennu /002
M P C S 135.98
18.10.2013 17.10.14
17.03.14Earth
work,foundation,sand
filling, Brick masonery,pedastals&plinthbeams.(22%)
17.07.14
VRCCcolumns,lintels,
roof beams,
roof slab,sun
shaddes & lofts, steps,bed blocks,
Brick masonary,
gradesteel.(64%)
17.10.14 Sump,septic tank, base
slab, wall,plasttering ceiling,
coat, flooring,flooring with
polished tandurstones, internalwalls, ceramic
tiles, dadooring towalls, RCM walls,platform, cubes,
Gravel back,pitching slopes,providing doors,
windows,ventilators, MSrailing, paintingsurface (100%)
74 Y 2 - 0
8 6
Construction of Cyclone Shelter at
Peda Tadika inKruthivennu Mandal
(Type-C)
93.391 - Work not started 0 0% 0 0
Progress of work is pooras per firstmile stone
Page 55 of 193Page 55 of 193
Sl. r y AgreementMilestone/Financial Targets (%)
Sl No c o d e Total
Value of % of work
ReasonsTPQA
AGG Date of Value of
% of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 57/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g o Amount
(Lakhs)/Date
DFCSl.No
of work
P r o j e c t c
Name of the Work Work
done forpackage(Lakhs)
work done for
thePackage
for non-startedworks
TPQAobservatio
n
Length(Mts)
Valueof work (Lakhs)
commencementof work
Stage of work Value of
work done in
work done
for thework
75 Y 2 - 0
8 7 Construction of
Cyclone Shelter atPedapalem-I (Type-A)
100.7 01.12.13 SBC sample collected. 0 0% 20.00 6.11
Over allpackage of works is as
per first mile
stone
76 Y 2 - 0
8 8 Construction of
Cyclone Shelter atTallapalem
126.12 01.12.13SBC sample collected.Earthwork excavation
for footing in progress.5 4%
77 Y 2 - 0
8 9 Construction of
Cyclone Shelter at V.Kanuru (Type-A)
100.72 01.12.13
M30 PCC work completed for C2 & C3colomns. Measurmentslike Width, Thickness,
and length areverified.
15 15%
78 Y 2 - 0
9 0 Construction of
Cyclone Shelter atGilakaladindi (Type-
B)
95.92 Work not started 0 0%
79 Y 2 - 0 9 1 Construction of
Cyclone Shelter atPoletitippa (Type-D)
120.63 - Work not started 0 0% 0 0
28
NCRMP/B-W/ AP/MPCS/PRED/06/
Machilipatnam/003
M P C S 327.6
18.10.2013 20.01.15
19.04.14Earth
work,foundation,sand
filling, Brick masonery,pedastals&plinthbeams.(20%)
20.09.14 VRCC
columns,lintels, roof
beams,roof slab,
sunshaddes &
lofts, steps,bed blocks,
Brick masonary,
gradesteel.(81%)
20.01.15 Sump,septic tank, base
slab, wall,plasttering ceiling,
coat, flooring,flooring with
polished tandurstones, internalwalls, ceramic
tiles, dadooring towalls, RCM walls,platform, cubes,
Gravel back,pitching slopes,providing doors,
windows,ventilators,MS
railing, paintingsurface, CC
Pavement. (100%)
18.08.14 VRCC
columns,lintels,
roof beams,
roof slab,sun
shaddes & lofts, steps,bed blocks,
Brick masonary,
gradesteel.(65%)
18.11.14 Sump ,septic tank, base
slab, wall,plasttering ceiling,
coat, flooring,flooring with
polished tandurstones, internalwalls, ceramic
tiles, dadooring towalls, RCM walls,platform, cubes,
Gravel back,pitching slopes,providing doors,
windows,ventilators, MSrailing, painting
surface, CC road.(100%)
Progress of work is pooras per firstmile stone
29
NCRMP/B-W/ AP/MPCS/PRED/06/
Machilipatnam/004
M P C S 216.55
18.10.2013 18.11.14
17.03.14Earth
work,foundation,sand
filling, Brick masonery,pedastals&plinthbeams.(21%)
Page 56 of 193Page 56 of 193
Sl.o r y Agreement
Milestone/Financial Targets (%)Sl No c o
d e Total Value of
% of work
ReasonsTPQA
AGG Date of Value of
% of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 58/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g o Amount
(Lakhs)/Date
DFCSl.No
of work
P r o j e c t c
Name of the Work Work
done forpackage(Lakhs)
work done for
thePackage
for non-startedworks
TPQAobservatio
n
Length(Mts)
Valueof work (Lakhs)
commencementof work
Stage of work Value of
work done in
work done
for thework
80 Y 2 - 0 9 2 Construction of
Cyclone Shelter atKammavaricheruvu(Type-A)
98.22 - Work not started 0 0% 0 0
81 Y 2 - 0
9 3 Construction of
Cyclone Shelter at PalliTummalapalem (Type-
C)
115.48 - Work not started 0 0%
31NCRMP/B-W/ AP/Br/R&B/
06/Tallapalem/018
B r i d g e
827.1230.08.13 30.07.15
30.04.14Completion
of Foundationup to pile
caps.Diversion
road(42.23%)
30.10.14Completion
up toabutments,
precastgirders.(3.89%)
30.02.15Completion up toprecast girders,wearing coat,
revetment,approach road
(53.287%)
82 Y 2 - 4
4 7
Construction of Bridge
across salt creek inKM, 11/4-6 of Tallapalem-
Narayanapuram Roadin krishna district
45 827.12 05.10.13
Earthwork completedfor diversion road.Bed
block completed forShifiting of bailey
Bridige for diversion
20 2% 20 2%
Over allprogress of works are
with in firstmile stone.
32NCRMP/B-W/
AP/Emb/I&CAD /06/Kona/01
E m
b83
Y 2 - 4
5 7
Restoration of KonaSaline Embankment tothe original standards
from Km. 0.000 to Km.18.600 in Divi Island of
Krishna District
Work not started 0
17.10.14 Sump,septic tank, base
slab, wall,plasttering ceiling,
coat, flooring,flooring with
polished tandur
stones, internalwalls, ceramic
tiles, dadooring towalls, RCM walls,platform, cubes,
Gravel back,pitching slopes,providing doors,
windows,ventilators, MSrailing, painting
surface, CC road.(100%)
Progress of work is pooras per firstmile stone
30
NCRMP/B-W/ AP/MPCS/PRED/06/
Machilipatnam/005
M P C S 213.7
18.10.2013 17.10.14
17.03.14Earth
work,foundation,sand
filling, Brick masonery,pedastals&plinthbeams.(17%)
17.07.14 VRCC
columns,lintels,
roof
beams,roof
slab,sunshaddes &
lofts, steps,bed blocks,
Brick masonary,
gradesteel.(46%)
Page 57 of 193Page 57 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 59/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 0
11 to 40% 4
41 to 70% 10
≥ 71% 16
Completed 1
Works Not Started 2
Total No of works 33
Abstract Status of NCRMP Works in West Godavari District as on
31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 60/194
Sl.N o r y Agreement
A t
Milestone/ Financial Targets(%)
Sl.No c o d e Total
Value of W k
% of work Reasons for
TPQAL gth AGGV l
Date of comme Value
% of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 61/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g o Amount
(Lakhs)/Date
DFC of work
P r o j e c t Name of the Work
Work done forpackage(Lakhs)
done forthe
Package
non-startedworks
TPQAobservation
Length(Mts)
Valueof work (Lakhs)
ncement of
work
Stage of work of work done in
donefor thework
5
NCRMP/B-W/AP/
RHB/PRED/05/Kalla/004
R H B 92.36
08.03.2013 07.12.13
07.06.2013Earth work,GSB, Roadfurniture(25%)
07.09.2013WMM,
Schoulders(72%)
07.12.2013Prime Coat,Tack Coat,
SDBC,(100%)
10 Y 2 - 2
9 9 K.G. R&B Road to
Mamidipudi of Kalawapudi.
2080 92.36 1 5
. 0 4
. 1 3
Earth work, GSB,WMM, SDBC,
Shoulders & CD Workscompleted. Road
furniture Work is inProgress.
91.0 99% 91.0 99%Progress of
work is as permile stones.
6
NCRMP/B-W/ AP/RHB/PRED/05/
Mogaltur/006 R H B 86.04
21.03.2013 20.12.13
20.07.2013
, Cd Works,Earth work,
GranularSub base.
(29%)
20.10.2013
GranularSub base,
WMM.(71%)
20.12.2013
Prime coat,Tack coat,
SDBC,Earth work,
GSB,Shoulders
& Roadfurniture(100%)
11 Y 2 - 3
0 2 Khalipatnam R&B
Road to Khalipatnamferry
1800 86.04 1 2
. 0 4
. 1 3 Scarifying, Subgrade &
GSB completed. WMMis in Progress.
84.0 98% 84.0 98%Progress of
work is as permile stones.
12 Y 2 - 3
0 6 Narsapur Perupalem
R&B Road toMelamvaripalemPerupalem (S)
800 42.64 1 5
. 0 4
. 1 3
25.9 61%
13
Y 2 - 3
0 7 Perupalem Mollaparru
R&B road viaSattinenivarimeraka toKD Pallavapalem
730 36.34
1 5
. 0 4
. 1 3
24.1 66%
14 Y 2 - 3
0 8 Perupalem –
Dibbalapallipalem R&Broad toMellapallavapalem
1860 81.90 1 5
. 0 4
. 1 3
52.5 64%
15 Y 2 - 3
0 9 Perupalem beach R&B
Road toChallavarimeraka viaMucherlavarimeraka
1760 80.48 1 5
. 0 4
. 1 3 Earth work,Sub grade,
GSB, WMM & CDWorks completed.
Shoulders in Progress.
62.4 78%
16 Y 2 - 3
1 0
Road from PerupalemR&B road to Dindla 1600 71.26
1 5
. 0 4
. 1 3 Sub grade, GSB, CD
Works completed.WMM 1.282 KM
Completed.
44.6 63%
17 Y 2 - 3 1 1
Road from NarsapurPerupalem R&B road
to Nellipallipalem via Ambedkar colonyHarijanapeta
4600 200.64 1 5 . 0 4
. 1 3
Earth work,Sub grade,GSB, WMM & CD
Works completed.Shoulders is inProgress.
113.0 56%
18 Y 2 - 3
1 2 Road from Perupalem
R&B Road toKouruvaripalem
1800 93.41 1 5
. 0 4
. 1 3 Earth work,Sub Grade,
GSB, WMM & CDWorks completed.
Shoulders in Progress.
59.9 64%
7
NCRMP/B-W/ AP/RHB/PRED/05/
Mogaltur/008 R H B 241.36
06.03.2013 05.06.14
05.09.2013Clearing & Grubbing,
cuttingtrees,
Scarifying,sub grade,
GSB,WMM, Pipe
Culverts.(31%)
05.02.2014Earth work,
GSB,WMM,
Shoulders,Pipe
Culverts,Prime coat,Tack coat,
SDBC,Road
furniture(65%)
05.06.2014Earth work
forformation,
WMM,Shoulders,Pitching,
PipeCulverts,
Prime Coat,Tack Coat,
SDBC(100%)
Earth work, Sub grade,GSB, WMM & CDWorks completed.
Shoulders is inProgress. 164.9 68% Progress of work is as permile stones.
17.02.2014Earth work,Sub grade,
GSB,WMM,
Shoulders,Pipe
Culverts,Prime coat,Tack coat,
SDBC,Road
Furniture(53%)
17.06.2014Earth work
forformation,
WMM,Shoulders,Pitching,
PipeCulverts,
Prime Coat,Tack Coat,SDBC, CCPavement(100%)
217.5 60%
Progress of
work is as permile stones.8
NCRMP/B-W/ AP/RHB/PRED/05/
Mogaltur/009 R H
B 365.3118.03.2013 17.06.14
17.09.2013Earth work,sub grade,
GSB,WMM, Pipe
Culverts(21%)
Page 60 of 193Page 60 of 193
Sl.No o r y Agreement
Amount
Milestone/ Financial Targets(%)
Sl.Not
c o d e Total
Value of Work
% of work Reasons for
TPQALength AGGValue
Date of comme Value
% of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 62/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g Amount(Lakhs)/
Date
DFC of work
P r o j e c t Name of the Work
Work done forpackage(Lakhs)
done forthe
Package
non-startedworks
TPQAobservation
Length(Mts)
Valueof work (Lakhs)
ncement of
work
Stage of work of work done in
donefor thework
19 Y 2 - 3
1 3
Road from SP R&Broad to Pasaladeevi 2650 155.48
2 0
. 0 3
. 1 3
Earth work,Sub grade,GSB, WMM, CC
Pavement & CD Workscompleted. Shoulders
work in Progress.
114.60 74%
20 Y 2 - 3 1
4
LT R&B road to Modi 800 39.31 2 0
. 0 3 . 1
3 Earth work, Sub grade,
GSB & WMMcompleted. Shouldersis in Progress.
28.8 73%
21 Y 2 - 3
1 5 SP R&B road to
Gannabathulavaripalem of Chamakuripalem
3750 168.14 2 0
. 0 3
. 1 3
Earth work, Sub grade,GSB, WMM & CDWorks completed.
Shoulders is inProgress.
120.9 72%
22 Y 2 - 3
1 6 Road from R&B road
to SC Colony of Pedalanka
750 52.27 − Not Started 0.0 0%
Afterconcluession
aggrement somevillagers objectednot to taking upthe work. There
are someobjections in
removing coconuttrees.
23 Y 2 - 3
1 7
R&B road to RajeevNagar of Darbharevu 1600 83.89 − Not Started 0.0 0%
Some villagerswent to courtwith a requestnot to take up
the work. At thetime of DPR there
is no objectionfrom thevillagers.
24 Y 2 - 3
1 8 SP R&B road to
Pedathota of Turputallu
250 20.42 0 1
. 0 4
. 1 3 Sub grade,GSB, WMM,
SDBC & CD Workscompleted. ShouldersWork is in progress.
19.2 94%
25 Y 2 - 3
1 9
R&B road to Peta of Turputallu 920 48.39 0 1
. 0 4 . 1
3 Sub grade, GSB &
WMM completed.Shoulders work is inProgress.
16.0 33%
26 Y 2 - 3
2 0
R&B road to Pedathotaof Turputallu 380 20.77
0 1
. 0 4
. 1 3 Sub grade,GSB, WMM,
SDBC & CD Workscompleted. ShouldersWork is in progress.
19.9 96%
13.02.2014Sub grade,
GSB,WMM, CD
Works,Prime coat,Tack coat,
SDBC & otherworks.(60%)
13.06.2014Earth work,
WMM,Shoulders,Pitching,
PipeCulverts,
Prime Coat,Tack Coat,SDBC, CCPavement,CD & Other
Works(100%)
264.3 73%
Progress of
work is as permile stones.9
NCRMP/B-W/ AP/RHB/PRED/05/
Narsapur/010 R H B 362.93
14.03.2013 13.06.14
13.09.2013Clearing & Grubbing,
Cuttingtrees,
Earth work,Scarifying,
Sub grade,GSB, CDWorks.(12%)
26.02.2014Slab
culvert,WMM,CD
works,Revetment
(70%)
26.06.2014Shoulders,Prime coat,Tack coat,SDBC, CCpavement,
roadfurniture
etc.(100%)
55.1 24%
Progress of works is
behind the firstmile stone.Progress of
three works isgood and other
2 works are
not started.The contractorhas informed
that aftercompletingSDBC, he
would speedup the other
works.10
NCRMP/B-W/ AP/RHB/PRED/05/
Narsapur/012 R H B 225.73
27.03.2013 26.06.14
26.09.2013Earth work,Sub grade,GSB, Slab
culvert(36%)
Page 61 of 193Page 61 of 193
Sl.No o r y Agreement
Amount
Milestone/ Financial Targets(%)
Sl.Not
c o d e Total
Value of Work
% of work Reasons for
TPQALength AGGValue
Date of comme Value
% of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 63/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
No.of
Pkg
Package Nos.
c a t a g Amount(Lakhs)/
Date
DFC of work
P r o j e c t Name of the Work
Work done forpackage(Lakhs)
done forthe
Package
non-startedworks
TPQAobservation
Length(Mts)
Valueof work (Lakhs)
ncement of
work
Stage of work of work done in
donefor thework
27 Y 2 - 3
2 1
R&B road toGuttulavarimeraka 970 43.73
0 1
. 0 4
. 1 3 Earth work, Sub grade,
GSB & WMMcompleted. ShouldersWork is is in Progress.
35.4 81%
28 Y 2 - 3 2 2
Road from R & B Roadto Pulaparthivaripalem 2000 92.45
0 1
. 0 4
. 1 3 Earth work, Sub grade,
GSB, WMMcompleted. Shoulderswork is in Progress.
74.9 81%
29 Y 2 - 3
2 3
R&B road toPedaedigapalem 630 39.49
0 1
. 0 4
. 1 3
Earth work, Sub grade,GSB & CD Works
completed. CCPavement is in
Progress.
38.5 97%
30 Y 2 - 3
2 4
R&B road toEvanivarimeraka 190 13.94
0 1
. 0 4
. 1 3 Sub grade, CD Works
& GSB Completed.Earth Work is in
Progress
5.5 39%
31 Y 2 - 3
2 5 Road from PR Road to
Prakashpuram SC
colony of Vemuladeevi(E)
300 18.82 2 2 . 0 3
. 1 3
Earth work, Sub grade,GSB, WMM, SDBC &
CD Works completed.Shoulders Work is in
Progress.
18.6 99%
32 Y 2 - 3
2 6
Road from PR road to Vemuladeevi (E)colony (Via) Rallacheruvu of
Vemuladeevi (E)
3025 111.39 2 2
. 0 3
. 1 3 Scarifying, WMM &
SDBC Completed.Shoulders work is in
Progress.
106.5 96%
33 Y 2 - 3
2 7 Road from PR road to
Addalavarimeraka of Vemuladeevi (E)
1400 61.99 2 2
. 0 3
. 1 3
Earth work, Sub grade,GSB, WMM & CDWorks completed.
Shoulders Work is inProgress.
48.2 78%
24.12.2013WMM, CDworks andCC Road.
(80%)
24.03.2014Shoulders,
Prime Coat,Tack Coat,
SDBC,Road
furniture &
other items(100%)
154.3 81%Progress of
work is as permile stones.
11
NCRMP/B-W/ AP/RHB/PRED/05/
Narsapur/013 R H B 189.61
25.03.2013 24.03.14
24.08.2013Earth work,Sub grade,GSB (37%)
07.12.2013Earth work,
Subgrade,GSB,WMM,
Shoulders,Pipe
Culverts,Prime coat,Tack coat,
SDBC,Road
furniture(54%)
07.03.2014Earth work,
WMM,
Shoulders,Pitching,Pipe
Culverts,Prime coat,Tack coat,
SDBC(100%) 173.3 90%
Progress of work is as permile stones.
