noble denton global 1200 dp2 fmea

80
14701 St Mary’s Lane, Suite 425 Houston, Texas, USA 77079 281-558-7180, www.nobledenton.com Global Industries Ltd Global 1200 DP2 FMEA Prepared by NOBLE DENTON MARINE, INC. C 02/04/10 Updated to reflect customer comments BA B 07/21/09 Issued for Customer Review BA BH MS A 07/16/09 Issued for Internal Review BA BH MS Rev Date Description By Check Approved Report No. H8675 Distribution: Larry McClure, Global Industries Ltd Internal Job #: 094586

Upload: era-ya

Post on 13-Apr-2015

186 views

Category:

Documents


21 download

TRANSCRIPT

Page 1: Noble Denton Global 1200 Dp2 Fmea

14701 St Mary’s Lane, Suite 425 Houston, Texas, USA 77079

281-558-7180, www.nobledenton.com

Global Industries Ltd

Global 1200 DP2 FMEA

Prepared by

NOBLE DENTON MARINE, INC.

C 02/04/10 Updated to reflect customer

comments BA

B 07/21/09 Issued for Customer Review BA BH MS

A 07/16/09 Issued for Internal Review BA BH MS

Rev Date Description By Check Approved

Report No. H8675 Distribution: Larry McClure, Global Industries Ltd Internal Job #: 094586

Page 2: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 2 of 80 February 4, 2009

Executive Summary

Project

Noble Denton was contracted by Global Industries LTD. to perform and generate a dynamic positioning (DP) failure mode and analysis (FMEA) report. This report is the Pre-trial DP FMEA.

Global 1200

The Global 1200 is a DP Class 2, Derrick pipelay vessel being constructed by Keppel Sing Marine. This 162m long vessel has one 880kW tunnel thruster, five 2400kW retractable azimuth thrusters, and two 4500kW main azimuth thrusters. These thrusters interface with a dual redundant Converteam DPS-21 DP control system with 6 position references. Electric power is provided by three 3760kW and three 4320kW generators that supply a split 6.6kV main switchboard.

Background

DP Class 2 vessels are required by classification society and industry standards to be capable of maintaining position and heading despite any single failure of any active system or component, or of any unprotected passive system or component. Classification societies and many potential clients require this to be proven by an FMEA and test program. Increasingly, annual trials are also expected.

Summary of Analysis Results

The following table shows the important findings for each system group. Single point failures (SPF) are single faults that can cause loss of position or heading. DPO faults could be SPF except for expected intelligent human intervention. Accuracy estimates the accuracy of the information the analysis is based on. More detailed information can be found in each systems summary section.

DP Main

Azimuth DD

Azimuth Tunnel Electric VMS Support Total

SPF 0 0 0 0 0 0 0 0

DPO 4 3 3 1 0 2 0 14

Accuracy Medium Medium Medium Medium Medium Medium Medium Medium

Worst Case Failure

Not yet confirmed. Loss of half 6.6kV switchboard.

Testing

DP FMEA testing has not yet been performed to verify the analysis and information it was based on.

Conclusion The vessel appears to meet ABS & IMO standards for a DP2 vessel, if properly

configured, operated and maintained, but its acceptance is pending successful test & survey.

Page 3: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 3 of 80 February 4, 2009

Recommendations

No information was received that indicated the ESB automatic changeover could be disabled. Recommendation if there is not an auto/manual changeover switch is to install a mechanical interlock in the ESB between the auxiliary switchboard #1 incoming breaker and the auxiliary switchboard #2 incoming breaker to the ESB. This will prevent the auto change over logic from working and in the event of failure the duty engineer can inspect the failed equipment before changing power source to the backup supply.

Page 4: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 4 of 80 February 4, 2009

Table of Contents

1. INTRODUCTION ............................................................................................................................................................ 6

1.1 PURPOSE .................................................................................................................................................................... 6 1.2 METHOD .................................................................................................................................................................... 6 1.3 APPLICABLE STANDARDS .......................................................................................................................................... 7 1.4 LIMITATIONS ............................................................................................................................................................. 8 1.5 REPORT FORMAT ....................................................................................................................................................... 8 1.6 ABBREVIATIONS USED .............................................................................................................................................. 9 1.7 VESSEL OVERVIEW .................................................................................................................................................. 10

2. DP SYSTEM ................................................................................................................................................................... 14

2.1 DP SYSTEM DATA ................................................................................................................................................... 14 2.2 DP SYSTEM DESCRIPTION ....................................................................................................................................... 15 2.3 SUMMARY OF DP SYSTEM ANALYSIS ...................................................................................................................... 22

3. MAIN AZIMUTH THRUSTERS ................................................................................................................................. 24

3.1 AZIMUTH SYSTEM DIAGRAM ................................................................................................................................... 24 3.2 MAIN AZIMUTH SYSTEM DATA ............................................................................................................................... 25 3.3 MAIN AZIMUTH SYSTEM DESCRIPTION ................................................................................................................... 25 3.4 MAIN AZIMUTH SYSTEM FMEA TABLE .................................................................................................................. 28 3.5 SUMMARY OF MAIN AZIMUTH SYSTEM ANALYSIS .................................................................................................. 32

4. DROP DOWN AZIMUTH THRUSTERS ................................................................................................................... 33

4.1 DROP DOWN AZIMUTH SYSTEM DATA .................................................................................................................... 34 4.2 DROP DOWN AZIMUTH SYSTEM DESCRIPTION ........................................................................................................ 34 4.3 DROP DOWN AZIMUTH SYSTEM FMEA TABLE ....................................................................................................... 38 4.4 SUMMARY OF DROP-DOWN AZIMUTH SYSTEM ANALYSIS ...................................................................................... 43

5. BOW TUNNEL THRUSTER........................................................................................................................................ 45

5.1 BOW THRUSTER SYSTEM DATA .............................................................................................................................. 45 5.2 BOW THRUSTER SYSTEM DESCRIPTION ................................................................................................................... 46 5.3 SUMMARY OF BOW THRUSTER ANALYSIS ............................................................................................................... 48

6. ELECTRICAL POWER SYSTEMS ............................................................................................................................ 50

6.1 ELECTRICAL POWER DISTRIBUTION DIAGRAM ........................................................................................................ 50 6.2 ELECTRICAL GENERATOR CONTROL DIAGRAM ....................................................................................................... 51 6.3 ELECTRIC POWER SYSTEM DATA ............................................................................................................................ 52 6.4 ELECTRIC POWER SYSTEM DESCRIPTION ................................................................................................................ 53 6.5 ELECTRIC POWER FMEA TABLE ............................................................................................................................. 60 6.6 SUMMARY OF ELECTRIC POWER SYSTEM ANALYSIS ............................................................................................... 60

7. POWER & VESSEL MANAGEMENT SYSTEM ...................................................................................................... 62

7.1 POWER AND VESSEL MANAGEMENT SYSTEM DIAGRAM ......................................................................................... 62 7.2 POWER AND VESSEL MANAGEMENT SYSTEM DATA ............................................................................................... 62 7.3 POWER & VESSEL MANAGEMENT SYSTEM DESCRIPTION ....................................................................................... 62 7.4 SUMMARY OF POWER & VESSEL MANAGEMENT SYSTEM ANALYSIS ...................................................................... 66

8. AUXILIARY SUPPORT SYSTEMS ............................................................................................................................ 68

8.1 DIESEL FUEL OIL SYSTEM ....................................................................................................................................... 68 8.2 LUBRICATING OIL SYSTEMS .................................................................................................................................... 71 8.3 HYDRAULIC OIL SYSTEMS ....................................................................................................................................... 71

Page 5: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 5 of 80 February 4, 2009

8.4 COOLING WATER SYSTEMS ..................................................................................................................................... 72 8.5 COMPRESSED AIR SYSTEMS .................................................................................................................................... 75 8.6 FIRE PROTECTION SYSTEMS .................................................................................................................................... 76 8.7 EMERGENCY SHUTDOWN SYSTEMS ......................................................................................................................... 77 8.8 HVAC SYSTEMS ..................................................................................................................................................... 78 8.9 COMMUNICATION SYSTEMS .................................................................................................................................... 78

Page 6: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 6 of 80 February 4, 2009

1. INTRODUCTION

1.1 Purpose

1.1.1 Noble Denton was contracted by Global Industries LTD. to perform and generate a dynamic positioning (DP) failure mode and analysis (FMEA) report. This report is the pre-trial DP FMEA.

1.1.2 DP Class 2 vessels are required by classification society and industry standards to be capable of maintaining position and heading despite any single failure of any active system or component, or of any unprotected passive system or component. Classification societies and many potential clients require this to be proven by an FMEA report and FMEA test program.

1.1.3 This report is the initial design review, based on customer provided documentation. Further information will be required to increase the reliability of the analysis.

1.2 Method

1.2.1 DP control systems maintain and correct position and heading by using the vessel’s thrusters to balance the wind, wave and current forces based on its position, heading and environmental sensors. For DP Class 2 operations, a vessel is not allowed to have a single failure that may cause the vessel to lose position or heading due to excessive thrust (drive off), insufficient thrust (drift off) or control errors (large deviations). There must be sufficient generators, main engines, thrusters, power supplies, controllers and reference systems online and redundantly configured for the vessel to remain in position if any item of equipment or section of the power distribution network should fail.

1.2.2 The failure mode and effect analysis verifies these by examining the vessel design and identifying systems whose failure could affect the vessel's station keeping capability. These systems typically include:

DP Control System, Thrusters and Thruster Control Systems, Electrical Power Generation, Distribution and Control Systems, Auxiliary Support Systems – Vessel Management & Alarm Systems

– Fuel Oil Distribution, Purification & Transfer Systems – Lubricating Oil Systems – Hydraulic Oil Systems – Fresh & Salt Water Cooling Systems – Compressed Air & Pneumatic Control Systems – Fire Protection Systems (e.g. CO2) – Emergency Stop Systems – Heating, Ventilation & Cooling Systems – DP Communication Systems

Page 7: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 7 of 80 February 4, 2009

1.2.3 Each of these systems’ control functions or components are examined to identify how they can fail (failure mode) and the effect of each type of failure on the system and on DP positioning keeping capability during DP Class 2 operation (failure effect). The analysis only examines individual failures and assumes that the systems are properly configured for operation in DP class 2, all equipment is available and working correctly (except for the failure mode being examined), and the vessel is operating within its worst case failure environmental limits.

1.2.4 The information for the analysis is based on examination of the documentation provided by the shipyard and vendors. Initially, the analysis is only as accurate and complete as the information provided. After FMEA testing and survey, the FMEA report will be updated to reflect the actual installation and function at the time of survey and testing. Any future changes to the vessel should be evaluated for their effect on DP redundancy and the document updated as necessary.

1.3 Applicable Standards

1.3.1 The vessel keel date is 2005, so the applicable DP class rules are ABS Steel Vessel rules 2005.

1.3.2 American Bureau of Shipping, Steel Vessel Rules, Part 4 Chapter 3 Section 5 15.1.1 Class notations and degree of redundancy:

DPS-2 For vessels which are fitted with a dynamic positioning system which is capable of automatically maintaining the position and heading of the vessel within a specified operating envelope under specified maximum environmental conditions during and following any single fault excluding a loss of compartment or compartments.

1.3.3 American Bureau of Shipping, Steel Vessel Rules, Part 4 Chapter 3 Section 5 15.5.2(a) DPS-2 Power Generation System:

Generators and their distribution systems are to be sized and arranged such that, in the event of any section of bus bar being lost for any reason, sufficient power is to remain available to supply the essential ship service loads, the critical operational loads and to maintain the vessel position within the specified operating envelope under the specified maximum environmental conditions.

Essential services for generators and their prime movers, such as cooling water and fuel oil systems, are to be arranged such that, with any single fault, sufficient power remains available to supply the essential loads and to maintain position within the specified operating envelope under the specified maximum environmental conditions.

1.3.4 I.M.O. MSC/Circ. 645 Section 2.2.2: For equipment Class 2, a loss of position is not to occur in the event of a single fault in any active component or system. Normally static components will not be considered to fail where adequate protection from damage is demonstrated, and reliability is to the satisfaction of the Administration. Single failure criteria include:

1. Any active component or system (generators, thrusters, switchboards, remote controlled valves, etc.).

2. Any normally static components (cables, pipes, manual valves, etc.) which is not properly documented with respect to protection and reliability.

1.3.5 I.M.O. MSC/Circ. 645 Section 3.2.3 For equipment class 2, the power system should be divisible into two or more systems such that in the event of failure of one system at least one other system will remain in operation. The power system may be

Page 8: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 8 of 80 February 4, 2009

run as one system during operation, but should be arranged by bus-tie breakers to separate automatically upon failures which could be transferred from one system to another, including overloading and short-circuits.

1.4 Limitations

1.4.1 The FMEA typically considers the failure of mechanical, electrical and control system hardware. The FMEA does not assess the structure of the vessel (a passive element that is already monitored), the efficiency of the co-ordination of the electrical protection scheme (requires regular testing and evaluation of the effect of system changes), deficiencies in component manufacturing or design, software design or inadequate maintenance. It is assumed that equipment design, system protection settings and maintenance practices are of sufficient standard to inhibit cross migration of any fault current and to efficiently identify losses of redundancy.

