no slide title– identify injection and production streams – oil, water, co2 – identify yearly...

43
Wyoming EOR / IOR Conference – Jackson, Wyoming September 15, 2008 Presented by: Craig Walters CO2-EOR Projects Key Considerations of Design, Implementation and Operation

Upload: others

Post on 18-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

Wyoming EOR / IOR Conference – Jackson, Wyoming September 15, 2008Presented by: Craig Walters

CO2-EOR Projects Key Considerations of Design, Implementation and Operation

Page 2: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

2

Multiple Project Types and Locations– Miscible Hydrocarbon – Algeria, Alaska– Miscible CO2 – Texas, Oklahoma, Wyoming

EOR Capabilities– Analytical tools and process– Geologic reservoir characterization– Fluid behavior studies & equation of state (EOS) development– Compositional reservoir simulation– Development planning– Operations experience– Commercial focus

– Experienced Technical and Operations Personnel

Anadarko – Gas Injection Experience

Page 3: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

3

Fields– Monell– Salt Creek– Sussex

Pipelines– 33 mile, 8”– 125 mile, 16”

CO2 Supply– XOM Shute

Creek

Anadarko’s Wyoming CO2-EOR Assets

Salt Creek

Monell

Sussex

16”

8”

Page 4: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

4

Salt Creek & Monell EOR Performance

0

2,000

4,000

6,000

8,000

10,000

12,000

Sep-2003 Sep-2004 Sep-2005 Sep-2006 Sep-2007 Sep-2008

Gro

ss O

il P

rodu

ctio

n (B

OP

D)

0

50

100

150

200

250

300

350

400

Tota

l CO

2 In

ject

ion

(MM

CFD

)

Monell, BOPDSalt Creek, BOPDTotal CO2 Injection, MMCFD

Salt Creek

Monell

September 200810,175 BOPD382 MMCFD CO2 Inj

Page 5: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

5

CO2-EOR: Going from Concept to Reality

Idea

Screening

Project Design

Approval

Implementation

Operation & Surveillance

RED DENOTES A “KEY CONSIDERATION”

Page 6: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

6

Idea – “I have an oil field…”

Strong oil prices– Drives up equipment & service costs during implementation– Delayed production response – ?? years after 1st injection– Timing can be critical

Everyone’s talking about CO2 flooding– How many of them know HOW to do it?– How many of them ARE doing it?

Sounds easy – just inject CO2 into my old waterflood

– It is NOT easy!!

Page 7: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

7

Screening

Page 8: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

8

Screening CO2-EOR Flood Candidates

Focus on the Basics– CO2 Source, Transmission and Cost– Basic Field, Reservoir, Rock and Fluid Properties– Miscible Process (Immiscible OK, but lower RF)– Analogs / Rules of Thumb– Field / Site Specific Analyses– Scoping Economics

Don’t Overlook the Obvious– CO2 supply to the field– Focus on fields that were successful waterfloods– CO2 will NOT overcome geology– Target the big fields first

• Big fields can support CO2 pipeline infrastructure expansion• Scarce human resources with the necessary skill sets

Page 9: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

9

Screening CO2-EOR (cont)

CO2 Source– Type – natural or anthropogenic– Quality – contaminants impact MMP– Quantity – adequate and consistent for the life of project

CO2 Transmission– Distance to source or existing

pipeline infrastructure– Existing infrastructure utilization

Is there capacity?

CO2 Cost– Supplier and transporter will want to cover costs and ROI– Expect CO2 cost to be tied to oil price – be mindful of

project timing

Page 10: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

10

Screening CO2-EOR (cont)

General Field Data– History: discovery, waterflood, other– Current daily gross production– Current well count: active, inactive (by

type if possible)

Reservoir Data– Reservoir name– Lithology & facies type– Depth, feet– Field area, acres– Geologic maps – structure, isopach,

volumes– Average gross and net pay with net-to-

gross ratio, feet– Fluid contact depths – gas/oil, oil/water– Well spacing, acres– Waterflood pattern configuration and

spacing, acres– BH Temperature, deg F– Initial and current BH pressure, psi– Frac gradient / pressure, psi– Expected BH CO2 flood operating

pressure, psi

Rock and Fluid Properties– Porosity, %– Permeability, md– Dykstra-Parsons coefficient– Saturations: Swi, Sorw– Oil gravity and type, deg API– Initial and current oil FVF, rb/stb– MMP, psi– CO2 FVF at operating conditions, rb/mcf– Relative permeability curves if available

OOIP and Production– OOIP, MMSTB– Primary production and RF, MMSTB and

% OOIP– Secondary production and RF– Total P+S and RF– S/P ratio

Key Considerations– Current reservoir pressure compared

to expected BH operating pressure– “Floodable” OOIP (NOT thin, edgy,

poor quality)