12
NCRMP/B-W/ AP/RHB/PRED/05/
Narsapur/014 R H B 192.20
08.03.2013 07.03.14
07.08.2013Earth work,Subgrade,
GSB,WMM, PiPeCulverts(23%)
Page 62 of 193Page 62 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 64/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 2
11 to 40% 0
41 to 70% 1
≥ 71% 3
Completed 0
Works Not Started 6
Total No of works 12
Abstract Status of NCRMP Works in Vizianagaram District as on 31.12.2013
Status of NCRMP works in Vizianagaram District as on 31.12.2013
Milestone/ Financial Targets e Total
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 65/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1
NCRMP/B-W
/AP/MPCS/PRED/ 02/
Pusapatirega /003
M P C S 92.11
14.03.2013 13.03.14
13.08.13Ground
FloorPlinthLevel
( 27%)
13.12.13
Casting of all slabs( 67%
Value)
13.03.14Completetion of all
works( 100% Value)
1 Y 2 - 0
4 1 Construction of MPCSin Boddugurayyapeta
(Type A)92.11 14.03.13
Earthwork Excavation,PCC for footings, RCCfootings, Back filling infoundation and Plinth
Beam completed.
Columns up to bottom of stilt floor slab, Staircaseand Ramp work are in
progress. Stilt floor slabcompleted. First floor
columns completed. Firstfloor form work in
progress.
42 46% 42 46%
Due to delay of sitehanding over by
RevuneDepartment. Date of commencement of work is 12.06.13.
Progress of work issatisfactory
2 Y 2 - 0
3 8 Construction of CS at
Barripeta H/oPathiwada in Pusapati
Rega Mandal.
Agreement has to bestarted 0%
3 Y 2 - 0
3 9 Construction of
Cyclone Shelters atKonaiapalem
Agreement has to bestarted 0%
3
NCRMP/B-W/AP/MPCS
PRED/02/Bhogapuram/
002
M P C S 99.59
30.11.13 29.11.14 4 Y 2 - 0
4 0 Construction of
Cyclone Shelter atThotaplli in
Bhogapuram Mandal
Agreement has to bestarted 0%
5 Y 2 - 1
6 0
Road from R & B Roadto Gudepuvalasa CS 440 15.75 14.03.13 Earth work in progress 0.6 4%
6 Y 2 - 1
6 1
Road from R&B roadto Kavulawada CS 150 17.5 14.03.13 Jungle clearance 0.1 1%
7 Y 2 - 1
6 2
Road from R & B Roadto Roluchappidi CS 550 21.35 14.03.13
Earth work for widening,GSB work, WBM Gr-II &
III, OGPC+Seal coatcompleted. Gravel
shoulders in prgress
19.5 91%
8 Y 2 - 1
6 3
Road from R&B roadto Chinapathiwada CS 60 4.75 14.03.13
Earth work for widening,GSB, CC Road
Completed.3.5 74%
9 Y 2 - 1
6 4
Road from R&B roadto BV peta 770 35.6 14.03.13
Earth work for widening,GSB work, WBM Gr-II &
III, OGPC+Seal coatcompleted. Gravel
shoulders in prgress
32.5 91%
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs) /
Date
DFC
Milestone/ Financial Targets(%)
Sl.Noof
work P r o j e c t c o d e
Name of the Work
Reasonsfor non-startedworks
TPQA observation
2
NCRMP/B-W /AP/MPCS/PRED/ 02/
Pusapatirega /001
M P C S 205.12
30.11.13 01.03.15
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work
Value of work
done inLakhs
% of work
done forthe work
13.08.13Earthwork,Pipe
culverts,
GSB & CCpavement
(50%)
13.12.13WBM Gr-II,Gr-III
and
shoulders(80%)
13.03.14BT andRoad
furniture( 100% )
Total Value of
Work done forpackage(lakhs)
% of work
done forthe
Package
4
NCRMP/B-W /AP/RCS/PRED/ 02/
Bhogapuram /001
R C S 94.96
14.03.2013 13.03.14 56.2 52%
Progress of work isslightly behind themile stone. It was
informed thatcontractor is
planning to speedup the progress andwanted 3 works tobe completed firstand take up theother 2 works.
Page 64 of 193Page 64 of 193
Sl.No.
P k N g o r y Agreement
AmountDFC
Milestone/ Financial Targets(%)
Sl.Nof t
c o d e
N f h W k
Reasonsfor non-
TPQA b iLength
AGG Value
Date of commen
S f k
Value of work
% of work
Total Value of
Work
% of work
d f
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 66/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
of Pkg
Package Nos.
c a t a g(Lakhs) /
Date
DFC of work
P r o j e c t Name of the Work
startedworks
TPQA observationg
(Mts) of work (Lakhs)
cementof work
Stage of work done inLakhs
done forthe work
done forpackage(lakhs)
done forthe
Package
7
NCRMP/B-W/AP/RHB/PR ED/02/Bhogap
uram /003 R H B 86.49
30.11.13 29.8.14 10 Y 2 - 2
7 7 Road connecting R&B
Road throughThotapalli Village in
Bhogapuram Mandal.
Agreement has to bestarted 0%
6
NCRMP/B-W/AP/RHB/PR
ED/02/Pusapatirega/002
R H B 64.27
19.11.13 18.08.14 11 Y 2 - 2
7 8 Road from R&B Road
to BoddugurrayyaPeta in Pusapati Rega
Mandal.
Agreement has to bestarted 0%
5
NCRMP/B-W/AP/RHB/PR
ED/02/Pusapatirega/001
R H B 300.62
30.11.13 01.03.15 12 Y 2 - 2
7 9 Road from Gumpam
R&B Road toPulligeddapalem in
Pusapati Rega Mandal
Agreement has to bestarted 0%
Page 65 of 193Page 65 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 67/194
RATE OF PROGRESS OF WORKS No of works
up to 10% 5
11 to 40% 1
41 to 70% 1
≥ 71% 1
Completed 2
Works Not Started 9
Total No of works 19
Abstract Status of NCRMP Works in Guntur District as on 31.12.2013
Status of NCRMP works in Guntur District as on 31.12.2013
Milestone/ Financial Targetsd
e Total% of% of
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 68/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
30.08.13Earthwork, GSB(5months)-13.64%
31.12.14CD
Works, CCRoad for
all works9 months -80.56%
31.03.14 BT& RoadfurnitureComplete(12 months)-100%
1 Y 2 - 2
2 6
Adavipallipalem R&BRoad to New
Tsunami Colony
(via) Krupanagarcolony, Adavi Village
751 44.20 Work notStarted 0 0%
Adjoining land owner issuednotice to not to start the
work. He has not raised anyobjection during EPTRI
inspection and gramasabha.
Departmental officersinformed that they wouldresolve the by involving
local leaders.
Progress of work is notwith in the milestones.
30.08.13Earthwork, GSB(5months)-11.02%
31.12.14CD
Works, CCRoad forall works
9 months-84.22%
31.03.14 BT& RoadfurnitureComplete(12 months)-100%
2 Y 2 - 2
2 7 Road from R&B
road toPattapupalem
770 41.26
770 mKeywalls,GSB and C.Cwork completed
38.83 94.12% NILProgress of work satisfactory
2
NCRMP/B-W/ AP/RCS/PRED/07/
Nizampatnam /005
R C S 52.43
21.03.2013 20.12.13
20.07.13Earthwork, GSB(4months)-16.81%
20.10.13WBM,WMM,CDWorks,CC
Road (7months)-48.31%
20.12.13BT & RoadfurnitureComplete (9months)-100%
3 Y 2 - 2
2 5 Road from R&B
roadKoosoorivaripalem
to Marakavaripalem
1050 52.43 03.06.13
392.6 m Keywalls , C.CWork completed
and 575mGSB work completed
25.00 48% 20.10 48% NILProgress of
work not
satisfactory.
3
NCRMP/B-W/ AP/RCS/PRED/
07/P.VPalem/001
R C S 52.43
01.11.201131.07.201
2
:Earthwork, GSB,PipeCulverts
months:Shoulders ,WBMGR-11
Months:BT,CC Pavementand Roadfurniture
4Rod from R&B road
to Alluru to Yadavapalem
1036m 66.86 01.11.2011
Work completed 52.43 100% 52.43 100% NIL FQCR
Submitted
4
NCRMP/B-W/ AP/RHB/PRED/
07/Nagaram/007
R H B 120.82
21.03.13 20.03.14
20.08.13Earthwork, GSB(5months)-24.24%
20.12.13WBM,WMM,CDWorks,CCRoad (9months)-55.52%
20.03.14BT & RoadfurnitureComplete(12months)-100%
5 Y 2 - 3
7 9 Road from R&B
Road toGattuvaripalem
2175 120.82 03.06.13
CD WorksCompleted,No Furtherwork isgoing on
10 8% 10 8% NIL
Progress of work is behindthe first milemile stone.
6 Y 2 - 3
7 6 Road from
Balavaripalem uptoGujulavaripalem
work Juststarted
7 Y 2 - 3
7 7 Road from R & B
Road to NakshatraNagar
Key walls inprogress
8 Y 2 - 3
7 8 Road from R & B
Road to AdavalaH/O Dindi.
Work notStarted
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC
(%)Sl.No
of work
P r o j e c t c o d
Name of theWork
Value of Work
done forpackage(Lakhs)
% of work
done forthe
Package
Reasons for non-startedworks
TPQAobservation
1
NCRMP/B-W/ AP/RCS/PRED/07/
Bapatla/006 R C S 93.07
01.04.2013 31.03.14 18.06.13
Length(Mts)
AGG Valueof work (Lakhs)
Date of commencementof work
Stage of work
Value of work
done inLakhs
% of work done
for thework
45.43 46%
5NCRMP/B-W/
AP/RHB/PRED/07/Bapatla/004
R H B Agreements concluded, Estimate copies and Drawings not given by Line
Deparment
Page 67 of 193Page 67 of 193
Sl.No.
Package Nos g o r y Agreement
AmountDFC
Milestone/ Financial Targets(%)
Sl.Noof c t
c o d e
Name of the
Total Value of
Work
% of work
done forReasons for non-started TPQALength
AGG Value
Date of commen Stage of
Value of work
% of work done
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 69/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
of Pkg
Package Nos.
c a t ag (Lakhs)/Date
DFC of work
P r o j e c
Work done forpackage(Lakhs)
done forthe
Package
works observation(Mts) of work (Lakhs)
cementof work
work done inLakhs
donefor thework
6
NCRMP/B-W/ AP/BR/R&B/07/ Pedapalli
/022 B r i d g e
137.0012.03.2013 11.03.14
11.07.1304
months:Completio
n of Foundations up tosill level-2.38%
11.11.13,08
months :completio
n up tobelow the
deck slab -47.85%
11.03.14 ,12 months:completion
of entirework
including
approaches-100%
9 Y 2 - 4
5 4
Reconstruction of bridge across
pedapalli drain atkm 14/60of
chandole bridge toNizampatnam inGuntur District
3 Ventsof 8m
Effectivespan
137 09.05.13
RaftConcretework Completed(M20GRADE),piers and
Abutmentwork inprogress.
23.04 19% 23.04 19% NIL
Progress of work is behindthe mile stonesas per value of
work done.
7NCRMP/B-
W/AP/BR/R&B/07/Bapatla/011 B
r i d g e
36701.12.2010
31.10.2013
6 Months:Completio
n of Foundations up tosill level
12Monthscompletion up tobelow theDeck Slab
31.10.201336 MonthsCompletionof entirework includingapproaches
10 Y 2 - 4
5 1
Reconstruction of HLB at km 2/4 of
Bapatla-Pandurangapuramacross Perali Drain
in Guntur District(y-1)
10 Vents,
8meffective
span
367 01.12.2010
Work completed 398 100% 398 100% NIL
Workingestimate
Submitted :423 Lakhs, asagainst of 398lakhs as peraggrement(Approved
estimate notgiven)
8NCRMP/B-W/
AP/BR/R&B/07 /REPALLE/020 B
r i d g e
11 Y 2 - 4 5 2
Construction of HighLevel bridge acrossRepalle main drain
at Km 4/8 of Adavuladeevi –Tummala road inGuntur District.
Work yet tobe started
9
NCRMP/B-W/ AP/MPCS/PRED/07/
Nizampatnam /003
M P C S 86.83
22.03.2013 21.03.14
21.08.135Months:Plinth Laid-20.04%
21.12.139 monthscasting of all slabs52.45%
21.03.1412 monthscompletion
of allbalance
works-100%
12 Y 2 - 0
9 7
Construction of Cyclone Shelter inSanjeev nagar of
Kothapalem (Type -B)
30mX40m 86.83 22.03.013 Work not
Started 0 0% 0 0%
The originally identified siteis changed as per thewishes of the villagescausing the delay in
handing over the site.
Valuable timeis lost. The lost
time shall bemade upwith
properplanning.
10
NCRMP/B-W/ AP/MPCS/PRED /07/REPALLE/0
05 M P C S 123.37
22.03.2013 21.03.14
21.08.135Months:Plinth Laid- 22.05%
21.12.139 monthscasting of
all slabs-51.52%
21.03.1412 monthscompletion
of allbalance
works-100%
13
Y 2 - 1
0 1 Construction of
Cyclone Shelter inLankivanidibba
(Type-D)
50mX50m 123.37 22.03.13 Earthwork
completed 0 0% 0 0% NIL
Valuable timeis lost. The lost
time shall bemade upwith
properplanning.
Agreements concluded , Estimate copies and Drawings not given by LineDeparment
Page 68 of 193Page 68 of 193
Sl.No.
Package Nos a g o r y Agreement
AmountDFC
Milestone/ Financial Targets(%)
Sl.Noof c t
c o d e
Name of the
Total Value of
Work
% of work
done forReasons for non-started TPQALength
AGG Value
Date of commen Stage of
Value of work
% of work done
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 70/194
First Second Third
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
of Pkg
Package Nos.
c a t a (Lakhs)/Date
DFC of work
P r o j e c
Work done forpackage(Lakhs)
done forthe
Package
works observation(Mts) of work (Lakhs)
cementof work
work done inLakhs
donefor thework
14 Y 2 - 0
9 8
Construction of Cyclone Shelter in
Fisherman colony of Nizampatnam
village (Type C)
Work notStarted
15 Y 2 - 0 9 9
Construction of Cyclone Shelter in
Near MRO office of Nizam Patnam(Type B)
Work notStarted
16 Y 2 - 1
0 0
Construction of Cyclone Shelter inPadamativeedhi of
Nizampatnamvillage (Type C)
Work notStarted
12NCRMP/B-W/
AP/MPCS/PRED /07/repalle/002 M
P C S
17 Y 2 - 0
9 6
Construction of Btype cyclone shelter
in Mollagunta of Katta, Repallemandal,Guntur
District
Work notStarted
18 Y 2 - 0 9
4 Construction of MPCS at Harbour of
Nizampatnamvillage
Work notStarted
19 Y 2 - 0
9 5 Construction of
MPCS atNakshatranagar of
Kothapalem
Earthwork completed
11
NCRMP/B-W/ AP/MPCS/PRED /07/NIZAMPAT
NAM/004 M P C S Agreements concluded, Estimate copies and Drawings not given by Line
Deparment
Agreements concluded, Estimate copies and Drawings not given by LineDeparment
13
NCRMP/B-W/ AP/MPCS/PRED
/07/Nizampatna
m/001
M P C S Agreements concluded, Estimate copies and Drawings not given by Line
Deparment
Page 69 of 193Page 69 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 71/194
Annexure - B
NCR Status of Works
SRIKAKULAM DISTRICT NCR STATUS AS ON 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 72/194
Sl.No.
Package No.catag
oryProject
codeWork name
Date of Issued
NCR No.
Observations Remedial meassures Present status of NCR
1NCRMP/B-W/AP/RHB/PRED/
01/Santhabommali/001B.RHB Y2-270
Road from DPN road togangaram village via
Srikrishnapuram, palatalagam17.06.13 8
Bridge portion execavated and barrication notprovided, Insisted to Provide strongbarrication.
NCR-8 Issued and the contractor/LineDepartment is requested to take suitableremedial action .
Pending
2NCRMP/B-W/AP/MPCS/PRED/
01/Polaki/018.MPCS Y2-030
Construction of Cyclone
shelter at Akkuvaram17.06.13 9
Cyclone shelter site located in School premisis
, Insistsed to provide strong barrication.
NCR-9 Issued and the contractor/LineDepartment is requested to take suitableremedial action .
Pending
3NCRMP/B-W/AP/RCS/PRED/
01/Mandasa/010.RCS Y2-157
Road from R&B road to Akkuvaram
06.07.13 11Prior permission was not taken to Waterusing for road curing purpose
NCR-11 Issued to the contractor/Linedepartment is requested to take suitableremedial action.
Pending
Page 71 of 193
VIZIANAGARAM DISTRICT NCR STATUS AS ON 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 73/194
Sl.No.
Package No. catagoryProject
codeWork name
Date of Issued
NCR No.
Observations Remedial meassures Present status of NCR
Nil
Page 72 of 193Page 72 of 193
SA A A A S C C S A S AS O 31 12 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 74/194
Sl.No.
Package No.catago
ryProject
codeWork name
Date of Issued
NCR No.
Observations Remedial meassures Present status of NCR
1 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005
RHB Y2-282 Road from R&B road toGajareddypalem
25.05.13 2 Right s ide compound wall is in obstructionKm2/652 to 2/658 approximaty 1mt.leftsideformers place is there.no contractor and linedepartment are tackling the land acqusitionissue at Km1/6 to Km1/9 (at stretch 400mts)shoulders not widths
NCR-2 Issued to take suitable remedial actionbefore proceding with further work.
NCR pending
2 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/005
RHB Y2-280 Road from R&B Roadto Rajavaram
12.06.13 3 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-3 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval
NCR pending
3 NCRMP/B-W/AP/RHB/PRED/03/Payakaraopeta/008
RHB Y2-283 Road from ZP RoadPalmanpeta toKorlayyapeta
12.06.13 4 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-4 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.
NCR pending
4 NCRMP/B-W/AP/RCS/PRED/03/S.Rsyavaram/006
RCS Y2-167 Road from R&B Roadto Revu polavaramcyclone sheler
12.06.13 5 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-5 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.
NCR pending
5 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/007
RCS Y2-168 Road from R&B Roadto Kothapatnamcyclone shelter
12.06.13 6 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-6 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.
NCR pending
6 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005
RCS Y2-165 Road from R&B road toChinanagamayyapalemcyclone shelter
12.06.13 7 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-7Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.
NCR pending
7 NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005
RCS Y2-166 Road from R&B Roadto Annavaram cycloneshelter
12.06.13 8 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-8 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.
NCR pending
8 NCRMP/B-W/AP/RHB/PRED/03/Atchuthapuram/009
RHB Y2-284 Road from R&B Roadto Vadapalem
12.06.13 9 At some locations in shoulder portion ElectricalPoles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.
NCR-9 Issued to take suitable remedial actionbefore proceding with further work. The fieldofficer are informed that they collected thedemand note from AP Transco and sent fromapproval.
NCR pending
VISAKHAPATNAM DISTRICT NCR STATUS AS ON 31.12.2013
Page 73 of 193Page 73 of 193
EAST GODAVARI DISTRICT NCR STATUS AS ON 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 75/194
Sl.No.
Package No.catago
ryProject
codeWork name
Date of Issued
NCR No.
Observations Remedial meassures Present status of NCR
Nil
Page 74 of 193Page 74 of 193
WEST GODAVARI DISTRICT NCR STATUS AS ON 31 12 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 76/194
Sl.No.
Package No.catago
ryProject
codeWork name
Date of Issued
NCR No.