1.4.2 The FMEA does not verify the quality of control software. It is also assumed that computer networks have been designed and tested to avoid common problems such as programming errors, program vulnerabilities and broadcast faults.

1.4.3 The findings of the analysis can be invalidated by incorrect or incomplete design information or any modification that could affect the vessel's station keeping capability. Any such modification should be reviewed to evaluate its effects on system redundancy and documented in a revised FMEA.

1.4.4 For Class 2 operations, the ship’s DP operators and engineers must be aware of the consequences of the failure of any single item of equipment, have chosen a redundant configuration and operate the vessel within the worst case failure environmental limits. It is possible to operate fully redundant vessels in a non-redundant manner and the ship’s crew must be careful not to negate redundant systems. The vessel should be operated at all times bearing in mind the thruster capacity after worst-case failure.

1.5 Report Format

1.5.1 An Executive Summary is provided at the beginning of this report to give a convenient overview of the purpose, subject, method, findings and conclusion of the analysis.

1.5.2 The report body begins with an introduction to the project and its terms of reference and an overview of the vessel. This is followed by sections covering the DP control system, the thruster systems, the electric power system, the vessel management system (if it has active DP effects), and the auxiliary support systems. The sections deal with systems that have a direct effect on the dynamic positioning system and the vessel’s ability to maintain a set heading and position. Each section contains a simplified system diagram, a data table that quickly summarizes system information, a description of the systems components and how it operates, failure mode and effect analysis tables and a final subsection summarizing the findings of the system analysis.

Page 9: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 9 of 80 February 4, 2009

1.5.3 The failure mode and effect analysis tables list the possible types of failure (failure modes) for each system and analyze the system effect, operator indication and DP effect of each failure mode. Failure modes with similar effects are lumped together as a general failure mode to make the table less unwieldy. Single point failures are highlighted in red, failure modes that may require DP intervention are high lighted in yellow and assumptions or unknowns are entered in red text for easy identification.

1.5.4 Each section’s final subsection summarizes the analysis results. It discusses significant failure modes (single point failure & DPO intervention), hidden failures that can reduce redundancy and identifies dangerous system configurations that effect system redundancy. It identifies failure modes in other systems that can affect the system, presents the worst case system failure and examines the reliability of the information the analysis was built on. This is all summarized in a final table that lists the number of identified single point failures, failures requiring DPO intervention, maintenance concerns raised by the analysis of hidden faults and rates the reliability of the system information. The information in the executive summary is taken directly from these tables.

1.6 Abbreviations Used

The following abbreviations are used in the document: ABS American Bureau of Shipping

A/C Air Conditioning

BT Bow Tunnel Thruster

AMC Advanced Micro Controller

AVC Automated Vessel Control

COS Common Operating System

DC Direct Current

DG Diesel Generator Set

DGPS Differential Global Positioning System

DMS Data Management System

DNV Det Norske Veritas

DP Dynamic Positioning

DPC Dynamic Positioning Cabinet

DSB Distribution Switchboard

ECR Engine Control Room

EG Emergency Generator

ER Engine Room

ESB Emergency Switchboard

FMEA Failure Mode and Effect Analysis

FO Fuel Oil

FW Fresh Water

FWC Fresh Water Cooling

Fwd Forward

GPS Global Positioning System

HO Hydraulic Oil

HPU Hydraulic Power Unit

HT High Temperature

HVAC Heating, Ventilation and Cooling Systems

IJS Independent Joystick

JB Junction Box

Ladar Laser Ranging and Detection (laser radar)

LO Lubrication Oil

LT Low Temperature

MCC Motor Control Centre

MV Medium Voltage (1–100kV)

MRU Motion Reference Unit

MSB Main Switchboard

OS DP Operator Station

OT DP Operator Terminal

P Port

PCV Pressure Control Valve

PLC Programmable Logic Controller

PROM Programmable Read Only Memory

PS Pressure Switch

RAM Random Access Memory

ROM Read Only Memory

ROV Remote Operated Vehicle

s second(s)

S Starboard

SB Switchboard

SBC Single Board Computer

SCR Silicon Controlled Rectifier

Sec Section

Stbd Starboard

SW Seawater

SWC Seawater Cooling

TCV Temperature Control Valve

TW Taut Wire

UPS Uninterruptible Power Supply

Page 10: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 10 of 80 February 4, 2009

Abbreviations used in the text but not listed here are usually manufacturer model, part identification, metric notation (m, kV, etc.), common marine terminology or the ship’s equipment identification.

1.7 Vessel Overview

1.7.1 Profile

1.7.2 Layout

Page 11: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 11 of 80 February 4, 2009

1.7.3 Vessel

Length 162m Type Derrick Pipelay Builder Kepper SingMarine

Breadth unknown Tonnage 8000 Owner Global Offshore International

Depth 16m Speed unknown Class ABS +AMS +ACCU, +DPS-2

Draft 6.6m Built 2005 Flag USA

1.7.4 Propulsion

# Type & Location Pitch Speed Model Drive

T1 Port Main Azimuth Fixed Variable Wärtsilä FS3500NU

4.5MW Electric Motor Converteam MV7000 T2 Stbd Main Azimuth

T3 Port Stern Azimuth

Fixed Variable Wärtsilä

FS1510/1530MNR 2.4MW Electric Motor Converteam MV3000

T4 Stbd Stern Azimuth

T5 Port Bow Azimuth

T6 Stbd Bow Azimuth

T7 Center Bow Azimuth

T8 Bow Tunnel Fixed Variable Wärtsilä FT175M-D 880kW Electric Motor Converteam MV3000

1.7.5 Electric

DG Switchboard Generator Diesel Controllers

1 6.6kVac Port Hyundai 4700Kva .8pf

MAN 8L32/40

HS7 AVR, SYMAP sync controller, AMC 2

3 4

6.6kVac Stbd Hyundai 5300Kva .8pf MAN

9L32/40 HS7 AVR, SYMAP sync

controller, AMC 5 6

EG 480Vac Leroy Somer 1250Kva .8pf CAT 3508B CAT AVR, SYMAP

1.7.6 Automation

Dynamic Positioning System Converteam DPS-21

Independent Joystick System Converteam

Propulsion Control Systems Converteam MTC

Vessel Management Systems Converteam AVC

1.7.7 Power Generation split FO QCV LO Comp

Air FWC SWC ESD 6.6kV 480V 208V/DC MSB

Cntrl PMS FS

Redund Type

2 split Indep Indep Start Air Only

2 split 2 split IND User Set 3 split Common 2 split 2 split

DG1 2 Elect Pump

Air Manual

Mech Common supply from compressor

to Air

Common system

ind. Mech. Pumps

Common system

3 Elect Pumps

IND Feeds bus 1

Pumps fed from port side and

emergency

All Battery Chargers fed

from emergency

Must be supplied

from Battery

FS1

DG2 Mech IND Feeds bus 2

Page 12: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 12 of 80 February 4, 2009

DG3 Mech receivers 2 split by

normally closed valves

IND Feeds bus 3

bus distribution board.

Charger 1

DG4 2 Elect Pump

Air & Manual

Mech Common system ind.

Mech. Pumps

Common system

3 Elect Pumps

IND Feeds bus 4

Pumps fed from stbd side and

emergency bus

Must be supplied

from Battery

Charger 2

FS2

DG5 Mech IND Feeds bus 5

DG6 Mech IND Feeds bus 6

1.7.8 Thruster Redundancy Overview

HO LO Service

Air FWC SWC ESD 6.6kV 480V 208V 24V

FS / UPS

Redund Type

Indep Indep Comnon 2 split 2 split Indep 2 split 2 split 2 split 4 split 4 split

T1 Elect Elect Common piping controls T1-T7 shaft

brakes & T3/T7 quick

connect clutch

Loss of service

air should have no affect on running thrusters

Common

System 2 elect. Pumps

Common

System 2

parallel coolers

Elect Port Port DB9 DC4 FS11 UPS4

T2 Elect Elect Elect Stbd Stbd DB10 DC6 FS12 UPS5

T3 Elect Elect Elect Port Port DB9 DC4 FS13 UPS4

T4 Elect Elect Elect Stbd Stbd DB10 DC7 FS14 UPS5

T5 Elect Elect

Common

System 2 elect pump

Common

System 2

parallel coolers

Elect Port Port DB9 DC5 FS15 UPS6

T6 Elect Elect Elect Stbd Stbd DB10 DC7 FS16 UPS7

T7 Elect Elect Elect C/O

switch P & E DB9 DC5

FS17 UPS6

T8 N/A Elect Elect Port Port N/A N/A FS18 UPS7

1.7.9 DP System Redundancy Overview

Gyro Wind VRU Position References DP Controller (CC1 & CC2)

DP Work Station

Process Use Median Use Median Use Median Weighting Diagnostic & Changeover

User Selected

System Power I/O Power I/O Power I/O Type Power I/O Power I/O Power I/O

Split 3 2 2 2 2 2 4 2 2 2 2 2 2

Unit 1 UPS 1 CC1 CC1 CC1 CC1 CC1 DGPS

UPS 1 CC1 UPS 1 Dual

Ethernet

UPS 1 Dual

Ethernet Unit 2 UPS 2 CC2 CC2 CC2 CC2 CC2 UPS 3 CC2 UPS 2 UPS 2

Unit 3 UPS 3 CC3 Acoustic Ship Sup

CC2

Unit 4

CyScan UPS 1 CC1 IJS Controller IJS Work Station

Unit 5

TW

Port 480V

CC1 UPS 3 Modbus Ship Sup

Modbus

Unit 6 Stbd 480V

CC2 Ship Sup

Modbus

Page 13: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 13 of 80 February 4, 2009

1.7.10 Safe Mode of Operation

System Redundancy Requirements

DP All system sensors control computers, work stations, Ethernets and thrusters healthy and selected. Minimum of two independent position reference sensors selected.

IJS Healthy and ready.

Thrusters All thrusters running and healthy. All support services engaged. Sufficient thrusters selected to maintain redundancy in the available operating environment. See DP Ops Manual for details.

6.6kV Split bus, and DC control power to each side of the bus fed from different battery chargers.

480V

Switchboards split and fed from their transformers. EG ready to start. No ground faults. Auxiliary switchboard #2 CB Q103 to the emergency switchboard is to be closed and Auxiliary switchboard #1 CB Q3 to the emergency switchboard is to be open. This disables the automatic changeover circuit, but still allows the EG to auto start and connect to the bus

120/240V Bus ties open and buses fed from their transformers. No ground faults.

UPS/DC Power

Batteries charged and power supplies healthy.

VMS/PMS Converteam operator stations and field stations healthy & ready

Fuel Operate split, sample, settle, purify, stagger filling to allow detection of problems

Lube Oil Maintain pipes, sample, and purify.

Cooling Maintain pipes, connections & coolers, no heavy lifts or hot work near common FWC or SWC piping during DP2 operations

ESD All power sources ready with no wire break alarms.

HVAC Running & effective.

Environment Operate within worst case environment envelope

Maintenance Regular maintenance and testing in accordance with the manufacturer’s recommendations for the equipment operating environmental and conditions. This is the foundation of future redundancy.

Page 14: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 14 of 80 February 4, 2009

2. DP SYSTEM

FWD. WH

AFT WH

ECR

WS01(DP)

WS02(DP)

WS03(PME)

WS04(IJS)

WS05(IJS)

CCO1(DP)

CCO2(DP)

Controller(IJS)

WS06(MTC)

WS07(MTC)

Wind1

Wind2

DGPS1

DGPS2

Gyro1

Gyro2

Gyro3

VRU1

VRU2

Tautwire1

Tautwire2

AcousticsSurvey

Box

FS18(T8)

FS17(T7)

FS16(T6)

FS15(T5)

FS14(T4)

FS13(T3)

FS12(T2)

FS11(T1)

Cyscan

Printer 2

Printer 1

Helideck mon syst

WS08(MTC)

WS10(MTC)

WS09(MTC)

FS01(PMS)

FS02(PMS)

Remote Access

NS02(Net B)

NS06(Net B)

NS04(Net B)

NS01(Net A)

NS05(Net A)

NS03(Net A)

LegendNet A

Net B

Net C/ Modbus

MTC Net

Serial to WS03

Serial to CC03

Serial to CC02

Serial to CC01

UPS 2UPS 1 UPS 3 UPS 4 UPS 5 UPS 6 UPS 7Ship

Supply

2.1 DP System Data

DP Control System Converteam DPS-21 DP UPSs Seven 4.5kVA, 230V 60Hz with earthed neutral

IJS Control System Converteam DP Switch Converteam Internal Switch logic, selection switches at each MTC panel

Position References

DGPS 1 Veripos DGPS LD3

DP UPS 1 L1 GPS with Spotbeam/Inmarsat, WAAS & IALA

DGPS 2 DP UPS 3 L1 GPS with Spotbeam, WAAS & IALA

Laser CyScan MK-2 DP UPS 1 Position relative to reflective targets

Acoustics Sonardyne Fusion USBL

480V vessel supply

Position relative to beacons

Tautwire 1 Converteam A series Position relative to angle of cable.

