new ship lift at niederfinow the planning process and ... · pdf filenew ship lift at...
TRANSCRIPT
New ship lift at Niederfinow –
the planning process and technical aspects
Dipl.-Ing. Peter Huth - Wasserstraßen-Neubauamt Berlin
Herr Dr.-Ing. Hans-Gerd Lindlar - Krebs und Kiefer,
Beratende Ingenieure für das Bauwesen GmbH
Summary
A second ship lift is to be constructed in Niederfinow adjacent to the existing lift. After extensive
preliminary studies, the Federal Waterways Administration decided on a vertical lift with balanc-
ing counterweights. A load-bearing structure consisting of reinforced concrete towers, columns
and cable pulley girders, all with foundations in a common caisson well, transfers the loads from
the water-filled caisson (9 000 t) into the bedrock via cable pulley girders. The caisson, which is
suspended on cables and balanced with counterweights, has a usable length of 115 m, a usable
width of 12.5 m and allows a water depth of 4.0 m. Vertical movements of the caisson take place
by means of rack and pinion drives. A safety system consisting of internally threaded columns
and rotary locking bars ensures that the caisson stops safely in an emergency. Official permission
for construction was granted on 04.01.2005 and the execution design of the lift was approved on
03.01.2006.
Figure 1. Overview
On 16.05.2008, the contract to construct the new ship lift was awarded to the Neues Schiffshebewerk
Niederfinow consortium, consisting of Bilfinger Berger Ingenieurbau GmbH, DSD Brückenbau GmbH,
Johann Bunte Bauunternehmung GmbH & Co. KG and Siemag M-Tec² GmbH. The consortium started
work in summer 2008.
The ship lift is expected to go into operation in 2014.
2
1. Reasons and preliminary studies
1.1 Basic principles
Due to its sound construction, the ship lift that opened in 1934 on the Oder-Havel canal in Nie-
derfinow has only been out of service for 60 unplanned days in 72 years of operation. Guarantee-
ing such a high level of operational readiness has, however, led to high maintenance costs and
increasingly extensive repair work.
The dimensions of the present caisson (85.0 m x 12.0 m x 2.5 m) represent a significant limita-
tion to shipping with today’s vessels. Moreover, cost-effective container traffic cannot be devel-
oped because of the maximum permissible passage height of 4.10 m. These considerations led to
the planning and construction of a new descent on the Havel-Oder waterway (HOW) in Nieder-
finow.
As a result of the preparatory work, the following concept was developed:
- the load-bearing structure extends over the entire length of the caisson
- the load-bearing elements subject to compression are made of concrete, those subject to
bending forces are made of steel
- the cables that connect the caisson with the counterweights are attached directly to the
caisson
- in the same way as in the existing lift, the caisson is secured by a rotary locking bar/internal
thread column system.
Further basic principles were published in May 2006 on the occasion of the XXXI. PIANC con-
gress in Estoril.
2. Technical solution
2.1 General description
The new ship lift facility is located at the foot of a 36 m high escarpment and consists of:
- the ship lift with its load-bearing structure, caisson with counterweights, caisson safety sys-
tem, caisson well and lower docking station
- the canal bridge with abutment, safety gate and upper docking station
- the upper basin that branches off the summit reach of the Havel-Oder waterway and the
lower basin that opens out into the Oderhaltung area of the Havel-Oder waterway.
The main dimensions are shown in Table 1, while Figure 2 shows a longitudinal section.
Height Width Length
Ship lift 55.0 m 32.4 m 46.7 m2)
154.0 m
Caisson 7.5 m 18.3 m 27.5 m2)
125.5 m
Caisson well (external) 11.0 m1)
36.5 m 48.4 m2)
133.2 m
Canal bridge 8.2 m 21.7 m 28.2 m2)
65.5 m
Upper basin 46.5 m 990.0 m4)
Lower basin 46.5 m – 90.0 m5)
800.0 m4)
1) depth to upper surface of caisson well sole
2) in the area of the pylons/drive housings
3) western support, without side extension for visitor walkways
4) length of waiting area for commercial shipping
5) widening due to curve
Table 1: Main dimensions
3
2.2 Basic design principles and load assumptions
Before the start of the planning process, basic design principles were established from which all
load assumptions and other basic planning information could be derived.