Observations Remedial meassuresPresent status of
NCR
1NCRMP/B-
W/AP/RHB/PRED/05/Narsapur/010
RHB Y2-315SP R&B road to
Gannabathulavari palem of Chamakuripalem
21.12.2013 21
Field density tests were conducted at two locationson WMM layer. The observed relative Compaction
values are 97.49% & 98.26% as against theSpecified min 100%, Re Compaction is to be done.
NCR-21 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding with
further work.
Pending
WEST GODAVARI DISTRICT NCR STATUS AS ON 31.12.2013
Page 75 of 193Page 75 of 193
KRISHNA DISTRICT NCR STATUS AS ON 31 12 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 77/194
Sl.No.
Package No.catago
ryProject
codeWork name
Date of Issued
NCR No.
Observations Remedial meassures Present status of NCR
1NCRMP/B-W/AP/RCS/PRED/
06/Machilipatnam/008RCS Y2-211
Road fromkammavanicheruvu R&B roadto Venkata durgambapuram in
Bandar Mandal
12.06.13 3
Electrical poles and Service wire is in-convinent for laying of road. So please takenecessary action and For GSB and Cartingearth work Test reports are not submitted.
NCR-3 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding with
further work.
Pending
2NCRMP/B-W/AP/RCS/PRED/
06/koduru/001RCS Y2-189
Road from R&B road toCyclone Shelter @ Ullipalem
26.06.13 4E ectrica po e @ 375 is in t e s ou er
portion. So please take necessary action for
further work,
NCR-4 issued please shift the electricalpole as soon as possible for further work.
Pending
3NCRMP/B-W/AP/RHB/PRED/
06/Koduru/004RHB Y2-328
Road from R&B Road toNarsimhapuram
26.06.13 5Electrical pole 12 No's are existing in the
shoulder portion.NCR-5 issued please shift the electrical
pole as soon as possible for furthur work.Pending
4NCRMP/B-W/AP/RCS/PRED/
06/Koduru/002RCS Y2-193
Road from R&B road toCyclone shelter @Chintakolla
06.08.13 8
Deep Rain gallies are formed in shoulderportion on left side of the canal
portion @ km 0/350, 0/355, 0/360,1/340,1/350,1/450,1/470 and 1/480.They shall be rectified immediately.
NCR-8 issued please rectify Pending
5NCRMP/B-W/AP/RHB/PRED/
06/Koduru/005RHB Y2-329
Road from R&B Road toKrishnapuram
06.08.13 10Electrical poles total 15 no's are existing inshoulder portion. So please take necessary
action for further work.
NCR-10 issued please shift the electricalpole as soon as possible for furthur work.
Pending
6NCRMP/B-W/AP/RHB/PRED/
06/Nagayalanka/008RHB Y2-336
Road from R&B road to
Pedagowdapalem27.08.13 12
One electrical pole is about 0.5 mts at
chainage 0/213 inside the carriage way
NCR-12 issued please shift the electrical
pole as soon as possible for furthur work.Pending
KRISHNA DISTRICT NCR STATUS AS ON 31.12.2013
Page 76 of 193Page 76 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 78/194
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 79/194
Sl cata Project Date of NCR
SPSR NELLORE DISTRICT NCR STATUS AS ON 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 80/194
Sl.No.
Package No.catagory
Projectcode
Work nameDate of Issued
NCR No.
Observations Remedial meassures Present status of NCR
1NCRMP/B-W/AP/RCS/PRED/
09/T.P.Gudur & Muthukur/019RCS Y2-256
Road from C.S Puram toEdurupalem
13.06 .2013 12
From km 1/8 to km 2/2 no.of electric polesare to be shifted 11 no of Electric poles.4. Action shall be taken to shift water pipe
lines, two water sumps and a pressurerelease valve in the carriageway From km
1/8 to km 2/2.
NCR-12 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding with
further work.
NCR Pending
2NCRMP/B-W/AP/RCS/PRED/
09/Alluru/012RCS Y2-242
Approach road to Labbipalemin nellore dt
25.07 .2013 15Contraction joints are not provided until now,it shell be provided immediately as per MORD
Clause1501.8.3
NCR-15 Issued and the contractor/LineDepartment is requested to take suitableremedial action before proceeding with
further work.
NCR Pending
Page 79 of 193Page 79 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 81/194
Annexure - C
QC Tests conducted by TPQA
Srikakulam District Summary of QC Tests as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 82/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 10 10 0 0 0 0 10 10 0 -
2 Shoulders 0 0 0 0 0 0 0 0 0 -
3 Granular Sub Base 73 69 4 20 20 0 93 89 4 -
4 Base Course (WBM) 34 34 0 12 12 0 46 46 0 -
5 TACK COAT/SDBC/OGPC 0 0 0 0 0 0 0 0 0 -
6 Sand 118 117 1 38 38 0 156 155 1 -
7 Coarse Agreegate 121 117 4 39 39 0 160 156 4 -
8 Cement 5 5 0 2 2 0 7 7 0 -
9 Steel 6 6 0 0 0 0 6 6 0 -
10 CC cubes - sets 63 63 0 1 1 0 64 64 0 -
11 Slump test 184 170 14 86 86 0 270 256 14 -
12 Water test 20 20 0 0 0 0 20 20 0 -
13 core cutting test 0 0 0 0 0 0 0 0 0 -
Total 634 611 23 198 198 0 832 809 23 -
Tests on Materials (CD Works)
Srikakulam District Summary of QC Tests as on 31.12.2013
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
Page 81 of 193Page 81 of 193
Vizianagaram District Summary of QC Tests up to 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 83/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 0 0 0 0 0 0 0 0 0 -
2 Soil /Shoulders/SGD 0 0 0 0 0 0 0 0 0 -
3 Granular Sub Base 12 12 0 0 0 0 12 12 0 -
4 Base Course (WBM) 36 35 1 6 6 0 42 41 1 -
5 OGPC+SEAL COAT 0 0 0 36 36 0 36 36 0 _
Tests on Materials (CD Works)
6 Sand 18 18 0 8 8 0 26 26 0
7 Coarse Agreegate 24 23 1 6 5 1 30 28 2
8 Cement 1 1 0 1 1 0 2 2 09 Steel & Water 4 4 0 0 0 0 4 4 0
10 pH Values 5 5 0 2 2 0 7 7 0
11 CC cubes 16 16 0 5 5 0 21 21 0
12 Workability 27 27 0 12 12 0 39 39 0
13 Rebound hammer 0 0 0 3 3 0 3 3 0
14 Core cutting test 0 0 0 0 0 0 0 0 0
Total 143 141 2 79 78 1 222 219 3
Vizianagaram District Summary of QC Tests up to 31.12.2013
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
Page 82 of 193Page 82 of 193
Visakhapatnam District Summary of QC Tests up to 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 84/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 0 0 0 0 0 0 0 0 0 -
2 Soil - set 5 5 0 0 0 0 5 5 0 -
3 Granular Sub Base/Shoulders 40 40 0 4 4 0 44 44 0 -
4 Base Course (WBM) 107 106 1 0 0 0 107 106 1 -
5 OGPC 43 42 1 0 0 0 43 42 1 -
Tests on Materials (CD Works)
6 Sand 60 60 0 0 0 0 60 60 0 -
7 Coarse Agreegate 71 71 0 0 0 0 71 71 0 -
8 Cement 10 10 0 0 0 0 10 10 0 -
9 Steel & Water 0 0 0 0 0 0 0 0 0 -
10 pH Value 26 26 0 0 0 0 26 26 0 -
11 CC cubes 67 67 0 0 0 0 67 67 0 -
12 Workability 163 163 0 0 0 0 163 163 0 -
13 Bricks 7 7 0 0 0 0 7 7 0 -
14 Rebound Hammer 8 8 0 0 0 0 8 8 0 -
Total 607 605 2 4 4 0 611 609 2
p y Q p
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
Page 83 of 193Page 83 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 85/194
East Godavari District Summary of QC Tests up to 31.12.2013
QC tests done to the end of Last
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 86/194
Total Passed Failed Total Passed Failed Total Passed Failed
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
7 Tack CoatRate of spread of Binder 2 2 0 0 0 0 2 2 0 -
8 OGPC
Grading of 13.2mm & 11.2mm c 2 2 0 0 0 0 2 2 0 -Temperature 4 4 0 0 0 0 4 4 0 -% of BT Content 2 2 0 0 0 0 2 2 0 -
9 Seal CoatTemperature 2 2 0 0 0 0 2 2 0 -
% of BT Content 2 2 0 0 0 0 2 2 0 -10 OGPC + SC
Bitumen Extraction Test 2 2 0 4 4 0 6 6 0 -
11 ShoulderSand Replacement (FDD) 0 0 0 0 0 0 0 0 0 -
Tests on Materials CD Works (CC Pavement and Culverts)1 Fine Agreegate
Sieve Analysis 7 7 0 3 3 0 10 10 0 -Silt Content 4 4 0 3 3 0 7 7 0 -
2 Coarse AgreegateSieve Analysis 8 8 0 3 3 0 11 11 0 -Flakiness Index Value 5 5 0 3 3 0 8 8 0 -
A I V 4 4 0 3 3 0 7 7 0 -Water Absorption 4 4 0 3 3 0 7 7 0 -
3 Cement 5 5 0 2 2 0 7 7 0 -
Page 85 of 193Page 85 of 193
East Godavari District Summary of QC Tests up to 31.12.2013
QC tests done to the end of Last
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 87/194
Total Passed Failed Total Passed Failed Total Passed Failed
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
4 pH Value 9 9 0 6 6 0 15 15 0 -5 CC cubes 19 19 0 6 6 25 25 0 -6 Workability 64 64 0 4 4 0 68 68 0 -
7 Bricks 0 0 0 0 0 0 0 0 0 -8 Rebound Hammer 0 0 0 0 0 0 0 0 0 -
Tests on Materials (MPCS)1 Fine Agreegate
Sieve Analysis 5 5 0 2 2 0 7 7 0 -
Silt Content 5 5 0 2 2 0 7 7 0 -2 Coarse Agreegate
Sieve Analysis 6 6 0 1 1 0 7 7 0 -
Flakiness Index Value 5 5 0 1 1 0 6 6 0 - A I V 5 5 0 1 1 0 6 6 0 -
Water Absorption 5 5 0 1 1 0 6 6 0 -3 Cement 6 6 0 1 1 0 7 7 0 -4 pH Value 6 6 0 1 1 0 7 7 0 -5 CC cubes 10 10 0 2 2 0 12 12 0 -
6 Workability 43 43 0 4 4 0 47 47 0 -7 Bricks 0 0 0 0 0 0 0 0 0 -8 Rebound Hammer 0 0 0 0 0 0 0 0 0 -
9 Steel & Water 18 18 0 0 0 0 18 18 0 -10 SBC 1 1 0 4 4 0 5 5 0 -
Page 86 of 193Page 86 of 193
East Godavari District Summary of QC Tests up to 31.12.2013
QC tests done to the end of Last
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 88/194
Total Passed Failed Total Passed Failed Total Passed Failed
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
Tests on Materials (R&B Bridges)1 Fine Agreegate
Sieve Analysis 10 10 0 10 10 0 20 20 0 -
Silt Content 10 10 0 10 10 0 20 20 0 -2 Coarse Agreegate
Sieve Analysis 25 25 0 10 10 0 35 35 0 -Flakiness Index Value 10 10 0 10 10 0 20 20 0 -
A I V 10 10 0 10 10 0 20 20 0 -
Water Absorption 10 10 0 10 10 0 20 20 0 -3 Cement 8 8 0 5 5 0 13 13 0 -4 pH Value 12 12 0 5 5 0 17 17 0 -
5 CC cubes 30 30 0 10 10 0 40 40 0 -6 Workability 90 90 0 10 10 0 100 100 0 -
7 Bricks 0 0 0 0 0 0 0 0 0 -8 Rebound Hammer 0 0 0 0 0 0 0 0 0 -9 Steel & Water 6 6 0 0 0 0 6 6 0 -
10 SBC 3 3 0 4 4 0 7 7 0 -
Total 575 575 0 178 178 0 753 753 0 0
Page 87 of 193Page 87 of 193
West Godavari District Summary of QC Tests as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 89/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 0 0 0 0 0 0 0 0 0 -
2 Shoulders 0 0 0 0 0 0 0 0 0 -
3 Sub Grade 85 84 13 0 0 0 85 84 13 -
4 Granular Sub Base 152 128 24 2 2 0 154 130 24 -
5 Base Course (WMM) 92 86 6 54 50 4 146 136 10 -
6 SDBC 6 6 0 33 33 0 39 39 0 -
Tests on Materials (CD Works)
7 Sand 21 21 0 4 4 0 25 25 0 -
8 Coarse Aggregate 24 23 1 10 8 2 34 31 3 -
9 Cement 6 6 0 2 2 0 8 8 0 -
10 Steel 0 0 0 0 0 0 0 0 0 -
11 CC cubes 38 38 0 4 4 0 42 42 0 -
12 Slump test 40 40 0 6 6 0 46 46 0 -
13 Water test 7 7 0 2 2 0 9 9 0 -
14 Core cutting test 0 0 0 0 0 0 0 0 0 -Total 471 439 44 117 111 6 588 550 50 -
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
Page 88 of 193Page 88 of 193
Krishna District Summary of QC Tests as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 90/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 0 0 0 0 0 0 0 0 0 -2 Shoulders 0 0 0 0 0 0 0 0 0 -
3 Sub grade 0 0 0 0 0 0 0 0 0 -3 Granular Sub Base 33 32 1 5 5 0 38 37 1 -4 Base Course (WMM) 29 29 0 14 14 0 43 43 0 -5 prime coat 4 4 0 18 18 0 22 22 06 Tack coat 4 4 0 18 18 0 22 22 07 SDBC 22 22 0 18 18 0 40 40 0 -
Tests on Materials (CD Works)8 Sand 49 48 1 6 6 0 55 54 1 -9 Coarse Aggregate 96 94 2 12 12 0 108 106 2 -
10 Cement 0 0 0 0 0 0 0 0 0 -11 Steel 0 0 0 0 0 0 0 0 0 -
12 CC cubes 12 12 0 6 6 0 18 18 0 -13 CC Cores 0 0 0 0 0 0 0 0 0 -14 Slump test 14 14 0 4 4 0 18 18 0 -15 Field density by core cutter method 0 0 0 0 0 0 0 0 0 -
16 Field density test by sand replacement
method 164 164 0 36 36 0 200 200 0 -
17 Water Absorbtion 13 13 0 1 1 0 14 14 018 Silt cintent in sand 0 0 0 3 3 0 3 3 019 AIV 18 18 0 1 1 0 19 19 0
Total 458 454 4 142 142 0 600 596 4 -
Sl.No
Layer/Component of RoadQC tests done to the end of Last
MonthQC tests done during this Month Cumulative no. of tests
Remarks
Page 89 of 193Page 89 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 91/194
Prakasam District Summary of QC Tests as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 92/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 0 0 0 0 0 0 0 0 0 -2 Sub Grade 5 5 0 0 0 0 5 5 0 -3 Granual Sub Base
Gradation 124 124 0 4 4 0 128 128 0 -Relative Compaction (FDD) 96 96 0 3 3 0 99 99 0 -
4 WBM Grade-IIGradation 53 49 4 29 29 0 82 78 4 -
Volumetric Analysis 20 20 0 11 11 0 31 31 0 -
Aggregate Impact Value 17 17 0 10 10 0 27 27 0 -Water Absorption 22 22 0 16 16 0 38 38 0 -Screenings 58 58 0 40 40 0 98 98 0 -
5 WBM Grade-IIIGradation 48 48 0 3 3 0 51 51 0 -
Volumetric Analysis 26 26 0 3 3 0 29 29 0 - Aggregate Impact Value 16 16 0 1 1 0 17 17 0 -Water Absorption 22 22 0 2 2 0 24 24 0 -Screenings 57 57 0 4 4 0 61 61 0 -
6 Prime CoatRate of spread of Binder 28 28 0 2 2 0 30 30 0 -
7 Tack CoatRate of spread of Binder 28 28 0 2 2 0 30 30 0 -
Sl.No
Layer/Component of RoadQC tests done to the end of Last
MonthQC tests done during this Month Cumulative no. of tests
Remarks
Page 91 of 193Page 91 of 193
Prakasam District Summary of QC Tests as on 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 93/194
Total Passed Failed Total Passed Failed Total Passed Failed
Sl.No
Layer/Component of RoadQC tests done to the end of Last
MonthQC tests done during this Month Cumulative no. of tests
Remarks
8 OGPCGrading of 13.2mm & 11.2mm chips 56 56 0 4 4 0 60 60 0 -Temperature 28 28 0 2 2 0 30 30 0 -% of BT Content 28 28 0 2 2 0 30 30 0 -
9 Seal CoatTemperature 28 28 0 2 2 0 30 30 0 -% of BT Content 28 28 0 2 2 0 30 30 0 -
10 OGPC + SCBitumen Extraction Test 59 59 0 4 4 0 63 63 0 -
11 ShoulderSand Replacement (FDD) 3 3 0 0 0 0 3 3 0 -
12 ConcreteCement 32 32 0 4 4 0 36 36 0 -Combined Gradation 65 65 0 4 4 0 69 69 0 -FA-Silt Content 52 52 0 4 4 0 56 56 0 -CA-Gradation 28 28 0 6 6 0 34 34 0 -CA-AIV 30 30 0 4 4 0 34 34 0 -CA-Water Absorption 29 29 0 2 2 0 31 31 0 -Water pH Test 60 60 0 9 9 0 69 69 0 -Slump 84 84 0 6 6 0 90 90 0 -Concrete Cubes 70 70 0 2 2 0 72 72 0 -Concrete Core 23 23 0 0 0 0 23 23 0Rebound Hammer 17 17 0 4 4 0 21 21 0 -FA-Gradation 0 0 0 5 5 0 5 5 0
1340 1336 4 196 196 0 1536 1532 4Total
Page 92 of 193Page 92 of 193
SPSR Nellore District Summary of QC Tests up to 31.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 94/194
Total Passed Failed Total Passed Failed Total Passed Failed
1 Embankment 96 96 0 0 96 96 0 -
2 Sub Grade 143 143 0 3 3 0 146 146 0 -
3 Granual Sub Base 327 326 1 26 26 0 353 352 1 -4 WBM 4 4 0 0 4 4 0
5 WMM 229 229 0 48 48 0 277 277 0 -
6 MSS 140 140 0 15 15 0 155 155 0 -
Tests on Materials
7 Sand 102 100 2 20 20 0 122 120 2 -
8 Coarse Agreegate 61 59 2 19 19 0 80 78 2 -
9 Cement 74 74 0 19 19 0 93 93 0 -
10 Steel 0 0 0 0 0 0 0 0 0 -
11 CC cubes 171 171 0 42 42 0 213 213 0 -
12 Cores 20 20 0 0 0 0 20 20 0 -
13 Slump 135 135 0 40 40 0 175 175 0 -
14 Water ph 35 35 0 14 14 0 49 49 0 -
Total 1537 1532 5 246 246 0 1783 1778 5
Sl.No
Layer/Component of Road
QC tests done to the end of LastMonth
QC tests done during this Month Cumulative no. of testsRemarks
Page 93 of 193Page 93 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 95/194
Annexure - D
Visits by TPQA Consultants
ABSTRACT STATUS OF NCRMP WORKS - TPQA (CIVIL ENGG) INSPECTION AS ON 31.12.2013
PR R&B I & CADD
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 96/194
W o r k s
U p t o l a s t
m o n t h
D u r i n g t h i s
M o n t h
C u m m u l a t i v e
W o r k s
U p t o l a s t
m o n t h
D u r i n g t h i s
M o n t h
C u m m u l a t i v e
W o r k s
U p t o l a s t
m o n t h
D u r i n g t h i s
M o n t h
C u m m u l a t i v e
W o r k s
U p t o l a s t
m o n t h
D u r i n g t h i s
M o n t h
C u m m u l a t i v e
W o r k s
U p t o l a s t
m o n t h
D u r i n g t h i s
M o n t h
C u m m u l a t i v e
1 Srikakulam 27 210 36 246 15 72 21 93 18 65 25 90 1 13 0 13 0 0 0 0 442
2 Vizianagaram 4 27 7 34 5 41 11 52 3 3 4 7 0 0 0 0 0 0 0 0 93
3 Visakhapatnam 2 49 4 53 4 66 2 68 5 66 0 66 0 0 0 0 0 0 0 0 187
4 East Godavari 6 33 3 36 9 49 7 56 8 32 7 39 3 52 33 85 0 0 0 0 216
5 West Godavari 0 0 4 4 9 74 12 86 24 205 25 230 0 0 0 0 0 0 0 0 320
6 Krishna 9 0 10 10 30 150 30 180 42 180 56 236 1 4 2 6 1 0 0 0 432
7 Guntur 8 16 4 20 4 77 16 93 4 39 5 44 3 73 7 80 0 0 0 0 237
8 Prakasam 11 6 5 11 12 73 21 94 30 304 29 333 1 27 1 28 0 0 0 0 466
9 Nellore 0 0 3 3 21 156 24 180 19 202 21 223 1 0 0 0 0 0 0 0 406
67 341 76 417 109 758 144 902 153 1096 172 1268 10 169 43 212 1 0 0 0 2799Total
Sl.No.
