    AVERAGE LEAD OF 1 km

    S.No. Kind of Materials Name of Quarry Lead Cost conveyance Total

    1 Mortar Sand Arjuna River 23 115.00 114.50 229.50

    2 Filling Sand Arjuna River 23 85.00 114.50 199.50

    3 40 mm Metal Malaipatti 19 290.00 97.85 387.85

    4 20 mm Metal Malaipatti 19 365.00 97.85 462.85

    5 6 mm Metal Malaipatti 19 215.00 97.85 312.85

    6 Rough Stone Malaipatti 19 160.00 97.85 257.85

    7 Bond Stone Malaipatti 19 250.00 97.85 347.85

    8 Country Bricks Gollapatti 29 1250.00 117.10 1250.00

    9 Brick Jelly 20 mm Gollapatti 29 240.00 #REF! #REF!

    10 Shell lime Virudhunagar 10 650.00 #REF! #REF!

    11 Pressed Tiles Virudhunagar 10 3550.00 63.00 3550.00

    12 Lime Stone Virudhunagar 10 320.00 #REF! #REF!

    13 Steel Virudhunagar 10 16110.00 35.00 16110.00

    14 Cement Virudhunagar 10 2600.00 35.00 2635.00

  • 8/14/2019 NEW Conveyance Rates 07-08

    2/37

    0 0

    1 3.50

    2 7

    3

    4 14

    5 186 21

    7 25

    8 28

    9 32

    10 35

    11 38

    1241 CEMENT

    13 44

    14 47

    15 5016 52

    17 55

    18 58

    19 61

    20 64

    21 67

    22 69

    23 72

    24 74

    2577

    26 79

    27 82

    28 84

    29 87

    30 89

    31 92

    32 94

    33 97

    34 99

    35 102

    36 10437 107

    38 109

    39 112

    40 114

  • 8/14/2019 NEW Conveyance Rates 07-08

    3/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    4/37

    1 7.90

    2 15.80

    3 23.70

    4 31.60

    5 39.50

    6 47.407 55.30

    8 63.20

    9 71.10

    10 79.00

    11 85.55

    12 92.10

    13 98.65

    14 105.20

    15 111.75

    16 118.30

    17 124.85

    18 131.40

    19 137.95

    20 144.50

    21 150-.15

    22 155.80

    23 161.45

    24 167.10

    25 172.75

    26 178.40

    27 184.0528 189.70

    29 195.35

    30 201.00

    31 206.65

    32 212.30

    33 217.95

    34 223.60

    35 229.25

    36 234.90

    37 240.5538 246.20

    39 251.85

    40 257.50

  • 8/14/2019 NEW Conveyance Rates 07-08

    5/37

    1 6.80

    2 13.60

    3 20.40

    4 27.20

    5 34.00

    6 40.807 47.60

    8 54.40

    9 61.20

    10 68.00

    11 73.40

    12 78.80

    13 84.20

    14 89.60

    15 95.00

    16 100.40

    17 105.80

    18 111.20

    19 116.60

    20 122.00

    21 126.45

    22 130.90

    23 135.35

    24 139.80

    25 144.25

    26 148.70

    27 153.1528 157.60

    29 162.05

    30 166.50

    31 170.95

    32 175.40

    33 179.85

    34 184.30

    35 188.75

    36 193.20

    37 197.6538 202.10

    39 206.55

    40 211.00

  • 8/14/2019 NEW Conveyance Rates 07-08

    6/37

    1 6.30

    2 12.60

    3 18.90

    4 25.20

    5 31.50

    6 37.807 44.10

    8 50.40

    9 56.70

    10 63.00

    11 68.20

    12 73.40

    13 78.60

    14 83.80

    15 89.00

    1694.20

    17 99.40

    18 104.60

    19 109.80

    20 115.00

    21 119.50

    22 124.00

    23 128.50

    24 133.00

    25 137.50

    26 142.00

    27 146.50

    28 151.00

    29 155..50

    30 160.00

    31 164.50

    32 169.00

    33 173.50

    34 178.00

    35 182.50

    36 187.00

    37 191.5038 196.00

    39 200.50

    40 205.00

    41-80 add 2.75 per km

    Mangalore Tiles (2000 nos.) Machine Presse

  • 8/14/2019 NEW Conveyance Rates 07-08

    7/37

    Tiles

  • 8/14/2019 NEW Conveyance Rates 07-08

    8/37

    1 4.75

    2 9.50

    3 14.25

    4 19.00

    5 23.75

    6 28.507 33.25 Country Bricks8 38.00

    9 42.75

    10 47.50

    11 51.40

    12 55.30

