nepool objective capability (installed capacity requirement) for power year 2005/2006
DESCRIPTION
NEPOOL Objective Capability (Installed Capacity Requirement) For Power Year 2005/2006. Presentation to the Joint ISO PAC/NEPOOL RC Meeting February 2, 2005 Wyndham Hotel, Westborough MA. Background. - PowerPoint PPT PresentationTRANSCRIPT
NEPOOL Objective Capability
(Installed Capacity Requirement)For Power Year 2005/2006
Presentation to the
Joint ISO PAC/NEPOOL RC Meeting
February 2, 2005
Wyndham Hotel, Westborough MA
ISO NEW ENGLAND | The people behind New England’s power 2
BackgroundNEPOOL Objective Capability (OC) is the amount of installed capacity that NE needs to meet the NEPOOL resource planning reliability criterion of 1 day in 10 years disconnection of non-interruptible customers. This criterion takes into account:
– Possible levels of peak loads due to weather variations,
– Impact of assumed generating unit performance, and
– Possible load and capacity relief obtainable through the use ofISO-NE Operating Procedure no. 4 – Action During a Capacity Deficiency.
ISO NEW ENGLAND | The people behind New England’s power 3
Background (Cont’d)
• OC is established by NEPOOL on an annual basis one year at a time.
• Power Supply Planning Committee – reviews assumptions and develop OC scenario(s) for Reliability Committee (RC) consideration.
• RC reviews the OC scenario(s) and votes a recommendation(s) for Participants Committee approval.
ISO NEW ENGLAND | The people behind New England’s power 4
Background (Cont’d)
OC is calculated using the single area Westinghouse/ABB Capacity Model Program. Single area refers to the assumption that there is adequate transmission to deliver capacity where and when is needed. Simply said, all loads and generators are assumed to be connected to a single electric bus.
ISO NEW ENGLAND | The people behind New England’s power 5
Background (Cont’d)
The Capacity Model uses probabilistic calculation that simulates the availability of system resources (taking into account each generating unit’s assumed forced outages and maintenance requirements) to meet the expected load (taking into account possible variations due to weather). This calculation is often referred to as the Loss of Load Expectation (LOLE) calculation.
ISO NEW ENGLAND | The people behind New England’s power 6
AssumptionsFor 2005/06 OC Calculations
ISO NEW ENGLAND | The people behind New England’s power 7
Assumptions• Loads
• Capacity– Existing
– Additions
– Attrition
– Purchases and Sales
– Daily Cycle Hydro Ratings
– ICAP Capable Load Response Program Assets
– SWCT RFP
• Unit Availability
• Tie Benefits
• Other OP-4 Load Relief
ISO NEW ENGLAND | The people behind New England’s power 8
Loads• Based on CELT 2005 forecast• Weekly distributions represented with:
– Expected value (mean)– Standard deviation– Skewness
• Based on short-run seasonal peak load forecast– Summer peak = 26,355 MW– Winter peak = 22,830 MW
ISO NEW ENGLAND | The people behind New England’s power 9
Capacity• Existing Capacity
– Based on 2005 CELT Data
• Assets within January 2005 Seasonal Claimed Capability (SCC) Report
– Summer Rating – August 2004 SCC Report
– Winter Rating – January 2005 SCC Report
• Units categorized as “EMS” & “SO” units included
– Energy Management System = 30,516 MW (S) & 32,878 MW (W)
– Settlement Only resources = 238 MW (S) & 313 MW (W)
ISO NEW ENGLAND | The people behind New England’s power 10
Capacity• Capacity Additions
– Ridgewood Generation (8.4 MW)
– Kendall Steam 3 Reactivation (25 MW)
– Kendall CT Reactivation (158 MW)
• Capacity Attrition
– No attrition assumed
ISO NEW ENGLAND | The people behind New England’s power 11
Capacity• Purchases and Sales
– Purchases and Sales as reported in 2004 CELT Report (453 MW)
• Daily Cycle Hydro Ratings
– 50 Percentile value of daily flows assumed with adjustment (59 MW in July) to OC.
