Page 1: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

NEC Annual SeminarWest Island Line Contract No. 713

Re-Provisioning of Kennedy Town Swimming Pool (Phase 2)

08/04/2019 © NEC Contracts 1

Page 2: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Agenda

1. Introduction - MTR WIL Project Manager, Mr. Steve Hamill

2. Project Information

3. Adoption of NEC Contract for Phase 2 swimming pool

4. Aerial Video - Paul Y General Manager, Mr. Stanley Lo

5. Experience Sharing

5.1 Early Completion Bonus

5.2 Project Completion Document

5.3 General Matters

08/04/2019 © NEC Contracts 2

Page 3: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

1. Introduction

MTR WIL Project Manager, Mr. Steve Hamill

08/04/2019 © NEC Contracts 3

Page 4: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

2. Project Information

08/04/2019 © NEC Contracts 4

Page 5: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

08/04/2019 © NEC Contracts 5

West Island Line Overview

Kowloon Peninsula

Hong Kong Island

Kennedy Town Swimming Pool

Page 6: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

08/04/2019 © NEC Contracts 6

West Island Line Overview

7

HKU

Page 7: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

West Island Line Overview

SHW

SYP

HKU

KET

KTSP

Old KTSP

08/04/2019 © NEC Contracts 7

Page 8: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Kennedy Town Station (KET)

KET

Old Swimming Pool

08/04/2019 © NEC Contracts 8

Tree Wall

West Island Line

Page 9: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Elevations

Kennedy Town Praya Elevation

East Elevation Sai Cheung Street North Elevation

Shing Sai Road Elevation

08/04/2019 © NEC Contracts 9

Page 10: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Project Information

Phase 1

Contract 710

Phase 2

Contract 713

Start 14 Jul 2009 1 Sep 2014

Completion 14 Mar 201130 Oct 2016

(3 Nov 2016 – EOT granted)

Contract Period 20 months 26 months

Form of Contract MTR Lump Sum(without quantities)

NEC3 Option A

(with relevant MTR Conditions)

Contract Sum HK$ 311 million

(£27.8 million)

HK$ 671 million

(£60 million)

Gross Floor Area 13,494 m2 7,058 m2

Final Account Apr 2011 Nov 2016 (envisaged)

08/04/2019 © NEC Contracts 10

Page 11: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Scope of Work

1. Bored Piles and Pile Caps

2. Superstructure – RC and Structural Steel

3. Architectural Building Works and Finishes

4. Phase 1 Interfacing and Improvement Works

5. Building Services

6. Built-in Furniture

7. Landscaping

08/04/2019 © NEC Contracts 11

Page 12: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

08/04/2019 © NEC Contracts 12

19

Phase 2Phase 1

Multipurpose Pool

15m x 50m

Training Pool

12.5m x 25m

Jacuzzis

Changing Rooms

Family cum Disabled

Changing Rooms

15 30

Leisure Park

Zone1 Zone2 Zone3

08/04/2019 © NEC Contracts 12

Project Information – Building Facilities

Page 13: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Project Information - Roof 3D Layout

PTFE Fabric

VM Zinc Roof Cladding

Sunshading Area

Structural

Steel Frame

08/04/2019 © NEC Contracts 13

Page 14: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

3. Adoption of NEC Contract

for Phase 2 Swimming Pool

08/04/2019 © NEC Contracts 14

Page 15: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Decision to Adopt NEC3

• Phase I swimming pool carried out under conventional MTR Form of Contract

(lump sum without quantities)

• Phase I opened on time and within budget – so why change for Phase II ?

• Success of Phase I gave good opportunity for comparison study

• MTR Partnering approach well established, therefore moving to more

contractually binding form of partnering contract is a logical progression

08/04/2019 © NEC Contracts 15

Page 16: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

• Hong Kong Government approach towards adopting NEC3 Contract

• MTR always looking to improve on Project Performance

• Success of NEC3 will augment the existing MTR suite of contracts

08/04/2019 © NEC Contracts 16

Decision to Adopt NEC3

Page 17: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Tender Preparation

• Conformed tender documents to comply with NEC3 (Option A)

• Appointment of NEC Contract advisers

• Review NEC3 clauses and modify where necessary (minimal changes and

no Z Clauses)

• Extensive workshop training for both MTR and design consultants’ staff prior

to tender preparation

• Workshop for tenderers to enable understanding of NEC3 tender documents

08/04/2019 © NEC Contracts 17

Page 18: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Contract Award

• Extended NEC advisers’ contract for construction phase

• Conducted start up workshops to explain requirements of NEC form of contract

• Conducted further workshops for MTR, Consultants’ and Contractors’ staff

• Established procedures, design meeting, risk reduction meeting, compensation

event meeting etc. to administer NEC Contract

08/04/2019 © NEC Contracts 18

Page 19: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Early Successes

• Achieved timely and equitable resolutions

– on late access to site

– modified foundations technical problems

• Adopted Potential Early Warning System

• Early implementation of risk reduction measures

08/04/2019 © NEC Contracts 19

Page 20: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Early Successes (cont’d)

• Realized programme savings quickly

• ‘Real time’ updating of cost and programme

• High level ‘buy in’ from the full team

• Developed mutual trust and respect

08/04/2019 © NEC Contracts 20

Page 21: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Current NEC Work Flow System

08/04/2019 © NEC Contracts 21

Page 22: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Via

Sharepoint

by Thur

noon

Risk Reduction Meeting

(2 hours)