District
MPCS RCS
T o t a l V i s i t s
PR R&B I & CADD
SALINE EMBANKMENTSRHB BRIDGES
Page 95 of 193Page 95 of 193
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 97/194
1 Y2-001 MPCS Construction of Cyclone shelter atKollipadu in Santhabommali Mandal. completed 12.12.13,
23.12.13 2
2 Y2-012 MPCS Construction of Cyclone shelter atChinakotturu
PCC, Footings, columns upto stiltfloor completed. Plinth beam
reinforcement & Back filling are inprogress.
4.12.13 1
3 Y2-018 MPCS Construction of Cyclone shelter atKomaravanipeta
Earth work excavation, PCC,footings completed. Columns for
stilt floor is in progress.19.12.13,30.12.13 2
4 Y2-021 MPCS Construction of Cyclone shelter atPotayyapeta
Earth work is in progress
6.12.13,10.12.13,12.12.13,14.12.13,26.12.13
5
5 Y2-023 MPCSConstruction of Cyclone shelter at
CH.Karrivanipalem Earth work is in progress 30.12.13 1
6 Y2-024 MPCS Construction of Cyclone shelter atRamayyapatnam
PCC, Footings completed, Columnsupto plint beam is in progress.
9.12.13,18.12.13,30.12.13
3
7 Y2-027 MPCS Construction of Cyclone shelter atR.Sunnapalli Earth work is in progress 7.12.13 1
Stilt floor slab and Columns below
Q ( )
Name of the District: SRIKAKULAM
Sl.
No
Project
Code
catag
oryName of work visited Work stage
Date of
visit
Total
visits
Name of the District: SRIKAKULAM
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 98/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
14 Y2-147 RCS Road from R&B road SJ puram Earth work and GSB completed,Key walls Completed, Concretingfor road is in progress.`
4.12.13,
5.12.13,23.12.13,30.12.13,31.12.13
5
15 Y2-148 RCS Road from Kothapeta road toSainooru
Earth work completed, CD Workscompleted.
4.12.13,5.12.13 2
16 Y2-150 RCS Road from Borubadra, Meghavaram
road to M.Maruvada
Earth work & Culverts, GSB 400MTS, CC road length of 380 mts,
WBM Layer is in progress.
7.12.13,13.12.13,
14.12.13,23.12.13
4
17 Y2-158 RCS Road from R&B road toPathadibbapalem
Culverts,GSB completed, WBM is inprogress
6.12.13,14.12.13,24.12.13,28.12.13,30.12.13
5
18 Y2-159 RCS Road from R&B road to Pothayyapeta CD works, GSB, WMM, CC Roadcompleted.
6.12.13,
10.12.13,12.12.13,14.12.13,26.12.13
5
19 Y2 266 RHB Road from DPN road to Marripalem GSB, Grade2 completed, Grade 3
5.12.13,6.12.13,9.12.13,
13.12.13, 8
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 99/194
1 Y2-041 MPCS Construction of cyclone shelter atBuddugurayyapeta
Earthwork excavation, PCC work,Footings work, Backfilling, Plinth Beambelow pcc work, Plinth Beam, Columns
upto roof level, Stilt slab, first floorcolumns completed, Ramp, staircase
works and First floor form work are in
progress.
02.12.1303.12.1305.12.1312.12.1321.12.1326.12.13
30.12.13
7
2 Y2-162 RCS Road from R&B Road toRoluchappidi cyclone shelter
Earth work, GSB and WBM gr-IICompleted. WBM Gr-III
completed.OGPC+Seal coatcompleted.Shoulders progress.
07.12.1312.12.1316.12.1321.12.1326.12.13
5
3 Y2-163 RCS Road from R&B road toChinapathiwada CS
C.C.Road completed.Shoulders incompleted 26.12.13 1
4 Y2-164 RCS Road from R&B road to B.V.Petacyclone shelter
Earth work, GSB and WBM gr-IICompleted. WBM Gr-III
completed.OGPC+Seal coatcompleted.Shoulders in progress.
07.12.1312.12.1313.12.1321.12.1326.12.13
5
5 Y2-277 RHB Road connecting R&B Roadthrough Thotapalli village Work to be started 26.12.13
30.12.13 2
1 R d f R & B d 21 12 13
Q ( )
Name of the District: VIZIANAGARAM
Sl.
No
Project
Code
catago
ryName of work visited Work stage
Date of
visit
Total
visits
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 100/194
Name of the District: VISAKHAPATNAM
1 Y2-051 MPCS Construction of MPCS inKadapalem (Type D) Earth work in progress 06.12.13
28.12.13 2
2 Y2-053 MPCS Construction of MPCS inPalmanpeta (Type C) SBC Sample collected 20.12.13 1
3 Y2-055 MPCS Construction of MPCS inPentokota (Type D) SBC Sample collected 20.12.13 1
4 Y2-165 RCSRoad from R&B road to
Chinanagamayyapalem cycloneshelter
WBM Gr-II & III, OGPC +Seal coat fromKM 0.000 to 0.800, 3 nos. CD works,
Shoulders completed.19.12.13 1
5 Y2-166 RCS Road from R&B road to Annavaram cyclone shelter
WBM Gr-II & III, OGPC + Seal coat, CCRoad work (from km 1.057 to 1.107)
and Shoulder completed.19.12.13 1
Total 6
( )
Sl.
No
Project
Code
catago
ryName of work visited Work stage
Date of
visit
Total
visits
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 101/194
Name of the District: EAST GODAVARI
1 Y2-076 MPCS Construction of CS atPadamatapalem (Type D)
First floor Roof slab completed.Columns is in progress above
11.12.1314.12.1324.12.13
3
2 Y2-169 RCS Road from R&B road toSamanthkurru Pallepalem CS
Carting earth work icomplete.GSB is inprogress 31.12.13 1
3 Y2-170 RCS Approach Road from R&B Road to
Turupupalem CS
Gravel collection for sub-garde is in
progress.14.12.13 1
4 Y2-173 RCSRoad from R&B road to
Katrenipadu Lanka CycloneShelter
Road A) OGPC + Seal Coat Completedfrom Km. 0.000 to Km 0.500. Road B)GSB completed and CC pavement is inprogress from Km. 0.000 to Km 0.210
12.12.13 1
5 Y2-174 RCSRoad from R&B road to
Kesavadasupalem (New) CycloneShelter
Road A) sub grade, GSB and CCpavement completed from Km. 0.000 toKm.0.320. Road B) sub grade, GSB and
CC pavement completed from Km. 0.000to Km.0.110
12.12.13 1
6 Y2-175 RCS Road from R&B road to KaravakaCS
2 nobs 600mm dia NP3 pipe culvertscompleted. Earth work and selected
earth layer completed from Km.0.500 to0.800
14.12.13 1
7 Y2 176 RCS CC Road from main proposed road GSB and CC Pavement completed from 23 12 13 1
Sl.
No
Project
Code
catago
ryName of work visited Work stage
Date of
visit
Total
visits
Name of the District: EAST GODAVARI
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 102/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
15 Y2-444 R&B BrConstruction of Bridge at
Km.43/10 of Vakalapudi- Edatamroad across Pampa Yeru in EG DT.
Abutement A1,A2, Pier P1 Top wellpluging is in progess.Pier p3,p4 Bottomwell pluging is in progess Pier p2 Well
shinking is in progess
05.12.13
03.12.1310.12.1312.12.1318.12.1319.12.1320.12.1323.12.1326.12.13
29.12.1330.12.13
11
16 Y2-445 R&B BrConstruction of Bridge at
Km.43/6of Vakalapudi- Edatamroad across Pampayeru in EG DT.
Abutement 1,2,Top well pluging is inprogess. Pier 1,2 Bottom well pluging is
in progess
05.12.1303.12.1310.12.1312.12.1318.12.1319.12.1320.12.1323.12.1326.12.1329.12.1330.12.13
11
Total 50
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 103/194
Name of the District: WEST GODAVARI
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 104/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
17 RHB Y2-314 LT R&B road to Modi
Earth work, Sub grade, GSB &
WMM completed. Shoulders is inProgress. 14.12.2013 1
18 RHB Y2-315 SP R&B road to Gannabathulavaripalem of Chamakuripalem
Earth work, Sub grade, GSB, WMM& CD Works completed. Shoulders
is in Progress.21.12.2013 1
19 RHB Y2-318 SP R&B road to Pedathota of Turputallu
Sub grade, GSB, WMM, SDBC & CDWorks completed. Shoulders Work
is in progress.
07.12.2013,08.12.2013 2
20 RHB Y2-319 R&B road to Pedathota of TurputalluSub grade, GSB, WMM, SDBC & CDWorks completed. Shoulders Work
is in progress.
07.12.2013,08.12.2013 2
21 RHB Y2-323 R&B road to PedaedigapalemEarth work, Sub grade, GSB & CDWorks completed. CC Pavement is
in Progress.
27.12.2013,30.12.2013 2
22 RHB Y2-325Road from PR Road to PrakashpuramSC colony of Vemuladeevi(E)
Earth work, Sub grade, GSB, WMM,
SDBC & CD Works completed.Shoulders Work in Progress.
06.12.2013,07.12.2013 2
23 RHB Y2-326Road from PR road to Vemuladeevi(E) colony (Via) Ralla cheruvu of
Vemuladeevi (E)
Scarifying, WMM & SDBCCompleted. Shoulders work is in
Progress.
06.12.2013,07.12.2013 2
24 RHB Y2-327 Road from PR road to Addalavarimeraka of Vemuladeevi(E)
Earth work, Sub grade, GSB, WMM& CD Works completed. Shoulders
Work is in Progress06.12.2013, 1
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 105/194
1 Y2-085 MPCS Construction of Cyclone Shelter atIntheru in Kruthivennu Mandal (Type-B)
SBC sample collected.Exacavationwork is in progress.
02.12.1326.12.13 2
2 Y2-088 MPCS Construction of Cyclone Shelter atTallapalem SBC test done. 01.12.13 1
3 Y2-089 MPCS Construction of Cyclone Shelter at V.Kanuru (Type-A)
M30 pcc work completed for C2 and
C3 coloumns. Measurments likeWidth, Thickness, and length are
verified.
01.12.1317.12.13
20.12.1321.12.1322.12.1330.12.13
6
4 Y2-091 MPCS Construction of Cyclone Shelter atPoletitippa (Type-D) work not started 20.12.13 1
5 Y2-189 RCS Road from R&B road to CS @ Ullipalem Earthwork, GSB WMM, SDBCcompleted. Measurments verified.
09.12.1323.12.13 2
6 Y2-190 RCS Road from R & B Road to CS atJaruguvanipalem
Earthwork, GSB,WMM, SDBCcompleted. Measurments verified.
09.12.1314.12.1323.12.13
3
7 Y2-191 RCS Road from R&B road to Cyclone Shelter@ Utagundam
Earthwork, GSB WMM, SDBCcompleted. Measurments verified.
10.12.1323.12.13 2
8 Y2-192 RCS Road from R&B road to Cyclone Shelter@ R k i
Earthwork, GSB WMM, SDBCl t d M t ifi d
10.12.1311.12.13 3
Name of the District: KRISHNA
Sl.
No
Project
Code
catago
ryName of work visited Work stage
Date of
visit
Total
visits
Name of the District: KRISHNA
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 106/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
20 Y2-211 RCS
Road from Kammavanicheruvu R&B road
to Venkata durgambapuram inMachilipatnam Mandal
Earth work, GSB, WMM and SDBCcompleted. 04.12.13 1
21 Y2-212 RCS Road from R&B Road Pedayadara toHarijanawada
Earth work completed, materialcollected for CD works. 20.12.13 1
22 Y2-218 RCS Road from R&B Road Pallithumalapalemto Nelithippa
GSB work is in progress,600mm diapipe culvert completed. 20.12.13 1
23 Y2-334 RHB Road from R&B Road to BasavanipalemGSB work is in progress. Thicknees,
Road width verified.
10.12.1311.12.1323.12.1329.12.13
4
24 Y2-335 RHB Road from R&B Road to Parra chivara Earth work,All CD works,GSB,WMMand prime coat completed.
03.12.1305.12.1308.12.1312.12.1314.12.13
5
25 Y2-336 RHB Road from R&B road toPedagowdapalem
Earth work,All CD works,GSB,WMM,SDBC Completed
05.12.1308.12.1314.12.13
3
26 Y2-337 RHB Road from R & B Road to Mulapalem Village
Earth work,All CD works,GSB,WMM,SDBC cpmpleted.
08.12.1309.12.13 2
27 Y2 338 RHBRoad from Ganapeswaram R&B Road to
P ll i h idibb Earth work ,GSB,WMM,SDBC
03.12.1305.12.1308.12.13 6
Name of the District: KRISHNA
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 107/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
36 Y2-359 RHB Road from R&B road Jonnalavanipalem
vuchalvanipalem via ThallapalemJungle cleareance completed 11.12.13 1
37 Y2-360 RHB Road from Pedapatnam R&B road toSajjalavaripalem Jungle cleareance completed 11.12.13 1
38 Y2-361 RHB Road from Thallapalem R&B road toBeach area Jungle cleareance completed. 11.12.13 1
39 Y2-362 RHB Road from Pedapatnam R&B roadThallapalem Jungle cleareance completed 11.12.13 1
40 Y2-363 RHB Road from R&B Potlapalem Road toChinapothepalli
Material test done for 10, 20mm, sandand GSB. GSB work in progress. 19.12.13 1
41 Y2-364 RHB Road from R&B road to Marridibba GSB ,600mm dia pipe culvert is inprogress.
16.12.1317.12.13 2
42 Y2-366 RHB Road from Gokavaram R & B road to
Vodarevupalem
Earthwork,All CD works,GSB andWMM Completed. Test done for
20mm, 12.5 mm and fine aggregatefor CC pavment.
02.12.1305.12.1307.12.1311.12.1313.12.1316.12.1317.12.13
7
43 Y2-367 RHBRoad from Gokavaram R & B road to
Badugovanipalem
Earthwork,All CD works,GSB WMMCompleted from km 0.312 to 0.470and CC pavment work is in progress
from km 0.312 to 0.470
13.12.1316.12.13 2
R d f R&B R d Th ll l E th k GSB 450 i l
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 108/194
1 Y2-095 MPCS Construction of MPCS at Nakshatranagar of kothapalem
Foundation work inprogress
05.12.201311.12.201318.12.201330.12.2013
4
2 Y2-225 RCSRoad from R&B Krosurivariplam road to
Markavaripalem
key walls, GSB and C.C
Work completed , WMMwork in progress
04.12.201310.12.201316.12.201318.12.201320.12.201323.12.2013
6
3 Y2-227 RCS Road from R&B Road to Pattapupalem key walls, GSB and C.CWork completed
02.12.201303.12.201305.12.201309.12.201310.12.201312.12.201321.12.201324.12.2013
8
4 Y2-377 RHB Road from R&B Road to Nakshatranagar keywalls work in progress
05.12.201311.12.201318.12.201330.12.2013
4
Name of the District: GUNTUR
Sl.
No
Project
Code
catago
ryName of work visited Work stage
Date of
visit
Total
visits
TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF DECEMBER-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 109/194
1 Y2-228 RCS Road from R&B road to Motupalli CS GSB Completed 23.12.1327.12.13 2
2 Y2-229 RCS
Road from Km1/2+186 of Chinaganjam Railway gate-
Bapaianagar ZP Road toRamachandranagar H/o Kothapalem
GSB Completed, WBM Grade-IICompleted & WBM Grade-III in
progress
23.12.1327.12.13 2
3 Y2-230 RCS
Motupalli R&B Road to Nirikshanagiri
(via) Rudramambapuram CS inMotupalli G.P.
