MARCH 2021 / ISSUE - 3 NEWS LETTER
Shri Ajay Seth, IAS
Managing Director
Bangalore Metro Rail Corporation Limited
Shri Durga Shanker Mishra, IAS
Chairman, Bangalore Metro Rail Corporation Limited &
Secretary, Ministry of Housing & Urban Affairs
Government of India
1
S M T P A D M A H E M AN TH W A S TH E C H I E F G U E S T A T C OR P OR A TE O F F I CE O F B MR C L . S H E I S T H E S E N I OR
F A C U L TY O F M / S U N I Q U E C O N S U L T AN T S , B E N G A L U R U & K I T H U R R AN I C H E N N AM M A A W AR D E E W H O
I N T E R A CT E D W I TH TH E W O M E N E M P L OY E E S A N D S P O K E AB O U T TH E W O R K L I F E B AL A N CE .
S H R I A J A Y S E TH , M AN A G I N G D I R E C T O R , L I G H TE D TH E L A M P A N D A D D R E S S E D TH E W O M E N E M PL OY E E S
O N T H E O CC A S I O N , S H R I N .M . D H OK E , D I R E C T OR ( RS E , O &M ) A N D S H R I D . R . K .R E DD Y , D IRE CTOR
( P & P ) , P A R T I C I P A T E D I N TH E CE L E BR A T I O N S .
S M T K A V I T H A A R U N W A S TH E C H I E F G U E S T A T O & M W I N G O F B M R C L A T B A I Y A P P AN A H AL L I . S H E I S
T H E W E L L K N O W N Y OG A T H E R A P I S T A N D S P O K E A BO U T TH E BE N E F I T S O F Y O G A AN D M E D I T A T I O N .
S H R I A . S . S H A N K AR , E X E C U T I V E D I R E C TO R ( O & M ) , A D D R E S S E D T H E W OM E N E M PL O Y E E S O N TH E
O C C A S I ON , S H R I B . S . P A TR I , G E N E R A L M A N A G E R ( H R ) , S H R I N . P . S H AR M A , P R I N C I P A L ( T R A I N I N G
I N S T I T U T E ) & C G M ( C I V I L ) P AR T I C I P A TE D I N T H E CE L E BR A T I O N S .
Land Acquisition Status for the month of February, 2021 of Phase-2, ORR -2A & Airport -2B
Sl. No Reaches
No. of properties
Required
No. of properties
Acquired
[As per 28(4) & 3(1)]
Handed over to Eng.
Section up to
February - 2021
Balance to be Handed
over to Engg. Section
Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total
1
Reach-1 Extn 38 585 623 38 572 610 38 521 559 0 64 64
Forest Land 21 0 21 21 0 21 21 0 21 0 0 0
2
Reach-2 Extn
Station & Viaduct 25 99 124 25 99 124 25 99 124 0 0 0
Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0
3 Reach-3C Extn 3 111 114 3 111 114 3 105 108 0 6 6
4
Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0
Anjanapura Depot 1 20 21 1 20 21 1 20 21 0 0 0
5
Reach-5 New Line 46 800 846 46 800 846 46 800 846 0 0 0
Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0
6
Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0
Reach - 6 (UG) 46 292 338 46 288 334 45 281 326 1 11 12
Kothnur Depot 4 57 61 4 57 61 4 57 61 0 0 0
Total 241 2561 2802 241 2544 2785 240 2480 2720 1 81 82
7 ORR Line 22 46 68 22 46 68 22 46 68 0 0 0
8 Airport Line 60 189 249 60 179 239 51 139 190 9 50 59
9 Shettigere Depot 1 0 1 1 0 1 0 0 0 0 0 1 (Part)
Total 61 189 250 61 179 240 51 139 190 9 50
Grand Total 241 2750 3052 302 2723 3025 291 2619 2910 10 131 82
2
Operational efficiency achieved in the month (Percentage) : 99.98
Ridership for the month in Numbers : 43,39,856
Revenue earned during the month (Amount) : ₹ 10,71,16,816/-
Highest Ridership for the Month on 22.02.2021 (Numbers) : 1,78,736
Highest Revenue collection for the month on 08.02.2021 : ₹ 51,22,469/-
As of now only Smart Cards are Sold and no Smart Tokens & Group Ticket are sold.