What data do I need to pull together? (List NOT exhaustive)

Page 11: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

11

Screening CO2-EOR (cont)

Miscible Process? (Immiscible OK, but lower RF)– Correlations based on reservoir temp and oil gravity (API)

– Is the reservoir deep enough? MMP < frac gradient

Page 12: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

12

Screening CO2-EOR (cont)

Miscible CO2 Analogs / Rules of Thumb– Other CO2 floods – must be similar reservoir and fluids– Tertiary Recovery Factor = 12% (8-18%)– Tertiary / (Primary + Secondary) = 25% (20-35%)– CO2 will NOT overcome geology

Reservoir Heterogeneities

Faults

Fractures

Genetic UnitBoundaries

PermeabilityZonation

BafflesBedding

Texture & Mineralogy

Weber (1986)

CO2 Flood – $$$ CO2 Flood – ???

Page 13: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

13

Screening CO2-EOR (cont)

Field / Site Specific Analyses– Streamline simulation (single pattern)

• Computer software (CO2 Prophet – Texaco software from early 1990’s)• Screening tool – falls between empirical correlations and numerical simulation• Uses parameters specific to your field – quickly analyze which are key drivers• Define initial CO2 slug size and WAG ratio (example 15% and 1:2)• Beware relative permeability curves and the “mixing” parameter

– Develop “Dimensionless Curves”

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2

HCPVI (CO2 + Water)

CO2 InjWater InjOil ProdWater ProdCO2 ProdCO2 Purch

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40

HCPVI (CO2 + Water)

CO2 InjWater InjOil ProdWater ProdCO2 ProdCO2 Purch

Page 14: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

14

Screening CO2-EOR (cont)

Field Development Scale-up– Map out patterns and development schedule by year

• Timely development with stable CO2 purchase volumes• Achievable activity and capital investment levels

– Identify injection and production streams – oil, water, CO2– Identify yearly capital investments – well work, flow &

injection lines, facilities

Scoping Economics with Sensitivities– Oil price– CO2 purchase price– OPEX – CO2 handling and recompression become

significant, expect double digit lifting cost for life of flood– Does the project make the 1st cut?

Page 15: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

15

Screening CO2-EOR (cont)

Ideas for improved economics– Target areas of high OOIP for early stage development– Increase processing rate – smaller patterns, drier WAG

Processing rate impact on a single pattern

CO2 Injected, MCFDCO2 Purchased, MCFD

CO2 Produced, MCFDWtr Injected, BWIPD

Oil Produced, BOPD

1

10

100

1,000

0 4 8 12 16 20 24 28 32Years

HCPVI/Yr = 10%

21 bopd peak

0 4 8 12 16 20 24 28 32Years

HCPVI/Yr = 8%

17 bopd peak

0 4 8 12 16 20 24 28 32Years

HCPVI/Yr = 5%

11 bopd peak

HCPVI per Yr 10% 8% 5%

Peak BOPD 21

1720%

1150%

Payout, yrs 4.6

6.439%

19.9333%

Life, yrs 2126

24%42

100%

NPV10 31% 92%

Page 16: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

16

Project Design

Page 17: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

17

Project Design

Reservoir Characterization

Fluid Characterization

Operating Parameters

Pilot Design and Implementation

Capital Investment Considerations

Detailed Economics

Page 18: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

18

Project Design (cont)

Reservoir Characterization (Geo-modeling)– Process to quantitatively assign reservoir properties, recognizing

geologic information and uncertainty in spatial variability– Upscaling– Simulation

EngineeringBarriers, production data,

volumetrics, material balance,interference tests, etc.

GeophysicsMajor surfaces, faults,

attributes, etc.

PetrophysicsPorosity, permeability, log-facies, flow zones, Sw, etc.

GeologyConceptual model, surfaces,

facies, sequences, etc.

High ResolutionGeologic Model

Integrated model, flowunits, uncertainty

Page 19: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

19

Project Design (cont)

Fluid Characterization– Use a reputable lab with recent field samples– PVT studies

• Routine oil tests + CO2 solubility, swelling, viscosity, asphaltene

– MMP determination• Rising Bubble Apparatus (RBA)• Slim-tube – generally more accurate than RBA• Need to consider CO2 quality and contaminants over time

– Equation of State• Develop and test

Pressure (psia)

0.70

0.75

0.80

0.85

0.90

0.95

1.00

1000 1100 1200 1300 1400 1500 1600 1700 1800 1900

Frac

tiona

l Rec

over

y

Lab Simulation

Lab MMP Simulation MMP

1423# 1460#

Pressure (psia)