ISO NEW ENGLAND | The people behind New England’s power 12
Load Response Assumptions• ICAP Capable Load Response Program
– All capacity listed as of January 1, 2005 as “ready to respond” enrolled in:
• Day-Ahead Demand Response Program• Real-Time Demand Response Program• Real-Time Profiled Response Program
– Assets grouped by Program and Area
– Assets assumed to have performance factors based on August 20, 2004 audit results and NERC Class Average EFORd values for known emergency generation.
ISO NEW ENGLAND | The people behind New England’s power 13
Program Load ZoneMW Assumed in 05/06
OC Calculations Assumed EFOR (%)
RT 2-hour Demand Response
ME 1.0 30.0
NEMA 1.5 99.0
WCMA 9.0 84.0
RT 30 Minute Demand Response
CT 218.0 3.9
NEMA 3.0 37.0
Profiled Response ME 76.0 100.0
NEMA 1.4 7.45
VT 5.9 100.0
Total 315.8
EFOR values based on Aug. 20, 2004 audit results and NERC Class average data
Assumed MW from Load Response Program
ISO NEW ENGLAND | The people behind New England’s power 14
Emergency Resources
• SWCT RFP
– Contracted SWCT RFP resources not currently enrolled in Real-Time Demand Response included
– 218 MW total contracted for summer 2005
ISO NEW ENGLAND | The people behind New England’s power 15
• PSPC recommended using EFORd instead of EFOR to be consistent with EFORd’s application in the ICAP market and the UCAP rating for generating units.
EFOR =Equivalent Forced Outage Hours
(Period Hours – Scheduled Outage Hours)
ISO NEW ENGLAND | The people behind New England’s power 16
EFORd Equation
Where:
D1
+ T1
+ r1
T1
+ r1
f f
EFOR
f FOH f EFOH - FOH
SH f FOHD
f p
f
r = average forced outage duration = FOH
number of forced outages
T average time between calls for a unit to run = RSH
number of attempted starts
D = average run time = SH
number of successful starts
f SH
AHp
ISO NEW ENGLAND | The people behind New England’s power 17
• EFORd - Equivalent Demand Forced Outage Rate
• ff - full f-factor
• fp - partial f-factor
• FOH - Full Forced Outage Hours
• EFOH - Equivalent Full Forced Outage Hours: Sum of all hours a unit was involved in an outage expressed as equivalent hours of full forced outage at its maximum net dependable capability
• SH - Service Hours: The time a unit is electrically connected to the system - Sum of all Unit Service Hours.
• AH - Available Hours: The time a unit is capable of producing energy, regardless of its capacity level -- Sum of all Service Hours + Reserve Shutdown Hours + Pumping Hours + Synchronous Condensing Hours
• RSH - Reserve Shutdown Hours: The time a unit is available for service but not dispatched due to economic or other reasons
ISO NEW ENGLAND | The people behind New England’s power 18
• Interpretation:
– The probability that a unit will not meet itsdemand periods for generating requirements.
– Best measure of reliability for all loading types(base, cycling, peaking, etc.)
– Best measure of reliability for all unit types(fossil, nuclear, gas turbines, diesels, etc.)
– For demand period measures and not for thefull 24-hour clock.
Equiv. Forced Outage Rate – Demand (EFORd)
ISO NEW ENGLAND | The people behind New England’s power 19
Unit Availability Assumption• 5-year average EFORd modeled
• Forced Outage Rates (EFORd) determined using combination of NERC Class Average EFORd data and available New England GADs data.
– NERC Class Average used Jan’00 – Feb’03
– Calculated EFORd using GADs used Mar’03 – Dec ’04
• Since Dec 04 data is not yet available,Dec 03 data is used for Dec 04.
ISO NEW ENGLAND | The people behind New England’s power 20
Unit Availability
• New England Nuclear units performance not correctly represented by NERC Class Average EFORd
• For Nuclear units, used ISO-NE calculated Jan’00 through Feb’03 EFOR and Mar’03 through Dec’04 EFORd.– Since Dec 04 data is not yet available,
Dec 03 data is used for Dec 04.