    13 59.20

    14 63.10

    15 67.00

    1670.90

    17 74.80

    18 78.70

    19 82.60

    20 86.50

    21 89.90

    22 93.30

    23 96.70

    24 100.10

    25 103.50

    26 106.90

    27 110.30

    28 113.70

    29 117.10

    30 120.50

    31 123.90

    32 127.30

    33 130.70

    34 134.10

    35 137.50

    36 140.90

    37 144.3038 147.70

    39 151.10

    40 154.50

    41-80 add 2.00 per km

  • 8/14/2019 NEW Conveyance Rates 07-08

    9/37

    1 3.85

    2 7.70

    3 11.55

    4 15.40

    5 19.25 Lime Stone,Broken Stone Brick jelly Wood Work

    6 23.107 26.95

    8 30.80

    9 34.65

    10 38.50

    11 41.70

    12 44.90

    13 48.10

    14 51.30

    15 54.50

    1657.70

    17 60.90

    18 64.10

    19 67.30

    20 70.50

    21 73.25

    22 76.00

    23 78.75

    24 81.50

    25 84.25

    26 87.00

    27 89.75

    28 92.50

    29 95.25

    30 98.00

    31 100.75

    32 103.50

    33 106.25

    34 109.00

    35 111.75

    36 114.50

    37 117.2538 120.00

    39 122.75

    40 125.50

    41-80 add 1.65 per km

  • 8/14/2019 NEW Conveyance Rates 07-08

    10/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    11/37

    44 195.30

    45 198.50

    46 201.70

    47 204.90

    48 208.10

    49 211.3050 214.50

    51 217.70

    52 220.90

    53 224.10

    54 227.30

    55 230.50

    56 233.70

    57 236.90

    58 240.10

    59 243.30

    60 246.5061 249.70

    62 252.90

    63 256.10

    64 259.30

    65 262.50

    66 265.70

    67 268.90

    68 272.10

    69 275.30

    70 278.50

    71 281.70

    72 284.9073 288.10

    74 291.30

    75 294.50

    76 297.70

    77 300.90

    78 304.10

    79 307.30

    80 310.50

  • 8/14/2019 NEW Conveyance Rates 07-08

    12/37

    Stone,Gravel,Surki

  • 8/14/2019 NEW Conveyance Rates 07-08

    13/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    14/37

    0 0

    1 3.50

    2 7.00

    3 10.50

    4 14.00

    5 17.506 21.00

    7 24.50

    8 28.00

    9 31.50

    10 35.00

    11 37.90

    12 40.80

    1343.70 STEEL

    14 46.60

    15 49.5016 52.40

    17 55.30

    18 58.20

    19 61.10

    20 64.00

    21 66.50

    22 69.00

    23 71.50

    24 74.00

    2576.50

    26 79.00

    27 81.50

    28 84.00

    29 86.50

    30 89.00

    31 91.50

    32 94.00

    33 96.50

    34 99.00

    35 101.50

    36 104.0037 106.50

    38 109.00

    39 111.50

    40 114.00

  • 8/14/2019 NEW Conveyance Rates 07-08

    15/37

    Mazon I 160

    Mazon II 145

    Mazdoor I 100

    Mazsdoor II 90

    Fitter I 140

    Fitter II 130

    Painter I 130Painter II 120

    Carpenter I 160

    Carpenter I I 145

    Stocking charge

    Metal 3.15

    Gravel 3.05

    Sand 3.05

    Filling gravel 9.20

    Filling Sand 8.20

    Mixing CM 27.00

    Mixing LM 38.00

    Cleaning surfa 1.80

  • 8/14/2019 NEW Conveyance Rates 07-08

    16/37

    Kind of Materials Rate

    Mortar Sand 110

    Filling Sand 11040 mm Metal 490

    20 mm Metal 685

    12 mm Metal 630

    10 mm Metal 465

    6 mm Metal 315

    Rough Stone 230

    Bond Stone 315

    Country Bricks 1470

    Brick Jelly 20 mm 280

    Shell lime 705

    Pressed Tiles 4500

    Lime Stone 345

    Steel 31000

    Cement 4300

    Red Gravel 92

    Well Gravel 82

    Quarry Rubbish 51

    Snowcem 30

    Distember 60

    Enemal paint 150

    0

  • 8/14/2019 NEW Conveyance Rates 07-08

    17/37

    Name of Work: Special Repairs to the cement concrete road at Mettu vLEAD STATEMENT