0.70

0.75

0.80

0.85

0.90

0.95

1.00

1000 1100 1200 1300 1400 1500 1600 1700 1800 1900

Frac

tiona

l Rec

over

y

Lab Simulation

Lab MMP Simulation MMP

1423# 1460#

Page 20: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

20

Project Design (cont)

Operating Parameters– Pattern type and size– WAG or continuous injection – water injectivity issues– Optimum slug size – initial and WAG ½ cycle– Recycle CO2 – full stream re-injection or NGL recovery– Operating BHP – consider MMP and frac gradient– Pumping or flowing producers– System pressure requirements – injection and production

Page 21: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

21

Project Design (cont)

Capital Investment Considerations– CO2 source / location / transmission– Current field operations proposed operations– Existing conditions of wells, facilities, etc.– Well work requirements– New facilities – gas handling, NGL recovery, etc.

Detailed Economic Analysis– Sensitivities to oil price, CO2 cost, project delays,

performance variations, OPEX, HCPVI– What are the key drivers and risks?

Page 22: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

22

Project Design (cont)

Pilot Design– What are the critical unknowns – is a pilot necessary?– Pilot design driven by what you need to learn – clearly

define the objectives– Scale appropriately – multiple patterns

Pilot Implementation– CO2 availability – pipeline or truck?– Wellbore utilization – existing or new?– Over-communicate with all team members– Involve regulatory agencies early– Be prepared to capture the pilot data when you need it

Don’t go “poor-boy”

Page 23: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

23

Approval

Page 24: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

24

Approvals

Internal – multi-year project sanctioningPartnersMineral interest owners – unitizationRegulatory agencies – Federal and State

BLM– Project Proposal / Plan of Development – provide detailed

overview of the project to BLM for evaluation if an Environment Assessment (EA) or Environmental Impact Statement (EIS) is required – 3 months

• EA preparation and approval – 6-12 months• EIS preparation and approval – 2-5 years• Right-of-way and sundry requirements – 1-4 months

– Wildlife stipulations – impact operations and scheduling

Page 25: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

25

Approvals (cont)

WOGCC– Approval of injection fluid for Class II wells (CO2, Water,

gas, etc.) – 60 days– Approval of wells for Class II injection (new drill,

reactivation, recompletion), including notification of surface owners within a ½ mile radius – 75 days

– Determine maximum surface injection pressures – 30 days after technical information is gathered (step rate tests, frac gradients, temp/tracer logs)

– Mechanical integrity testing – upon well completion and then every 5 years

WYDEQ– Air Quality Permits (compressors, dehy, tank battery, etc.) –

4-6 months

Page 26: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

26

Implementation

Page 27: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

27

Implementation

Project Execution PlanPlanning and SchedulingContracting and Procurement StrategyFacilitiesNGL Recovery CompressionInfrastructureElectrical SystemWell WorkSurface Control and Measurement

Page 28: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

28

Implementation (cont)

Project Execution Plan– Identifies high level goals and objectives– Defines roles and responsibilities– Identifies manpower requirements – internal and external– States major assumptions and risks to successful execution

Planning and Scheduling– Map the process with all stakeholders – avoid “Uh-Ohs”– Identify work breakdown structure – Include contractors in the scheduling process for

accountability– Key to success – planning, planning and more planning

Page 29: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

29

Implementation (cont)

Contracting and Procurement Strategy– Proper assessment of manpower requirements is critical– Level load contractors to avoid excess mob and demob

• Minimize labor turnover• Increased efficiency with consistent workforce

– Supply chain management – plan for long lead items

Facilities– CO2 is corrosive when wet – operating conditions and

temperatures are key– Fluid composition – CO2, hydrogen sulfide, oxygen, water– Plan for corrosion – materials, metallurgy, dehydration,

chemical inhibition, monitoring– Stainless or carbon steel, fiberglass, polyethylene liners

Page 30: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

30

Implementation (cont)

100

125

150

175

200

225

250

Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08

Cha

nge

In P

rice

Inde

x

Consumer Price Index

#2 Diesel Fuel Price Index

Copper & Copper Products Price Index

Steel Pipe and Tube Price Index

Oil Field Equipment Price Index

Stainless Steel Index

Data Source: U.S. Bureau of Labor Statistics

104%

89%

47%

16%

7%

% Increase

70%

Recent Inflationary Pressures

7%

Page 31: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

31

Implementation (cont)

Page 32: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

32

Implementation (cont)

NGL Recovery from Produced CO2– Full stream re-injection or NGL recovery?– Why? – $ and MMP increases with decreasing CO2 mole %– Increases electrical consumption and compression needs

Compression– Field pressure and volume requirements dictate HP needs– Configure dehydration to minimize stainless steel needs– Electric or gas – fuel gas availability vs. electricity cost– Only need compression to reach “super-critical” conditions –

use lower cost H-pumps to get to higher system pressure– Station design should facilitate future expansion– Cooling capability matched to ambient conditions