The most important design principles are:
2.2.1 Water levels
Water levels in the upper pound (summit reach of HOW)
BWo + dyn z = NN + 37.60 m
BWo = NN + 37.55 m
Figure 2: Longitudinal section
Top water level = NN +37.25 m
BWu = NN +37.05 m
BWu - dyn z = NN +36.95 m
Water levels in the lower pound (HOW, Oderhaltung)
BWo + dyn z = NN + 1.85 m
BWo = NN + 1.85 m
BWu = NN + 1.20 m
BWu - dyn z = NN + 1.20 m
2.2.2 Period of operation
The ship lift is to be in operation for 80 years with 310 days of operation per year, 16 hours per
day and 0.5 hours transition time.
2.2.3 Design principles
Typical values of the forces
The values specified in DIN 19704-1, Point 5 apply with the following additions:
- hydrostatic design water level taking wind and surge into account = BWo + dyn z
- hydrodynamic effect of ship movement = ± 0,11 m (in addition to hydrostatic design water
level)
4
- area load = 150 kN/m² (at height BWo)
- ice thickness = 0.30 m
- raising of the bearings
raising of one bearing axis with hydraulically coupled presses under its own weight plus a wa-
ter layer 0.20 m deep
- wind load
According to the expert report on wind, the effect of dynamic pressure of qK= 0.4 N/m²
transversely and qK = 1.3 kN/m² longitudinally to the bridge with an aerodynamic force coef-
ficient of 2.1 is to be taken into account.
Height of traffic area 4 m above BWo
- sunken ship
in the water-filled canal bridge (water level at BWo)
load on floor of canal bridge pS = 26kN/m2
load width B2 = 11,4kN/m²
load length LS = 110 m
in a transverse direction in the most unfavorable position for the building
component involved
in the empty canal bridge
load on floor of canal bridge pS = 30kN/m²
otherwise as above
2.2.4. Combinations of loads
Based on the requirements of DIN 19704-1, basic combinations and extraordinary combinations
were considered with the loads and factors given in Table 2 below.
5
Partial safety factors F and combination factors for ultimate limit state checks
(not including proof of fatigue strength) for the steel construction of the canal bridge
No. Type Forces
Basic combinations Extraordinary combinations
Case 1 Case 2 Case 3 Case 42) Case 52) Case 62)
1 constant Self weight
Fo
r al
l fo
rces
F
=1.3
5
= 1.0 = 1.0
2
var
iab
le
Hydrostatic design water level
= 1.0
= 0.9
= 0.9 = 0.8
3 Hydrodynamic force from ship
motion
4 Live load
= 0.8
5 Accelerating + braking forces
6 Change to support conditions = 0.8
7 Raising of bearings
8 Ice pressure
= 0.9
9 Temperature3) = 0.8 = 0.8 = 0.8
10 Wind
11 Friction from ships
12
Resistance to motion and de-
formation in the bearings, mov-
able joints and seals
= 0.9
13
extr
aord
inar
y
Impact of ship1) = 0.8
14 Sunken ship, canal bridge full = 0.8
15 Sunken ship, canal bridge emp-
ty
= 0.8
16 Snow during construction = 0.8
17 Special loads during construc-
tion
= 0.8
1)
DIN 19704-1 Point 7.2 applies to the ship arrester equipment 2)
Superposition of constant and variable forces with one extraordinary force in each case 3)
When using the temperature fields for the exceptional combinations, the partial safety factor F =1.15
can be used
Table 2: Loads, basic combinations and extraordinary combinations
3. Ship lift
3.1 Load-bearing structure
The load-bearing structure transfers the loads of the caisson and counterweights via the cable
pulleys into the cable pulley girders and from there via two pylons and six cable pulley girder
piers on each side into the bedrock via the caisson well. The principle of the load-bearing system
is shown in Figure 3.
