nem mrl level

Upload: kalyanmalla

Post on 14-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Nem Mrl Level

    1/10

    National Electricity Market

    Management Company LimitedABN 94 072 010 327

    2006 Minimum ReserveLevel Recalculation

  • 7/27/2019 Nem Mrl Level

    2/10

    1.1 INTRODUCTION

    NEMMCO determines minimum reserve levels which are consistent with the ReliabilityStandard. Minimum reserve levels were last reviewed by NEMMCO in 2004, and sincethat time Basslink has been commissioned, Kogan Creek is well advanced, and

    generator forced outage data has been refined and clarified. As a result of thesechanges NEMMCO began modelling to review the current minimum reserve levels. Thiswork was foreshadowed in the 2005 Statement of Opportunities.

    The following sections of this document provide a summary of the:

    process adopted by NEMMCO in the calculation of minimum reserve levels;

    feedback provided by the jurisdictions following briefings on preliminary results;

    additional work conducted to address those concerns raised by the jurisdictions,particularly with regard to input data assumptions;

    the minimum reserve levels being considered for implementation;

    an explanation of negative minimum reserve levels; and

    a regional assessment of the reserve margin available (assuming just sufficient

    generation to just meet the minimum reserve levels) to each NEM region at timeof its 50% POE Scheduled Maximum Demand.

    1.2 PROCESS

    In January 2006 NEMMCO contracted ROAM Consulting to calculate the minimumreserve level for each region of the NEM, with the exception of Tasmania1. ROAMperformed similar work for NEMMCO in the 2003 and 2004 assessments.

    The previous minimum reserve level assessment was completed in 2004. In thatassessment, NEMMCO developed a methodology that aimed to determine:

    - The minimum level of NEM-wide installed capacity required to deliver theReliability Standard in each region.

    This methodology was reviewed by KEMA Consulting, who made a number ofrecommendations regarding the assumptions used in modelling generator performance.To address these recommendations, NEMMCO and the NGF created the ForcedOutage Data Working Group (FODWG). The recommendations of the FODWG havebeen incorporated in the calculation of the generator forced outage statistics used inROAMs assessment. For more information on the FODWG and its activities please referto the following URL: http://www.nemmco.com.au/powersystemops/240-0011.htmOne of the most significant aspects of the FODWG activities was the collection of a set

    of historical forced outage data records on an event by event basis from each NEMscheduled generator. This collection provided NEMMCO with significantly moreinformation than had been collected previously and allowed forced outage rate (FOR)statistics to be calculated by NEMMCO on a consistent basis. Previously NEMMCOrelied on generators to aggregate their own data set into a format suitable for the

    1An assessment of the minimum reserve levels for Tasmania was excluded from the studies.

    Instead the studies focus on assessing the impact of Tasmanian reserve capacity being availableto Victoria and South Australia across Basslink.

    5 October, 2006 Page 2

    http://www.nemmco.com.au/powersystemops/240-0011.htmhttp://www.nemmco.com.au/powersystemops/240-0011.htm
  • 7/27/2019 Nem Mrl Level

    3/10

    calculation of FOR statistics. It is believed that generators may have been inconsistentin their approach to data reporting and aggregation.

    NEMMCO was not confident in the accuracy of the FOR data being used in the 2004minimum reserve level assessment and decided to double the FORs in the

    determination case

    2

    . Given the increased confidence in the recently collected FOR dataset, NEMMCO no longer believes it necessary to double the FORs. Table 1 provides ahigh level summary of the differences between the FORs used in the 2006 and the 2004assessments.

    Note: In the 2006 assessment both a Full Forced Outage Rate (FFOR) and a PartialForced Outage Rate (PFOR) were modelled. For each partial outage a mean derating(MeanDer) was applied to the relevant generator. An Equivalent Forced Outage Rate(EFOR) has been calculated for 2006 statistics to facilitate a comparison between the2006 EFOR and 2004 FOR.