    S.No. Unit Cost Total

    1 Mortar Sand 29 1 cum 110.00 ### 248.502 Filling Sand 29 1 cum 110.00 ### 248.50

    3 Cement 7 1 Mt 3600.00 24.50 3624.50

    4 Steel 7 1 Mt ### 0.00 31000.00

    5 40 mm Metal 3 1 cum 490.00 16.80 506.80

    6 20 mm Metal 3 1 cum 685.00 16.80 701.80

    7 12mm Metal 3 1 cum 630.00 16.80 646.80

    8 10 mm Metal 3 1 cum 465.00 16.80 481.809 6 mm Metal 3 1 cum 315.00 16.80 331.80

    10 Rough Stone 3 1 cum 230.00 16.80 246.80

    11 Bond Stone 3 1 cum 315.00 16.80 331.80

    12

    Country Bricks (8 3/4x 4

    2 000 No 1470.00 9.50 1470.00

    13 Brick Jelly 20 mm 2 1 cum 280.00 7.70 287.70

    14 Red Gravel 1 1 cum 92.00 5.60 97.60

    15 Well Murambu 1 1 cum 82.00 5.60 87.60

    16 Lime Stone 1 1 cum 345.00 3.85 348.85

    17 Pressed Tiles (20 cm 20 12 000 No 4500.00 36.70 4536.70

    18 Shell Lime 1 cum 705.00 705.00

    er e a e a ove ea s an ra es are s or es an correc o e es o

    Kind ofMaterials

    Name ofQuarry

    Leadin km

    conveyan

    ce

  • 8/14/2019 NEW Conveyance Rates 07-08

    18/37

    dakarai.

    my now e ge.

  • 8/14/2019 NEW Conveyance Rates 07-08

    19/37

    SUB-DATA

    Name of MateriCost of MateMixing Ratio

    CM 1:1 1/2 960 1:2 720 1:3 480 1:4 360 1:5 288

    Cement 3624.50 3479.52 2609.64 1739.76 1304.82 1043.86

    Sand 248.50 248.50 248.50 248.50 248.50

    Concrete Works

    3728.02 2858.14 1988.26 1553.32 1292.36

    Mixing charges

    27.00 27.00 27.00 27.00 27.00 27.00For Mortar Works

    3755.02 2885.14 2015.26 1580.32 1319.36

    Main Data

    7.Earth work excavation in all clauses of soils with initial lead and lift except hard rock requiring

    blasting etc., complete for foundation as per SS 20 B.

    8. Filling with carted sand including cost and conveyance and all labour

    charges such as watering and ramming etc., complete as per standard specification.

    1.00 Cum Cost of Sand 248.50 1 Cum 248.50

    1.00 Cum 8.20 1 Cum 8.20

    Total 256.70

    Rs 256.70 /1CUM

    For Structure works Rs.26 x 2 = 52.00/ 1 cum.

    For Drainage works Rs.26 x 1.5 = 39.00/ 1 cum.

    For C.C pavement Rs.26x1 = 26.00/ 1 cum.

    FillingCharges

  • 8/14/2019 NEW Conveyance Rates 07-08

    20/37

    SKM,SVPR.