GSB Completed, WBM Grade-II
Completed & WBM Grade-III inprogress
23.12.1327.12.13 2
4 Y2-231 RCS Road from R&B road to MattiguntaCS
WBM Grade-II Completed & WBMGrade-III in progress
23.12.1327.12.13 2
5 Y2-232 RCS Vedullapalli Vodarevu R&B road to CSat Vijayalakshmipuram
WBM Grade-II Completed & WBMGrade-III in progress (440m)
06.12.1323.12.1327.12.13
3
6 Y2-233 RCS Pakala PR Road toChellammagaripattapupalem CS
GSB, WBM Gr-II, CD, CC Completed & WBM Gr-III in Progress
14.12.1326.12.13 2
7 Y2-234 RCS Pakala PR road to PotthaiahgaripalemCS, Kranthinagar Revu.
GSB, WBM Gr-II, CD, CC Completed & WBM Grade-III in Progress
14.12.1326.12.13 2
8 Y2-235 RCS Woollapalem R&B road toDevalampallipalem CS
Earth Work in Progress, GSB & CCCompleted for 64m
14.12.1319.12.13 2
Name of the District: Prakasam
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
Name of the District: Prakasam
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 110/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
20 Y2-404 RHB Road from Tangutur-Ravivaripalemroad @1/2 KM to Pasukuduru.
GSB, CD Works, CC, WBM Gr-IICompleted & WBM Gr-III in progress
14.12.1326.12.13 2
21 Y2-405 RHB Road from Kanuparthy toKukkalavaripalem
GSB Completed & WBM Grade-IICompleted for 500m
05.12.1309.12.1319.12.1320.12.13
4
22 Y2-406 RHB Road from Kanuparthy to YanadiSangam
GSB Completed & WBM Grade-IICompleted
05.12.1309.12.1319.12.1320.12.13
4
23 Y2-407 RHB Road from Kanuparthy to MSPattapupalem
GSB, WBM Grade-II Completed & WBM Grade-III in progress
05.12.1309.12.1320.12.13
3
24 Y2-410 RHB KEM R & B road to Pinnivaripalem GSB,CC,WBM Gr-II & III, OGPC + SCCompleted, Shoulders in Progress 17.12.13 1
25 Y2-414 RHB Road From M.C road to West STcolony of Veerapalli
GSB, CC, WBM Gr-II & III, OGPC + SCCompleted, Shoulders in Progress
12.12.1319.12.1326.12.13
3
26 Y2-455 BridgeReconstruction of High level bridge atKm. 11/10 of Ongole - Kothapatnam
roadWork Stoped 17.12.13 1
27 Y2-102 MPCSConstruction of B type CS in Pakala
Main, S.Konda mandal,PrakasamDistrict
Excavation in Progress 14.12.13 1
28 Y2 111 MPCS Construction of CS in Peddapallipalem Excavation Completed & PCC in 12 12 13 1
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 111/194
Name of the District: SPSR Nellore
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 112/194
Sl.No
ProjectCode
catagory
Name of work visited Work stageDate of
visitTotalvisits
21 Y2-429 RHBRoad from Ponnapudi – Utukur R&B road To
KothuruSG,GSB,WMM completed.
CC road progress
20.12.13
27.12.1330.12.13
3
22 Y2-430 RHB Road from Ponnapudi – Utukur R&B road toPrasanthi giri colony
SG,GSB,WMM & BTcompleted 20.12.13 1
23 Y2-431 RHB Ponnapudi R&B road to Venkatanarayanapuram SG,GSB,WMM & BTcompleted 20.12.13 1
24 Y2-432 RHB Road from Ponnapudi R&B road to Ponnapudi GSB,CC road completed 20.12.13 1
25 Y2-433 RHB Road from Mypadu R&B Road to Kollimittapalem SG,GSB,WMM,CC roadcompleted 17.12.13 1
26 Y2-434 RHB Road from Nellore – Mypadu R&B Road to WestPattapupalem GSB,CC road completed 07.12.13
11.12.13 2
27 Y2-459 RCSRoad from Nidigurthi R&B road to Mukkidipalem
via gollapalem and to Cyclone shelter of Chittamur mandal in Nellore dist
SG,GSB,CD workscompleted 11.12.13 1
Total 48
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 113/194
Sl.No
District
Category
ProjectCode
Name of work visited Work stageDate of
visitTotalvisits
Observations / Remarks
TPQA SITE INSPECTIONS DURING THE MONTH OF DECEMBER - 2013.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 114/194
No rict ory Code visit visits
1 MPCS Y2-023Construction of MPCS at Ch.
KarrivanipalemEarth work is in progress 26.11.13 1
1) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.3) Project information board shall be provided at the work site.
2 MPCS Y2-001Construction of Cyclone Shelter at
KollipaduFinishing work is in
progress26.11.13 1
No labor camp is established and the Contractor has provided thefirst aid box and safety measures to the workers.
3 MPCS Y2-002 Construction of Cyclone Shelter atRunku
Finishing work is inprogress
26.11.13 1 1) No labor camp is established and the Contractor has providedthe first aid box and safety measures to the workers.
4 MPCS Y2-028Construction of MPCS at
CalingapatnamPlinth beam completed 26.11.13 1
1) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
Project information board shall be provided at the work.
5 MPCS Y2-010 Construction of MPCS at Bypalli
PCC for Footings, footings,pedestals and columns upto bottom of plinth beam
are completed, Back fillingin foundation is in progress.
26.11.13 11) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
6 MPCS Y2-012 Construction of MPCS atChinakothuru
PCC, Footings completed.Columns is in progress
26.11.13 1
1) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site. 3)
The compound wall of the school and the Coconut tree adjacentto the school shall be removed for the construction of CS
7 MPCS Y2-011Construction of MPCS at
Chinavanka
PCC for Footings, footings,pedestals and columns upto bottom of plinth beam
are completed, Back fillingin foundation in progress.
26.11.13 11) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site
8 MPCS Y2-029Construction of MPCS at
Bandaruvanipeta
Earthwork Excavation, PCCfor footings, RCC footings,
pedestals and columns upto
bottom of plinth beam work completed.
26.11.13 11) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
S r i k a
k u
l a m
Page 113 of 193Page 113 of 193
Sl.No
District
Category
ProjectCode
Name of work visited Work stageDate of
visitTotalvisits
Observations / Remarks
TPQA SITE INSPECTIONS DURING THE MONTH OF DECEMBER - 2013.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 115/194
No rict ory Code visit visits
9 MPCS Y2-018 Construction of MPCS at
Kommaravanipeta26.11.13 1
1) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
10 MPCS Y2-025 Construction of MPCS at Metturu 26.11.13 11) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
11 MPCS Y2-027 Construction of MPCS at ReddicaSunnapalli
Earth work is in progress 26.11.13 1 1) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
12 MPCS Y2-031Construction of MPCS at
Jagannadhapuram
Earthwork Excavation, PCCfor footings, RCC footings,
pedestals and columns uptobottom of plinth beam
work completed.
27.11.13 11) Proper barricading shall be provided to the construction site.2) House keeping shall be properly maintained at the work site.
13 MPCS Y2-032Construction of MPCS at
Kothamukkam
PCC completed,Reinforcement for footings
is in progress.27.11.13 1
1) Proper barricading shall be provided to the construction site. 2)Protective equipment like shoes, helmets etc., shall be provided to
the workers. 3) First Aid box shall be kept at the site.
14 MPCS Y2-030Construction of MPCS at
Akkuvaram
PCC completed,Reinforcement for footings
is in progress.27.11.13 1
1) Proper barricading shall be provided to the construction site.2) Project information board with details shall be erected at the
site. 3) First Aid box shall be kept at the site.
15 MPCS Y2-036Construction of MPCS at
Bonthalakoduru
PCC completed,Reinforcement, shuttering
for footings completed.27.11.13 1
16 MPCS Y2-037Construction of MPCS at
PathadibbalapalemFootings, columns belowplinth beam completed
27.11.13 1
17 MPCS Y2-024Construction of MPCS at
RamayyapatnamPCC completed 27.11.13 1
1) Proper barricading shall be provided to the construction site.2) Project information board with details shall be erected at the
site. 3) First Aid box shall be kept at the site.
18 RCS Y2-145Construction of Road from
Chinnavanka to GopaldavooruEarth work completed 27.11.13 1
Necessary action shall be taken to protect the temple on theshoulder on RHS of the road. A tap is there on the RHS of the
shoulder in Km 0.1.
19 RCS Y2-146Construction of Road from MN peta
to Kondavooru and to CSEarth work completed 27.11.13 1 No Issues till date.
PCC for Footings, footings,pedestals and columns upto bottom of plinth beam
are completed, Back fillingin foundation in progress.
1) Proper barricading shall be provided to the construction site.2) Protective equipment like shoes, helmets etc., shall be provided
to the workers. 3) First Aid box shall be kept at the site.
S r i k a
k u
l a m
Page 114 of 193Page 114 of 193
Sl.No
District
Category
ProjectCode
Name of work visited Work stageDate of
visitTotalvisits
Observations / Remarks
TPQA SITE INSPECTIONS DURING THE MONTH OF DECEMBER - 2013.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 116/194
y
20 RCS Y2-147Construction of Road from R&B
Road to S.J. PuramEarth work and GSB
completed27.11.13 1 No issues till date.
21 RCS Y2-148Construction of Road from
Kothapeta Road to Sainooru CSEarth work completed 27.11.13 1 No Issues till date.
22 RCS Y2-157 Construction of Road from R&BRoad to Akkuvaram
Earth work and Culvertscompletd, GSB 400 MTS
Laying is in progress.27.11.13 1 No Issues till date.
23 RCS Y2-158Construction of Road from R&B
Road to Pathadibbapalem
Culverts,GSB completed,Road widening is in
progress27.11.13 1 No issues till date.
24 RCS Y2-154Construction of Road from
Yeeramukkam-Rati R&B Road toDunnavooru
Road widening is inprogress, earth work,culverts is in progress.
27.11.13 1 The obstructions on both the side of the road shall be removed to
provide sufficient width to the road
25 RCS Y2-155Construction of Road from
Yeeramukkam-Rati R&B Road toGeddavooru
Earth work, culverts is inprogress.
27.11.13 1 The obstructions on both the side of the road shall be removed to
provide sufficient width to the road.
26 RCS Y2-156Construction of Road from R&BRoad to Ganguwada to Road to
Sigalaputtuga
Earth work, culverts is inprogress.
27.11.13 1 No issues till date.
27 RCS Y2-150Construction of Road from
Borubhadra – Meghavaram Road toM. Maruvada
CC road completed, Graverlshoulder laying is in
progress27.11.13 1 No Issues till date.
28 RHB Y2-273Construction of Road from DPN
Road to DL Puram Jn. Via Koduru,Magathapadu, Guppidipeta
Culverts completed, WBMGR-II laying is in progress
27.11.13 1 No Issues till date.
29 RHB Y1-098Construction of Road from
Talasamudram to Dola regulatorCompleted 27.11.13 1
No labor camp is established and the Contractor has provided thefirst aid box and safety measures to the workers.
30 RHB Y2-272Road from R&B road Mobagam to
Dubbakavanipeta viaGajapathinagaram
Completed 27.11.13 1No labor camp is established and the Contractor has provided the
first aid box and safety measures to the workers
S r i k a
k u
l a m
Page 115 of 193Page 115 of 193
Sl.No
District
Category
ProjectCode
Name of work visited Work stageDate of
visitTotalvisits
Observations / Remarks
TPQA SITE INSPECTIONS DURING THE MONTH OF DECEMBER - 2013.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 117/194
y
31 RHB Y2-271Construction of Road from R&B
Road Edulavalasa-Killam to Jonnamvia Talasamudram
GSB,WBM Gr-II, WBM Gr-III, BT and CC road work
completed27.11.13 1 No issues till date.
32 RHB Y2-265Road from B.M R&B Road to
Simmayyapeta
Culverts,GSB completed,Road widening is in
progress
27.11.13 1 No issues till date.
33 RHB Y2-266Construction of Road from R&B
Road to Marripadu
Road widening is inprogress, culverts and GSB
completed27.11.13 1 No Issues till date.
34 RHB Y2-267Construction of Road from R&B
Road to KakarapalliRoad widening is in
progress27.11.13 1
The width of the road is narrow due to railway lines in Km.0.400.For the remaining road also, the vegetation shall be cleared on
both sides to have a sufficient width to the road.
35 RHB Y2-276Construction of Road from K.C.
Road to Amplam via Urjam,Nandigam
GSB completed 27.11.13 1 No Issues till date.
36 RHB Y2-270
Construction of Road from DPN
Road to Gangaram village viaPalatalagam, Srikrishnapuram
Road widening is inprogress 27.11.13 1 No Issues till date.
37 RHB Y2-269Construction of Road from R&B
Road to PethalingapuramRoad widening is in
progress27.11.13 1 No issues till date.
38 RHB Y2-275Construction of Road from K.C.
Road to Rajarampuram via Ampalem Revuamplam
Culverts completed, WBMGR-II collection & laying is
in progress27.11.13 1 No Issues till date.
39 MPCS Y2-091Construction of Cyclone shelter at
PoletitippaWork not yet sarted 20.12.13 1
Barricading is necessary to avoid disturbance to the adjacenthouseholds during the execution of the work.
40 MPCS Y2-089Construction of Cyclone shelter in
V.KanuruFootings, columns belowplinth beam completed
20.12.13 1 No Issues till date.
41 RCS Y2-212 Road from R&B road Pedayadara
to HarijanawadaGSB work is in progress 20.12.13 1 No Issues till date.
42 RCS Y2-218 Road from R&B road to
Palletummalapalem to NelatippaGSB work is in progress 20.12.13 1 No Issues till date.
S r i k a
k u
l a m
K r i s
h n a
Page 116 of 193Page 116 of 193
Sl.No
District
Category
ProjectCode
Name of work visited Work stageDate of
visitTotalvisits
Observations / Remarks
TPQA SITE INSPECTIONS DURING THE MONTH OF DECEMBER - 2013.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 118/194
43 RCS Y2-215Road from R&B Road
Karagraharam to PallipalemGSB work is in progress 20.12.13 1 No Issues till date.
44 RCS Y2-216Road from R&B Road
Kammavaricheruvu to KPT PalemGSB work is in progress 20.12.13 1 No Issues till date.
45 RCS Y2-217R&B Road Kammavaricheruvu to
Malakayalanka GSB work is in progress 20.12.13 1 No Issues till date.46 RHB Y2-330 R&B Road to Pedagudumotu Earth work is in progress 20.12.13 1 No Issues till date.
47 Emb Y2-457
Restoration of Kona salineembankment to the original
standards from Km 0.000 to Km18.6000 in Divi Island.
Work not yet sarted 20.12.13 1 Some migrant fishermen have constructed temporary huts on thebank and they said that they will remove the huts.
48 MPCS Y2-112Construction of cyclone shelter at
AlagayapalemFootings, columns belowplinth beam completed
26.12.13 1
1) The field officers are requested to erect the project informationboard at starting point (i.e., near Km. 0.0) of the working reaches.2) Safety measures for workers such as Helmets and Gum Shoesto workers shall be provided by the contractor. 3) Permanentbarricading shall be provided to the work site to prevent anycasualties to the public and the workers.
49 RHB Y2-414Construction of Road from M. C.
Road to West ST Colony of Veerapalli
GSB Completed, CC inProgress, WBM Grade-II,WBM Grade-III & OGPC +SC in Completed. Shouldersin Progress
26.12.13 1
1) Guard stones with reflective stickers are not provided from Km.3/6 to Km. 3/8 and at Km. 3/150. The field staff shall takenecessary action. 2) The field staff shall insist the contractor toprovide safety measures to all the 14 culverts under construction.3)1) The field staff shall take necessary action for sufficient widthof the road and remove obstructions at Km. 2/2.
50 RHB Y2-235Road from Woollapalem R&B road
to Devalampallipalem CSEarth Work in Progress 26.12.13 1
The field officers are requested to erect the project informationboard at starting point (i.e., near Km. 0.0) of the working reaches.
51 N e
l l o r e
RHB Y2-423Road from Annagaripalem R&B
road to Pedanattu PattapupalemEarth work is in progress 27.12.13 1 No Issues till date.
K r i s h n a
P r a
k a s a m
Page 117 of 193Page 117 of 193
NCRMP Works - Abstract of TPQA (Electrical Engineer) Inspection Status up to
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 119/194
WorksUp to last
monthDuring this
MonthCummulative
1 Srikakulam 27 13 2 15
2 Vizianagaram 4 1 1
3 Visakhapatnam 2 14 14
4 East Godavari 6 10 10
5 West Godavari 0 0 0
6 Krishna 9 0 0
7 Guntur 8 0 0
8 Prakasam 8 0 0
9 Nellore 0 0 0
Q ( g ) p pDecember 2013
Sl.No. District
PR
MPCS
TPQA SITE (ELECTRICAL) INSPECTIONS DURING THE MONTH OF DECEMBER - 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 120/194
3 Srikakulam Y2-001 Construction of MPCS at Kollipadu Finishing 12.12.2013
4 Srikakulam Y2-002 Construction of MPCS at Runku Finishing 12.12.2013
DistrictSl. No
Q ( )
Name of work visited Work stage Date of visit Remarks if anyProject
Code
Page 119 of 193Page 119 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 121/194
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 122/194
Up to Lastmonth
During thisMonth
Cummulative
1 Srikakulam 66 21 87
2 Vizianagaram 18 4 22
3 Visakhapatnam 35 2 37
4 East Godavari 25 8 33
5 West Godavari 41 10 51
6 Krishna 108 12 120
7 Guntur 83 21 104
Abstract details of Surprise Inspections carried out by TPQA Consultant upto end of December 2013
Surprise visitsDistrict
Sl.No.