    Table 1 Comparison of forced outage rates used in 2006 and 2004 assessments

    2004 ASSESSMENT

    FFOR PFOR MeanDer EFOR FFOR

    QLD BASE 3.72% 4.42% 16.81% 4.46% 5.00%

    QLD PEAK 7.76% 5.83% 63.69% 11.47% 8.92%

    QLD HYDRO 8.18% 0.26% 40.60% 8.28% 0.24%

    QLD INTER 2.81% 4.70% 20.33% 3.77% 8.88%

    NSW BASE 1.95% 5.95% 16.34% 2.93% 5.22%

    SNOWY 1.78% 0.00% 0.00% 1.78% 1.80%

    VIC BASE 4.62% 19.92% 12.44% 7.10% 3.72%

    VIC PEAK 4.19% 0.17% 10.77% 4.20% 2.30%

    VIC HYDRO 2.90% 2.13% 27.29% 3.48% 1.80%

    SA BASE 3.79% 2.88% 11.23% 4.12% 4.70%

    SA INTER 2.81% 4.70% 20.33% 3.77% 8.88%

    SA PEAK 16.73% 5.55% 60.00% 20.06% 8.92%

    TAS 1.25% 5.43% 21.10% 2.39% n/a

    NERC GADS - New plant 10.00% 0.00% 0.00% n/a n/a

    2006 ASSESSMENT

    In addition to the FOR data, NEMMCO also provided ROAM Consulting with all inputdata required for their calculation of minimum reserve levels and performed shadowstudies on key simulation cases.

    ROAM performed Monte Carlo analysis using their market simulation tool 24C anditeratively adjusted the amount of installed generation in each region to:

    approach 0.002% USE within each region simultaneously; maximise the capability for reserve sharing between regions; and

    approach an outcome which achieves the minimum level of installed generationwithin the NEM as a whole .

    For more information on the process please refer to the attached report MinimumReserve Level Recalculation 2006.

    2The FOR for all plant was doubled with exception to QLD baseload plant

    5 October, 2006 Page 3

  • 7/27/2019 Nem Mrl Level

    4/10

    ROAM provided NEMMCO with preliminary results including a draft set of recommendedminimum reserve levels in March 06 and NEMMCO briefed each of the NEM

    jurisdictions on these results during April.

    1.3 JURISDICTIONAL FEEDBACK ON PRELIMINARY RESULTS - APRIL

    Following the Jurisdictional briefings in April, two Jurisdictions (New South Wales andSouth Australia) raised concerns over some key input data used in the NEMMCOstudies 3.

    The issues raised by the New South Wales jurisdiction related to the assumed timing ofa committed transmission augmentation in New South Wales. Concern was raised thatstudies may have incorrectly modelled the commissioning date of a project, andsubsequent impact on network constraints. NEMMCO has since confirmed that theTransGrid augmentation timing that was used in the simulation studies is consistent withthe advice provided by TransGrid.

    The South Australian jurisdiction raised concern over the forced outage rates (FOR)used in the simulations, particularly for the South Australian peaking class of plant. Toaddress these concerns NEMMCO, ESIPC and the FODWG developed an agreedapproach to re-calculate the FORs for this class of plant. This new approach was moreconsistent with the recently developed definitions by the FODWG and delivered achange in the FOR from 25.1% to 16.73% for the SA peaking plant. The primary driverbehind the change in FOR was the exclusion of loss of availability events due to fuelsupply related outages beyond the control of the generators

    On account of the revision made to the SA peaking class of plant NEMMCO revisited theFOR assumed for new open cycle gas turbines, and existing plant of this type without

    any forced outage data history. NEMMCO requested information from the proponents ofnew committed generation regarding the expected long term FOR of their plant andsourced information from the North American Electric Reliability Council (NERC) GADSwebsite. This work resulted in a change in the FOR for this class of plant from 25.9% to10%.

    The impact of the revised input data on the calculated minimum reserve level was thenassessed. The revised minimum reserve level recommendation is presented in section1.4.

    3As these concerns would take time to resolve and additional sensitivity studies were required,

    this precluded the minimum reserve level results being incorporated in the 2006 SOO/ANTS inearly June 2006. The SOO/ANTS will now be published in October with the existing reservelevels as the basis for all conclusions. The impact of revised minimum reserve levels on the 10year supply-demand outlook will be provided in the Executive Briefing document released withthe 2006 SOO.

    5 October, 2006 Page 4

  • 7/27/2019 Nem Mrl Level

    5/10

    1.4 REVISED RECOMMENDED MINIMUM RESERVE LEVELS

    ROAM recalculated the minimum reserve levels following modifications to the FOR inputdata outlined above. Table 2 identifies the revised minimum reserve levels calculated by

    ROAM to deliver 0.002% USE in each region of the NEM simultaneously4

    .