Tautwire 2

Page 15: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 15 of 80 February 4, 2009

System References

Gyro 1

TSS Meridian Standard

DP UPS 1

Heading Reference Gyro 2 DP UPS 2

Gyro 3 DP UPS 3

Wind Sensor 1 Gill Instruments Ultrasonic

CC01 Wind force correction

Wind Sensor 2 CC02

VRU 1 TSS DMS-10

CC01 Pitch/Roll correction

VRU 2 CC02

Power Supplies Input Output

UPS 1 Main-PDB7(P) Emergency.- EPDB1 CC01, WS01, WS06 supply 1A, WS07 supply 2B, WS08 supply 1A and 2A, WS03, DP Printer 1, Gyro 1, CyScan, DP Alert System, NS01

CC01 24Vdc CC01 AC Input (UPS 1) Wind 1, VRU 1

UPS 2 Main-PDB7(S) Emergency- EPDB1 CC02, WS02, WS06 supply 2B, WS07 Supply 1A, WS08 supply 1B and 2B, DP printer 2, Gyro 2, DGPS 1, NS02

CCO2 24Vdc CC02 AC Input (UPS 2) Wind 2, VRU 2

UPS 3 Main-PDB7(P) Emergency- EPDB1 CC04, WS04, WS05, Gyro 3, DGPS 2, WS13, AVC alarm/events printer, Helideck HMS system interface cabinet

UPS 4 Main-PDB1 Emergency- EPDB2 WS09 supply 1A, FS11(T1), FS13(T3), NS05, Port Aft Winch LCP 1 and 2

UPS 5 Main-PDB2 Emergency.- EPDB2 WS09 supply 2B, FS06, FS12 (T2), FS14 (T4) NS06

UPS 6 Main-PDB1 Emergency- EPDB2 WS10 supply 1A, FS15(T5), FS18(T8), NS03, FS01, FS17(T7) supply 1

UPS 7 Main-PDB2 Emergency- EPDB2 WS10 supply 2B, FS16(T6), NS04, FS02, FS17(T7) supply 2

Ship AC Supply PDB7(port and starboard) TW1, TW2, Acoustics

Other:

Sources Converteam DP FMEA document DV5P01C01 Ver. 5 06 Aug 08

Converteam ESDI-1R42974 different sheets have different revision numbers no date

Converteam ESAS-1R-42951 Rev. 8 sheet 1 12-11-08

Converteam DP Functional Design Specification document DV1P2C1 14-Oct-08

2.2 DP System Description

2.2.1 Redundancy Concept: The DP Control system is essentially a two split system that relies on software and hardware fault detection and elimination to enhance its redundancy. It has two control computers, operator stations and Ethernet networks. It lacks the extra wind sensor and VRU required for automatic fault resolution.

2.2.2 Overview: The Global 1200 uses a dual redundant Converteam DPS-21 dynamic positioning control system. The system consists of two DP work stations, two DP control cabinets, two IJS

Page 16: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 16 of 80 February 4, 2009

work stations, one IJS control cabinet, six manual thruster control stations, two alarm printers, six network switch boxes, eight thruster field stations, seven uninterruptable power systems, seven system references, and six position references. The DP and IJS controllers and workstations are located on the bridge with four MTC stations. The remaining two MTC stations are located in the ECR. The vertical reference units are located at the ship’s center of gravity, while the DGPS antennas, CyScan, and wind sensors are located on the bridge top. The Tautwire systems are located on the main deck, and the field stations are located near their respective thruster.

2.2.3 DP Controller: The heart of the system is the marine controller inside the Control Cabinet. The marine controller receives and analyzes the system and position reference information, communicates with the work stations, and monitors and commands the thrusters. One controller is in command and the second controller is in standby. Each controller calculates independently and the standby computer takes over if the primary computer should fail. If there is a mismatch between the computers sensor and/or thruster selection/availability the controller will generate a mismatch alarm.

2.2.4 Work Stations: The operator consoles display the system settings and status, and relay the operator commands to the DP control computers. Each workstation consists of: a HMI PC, a touch screen LCD monitor and an operator panel. The operator panel includes a DP joystick, a moment control potentiometer, glide-pad, pushbuttons and LEDs to provide manual control for the DP system. Only one of the consoles is used for active control but the second console can be used for display. The standby console is updated by the console in command and can take control if that console fails. Command can be transferred between consoles. Two star-shaped Ethernet networks connect the two operator consoles, and the two controllers.

2.2.5 Ethernet: A dual Ethernet link exists between the workstations, control cubicles and the field stations; only one of these pairs of Ethernet links is active at any one time, the other link being in standby mode. The combined network is relatively immune to simple hardware failures but can still fail due to incorrect software settings or data overload. It is assumed that Converteam has designed the system so it is immune to common network faults.

2.2.6 System Sensors: The system sensors monitor the vessel’s heading, pitch/roll and wind speed/direction. These sensors are used to maintain heading, display vessel motion and estimate wind load. The system sensors consist of two TSS DMS-10 vertical reference units, two Gill Instruments Wind Observer 2 ultrasonic wind sensors and three TSS Meridian gyrocompasses. While this meets the 2005 ABS rules, IMO and IMCA recommend 3 VRUs and 3 wind sensors. ABS rules started requiring 3 wind sensors in 2008 and require a 3rd VRU if they correct all position references. This vessel is grandfathered from the latest ABS requirements, but 2008+ vessels must have them and some oil companies already require 3 sensors of each type.

2.2.7 System Sensor Handling: DP system monitors all enabled system sensors with three references (gyro) the system will automatically reject the mismatched sensor. When there are only two system sensors enabled (wind and VRU) the system uses the average of both inputs for system calculations unless it detects sensor faults. The DPS-21 rejects a wind sensor on loss of serial, jump, freeze or fast drift but requires operator correction for “slow” drift. The DPS-21 rejects a VRU for jump, freeze, or lost signal but not drift. The DPS-21 rejects a gyro on large jump and

Page 17: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 17 of 80 February 4, 2009

with three sensors selected will deselect a gyro on drift or freeze. If two sensors disagree then the system generates a mismatch alarm and DPO must decide which sensor is the faulty one and deselect it. Converteam two sensor systems depend on operator action to resolve system sensor faults but industry recommendations are to have automatic rejection of a faulty sensor. Based on this, we recommend the installation of an extra wind sensor and VRU to allow automatic rejection of a faulty sensor.

2.2.8 Position Reference Sensors: The position reference sensors monitor the position of the vessel in absolute or relative terms. The vessel has four relative position reference systems consisting of a CyScan that uses the distance and angle from a reflective target to establish position, a Sonardyne hydro-acoustic relative position reference system that determines distance from under water beacons by acoustic delay, and two Tautwire systems that use the angle of the attached cable from the bottom of the seabed to the release mechanism to establish position. The vessel has two absolute position reference systems consisting of two Veripos DGPS systems that combines the global positioning satellite position reference signals with radio correction signals to establish position. One Veripos is equipped with a switch that can be changed between Spotbeam and Inmarsat differential corrections, the second Veripos utilizes Spotbeam.

2.2.9 Position Reference Handling: The DP system weighs the value of each selected position reference automatically according to the variance of its position or operator weighting. Sensors are rejected for the following reasons: frozen information, sudden jumps in position, large position variance, and large variance compared to the calculated position and slow drift. The table below shows the position reference systems and groups them by common vulnerability. Equipment in the same row are interfaced to the same CC while the equipment in the same column are based on the same principle and are subject to common mode failures. The minimum redundant configuration can be checked by ensuring that at least 2 sensors do not share the same column or row.

DGPS1 CyScan Taut 1 DGPS2 HPR Taut 2

2.2.10 DP Switch: The DP/IJS/Manual mode selection is done through internal software. Each station has a “Control Here” PB. Pressing this button at the station in control causes the button’s light to start flashing at all available consoles. Control is taking at the new station by pressing its “control here” PB. If the DP system fails, control is automatically offered to the IJS. On loss of both the DP and IJS control is automatically offered to the MTC.

2.2.11 Thruster Interface: Eight “field stations” each provide analogue and digital I/O to each one of the vessels thrusters. At the heart of each field station is the AMC processor. Each field station communicates thruster ‘ready’ and feedback signals to the DP system, thruster data to the AVC over the Ethernet network, communicates with the IJS over dedicated serial links, and outputs hard wired reference signals to the thruster steering and pitch controls. Reference signals to the Converteam variable speed drives is via Ethernet (DP) or modbus (IJS). IJS or MTC control is still available in the unlikely event of a dual Ethernet failure.

Page 18: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 18 of 80 February 4, 2009

2.2.12 DP Power: The most important services are supplied from seven, 230Vac uninterruptible power supplies that are protected against over-voltage.

DP UPS 1 DP UPS 2 DP UPS 3 DP UPS 4 DP UPS 5 DP UPS 6 DP UPS 7

Main Supply

PDB7(P) PDB7(S) PDB7(P) PDB1 PDB2 PDB1 PDB2

Emergency Supply

EBDB1 EBDB1 EBDB1 EBDB2 EBDB2 EBDB2 EBDB2

Loads

WS01 CC01

Wind 1 Gyro 1 CyScan

DP Printer 1 DP Alert

NS01

WS2 CC02

Wind 2 Gyro 2

DGPS 1 DP Printer

2 NS02

DGPS 2

CC04

WS04

WS05

Gyro 3

DGPS 2

FS11 T1

FS13 T3

NS05

FS12 T2

FS14 T4

NS06

FS15 T5

FS18 T8

FS17 T7

NS03

FS16 T6

FS17 T7

NS04

2.2.13 Independent Joystick: A Converteam independent joystick system is available for use if the dynamic positioning system fails. It is supplied and controlled by a dedicated processing unit that in turn is powered by UPS 3 fed from both main and emergency 208V. It allows automatic heading control, automatic wind compensation and control of all available thrusters from a joystick after failure of the DP system. It communicates with each field station and reference systems via individual RS485 serial links.

2.2.14 DP Control System FMEA Table: # Fault Effect Indication DP Effect

Position Reference Systems

1a DGPS 1 or 2 failed

Loss of one position reference. DGPS failed alarm

No immediate effect on position keeping. Other position references still available.

1b Radio interference

Loss of all radio based position references.

DGPS 1 & 2 failed alarms

No immediate effect on position keeping. Other position references still available.

1c

Faulty IALA, delayed signal, low # of satellites

Both DGPS wrong together. Quick drift or jumping can be detected by the DP system.

Position reference alarms

Possible DPO Intervention. If only three reference systems then Vessel “averages” away from position until the DGPS are deselected. With four or more reference systems DGPS will be rejected.

1d CyScan failed Loss of one position reference. CyScan failed alarm

No immediate effect on position keeping. Other position references still available.

1e Multi target CyScan incorrect and rejected by DP system for high variability or quick jump.

No immediate effect on position keeping. Other position references still available.

Page 19: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 19 of 80 February 4, 2009

# Fault Effect Indication DP Effect

1g False Target CyScan incorrect and rejected by DP system for high variability or quick jump.

No immediate effect on position keeping. Other position references still available.

1h Tautwire Failed Lose of one position reference Tautwire failed alarm

No immediate effect on position keeping. Other position references still available.

1i Tautwire incorrect data

Tautwire incorrect and rejected by DP system for high variability or quick jump

Tautwire failed alarm

No immediate effect on position keeping. Other position references still available.

1j Acoustic Failed Loss of one position reference. Acoustic beacon failed alarm

No immediate effect on position keeping. Other position references still available.

1k Acoustic incorrect data

Acoustics incorrect and rejected by DP system for based on fault bit set in telegram

Acoustic beacon failed alarm

No immediate effect on position keeping. Other position references still available.

System Sensors

2a Wind sensor failed

Loss of one wind sensor. Wind failed alarm

No immediate effect on position keeping. Other wind sensor still available.

2b

Ultrasonic interference and some weather conditions

Loss of all wind sensors Wind 1, and 2 failed alarms

No immediate effect on position keeping. Loss of direct wind compensation. Position keeping may be rougher.

2c wind sensor incorrect data

Incorrect wind compensation. Wind direction mismatch alarm.

DPO must select the good wind sensor, if it can be identified, or position may be lost.

2d Gyroscope 1 failed

Loss of one gyrocompass. IJS auto heading control not available.

Gyro failed alarm

No immediate effect on position keeping. Loss of one gyroscope. Other gyroscopes ok. System defaults to selected or next gyro. If a second fault occurs the DPO must be ready to select the good gyro.

2e Gyroscope 2 failed

Loss of one gyrocompass.

2f Gyroscope 3 failed

Loss of one Gyrocompass

2g Heading jump DP system rejects a large jump. Gyro rejected alarm

No loss of heading. Loss of gyro redundancy.

2h Heading mismatch

DP system rejects selected gyro No loss of heading. Loss of gyro redundancy

2i VRU failed Loss of one VRU. Secondary VRU continues to operate

VRU failed alarm No immediate effect on position keeping. Loss of redundant sensor.

2j A VRUs data is incorrect

The VRUs are used to correct the CyScan, Acoustics & DGPS position reference data for vessel movement. False corrections cause false position data. DP system rejects data out of a certain window

VRU difference alarm

DPO must select the good MRU, if it can be identified, or position may be lost.

DP Controllers

Page 20: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 20 of 80 February 4, 2009

# Fault Effect Indication DP Effect

3a In command DP controller AMC failed

Standby controller detects fault and takes command.

Controller failed and command transfer alarm

No immediate effect on position keeping. Loss of DP controller.