District : SRIKAKULAM
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 123/194
District : SRIKAKULAM
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
1 6.12.13 SE2 10.12.13 SE
3 14.12.13 DPM,SE4 5.12.13 SE5 7.12.13 SE6 5.12.13 SE7 18.12.13 SE
8 30.12.13 PM,DPM SE9 5.12.13 SE
10 18.12.13 SE11 30.12.13 PM,DPM SE
12 2.12.13 SE13 13.12.13 SE14 30.12.13 PM,DPM SE
15 23.12.13 RHBRoad from DPN road to Gangaram village via Srikrishnapuram,
palatalagamNCRMP/B-W /AP/RHB/ PRED/01/
Santhabommalli /001BSE
16 5.12.13 DPM,SE17 30.12.13 SE
18 30.12.13 MPCS Construction of Cyclone shelter at CH.KarrivanipalemNCRMP/B-W/ AP/MPCS/ PRED/01/
Kavati/011SE
19 7.12.13 MPCS Construction of Cyclone shelter at R.Sunnapalli NCRMP/B-W/ AP/MPCS/ PRED/01/Santhabommali /014
SE
20 10.12.13 DPM, SE21 19.12.13 SE
MPCS Construction of Cyclone shelter at KottamukkamNCRMP/B-W/ AP/MPCS/ PRED/01/
Ranastalam /016
NCRMP/B-W /AP/RHB/ PRED/01/Santhabommalli /001A
MPCS Construction of Cyclone shelter at AkkuvaramNCRMP/B-W /AP/RHB/ PRED/01/
Polaki /018
RCS Road from R&B road SJ puramNCRMP/B-W /AP/RCS/ PRED/01/
V.Kotturu/001
NCRMP/B-W/ AP/MPCS/ PRED/01/Ranasthalam/009
MPCS Construction of Cyclone shelter at Potayyapeta
MPCSConstruction of Cyclone shelter at Bandaruvanipeta
NCRMP/B-W/ AP/MPCS/ PRED/01/Gara/015
Road from DPN road to Marripalem Adl roadNCRMP/B-W /AP/RHB/ PRED/01/
Santhabommalli /001A RHB
RHB Road from DPN road to Marripalem Adl road
Page 122 of 193Page 122 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 124/194
District : VISAKHAPATNAM
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 125/194
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
1 19.12.13 RCS Road from R&B road to Annavaram cyclone shelter SE
2 19.12.13 RCS Road from R&B road to Chinanagamayyapalem CS SE
NCRMP/B-W/AP/RCS/PRED/03/Bheemili/005
Page 124 of 193Page 124 of 193
District : EAST GODAVARI
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 126/194
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
13.12.2013
19.12.201320.12.2013
R&B BrConstruction of Bridge at Km.43/10 of Vakalapudi-
Edatam road across Pampa Yeru in EG DT.NCRMP/B-W/AP/Br/R&B/04/Uppiteru- vagu/014
Site EngineerBr. Engineer
Field registers notavailable at site
23.12.2013
19.12.201320.12.2013
R&B BrConstruction of Bridge at Km.43/6of Vakalapudi- Edatam
road across Pampayeru in EG DT.NCRMP/B-W/AP/Br/R&B/04/Uppiteru- vagu/014
Site EngineerBr. Engineer
Field registers notavailable at site
3 31.12.13 RCSConstruction of Road from R&B road to samanthukuru
pallepalem E.G.DTNCRMP/B-W/AP/RHB/PRED/
04/Katrenikona/014Site Engineer
GSB grade is inprogess
4 31.12.2013 RHBConstruction of BTRoad from Komaragiripatenam to
kadadari E.G.DTNCRMP/B-W/AP/RHB/PRED/
04/Katrenikona/016Site Engineer
WBM grade III isin progess
Page 125 of 193Page 125 of 193
District : WEST GODAVARI
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 127/194
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
1 26.12.2013 RCS Road from R&B road to Kothakayalathippa CS DPM & SE
2 21.12.2013 RCSRoad from Narsapur Perupalem R&B road to
MandavarithotaDPM & SE
3 21.12.2013 RCSRoad from Mollaparru R & B road to Mollaparru PathaColony
DPM & SE
4 21.12.2013 RCS Road from K.P Palem (N) Panchayat office to MetturevuPalli palem
SE
5 21.12.2013 RCS R&B road to ChinamynavanilankaNCRMP/B-W/AP/RCS/PRED/
05/Narsapur/006SE
6 01.12.2013 RHB Khalipatnam R&B Road to Khalipatnam ferryNCRMP/B-W/AP/RHB/PRED/
05/Mogaltur/006SE
7 03.12.2013 RHB Road from SP R&B road to Pasaladeevi SE
8 21.12.2013 RHBSP R&B road to Gannabathulavari palem of Chamakuripalem
SE
9 30.12.2013 RHB R&B road to PedaedigapalemNCRMP/B-W/AP/RHB/PRED/
05/Narsapur/013SE
10 7.12.2013 RHBRoad from PR road to Addalavarimeraka of
Vemuladeevi(E)NCRMP/B-W/AP/RHB/PRED/
05/Narsapur/014SE
NCRMP/B-W/AP/RCS/PRED/05/Mogaltur/005
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010
Page 126 of 193Page 126 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 128/194
District : GUNTUR
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 129/194
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
1
04.12.201311.12.201316.12.2013
23.12.2013
BR Reconstruction of bridge across peddapallidrain at km
14/6 of chandole bridge to Nizampatnam roadNCRMP/B-W/AP/Br/R&B/
07/Pedapalli/022SE 4
211.12.201318.12.2013
MPCS Construction of MPCS at Nakshatranagar of KothapalemNCRMP/B-W/AP/MPCS/R&B/
07/Repalle/002SE 2
3 11.12.201318.12.2013
RHB Road from R&B Road to Nakshatranagar NCRMP/B-W/AP/RHB/PRED/07/Bapatla/004
SE 2
4
03.12.201305.12.201312.12.201321.12.2013
RCS Road from R&B Road to PattapupalemNCRMP/B-W/AP/RCS/PRED/
07/Bapatla/006SE 4
5 17.12.2013 RCSRoad from Ganapavaram R&B Road to
Pedamarpuvaripalem (Year-1)SE 1
6 17.12.2013 RCS R&B Road to Chinapuluguvaripalem (Year-1) SE 1
7
04.12.201305.12.201316.12.201318.12.201320.12.2013
RCS Road from R&B Krosurivariplam road to MarkavaripalemNCRMP/BW/AP/RCS/PRED/
07/Nizampatnam/005SE 5
816.11.201320.11.2013
RHB Road from R&B road to GattuvaripalemNCRMP/B-W/AP/RHB/PRED/
07/Nagaram/007SE 2
NCRMP/B-W/AP/RCS/PRED/07/karlapalem/002
Page 128 of 193Page 128 of 193
District : PRAKASAM
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 130/194
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
1 14.12.2013 RCS Pakala PR Road to Chellammagaripattapupalem CS DPM/SE
2 14.12.2013 RCS Pakala PR road to Potthaiahgaripalem CS, Kranthinagar Revu. DPM/SE
3 14.12.2013 RCS Woollapalem R&B road to Devalampallipalem CS DPM/SE
4 14.12.2013 RCS Road from Tangutur to Ananthavaram DPM/SE
5 12.12.2013 RCS Road from Z.P. road to Srirampattapupalem DPM/SE
6 12.12.2013 RCS Road from ZP road to Pallipalem of Chakicharala DPM/SE
7 14.12.2013 RHBRoad from Tangutur to Tallapalem (via) Velagapudi (Km 4/5
to 7/465)NCRMP/B-W/AP/RHB/PRED/
08/Tangutur/021DPM/SE
8 14.12.2013 RHBRoad from Tangutur-Ravivaripalem road @1/2 KM to
Pasukuduru.NCRMP/B-W/AP/RHB/PRED/
08/Tangutur/022DPM/SE
9 09.12.2013 RHB Road from Kanuparthy to Kukkalavaripalem PM/DPM/SE
10 09.12.2013 RHB Road from Kanuparthy to Yanadi Sangam PM/DPM/SE
11 09.12.2013 RHB Road from Kanuparthy to MS Pattapupalem PM/DPM/SE
12 17.12.2013 Bridge Reconstruction of High level bridge at Km. 11/10 of Ongole -Kothapatnam road in Prakasam District
NCRMP/B-W/AP/Br/R&B/08/Ongole/023
DPM/SE
NCRMP/B-W/AP/RCS /PRED/
08/S.Konda&Tangutur/010
NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009
NCRMP/B-W/AP/RHB/PRED/08/N.G.Padu/011
Page 129 of 193Page 129 of 193
District : SPSR NELLORE
SURPRISE VISITS DURING THE MONTH OF DECEMBER 2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 131/194
Sl.No Date Habitation Name of Work Package No. Visited by Remarks
1 4.12.2013 RCSRoad from @ Km 56/8 to CK Road to Periyavettu Kuppam
CSNCRMP/B-W/AP/RCS/PRED/
09/Tada/009SE
2 07.12.2013 RHB Road from Mypadu R&B Road to KollimittapalemNCRMP/B-W/AP/RHB/PRED/
09/I.Peta/027SE
3 13.12.2013 RHB Ponnapudi-Utukur road to PattapupalemNCRMP/B-W/AP/RHB/PRED/
09/Vidavaluru/025SE
4 13.12.201 RCS Road from R&B road to Utukuru Pallipalem SE
5 19.12.2013 RCS Road from Ponnapudi R&B Road to Lakshimipuram SE
6 19.12.2013 RHB Road from Ponnapudi – Utukur R&B road To Kothuru SE
7 19.12.2013 RHB Road from Ponnapudi R & B road to Ponnapudi SE
8 31.12.2013 RHB Ponnapudi-Utukur road to Pattapupalem NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/025
SE
9 31.12.2013 RCS Road from Ramudupalem on R&B road to Pallipalem NCRMP/B-W/AP/RCS/PRED/09/I. Pet/018
SE
10 31.12.2013 RCS Road from C.S. Puram to EdurupalemNCRMP/B-W/AP/RCS/PRED/
09/T.P.Gudur& Muthukur/019SE
NCRMP/B-W/AP/RHB/PRED/09/Vidavaluru/026
NCRMP/B-W/AP/RCS/PRED/09/Vidavaluru/ 021
Page 130 of 193Page 130 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 132/194
Annexure - F
Audit Reports submitted by
QCRs submitted in the month of December-2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 133/194
Package Number Name of Work District
NCRMP/B-W/AP/MPCS/PRED/01/Polaki/018
Construction of Cyclone Shelter at Akkuvaram (type B) in PolakiMandal
Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Ranastalam/008
Construction of Cyclone Shelter at Kommarivanipeta inRanastalam Mandal
Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Ranasthalam/005
Construction of MPCS in Jaganadhapuram (type B) of Ranasthalam Mandal
Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Ranasthalam/005
Construction of MPCS in Kothamukkam (Type A) of RanasthalamMandal
Srikakulam
NCRMP/B-W/AP/MPCS/PRED/01/Ranasthalam/009
Construction of MPCS in Pothyyapeta (Type B) of RanasthalamMandal
Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla & Ranasathalam/012
Road from R&B road to Pothayyapeta in Ranastalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla & Ranasathalam/012
Road from R&B road to Pothayyapeta in Ranastalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla & Ranasathalam/012
Road from R&B road to Pathadibbalapalem in Ranastalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla & Ranasathalam/012 Road from R&B road to Pothayyapeta in Ranastalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla & Ranasathalam/012
Road from R&B road to Pothayyapeta in Ranastalam Mandal Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Santhabommali/008
Road from Borubadra-Megavaram road to M.Maruvada of Santhabommali Mandal
Srikakulam
NCRMP/B-W/AP/RCS/PRED/ Road from Borubadra-Megavaram road to M.Maruvada of Srikakulam
Package Number Name of Work District
NCRMP/B W/AP/RCS/PRED/ Road from R&B road to Samanthakuru Cyclone Shelter in
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 134/194
NCRMP/B-W/AP/RCS/PRED/04/Allavaram/016
Road from R&B road to Samanthakuru Cyclone Shelter in Allavaram Mandal
East Godavari
NCRMP/B-W/AP/RCS/PRED/05/Narsapur/006
Road from R&B road to Chinamynavanilanka in Narsapur Mandal West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/006
Road from Khalipatnam R&B Road to Khalipatnam ferry inMogaltur Mandal
West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010
Road from SP R&B road to Pasaladeevi in Narsapur Mandal West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/010
LT R&B road to Modi in Narsapur Mandal West Godavari
NCRMP/B-W/AP/RHB/PRED/
05/Narsapur/013Road from R&B road to Evanivarimeraka in Narsapur Mandal West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014
Road from PR road to Addalavarimeraka of Vemuladeevi (E) inNarsapur Mandal
West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014
Road from PR Road to Prakashpuram SC colony of Vemuladeevi(E) in Narsapur Mandal
West Godavari
NCRMP/B-W/AP/RHB/PRED/05/Narsapur/014
Road from PR road to Vemuladeevi (E) colony (via) Ralla cheruvuof Vemuladeevi (E) in Narsapur Mandal
West Godavari
NCRMP/B-W/AP/MPCS/PRED/06/Machilipatnam/003
Construction of Cyclone Shelter at V.Kanuru in MachilipatnamMandal
Krishna
NCRMP/B-W/AP/RCS/PRED/06/Koduru/001
Road from R&B Road to Cyclone Shelter @ Jaruguvanipalem inKoduru Mandal
Krishna
NCRMP/B-W/AP/RCS/PRED/06/Koduru/001
Road from R&B road to Cyclone Shelter @ Ullipalem in KoduruMandal
Krishna
NCRMP/B-W/AP/RCS/PRED/ Road from R&B Road to Cyclone Shelter @ Jaruguvanipalem ini h
Package Number Name of Work District
NCRMP/B-W/AP/RHB/PRED/
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 135/194
NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/008
Road from R&B road to Parrachivara in Nagayalanka Mandal Krishna
NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/008
Road from R&B road to Parrachivara in Nagayalanka Mandal Krishna
NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka/010
Road from ZP Road to Sorlagondi in Nagayalanka Mandal Krishna
NCRMP/B-W/AP/RCS/PRED/07/Bapatla/006
Road from R&B road to Pattapupalem in Bapatla Mandal Guntur
NCRMP/B-W/AP/RCS/PRED/07/Bapatla/006
Road from R&B road to Pattapupalem in Bapatla Mandal Guntur
NCRMP/B-W/AP/RCS/PRED/
08/Chinaganjam & Chirala/006Road from R&B Road to Mattigunta CS of Chirala Mandal Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Chinaganjam & Chirala/006
Motupalli R&B Road to Nirikshanagiri (via) Rudramambapuram CSin Motupalli GP of Chinaganjam & Chirala Mandal
Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Chinaganjam & Chirala/006
Road from Km1/2+186 of Chinaganjam Railway gate-BapaianagarZP Road to Ramachandranagar H/o Kothapalem in Chinaganjam
MandalPrakasam
NCRMP/B-W/AP/RCS/PRED/08/S.Konda & Tanguturu/010
Road from Pakala PR Road to Chellammagaripattapupalem CS inSingaraya Konda Mandal
Prakasam
NCRMP/B-W/AP/RCS/PRED/08/S.Konda & Tangutur/010
Road from Tangutur to Ananthavaram in Singaraya Konda Mandal Prakasam
NCRMP/B-W/AP/RCS/PRED/08/S.Konda & Tangutur/010
Road from Woollapalem R&B Road to Devalampallipalem CS inTangutur Mandal
Prakasam
NCRMP/B-W/AP/RCS/PRED/08/Ulavapadu/009
Road from ZP road to Pallipalem of Chakicharala in UlavapaduMandal
Prakasam
Package Number Name of Work District
NCRMP/B-W/AP/RCS/PRED/ Road from R&B road to Nelaturu to Ananthavaram Cyclone
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 136/194
NCRMP/B W/AP/RCS/PRED/09/T.P.Gudur & Muthukur/019
Road from R&B road to Nelaturu to Ananthavaram Cycloneshelter in T.P.Gudur Mandal
SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Vidavalur/021
Road from Ponnapudi R&B road to Ramachandrapuram in Vidavalur Mandal
SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Vidavalur/021
Road from R&B Road to Utukuru Pallipalem in Vidavalur Mandal SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Vidavalur/021
Road from Ponnapudi R&B road to Ramachandrapuram in Vidavalur Mandal
SPSR Nellore
NCRMP/B-W/AP/RCS/PRED/09/Vidavalur/021
Road from R&B Road to Utukuru Pallipalem in Vidavalur Mandal SPSR Nellore
NCRMP/B-W/AP/RHB/
PRED/09/Kavali/024
Road from Annagaripalem R&B road to Pedanattu Pattapupalem
of Kavali MandalSPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/I.Peta/027
Road from Nellore - Mypadu R&B Road to West Pattapupalem inI.Peta Mandal
SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026
Road from Ponnapudi R&B Road to Venkatanarayanapuram in Vidavalur Mandal
SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026
Road from Ponnapudi- Utukur R&B Road to Prasanthagiri Colonyin Vidavalur Mandal
SPSR Nellore
NCRMP/BW/AP/RHB/PRED/09/Vidavalur/026
Road from Ponnapudi- Utukur R&B Road to Srigowripuram in Vidavalur Mandal
SPSR Nellore
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 137/194
Package Number Name of Work District
NCRMP/B-W/AP/RCS/PRED/
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 138/194
NCRMP/B W/AP/RCS/PRED/01/V.Kottoru/001
Construction of Road from R&B Road to S.J. Puram Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/V.Kottoru/001
Construction of Road from Kothapeta Road to Sainooru CS Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Mandasa/010
Construction of Road from R&B Road to Akkauvaram Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Etcherla & Ranasthalam/012
Construction of Road from R&B Road to Pathadibbapalem Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Mandasa/010
Construction of Road from Yeeramukkam-Rati R&B Road toDunnavooru
Srikakulam
NCRMP/B-W/AP/RCS/PRED/
01/Mandasa/010
Construction of Road from Yeeramukkam-Rati R&B Road to
GeddavooruSrikakulam
NCRMP/B-W/AP/RCS/PRED/01/Mandasa/010
Construction of Road from R&B Road to Ganguwada to Roadto Sigalaputtuga
Srikakulam
NCRMP/B-W/AP/RCS/PRED/01/Santhabommali/008
Construction of Road from Borubhadra – Meghavaram Roadto M. Maruvada
Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/001A
Construction of Road B.M. (R&B) Road to Simmayyapeta Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/001A
Construction of Road from R&B Road to Marripadu Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/001A
Construction of Road from R&B Road to Kakarapalli Srikakulam
NCRMP/B-W/AP/RHB/PRED/01/Polaki/008
Construction of Road from K.C. Road to Amplam via Urjam,Nandigam
Srikakulam
NCRMP/B-W/AP/RHB/PRED/ Construction of Road from DPN Road to Gangaram village via
Package Number Name of Work District
NCRMP/B-W/AP/MPCS/PRED/
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 139/194
NCRMP/B W/AP/MPCS/PRED/08/Ulavapadu/008
Construction of cyclone shelter at Alagayapalem Prakasam
NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/016
Construction of Road from M. C. Road to West ST Colony of Veerapalli
Prakasam
NCRMP/B-W/AP/RCS/PRED/08/S.Konda&Tangutur/010
Road from Woollapalem R&B road to Devalampallipalem CS Prakasam
NCRMP/B-W/AP/RCS/PRED/09/Kavali/024
Construction of Road from Annagaripalem R&B road toPedanattu Pattapupalem
Nellore
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 140/194
Annexure - G
Environment & Social Issues
Environment and Social Issues in the NCRMP works in all districts to the end of 31.12.2013
Date of Soc &
Env visitTPQA observation Action Taken
Sl.No.of
Pkg
Package Nos.
c a t a g o r y Agreement
Amount(Lakhs)/
Date
DFC S l . N o o f
w o r k
P r o
j e c t
c o d e
Name of the Work Stage of work
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 141/194
1 2 3 4 5 6 7 8 9 10 11 12
1
NCRMP/B-W/ AP/RCS/
PRED/09/Tada/009
R C S 104.300
14.09.1213.09.13 1
Y 2 - 2
4 1 Providing BT road to
Pedapannamgadu inTada Mandal
Earth work, GSB WBMGr-II & III and BT
completed.11.11.13
Project information board shallbe erected at the site. Necessaryaction shall be taken to clear theobstrcutions on both the sides of
the road to avoid accidents.
The field staff initiated
the process.
2 Y 2 - 2
4 4
Road fromRamudupalem on
R&B road toPallipalem
WMM is Progress 06.06.13
Electrical cables are crossingthe road which are dangerous tothe road users. There is no landon eitherside to shift the poles.
One elctrical pole is in thecarriageway at km 2/6. All these
need to be relocated. Safetymeasures shall be taken to the
culvert under construction.
No action was takenby the field staff.
3 Y 2 - 2
4 5
Road from Korutur toPattapupalem
Earth work, ventedroad dam, CD works&. GSB Completed.WMM is in progress
11.11.13Road width is not suffiecient dueto houses and few trees on the
both th sides of the road.
The line depatmentapproached the village
community and withtheir help started
removing theobstructions.
3
NCRMP/B-W/ AP/RCS/PRED/09/Kavali/02o
R C S 369.51
20.03.1319.06.14 4
Y 2 - 2
4 6 Road from 230/6 km
of M.C of Pedapattapupalem
WMM is Progress11.11.1326.12.13
The contractor not providedpersonal protective equipment to
the workers.
The contractorprovided personal
protective equipmentto the workers.
5 Y 2 - 2
4 7
Road from R&B roadto Utukuru Pallipalem
Earth work and GSBare completed.
11.11.1326.12.13
Road width is not suffiecient.Houses and few trees inobstruction the both th sides of the road. Necessary action shall
be taken to clear theobstructions.
The field staff initiatedthe process.
2
NCRMP/B-W/ AP/RCS/
PRED/09/ I.
Pet/018
R C S 369.51
20.03.1319.06.14
NELLORE DISTRICT
Page 140 of 193Page 140 of 193
1 2 3 4 5 6 7 8 9 10 11 12
9
Temporary walls are inobstruction on eitherside of the
road at Km 1/6 to 1/8. A
The line deptapproached the village
community and thevillagers are not
accepting to cut the
4
NCRMP/B-W/ AP/RCS/PRED/09/
Vidavaluru /021 R C S 497.800
20.03.1319.06.14
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 142/194
6 Y 2 - 2
4 9
Ponnapudi R&B roadto Busagadipalem
Earth work & GSB arecompleted.