    Table 2 NEM-Wide Draft Minimum Reserve Levels

    [MW Above M10 Regional Demand Forecast]

    Year QLD* NSW VIC & SA SA*

    2006-07 480 -1490 370 370

    2007-08 560 -1430 360 390

    * This is a local requirement and must be met by generation within the region assuming 0MW

    support from neighboring regions.

    Notes:

    A requirement for a 370 MW (2006-07) minimum reserve level sourcedsolely from within SA was identified. That is, SA must source 370 MW ofgeneration capacity within its own region in excess of the SA 10% POEScheduled Maximum Demand (MD), assuming 0 MW support from VIC.

    Similarly a requirement for a 480 MW (2006-07) minimum reserve levelsourced solely from within QLD was identified, assuming 0 MW supportfrom NSW.

    The minimum reserve levels in Table 2 are consistent with just achieving the ReliabilityStandard in all regions. However, the practical difficulties associated with sourcing370MW of generation in SA in excess of the SA 10% POE Scheduled MD must berecognised. In the near term it is unlikely that a minimum reserve level of 370MW in SA

    will be achievable. If implemented in market systems reserve trader is likely to betriggered, and may fail to deliver the required level of supply.

    In recognition of this practical limitation NEMMCO has re-assessed the minimum reservelevel requirement in South Australia considering the committed level of plant likely to beavailable in Victoria for the 2006-07 and 2007-08 years. That is, ROAM has conductedfurther simulation studies which attempt to minimise the minimum reserve level in South

    Australia through consideration of the capacity available in Victoria. This method:

    increases the combined Victoria and South Australia minimum reserve level;

    reduces the South Australian minimum reserve level; and

    delivers the Reliability Standard in South Australia but better than the ReliabilityStandard in Victoria.

    Table 3 provides a summary of the minimum reserve levels which have been calculatedin this process.

    4Please refer to the attached report Minimum Reserve Level Recalculation 2006 for more

    information regarding the actual simulated USE outcomes.

    5 October, 2006 Page 5

  • 7/27/2019 Nem Mrl Level

    6/10

    Table 3 Reliability Reserve Levels To Be Implented

    [MW Above M10 Regional Demand Forecast]

    Year QLD* NSW VIC & SA SA*

    2006-07 480 -1490 615 -50

    2007-08 560 -1430 615 -50* This is a local requirement and must be met by generation within the region.

    The minimum reserve levels in Table 3 were approved by the NEMMCO Board andnoted by the Reliability Panel in September 2006.

    1.5 EXPLANATION OF NEGATIVE MINIMUM RESERVE LEVELS

    NEMMCO notes from previous discussions with jurisdictions and market participants thatit may be necessary to provide an explanation of how a region may have a negativeminimum reserve level. Figure 1.5 illustrates the relationship between the requiredscheduled generation in each region and the minimum reserve levels in Table 3 for the

    2006-07 year, assuming: regional transfers that are simultaneously feasible;

    interconnector transfers used to determine the minimum reserve levels in Table 3;

    spare capacity in Tasmania is fully allocated to Victoria;

    Snowy generation is fully allocated to Victoria and New South Wales; and

    scheduled generation capacity in the Snowy region equal to that when determining

    the minimum reserve levels in Table 3.

    Considering New South Wales minimum reserve level of -1490 MW:

    NSW can have a negative minimum reserve level because NSW has the ability to share

    spare generation capacity from QLD, Snowy and VIC/SA (480 MW + 615 MW) usingspare transfer capability on the interconnectors. The NSW minimum reserve level has

    been determined assuming transfers from QLD and Snowy of 1878 MW. Assuming a

    maximum import capability into NSW of approximately 4000 MW (2900MW on Snowy1

    and 1100MW from Qld) there is 2122 MW spare import capability. This spare import

    capability provides NSW with access to share significant spare capacity with neighboring

    regions. As a result NSW can have such large negative minimum reserve level.