ISO NEW ENGLAND | The people behind New England’s power 21
Results of 60-Month Average
Unit CategorySummer
MW% of
System05/06 Assumed
WEFORd (%)
Fossil 10,179 32.9 6.71
CC 11,040 35.7 6.03
Diesel 121 0.4 5.56
Jet 1,873 6.1 7.09
Nuclear4,387 14.2 1.35
Hydro(Includes Pumped Storage)
3,340 10.8 3.80
Total System 30,940 100 5.41
ISO NEW ENGLAND | The people behind New England’s power 22
Tie Reliability Benefits
• Tie Reliability Benefits from Hydro-Quebec, New Brunswick, and New York are modeled in the Westinghouse Capacity Model as Resources
– PSPC suggested two sets of tie benefits assumptions
• 1,400 MW (summer values including HQICC)• 2,000 MW (summer values including HQICC)
ISO NEW ENGLAND | The people behind New England’s power 23
Tie Reliability Benefits - HQICC• Hydro-Quebec Interconnection Capability Credits for
2005/06 are determined based on load and capacity data submitted to ISO-NE by Hydro-Quebec Distribution and Hydro-Quebec Production.
• The monthly HQICC values recommendedby ISO-NE are:– June through November, March through May – 1,200 MW– December through February – 0 MW
ISO NEW ENGLAND | The people behind New England’s power 24
OP-4 Load Relief• Load Relief values based on ISO-NE Operating Procedure No. 4 (OP-4)
2005-2006 Power Year OP-4 Load Relief (MW)
(A) (B) (C) (B+C-A)
Minimum
Operating
Reserve
OP-4
Actions 9 &
10
5% Voltage
Reduction
Total OP-4
Load Relief
June – September 200 45 395 240
October - May 200 45 342 187
• 5% Voltage Reduction is based on 1.5% of the seasonal peak load as determined by Spring Voltage Reduction Test Results
ISO NEW ENGLAND | The people behind New England’s power 25
Tie Reliability Benefits Scenarios
The PSPC suggested calculating NEPOOL OC for
2005/06 Power year with two sets of tie reliability
benefits assumptions. The results are:
ISO NEW ENGLAND | The people behind New England’s power 26
2005-2006 Power Year Objective Capability ValuesAssuming ISO Recommended HQICC Values (MW)
Forecasted Monthly Peak
Load
Preliminary 2005-2006 OC with 1,400 MW of
Tie Benefits
Preliminary 2005-2006 OC with 2,000 MW of Tie
BenefitsJun-05 23,651 30,709 30,092 Jul-05 26,355 30,616 30,000
Aug-05 26,355 30,623 30,007 Sep-05 21,862 30,645 30,029 Oct-05 18,489 32,985 32,320 Nov-05 20,349 32,977 32,312 Dec-05 22,830 31,773 31,107 Jan-06 22,404 31,759 31,094 Feb-06 21,711 31,776 31,111 Mar-06 20,270 32,967 32,302 Apr-06 18,037 32,958 32,293 May-06 20,102 32,970 32,304
ISO NEW ENGLAND | The people behind New England’s power 27
2004-2005 Power Year Objective Capability Values(MW)
Forecasted Monthly Peak Load
2004/2005OC Values
Jun-04 23,050 28,915 Jul-04 25,735 28,874
Aug-04 25,735 28,884 Sep-04 21,375 28,885 Oct-04 18,145 30,607 Nov-04 19,975 30,590 Dec-04 21,580 29,587 Jan-05 22,370 29,583 Feb-05 21,260 29,590 Mar-05 19,865 29,876 Apr-05 17,680 30,566 May-05 19,805 30,581
ISO NEW ENGLAND | The people behind New England’s power 28
ISO-NE OC Recommendation
ISO-NE recommends that the NEPOOL Objective
Capability for the Power Year commencing on
June 1, 2005 and ending on May 31, 2006 be
those associated with assuming 2,000 MW of tie
reliability benefits.
