NMD Project Overview

NMD Project Overview

> Information system to support long-term planning (e.g. TYNDP)

> Provides central model storage

> Main storage of tie-line information

> Generates ENTSO-E boundary set on demand

> Reference system in ENTSO-E CIM/XIM IOP tests

> All members of ENTSO-E will use the system (41 TSOs)

> Unicorn Systems acts as a System Integrator.

> Unicorn System delivers Unicorn Open Platform and NMD Functional

Module.

> Alstom delivers e-terrasource (CIM compatible database and modelling

tool)

Copyright © Unicorn Systems 3

NMD Project Overview

> February 2011 – Tender invitation

> April 2011 – Proposal deadline

> 1.12.2011 – Project kick-off

> December 2011 – January 2012 – Analytical phase

> February – April 2012 – Implementation phase

> May 2012 – Test phase (FAT/SAT)

> 31.5.2012 – Go-live

> July 2012 – ENTSO-E CIM IOP 2012

Copyright © Unicorn Systems 4

High-Level Concept

Copyright © Unicorn Systems 5

High-Level Concept

Copyright © Unicorn Systems 6

NMD Features

Unicorn Open Platform

> Proven on several projects (e.g. CTDS, CWE CS)

> Based on mature open source products

> Java EE 5

> jBPM

> JBoss ESB

> JBoss AS

> Jackrabbit

> Pentaho Reporting

> Provides a lot of useful components including

> Business Process Management

> Document Management

> Messaging

> Configuration

> User, Roles and Rights Management

> Ready for Integration

Copyright © Unicorn Systems 8

Unicorn Open Platform Components

Copyright © Unicorn Systems 9

Alstom e-terrasource

> CIM Compliant Modelling tool.

> Metadata driven architecture.

> Including import and export sequences.

> Features

> MAS concept support.

> Time-based delta increments.

> Versioning

> Workspaces

> Multiple detail levels.

> Visualization.

> Flexible validations.

> Client/Server architecture.

> Provides WS API

Copyright © Unicorn Systems 10

Alstom e-terrasource GUI

Copyright © Unicorn Systems 11

Business Processes

> Data Assembling Process

> Tie-Lines Maintenance

> User roles:

Copyright © Unicorn Systems 12

Data Assembling Process

> Result of Data Assembling Process is complete and valid power

system model for given situation.

> This model is composed of TSO models, Boundary Set and

Solution.

> Boundary set – contains boundary objects to which tie-lines are connected

> Solution – calculated load-flow for the whole model

Copyright © Unicorn Systems 13

Data Assembling Process

Copyright © Unicorn Systems 14

Domain Model

Copyright © Unicorn Systems 15

NMD CIM Features

> Model Formats > ENTSO-E CIM Profile

> Version 1

> Version 2 (2nd draft)

> File types > Equipment, Topology, State Varibles

> Geographical Data, Dynamic Data, Diagram Layout

> Model Types > Complete Model

> Contains all mandatory profiles as full files for given case > Partial Model

> Contains only profiles as full file > Differential Model

> Contains differentials files

> Syntax and business validations

Copyright © Unicorn Systems 16

NMD Use Cases

Showcase

> Login

> Main page layout

> Scenario / Case / Situation

> Submit Model

> Approve Model

> Assemble Model

> Submit Solution

> Download Model

Copyright © Unicorn Systems 18

Login

Copyright © Unicorn Systems 19

Main Page Layout

Copyright © Unicorn Systems 20

Scenario

Copyright © Unicorn Systems 21

Case

Copyright © Unicorn Systems 22

Case

Copyright © Unicorn Systems 23

Case

Copyright © Unicorn Systems 24

Situation

Copyright © Unicorn Systems 25

Submit Model

Copyright © Unicorn Systems 26

Approve Model

Copyright © Unicorn Systems 27

Assemble Model

Copyright © Unicorn Systems 28

Submit Solution

Copyright © Unicorn Systems 29

Download Model

Copyright © Unicorn Systems 30

Tie-Lines Maintenance

> Manage information about tie-lines

> Tie-Line Approval Process

> Create new tie-line

> Modify tie-line

> Generate Boundary set from tie-lines

Copyright © Unicorn Systems 31

Tie-Line Approval Process

Copyright © Unicorn Systems 32

Tie-line Request Screen

Copyright © Unicorn Systems 33

Next Steps

> End of testing phase

> Go-live

> ENTSO-E CIM IOP 2012

> Further development

> Support of final version of ENTSO-E CIM Profile 2

> Extensions on UI level (e.g. editing of entities, discussions over entities)

> Integration with other systems (e.g. GIS)

Copyright © Unicorn Systems 34

Contact

Unicorn Systems a. s.

Executive Briefing Centre – Classic 7

Jankovcova 1037/49

170 00 Praha 7

Czech Republic

Tel.: +420 221 400 111

Fax: +420 221 400 114

E-mail: [email protected]

http://www.unicornsystems.eu

Copyright © Unicorn Systems