3b Standby DP controller AMC failed

No disruption of in command controller. Standby no longer available

Controller failed alarm.

No immediate effect on position keeping. Loss of DP controller.

3c MAE 99-04 serial link panel failed

Loss of equipment associated to failed serial link panel.

loss of connected sensors and/or PMEs with DP alarms.

No immediate effect on position keeping. Possible loss of sensor and/or PME redundancy.

3d

In command DP controller 24Vdc PSU failure

Standby controller detects fault and takes command. Loss of some sensors and PME equipment

Controller, sensor, PME failed and command transfer alarms

No immediate effect on position keeping. Loss of DP controller, sensor, and PME redundancy.

3e

Standby DP controller

24Vdc PSU failure

No disruption of in command controller. Standby no longer available. . Loss of some sensors and PME equipment

Controller, sensor and PME failed alarms

No immediate effect on position keeping. Loss of DP controller, sensor, and PME redundancy.

Operator Workstations

4a DP workstation display failed

Display not available. Panel and other workstation displays still ok. Changes can still be input to this workstation from the panel but should be done with care.

Display not available but panel information still good.

No immediate effect on position keeping. Reduced workstation redundancy. Other workstation available for control. DP system continues operating normally.

4b DP workstation panel failed

No response to operator joystick or turning moment commands.

System does not respond to panel commands.

No immediate effect on position keeping. Reduced workstation redundancy. Other workstation available for control. DP system continues operating normally.

4c DP workstation glide pad failed

Changes can still be input to this workstation from LCD Touch screen.

System does not respond to glide pad commands

No immediate effect on position keeping. Reduced workstation redundancy. Standby workstation available for control. DP system continues operating normally.

4d DP workstation CPU/Ethernet Failures

Loss of one operator console. Control offered to standby work station.

Audible alarm at the redundant work station, frozen or dead display

No immediate effect on position keeping. Control also available at plug-in operator terminals.

4e DP workstation LCD Failed

No operator Display, panel and glide pad still operational

Display turns black

No immediate effect on position keeping. .Control can be assumed at remaining DP workstation.

4f Independent Joystick failed

IJS not available as backup. The IJS should be tested before entering DP.

Workstation network alarms

No immediate effect on position keeping. Loss of backup system

Page 21: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 21 of 80 February 4, 2009

# Fault Effect Indication DP Effect

4g DP workstation 24Vdc PSU

Failure detected by controller. Loss of workstation panel control offered to standby work station

Flashing visible alarm on LCD and audible alarm

No immediate effect on position keeping. Reduced workstation redundancy. Standby workstation available for control. DP system continues operating normally.

Thruster Field Stations

5a Field station Processor failure

Loss of associated thruster. DP alarm and de-select.

No loss of heading or position. DP system compensates with remaining thrusters.

5c Analogue module input

Lost or incorrect feedback. System model is not disrupted because thruster feedback is not used in force calculations. (System assumes commands are followed and alarms on the difference).

Thruster DP feedback alarm

No immediate effect on position keeping. DPO must quickly determine if the problem is loss of feedback or lost thruster control. In this case the problem is feedback and DP control does not deteriorate despite the alarm.

5d Analogue module output failure

Lost or incorrect command. System model begins being corrupted because the force calculations assume commands are followed. The force difference between the expected and the actual thrust begins building into the model as environmental current.

Thruster DP feedback alarm

DPO action required. DPO must quickly determine if the problem is loss of feedback or lost thruster control. In this case the problem is lost control, position keeping deteriorates and environmental current changes value. The DPO must recognize these signs and deselect the thruster. If the thruster continues thrusting after deselect it must be stopped.

5e Digital input module failure

Loss of thruster ready. Thrust command set to zero. Thruster follows command.

Loss of ready DP alarm and de-select.

No loss of heading or position. DP system compensates with remaining thrusters.

5f Field Station 24Vdc PSU failed

Loss of associated thruster. DP alarm and de-select.

No loss of heading or position. DP system compensates with remaining thrusters.

Ethernet

6a Loss of one link. Loss of redundant link to one field station, workstation or controller.

Ethernet link failed alarm

No immediate effect on position keeping. Communication continues on remaining link to that device.

6b Network A or B switch failed

Loss communications failed network. Redundant network continues to function.

Ethernet link failed alarms

No immediate effect on position keeping. Communication transfers to healthy network. Communication redundancy lost.

DP Power

7a DP UPS 1 or 2 Charger fault

UPS on battery backup for a minimum half hour.

UPS input alarm No immediate effect on position keeping. Limited operating time until failure. No loss of DP after

Page 22: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 22 of 80 February 4, 2009

# Fault Effect Indication DP Effect

7b DP UPS 1 or 2 output failed

DP degraded to simplex mode. Loss of one workstation, some sensors and PMEs.

Many alarms. No immediate effect on position keeping. Loss of redundancy.

7c DP UPS 4, 5, 6 or 7 Charger fault

UPS on battery backup for a minimum half hour.

UPS input alarm No immediate effect on position keeping. Limited operating time until failure. No loss of DP after

7d DP UPS 4, 5, 6 or 7 output failed

Loss of two thruster field stations, one feed to the MTC desks, and power feedback signals from one of the switchboards

Many alarms. No loss of heading or position. DP system compensates with remaining thrusters and sensors.

2.3 Summary of DP System Analysis

2.3.1 Significant Failure Modes: The analysis found no single point failures and three failure modes that may require DPO intervention:

2c – Faulty wind compensation - Drastic error in the selected wind sensor may cause loss of position due to incorrect wind compensation. DPO must quickly identify and select the healthy wind sensor.

2m - False VRU correction data - Converteam DP systems use the VRU data to correct the position references for the motion of the vessel rather than using mathematical filtering. This allows fast accurate results when the VRUs are correct but causes all references to appear to move if the VRU is wrong. DPS-21 rejects a VRU for jump, freeze or lost signal but not drift. As the position references are dependent on the accuracy of the selected VRU and the VRUs have known failure modes, Converteam systems that use VRUs to correct position reference systems need three VRUs to allow automatic correction of a VRU fault.

5d – Thruster field station analog output module failure - Expected and actual thrust don’t match because the thruster does not perform as expected. This endangers the DP model and the thruster has to be deselected or stopped.

2.3.2 Hidden Failures: The analysis identified failures that could reduce system redundancy: Failure Problem Solution

DP software not updated

Software may resolve hidden faults that were discovered on similar systems on other vessels

Regularly check for new software revisions and install proven solutions.

Battery failure No battery backup when charger fails. Regular battery maintenance and regular testing under load.

2.3.3 Maloperation: Converteam equipment is protected against accidental maloperation by requiring vital push buttons to be pressed twice to operate. Light objects that may bounce, such as a phone receiver, should be kept from above these buttons.

2.3.4 Configuration Analysis: When only three reference systems are being used the DPO must ensure proper weighting between position references to ensure redundancy as DGPS 1 & 2 are really a single reference.

Page 23: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 23 of 80 February 4, 2009

2.3.5 Related Failures: This system is affected by thruster, power and some auxiliary support system faults. These failures are examined in the appropriate sections.

2.3.6 Worst Case Failure: The worst case failure is loss of position or heading due to an unrecognized VRU fault. While it was once considered possible for a DPO to correct these faults, greater experience has lead to the industry requiring three of these sensors to allow automatic correction of these faults.

2.3.7 Accuracy: The analysis is based on the Converteam documentation and the shipyard power one lines. Failure modes not included in this analysis include software fault causing loss of position and network faults causing loss of communication. These problems have occurred in operation on other vessels but are rare but should be included in the Converteam analysis. Analysis has not yet been confirmed by survey or testing.

2.3.8 DP System Summary:

Single Point Failures 0

DPO Intervention Required 4

Maintenance Issues 2

Analysis Accuracy Medium

Page 24: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 24 of 80 February 4, 2009

3. MAIN AZIMUTH THRUSTERS

3.1 Azimuth System Diagram

Page 25: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 25 of 80 February 4, 2009

3.2 Main Azimuth System Data

Type Azimuth Thruster Manufacturer/Model Wärtsilä FS3500 NU

Propeller 5 blade, 3.6m Ni Al. Bronze

Nozzle Yes. LIPS HR

Pitch Fixed Pitch Control N/A

Speed Range 0 to 170 RPM Speed Control Converteam MV7000 VSD

Deployment Permanent (bolted) Deployment Control N/A

Steering 360˚, 2 rpm, ±2˚ Steering Control Wärtsilä Lip Controller

Steering HPU Source

2 480V pumps. Steering Cooling Oil Coolers supplied FWC system

Gear Box Type Cooling Lubrication

Lower 90˚, Reduction, Azimuth LO FW cooler Forced (elect pump, header tank)

VSD Drive Power Main 6.6kVareduced to 1680V,

VSD control Power 220 and 24vdc

Drive Auxiliary Power

Auxiliary 480V Thruster Controller Power

220V, 24Vdc primary and backup

Drive Motor 4500kW Electric motor

Drive Power source T1=Port 6.6kV switchboard T2= Starboard 6.6kV switchboard

Drive Motor cooling

2 Electric pumps Thruster FWC Sys. VSD cooling

Fresh water cooled, Internal glycol

Other: T1 and T2, Air Brake

Sources: Wärtsilä FS3502-571 NU Installation Manual Rev. 1 5-9-2007 Converteam PV1P01C02S01_B_Propulsion System Functional Requirements T1 & T2.doc

3.3 Main Azimuth System Description

3.3.1 Redundancy Concept: These two thrusters provide most of the stern surge sway and yaw power. The thrusters have independent power and separate control circuits, but share the aft FWC system with each other and the two other aft thrusters. The aft FWC system has 2 independent electric pumps and 2 coolers but the common piping means that proper protection of this system is vital to redundancy.

3.3.2 Location: Thruster one is located in the propulsion room aft PS while thruster two is located in the propulsion room aft SB. The MV7000 cabinets and auxiliary equipment are located near the thrusters. Each thruster has manual controls in the forward Bridge, DP control room and in the ECR.

3.3.3 6.6kV supply transformer: Each thrusters’ drive power is supplied from a dedicated 5.8MVA, water-cooled, 6.6kV/1680V transformer. The transformer has an auxiliary service that is supplied from the auxiliary switchboard associated with the thruster. The transformers are cooled with water from the thruster FWC system. The transformer supply breaker is tripped by transformer winding over temperature or secondary over current. The VSD monitors the transformer for faults. The VSD controls the starting and stopping of the transformer auxiliary services

Page 26: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 26 of 80 February 4, 2009

3.3.4 VSD Control: The Propeller speed is used to control the magnitude of thrust from each thruster because the blade pitch is set. The VSD controls the propeller speed by varying the motor speed from zero to 600rpm. The VSD is under Converteam field station command except during local emergency operation. The VSD is monitored from the associated Converteam field station. The field station monitors alarm and status contacts plus the analog feedback signals. It sends command signals, speed commands and a power limit signal to the VSD via Ethernet. LIPs receive motor and brake control contacts from the VSD. The LIPS controller provides the VSD with a start permissive contact.

3.3.5 VSD Support: Each of the Converteam supplied MV7000 variable speed drive units is equipped with an independent (secondary) internal glycol cooling system. This cooling system is then cooled by an external (Primary) FW cooling system. Each VSD is supplied with power from a fresh water cooled transformer fed from the main switchboard. The drive hardware is controlled by a Programmable Electronic Controller (PEC), which is linked to the dual redundant network for communication with the DP, VMS and MTC. A single MODBUS serial link to a GE “Quick panel” MMI provides local alarms and monitoring.

3.3.6 Drive Motor: Each azimuth thruster’s shaft rotation power is supplied by a vertically mounted 4.5mW, 12-pole, 0-600 rpm electrical motor that is connected to the thruster by a flexible coupling. The motor has self-contained greased roller bearings and is cooled by the thruster FWC system. The drive motors are protected by RTD‘s that are monitored by the VSD and have leak detectors for alarm. Each motor has a pneumatic shaft brake. Wärtsilä speed feedback is also taken from the motor shaft.

3.3.7 Thruster FWC: Each thruster’s motor, lube oil and hydraulic oil system is cooled from the aft thruster FWC system. Both azimuths share the same cooling system but they are protected against failure by using redundant pumps. Failure of the running pump causes the vessel management system to start a standby pump. The fresh water is cooled by two parallel seawater coolers.

3.3.8 Lower gearbox: The lower gearbox rotates for azimuth steering, changes the vertical shaft rotation to horizontal rotation and reduces the output propeller shaft speed (1:3.538). It is lubricated by 2 electric pumps arranged in a primary/secondary arrangement and cooled by the aft Thruster FWC system. The gears are supported by roller bearings; the output shaft has a triple lip seal, the input shaft a lip seal and other parts are sealed by O-rings. The lube oil pumps are started/stopped/monitored from Wärtsilä/Converteam and feed from the auxiliary switchboard. The associated Converteam field station monitors lube oil alarms.

3.3.9 Propeller: Each propeller is a five-bladed, 3.6m diameter, fixed-pitch unit. Each propeller sits in a thruster nozzle bolted to the lower gearbox housing. The nozzles are constructed of mild steel grade A, with stainless steel in way of propeller to end of trailing edge. Aluminum anodes provide cathodic protection of the lower gearbox, propeller and nozzle.