Figure 3: Principle of the load-bearing system
Seilrollen
Tragwerk
- Seilrollenträger
- Pylone
- Stützen
Trog
Gegenge-
wichte
Trogwanne
6
The caisson well is a half-frame which lies flat on the underwater concrete base of the construc-
tion pit. The sides of the load-bearing structure are not connected in a statically effective way.
The cable pulley girders, cable pulley girder piers, pylons and caisson well are rigidly connected.
Viewed as a total system, they form a half-frame with substantially separated sides of variable
stiffness. In the east, the caisson well merges into the lower pound.
The load-bearing structure supports the eastern support of the canal bridge, the cable pulley hall,
the control room, the visitor bridges between the canal bridge and the western pylons, the visitor
bridges between the pylons and also the lattice girders between the pylons. To support the canal
bridge, the westernmost cable pulley girder piers are connected with each other by a concrete tie
bar.
Steel of quality S355 was specified for the cable pulley girders which are subject to bending
loads and for the caisson. For the pylons and piers, which are primarily subject to compression,
and also for the caisson well, which is integrated into the site foundations, concrete of quality
C35/45 was chosen. In order to achieve an attractive concrete surface, sample formwork draw-
ings patterns were produced which specify the formwork material including its distribution and
construction joints.
3.1.1 Cable pulley girders
The two cable pulley girders run lengthwise along the lift above the pylons and cable pulley
girder piers. They support the loads from the cable pulleys, cable pulley hall, visitor walkways,
visitor bridges and control room.
Their overall length is 131.2 m, their height is 2.0 m and their width 7.2 m. They are manufac-
tured as hollow sections from plates up to 40 mm thick. On each cable pulley girder the twin
cable pulleys are supported in bearing blocks, except in the areas above the pylons. The 256
counterweight cables running over the cable pulleys are guided through the cable pulley girder
through openings of d = 520 mm.
3.1.2 Cable pulley halls
Two cable pulley halls protect the cable pulleys from the weather. They are 131.2 m long, up to
9 m high and around 8 m wide at their base. Including a canopy cantilevered inward over the
visitor walkways, their roof width is 10.60 m. A cross-section is shown in Figure 4.
Lengthwise, each cable pulley hall is divided into five sections. The cable pulleys are located in
the outer and center sections. In the sections above the pylons, the visitor routes and emergency
routes cross over to the stairwells and elevators located in the pylons on the outside of the build-
ings. The section above the eastern pylons has a further storey through which the control room is
accessed and in which operations rooms are located.
The external shape of the cable pulley halls is a feature of the architectural design; they have
pent roofs which incline inwards at 14°, outer walls that incline outwards by 3°, roof covering
and façade cladding with profiled aluminum panels and glazing of the end surfaces and internal
walls.
To allow replacement of the cable pulleys, the roof beams and covering can be completely re-
moved.
7
Figure 4: Cross-section of a cable pulley hall
3.1.3 Caisson well
The caisson well is constructed as a watertight concrete tank with a base that is 2.4 m thick and
side walls that are 1.5 m thick at the top and up to 3.0 m thick at the bottom. In the area of the
pylons, the caisson well is around 8 m wider than between the pylons. For drainage purposes, its
surface is constructed in first-stage concrete with a slope of 1 % transverse to the longitudinal
axis of the lift.
In order to avoid negative effects on the existing lift, the caisson well will be constructed in a pit
that is impermeable to ground water. For this purpose, a mixed sheet pile wall with size 1000 I-
beams and double-plank infill walling will be driven into the bedrock to a depth of over 22 m
and anchored. To prevent uplift, slender piles at intervals of 2.5 m will be bored under water 17.5
m into the base of the caisson well from the base of the pit which is about 15 m below ground
level. After this, a 1.2 m thick layer of underwater concrete will be laid. The shoring of the pit
will be used to support the formwork for the caisson well and provided with leveling formwork
so that the construction concrete has a uniform thickness.
