nme tal e n linka g n fact sheet summer 2021
TRANSCRIPT
PURPOSE AND NEED
Enhance opportunities within the Las Vegas Valley for economic development
Improve access to activity centers within the Las Vegas Valley
Facilitate e�cient mobility for emergency access, evacuation, & national defense
The purpose and need will continue to be re�ned as we receive input from the public, agencies, and other stakeholders.
The purpose of the I-11 Corridor within the Las Vegas Metropolitan Area is to:
Support improved regional mobility for people & freight by reducing congestion and improving travel e�ciency
Provide the link through the Las Vegas Valley for a continuous I-11 that connects major metropolitan areas & markets in the Intermountain West Corridor with Mexico & Canada
Provide a high-capacity, access-controlled transportation corridor
The Interstate 11 (I-11) Corridor is envisioned as a new major north-south multimodal corridor that will provide enhanced transportation mobility and goods movement while creating a foundation for robust economic vitality for the region. The Nevada Department of Transportation (NDOT), in cooperation with the Federal Highway Administration (FHWA), have determined that an I-11 Planning and Environmental Linkages (PEL) Study is the most appropriate approach in identifying a recommended
corridor, building upon data from the previous Tier 1 EIS. A thorough review and evaluation of initial corridor alternatives has identi�ed a western and a central corridor alternative to be advanced for further study. An eastern corridor alternative will no longer be considered for further analysis in the PEL study. The result of the PEL process will select an I-11 corridor through the Las Vegas Metropolitan Area, between the Arizona border on US 93 and the vicinity of Kyle Canyon Road on US 95.
I-11 LAS VEGAS METROPOLITAN AREA PEL STUDY
FACT SHEET SUMMER 2021
PROJECT TIMELINE
Ongoing Stakeholder Engagement
MayFinal PEL Report &
Selection ofI-11 Corridor
2021 2022
Mar – AprIn-Person
PublicHearings
MarchDraft
PEL Report
Sept – FebStakeholder
Meetings(In Person)
SeptemberTelephoneTown Hall
Aug – SeptOnline &
In-Person Public Information
Meetings
JuneStakeholder
Meetings (Virtual)
MayAlternatives
Development Report
JanuaryTransition
from Tier 1 EISto PEL Study
PLAN
NIN
G&
ENVIRONMENTAL LINKAGES
STUDY
LAS VEGAS METROPOLITAN AREA
STAY UPDATED!
ENVIRONMENTAL PROCESS
COMMUNITY OUTREACH
For federally funded projects, a PEL study lays the groundwork for the future studies that may be used during the NEPA process. The PEL study develops the project purpose and need, de�nes the important issues, identi�es critical environmental concerns, and recommends corridor alternatives to be further evaluated in the NEPA process. Through coordination with local, regional, state, and federal partners, including regulatory agencies and public stakeholders, the PEL recognizes potential risks of impacts related to the identi�ed corridor alternatives.
The PEL process also ensures:
• Reasonable transportation corridor alternativesare considered
• Community input and involvement play a key role
• Environmental and community e�ects are disclosed
During the PEL process there are ongoing opportunities for engagement with key public comment periods identi�ed below:
Public Involvement is a critical component to a successful PEL process. There are numerous opportunities for public participation from in-person, virtual, and online public meetings to a telephone town hall and ongoing engagement throughout the project in the best interest of stakeholders and the overall community.
NDOT is committed to providing transparent and timely public involvement. Please visit the project website to sign-up for noti�cations and for information on upcoming engagement opportunities.
Website: i11nv.com
Email: [email protected]
Hotline: (702) 472-8018
PUBLIC AND AGENCY SCOPING
ALTERNATIVES DEVELOPMENT
PREPARE DRAFT PEL STUDY
PUBLIC REVIEW OF DRAFT PEL STUDY/PUBLIC HEARING
RESPONSE TO COMMENTS ON DRAFT PEL STUDY
PREPARE FINAL PEL STUDY AND DECISION DOCUMENT
ONGOING REGIONAL
STAKEHOLDER ENGAGEMENT
WILL OCCUR THROUGHOUT
THE STUDY
PUBLIC MEETINGS/HEARINGS& KEY COMMENT PERIODS
I-11 LAS VEGAS METROPOLITAN AREA PEL
WE ARE HERE
PLAN
NIN
G&
ENVIRONMENTAL LINKAGES
STUDY
LAS VEGAS METROPOLITAN AREA
SpringValley
Paradise
NorthLas Vegas
Las Vegas
Henderson
BoulderBasin
604
146
564
166
167
147
582
215
215
159
159
593
595
15
15
515
515
215
95 95
93
Corridor AlternativesRecommended to Advance to Complete PEL
Western AlternativeWestern Alternative(Sheep Mountain option)Western Alternative(Centennial Bowl option)Central Alternative
Las Vegas Metropolitan Area