3.3.10 Steering Hydraulics: Each lower gearbox is rotated by an electrically controlled hydraulic system to control the direction of thrust (propeller blade pitch is fixed). The position of the lower gearbox is set by hydraulic motors that can turn the lower gearbox using gear drives and the

Page 27: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 27 of 80 February 4, 2009

toothed rim of the lower section. The hydraulic pressure to change the motors’ positions is supplied by a positive displacement hydraulic pump driven by an electric motor. Two proportional solenoid control valves control the volume and direction of the pump flow to the hydraulic motors. One is used to control the volume of flow, or speed of the motors, while the second valve is used to control the direction of flow, or motor rotation. When the proportional valves are in the zero position the steering motors are hydraulically locked and will not suffer from rotation creepage providing the hydraulic oil system is in good condition. Other hydraulic valves regulate pressure and release overpressures. An oil cooler supplied with fresh water from the fresh water cooling system cools the steering hydraulic oil. Steering position is given via mechanical feedback and electrical transducers supply the steering feedback for display and control. The electrical steering pump are setup primary and secondary when steering pressure is low the standby pump will start.

3.3.11 Wärtsilä Steering Control: The LIPS controller can be used to control steering locally, but is normally controlled from the Converteam field station associated with that thruster. It compares the direction command, from the system selected for control, with the actual direction given by the steering control feedback. The difference between the two is used to determine the direction and rate of desired change. The rate of change is used to control the proportional control valve. As the thruster nears the required position, the required rate of change lowers and stops when the thruster is within tolerance of the command. The Converteam field station uses separate steering feedback pots but they are not independent as they share a same mechanical feedback link. Separate pots allow a single failed pot to be corrected but a failed feedback link must be protected against by good maintenance, calibration and watch keeping. The associated Converteam field station monitors the Wärtsilä controller for alarm and status contacts and analogue steering feedback. It sends command contacts and an analogue steering command to Wärtsilä. This allows the controller to react to loss of steering command with a major fault alarm. In this case, typical thruster control logic expects the field station to identify the thruster as not ready for DP and stop the drive motor. This will be verified during trials.

3.3.12 Field Station: The field station associated with each thruster provides the control access for the DP, MTC and IJS systems. If DP control is selected, then the DP system controls and monitors the thrusters over the dual Ethernet network. If IJS control is selected, then the IJS system controls and monitors the thrusters over its dedicated serial link interface. The MTC consoles contain the protected thruster emergency stop buttons and allow individual, group or joystick thruster control. Each field station receives control power from a Converteam supplied 220V UPS. Converteam protects their equipment from supply over-voltages.

3.3.13 Thruster Control: The VSD is normally controlled by the DP system but can be controlled from the MTC stations on the Bridge, or the MTC ECR in an emergency or for maintenance. Communication between the field station and DP is via dual Ethernet. MTC communicates utilizing an independent Ethernet system, while the IJS uses serial communication (Modbus). The motor drive does an internal systems and auxiliary status check and if healthy and in remote, it sends a ready to start signal to the MTC. When the drive is started it becomes available for control at each control station (MTC, IJS, DP) after the thruster is selected for control by a station it begins following the field station commands. The field station communicates with the

Page 28: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 28 of 80 February 4, 2009

DP system to determine the system in control (MTC, DP or IJS) and sends that system’s speed command to the VSD.

3.3.14 Redundancy/Commonality: Both thrusters have aft thruster FWC and SWC systems piping in common. Service Air

3.4 Main Azimuth System FMEA Table Failure Effect Indication DP Effect

Converteam MV7000 Signals

1a

Shorted over temperature fault

signal from XFMR to VSD

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1b

Open over temperature warning signal from XFMR

to VSD

High temperature warning not available

Hidden fault. Possible automatic S/D without warning

on overheating

No loss of position or heading. Thruster continues to operate

1c Open water leak detection signal

from XFMR to VSD

alarm on false water leak detection

False water leak alarm No loss of position or heading. Thruster

continues to operate

1d Open cooling fan status signal from XFMR to VSD

False loss of cooling fan alarm power reduced

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

1e Open RTD signal

from XFMR to VSD Loss of temperature

monitoring VSD system fault alarm

No loss of position or heading. Thruster continues to operate

1f Open RTD signal from MOTOR to

VSD

Loss of temperature monitoring

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

1g Failed net A FS-

VSD No redundancy in communication

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

1h Failed net B FS-

VSD No redundancy in communication

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

1i Open E-Stop signal

to VSD Unable to remotely E-

Stop VSD

Local VSD alarm E-Stop Wire break detected alarm. VMS

alarm VSD system fault alarm

No loss of position or heading. Thruster continues to operate

1j Incorrect DP Speed

Command.

Depending on the source, effects could

range from a flicker in speed to an incorrect speed setting to full

RPM.

DP feedback DP command. Possible RPM feedback alarm

on DP.

DPO Intervention. DP assumes requested thrust is achieved faulty command causes

inaccuracy in model. DPO to E-Stop thruster if station keeping endangered.

1k Loss of Speed

Feedback to VSD. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1l Incorrect Speed

Feedback to VSD.

The thruster still follows DP commands. No

effect on DP Possible DP feedback alarm.

No loss of heading or position. Loss of one thruster.

Wärtsilä- LIPS Controller

2a Open motor start allowed LIPS to

VSD Unable to restart VSD VSD system fault alarm

No loss of heading or position. Thruster continues to operate restart unavailable

2b Open motor off

signal VSD to LIPS No panel indication No indication on local control

No loss of heading or position. Thruster continues to operate.

Page 29: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 29 of 80 February 4, 2009

Failure Effect Indication DP Effect

2c Open release brake signal VSD to LIPS

Unable to remotely engage brake

Brake does not engage remotely local operation

available

No loss of heading or position. Thruster continues to operate.

2d Open thruster

healthy signal to FS Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2e Open local control select signal to FS

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2f Open remote control select signal to FS

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2g Open control

accepted signal from FS

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust.

No loss of heading or position. Loss of one thruster.

2h Open remote in

control signal to FS Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2i

Open steering pressure available at primary pump

signal to FS

Primary steer pump stopped and standby

pump started.

VMS alarm thruster steering standby pump running

No loss of heading or position. Loss of one thruster.

2j Failed steering

command from FS Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2k Incorrect steering command from FS

Depending on the source, effects could

range from a flicker in azimuth to an incorrect

azimuth setting.

DP feedback DP command. Possible thruster azimuth feedback alarm on DP.

DPO Intervention. DP assumes requested azimuth is achieved faulty command causes

inaccuracy in model. DPO to E-Stop engine if station keeping endangered.

2l Incorrect steering command from

LIPS

LIPS controller detects fault and motor shut

down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2m Open minor failure alarm signal to FS

False minor failure alarm VMS thruster minor steering

failure alarm No loss of heading or position. Thruster

continues to operate.

2n Open major failure alarm signal to FS

False major failure alarm. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2o Open power failed alarm signal to FS

False power fail alarm VMS thruster controller power

failure alarm No loss of heading or position. Thruster

continues to operate.

2p Open brake engaged

signal to FS No brake engaged signal

available No indication until failure has

a control effect. No loss of heading or position. Thruster

continues to operate.

2q Open LO primary pump psi ok signal

Motor shutdown

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2r Open LO secondary pump psi ok signal

Motor shutdown

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

Page 30: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 30 of 80 February 4, 2009

Failure Effect Indication DP Effect

2s Loss of steering

control feedback. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust.

No loss of heading or position. Loss of one thruster.

2t Incorrect steering control feedback.

Actual thrust value is wrong because the

feedback reference is wrong.

DP feedback = command but indication feedback. Position

keeping deteriorates and/or current changes.

DPO intervention required. Loss of one thruster. DP system compensates with

remaining thrusters.

2u Loss of steering

indication feedback to LIPS.

LIPS controller Feedback not correct.

No effect on DP

LIPS Controller feedback indication incorrect.

No immediate effect on position keeping.

2v Incorrect steering

indication feedback to LIPS.

LIPS controller Feedback not correct.

No effect on DP

LIPS Controller feedback indication incorrect.

No immediate effect on position keeping.

Thruster Auxiliary equipment interface

3a Stuck CW steering

solenoid vv Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3b Stuck CCW steering

solenoid vv Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3c Open shaft speed encoder signal to

LIPS Unable to engage brake Thruster common alarm

No loss of heading or position. Thruster continues to operate.

3d Open brake engage signal from LIPS

Unable to engage brake No indication until failure has

a control effect No loss of heading or position. Thruster

continues to operate.

3e Open activate CW FU solenoid signal

Unable to turn azi in clockwise direction

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3f Open activate CCW FU solenoid signal

Unable to turn azi in clockwise direction

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3g Failed primary

steering pump psi ok signal to LIPS

Standby pump starts and primary pump stopped

VMS alarm thruster standby pump running

No loss of heading or position. Thruster continues to operate.

3h Open start steering pump1 command signal from LIPs

Unable to start steering pump

VMS failed to start alarm No loss of heading or position. Thruster

continues to operate.

3i Open start steering pump2 command signal from LIPS

Unable to start steering pump

VMS failed to start alarm No loss of heading or position. Thruster

continues to operate.

3j Open stop steering pump1 command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3k Open stop steering pump2 command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3l Open steering

pump1 running indication to LIPS

False pump stopped indication local

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3m Open steering

pump2 running indication to LIPS

False pump stopped local indication

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

Page 31: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 31 of 80 February 4, 2009

Failure Effect Indication DP Effect

3n Open steering

pump1 running indication to FS

False pump stopped indication at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3o Open steering

pump2 running indication to FS

False pump stopped indication at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3p Open steering

feedback to LIPS from thruster

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3q

Open primary LO pump start

command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3r

Open secondary LO pump start

command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3s Open primary LO

pump running signal from LIPS

False pump stopped indication local

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3t Open secondary LO pump running signal

from LIPS

False pump stopped local indication

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3u Open primary LO

pump running signal from FS

False pump stopped indication at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3v Open secondary LO pump running signal

from FS

False pump stopped local at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3w Failed Azimuth

angle feedback to FS

Loss of feedback to DP system with eventual DP

feedback alarm.

DP thruster feedback alarm, no effect on station keeping as feedback is not used in DP

thrust calculations

No loss of heading or position. Thruster continues to operate.

Lipstronic VMS alarm interface signals

4a Open clogged

steering oil return filter alarm signal

False clogged steering oil return filter alarm

VMS alarm thruster clogged return filter

No loss of heading or position. Thruster continues to operate.

4b Open clogged

steering oil pressure filter alarm signal

False open steering oil pressure filter alarm

VMS alarm thruster clogged pressure filter

No loss of heading or position. Thruster continues to operate.

4c Open steering oil high temperature

alarm signal

False steering oil high temperature alarm

VMS Alarm thruster steering oil high temperature

No loss of heading or position. Thruster continues to operate.

4d Open low steering oil tank level alarm

signal

False low steering oil tank level alarm

VMS Alarm thruster low steering oil level

No loss of heading or position. Thruster continues to operate.

4e Open LO primary

pump clogged filter 1 signal

False filter clogged alarm

VMS alarm Primary LO pump clogged filter 1

. No loss of heading or position. Thruster continues to operate

4f Open LO primary

pump clogged filter 2 signal

False filter clogged alarm

VMS alarm Primary LO pump clogged filter 2

. No loss of heading or position. Thruster continues to operate

4g Open LO high temp

alarm signal False high temp alarm

VMS Alarm thruster LO oil high temperature

No loss of heading or position. Loss of one thruster.

4h Open LO secondary pump clogged filter

signal

False filter clogged alarm

VMS alarm Secondary LO pump clogged filter

. No loss of heading or position. Thruster continues to operate

Page 32: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 32 of 80 February 4, 2009

Failure Effect Indication DP Effect

Power Failures

5a 230V Main Power

supply fail Loss of redundant

power supply Power fail alarm

No loss of heading or position. Thruster continues to operate.

5b 24Vdc backup power fail

Loss of redundant power supply

Power fail alarm No loss of heading or position. Thruster

continues to operate.

5c Internal power

failure Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP.

Manual & DP feedback indicates zero thrust

No loss of heading or position. Loss of one thruster.

3.5 Summary of Main Azimuth System Analysis

3.5.1 Significant failure modes: The azimuth thruster failure mode and effect analysis table found no single point failures, and three failure modes that require DPO intervention to correct. These failure modes reflect a control fault that causes incorrect thrust magnitude or direction. The wrong thrust force or angle is significant, because it moves the vessel. The DP operator must be familiar with these failure modes, able to identify them and intervene by deselecting or stopping the thruster if position keeping is endangered.

3.5.2 Hidden Failures:

Failure Problem Solution

Mechanical feedback link Thrust control lost but difficult to detect. Regular calibration and maintenance is needed.

Alarm failures No advance notification of impending failures Regular testing is needed.

Battery failure No battery backup when charger fails. Regular battery maintenance and regular testing under load.

3.5.3 Configuration Analysis: Both main thrusters are required for DP2 operation.

3.5.4 Related Failures: This system is affected by power, Converteam and some auxiliary support system faults. These failures are examined in the appropriate sections.

3.5.5 Worst Case Failure: An incorrect speed command will cause wrong thrust with eventual feedback alarms. Large changes of force can cause loss of heading and position unless the DPO quickly recognizes the fault and deselects the thruster.