  • 8/14/2019 NEW Conveyance Rates 07-08

    21/37

    kgs

  • 8/14/2019 NEW Conveyance Rates 07-08

    22/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    23/37

    Name of Work :-

    Qty Unit Description of Work KM

    Rate Per Amount

    4.000 KG Cost of Biumen 24700 MT 98.80

    10 SQM 75.40 75.40

    10 Sqm Labour Charges

    Rate for 10 sqm 174.20

    Rate for 1 sqm 17.42

    Applying tack coat over WBMsurface using 4Kg of Bitumen

    per 10 sqm. Including cost ofBitumen emulsion which willbe supplied departmentally atsection stores cost of whichwill be recovered at the ratesas per special conditionsappended herewith includingconveyance of Bitumenemulsion to actual workspothandling charges includinglabour charges for brushing,

    cleaning and preparing thesurface for laying the tack coatand labour for applying therequired quantity of bitumenemulsion including, hire, fueland running charges for alltools and plants employed forthe work including all otherincidental charges such as

    Higher Charges for Tools andPlan 10sqm

    10Sqm

  • 8/14/2019 NEW Conveyance Rates 07-08

    24/37

    Name of Work :-

    Qty Unit Description of Work KM

    Rate Per Amount

    PROVIDING AND LAYING PREMIX CARPET WITH SEAL COAT TYPE - A

    0.180 Cum 657 1 cum 118.22

    0.090 Cum 512 1 Cum 46.06

    0.090 Cum 383 1 Cum 34.45

    KG Cost of packed Bitumen 26500 1 Mt 646.60

    10 Sqm 266.25 266.25

    10 Sqm Labour Charges

    Rate for 10 Sqm 1111.57

    Rate for 1 Sqm 111.16

    Providing and laying P.C. withseal coat type A for 20mmthickness using 0.18 cum of13.20 MM IRC and 0.09 Cum of11.2 mm IRC. Machine crushedmetal with 14.60 Kg ofBitumen for Green mixing 10Sqm of premix carpet and 0.09cum of 6.70mm IRC machine

    crusher metal with 9.80 kgs ofbitumen for seal coat type Aper 10 sqm including cost andconveyance of materials to thework sight and stacking themto the departmental metricguage for pre measurementhating bitumen boiler heatingCost of 13.2 mm IRC HBGmachine metal