Page 33: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

33

Implementation (cont)

Flow and Injection Infrastructure– Optimize for cost efficiency and operational control– Hub & Spoke or Trunk & Lateral– Provide for accurate well testing capability

Electrical System– Load projections– Optimize cost based on voltage purchase rate schedules– Optimize distribution grid

Page 34: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

34

Implementation (cont)

Well Work– Well mechanical integrity critical to maintaining proper

isolation of the target zone– Requires special cement blends, tools, tubulars, kill fluids

Surface Control and Measurement– Evaluate system for pressure drops that could cause

freezing issues due to CO2 expansion – choke placement, slip-stream

– Accurate measurement & well testing is critical – bad data can lead to bad decisions

– Effective allocation methods– Mass flow meters for custody transfer– Other meter types – wedge, V-cone, turbine

Page 35: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

35

Operations & Surveillance

Page 36: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

36

OperationProject Execution Plan

– Details the yardsticks with which to measure performance, and the surveillance program to measure the yardsticks

– “Plan the work, work the plan”BUT be prepared to make changesThe plan is not etched in stone

Operational Issues– Artificial lift – ESP, rod, other– Scaling, corrosion– Well interventions w/ 1.0 psi/ft grad – Temperature issues

• Pressure drops & freezing – slip stream• Difficulty in separation• Recycle compression – “hot” CO2 less

dense, impacts injectivity – heat exchanger– Many others – no 2 floods are the same

Page 37: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

37

Surveillance

Waterflood vs. CO2 flood– Water: plentiful, cheap, favorable mobility– CO2: scarce, expensive, unfavorable mobility– Smaller CO2 RF / oil target leaves less margin for error

Surveillance Program – Vital to Success– Goal is to optimize the performance and value of the project

• Maximize processing rate• Optimize WAG – dry as possible• Maximize sweep efficiency – areal and vertical

– Establish a dedicated surveillance team– Pattern surveillance / analysis

Page 38: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

38

Surveillance (cont)

Surveillance Team– Guides all aspects of flood operations and defines operating

parameters– Engineers, geologists, field foreman, technicians, operators– Frequent communication is critical– Set slug sizes, WAG ratios, schedules, IWR, balances

patterns– Monitors bottom-hole pressure and automation settings– Maintain Pres > MMP & Pinj < frac gradient

• Bottom-hole pressures (dedicated monitoring wells) & step-rate tests

– Evaluates performance and CO2 utilization– Recommends pattern re-configuration, stimulations, infill

drilling

Page 39: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

39

Surveillance (cont)

Pattern Surveillance Data Requirements– Measure and account for all injected and produced fluids and pressures– Average Reservoir Conditions – BH temp and pressure– Formation Volume Factors – Oil, CO2 and water– Reservoir volumes – PV and/or HCPV– Pattern allocation factors – injector centered patterns

• Subjective process: use geometric initially, modifying over time based on streamline simulation or field observation

Pattern Analysis – Plots with both Time and HCPVI on the X-axis• Surface Rate and Pressure Data – typical prod & inj plot• Cumulative HCPVI, CO2 + water• Cumulative HCPVP, CO2 + water + oil + HC gas• Injection / Withdrawal ratio (monthly and cumulative)• Cumulative CO2 Injected, % of HCPV• Cumulative Oil Produced, % of OOIP• Gross and Net CO2 Utilization, MCF / BO (standard conditions)• Gas-Liquids Ratio (GLR), CO2 / (Oil + Water) (standard conditions)

Page 40: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

40

Surveillance (cont)

What to Look For– Actual vs Forecast performance – how are we doing– Pattern maturity and balancing – when to WAG– Maintain injection-withdrawal ratio > 1.0– Processing rate differences – understand why, think about

the parameters involved with HCPV and Q

Goal: Optimize NPV without jeopardizing recovery

Page 41: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

41

Summary

Page 42: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

42

CO2-EOR Projects – Keys to Success

1. Identify the “right” field – can’t change Mother Nature2. Put the time in upfront to avoid headaches later

Visit other CO2 floodsPilot test? If so, define size, scope and objectivesWhere necessary, get early involvement from regulatory agencies

3. Design & implementation – understand the big knobsAccelerate oil responsePhased implementation – continual learning & improvement

4. On-going surveillance is vital5. Right #’s of right people in the right jobs6. Open communication by ALL involved parties7. Planning, planning and more planning8. Maintain commercial focus: Drive for Economic success – not

just technical success

Page 43: No Slide Title– Identify injection and production streams – oil, water, CO2 – Identify yearly capital investments – well work, flow & injection lines, facilities Scoping Economics

43

Thank you!