3.5.6 Accuracy: The analysis is based on shipyard drawings and manufacturer documentation. The analysis has not yet been confirmed by survey and testing.

3.5.7 Azimuth Thruster Summary: Single Point Failures 0 DPO Intervention Required 3 Maintenance Issues 7 Analysis Reliability Medium

Page 33: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 33 of 80 February 4, 2009

4. DROP DOWN AZIMUTH THRUSTERS

Page 34: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 34 of 80 February 4, 2009

4.1 Drop Down Azimuth System Data

Type Drop Down Azimuth Thruster

Manufacturer/Model Wärtsilä FS3500 NU

Propeller 5 blade, 2.5m NiAl Bronze

Nozzle Yes. LIPS HR

Pitch Fixed Pitch Control N/A

Speed Range 0 to 258 RPM Speed Control Converteam MV3000 VSD

Deployment Retractable Deployment Control Hydraulic

Steering 360˚, 2 rpm, ±2˚ Steering Control Wärtsilä LIPS controller

Steering HPU Source

2 480V pumps. Steering Cooling Oil Coolers supplied FWC system

Gear Box Type Cooling Lubrication

Upper 90º, Reduction Cooler Spray lube/Oil bath (elect pump, header tank)

Lower 90˚, Reduction, Azimuth

Surrounding seawater Splash lube/Oil Bath (elect pump, header tank)

VSD Drive Power Main 6.6kV reduced to 720V ,

VSD control Power 220V and 24Vdc

Drive Auxiliary Power

Auxiliary 480V Thruster Controller Power

220V, primary 24Vdc backup

Drive Motor 2400kW Electric motor

Drive Power source T3,5,7=Port 6.6kV switchboard T4,6,7= Starboard 6.6kV switchboard

Drive Motor cooling

2 Electric Pumps VSD cooling

Fresh water cooled, Internal glycol

Other: T3& T4 Aft, T5 – 7 FWD, T7 switching

Sources: Wärtsilä 00345M1C33-7 Design Specification Document Rev. 02 Wärtsilä DAAK004483 Thruster installation Document Rev. 01 Converteam PV1P1C2S2_D_ Propulsion system control T3-T7

4.2 Drop Down Azimuth System Description

4.2.1 Aft Redundancy Concept: T3 and T4 provide 1/3 of the stern surge, sway and yaw power. These thrusters have independent power and separate control stations from each other, but share the aft FWC system with all aft thrusters and each shares power sources with a main azimuth thruster, creating a two split system if the FWC and supplying SWC system are properly protected.

4.2.2 Fwd Redundancy Concept: T5 – 7 provide most of the bow surge, sway and yaw power. T5 and 6 have independent power and separate control stations from each other. T7 is meant to be able to be switched between port or starboard power but share 220V, 24V and FS UPS power with port thruster T5. All three thrusters share the same FWC system.

4.2.3 Location: There is a total of five drop down azimuth thrusters. Two are located on the port side. T3 is located in the aft thruster/pump room and T5 is located in the thruster room PS. Two are located on the starboard side T4 in the aft thruster/pump room and T6 is in the thruster room SB. T7 is located close on the centerline in the forward thruster room. The MV3000 cabinets and

Page 35: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 35 of 80 February 4, 2009

auxiliary equipment are located near the thrusters. Each thruster has manual controls in the forward Bridge and DP control room.

4.2.4 6.6kV supply transformer: Each thruster’s drive power is supplied from a dedicated, 3.1MVA, water-cooled, 6.6kV/7200V transformer. The transformer has an auxiliary service that is supplied from the auxiliary switchboard associated with the thruster. The transformer is cooled with water from the thruster FWC system. The transformer supply breaker is tripped by transformer winding over temperature or secondary over current. The VSD monitors the transformer for faults. It starts and stops the transformer auxiliary services

4.2.5 VSD Control: The Propeller speed is used to control the magnitude of thrust from each thruster because the blade pitch is set. The VSD controls the propeller speed by varying the motor speed from zero to 1000rpm. The VSD is under Converteam field station command except during local emergency operation. The VSD is monitored from the associated Converteam field station. The field station monitors alarm and status contacts plus the analog feedback signals. It sends control signals, speed commands and a power limit signal to the VSD via Ethernet. LIPs receive motor and brake control contacts from the VSD. The LIPS controller provides the VSD with a start permissive contact.

4.2.6 VSD Support: Each of the Converteam supplied MV3000 variable speed drive units is equipped with an independent (secondary) internal glycol cooling system. This cooling system is then cooled by an external (Primary) FW cooling system. Each VSD is supplied with power from a fresh water cooled transformer fed from the main switchboard. The drive hardware is controlled by a Common Drive Controller (CDC) which is linked by MODBUS to the Converteam field stations AMC for communication with the DP, IJS, MTC and VMS. An Ethernet link to a door mounted HMI display provides local alarms and monitoring.

4.2.7 Thruster Clutch: The clutch is of the quick connect type and is automatically engaged and disengaged during the deployment/retraction sequence of the thruster. The clutch is controlled by a 5 port 2 position solenoid controlled pneumatic valve. Loss of air pressure or control power will not cause clutch to change states.

4.2.8 Thruster Brake: A disc-type brake is fitted on the propeller shaft to prevent shaft from turning when thruster is not in operation. The brake is engaged by energizing a pneumatic controlled solenoid. Loss of pneumatic air will cause brake to be disengaged. The only two ways of controlling the brake is automatically during remote steering control or manually during local steering control. When in remote the Lipstronic control system automatically controls the brake. The brake can be engaged when remote control is in service, the propeller motor off contact (from VSD) is closed and the drive motor shaft RPM is below 50. If all these conditions are met the engage/release brake contact (from VSD) closing will engage the brake. Loss of any of the previous conditions will cause the brake to automatically release. The Converteam field station receives a contact from the thruster indicating brake position. When in local control, the brake can be engaged when local control is in service, the propeller motor off contact (from VSD) is closed and the drive motor shaft RPM is below 50. If all these conditions are met then pressing the brake standby/off pushbutton will engage the brake. The brake will be released when in local control by either of two scenarios. Both scenarios require local control in service and the

Page 36: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 36 of 80 February 4, 2009

thruster fully deployed. The first scenario also requires pressing the standby/off pushbutton while the second scenario would require the propeller motor off contact (from VSD) to be open. A lamp on the local control panel indicates brake position. During change from remote to local control the brake will not change states. During change from local to remote the brake will engage when permissives stated above are met for engaging break in remote.

4.2.9 Drive Motor: Each azimuth thrusters’ shaft rotation power is supplied by a horizontally mounted 2.4mW, 12-pole, 0-1000 rpm electric motor that is connected to the thruster by a flexible coupling. The motor is water cooled by the thruster FWC system. The motor has self-contained, greased, roller bearings. The drive motors are protected by RTD monitored by the VSD and have leak detectors for alarm. Each motor has a pneumatic shaft brake. Wärtsilä speed feedback is also taken from the motor shaft.

4.2.10 Thruster FWC: Each thruster’s motor and hydraulic power unit is cooled from the thruster FWC system. Both azimuths share the same cooling system but they are protected against failure by using redundant pumps. Failure of the running pump causes the vessel management system to start a standby pump. The fresh water is cooled by two parallel seawater coolers.

4.2.11 Thruster Retraction System: The thruster is retracted and deployed using the thruster’s hydraulic steering system. The retraction/deployment can be controlled locally from the control cabinet or remotely from the vessel management system. Permissives that must be met before deployment/retraction are steering pumps running, azimuth in park position and the drive motor off. During deployment/retraction the steering mode is disabled. Using the vessel management system to send a signal to the system when the vessel is travelling more than 4 knots will prevent deployment/retraction of the thruster. The thruster motor must be stopped to enable retractions with the steering pumps still on; pressing the “Retract” pushbutton automatically causes the thruster to turn until it reaches the parked position. A lamp at the control cabinet will light indicating the thruster is in the parked position. Then the locking hooks are unlocked the brake is engaged and the clutch is released. While retracting the “Retract” lamp will flash and warning horn will sound. Once fully retraced the locking hooks will lock and the thruster will lower till it reaches the locking hooks. The process can be reversed by pushing the “Deploy” button or stopped completely by pressing the emergency stop button causing the thruster to hydraulically lock. To restart the operator should press either the “Retract” or “Deploy” pushbutton. If there is a failure during retraction the system will send a retraction failed signal to the vessel management system.

4.2.12 Upper Gearbox: The power of the prime mover is transmitted through a floating shaft and quick connect clutch to the input shaft of the upper gearbox of the thruster. The secondary shaft of the upper gearbox is connected to the primary shaft of the lower gearbox through a vertical intermediate shaft. It is lubricated by an electric pump and cooled by the aft Thruster FWC system. The lube oil pump is started/stopped/monitored from Wärtsilä/Converteam and feed from the auxiliary switchboard. The associated Converteam field station monitors lube oil alarms.

4.2.13 Lower gearbox: The propeller gearbox is fitted with a spiral bevel gear set. The crown wheel and the pinion are independently supported on both sides in order to minimize deflections and to

Page 37: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 37 of 80 February 4, 2009

assure optimal teeth contact under all load conditions. The propeller gearbox is bolted to the thruster’s support pipe. The lower gearbox rotates for azimuth steering, changes the vertical shaft rotation to horizontal rotation and reduces the output propeller shaft speed (1:3.738). It is lubricated by an electric pump and cooled by surrounding seawater. The lube oil pump is started/stopped/monitored from Wärtsilä/Converteam and feed from the auxiliary switchboard. The associated Converteam field station monitors lube oil alarms.

4.2.14 Propeller: Each propeller is a five-bladed, 2.5m diameter, fixed-pitch unit. Each propeller sits in a thruster nozzle bolted to the lower gearbox housing. The nozzles are constructed of mild steel grade A, with stainless steel in way of propeller to end of trailing edge. Aluminum anodes provide cathodic protection of the lower gearbox, propeller and nozzle.

4.2.15 Steering Hydraulics: Each lower gearbox is rotated by an electrically controlled hydraulic system to control the direction of thrust (propeller blade pitch is fixed). The position of the lower gearbox is set by two geared hydraulic motors. The steering gear is connected to the steering pipe and rotated round its vertical axis. The hydraulic pressure to change the motor’s positions is supplied by a positive displacement hydraulic pump driven by an electric motor. Two proportional solenoid control valves control the volume and direction of the pump flow to the hydraulic motors. One is used to control the volume of flow, or speed of the motors, while the other is used to control the direction of flow, or motor rotation. When the proportional valves are in the zero position the steering motors are hydraulically locked and will not suffer from rotation creepage, provided the hydraulic oil system is in good condition. Other hydraulic valves regulate pressure and release overpressures. An oil cooler supplied with fresh water from the fresh water cooling system cools the steering hydraulic oil. Steering position is given via mechanical feedback and electrical transducers supply the steering feedback for display and control. The electrical steering pumps are setup primary and secondary, and when steering pressure is low the secondary pump will start.

4.2.16 Wärtsilä Steering Control: The LIPS controller can be used to control steering locally, but is normally controlled from the Converteam field station associated with that thruster. It compares the direction command, from the system selected for control, with the actual direction given by the steering control feedback. The difference between the two is used to determine the direction and rate of desired change. The rate of change is used to control the proportional control valve. As the thruster nears the required position, the required rate of change lowers and stops when the thruster is within tolerance of the command. The Converteam field station uses separate steering feedback pots but they are not independent as they share the same mechanical feedback link. Separate pots allow a single failed pot to be corrected but a failed feedback link must be protected against by good maintenance, calibration and watch keeping. The associated Converteam field station monitors the Wärtsilä controller for alarm and status contacts plus the analog steering feedback signal. It sends command contacts and an analogue steering command to Wärtsilä. This allows the system to react to loss of steering command with a major fault alarm. In this case, typical thruster control logic expects the field station to identify the thruster as not ready for DP and stop the drive motor. This will be verified during trials.

4.2.17 Field Station: The field station associated with each thruster provides the control access for the DP, MTC and IJS systems. If DP control is selected, then the DP system controls and monitors

Page 38: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 38 of 80 February 4, 2009

the thrusters over the dual Ethernet network. If IJS control is selected, then the IJS system controls and monitors the thrusters over its dedicated serial link interface. The MTC consoles contain the protected thruster emergency stop buttons and allows for individual, group or joystick thruster control. Each field station receives control power from a Converteam supplied 220V UPS. Converteam protects their equipment from supply over-voltages.

4.2.18 Thruster Control: The VSD is normally controlled by the DP but can be controlled from the MTC stations on the bridge, or the MTC ECR in an emergency or for maintenance. Communication between the field station and DP is via dual Ethernet, MTC communicates utilizing an independent Ethernet system, while the IJS uses serial communication (Modbus). The motor drive does an internal system and auxiliary status check and if healthy and in remote, it sends a ready to start signal to the MTC. When the drive is started it becomes available for control at each control station (MTC, IJS, DP) after the thruster is selected for control by a station it begins following the field station commands. The field station communicates with the DP system to determine the system in control (MTC, DP or IJS) and sends that system’s speed command to the VSD.