07.06.13religious tree is nearby the
carriageway is in obstruction tothe road. Necessary action shall
be taken to clear theobstructions.
accepting to cut thetree or its branches.They suggested toprovide reflective
colour on the trunk of the tree to avoid
accidents.
5
NCRMP/B-W/ AP/RCS/PRED/09/
Chillakur/015 R C S 112.77
21.03.1320.03.14 7
Y 2 - 2
5 3 Road from R&B road
(via) Narravaripalemto Srinivasa Satram
Earth work forwidening is
completed.GSBCompleted.WMM is in
Progress
06.06.13
Two water taps are inobstruction on LHS of the roadfrom Km 2/6 to Km 2/8. Safetymeasures shall be provided tothe workers at the worksite.
The TPQA consultantinsisted the line
department to takenecessary action and
the contractor initatedthe process.
6
NCRMP/B-W/ AP/RCS/PRED/09/Kota/016
R C
S 157.20020.03.13 19.03.14 8 Y
2 - 2 5 4
Road from R&B Roadto Doruvukatta road
(via) Allampadu,Deyyaladibba
Earth work forwidening, GSB, CC
pavement ,CD works ,WMM and BT
completed.
06.06.13
Two electrical poles are in thecarriageway at Km 1/8 and Km
2/8. Trees are there onbothsides of the road in the
shoulders. A transformer is onthe LHS of the road and near tothe carriageway shall be shifted
to avoid accidents.
The field staff initiatedthe process.
7 R C S 157.200
20.03.1319.03.14 9
Y 2 - 2
5 5
Road fromKothakoduru -
Katepalli road toPathapattapupalem
Earth work forwidening, GSB, CC
pavement, CD works ,WMM and BT
completed.
06.06.13Trees are in obstruction in theentire stretch of the road on
both the sides.
No action was takenby the field staff.
8 R C S 157.200
20.03.1319.03.14 10
Y 2 - 2
5 6 Road from C.SPuram to
Edurupalem
Earth work forwidening, GSB, CC
pavement ,CD works ,WMM and BT
completed.
06.06.1320.12.13
Two pipe lines and two watersumps and pressure release
valve of RWS department are inthe carriageway on RHS from Km
1/1 to 1/2.
The electrical poles arein obstruction in the
carriageway areshifted. No action was
taken by the linedepartment for theremaining works.
NCRMP/B-W/ AP/RCS/PRED/09/ T.P .Gudurand Muthkur
/019
Page 141 of 193Page 141 of 193
1 2 3 4 5 6 7 8 9 10 11 12
9
NCRMP/B-W/ AP/RCS/PRED/09/Tada/024
R C S 97.55
22.03.1321.03.14 11
Y 2 - 2
5 9 Road from @ Km
65/4 of CK Road toTada Kuppam CS
Earth work forwidening,CD, GSB and
WMM and BTcompleted.
11.11.13
Project information board shallbe erected at the site. Necessary
action shall be taken for theelectrical lines crossing the road
and hanging low to avoid
The line department isapproaching the
TRANSCO fornecessary action.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 143/194
Tada/024 completed. and hanging low to avoidaccidents.
necessary action.
10
NCRMP/B-W/ AP/RHB/PRED/09/ Allur/019
R H B 249.24
18.03.1317.03.14 12
Y 2 - 4
2 0
Salt Road fromIskapalli to Salt fields
at KothaKurrupattapupalem
CD works completed.07.06.1320.12.13
NCR has given due to failure toprovide the temporary shelter to
the workers.
A temporary shelterwas provided by the
contractor to theworkers.
13 Y 2 - 4
2 9
Ponnapudi – UtukurR&B road To Kothuru
Earth work forwidening and GSB
completed.12.11.13
Two village platforms areobstruction in the carriage way.Necessary action shall be takento avoid problems for the road
users.
The department isnegotiating with the
community.
14 Y 2 - 4
3 2 Road from
Ponnapudi R&B roadto Ponnapudi
Earth work, GSB & CCpavement are
completed07.06.13
Two village platforms areobstruction in the carriage way
at Km 1/3 and 1/8. Linedepartment shall take immediateaction to avoid problems for the
road users. Necessary actionshall be to shift the electrical
poles are in obstruction in theentire stretch of the road.
The department isnegotiating with the
community.
12
NCRMP/B-W/ AP/RHB/PRED/09/
V.Chalam/021 R H B 69.400
08.02.1307.11.13 15
Y 2 - 4
3 5
Road fromThirumalammapalem
R&B Road toGajulapalli Koneru
WMM & BT arecompleted.
12.11.13
At Km 2.400 the work wasstopped due to court case. Theland owners are not giving the
consent.
The case is stillpending in the court.
13
NCRMP/B-W/ AP/RHB/
PRED/09/Kota/022
R H B 252.640
19.03.1318.06.14 16
Y 2 - 4
3 6
Road from R&B roadKothapatnam to
Yamadinnepalem(via) Srinivasasatram
WMM work is in
progress.06.06.13
At Kothapatnam a 400 mtsreserve forest comes under the
proposed road. The issue ispending with the forest officials.
Clearance is pending .
The line departmen isapproached the forest
department forclearance.
11
NCRMP/B-W/ AP/RHB/PRED/09/
Vidavaluru /026 R H B 294.86
20.03.1319.06.14
Page 142 of 193Page 142 of 193
1 2 3 4 5 6 7 8 9 10 11 12
1
NCRMP/B-W/AP/MPCS/PRED/03/S Rayavaram/ M
P C S 129.92
20.04.1319.04.13 1
Y 2 - 0
5 7
Construction of CS atBangarampalem I &
II H/o Vakadu. (Type
Earthwork excavationstopped due to site
dispute. Alternate sitei id tifi d d
25.09.13The village proposed to be
aquired as Naval base.
The field officersinformed the higher
authorities forll ti f th
VISHAKHAPATNAM DISTRICT
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 144/194
y009
Y ( ypD)
is identified andapproval is pending.
qcancellation of the
work
2 Y 2 - 1
6 5
Road from R&B roadto
Chinanagamayyapalem CS
WBM Gr-III From KM0.000 to Km 0.800
completed.
25.09.13
Work was stopped due to forestland from km 0/860 to km 1/525.
Forest Clearance is pending.
Electric poles are close to thecarriageway.
survey has been doneby the concerned
department. The file is
pending with theconservator of forests.
3 Y 2 - 1
6 6
Road from R&B roadto Annavaram CS
WBMGr-III and OGPC+ Seal coat from 0.00
to Km1.057completed.
25.09.13
A Pump house is in obstructionon the shoulder on the LHS of the road. Personal protectionequipment for workers in notprovided by the contractor.
Personal protectionequipment for
workers provided bythe contractor
3
NCRMP/B-W/ AP/RCS/PRED/03/
Rambilli/007 R C S 38.78
11.03.1310.09.13 4
Y 2 - 1
6 8
Road from R&B roadto Kothapatnam CS
Earth work, subgrade,GSB, shoulders
and CC Road work completed from KM
0.000 to KM 0.610.
25.09.13
A Water tap is in the adjoiningthe road. Necessary action shallbe taken for the compound walland steps of the house adjoining
the carriageway of the road.
The compound wall isremoved to a possible
extent.
5 Y 2 - 2
8 0
Road from R&B roadto Rajavaram
One pipe culvert, WBMGr-II &III, OGPC+sealcoat completed from
KM 0.0 to 0.425
25.09.13
Necessary action shall be takenfor the electrical poles in
obstrution near the carriagewayon both sides of the road.
The line departmentapplied for TRANSCOto shift the electrical
poles.
6 Y 2 - 2
8 2 Road from R&B road
to Gajareddipalemvia Venkaypalem
GSB work completed. 25.09.13
A stretch of 300 mtrs. of roadfrom Km 1/6 to 1/9 is not taken
up due to obstruction of twothatched houses, some trees and
electrical poles. A compound
wall on the right side andfarmers land in the left side arein obstruction in the shoulder of the road between Km 2/652 and
2/658.
The line departmentofficers informed thatthey are pursuing the
matter with landowners.
2NCRMP/B-W/
AP/RCS/PRED/03/
Bheemili/005 R C S 78.44
11.03.1310.12.13
4
NCRMP/B-W/ AP/RHB/PRED/03/
Payakaraopeta /005
R H B 189.59
07.03.1306.06.14
Page 143 of 193Page 143 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 145/194
1 2 3 4 5 6 7 8 9 10 11 12
5
NCRMP/B-W/ AP/MPCS/PRED/01/
VK / 013 M P C S 239.55
15.03.1314.06.14 7
Y 2 - 0
2 5
Construction of MPCSin Metturu (Type D)
PCC for Footings,footings, pedestals andcolumns up to bottom
of plinth beam arecompleted, Back filling
08.07.13,28.11.13
3 temples adjascent to theworksite shall be protected.
.Barricading shall be provided toprotect the the worksite.
H k i h ll b
The TPQA consultantinsisted the linedepartment for
i
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 146/194
V.Kotturu / 013p , g
in foundation is inprogress.
Housekeeping shall bemaintained properly
necessary action.
6
NCRMP/B-W/AP/MPCS/PRED/01/
Santhabommalli /014
M P C S 116.89
20.03.13 19.03.14 8 Y 2 - 0
2 7 Construction of MPCS
in R.Sunnapally(Type C)
Earth work is in
progress
08.07.13,
27.11.13
Caution board is required for the
worksite.Barricading shall beprovided for the worksite.
The TPQA consultantinsisted the line
department fornecessary action.
9 Y 2 - 0
2 8 Construction of MPCS
in Calingapatnam(Type D)
Plinth beam completed05.07.13,27.11.13
Barricading shall be provided toprotect the worksite.
Housekeeping shall bemaintained properly. A
temporary shed provided for thestoring the chemicals and othermaterial shall be kept as per the
standards of the agreement.
The line department isinsisting the contractor
to implement theconditions in the
agreement.
10 Y 2 - 0
2 9 Construction of MPCS
in Bandaruvanipeta(Type D)
Earthwork Excavation,PCC for footings, RCCfootings, pedestals & columns upto bottom
of plinth beam andBack filling in
foundation completed.
05.07.13,27.11.13
Barricading shall be provided toprotect the worksite.
The contractor is inthe process of
barricading the site.
8
NCRMP/B-W/ AP/MPCS/
PRED/01/Polaki/018 M
P C S 92.48
15.03.1314.03.14 11
Y 2
- 0 3 0 Construction of MPCS
in Akkuvaram(Type C)
PCC completed,Reinforcement for
footings is in progress.
05.07.13,
27.11.13
Barricading shall be provided to
protect the worksite.
NCR already given bythe concerned TPQA site engineer in the
month of June, 2013.Till now no action hastaken.
7
NCRMP/B-W/ AP/MPCS/PRED/01/Gara/015
M P C S 251.57
15.03.1314.06.14
Page 145 of 193Page 145 of 193
1 2 3 4 5 6 7 8 9 10 11 12
9 12 Y 2 - 0
3 1 Construction of MPCS
in Jaganadhapuram(Type B)
PCC, Footings & columns below plinthbeam completed and
back filling is inprogress.
08.07.13,27.11.13
Barricading shall be provided toprotect the worksite.
No action was takenby the field staff.
NCRMP/B-W/AP/MPCS/PRED/01/ C
S 178.26
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 147/194
p g
10 13 Y 2 - 0
3 2 Construction of MPCS
in Kottamukkam(Type A)
PCC, Reinforcement,shuttering for footings
completed.
05.07.13,26.11.13
Barricading shall be provided toprotect the worksite.
No action was takenby the field staff.
14 Y 2 - 0
3 6 Construction of MPCS
in Patadibbalapalem(Type A)
Footings, columnsbelow plinth beam
completed
07.07.13,28.11.13
Barricading shall be provided toprotect the worksite.
The contractorinitiated the process of
barricading.
15 Y 2 - 0
3 7 Construction of MPCS
in Bontalakoduru(Type B)
Earth work Completed08.07.13,28.11.13
Barricading shall be provided toprotect the worksite.
No action was takenby the field staff.
16 Y 2 - 1
4 5 Road from
Chinnavanka toGopaladavooru
Earth work completed07.07.13,28.11.13
1. Necessary action shall be
taken for the temple and tap inobstruction on the shoulder onRHS of the road in Km 0.1. 2.Statuatory Clearances, PUCCertificates and EMP are notSubmitted by the contractor.
The contractor is inthe process obtaining
the statuatoryclearances.
17 Y 2 - 1
4 6 Road from MN peta
Road to Kondavooruand CS
Earth work completed 26.11.13Project information board with
details is not erected at the site.
The contrator said thatthere is no provision
for project informationboard in theagreement.
18 Y 2 - 1
4 8
Road from KothapetaRoad to Sainooru CS
Earth work completed06.07.13,27.11.13
Rain Gullies are there on theshoulder in the entire stretch of
the road.
The contractor is inthe process of rectifying the
shoulders of the road.
MPCS/PRED/01/Ranastalam
/016 M P C 178.26
15.03.1314.06.14
11
NCRMP/B-W/ AP/MPCS/PRED/01/
Etcherla/017A M P C S 176.94
03.04.1302.07.14
12
NCRMP/B-W/ AP/RCS/PRED/01/
V.Kottoru/001 R C S 136.07
15.03.1314.03.14
Page 146 of 193Page 146 of 193
1 2 3 4 5 6 7 8 9 10 11 12
19 Y 2 - 1
5 4 Yeeramukkam – Rati
R&B road toDunnavooru
26.11.13 No sufficient width for the road.The line department is
finding the solution.
20 1 5 5
Road from Yeeramukkam – Rati
26 11 13 N ffi i t idth f th dThe line department is
NCRMP/B-W/AP/RCS/ S 123 36
Road widening is in
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 148/194
20 Y 2 - 1
R&B roadGeddavooru
26.11.13 No sufficient width for the road.p
finding the solution.
21 Y 2 - 1
5 6 Road from R&B road
Ganguwada to road
to Sigalaputtuga
26.11.13
Necessary action shall be takenfor the electrical poles in
obstruction on the LHS of theroad to avoid accidents.
The line department isapproaching the
TRANSCO fornecessary action.
14
NCRMP/B-W/AP/RCS/PRED/01/
Etcherla & Ranasathalam
/012
R C S 162.54
15.03.1314.03.14 22
Y 2 - 1
5 8 Road from R&B road
toPathadibbalapalem
Culverts,GSBcompleted, Road
widening is in progress
07.07.13,27.11.13
The electrical lines are hanginglow and the height shall be
raised to avoid accidents on theshoulder on LHS of the roadfrom km 0.800 to Km 0.900.
No action was takenby the field staff.
23 Y 2 - 2
6 6
Road from R&B roadto Marripadu
GSB completed06.07.13,27.11.13
Land acquisiton problem for 100mts is resolved by the
consultations with the villagersby the TPQA consultant at Km
0/0.
The TPQA consultantand line department
resolved the landacquisition problem
with the help of Villagecommunity.
24 Y 2 - 2
6 7
Road from R&B Roadto Kakarapalli
Road widening is inprogress
26.11.1320.12.13
Road has no sufficient width dueto railway track.
The proposedalignment is crossingthe railway lines in
0/4. It will be aunmanned railway
crossing if the road islaid according to thepropasal. The railway
level crossing isobserved within 300
mts from the proposedalignment. The field
officers are requestedto examine the
alignment.
13 AP/RCS/PRED/01/
Mandasa/010 R C S 123.36
15.03.1314.03.14 progress, earth work,
culverts is in progress.
15
NCRMP/B-W/ AP/RHB/PRED/01/
Santhabommali /001A
R H B 118.46
25.03.1324.06.14
Page 147 of 193Page 147 of 193
1 2 3 4 5 6 7 8 9 10 11 12
25 Y 2 - 2
6 8
Road from R&B roadto Marripadu
GSB completed 26.11.13No Project sign board is erected
from the project site.
The contrator said thatthere is no provision
for project informationboard in theagreement.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 149/194
16
NCRMP/B-W/ AP/RHB/PRED/01/
Santhabommali /001B
R H B 216.17
23.03.1322.09.14 26
Y 2 - 2
7 0
Road from DPN roadto Gangaram Village
via Palatalagam,Srikrishnapuram
Bridge excavationcompleted.
06.07.13,27.11.13
Land acquisiton problem isresolved with the cooperation of
the villagers.
Land acquisitonproblem is resolvedwith the cooperation
of the villagers
17
NCRMP/B-W/ AP/RHB/PRED/01/Polaki/007
R H B 164.92
20.03.1319.03.14 27
Y 2 - 2
7 3
DPN road to DLPuram jn. via
Koduru,Magathapadu,
Guppidipeta
Culverts completed,WBM GR-II laying is in
progress26.11.13
Caution boadrs shall be providednear the culvers under
construction and S curves in theentire stretch of the road.
The contractor ismaking necessary
arragements for thecaution boards.
18
NCRMP/B-W/ AP/Br/R&B/
01/Uppugedda /002
R & B -
B r
119.5617.12.10
16.06.12EOAT
approvedup to
30.07.13
28 Y 2 - 4
3 8
Construction of Highlevel bridge acrossUppugedda at KM7/6 of Srikakulammuncipal limits toPukkalapeta via
Killipalem
Approach road SDBCwork pending
27.11.13
It is a private land. The linedepartment discussing with theconcerned persons to resolve
the issue.
Consultations aregoing on with the
concerned persons.
1
NCRMP/B-W/ AP/RCS/PRED/04/
I.Polavaram /003
M P C S 33.00
08.03.1307.09.13
Y2-063
Construction of CS atBhiravapalem
Work not Started 11.11.13 A case filed by the contractor in
the civil court.
2
NCRMP/B-W/
AP/RCS/PRED/04/Katrenikona /006
M P C S
33.0008.03.13 07.09.13 Y 2 - 0
6 5
Construction of CS atBasulutippa Work not Started 11.11.13 A case filed by the contractor inthe civil court.
EAST GODAVARI DISTRICT
In the earlier project,this work stopped due
to deviations in thedesign of the cyclone
shelter. Thecontractor who got thecontract in the earlierproject approached
court for the sanctionof the project underNCRMP. The case is
pending with thecourt.
Page 148 of 193Page 148 of 193
1 2 3 4 5 6 7 8 9 10 11 12
1st proposed site for KaravakaMPCS in Indiramma colony. Site
area is sufficient but the villagersare not accepting the location
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 150/194
3
NCRMP/B-W/ AP/RCS/PRED/04/
Mamidikuduru /013
R C S 33.00
08.03.1307.09.13 1
Y 2 - 1
7 5
Road from R&B roadto Karavaka CS
2no. Pipe Culvert, EW,Selected earth
completed fromKm.0.500 to 0.800.
Road was stopped dueto land problem for
Karavaka MPCS
23.10.1303.01.14
after the work is awarded. 2ndproposed site is near Panchayatoffice which was also deferred.
3rd proposed site in thecompound of Anganavadi
building. This building needs tobe dismantled. Even after that
the site area is not sufficient forMPCS construction. It was clearly
informed the villagers that this3rd proposed site is not suitable.