3.2 Caisson
The lift caisson is a self-supporting structure with a load-bearing cross-section consisting of the
operations walkways, the side walls of the caisson and the caisson floor. Cross beams and longi-
tudinal ribs stiffen the cross-section as shown in Figure 5. The cross beams are connected at both
ends by longitudinal beams to which the counterweight cables are secured.
8
The cross beams, which are reinforced in the area of the caisson quarters, transfer the imbalance
loads into the load-bearing structure via the caisson safety system. The drives that run through
the pylons are located in this area at the sides of the caisson. Machine housings protect the
drives.
The specifications on the use of the lift result in an overall caisson length of 125.5 m, a width of
18.3 m in the area of the counterweights and of 27.9 m in the area of the drive housings; the con-
struction height in the area of the counterweights is 6.3 m. In the area of the caisson safety sys-
tem, the cross beams are 2.5 m high, resulting in a construction height in that area of 7.5 m. The
operations walkways along the sides at the top of the caisson are 2.0 m wide; those in the area of
the ship arrester equipment are 0.6 m wide and those at the height of the caisson base are 1.1 m
wide. During motion, the caisson is guided in transverse and longitudinal directions in such a
way that it moves at equal distances between transverse guides.
While moving into or out of the caisson, ships cause fluctuations in the water level. In order to
reduce the resulting loads on the drives, the caisson is secured by a caisson locking mechanism
when it is at the docking points. This locking system is designed for a caisson imbalance corre-
sponding to a water level fluctuation of 25 cm. A latch design is envisaged which is secured to
the caisson and locks by means of a travelling counterpart (locking bar). To protect the locking
mechanism from damage in the event of greater imbalance, it yields when overloaded so that the
caisson begins to move. The rotary locking bars of the caisson safety system then engage with
the internally threaded columns.
Swivel-radial gates close off the caisson at both ends. When open, they are rotated into niches in
the floor, and they can be rotated upwards out of the water for inspection purposes. The gates are
moved by two electric jacks, each with 650 kN drive force. A cable-arrester facility protects the
gates against ship impact.
Figure 5: Cross-section of the caisson
9
3.3 Caisson safety system
The caisson safety system prevents overloading of the pinion and the brakes of the drive by se-
curing the caisson by means of four rotary locking bars in four internally threaded columns. This
operating situation constitutes an emergency and can occur if the caisson is emptied or over-
filled. Planned emptying of the caisson also takes place approximately once a year for inspection
and repair purposes.
The internally threaded columns are 41.6 m long, with a split internal thread anchored inside the
pylons, and consist of several sections. The rotary locking bars, connected with the caisson via
pendulum supports, have 4 thread pitches, a height of 3 m and an outer diameter of 1.08 m. Each
weighs around 10 t. At right angles to the caisson, the four axes of the internally threaded col-
umns are 30 m apart, and lengthwise along the caisson they are 69.85 m apart.
During normal operation, the caisson drives rotate the rotary locking bars freely via a coupled
shaft system. Up to the point of settlement on the internally threaded columns, the force on the
pinion corresponds to the external force on the spring housing, taking leverage into account.
Taking into account friction, accelerating/braking forces and wind forces and a water level in the
caisson of less than 0.08 m, the force on the spring housing is less than 200 kN.
The pre-loading of the springs is selected so that the pinion does not start to deflect against the
spring until a force of 200 kN is exceeded. When spring deflection in one spring housing starts,
the 4 caisson drives are stopped. The force on the pinion then increases in accordance with the
spring characteristics. When the force on the pinion reaches 990 kN, the rotary locking bar set-
tles in the internally threaded column and absorbs the differential loads until the maximum im-
balance load has been applied and a force of 1090 kN therefore acts on the pinion. The force
acting on the pinion is continuously measured, both while the caisson is stationary and while it is
moving. In the event that the maximum operating force on the pinion is exceeded, the drive is
switched off and the pinion deflects against the spring.