4.2.19 T7 Auto changeover logic: T7 is designed to automatically change over on a loss of main power to the 6.6kV incomer supply. Upon loss of power the T7 logic will check to ensure that both incomer breakers are healthy and that neither CB lockout is active. If both breakers are healthy then the logic will trip the CB that lost incoming power, then verifies both breakers are open before initiated the pre-charge circuit. After the pre-charge circuit is charged the alternate CB will be closed and T7 will be under DP control. The logic is setup to prevent a wire break from activating the changeover. The process will take a minimum of 30 seconds to complete based on the CB motor limitation.

4.2.20 Redundancy/Commonality: Thrusters have service air in common.

4.3 Drop Down Azimuth System FMEA Table Failure Effect Indication DP Effect

Converteam MV3000 Signals

1a Open water leak detection signal

from XFMR to VSD Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1b Open cooling fan status signal from XFMR to VSD

False loss of cooling fan alarm power reduced

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

1c Open RTD signal

from XFMR to VSD Loss of temperature

monitoring VSD system fault alarm

No loss of position or heading. Thruster continues to operate

1d Open water leak detection signal

from Motor to VSD Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1e Open RTD signal from MOTOR to

VSD

Loss of temperature monitoring

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

Page 39: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 39 of 80 February 4, 2009

Failure Effect Indication DP Effect

1f Failed Modbus Link

FS-CDC Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1g Open E-Stop signal

to VSD Unable to remotely E-

Stop VSD

Local VSD alarm E-Stop Wire break detected alarm. VMS

alarm VSD system fault alarm

No loss of position or heading. Thruster continues to operate

1h Incorrect DP Speed

Command.

Depending on the source, effects could

range from a flicker in speed to an incorrect speed setting to full

RPM.

DP feedback DP command. Possible RPM feedback alarm

on DP.

DPO Intervention. DP assumes requested thrust is achieved faulty command causes

inaccuracy in model. DPO to E-Stop engine if station keeping endangered.

1i Loss of Speed

Feedback to VSD. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1j Incorrect Speed

Feedback to VSD.

The thruster still follows DP commands. No

effect on DP Possible DP feedback alarm.

No loss of heading or position. Loss of one thruster.

1k Fail cooling water

leak Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

Wärtsilä- LIPS Controller

2a Open motor start allowed LIPS to

VSD Unable to restart VSD VSD system fault alarm

No loss of heading or position. Thruster continues to operate restart unavailable

2b Open motor off signal VSD to

LIPS No panel indication No indication on local control

No loss of heading or position. Thruster continues to operate.

2c Open release brake signal VSD to LIPS

Unable to remotely engage brake

Brake does not engage remotely local operation

available

No loss of heading or position. Thruster continues to operate.

2d Open thruster

healthy signal to FS Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2e Open local control select signal to FS

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2f Open remote control select signal to FS

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2g Open remote in

control signal to FS Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2h

Open steering pressure available at primary pump

signal to FS

Primary steer pump stopped and standby

pump started.

VMS alarm thruster steering standby pump running

No loss of heading or position. Loss of one thruster.

2i failed steering

command from FS Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

Page 40: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 40 of 80 February 4, 2009

Failure Effect Indication DP Effect

2j Incorrect steering command from FS

Depending on the source, effects could

range from a flicker in azimuth to an incorrect

azimuth setting.

DP feedback DP command. Possible thruster azimuth feedback alarm on DP.

DPO Intervention. DP assumes requested azimuth is achieved faulty command causes

inaccuracy in model. DPO to E-Stop engine if station keeping endangered.

2k Incorrect steering command from

LIPS

LIPS controller detects fault and motor shut

down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2l Open brake engaged

signal to FS Loss of Brake Engaged

Indication No indication until failure has

a control effect. No loss of heading or position. Thruster

continues to operate.

2m Open Brake engage cmd signal from FS

Loss of remote brake engage function

No indication until failure has a control effect.

No loss of heading or position. Thruster continues to operate.

2n Open UGB LO PSI available signal to

FS Motor shutdown

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2o Open LGB LO PSI available signal to

FS Motor shutdown

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

2p Loss of steering

control feedback. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust.

No loss of heading or position. Loss of one thruster.

2q Incorrect steering control feedback.

Actual thrust value is wrong because the

feedback reference is wrong.

DP feedback = command but indication feedback. Position

keeping deteriorates and/or current changes.

DPO intervention required. Loss of one thruster. DP system compensates with

remaining thrusters.

2r Loss of steering

indication feedback to LIPS.

LIPS controller Feedback not correct.

No effect on DP

LIPS Controller feedback indication incorrect.

No immediate effect on position keeping.

2s Incorrect steering

indication feedback to LIPS.

LIPS controller Feedback not correct.

No effect on DP

LIPS Controller feedback indication incorrect.

No immediate effect on position keeping.

2t Open Clutch

engaged signal to FS

Loss of clutch engaged indication. Motor

Shutdown

False clutch disengaged indication remotely

No immediate effect on position keeping.

2u Open Speed < 4kts

signal Unable to deploy or

retrace thruster No indication until failure has

a control effect. No immediate effect on position keeping.

Thruster Auxiliary equipment interface

3a Stuck CW steering

solenoid vv Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3b Stuck CCW steering

solenoid vv Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3c Open shaft speed encoder signal to

LIPS Unable to engage brake Thruster common alarm

No loss of heading or position. Thruster continues to operate.

3d Open brake engage signal from LIPS

Unable to engage brake No indication until failure has

a control effect No loss of heading or position. Thruster

continues to operate.

3e Loss of air pressure Unable to change air

pressure for draft compensation

VMS low air pressure alarm No loss of heading or position. Thruster

continues to operate.

Page 41: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 41 of 80 February 4, 2009

Failure Effect Indication DP Effect

3f Open FU CW

command signal Unable to turn azi in clockwise direction

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3g Open FU CCW command signal

Unable to turn azi in clockwise direction

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3h Failed primary

steering pump psi ok signal to LIPS

Standby pump starts and primary pump stopped

VMS alarm thruster standby pump running

No loss of heading or position. Thruster continues to operate.

3i Open start steering pump1 command signal from LIPs

Unable to start steering pump

VMS failed to start alarm No loss of heading or position. Thruster

continues to operate.

3j Open start steering pump2 command signal from LIPS

Unable to start steering pump

VMS failed to start alarm No loss of heading or position. Thruster

continues to operate.

3k Open stop steering pump1 command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3l Open stop steering pump2 command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3m Open steering

pump1 running indication to LIPS

False pump stopped indication local

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3n Open steering

pump2 running indication to LIPS

False pump stopped local indication

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3o Open steering

pump1 running indication to FS

False pump stopped indication at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3p Open steering

pump2 running indication to FS

False pump stopped indication at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3q Open steering

feedback to LIPS from thruster

Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

3r

Open UGB LO pump start

command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3s

Open LGB LO pump start

command signal from LIPS

No immediate effect, unable to stop pump

remotely

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3t Open UGB LO

pump running signal from LIPS

False pump stopped indication local

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3u Open LGB LO

pump running signal from LIPS

False pump stopped local indication

LIPS pump stopped local indication

No loss of heading or position. Thruster continues to operate.

3v Open UGB LO

pump running signal from FS

False pump stopped indication at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

Page 42: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 42 of 80 February 4, 2009

Failure Effect Indication DP Effect

3w Open LGB LO

pump running signal from FS

False pump stopped local at VMS

VMS pump stopped indication No loss of heading or position. Thruster

continues to operate.

3x Failed Azimuth

angle feedback to FS

Loss of feedback to DP system with eventual DP

feedback alarm.

DP thruster feedback alarm, no effect on station keeping as feedback is not used in DP

thrust calculations

No loss of heading or position. Thruster continues to operate.

3y Open Engage clutch cmd signal to Clutch

Unable to engage brake No indication until failure has

a control effect No loss of heading or position. Thruster

continues to operate.

3z Open Disengage

clutch cmd signal to Clutch

Unable to disengage brake

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

3aa Open clutch

engaged fdbk signal from clutch

Loss of Brake Engaged Indication

No indication until failure has a control effect.

No loss of heading or position. Thruster continues to operate.

3ab Open clutch

disengaged fdbk signal from clutch

Loss of Brake disengaged Indication

No indication until failure has a control effect.

No loss of heading or position. Thruster continues to operate.

Lipstronic VMS alarm interface signals

4a Open clogged

steering oil return filter alarm signal

False clogged steering oil return filter alarm

VMS alarm thruster clogged return filter

No loss of heading or position. Thruster continues to operate.

4b Open clogged

steering oil pressure filter alarm signal

False open steering oil pressure filter alarm

VMS alarm thruster clogged pressure filter

No loss of heading or position. Thruster continues to operate.

4c Open steering oil high temperature

alarm signal

False steering oil high temperature alarm

VMS Alarm thruster steering oil high temperature

No loss of heading or position. Thruster continues to operate.

4d Open low steering oil tank level alarm

signal

False low steering oil tank level alarm

VMS Alarm thruster low steering oil level

No loss of heading or position. Thruster continues to operate.

4e Open LO UGB

pump clogged filter 1 signal

False filter clogged alarm

VMS alarm Primary LO pump clogged filter 1

. No loss of heading or position. Thruster continues to operate

4f Open LO UGB

pump clogged filter 2 signal

False filter clogged alarm

VMS alarm Primary LO pump clogged filter 2

. No loss of heading or position. Thruster continues to operate

4g Open LO high temp

alarm signal False high temp alarm

VMS Alarm thruster LO oil high temperature

No loss of heading or position. Loss of one thruster.

4h Open LO LGB

pump clogged filter 1 signal

False filter clogged alarm

VMS alarm Secondary LO pump clogged filter

. No loss of heading or position. Thruster continues to operate

4i Open LO LGB

pump clogged filter 2 signal

False filter clogged alarm

VMS alarm Secondary LO pump clogged filter

. No loss of heading or position. Thruster continues to operate

4j Open minor failure alarm signal to FS

False minor failure alarm

VMS thruster minor steering failure alarm

No loss of heading or position. Thruster continues to operate.

4k Open major failure alarm signal to FS

False major failure alarm. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP.

Manual & DP feedback indicates zero thrust

No loss of heading or position. Loss of one thruster.

4l Open power failed alarm signal to FS

False power fail alarm VMS thruster controller power

failure alarm No loss of heading or position. Thruster

continues to operate.

Deployment System Failures

5a Loss of Retracted

feedback to FS Loss of remote

indication Remote panel flashes

No loss of heading or position. Thruster continues to operate.

Page 43: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 43 of 80 February 4, 2009

Failure Effect Indication DP Effect

5b Loss of Retracted feedback to LIPS

Loss of local and remote indication

Local and remote panel flashes No loss of heading or position. Thruster

continues to operate.

5c Loss of Deployed

feedback to FS Loss of remote

indication Remote panel flashes

No loss of heading or position. Thruster continues to operate.

5d Loss of Deployed feedback to LIPS

Loss of local and remote indication

Local and remote panel flashes No loss of heading or position. Thruster

continues to operate.

5e Loss of Parked feedback to FS

Loss of remote indication

Remote panel flashes No loss of heading or position. Thruster

continues to operate.

5f Loss of Parking position reached signal to LIPS

Loss of local and remote indication

Local and remote panel flashes No loss of heading or position. Thruster

continues to operate.

5g Open retraction

failed signal Alarm indicating retraction failure

VMS and Local alarm retraction failed

No loss of heading or position. Thruster continues to operate.

5h Loss of Retract cmd

signal from FS Can’t retract thruster remotely from bridge

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

5i Loss of Retract cmd

from LIPS

Can’t retract thruster remotely or locally from

LIPS

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

5j Loss of Deploy cmd

signal from FS Can’t deploy thruster remotely from bridge

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

5k Loss of Deploy cmd

from LIPS

Can’t deploy thruster remotely or locally from

LIPS

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

5l Loss of enable

steering cmd from LIPS

No immediate effect, if system changed to

retraction mode, then can’t switch back

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

5m Loss of enable

retraction cmd from LIPS

No immediate effect, if system changed to steering mode, then can’t switch back

No indication until failure has a control effect

No loss of heading or position. Thruster continues to operate.

Power Failures

6a 230V Main Power supply to LIPS fail

Loss of redundant power supply

Power fail alarm No loss of heading or position. Thruster

continues to operate.

6b 24Vdc backup power to LIPS fail

Loss of redundant power supply

Power fail alarm No loss of heading or position. Thruster

continues to operate.

6c Internal LIPS power

failure Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP.

Manual & DP feedback indicates zero thrust

No loss of heading or position. Loss of one thruster.

6d 480V AUX Power to MV3000 Failure

Cooling pump stops VMS alarm thruster Aux power

failed alarm No loss of heading or position. Loss of one

thruster.

4.4 Summary of Drop-Down Azimuth System Analysis

4.4.1 Significant failure modes: The azimuth thruster failure mode and effect analysis table found no single point failures, and three failure modes that require DPO intervention to correct. These failure modes reflect a control fault that causes incorrect thrust magnitude or direction. The wrong thrust force or angle is significant, because it moves the vessel. The DP operator must be

Page 44: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 44 of 80 February 4, 2009

familiar with these failure modes, able to identify them and intervene by deselecting or stopping the thruster if position keeping is endangered.

4.4.2 Hidden Failures:

Failure Problem Solution

Mechanical feedback link Thrust control lost but difficult to detect. Regular calibration and maintenance is needed.

Alarm failures No advance notification of impending failures Regular testing is needed.