ISO NEW ENGLAND | The people behind New England’s power 29
Change in Objective Capability04/05 to 05/06
24,000
25,000
26,000
27,000
28,000
29,000
30,000
31,000
04/05 PSPCApproved OC
Effect of LoadGrowth
Effect of UpdatedCapacity and
EFORd
Preliminary05-06 OC
July
OC
(M
W)
04/05 PSPC Approved OC
438 MW703 MW1,153 MW
ISO NEW ENGLAND | The people behind New England’s power 30
Appendix
• Examples of LOLE calculation
ISO NEW ENGLAND | The people behind New England’s power 31
Consider two Generators – one of 100 MW capability, and another of 200 MW.
Their binary (full capacity up, or full capacity down) behaviors are:
Gen. Cap. OutageProbability.
#1 100 0.1 (10%) Representation#2 200 0.15 (15%)
0.9
0.1
0.850.15
0
0
100
200
prob
abil
ity
Capacity on outage
Joint outcomesAvailable Cap. On Prob.
State Cap. Outage
Gen. #1 up, Gen. #2 up 100 + 200 = 300 0 0.9 * 0.85 = 0.765Gen. #1 down, Gen. #2 up 0 + 200 = 200 100 0.1 * 0.85 = 0.085Gen. #1 up, Gen #2 down 100 + 0 =100 200 0.9 * 0.15 = 0.135Gen. #1 down, Gen #2 down 0 + 0 = 0 300 0.1 * 0.15 = 0.015
1.00
Capacity outage probability table (distribution)
0 100 200 300
0.765
0.085 0.135 0.015
Consider two Generators – one of 100 MW capability, and another of 200 MW.
Their binary (full capacity up, or full capacity down) behaviors are:
Gen. Cap. OutageProbability.
#1 100 0.1 (10%) Representation#2 200 0.15 (15%)
0.9
0.1
0.850.15
0
0
100
200
prob
abil
ity
Capacity on outage
Joint outcomesAvailable Cap. On Prob.
State Cap. Outage
Gen. #1 up, Gen. #2 up 100 + 200 = 300 0 0.9 * 0.85 = 0.765Gen. #1 down, Gen. #2 up 0 + 200 = 200 100 0.1 * 0.85 = 0.085Gen. #1 up, Gen #2 down 100 + 0 =100 200 0.9 * 0.15 = 0.135Gen. #1 down, Gen #2 down 0 + 0 = 0 300 0.1 * 0.15 = 0.015
1.00
Capacity outage probability table (distribution)
0 100 200 300
0.765
0.085 0.135 0.015
ISO NEW ENGLAND | The people behind New England’s power 32
Consider a demand of 180 MW in a single hour. Reserve capacity= Installed capacity – load= 300 – 180 =120 MW.
Hence, if the capacity on outage is greater than the reserve cap. (120 MW), curtailment is necessary.
0 100 300
0.765
0.085 0.135 0.015
200Capacity on outage
120
MW
Probability of loss of > 120 MW = 0.135 + 0.015 = 0.15.
If we continue this procedure for 7200 hours corresponding to 300 working days of the year, let the average loss of load probability (LOLP) computed be 0.002. This is expressed as a mathematical expectation as the no. of expected hours = 0.002 * 7200 = 14.4 hours per year, or as 14.4 / 24 = 0.6 days per year. This mathematical expectation is expressed as loss of load expectation (LOLE).
Similarly, let the demand in another hour be 99 MW. Then, since reserve = 300 –99 = 201 MW, curtailment results if more than 201 MW is on outage. This, from the above distribution, is equal to0.015. Over a period of two hours, the average probability of loss of load (if we value, or weight,them equally) is (0.15 +0.015) / 2 = 0.0825.
This is the probability of curtailment , or probability of loss of load.
Consider a demand of 180 MW in a single hour. Reserve capacity= Installed capacity – load= 300 – 180 =120 MW.