The line departmentofficers informed that
they are discussingwith the stakeholders
to finalize the site forcyclone shelter.
4
NCRMP/B-W/AP/RCS/PRED/04/Mamidikuduru
/013 M P C S 94.00
22.04.1321.04.14 2
Y 2 - 0
7 8
Construction of CS atKaravaka (Type B)
Earthwork is inprogress
03.01.14The work was stopped due to
land problem for cyclone shelter. Problem resolved.Earth work started.
5
NCRMP/B-W/ AP/RCS/PRED/04/
Malikipuram/009 M P C S
04.04.13 03.04.14 3 Y 2 - 1
7 1 Road from R & B
Road to Kesanapalli(New) CS
Jungle clearance is inprogress
03.01.14
Site proposed is Governmentland adjacent to Rural Dev
building. Original site identified isin ZPHS compound. But the
villagers wanted it in the villagecenter. New Site for Kesanapalli
(Makipuram Mandal) MPCSproposed by villagers and local
representatives. The shrubs andtrees are to be cleared and the
site is to be handed over to thecontractor. Work will be startedafter the MPCS site is handed
over
Site is finalized. Work was started.
Page 149 of 193Page 149 of 193
1 2 3 4 5 6 7 8 9 10 11 12
6
NCRMP/B-W/AP/RHB/PRED/04/
Katrenikona /014
R H B 155.00
27.04.1326.04.14 4
Y 2 - 2
9 6 Road from R&B road
to RamalayampetaPallamkurru (v)
Sub. Grade is inProgress.
03.09.1323.10.13
Necessary action shall be takenfor the 38 electrical poles are in
obstruction on both sides theroad. 3 Neem trees are also
close to the carriageway.
The line department isapproaching the
TRANSCO fornecessary action.
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 151/194
7
NCRMP/B-W/ AP/RHB/PRED/04/
Katrenikona /016
R H B 157.00
30.03.1329.03.14 5
Y 2 - 2
9 7 Road from N.
Kothapalli to G.Pora
in Katrenikone (v)
Sub. Grade is inProgress.
03.09.1323.10.13
8 coconut trees are inobstruction on the shoulders of
the road. Field channels aregoing through on eitherside of
the road. Necessary action shallbe taken by the line department.Guard posts need to be placed at
locations.
The line department isapproaching the land
owners necessaryaction.
8
NCRMP/B-W/ AP/Br/R&B/ 04/
Pampa Yeru-1 /015
B r i d g e
505.0026.03.13
25.09.14 6 Y 2 - 4
4 4
Construction of Bridge at Km 43/10
of Vakalapudi -Edatam road acrossPampa Yeru in EG
District.
Abutments 1,2, Piers1,2,3 and 4 Wells
concrete and shinkingin progress.
24.10.13Necessary action shall be taken
for the five electrical poles are inobstruction in the approach road
The line department isapproaching the
TRANSCO fornecessary action.
9
NCRMP/B-W/ AP/Br/R&B/
04/Pampa Yeru-2 /016
B r i d g e
355.0025.03.13
24.09.14 7 Y 2 - 4
4 5
Construction of Bridge at Km 43/6 of
Vakalapudi - Edatamroad across Pampa
Yeru in EG District.
Abutments1 wellpluging completed.
Abutment 2, Piers 1,2,Wells concrete and
shinking in progress.
24.10.13
Necessary action shall be takenfor the eight electrical poles arein obstruction in the approach
road
The line department isapproaching the
TRANSCO fornecessary action.
2
NCRMP/B-W/ AP/RCS/PRED/06/
Machilipatnam /008
R C S 270.096
22.03.1321.04.14 2
Y 2 - 2
1 1
Road fromKammavanicheruvu
R&B road to Venkata
durgambapuram inMachilipatnam
Mandal
Earth work, GSB,
WMM completed.15.10.13
The line department and TPQA discussing with the stakeholders
resolve the land issue of theroad.
The issue may settlle
within 15 to 20 days.
KRISHNA DISTRICT
Page 150 of 193Page 150 of 193
1 2 3 4 5 6 7 8 9 10 11 12
3
NCRMP/B-W/ AP/RHB/PRED/06/
Koduru/005 R H B 206.00
22.03.1321.03.14 3
Y 2 - 3
2 9
Road from R&B Roadto Krishnapuram
Earth work, All CDwork, GSB, WMM 2ndlayer completed from
km 1.200 to 2.560
15.10.13Personal protective equipment
shall be provided to the workersby the contractor.
Personal protectiveequipment provided to
the workers by thecontractor.
NCR Closed on 03 01
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 152/194
4
NCRMP/B-W/AP/RHB/PRED/06/Nagayalanka
/008 R H B 274.69
25.03.1324.06.14 4
Y 2 - 3
3 6
Road from R&B roadto Pedagowdapalem
WMM 1st layer is inprogress.
15.10.13
Necessary action shall be shiftedto shift the one electric pole inthe carriageway at Km 0/4 to0/5. NCR issued on 23.08.13.
NCR Closed on 03-01-14. One electrical pole
was shifted to saferplace at chianage
0/213 mts.
1
NCRMP/B-W/ AP/RCS/PRED/05/
Achanta/002 R C S 140.53
30.03.1329.03.14 1
Y 2 - 1
7 8
Road from R&B roadto Ayodya lanka
Marrimula CS. (CCRoad)
Sub grade completed. 27.09.1364 electrical poles are in
obstruction on eitherside of theroad.
The line department isapproaching the
TRANSCO fornecessary action.
NCRMP/B-W/ AP/RCS/PRED/
05/Mogaltur/005
R C S 213.56
20.03.1319.06.14 2
Y 2 - 1
8 3 Road from Narsapur
Perupalem R&B roadto Mandavarithota
GSB completed 27.09.13 Temple steps are in obstructionto the road on the shoulder LHS.
The line department isapproaching the
Villagers for solution.
3NCRMP/B-W/AP/RCS/PRED/05/
Narsapur/006 R
C S 159.14
21.03.1320.03.13 4
Y 2 - 1
8 6
R&B road toChinamynavanilanka
GSB Completed. 26.09.13 A temple is in obstruction on the
shoulder on LHS at Km 1.250
The line department isapproaching the
Villagers for solution
4NCRMP/B-W/AP/RHB/PRED/05/
Kalla/004 R
H B 92.36
08.03.135
Y 2 - 2
9 9 K.G. R&B Road to
Mamidipudi of Kalawapudi.
Work completed 26.09.13
1. Upto 1.5Km shoulder Problemis there. Right side there is a
tank and left side there is a fieldcanal. 2. Nine electrical poles arein the entire stretch of the road.
3. Again a field canal is inobstruction on the RHS from Km1.750 to 1.900 and a field canal
on the LHS from Km 1.000 to1.500. 4. Both sides Ponds are in
obstruction from Km 0.900 to1.800. 5. A Palm tree is in
obstruction near the c.way onthe LHS and a cement bench in
RHS at Km 2.050
No action was takenby the field staff.
WEST GODAVARI DISTRICT
Page 151 of 193Page 151 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 153/194
1 2 3 4 5 6 7 8 9 10 11 12
12 Y 2 - 3
2 0 R&B road to
Pedathota of Turputallu
Sub grade, GSB,WMM, CD Works
completed. ShouldersWork is in progress.
26.09.13Two water sumps on eitherside
shall be covered properly toaviod accidents at Km 0.050.
The line department isapproaching the
Villagers for solution
9NCRMP/B-W/AP/RHB/PRED/05/ 14 3
2 4
R&B road toSub grade Completed.GSB M i l ll i 26 09 13
Barricading and caution boardsh ll b id d h l
No action was taken
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 154/194
9 RHB/PRED/05/Narsapur/013
14 Y 2 - 3
EvanivarimerakaGSB Material collectionCD Work in Progress
26.09.13 shall be provided to the culvertunder construction at Km 0.020.
by the field staff.
1
NCRMP/B-W/AP/
RCS/PRED/02/Bhogapuram /001
R C S 94.9614.03.13 13.03.14 1
Y 2 - 1
6 0
R&B Road toGudepuvalasa CS Jungle clearance 21.09.13 A temporary hut is in obstructionfor the road. Problem resolved.
1
NCRMP/B-W/ AP/RCS/PRED/07/
Bapatla/006 R C S 93.07
01.04.1320.12.13 1
Y 2 - 2
2 6
Adavipallipalem R&BRoad to New
Tsunami Colony (via)Krupanagar colony,
Adavi Village
Work not Started 21.10.13
At Km 0/0 a compound wall isin obstruction to start the road.The owner of the house is notwilling to objections. Work was
delayed.
The line department isapproaching the land
owner for solution
2NCRMP/B-W/
AP/BR/ R&B/07/Pedapalli /022 B
r i d g e
137.0012.03.13
11.03.14 2 Y 2 - 4
5 4
Reconstruction of bridge across
pedapalli drain at km14/60of chandole
bridge toNizampatnam inGuntur District
Raft Concrete work Completed (M20
GRADE), piers and Abutment work in
progress.
21.10.13
Proper safety arrangements arenot provided at the bridge site.
Refelctive sign boards shall beprovided near the bridge site. Along the diversion painted
guardstones shall be provided onboth sides. Partition wall may be
constructed on both theabutements and painted withreflective paint to guide the
public during night time.
NCR has been issued .Safety barricading
arranged . NCR closedon 22.11.13
3
NCRMP/B-W/AP/MPCS/PRED/07/
Nizampatnam /004 M
P C S 86.83
22.03.13 _ 3
Y 2 - 0
9 7
Construction of CS inSanjeev nagar of
Kothapalem (Type -B)
Work not Started Villagers objected the original
proposed site.
Line departmentofficials shall take
necessary action toresolve the issue.
4
NCRMP/B-W/AP/MPCS/R& B/07/REPALLE/0
05 M P C S 123.37
22.03.13 _ 4
Y 2 - 1
0 1
Construction of Cyclone Shelter in
Lankaladibba (Type-D)
Excavation started.
Villagers objected the proposedsite identifed. The line
department moved to anothersite which falls under forest
lands.
The problem wasresolved after the
discussions with theforest officials by the
public representatives.
VIZIANAGARAM DISTRICT
GUNTUR DISTRICT
Page 153 of 193Page 153 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 155/194
1 2 3 4 5 6 7 8 9 10 11 12
6 Y 2 - 3
9 0
Motupalli R & B Roadto Krishna Nagar
GSB In Progress 22.11.13Road width is not sufficient for
the shoulders.
The line dept is sayingthey will take only the
available width.Further, the line deptmentioned that it is
not possible to do anNCRMP/B-W/
AP/RHB/
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 156/194
not possible to do anyexpansion.
7 Y 2 - 3
9 2 Jeedichetlapalem
R&B road toKunkuduchetlapalem
Earth Work in Progress 22.11.13
Forest department is claimingthat the entire strech of the 2040
mts lies in their land. Linedepartment officials persuing this
issue with the officilas of theforest department.
by the forest dept for340 mts CC road. The
line dept isapproaching the forest
dept for further
8 Y 2 - 3
9 7
KEM R&B road toChinapattapupalem
GSB Completed. 07.06.13
Necessary action shall be takenfor the electrical lines crossing at
Km 0.100 to 0.200. Necessaryaction shall be taken for the
trees in obstrcution on the LHSfrom Km 0.200 to 0.250.
The field staff initiatedthe process.
9 Y 2 - 4
0 2
Salt Road fromMadnur ZP road to
Thotagunta yanadicolony
GSB Completed 25.06.13
Reflective stickers shall bepasted to the trees on both sides
of the road in the shoulders toavoid accidents.
The line departmentinsisted the contractor
to take necessaryaction.
6
NCRMP/B-W/ AP/RHB/PRED/08/
Tangutur/021 R H B 143.00 /
14.04.1310.04.14 10
Y 2 - 4
0 3
Road from Tanguturto Tallapalem (via)
Velagapudi (Km 4/5to 7/465)
GSB Completed, CCCompleted & WBM
Grade-II in Progress
26.06.1322.11.13
NCR has given for the due failureto provide the traffic safetyarrangements and warning
signage boards in the culvertconstruction. Caution shall be
provided at the S curves in theentire stretch of the road.
Traffic safetyarrangements were
made by thecontractor. NCR
closed.
7NCRMP/B-W/AP/RHB/ PRED/08/Tangutur/022 R
H B 131.00 /
14.03.1313.03.14 11
Y 2 - 4
0 4
Tangutur-Ravivaripalem road
@1/2KM toPasukuduru.
GSB Completed, CDWorks Completed &
CC Completed 22.11.13
A reflective stickers shall beprovided on the well to avoid
accidents.
The line departmentinsisted the contractor
to take necessaryaction.
12 Y 2 - 4
0 9 KEM R&B Road to
Vajjireddypalem -Pattapupalem
GSB Comple ted 07.06.13Necessary action shall be takenfor the elec lines crossing theroad from Km 0.100 to 0.200.
The line dept isapproaching the
TRANSCO fornecessary action.
18.03.14
NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam
/019
5
NCRMP/B-W/ AP/RHB/PRED/08/
Kothapatnam/020
R H B 256.00 /
11.03.1310.09.14
8 R H B 240.00 /
15.03.1314.06.14
4 AP/RHB/PRED/08/
Chinaganjam /013
R H B 197.00 /
19.03.13
Page 155 of 193Page 155 of 193
1 2 3 4 5 6 7 8 9 10 11 12
13 Y 2 - 4
1 1 Salt Road from
Madnur ZP road toChinnapattapupalem
GSB Completed 07.06.13
Necessary action shall be takenfor the trees in obstruction on
the LHS of the shoulderfrom Km0.175 to Km 0.200.
The line departmentinsisted the contractor
to take necessaryaction.
1) Guard stones with reflectivestickers shall be provided to the
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 157/194
9
NCRMP/B-W/ AP/RHB/PRED/08/
Ulavapadu /016 R H B 359 /
11.03.1310.06.14 14
Y 2 - 4
1 4 Road From M.C road
to West ST colony of Veerapalli
GSB Comple ted 25.06.13
stickers shall be provided to theRoad on the LHS to avoid
accidents from Km.3/6 to 3/8. 2)Guard stones with relflectivestickers shall be provided on
both the sides of the culvert toavoid accidents at Km 3/150. 3)
A temple is in obstruction on theRHS of the Road and a House isin obstruction on the LHS of the
road. The road width is notadequate at Km. 2/2. 4) All the11 culverts under constructionshall be properly barricaded to
avoid accidents in the entirestretch of the road.
A semi reflective
directive Signboarswere kept by thecontractor. The
process of shifting of electirc poles was
initiated by the linedepartment.
10NCRMP/B-W/AP/RHB/PRED/08/
S.Konda&Tangutur/010
R H B 359 /
11.03.1310.06.14 15
Y 2 - 2
3 6Road from Tangutu
to Anantavaram
Sub grade, GSB,WMM, CD Works
completed.20.11.13
The electrical poles in thecarriageway shall be shifted to
avoid accidents.
The electrical poles inthe carriageway areshifted by the
TRANSCO.
11NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu /008 M
P C S
14.11.13 13.11.15 15 Y 2 - 1
1 2 Constrcution of
Cyclone shelter at Alagayapalem
PCC completed 19.12.13
Permanent barricading at Site,PPE not provided to the workers.Project information board is not
erected at the site.
The TPQA consultantinsisted the line
department to takenecessary action.
Page 156 of 193Page 156 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 158/194
Photo Documentation
Annexure - H
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 159/194
Page 158 of 193Page 158 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 160/194
Page 159 of 193Page 159 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 161/194
Page 160 of 193Page 160 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 162/194
Page 161 of 193Page 161 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 163/194
Page 162 of 193Page 162 of 193
GSB thickness being checked.TPQA inspection on18.11.2013
TPQA-NCRMP inspection R&B road toChinamynavanilanka in Narasapur Mandal of WestGodavari District on 02-12-2013 GSB Completed
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 164/194
GSB width being checked. TPQA inspection on18.11.2013 GSB width and thickness verified as on 18.11.2013GSB Completed. TPQA inspection on 02-12-2013
Page 163 of 193Page 163 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 165/194
Page 164 of 193Page 164 of 193
TPQA-NCRMP inspection Road from ZP Road toSorlagondi in Nagayalanka Mandal of Krishna District on
03-12-2013 SDBC camber being checked.
SDBC width being checked.TPQA inspection on03.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 166/194
SDBC thickness being checked.TPQA inspection on03.12.2013
SDBC width being checked.TPQA inspection on03.12.2013
Page 165 of 193Page 165 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 167/194
Page 166 of 193Page 166 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 168/194
Page 167 of 193Page 167 of 193
TPQA-NCRMP inspection Road from R&B Road to Cyclone Shelter @ Jaruguvanipalem in Koduru Mandal of Krishna District on 09-12-
2013 WMM completed
WMM thickness being checked.TPQA inspection on 09.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 169/194
WMM completed.TPQA inspection on 09.12.2013WMM width being checked.TPQA inspection on 09.12.2013
Page 168 of 193Page 168 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 170/194
Page 169 of 193Page 169 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 171/194
Page 170 of 193Page 170 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 172/194
Page 171 of 193Page 171 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 173/194
Page 172 of 193Page 172 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 174/194
Page 173 of 193Page 173 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 175/194
Page 174 of 193Page 174 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 176/194
Page 175 of 193Page 175 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 177/194
Page 176 of 193Page 176 of 193
TPQA-NCRMP inspection Road from R&B road toParrachivara in Nagayalanka Mandal of Krishna District
on 14-12-2013 WMM completed in cross road No:1
WMM completed.TPQA inspection on 14.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 178/194
WMM thickness being checked.TPQA inspection on
14.12.2013
WMM thickness being checked.TPQA inspection on
14.12.2013
Page 177 of 193Page 177 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 179/194
Page 178 of 193Page 178 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 180/194
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 181/194
Page 180 of 193Page 180 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 182/194
Page 181 of 193Page 181 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 183/194
Page 182 of 193Page 182 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 184/194
Page 183 of 193Page 183 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 185/194
TPQA-NCRMP inspection Road from R&B road toSamanthakuru Cyclone Shelter in East Godavari District. on
23.08.13 Retaining wall completed.
Retaining wall completed.TPQA inspection on 23.08.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 186/194
Retaining wall width being checked.TPQA inspection on 23.08.2013Retaining wall completed.TPQA inspection on 23.08.2013
Page 185 of 193Page 185 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 187/194
TPQA-NCRMP inspection Construction of Cyclone Shelter at V.Kanuru in Machilipatnam Mandal of krishna District.
On 20.12.13 placing of steel reinforcement for footingbeing checked.
M20 PCC footing thickness being checked. TPQAinspection on 22.12.2013
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 188/194
M20 PCC footing width being checked. TPQA inspectionon 22.12.2013
M20 PCC footing completed. TPQA inspection on22.12.2013
Page 187 of 193Page 187 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 189/194
Page 188 of 193Page 188 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 190/194
Page 189 of 193Page 189 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 191/194
Page 190 of 193Page 190 of 193
8/13/2019 NCRMP-TPQA Monthly Progress Report December 2013
http://slidepdf.com/reader/full/ncrmp-tpqa-monthly-progress-report-december-2013 192/194
Page 191 of 193Page 191 of 193