New Vertical DatumImplementation Plan
FGDCSilver Spring, MD.
July 30, 2013
Mark C. EcklMark C. EcklChief of the Observation and Analysis Division,Chief of the Observation and Analysis Division,
National Geodetic SurveyNational Geodetic Survey
Implementation Plan – 2.2 ReplaceNAVD 88
Objective: By 2022, reduce all definitional and access related errors in orthometric heights in the geopotential reference frame to 2 centimeters when using 15 minutes of GNSS data.
How completion/success is defined
1. All datasheets express heights and velocities in the new vertical datum
2. A Federal Register Notice has been posted noting that the results of this project represent the
official U.S. vertical datum
3. . NGS authors publish a few papers - including the official datum definition - in trade
magazines, journals, etc.
4. Adoption by FGDC/FGCS
Strategies and actions for moving towards achieving this objective
Strategy 1: GeodesyStrategy 2: Geodetic SurveyingStrategy 3: Product Dissemination Strategy 4: Policy Recommendations
Strategy 1: Geodesy
Action Est. Completion date Responsible Person
Compute final geoid 1.5 yr. prior to release Dan Roman
Compute a geometric fiducial ref. frame (CORS)
1.5 yr. prior to release Joe Evjens
Complete a national geometric control adjustment
6 mo. prior to release Michael Dennis
Evaluate national level line adjustment Oct. 31, 2014 Jarir Saleh
National readjustment of level lines 6 mo. prior to release Jarir Saleh
Enable translations between surfaces at release
Strategy 2: Geodetic Surveying
Action Est. Completion date Responsible Person
Develop best practices for ellipsoid ht. 3 yr. prior to release Michael Dennis
Establish absolute / relative standards 2 yr. prior to release VRSWG
Establish specifications for standards 1 yr. prior to release VRSWG
Develop best practices for leveling 2 yr. prior to release Mark Eckl
Strategy 3: Product Dissemination
Action Est. Completion date Responsible Person
Determine data reporting products 2 yr. prior to release OAD Records Management Branch (RMB) Chief
Develop QA/QC procedures 1.5 yr. prior to release
OAD Project Analysis Branch (PAB) Chief
Develop data transmittal format/methodology
1.5 yr. prior to release
RMB/PAB Chiefs
Strategy 4: Policy Recommendations
Action Est. Completion date Responsible Person
Set target release date for new datum Oct. 31, 2013 Mark Eckl
Define objective Oct. 31, 2013 Mark Eckl
Vertical ref. surface updates 6 mo. prior to release ESC
Vertical ref. surface replacement 6 mo. prior to release ESC
Approval of new datum from FGCS 2 yr. prior to release Mark Eckl
Control ellipsoid ht. replacement 6 mo. prior to release ESC
Adopt vertical reference surface 1 yr. prior to release ESC
Adopt ellipsoid reference surface 1 yr. prior to release ESC
Released Data
Processing
Partially Complete
Planned
GRAV-D Block Status and Released Data
as of July 30th, 2013www.ngs.noaa.gov/GRAV-D