3
R EA CH - 6- ELEV ( KA LEN AG R AH AR A T O SW A G AT H CR O SS R O A D)
R EA CH - 5- P-3 ( B O MM ANA HA LLI T O R V R O A D)
R EA CH - 5- P-2 ( H O SA R O A D T O B O M MA NA HA LLI)
R EA CH - 5- P1 ( B O MMA SA NDRA T O H O SA R O A D)
R EA CH - 4B ( Y ELA CHENA HA LLI CR O SS T O SILK IN ST IT U TE)
R EA CH - 3C ( H ESSA R AG HA TT A CR O SS T O B A N G A LO R E IN T ER NAT ION AL EXH IB IT ION
CEN T ER )
R EA CH - 2B ( PA T TA NA G ER E T O CH ELLA G HA TT A DEPO T )
R EA CH - 2A ( M Y SURU R O A D T O PA T TA NA G ERE)
R EA CH - 1B ( V ISVESVA R AY A IN DU STR IA L A R EA T O W H IT EFIELD)
R EA CH - 1A ( B A IY APPA NA HA LLI T O V ISVESVA R AY A IN DU ST R IA L A R EA )
37
41
88
74
96
69
94
96
98
84
C IVIL W ORK I N PROGRESS I N PERCENTAGE
Phase– 2 Progress Photos at a glance
R-1B: Whitefield Station E&E (Left Hand Side)
Concourse slab
R-2A: Jnanabharathi Station Track Level Work R-2B: View of Challaghatta Station Pier arms from P3-P5
R-3C: BIEC Station Pier work in progress from
Ground Level-l to Concourse Level
R-4B: Portal Beam at Pier 331-Reinforcement in progress
R-1A: Mahadevpura Station Roof Portal Erection
4
Phase– 2 Progress Photos at a glance
R-5-P2: Muneshwaranagar Station: Truss erection
work in progress
R-6-Ele: Viaduct – Portal Beam work in progress
5
R-5-P1: Electronic City -2 Station Adjacent span
I-Girder Erection
R-5-P3: Grid A-B Double Tee erection completed
at Ragigudda Station
R-6-UG-RT1: Cutter Head Lowering at Rashtriya
Military School Shaft
R-6-UG-RT1: Aerial View – Rashtriya Military School
Shaft at Vellara Launching Shaft
Phase– 2 Progress Photos at a glance
Secant Pile Cage lowering works at Tannery Road Station
North Bound Tunnel View (Urja TBM) Birds eye view Cantonment Station
TBM-2 (Lavi) 2 No’s of Temporary Rings Erected Shivajinagar Station: Aerial View of works in progress
TBMs - TUNGA & BHADRA at HK Factory Chennai
6
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS Sl
No RT-01 Progress Details as on 28.02.2021— Package-1
1 Contractor & Alignment of
RT-1
M/s Afcons Infrastructure Limited. 3.655 Kms, between South Ramp to Rashtriya Military
School, 3 Nos of UG Stations (i.e. Dairy Circle, MICO Industries & Langford Town)
2 Station Works Progress
South Ramp:
Excavation work completed at Launching shaft 8780 Cum / 8780 Cum and work is in progress at
Cut & Cover portion 18328 Cum/26000 Cum (70% Completed). Base Slab PCC work at Cut and
Cover portion work is in progress 1391Sqm / 4155 Sqm (33% Completed).
TBM 1 (Up Line)
Backup Gantry lowering work is in progress.
Cradle lowering completed.
TBM 2 (Down Line)
Preparatory works for Eye seal erection work is in progress.
Dairy Circle Station:
Secant Pile Construction work is in progress 534 Nos completed out of 794 Nos (67% work
completed).
Road diversion work is in progress at east side.
Lakkasandra Station:
Secant Pile Construction work is in Progress 519 Nos / 794 Nos (65% completed).
Utility diversion work is in progress (78% completed).
Road diversion work is in progress at east side (52% completed).
Drain construction work is in progress 416 Rm / 468 Rm (90% completed).
Langford Station:
Secant Pile construction work is in progress 14 Nos/155 Nos (9%Completed).
900mm dia water pipe line shifting work is in progress.
Work area barricading/high fencing 75% completed.
Rashtriya Military School (Vellara Launching Shaft):
Temporary base slab casting completed 531 Sqm / 531 Sqm.
5th level excavation completed 9740Cum / 9740Cum.
5th level strut and waler erection completed.
TBM 3 (Up Line):
Front, middle & tail shield erection completed. Backup Gantry lowering work completed.
Backup Gantry lowering work is in progress.
7
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Sl No RT-01 Progress Details as on 28.02.2021—Package –1
3 Station & Casting Yard
Works in Progress
Casting Yard (Baiyappanahalli):
Casting of Permanent Tunnel Rings (segments) in progress 689 Nos / 3822 Nos
(18% completed).
Casting of Temporary Tunnel Rings (segments) in progress 22 Nos / 24 Nos
(92% completed).
Drain construction work is completed.
Segment production yard shed completed.
Stacking yard works area completed.
Internal road work is in progress.
QC lab and other site establishments completed .
Sl
No RT-02 Progress Details as on 28.02.2021—Package –2
1 Contractor & Alignment of
RT-02
M/s Larson & Toubro Ltd. 2.762 Kms, between Rashtriya Military School to Shivajinagar,
3 Nos of UG Stations (i.e. Rashtriya Military School, M G Road & Shivajinagar)
2 Station Works Progress
Rashtriya Military School Station:
89.62% of the secant piles for station box and 100% of the piles for entry exit have been
completed. 17530.02 Cum (15.12%) of excavation for the station box has been completed.
13.14% of Base slab casting works are completed. 7.40% of Station wall casting from Base slab
to concourse completed.