    5 October, 2006 Page 6

  • 7/27/2019 Nem Mrl Level

    7/10

    Figure 1.5QUEENSLAND

    Minimum reserve level 480

    Transfers from NSW 0

    0 Actual import capability into QLD from NSW 300

    Spare import capability into QLD 300

    NEW SOUTH WALES

    Minimum reserve level -1,490

    1,878 Transfers from QLD and Snowy 1,878

    Actual import capability into NSW from QLD and Snowy 4,000

    Spare import capability into NSW 2,122

    SNOWY

    No minimum reserve level requirement

    1,900 Scheduled generation 3,778

    VICTORIA AND SOUTH AUSTRALIA

    Minimum reserve level 615

    Transfers from Snowy and TAS 2,510

    610 Actual import capability into VIC and SA from Snowy and TAS 2,510

    Spare import capability into VIC 0

    TASMANIA

    Minimum reserve level 144

    Transfers to TAS from VIC -610

    Actual import capability into TAS from VIC 500

    Spare import capability into TAS 1,110

    All numbers in MW except as otherwise signed.

    Scheduled generation required = QLD 10% POE Scheduled demand - QLD DSP + QLD minimum reserve level

    (480) - transfers from NSW

    Scheduled generation required = NSW 10% POE Scheduled demand - NSW DSP + NSW minimum reserve

    level (-1490) - transfers from QLD and Snowy

    Scheduled generation required = TAS 10% POE Scheduled demand - TAS DSP + TAS minimum reserve level

    (144) - transfers from VIC

    Scheduled generation required = VIC 10% POE Scheduled demand + SA 10% POE scheduled demand - VIC

    and SA DSP + VIC and SA minimum reserve level (615) - transfers from TAS and Snowy

    Snowy

    VIC AND SA

    TAS

    NSW

    QLD

    1.6 REGIONAL RESERVE MARGIN AT TIME OF 50% POE SCHEDULED

    MAXIMUM DEMAND

    Figures 1.6.1 to 1.6.4 provide an illustration of the reserve margin available to each NEMregion (with Victoria and South Australia treated as a single region). Each regionsreserve margin has been assessed sequentially under the following conditions:

    The Scheduled demand in the region matches the 50% POE Scheduled MD

    projection for summer 2006/07 5 less any committed DSP in the region.

    The Scheduled demand in other regions is lower than the 50% POE Scheduled MD

    projection as peaks in regional demand do not generally occur simultaneously. To

    account for this, the demand shown assumes a 95% coincidence factor6.

    Spare capacity in other regions is made available across interconnectors up to the

    assumed maximum transfer capabilities defined in Table 4 7.

    5The reserve available to Tasmania is illustrated at the time of the Tasmanian 50% POE

    Scheduled MD projection for winter 2007.6

    The Scheduled demand shown in other regions is 95% of the 50% POE Scheduled MDprojection.

    5 October, 2006 Page 7

  • 7/27/2019 Nem Mrl Level

    8/10

    Sufficient scheduled generation is available in each region to satisfy no more than

    the minimum reserve level requirements specified in Table 3 for summer 2006/07 8

    The Snowy generation capacity matches the committed scheduled generation

    capacity forecast for 2006/07.

    Table 4 Assumed Maximum Transfer CapabilityInterconnector

    Assumed Maxi mumTransfer Capability (MW)

    QLD->NSW (QNI and Terranora) 1,1001

    NSW->QLD (QNI and Terranora) 300

    SNOWY->NSW 2,900

    SNOWY->VIC 1,900

    TAS->VIC 610

    VIC->TAS 500

    1. Special switching of some 132kV circuits in Northern New SouthWales may be necessary to achieve 1,100 MW under certainconditions, provided system security can be maintained.

    Figure 1.6.1 Available Reserve Margin During 50% POE Scheduled MD Project ion(Summer 2006/07) - Queensland (MW)Coincidence Factor

    Reserve (% Scheduled Demand) 14% QUEENSLAND 100%Scheduled Demand - DSP 9,071

    Generation 10,058

    Support from NSW 300

    Reserve 1,287

    300NEW SOUTH WALES 95%

    Scheduled Demand - DSP 13,070

    Generation 11,661

    Support from Snowy & QLD 2,600

    Reserve 1,191

    2,900

    SNOWY 95%Scheduled Demand - DSP 0

    Generation 3,426

    VICTORIA AND SOUTH AUSTRALIA 95%

    Scheduled Demand - DSP 11,728

    Generation 11,756

    Support from Snowy 526

    610 Support from TAS 610

    Reserve 1,164

    TASMANIA 95%

    Scheduled Demand - DSP 1,366

    Generation 2,002

    Support from VIC -610

    All numbers in MW except as otherwise signed Reserve 26

    QUEENSLAND

    526

    QLD

    Snowy

    NSW

    TAS

    VIC AND SA

    Figure 1.6.2 Available Reserve Margin During 50% POE Scheduled MD Project ion(Summer 2006/07) - New South Wales (MW)

