NERC Project Increase Analytical Capabilities in the
Probabilistic Domain
Noha Abdel-Karim, PhD.
Senior Engineer for Reliability Assessment
IEEE-LOLE Working Group Meeting
July 21-22, 2016
RELIABILITY | ACCOUNTABILITY 2
About NERC
International regulatory authority for electric reliability in North America
Develops and enforces reliability standards
Analyzes system outages, near-misses and risks and recommends
improved practices
Accountable as electric reliability organization (ERO) to regulators in the
United States (FERC) and Canada (provincial governments)
Assesses current and future risks to reliability
RELIABILITY | ACCOUNTABILITY 3
About NERC
RELIABILITY | ACCOUNTABILITY 4
About NERC
RELIABILITY | ACCOUNTABILITY 5
About NERC
July 20, 2016
NERC 10th anniversary of being certified as the Electric Reliability Organization by the Federal
Energy Regulatory Commission
RELIABILITY | ACCOUNTABILITY 6
• Peak demand forecasts
• Resource adequacy
• Transmission adequacy
• Key issues - emerging trends
Technical challenges
Evolving market practices
System elements/dynamics
Potential legislation/regulation
• Regional self-assessment
• Ad-hoc special Assessments
NERC Reliability Assessment
RELIABILITY | ACCOUNTABILITY 7
NERC Planning Committee Subgroup Organizational Chart
RELIABILITY | ACCOUNTABILITY 8
• Reserve Margins in all Assessment Areas appear sufficient but continue to trend downward
• A changing resource mix requires additional measures and approaches for assessing future reliability
• Operators and planners face uncertainty with increased levels of distributed energy resources and new technologies
• NERC continues its reliability assessment of the Clean Power Plan and other environmental rules
2015 LTRA Key Findings
RELIABILITY | ACCOUNTABILITY 9
2015 LTRA Key Findings
• NERC continues its reliability assessment of the Clean Power Plan and other environmental rules
• Early Retirement of Nuclear Plants
• Energy Storage
• Regional/Interconnection-Wide Modeling
• Increasing Nameplate Capacity of Nonsynchronous Generation Compared to Synchronous Generation
RELIABILITY | ACCOUNTABILITY 10
NERC Strategic Goals
• Increased NERC Analytical Capabilities
In-house software capabilities
Ad-hock special assessments
• Improve NERC Probabilistic Assessments
Extend the LTRA data with probabilistic reliability measures on all 20 Assessment Areas for two of the 10 years of the LTRA.
Improve Probabilistic Modeling
NERC identified several considerations and lessons learned that should be evaluated before proceeding with additional probabilistic assessments.
Probabilistic Assessment
RELIABILITY | ACCOUNTABILITY 11
Uncertainties Impacting Resource Adequacy Planning • Regulatory Policies & Economic Factors
• New technologies on transmission and distribution sides
• Unexpected event or behavior - Extreme Weather
• Generation Resource Uncertainties – future forecast, generation output (for variable
generation), water availability for hydro, EFOR, ramping
• Transmission Uncertainties – future forecast, determination of transmission paths,
time required to build transmission, component outages
• Demand Uncertainties – future load forecast, Demand Side Management
(DSM)/Distributed Resources (DR) program impacts, and distributed generation impacts
• Fuel Uncertainties – Price/delivery system based
Uncertainty Areas
RELIABILITY | ACCOUNTABILITY 12
NERC Probabilistic Assessment Effort
• PC Approved GTRPMTF Methodology and Metrics Report in September 2010.
• OBJECTIVE: To provide a common set of probabilistic reliability indices and recommend probabilistic-based work products that could be used to supplement the NERC’s long-term reliability assessments.
• Pilot Assessment Report – 2011
• ProbA Reports –2012 & 2014 Annual EUE
Annual LOLH
EUE as a percentage of Net Energy for Load (normalized EUE).
• ProbA Report –2014 Annual EUE, Annual LOLH, and EUE as a percentage of Net Energy for Load
(normalized EUE).
Scenario Modeling: calculate the LOLH and EUE if load were interrupted to maintain full operating reserves.
RELIABILITY | ACCOUNTABILITY 13
NERC Probabilistic Assessment Effort
• Probabilistic Assessment Improvement Task Force (PAITF) – Formed May 2015
– Objective: Support the identification of improvement opportunities for NERC’s Long-Term Reliability Assessment and the complementary probabilistic analysis.
– Main deliverables: • Summary and Recommendations Report, December 2015
• Probabilistic Assessment Technical Guideline Document –Draft, July 2016
• Kickoff NERC 2016 ProbA –March, 2016 – Including Enhancements and Recommendations by PAITF
• Integration of Probabilistic Assessment into NERC Long Term Reliability Assessment
– More exposure to the importance of ProbA
RELIABILITY | ACCOUNTABILITY 14
• Background: Prepare Probabilistic Assessment Guidelines document to Identify modeling requirements and recommendations, and to support Regional scenarios to study emerging risks to reliability.