4. Canal bridge
Figure 6: Canal bridge
10
The 65.5 m long canal bridge connects the lift with the upper basin. Like the lift caisson, it has a
usable width of 12.5 m. Figures 6, 7 and 8 show different views of the canal bridge.
Like the lift caisson, it is closed on the lift side by a swivel-radial gate which is protected by a
cable arrester facility. The gate thus forms the eastern end of the summit reach of the canal. The
clearance evacuation and reversing equipment is located in the eastern head area of the canal
bridge, in addition to the gate drives.
On the right and left of the canal bridge there are side paths which can be used by maintenance
vehicles. This makes it is possible to lift the heavy sliding gates of the caisson evacuation
equipment through openings using a truck-mounted crane on the canal bridge and to take them
away for repair. For inspection purposes, the canal bridge can be viewed from the side paths us-
ing special vehicles that can reach underneath it, as is customary for motorway bridges.
In addition to the canal bridge, the 25 m long and up to 31.5 m wide western abutment supports
the safety gate with its gate drive housings. The gate is closed for scheduled emptying of the
canal bridge, or if, in an emergency, there is a risk of water flowing out of the summit reach of
the canal via the canal bridge or the lift. A hawser capture cavity with a volume of 75 m³ is inte-
grated into the base of the abutment. To ensure that the abutment reliably directs the horizontal
loads from the canal bridge into the site foundations when the pound gate is closed and the clear-
ance is empty, it has foundations consisting of bored piles embedded in the solid boulder clay.
For this reason, the 28 piles with a diameter of 1.2 m are 24 to 30 m long.
On the headwater side, the clay sealing layer of the upper basin and the safety bulkhead with an
inspection walkway connect with the abutment. The connection with the canal sealing consists of
a 3 m thick clay wedge. The integrity of the connection of the safety bulkhead with the abutment
can be monitored from an inspection walkway which crosses the canal on the eastern side under
the abutment.
Figure 7: Cross-section of the canal bridge
Quelle: HPI
11
Figure 8: Radial sectional gates between the canal bridge and the caisson
5. Participants in the project and outlook
As preparatory measures, electrical cables were re-routed and parts of the Niederfinow municipal
building yard were relocated in 2005. In March 2006, invitations to tender for the necessary
demolition tasks were sent out. In parallel with this, the contract documents for the construction
of the ship lift were produced and preparations for the awarding of contracts were made.
On 16.05.2008, the contract to construct the new ship lift was awarded to the Neues Schiffshe-
bewerk Niederfinow consortium consisting of Bilfinger Berger Ingenieurbau GmbH, DSD
Brückenbau GmbH, Johann Bunte Bauunternehmung GmbH & Co. KG and Siemag M-TEC2
GmbH. The consortium started work in summer 2008.
The most important participants in the project are listed in the table below.
Role/task Name
Owner Wasserstraßen-Neubauamt Berlin
Study of alternative solutions Krebs und Kiefer, SBE Magdeburg, Germanischer Lloyd
Design planning Lahmeyer International/Hydroprojekt with Ingenieurbüro
Rapsch und Schubert, Werner Sobek Ingenieure, DriveCon
Inspection of structural design Prüfgemeinschaft (inspection consortium) Niederfinow
consisting of
Krebs und Kiefer, Germanischer Lloyd, SBE Magdeburg
Advice to owner,
site foundations and design
Bundesanstalt für Wasserbau (BAW)
Construction Bilfinger Berger Ingenieurbau GmbH,
DSD Brückenbau GmbH,
Johann Bunte Bauunternehmung GmbH & Co. KG
Siemag M-Tec2 GmbH
Table 3: Participants in the project
Segmenttore
Kanalbrücke Trog
12
Assuming that construction proceeds smoothly, the new Niederfinow ship lift will go into opera-
tion in 2014. By then, ca. 53 700 m3 of concrete, 8 900 t of reinforcing steel and 6 000 t of steel
will have been used. A total of ca. 396 000 m³ of earth will have been moved. The construction
costs are estimated at ca. 285 million €.
Figure 9: Construction site in August 2010