    7Transfers at the assumed maximum transfer capability can only be achieved if neighbouring

    regions have sufficient spare generation capacity, and under appropriate system conditions.8

    The reserve available to Tasmania is determined based on the Scheduled generation capacityto satisfy no more than the minimum reserve level of 144 MW for winter 2007.

    5 October, 2006 Page 8

  • 7/27/2019 Nem Mrl Level

    9/10

    Coincidence Factor

    Reserve (% Scheduled Demand) 14% QUEENSLAND 95%Scheduled Demand - DSP 8,613

    Generation 10,058

    Support from NSW -1,100

    Reserve 345

    1,100NEW SOUTH WALES 100%

    Scheduled Demand - DSP 13,759

    Generation 11,661

    Support from Snowy & QLD 4,000

    Reserve 1,902

    2,900SNOWY 95%

    Scheduled Demand - DSP 0

    Generation 3,426

    VICTORIA AND SOUTH AUSTRALIA 95%

    Scheduled Demand - DSP 11,728

    Generation 11,756

    Support from Snowy 526

    610 Support from TAS 610

    Reserve 1,164

    TASMANIA 95%

    Scheduled Demand - DSP 1,366

    Generation 2,002

    Support from VIC -610

    All numbers in MW except as otherwise signed Reserve 26

    526

    NEW SOUTH WALES

    QLD

    Snowy

    NSW

    TAS

    VIC AND SA

    Figure 1.6.3 Available Reserve Margin During 50% POE Scheduled MD Project ion(Summer 2006/07) - Victoria and South Aust ralia (MW)

    Coincidence Factor

    Reserve (% Scheduled Demand) 15% QUEENSLAND 95%Scheduled Demand - DSP 8,613

    Generation 10,058

    Support from NSW -1,100

    Reserve 3451,100

    NEW SOUTH WALES 95%

    Scheduled Demand - DSP 13,070

    Generation 11,661

    Support from Snowy & QLD 2,626

    Reserve 1,217

    1,526SNOWY 95%

    Scheduled Demand - DSP 0

    Generation 3,426

    1,900VICTORIA AND SOUTH AUSTRALIA 100%

    Scheduled Demand - DSP 12,360

    Generation 11,756

    Support from Snowy 1,900610 Support from TAS 610

    Reserve 1,906

    TASMANIA 95%

    Scheduled Demand - DSP 1,366

    Generation 2,002

    Support from VIC -610

    All numbers in MW except as otherwise signed Reserve 26

    VICTORIA AND SOUTH AUSTRALIA

    QLD

    Snowy

    VIC AND SA

    NSW

    TAS

    5 October, 2006 Page 9

  • 7/27/2019 Nem Mrl Level

    10/10

    Figure 1.6.4 Available Reserve Margin During 50% POE Scheduled MD Project ion(Winter 2007) - Tasmania (MW)

    Coincidence Factor

    Reserve (% Scheduled Demand) 36% QUEENSLAND 95%Scheduled Demand - DSP 7,432

    Generation 8,467

    Support from NSW -1,035

    Reserve 0

    1,035NEW SOUTH WALES 95%

    Scheduled Demand - DSP 13,099

    Generation 11,093

    Support from Snowy & QLD 2,561

    Reserve 556

    1,526SNOWY 95%

    Scheduled Demand - DSP 0

    Generation 3,426

    1,900VICTORIA AND SOUTH AUSTRALIA 95%

    Scheduled Demand - DSP 9,518

    Generation 8,898

    Support from Snowy 1,900500 Support from TAS -500

    Reserve 780

    TASMANIA 100%

    Scheduled Demand - DSP 1,824

    Generation 1,988

    Support from VIC 500

    All numbers in MW except as otherwise signed Reserve 664

    TASMANIA

    QLD

    Snowy

    NSW

    TAS

    VIC AND SA

    5 October, 2006 Page 10