new design considerations for fire pump installations

Upload: jrainman

Post on 01-Jun-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    1/28

    New Design Considerationsfor

    Fire Pump Installations

    Milosh Puchovsky, PE, FSFPE

    Professor of PracticeWorcester Polytechnic Institute

    Dept. of Fire Protection Engineering

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    2/28

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    3/28

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    4/28

     Agenda

    • 

    Very Tall Buildings

    • 

    Redundancy

    • 

    Fire Pump Access•  Water Supply

    •  Pressure Control

    • 

    Testing & Piping Arrangements

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    5/28

    Should all high rise buildings be

    considered the same way?

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    6/28

    Very Tall Buildings

    What about buildings beyond the pumping

    capability of the fire department?

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    7/28

    Very Tall Buildings

    • 

    Not connected to a specific height.

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    8/28

    Very Tall Buildings

    Where primary water

    supply is from tanks,

    how many tanksshould be provided?

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    9/28

    Very Tall Buildings

    • 

    Total volume of all tanks or compartments

    to be sufficient for the full fire protection

    demand.•

     

    Each individual tank or compartment to be

    sized so that at least 50% of the fire

    protection demand is stored with any one

    compartment or tank out of service. (20:5.6.1)

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    10/28

    Very Tall Buildings

    • 

     Automatic & manual refill valves sized and

    arranged to independently supply the

    system fire protection demand for eachwater tank or compartment. (20:5.6.1)

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    11/28

    Very Tall Buildings

    • 

    Should redundant fire pumps be provided?

    • 

    Under what conditions?

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    12/28

    Very Tall Buildings

    Fire pumps serving zones that are partially or whollybeyond the pumping capability of the fire department

    apparatus to be provided with one of the following: 

    (1) 

     A fully independent and automatic backup fire pump

    unit(s) arranged so that all zones can be maintained in

    full service with any one pump unit out of service.

    (2) An auxiliary means that is capable of providing the fullfire protection demand and that is acceptable to the

     AHJ, i.e. gravity fed standpipe systems. (20:5.6.2)

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    13/28

     Auxiliary Power for Pumps in

    High Rise Buildings•

     

    Where electric motors are used, and the

    height of the structure is beyond the

    pumping capability of the fire departmentapparatus, an alternate source of power to

    be provided. (20:9.3)

    • 

     Alternate source not required where the

    following are provided: –  Back up engine driven pump

     –  Back-up motor driven pump on independent

    power source

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    14/28

    Terminology

    On-Site Standby Generator. A facility

    producing electric power on site as the

    alternate supply of electric power. It differsfrom an on-site power production facility, in

    that it is not constantly producing power.(20:3.35)

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    15/28

    Pump Room Access in High

    Rise BuildingsConsiderations to be addressed with the

    Fire Department (20:5.3)

     – 

     Access directly from outside –

     

    Locations above and below grade (protected

    passageways)

     –  Discharge of pump equipment (packing

    glands, relief valves, etc.)

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    16/28

    Pressure Fluctuations – Water

    Supply

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    17/28

    Confirmation of Water Supply

    • 

    Water flow tests to be completed not more

    than 12 months prior to the submission of

    working plans

    • 

     Acceptance Testing. Unadjusted fire

    pump discharge flows and pressures to

    meet or exceed the system demand.

    • 

    Comparison with shop curves still

    required.

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    18/28

    Low Suction Throttling Devices

    • 

    Friction loss through a low suction-

    throttling valve in the fully open position

    must be taken into account during design.

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    19/28

    System Overpressures

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    20/28

    System Overpressures

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    21/28

    System Overpressure –

    Variable Speed Control

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    22/28

     Acceptance Testing

    • 

    Where variable speed pressure limiting

    control is employed, fire pump

    performance to be tested at: churn, 25%,

    50%, 75%,100%,125% and 150% of rated

    pump capacity.

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    23/28

    Pressure Relief Valve Discharge

    Back to Suction•  Relief valves only

    permitted to

    address

    abnormal

    conditions.

    •  Dischargepermitted to be

    piped back to

    suction.

    Concerns for diesel engine driven pumps that incorporateheat exchanger cooling for the engine.

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    24/28

    Flow

    Meters &

    Testing

    Devices

    Where a

    installed in alooped

    arrangement

    for flow

    testing, an

    alternate

    means of

    measuring

    flow to be

     provided.

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    25/28

    Break Tank Sizing

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    26/28

    Series Fire Pump Arrangement

    Should all pumps

    comprising a series

    fire pump installationbe located in the

    same fire pump

    room?

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    27/28

    Final Remarks

    Given the same conditions, will a fire behave

    differently based on it geographic location?

     

  • 8/8/2019 New Design Considerations for Fire Pump Installations

    28/28

    Thank You