    Cost of 11.2mm IRC HBG

    machine metalCost of 6.70mm IRC HBGmachine metal

    24.400

    Hire charges for Tools andplant

    10Sqm

    10Sqm

  • 8/14/2019 NEW Conveyance Rates 07-08

    25/37

    Name of Work :-

    I Layer Using Grade II Metal (90mm to 22.4mm) size metal

    Qty Unit Description Rate Per Amount

    0.050 Cum Cost of 90mm IRC HBG Metal 221.75 1 cum 11.09

    0.450 Cum Cost of 63mm IRC HBG Metal 358.75 1cum 161.44

    0.425 Cum Cost of 53mm IRC HBG metal 433.75 1 cum 184.34

    0.050 Cum Cost of 45mm IRC HBG metal 509.75 1 cum 25.49

    0.025 Cum Cost of 22.4 mm IRC HBG metal 710.75 1 cum 17.77

    0.24 Cum Cost of Red Gravel 100.65 1 cum 24.16

    10.00Sqm Higher Charges for Tolls & Plant 169.1710 Sqm 169.17

    10.00Sqm Labour Charges

    - Rate for 10 Sqm 593.45

    - Rate for 1 Cum 791.27

    Name of Work :-

    II Layer Using Grade III Metal (63mm to 22.4mm) size metal

    Qty Unit Description Rate Per Amount

    0.025 Cum Cost of 63mm IRC HBG Metal 358.75 1 cum 8.97

    0.200 Cum Cost of 53mm IRC HBG metal 433.75 1 cum 86.75

    0.725 Cum Cost of 45mm IRC HBG metal 509.75 1 cum 369.57

    0.025 Cum Cost of 22.4 mm IRC HBG metal 710.75 1 cum 17.77

    0.025 Cum 511.75 1 cum 12.79

    0.24 Cum Cost of Red Gravel 100.65 1 cum 24.16

    10 Sqm 169.1710 Sqm 169.17

    10Sqm Labour Charges

    - Rate for 10 Sqm 689.18

    - Rate for 1 Cum 918.91

    Cost of 11.20 mm IRC HBG

    Higher Charges for Tolls & Plant

  • 8/14/2019 NEW Conveyance Rates 07-08

    26/37

    Name of Work :-

    LEAD PARTICULARS

    KIND OF MATERIALS NAME OF QUARRY LEAD IN KM COST TOTAL

    190MM IRC HBG METAL 1 213.00 5.60 3.15 221.75

    2 63 MM IRC HBG METAL 1 350.00 5.60 3.15 358.75353MM IRC HBG METAL 1 425.00 5.60 3.15 433.75

    445 MM IRC HBG METAL 1 501.00 5.60 3.15 509.75

    526.5 MM IRC HBG METAL 1 550.00 5.60 3.15 558.75

    622.4 MM IRC HBG METAL 1 702.00 5.60 3.15 710.75

    7 1 648.00 5.60 3.15 656.75

    8 1 503.00 5.60 3.15 511.75

    9 1 374.00 5.60 3.15 382.75

    10Red Gravel 1 92.00 5.60 3.05 100.65

    11Well Murambu 1 82.00 5.60 3.05 90.65

    12Bitumen (packed) 60/70

    13Emulsion Bitumen

    Certified that the Lead particulars furnished above are correct to the best of my knowledge

    Sl.No

    CONVEYANCE

    STACKING

    13.2MM IRC Machine Crusher

    11.2MM IRC Machine CrusherMetal6.7MM IRC Machine CrusherMetal

    26500.00

    26500.00

    24700. 24700.0

  • 8/14/2019 NEW Conveyance Rates 07-08

    27/37

    9.Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and

    conveyance and all labour charges etc., Complete for 10 Cum

    9.00 Cum Cost of 40mm metal 506.80 1 Cum 4561.20

    4.50 Cum Cost of CM 1:4 1553.32 1 Cum 6989.94

    1.80 Nos Mason II Class 145.00 Each 261.00

    17.70 Nos Mazdoor I Class 100.00 Each 1770.00

    14.10 Nos Mazdoor II Class 90.00 Each 1269.00

    L.S. Sundries L.S 0.06

    For 10 cum 14851.20

    Rs. 1485.12 /1 cum

    Brick work in CM 1:5 mix using country bricks of size 8 x 4 x 2 including all

    cost and conveyance of all materials and all labour charges etc., Complete for 10 Cum.

    6570.00 Nos Cost of country bricks 1470.00 1000 Nos 9657.90

    3.00 Cum Cost of Sand 248.50 1Cum 745.50

    860.00 Kgs Cost of Cement 3624.50 1Mt 3117.07

    3.50 Nos Mason I Class 160.00 Each 560.00

    7.10 Nos Mason II Class 145.00 Each 1029.50

    7.10 Nos Mazdoor I Class 100.00 Each 710.00

    14.10 Nos Mazdoor II Class 90.00 Each 1269.00

    L.S Sundries L.S 0.03

    Rate for 10 Cum 17089.00

    Rs. 1708.90 / 1 cum

    Plastering with Cm 1:5 mix using to 12 mm thick including all cost andconveyance of all Materials and all labour charges etc., Complete for 10 Sqm.

    0.14 Cum Cost of CM 1:5 1319.36 1Cum 184.71

    1.10 Nos Mason I Class 160.00 Each 176.00

    0.50 Nos Mazdoor I Class 100.00 Each 50.00

    1.10 Nos Mazdoor II Class 90.00 Each 99.00

    L.S Sundries L.S 0.09

    For 10 sqm 509.80

    Rs 50.98 /1 sqm

    Random Rubble Masonry in CM 1:5 mix using required Bond stone simultaneous

    pointing including all cost conveyance and all labour charges etc, Complete.

    10.00 Cum Cost of Rough stone 246.80 1Cum 2468.00

    1.00 Cum Cost of Bond stone 331.80 1Cum 331.80

    3 40 Nos Cost of CM 1:5 1553 32 1Cum 5281 29

  • 8/14/2019 NEW Conveyance Rates 07-08

    28/37

    Plastering with CM 1:5 mix using to 20 MM thick including all costconveyance etc., Complete.

    0.22 Cum Cost of CM 1:5 1319.36 1 Cum 290.26

    2.20 Nos Mason I Class 160.00 Each 352.00

    0.50 Nos Mazdoor I Class 100.00 Each 50.00

    3.20 Nos Mazdoor II Class 90.00 Each 288.00

    L.S Sundries L.S 0.04

    For 10 sqm 980.30

    Rs. 98.03 /1 sqm

    CC 1: 2: 4 Mix using 20mm ISS HBG metal including all costand conveyance and all labour charges etc., Complete.

