New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Upload: eugenia-ward

Post on 13-Jan-2016

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

New Supervisor’s Office and Ranger District Building

Some interesting things that can happen when initiating a build-to-suit lease

Mike Shoup2007

Page 2: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Old Supervisor’s Office and Ranger District Office

30,629 sq ft

Page 3: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

New Supervisor’s Office and Ranger District Office

25, 203 sq ft

Page 4: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Old Warehouse/Shop

12,840 sq ft

Page 5: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

New Warehouse/Shop

10,132 sq ft

Page 6: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Lease Statistics

• $ 21 per square ft lease price awarded, for a total of $742,000 per year

• 15 year lease with a five year renewable option.

Page 7: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Challenging Items:

• Creative Press reports

• General Contractor Safety, schedule, & quality issues

• Telecommunications

Page 8: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Press Reports• It was reported that

the Forest Service chose to leave it’s current office lease of $404,000 to move into a new office and pay $742,000

• The press indicated the current building owner offered a better deal than $742,000

Page 9: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Facts Omitted by the Local Press:

• The $404,000 lease price was last awarded in 1982. Lease costs rose with each extension and were currently well over $750,000 per year.

• The government is at the end of its lease extensions and a new solicitation is required for best price competitiveness.

• The government received five offers and selected the best value based on price, location, and conformance with the solicitation.

• The old building owners’ proposal to offer a cut rate price did not meet the requirements for the building code, energy code, space requirements, or solicitation and could not even be considered.

Page 10: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Schedule, Safety, Quality Issues with the builder.

• Weird Dynamic– Owner: a Business

Man– On site

superintendent: owner’s former son-in-law.

Page 11: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Poor Emphasis on Safety.

• It was a drain on contract administration time to continually explain basic employee safety requirements to the general contractor.

Page 12: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Schedule

• Notice to Proceed delivered November 2006.

• Lease expiration was Oct. 15, 2007

• Eleven month construction contract that began in the winter didn’t allow for any schedule problems. Float in schedule was not available.

• Schedule commitments to the CO were not backed up with accelerations in the construction effort.

Page 13: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Move In Day• No siding

– Consider what it takes to put on siding (just a little noise).

• Boarded up windows due to window delivery problems

• Numerous punch list and quality issues.

• No phone or computer hook-up

Page 14: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Telecommunications Challenge

• Oct. 5th was scheduled telecommunications move date. Movers, phones, computer access, vacating current lease, and public opening pivoted around the Oct. 5th date.

• Sept. 21st, we received notice from the Facilities Move Strike Team that Qwest would not be able to connect phone and data until Oct. 22nd.

Page 15: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Results of Telecomm Challenge

• Planned telecomm move dates of cut service on Friday Oct. 5th and resume service and open for business on Tuesday Oct. 9th turned into partial telecomm service available Oct. 24th, 9 days after the current lease expiration.

• Strike Team departed with phone and data only 75% connected.

Page 16: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Telecommunciations

Page 17: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Good News

• Moved from 43,469 sf to 35,335 sf leased space

• Made an 8,134 sf reduction in square footage or 19%

• At $21 per sf, made a $170,814 reduction in lease cost per year, $3.4 million over the terms of the lease.

Page 18: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

How did we do it?

• Each employee gets a 9’x 9’ (81 sf) modular work area

• Staff gets a 10’x12’ office

• Forest Supervisor and District Ranger have a 150 sf office. Forest Supervisor down from 266 sf office.

Page 19: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

Modular Work Stations

• Each employee gets a 9’x 9’ (81 sf) modular work area

• We used HON furniture company.

• Total price for the modular furniture contract was $ 214,000

Page 20: New Supervisor’s Office and Ranger District Building Some interesting things that can happen when initiating a build-to-suit lease Mike Shoup 2007

More Good News• Combined the Forest

Supervisors Office with a Ranger District Office and the Interagency Fire Dispatch Center.

• Energy efficiency is in the top 25% for buildings in its class

• Eventually, everything was completed and the building became a big improvement over the old building