new town heights dlf – kakkanad work progress report for the month of may 2011 click to...

16
NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..

Upload: meagan-dwyer

Post on 14-Dec-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

NEW TOWN HEIGHTS DLF – KAKKANADWORK PROGRESS REPORT FOR THE MONTH OF MAY 2011

Click to proceed……..

Page 2: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Dear Sir,

We are glad to inform you that the construction activities are in full swing at New Town Heights DLF – Kakkanad, in all the launched towers. Please find below the Tower wise progress report.

Tower 6 / Block N• 17th floor slab shuttering work in Progress.• Block work progressing on the 10th floor.• Ceiling plastering progressing on the 5th floor.

Tower 6 / Block P • 17th to 18th floor slab column raising in progress.• Block work in progress on the 11th floor.• Ceiling plastering progressing on the 3rd floor

Tower 6 / Block Q • 18th floor slab casting in progress.• Block work in progress on the 11th floor.• Ceiling plastering progressing on the 5th floor.

Tower 5 / Block K• 16th floor slab shuttering in progress.• Block work in progress on the 6th floor.• Ceiling plastering progressing on the 9th floor.

Tower 5 / Block L • 15th floor slab casting in progress.• Block work in progress on the 7th floor.• Ceiling plastering in progress on the 9th floor.

Tower 5 / Block M • 15th floor slab shuttering in progress.• Block work in progress on the 7th floor.• Ceiling plastering progressing on the 8th floor.

Page 3: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Tower 4 / Block H•Ground to 1st floor column raising in progress.

Tower 4 / Block J• 2nd floor slab shuttering work in progress.

Tower 3 / Block G• 16th floor slab shuttering work in progress.• Block work progressing on the 3rd floor.• Ceiling Plastering in progress on the 3rd floor.

Tower 2a / Block D • 9th to 10th floor column raising in progress.• Block work in progress on the 3rd floor.• Ceiling plastering work in progress on the ground floor.

Tower 2b / Block E • 6th to 7th floor column raising in progress.• Block work in progress on the ground floor.• Ceiling plastering in progress on the 2nd level podium floor.

Tower 2b / Block F• 7th floor slab shuttering in progress.• Block work in progress on the 2nd floor.• Ceiling plastering in progress on the 1st floor.

Page 4: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Tower 1 / Block A • 16th floor slab casting completed.• Block work progressing on the 8th floor.• Ceiling Plastering in progress on the 7th floor.

Tower 1 / Block B• 18th floor slab casting completed.• Block work progressing on the 10th floor.• Ceiling plastering work in progress on the 8th floor.

Tower 1 / Block C• 12th to 13th floor column raising in progress.• Block work progressing on the 5th floor.

We are also attaching the site progress photographs along with this.

Page 5: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

TOWER 6

Block work 10th floor in Progress. Ceiling Plastering 5th Floor

in Progress.

Block work 11th floor in Progress. Ceiling Plastering

3rd floor in Progress

Block work 11th floor in Progress. Ceiling Plastering

5th floor in Progress

Block –Q 18th Floor Slab Reinforcement work in Progress

Block –P 17th to 18th floor Column Raising in Progress

Block –N17th Floor Slab Shuttering in Progress

Page 6: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Tower 5Block –K, 16th floor slab Shuttering & Reinforcement work in Progress

Block –L,15th Floor slab reinforcement work is in Progress

Block work 7th floor in Progress. Ceiling

Plastering 9th floor in Progress

Block work 6th floor in Progress. Ceiling Plastering 9th floor

in Progress

Block work 7th floor in Progress. Ceiling Plastering 8th floor in

Progress

Block –M 15th Floor Slab Shuttering work in Progress

Page 7: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

TOWER -4 (Block H)

Block –HGround floor to 4th floor Column Raising in Progress

Page 8: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

TOWER 4-(Block J)Block –J2nd floor Slab Shuttering work in Progress

Page 9: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

TOWER-3 (Block G)

Block work 3rd floor is in Progress & Ceiling Plastering 3rd Floor in Progress

Block G16th floor slab shuttering work in Progress

Page 10: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Tower -2a(Block D)

Block work 3rd floor is in Progress & Ceiling Plastering Ground Floor in Progress

Block –D9th to 10th floor Column Raising in Progress

Page 11: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Tower -2b(Block E)Block –E6th to 7th floor Column Raising in Progress.

Block work Ground floor is in Progress & Ceiling Plastering 2nd level podium Floor in Progress

Page 12: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Tower -2b(Block F)Block –F7th Floor Slab Shuttering work in Progress

Block work 2nd floor is in Progress & Ceiling Plastering 1st Floor in Progress

Page 13: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

TOWER 1Block –C12th to 13th Floor column raising in progress

Block –B18th Floor Slab casting completed.

Block –A16th floor slab casting completed

Block work 8th floor in Progress. Ceiling

Plastering 7th Floor In Progress

Block work 10th floor in Progress. Ceiling Plastering

8th Floor In Progress

Block work 5th Floor in

Progress

Page 14: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

Block –Q 1st level podium Slab Completed

Block –E & FPodium Pile cap work completed & column raising is in Progress

Page 15: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

MARKETING OFFICE -MODEL FLAT

Signature Tower Model Flat Partition Wall & False Ceiling Work in Progress

Tower 2 Model Flat Partition Wall & False ceiling Work in Progress

Page 16: NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……

THANK YOU