M G Road Station:
Secant piles for station box are completed and 60.60% of the piles for entry exit have been
completed. 85784.33 Cum (88.27%) of excavation for the station has been completed. 13.09% of
Base slab casting works are completed.
Shivajinagar Station:
Secant piles for station box are completed and 47.25% of the piles for entry exit have been
completed. 121573.64 Cum (88.96%) Excavation works has been completed.
26.4% of Base slab works are completed. 9.58% of station wall casting from Base slab to
concourse is completed.
3 Tunnel Works Progress
TBM 1: AVNI -(Tunnel Boring Starts at Shivajinagar & Ends at Rashtriya Military School)
Total of 224 Permanent Rings erection completed.
Total of 29 Hyperbaric interventions completed and disc replaced.
Secondary grouting completed up to Ring 214.
TBM 2: LAVI-(Tunnel Boring Starts at Shivajinagar & Ends at Rashtriya Military School)
2 temporary rings erection completed.
Ready for Tunnelling.
8
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Sl
No RT-03 Progress Details as on 28.02.2021—Package-3
1 Contractor & Alignment of
RT-3
M/s Larson & Toubro Ltd. 2.884 Kms, between Shivajinagar to Tannery Road Station, 2 Nos
of UG Stations (i.e. Cantonment & Pottery Town)
2 TBM Works Progress
Urja TBM (TBM No. 01):
North Bound Tunnelling from Cantonment Station to Shivajinagar commenced from 14.08.2020 and
completed so far 328 Rmt (219 Rings) out of 864 Rmt (576 rings).
Vindhya TBM (TBM No-2): South Bound Tunnelling from Cantonment Station & Shivajinagar
commenced from 01.10.2020 and completed so far 279 Rmt (186 Rings) out of 864 Rmt (576 rings).
3 Station Works Progress
Cantonment Station:
Hard Rock Excavation using Controlled blasting technique is in progress. 59.61% i.e. 96,572 Cum of
excavation is completed out of 1,62,000 Cum. 1948 Sqm (25.6%) of PCC has been carried out of the
total scope of 7,957 Sqm. Base Slab Concreting of 763 (9.6%) Sqm has been completed out of total
7957 Sqm.
Pottery Town Station:
Excavation for station box construction is in progress and 1,18,320 Cum (68.4%) of excavation
completed out of 1,72,889 Cum. Fabrication & Installation of 3rd & 4th layer struts and waler beams
are in progress. 361 Sqm. (25.6%) of PCC has been carried out of the total scope of 9362 Sqm.
4 Peenya Casting Yard Casting of 1011 Nos (31.16%) of Precast Tunnel Segments has been completed so far out of total
scope of 3244 Nos.
Sl
No RT-04 Progress Details as on 28.02.2021—Package– 4
1 Contractor & Alignment of
RT-4
M/s ITD Cementation India Limited. 4.591 Kms, between South of Tannery Road Station to
North Ramp, 4 Nos of UG Stations (i.e. Tannery Road, Venkateshpura, Kadugondanahalli &
Nagawara)
2 Station Works Progress
Tannery Road Station:
Guide wall: 411 m out of 522 m is completed. Secant Pile: 513 nos. out of 742 nos are completed.
Venkateshpura Station:
Temporary Retaining wall: 401 m out of 520 m is completed. Excavation: 34,144 Cum out of
1,20,000 Cum is completed.
Kadugondanahalli Station:
Barricading Works: 650 m out of 770 m is completed. Guide Wall: 352 m out of 540 m is
completed. Secant Pile: 140 Nos out of 610 nos are completed.
Cut & Cover-1: Barricading Works: 400 m out of 643 m completed. Guide Wall construction work
commenced on 27.01.2021.
Nagawara Station: Barricading Works: 590 m out 610 m is completed.
3 Casting Yard Casting of Rings for Tunnel Lining: 485 nos out of 4834 nos is completed.
UNDERGROUND WORKS - REACH 6
9
Track Works at a Glance
Contractor - M/s Texmaco Rail & Engineering Limited
Sl
No
Progress of the Month of February 2021
Item Description Unit Track Plinth Casting Flash Butt Welding in numbers
Sections Track
Meters
Reach 4
Reach 2
Reach-1 Reach-5
Reach 4
Reach 2
Reach-1 Reach-5
1 Scope of Work Trm 12580 17628 30500 36000 12580 17628 30500 36000
2 Progress for the month Trm Nil 855 2174 Nil Nil Nil 4500 4600
3 Cumulative progress Trm 11700 15028 2497 Nil 11700
(1233 Nos)
14900
(1512 Nos)
22150
(2380 Nos)
5950
(570 Nos)
4 Access Handed over Trm 11700 15100 7500 Nil 11700 15100 22000 5073
Check Rail Installation at Reach 02 Extension Flash Butt Welding work in progress at Reach-05 Extension
Track Plinth work is in progress at Reach-01 Extension
10
Flash Butt Welding work is in progress at Reach-01 Extension