Hence, if the capacity on outage is greater than the reserve cap. (120 MW), curtailment is necessary.
0 100 300
0.765
0.085 0.135 0.015
200Capacity on outage
120
MW
Probability of loss of > 120 MW = 0.135 + 0.015 = 0.15.
If we continue this procedure for 7200 hours corresponding to 300 working days of the year, let the average loss of load probability (LOLP) computed be 0.002. This is expressed as a mathematical expectation as the no. of expected hours = 0.002 * 7200 = 14.4 hours per year, or as 14.4 / 24 = 0.6 days per year. This mathematical expectation is expressed as loss of load expectation (LOLE).
Similarly, let the demand in another hour be 99 MW. Then, since reserve = 300 –99 = 201 MW, curtailment results if more than 201 MW is on outage. This, from the above distribution, is equal to0.015. Over a period of two hours, the average probability of loss of load (if we value, or weight,them equally) is (0.15 +0.015) / 2 = 0.0825.
This is the probability of curtailment , or probability of loss of load.
ISO NEW ENGLAND | The people behind New England’s power 33
Assuming that the load is 100 MW, then the probability of not being able to serve the load is 0.01
Capacity Outage (MW) unit-1 unit-2
0 up up 0.9*0.9 0.81 0.81down up 0.1*0.9 0.09
up down 0.9*0.1 0.09200 down down 0.1*0.1 0.01 0.01
Unit Status
Probability
100 0.18
Two Identical Units – 100 MW RatingEquivalent Forced Outage Rate = 0.10
Capacity Outage Calculation
ISO NEW ENGLAND | The people behind New England’s power 34
Assuming that the load is 100 MW, then the probability of not being able to serve the load is 0.00715 + 0.000125 = 0.00725
Three Identical Units – 50 MW RatingEquivalent Forced Outage Rate = 0.05
Capacity Outage (MW) unit-1 unit-2 unit-3
0 up up up 0.95*0.95*0.95 0.85738 0.857375down up up 0.05*0.95*0.95 0.04513
up down up 0.95*0.05*0.95 0.04513up up down 0.95*0.95*0.05 0.04513
down down up 0.05*0.05*0.95 0.00238down up down 0.05*0.95*0.05 0.00238
up down down 0.95*0.05*0.05 0.00238150 down down down 0.05*0.05*0.05 0.00013 0.000125
Unit Status
50
100
Probability
0.135375
0.007125
Capacity Outage Calculation (Cont’d)
ISO NEW ENGLAND | The people behind New England’s power 35
Assuming that the load is 100 MW, then the probability of not being able to serve the load is 0.000475 + 0.00000625 = 0.0004813
Four Identical Units – 50 MW Rating Equivalent Forced Outage Rate = 0.05
Capacity Outage (MW) unit-1 unit-2 unit-3 unit-4
0 up up up up 0.95*0.95*0.95*0.95 0.8145063 0.81450625down up up up 0.05*0.95*0.95*0.95 0.0428688
up down up up 0.95*0.05*0.95*0.95 0.0428688up up down up 0.95*0.95*0.05*0.95 0.0428688up up up down 0.95*0.95*0.95*0.05 0.0428688
down down up up 0.05*0.05*0.95*0.95 0.0022563down up down up 0.05*0.95*0.05*0.95 0.0022563down up up down 0.05*0.95*0.95*0.05 0.0022563
up down down up 0.95*0.05*0.05*0.95 0.0022563up down up down 0.95*0.05*0.95*0.05 0.0022563up up down down 0.95*0.95*0.05*0.05 0.0022563
down down down up 0.05*0.05*0.05*0.95 0.0001188down down up down 0.05*0.05*0.95*0.05 0.0001188down up down down 0.05*0.95*0.05*0.04 0.0001188
up down down down 0.95*0.05*0.05*0.05 0.0001188200 down down down down 0.05*0.05*0.05*0.05 0.0000063 0.00000625
Unit Status
50
Probability
0.1714750
150 0.0004750
100 0.0135375
Capacity Outage Calculation (Cont’d)