• Core Probabilistic Assessment Continuation of the individual area probability
assessments.
Modeling consistency will be improved by following a Probabilistic Assessment Guidelines document.
• NERC-Regional Coordinated Special Assessment Expand the probabilistic study efforts with NERC and the
Regions leading the development and evaluation efforts of additional scenario studies on reliability concerns related to the BPS higher risk areas identified in the LTRA.
Probabilistic Assessment Improvement Task Force
RELIABILITY | ACCOUNTABILITY 15
• Core Probabilistic Assessment Metric Reporting Areas
Metrics Descriptions
Metric Calculations
Probabilistic Study Reporting
o Study Frequency and Study Years
Simulation software
• Coordinated NERC Regional Special Assessment Special Assessment Determination
Roles and Responsibilities
Modeling Requirements and Scope of Work
• General Modeling Assumptions Load Modeling
Capacity Modeling
Emergency Operating Procedures
Transmission Modeling
Sensitivity and Scenario Modeling
Data Preparation and Collection
ProbA Technical Guideline Document
RELIABILITY | ACCOUNTABILITY 16
Objectives
• Identify practices, requirements and recommendations needed to perform high-quality probabilistic resource adequacy assessments.
• Complement reserve margin analyses in NERC’s Long-Term Reliability Assessments by producing enhanced resource adequacy metrics and modeling approaches.
• Provide NERC and policy makers with far greater insight, understanding, and the perspectives on BPS reliability.
• Support regional scenarios to study reliability issues identified in the Long-Term Reliability Assessment.
ProbA Technical Guideline Document
RELIABILITY | ACCOUNTABILITY 17
ProbA Technical Guidelines
Enhancements Summary
NERC to develop and maintain documentation describing the establishment of Assessment Areas.
1
NERC within the RAS to evaluate the need for a ProbA Working Group
2
Regions and Assessment Areas need to estimate or calculate monthly resource adequacy measures in their metrics calculations
3
Regions and Assessment Areas need to incorporate seasonal variations in their load modeling
4
RELIABILITY | ACCOUNTABILITY 18
Enhancements Summary
Regions and Assessment Areas need to incorporate seasonal variations in their modeling of resource outages
5
Assessment Areas need to coordinate with neighboring areas to determine the appropriate amount of capacity transfers
6
ProbA Technical Guideline Document
RELIABILITY | ACCOUNTABILITY 19
Probabilistic Metrics • Annual LOLH
• Monthly LOLH
• Annual EUE, both actual and normalized
• Monthly EUE, both actual and normalized
Probabilistic Study Frequency and Study Years • With inputs from the RAS, RAS-ProbA, PAITF and ERO-RAPA
Probabilistic assessment is on a biennial basis
• Assessment Areas study both year 2 and 4 of the Long-Term Reliability Assessment (LTRA).
• Year 2 reporting is to track and trend resource adequacy measures assessment to assessment.
ProbA Technical Guideline Document
RELIABILITY | ACCOUNTABILITY 20
• Assess the impact of a change in an input (either load, transmission or resource-related) on resource adequacy metrics.
• The runs are performed by changing one input at-a-time in order to isolate the potential impact of each input.
• Ideally, the change in each input should be accompanied by an associated probability.
• The sensitivity modeling should be addressed within the Core Probabilistic Assessment framework.
• Assess the impact of changes in multiples inputs (either load, transmission or resource-related) on resource adequacy metrics.
• The runs are performed by changing multiple inputs at the same time
• Scenarios are likely to be identified in the LTRA or by sensitivity analysis results.
• The scenario modeling should address the reliability issues identified within the LTRA that impact resource adequacy, within the Special-Coordinated Probabilistic Assessment framework
Scenario Modeling Sensitivity Modeling
ProbA Technical Guideline Document
RELIABILITY | ACCOUNTABILITY 21
• 2016 ProbA Enhancements Monthly Probabilistic Measures
Per guidelines, Assessment Areas describe in their narratives the assumptions used to develop ALL modeling categories of their probabilistic studies.
ProbA Technical Guideline Document
RELIABILITY | ACCOUNTABILITY 22
• Special Assessments Coordinated NERC/NPCC pilot assessment on natural gas pipeline
disruptions
• Technical papers/reports: Variable energy resources (VER)
o Diminishing value of solar
o High penetrations –Impact on RM
Ramping issues
LOL calculations with increased VER
• Tools to incorporate transmission modeling into probabilistic assessments
Future and In Progress Effort
RELIABILITY | ACCOUNTABILITY 23