    9.00 Cum 701.80 1Cum 6316.20

    4.50 Cum Cement Mortar 1:2 2858.14 1Cum 12861.63

    1.80 1Nos Mason II Class 145.00 1Cum 261.00

    17.70 Nos Mazdoor I Class 100.00 Each 1770.00

    14.10 Nos Mazdoor II Class 90.00 Each 1269.00

    L.S Sundries L.S 0.07

    Rate for 10 cum 22477.90

    Rs. 2247.79 / 1 cum

    and conveyance etc., complete

    1.00 Qtl Cost of steel 31000.00 1Mt 3100.00

    0.01 Qtl Cost of binding wire 33.00 1 kg 33.00

    3.50 Nos Fitter I Class 140.00 Each 490.00

    For 1 qtl 3623.00

    Rs. 3623.00 /qtl

    RCC 1:11/2:3 mix using using 20mm size of HBG metal including all costand conveyance etc., complete

    9.00 Cum Cost of 20mm Metal 701.80 1 Cum 6316.20

    4.50 Cum Cost of Sand 248.50 1Cum 1118.25

    4308.00 Kgs Cost of Cement 3624.50 1 Mt 15614.35

    3.50 Nos Mason II Class 145.00 Each 507.50

    21.20 Nos Mazdoor I Class 100.00 Each 2120.00

    35.30 Nos Mazdoor II class 90.00 Each 3177.00

    L S S d i L S 0 00

    Cost of 20mm IssHBG metal

    Supplying and fabrication of steel for RCC works including all cost

  • 8/14/2019 NEW Conveyance Rates 07-08

    29/37

    Granolithic Cement Concrete 1:2:4 mix to 0.25m thick using 10mm to12mm ISS size of HBG metal including all cost and conveyance of all materials

    to work site and all labour charges etc., complete for 10 cum

    9.00 Cum 564.30 1 Cum 5078.70

    4.50 Cum Cement Mortar 1:2 2858.14 1 Cum 12861.63

    1.80 Nos Mason II Class 145.00 Each 261.00

    17.70 Nos Mazdoor I Class 100.00 Each 1770.00

    14.10 Nos Mazdoor II 90.00 Each 1269.00L.S Sundries L.S 0.07

    For 10 cum 21240.40

    Rs. 2124.04 /1 cum

    Pointing with CM 1:3 mix over pressed titles on terrace roofing including all cost

    and conveyance of all materials and labour charges etc., Complete for 10 sqm

    0.04 Cum Cost of CM 1: 3 2015.26 1 Cum 80.61

    2.20 Nos Mason II Class 145.00 Each 319.00

    0.50 Nos Mazdoor I Class 100.00 Each 50.00

    1.10 Nos Mazdoor II Class 90.00 Each 99.00L.S Sundries L.S 0.09

    For 10 sqm 548.70

    Rs. 54.87 /1 sqm

    Brick jelly with lime concrete using 20mm size of brick jelly with no sand

    to be add including all cost and conveyance and all labour charges etc., complete

    12.80 Cum 287.70 1 Cum 3682.56

    5.00 Cum Cost of lime Stone 348.85 1 Cum 1744.25

    1.80 Nos Mason I Class 160.00 Each 288.00

    17.70 Nos Mazdoor I Class 100.00 Each 1770.00

    14.10 Nos Mazdoor II Class 90.00 Each 1269.00

    L.S Sundries L.S 0.09

    For 10 cum 8753.90

    Rs. 875.39 / 1 cum

    Weathering course concrete using brick jelly of size 20mm slacked lime

    (no sand to be used) over the RCC roof slab brick jelly in lime being 32 : 12 by volumeand top finished with one course of pressed tiles and pointing with CM 1:3 etc., complete.

    Cost of 10mm to12mm ISS HBG metal

    Cost of 20mm brickjelly

  • 8/14/2019 NEW Conveyance Rates 07-08

    30/37

    1.10 Nos Mazdoor II Class 90.00 Each 99.00

    L.S Sundries L.S 0.05

    For 10 sqm 3496.80

    Rs. 349.68 / 1 sqm

    White washing two coats with best shell lime including all cost and

    conveyance and all materials and all labour charges etc., complete for 100 Sqm

    0.07 Cum Cost of shell lime 705.00 1 Cum 49.35

    1.60 Nos Mason II Class 145.00 Each 232.00

    0.50 Nos Mazdoor I Class 100.00 Each 50.00

    2.70 Nos Mazdoor II Class 90.00 Each 243.00

    L.S L.S 2.05

    For 100 sqm 576.40

    Rs. 5.76 / 1 sqm

    Colour washing two coats including all cost conveyance and all labour

    charges etc., complete

    10.00 Sqm Cost of white washing 5.76 1 Sqm 57.64

    L.S L.S 28.82

    For 10 sqm 86.46

    Rs. 8.65 / 1 sqm

    Painting with ready mixed good quality of enamel paint two coats including

    all cost and conveyance etc., complete for 10 Sqm Over new Iron works.