Design Meeting (2 hours)

Internal Meeting

(1 hour)

Compensation Event Meeting

(1 hour)

Early Warning Register

PEW Summary

CE Register

Mon Tue Wed Thur Fri

KPI Summary

• Update EAR Register

• Add any PEW / EAR items

By

email

• Review EAR Register

• Review PEW Summary

• Add any PEW from DDC

Submit EAR via ePMS

• Review quotations

• Update CE Register

Risk Reduction

& Mitigation

Cost/ Time Assessment

Prepare DamS

Update

EAR/ PEW

Register

Project Management

Update KPI

Summary for

Weekly

PM Report

Report Writing

NEC3 Work Flow – Regular Meeting Schedule

08/04/2019 © NEC Contracts 22

• Works / CM Meetings to be held bi-weekly on Tuesdays before Risk Reduction Meetings

• Sketch/ DamS/ DIS Register is contained in PEW Summary

Page 23: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

KPI Monitoring Summary

Early Warning and Compensation Event Summary

Current status:1) CE Event Quotations – 98% agreed. 2) Early Warnings - 90% closed out.3) MTR response to Paul Y submissions = Average 10 days.

1st – 7th April 2016

08/04/2019 © NEC Contracts 23

Page 24: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

4. Aerial Video

Paul Y General Manager, Mr. Stanley Lo

08/04/2019 © NEC Contracts 24

Page 25: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

2508/04/2019 © NEC Contracts 25

Page 26: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

08/04/2019 © NEC Contracts 26

Zone 1

Zone 2

Phase 1 Swimming Pool (in use)

Phase 2 Swimming Pool

(Under Construction)

Zone 3

Page 27: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

5. Experience Sharing

5.1 Early Completion Bonus

08/04/2019 © NEC Contracts 27

Page 28: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

08/04/2019 © NEC Contracts 28

Early Completion Bonus

Page 29: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Early Completion Bonus

08/04/2019 © NEC Contracts 29

• The completion of foundation is 4 weeks earlier than planned programme.

• Pursuant to NEC Contract, Paul Y is entitled to a bonus if early completion is indeed achieved

• Paul Y considered it an opportunity to maintain this advancement until the project completionby increasing resources, plant and optimizing construction method / sequence.

• Paul Y submitted an Early Warning on project completion to seek approvals from MTR andLeisure and Cultural Services Department of Hong Kong Government (“LCSD”)

• Early Completion Bonus allows Paul Y to commit additional resources, plant and materials tomaintain 4 weeks programme advancement through early planning and collaborative workingwith MTR and Government.

Page 30: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

Risk Management - Structural Steel Roof

08/04/2019 © NEC Contracts 30

Early Completion Bonus

Page 31: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

• Paul Y issued EAR to alert potential delay which may be caused by early inclement weather

Typical Wet Season

• Wet season is from April to August in Hong Kong.

• Recent rainy days tend to come earlier.

• Measures implemented to ensure Zones 1 & 2 welding

completed before wet season.

• Zone 3 welding activities unavoidably fall in wet season.

Risk on Remaining Structural Steel Roof (Zone 3)

1 2 3 4 5 6 7 8 9 10 11 12

08/04/2019 © NEC Contracts 31

Early Completion Bonus

Page 32: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

• To ensure Zones 1 & 2 welding completed before wet season in

April and to minimize Zone 3 welding during wet season, the

following measures are implemented:

– To increase production rate.

– Since February, the number of welders are increased.

– To increase number of temporary platforms.

Risk Management and Control Measures Actual. Welder Nos.

Jan 5

Feb 7

Mar 8

Apr 8

Total nos. of welders employed in April

08/04/2019 © NEC Contracts 32

Early Completion Bonus

– With this production rate, we target to complete the structural steel roof by 29 April 16.

• Minimized the risk of early wet season

Page 33: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

5. Experience Sharing

5.2 Project Completion Document

08/04/2019 © NEC Contracts 33

Page 34: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

• Sufficient time to be allowed for document preparation for handover of

Government facilities.

• Handover documents at least six months before works completion.

• MTR agreed Paul Y completion document plan and jointly review the

progress on a bi-weekly basis.

Project Completion Document

08/04/2019 © NEC Contracts 34

Page 35: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

5. Experience Sharing

5.3 General Matters

08/04/2019 © NEC Contracts 35

Page 36: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

General Matters• Swimming pool project is MTR and Paul Y’s first NEC Contract.

• During the first 3 months of contract, MTR and Paul Y went through some teethingissues and resulted in some heated debates.

• After that, both MTR and Paul Y acknowledged that mutual trust and respect wereessential for achieving contract goals.

• MTR and Paul Y top managements’ full support.

• MTR and Paul Y invested significant management resources on contract administrationat the early stage, e.g. Risk Reduction Meeting, Compensation Event etc.

08/04/2019 © NEC Contracts 36

Page 37: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues

• NEC Contract provides a forum to promote:– open exchange of ideas and proposals,

– cohesive working relationship between and within both teams

• Early investment of management resources will reduce engineering and QSresources to complete the final account.

08/04/2019 © NEC Contracts 37

General Matters

Page 38: NEC Annual Seminar · • Swimming pool project is MTR and Paul Y’sfirst NEC Contract. • During the first 3 months of contract, MTR and Paul Y went through some teething issues