    2.22 Lits Cost of enamel paint 150.00 1 Litter 333.00

    1.10 Nos Painter Ist Class 130.00 Each 143.00

    L.S Sundries L.S 0.00

    For 10 sqm 476.00

    Rs. 47.60 / 1 sqm

    Plastering withs CM 1:3 10mm thick including all cost and conveyance and alllabour charges etc., complete.

    0.10 Cum Cost of CM 1:3 2015.26 1Cum 201.53

    1.10 Nos Mason I Class 160.00 Each 176.00

    1.10 Nos Mazdoor I Class 100.00 Each 110.00

    1.10 Nos Mazdoor II Class 90.00 Each 99.00

    L.S Sundries L.S 0.07

    For 10 sqm 586.60

    Rs. 58.66 / 1 sqm

    Distermpering two coats includidng all cost anad conv eyance and all labour chargesfor 10 sqm.

    1.34 Kgs Distember 60.00 1Kg 80.40

    Sundries for gum &conjee water

    and for colour pigments(50%

  • 8/14/2019 NEW Conveyance Rates 07-08

    31/37

    3.23 kgs snowcem paint 30.00 1Kg 96.90

    0.50 No. Painter I class 130.00 Each 65.00

    0.50 No. Mazdoor Igrade 100.00 Each 50.00

    0.80 No. Mazdoor II Grade 90.00 Each 72.00

    Sundries L.S. 0.10

    for 10 sqm 302.00

    Rs. 30.20/ 1 sqm

    Brick work in CM1:3mix using country bricss including all cost and conveyance etc. complet

    6570.00 Nos Cost of country bricks 1470.00 1000 Nos 9657.90

    3.00 Cum Cost of Sand 248.50 1Cum 745.50

    1433.33 Kgs Cost of Cement 3624.50 1Mt 5195.10

    3.50 Nos Mason I Class 160.00 Each 560.00

    7.10 Nos Mason II Class 145.00 Each 1029.50

    7.10 Nos Mazdoor I Class 100.00 Each 710.00

    14.10 Nos Mazdoor II Class 90.00 Each 1269.00

    L.S Sundries L.S 0.07

    Rate for 10 Cum 19167.07

    Rs. 1916.71 / 1 cum

    Plastering with C 1:3, 20mm thick including all cost andconveyance etc., Complete.

    0.22 Cum Cost of CM 1:3 2015.26 1 Cum 443.36

    2.20 Nos Mason I Class 160.00 Each 352.00

    0.50 Nos Mazdoor I Class 100.00 Each 50.00

    3.20 Nos Mazdoor II Class 90.00 Each 288.00

    L.S Sundries L.S 0.04

    For 10 sqm 1133.40

    Rs. 113.34/1 sqm

  • 8/14/2019 NEW Conveyance Rates 07-08

    32/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    33/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    34/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    35/37

  • 8/14/2019 NEW Conveyance Rates 07-08

    36/37

    .

  • 8/14/2019 NEW Conveyance Rates 07-08

    37/37

    11.00 Cum Cost of Rough stone 1 Cum

    3.50 Nos Wooder 105.00 Each 367.50

    10.60 Nos Mazdoor I Class 100.00 Each 1060.00

    7.10 Nos Mazdoor II Class 90.00 Each 639.00

    11.60 Cum Cost. Red Gravel 97.60 Each 1132.16

    7.10 Nos Mazdoor I Class 100.00 710.00

    3.50 Nos Mazdoor II Class 90.00 315.00

    L.S. Sundries L.S

    For 10 cum

    Rs. /1 cum

    Rough stone Dry packing for approns and revetmante including Gravelpacking including all lapour Charges etc. complete