Deployment system command signals

No advanced notification of lose of ability to deploy or retract thruster

Regular testing is needed.

Battery failure No battery backup when charger fails. Regular battery maintenance and regular testing under load.

4.4.3 Configuration Analysis: All five thrusters are required for DP2 operation.

4.4.4 Related Failures: This system is affected by power, Converteam and some auxiliary support system faults. These failures are examined in the appropriate sections.

4.4.5 Worst Case Failure: An incorrect speed command will cause wrong thrust with eventual feedback alarms. Large changes of force can cause loss of heading and position unless the DPO quickly recognizes the fault and deselects the thruster.

4.4.6 Accuracy: The analysis based on manufacturer and shipyard drawings and documents and has not yet been confirmed by survey and testing. Surveyor to confirm final arrangement and logic of the T7 auto change over circuit.

4.4.7 Drop Down Azimuth Thruster Summary:

Single Point Failures 0

DPO Intervention Required 3

Maintenance Issues 18

Analysis Reliability Medium

Page 45: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 45 of 80 February 4, 2009

5. BOW TUNNEL THRUSTER

880kW

Electric

Motor

Drive Power

FW

C

HeadTank

Converteam Field Station (located in MV3000 drive cubicle)

ConverteamMV3000

220V UPS

M

LO Tank

RTD Signals

DP IJS MTC

Inde

pend

ent

Net

wor

k

Mod

Bus

Net

wor

k A

Net

wor

k B

CDC

6.6Kv SBD

Mod

Bus

620V

480V Aux

5.1 Bow Thruster System Data

Type Transverse Tunnel Thruster

Manufacturer/Model Wärtsilä FT175M

Propeller 4 blade, 1.75m NiAl Bronze

Nozzle N/A

Pitch Fixed Pitch Control N/A

Speed Range 0 to 375rpm Speed Control Converteam MV3000 VSD

Deployment Permanent Steering Propeller direction

Gear Box Type Cooling Lubrication

Lower Reduction Surrounding seawater Forced lube/Oil Bath (elect pump, header tank)

VSD Drive Power Main 6.6kV reduced to 720V

VSD control Power 220V and 24Vdc

Drive Auxiliary Power

Auxiliary 480V Thruster Controller Power

N/A

Drive Motor 880kW Electric motor

Drive Power source Port 6.6kV switchboard

Drive Motor cooling

2 Electric Pumps VSD cooling

Fresh water cooled, Internal glycol

Other: T8

Sources: Converteam PV1P1C2S3_C_ Propulsion system control T8 Wärtsilä Transverse Thruster Installation Manual

Page 46: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 46 of 80 February 4, 2009

5.2 Bow Thruster System Description

5.2.1 Redundancy Concept: T8 provides 10% of the bow sway and yaw power. The bow tunnel has port main power but appears to reflect T6 control power.

5.2.2 Location: The tunnel thruster is in the forward thruster frame 55. The MV3000 cabinets and auxiliary equipment are located near the thrusters. Each thruster has manual controls in the forward Bridge, DP control room and in the ECR.

5.2.3 6.6kV supply transformer: The thruster’s drive power is supplied from a dedicated, 1.1MVA, water-cooled, 6.6kV/7200V transformer. The transformer has an auxiliary service that is supplied from the auxiliary switchboard associated with the thruster. The transformer is cooled with water from the thruster FWC system. The transformer supply breaker is tripped by transformer winding over temperature or secondary over current. The VSD monitors the transformer for faults. It starts and stops the transformer auxiliary services. The transformer is wound phase-shifted from thrusters 1-7 and provides a small amount of harmonic distortion cancellation depending on loads.

5.2.4 VSD Control: The Propeller speed and direction of rotation is used to control the magnitude of thrust from this thruster because the blade pitch is set. The VSD controls the propeller speed by varying the motor speed from zero to 1200rpm. It changes the rotation of the motor to change the direction of thrust. The VSD is equipped with separately mounted air cooled breaking resistors for faster propeller reversal. The VSD is controlled and monitored from the associated Converteam field station. The field station monitors alarm and status contacts, analog feedback. It sends command signals, speed commands and a power limit signal to the VSD via Modbus.

5.2.5 VSD Support: The Converteam supplied MV3000 variable speed drive unit is equipped with an independent (secondary) internal glycol cooling system. This cooling system is then cooled by an external (Primary) FW cooling system. Each VSD is supplied with power from a fresh water cooled transformer fed from the main switchboard. The drive hardware is controlled by a Common Drive Controller (CDC) which is linked by MODBUS to the Converteam field stations AMC for communication with the DP, IJS, VMS and MTC. An Ethernet link to a door mounted HMI display provides local alarms and monitoring.

5.2.6 Drive Motor: The tunnel thruster’s shaft rotation power is supplied by a vertically mounted 88kW, 12-pole, 0-1200rpm electric motor that is connected to the thruster by a flexible coupling. The motor is water cooled by the thruster FWC system. The motor has self-contained, greased, roller bearings. The drive motors are protected by RTD monitored by the VSD and have leak detectors for alarm.

5.2.7 Thruster FWC: The thruster’s motor is cooled from the fwd thruster FWC system. The bow tunnel thruster and the forward azimuths share the same common cooling system but it is protected against failure by using redundant pumps. Failure of the running pump causes the vessel management system to start a standby pump. The fresh water is cooled by two parallel seawater coolers.

Page 47: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 47 of 80 February 4, 2009

5.2.8 Gearbox: The rolled mild steel center tunnel section provides seating for a vertically mounted electric motor. It also contains a wearing ring to prevent corrosion. The pinion and shaft are one piece while the gear wheel is bolted to the propeller shaft. The thruster contains spherical roller bearings used to absorb loads. The pinion shaft is sealed using a radial lip seal. The propeller shaft is sealed using three supported radial lip seals.

5.2.9 Gearbox support: Lubrication system consists of header tank pressurized by the service air system, an electric pump, and a CJC filter. The header tank is used to ensure oil pressure is greater that static water pressure to prevent water leakage in the event of seal failure. The system contains a pressure filter that sends a high pressure alarm to the VMS at 2.5bar and a low pressure alarm at .3bar. The system is also equipped with a high temperature alarm. Pump can be set to filter only mode which allows it to be run continuously. System cooled by surrounding seawater. The lubrication pump running is not essential to thruster operation. The manufacturer does state that it needs to be operated a minimum of 20 hours every 200 operating hours.

5.2.10 Propeller: The propeller has four 1.75m fixed pitch blades and is made out of NiAl Bronze. The propeller is designed to rotate up to 350 times per minute.

5.2.11 Field Station: The field station associated with the thruster provides the control access for the DP, MTC and IJS systems. If DP control is selected, then the DP system controls and monitors the thrusters over the dual Ethernet network. If IJS control is selected, then the IJS system controls and monitors the thrusters over its dedicated serial link interface. The MTC consoles have the protected thruster emergency stop buttons and allow individual, group or joystick thruster control. Each field station receives control power from a Converteam supplied 220V UPS. Converteam protects their equipment from supply over-voltages.

5.2.12 Thruster Control: The VSD is normally controlled by the DP but can be controlled from the MTC stations on the Bridge, or the MTC ECR in an emergency or for maintenance. Communication between the field station and DP is via dual Ethernet, MTC communicates utilizing an independent Ethernet system, while the IJS uses serial communication (Modbus). The motor drive does an internal systems and auxiliary status check and if healthy and in remote, it sends a ready to start signal to the MTC. When the drive is started it becomes available for control at each control station (MTC, IJS, DP) after the thruster is selected for control by a station it begins following the field station commands. The field station communicates with the DP system to determine the system in control (MTC, DP or IJS) and sends that system’s speed command to the VSD.

5.2.13 Redundancy/Commonality: Utilizes the same FWC piping as T4 and T6. T8 uses the same seawater coolers as T4 and T6. Service Air system is common to thrusters T1-T7.

5.2.14 Bow Thruster System FMEA Table: Failure Effect Indication DP Effect

Converteam MV3000 Signals

1a Open RTD signal from MOTOR to

VSD

Loss of temperature monitoring

VSD system fault alarm No loss of position or heading. Thruster

continues to operate

Page 48: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 48 of 80 February 4, 2009

Failure Effect Indication DP Effect

1b Failed Modbus Link

FS-CDC Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1c Open E-Stop signal

to VSD Unable to remotely E-

Stop VSD

Local VSD alarm E-Stop Wire break detected alarm. VMS

alarm VSD system fault alarm

No loss of position or heading. Thruster continues to operate

1d Fail cooling water

leak signal Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1e Incorrect DP Speed

Command.

Depending on the source, effects could

range from a flicker in speed to an incorrect speed setting to full

RPM.

DP feedback DP command. Possible RPM feedback alarm

on DP.

DPO Intervention. DP assumes requested thrust is achieved faulty command causes

inaccuracy in model. DPO to E-Stop engine if station keeping endangered.

1f Loss of Speed

Feedback to VSD. Motor shut down

Thruster not ready alarm on DP. Thruster deselected from DP. Manual & DP feedback

indicates zero thrust

No loss of heading or position. Loss of one thruster.

1g Incorrect Speed

Feedback to VSD.

The thruster still follows DP commands. No

effect on DP Possible DP feedback alarm.

No loss of heading or position. Loss of one thruster.

1h Fail Ethernet A or B

to FS

No effect redundant network still

communicating

DP Thruster Ethernet Failure alarm

No loss of position or heading. Thruster continues to operate

1i Fail Independent Link from MTC

No effect. DP has control

Communication Failure alarm No loss of position or heading. Thruster

continues to operate

Thruster Auxiliary equipment interface

2a Fail LO Pump No Effect. LO Pump not

essential to thruster operation

Possible Pump Failure alarm at VMS

No loss of heading or position. Thruster continues to operate.

Thruster VMS alarm interface signals

3a Open LO high temp

alarm signal False high temp alarm

VMS Alarm thruster LO oil high temperature

No loss of heading or position. Loss of one thruster.

3b Open LO pressure

switch. False low pressure

alarm. VMS alarm thruster LO

pressure low . No loss of heading or position. Thruster

continues to operate

Power Failures

4a 480V AUX Power to MV3000 Failure

Cooling pump stops VMS alarm thruster Aux power

failed alarm No loss of heading or position. Loss of one

thruster.

5.3 Summary of Bow Thruster Analysis

5.3.1 Significant failure modes: The azimuth thruster failure mode and effect analysis table found no single point failures, and one failure mode that requires DPO intervention to correct. This failure mode reflects a control fault that causes incorrect thrust magnitude or direction. The wrong thrust force or angle is significant, because it moves the vessel. The DP operator must be familiar with these failure modes, able to identify them and intervene by deselecting or stopping the thruster if position keeping is endangered.

Page 49: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 49 of 80 February 4, 2009

5.3.2 Hidden Failures:

Failure Problem Solution

Alarm failures No advance notification of impending failures Regular testing.

Battery failure No battery backup when charger fails. Regular battery maintenance and regular testing under load.

5.3.3 Configuration Analysis: Thruster is required for DP2 operation.

5.3.4 Related Failures: This system is affected by power, Converteam and some auxiliary support system faults. These failures are examined in the appropriate sections.

5.3.5 Worst Case Failure: An incorrect speed command will cause wrong thrust with eventual feedback alarms. Large changes of force can cause loss of heading and position unless the DPO quickly recognizes the fault and deselects the thruster.

5.3.6 Accuracy: The analysis is based on shipyard drawings and manufacturer documentation. The analysis has not yet been confirmed by survey and testing.

5.3.7 Bow Thruster Summary:

Single Point Failures 0

DPO Intervention Required 1

Maintenance Issues 3

Analysis Reliability Medium

.

Page 50: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 50 of 80 February 4, 2009

6. ELECTRICAL POWER SYSTEMS

6.1 Electrical Power Distribution Diagram

G

DG1

G

DG2

G

DG4

G

DG5

MAN 9L32/404230kW

MAN 8L32/403760kW

6.6kV630A 630A 630A 630A

T1 4500KW

Xfmr 5850kVA

6600/2x1680V

GDG3

G

DG6

630A 630A

MAN 9L32/404230kW

MAN 9L32/404230kW

MAN 8L32/403760kW

MAN 8L32/403760kW

MV7000IGBT PWM

Pre Charge

Precharge

T8 880KW

MV3000IGBT PWM

Precharge

Xfmr 1150kVA

6600/720V

MV3000IGBT PWM

T5 2400 KW

Xfmr 4000kVA

6600/510V

Precharge

Xfmr 5850kVA

6600/2x1680V

T3 2400KW

MV3000IGBT PWM

Xfmr 1150kVA

5500/720VXfmr

1150kVA6600/720V

MV3000IGBT PWM

T7 2400 KW

Precharge

C/OSwitch

C/OSwitch

Lin

k

Xfmr 1150kVA

6600/720V

MV3000IGBT PWM

T6 2400 KW

Precharge

T2 4500KW

Xfmr 5850kVA

6600/2x1680V

MV7000IGBT PWM

Pre Charge

Precharge

Precharge

Xfmr 4000kVA

6600/510V

T4 2400KW

MV3000IGBT PWM

Xfmr 1150kVA

5500/720V

6600/720V 5500kVA

6600/720V 5500kVA

690V Pipelay/Crane Switchboard

480V Pipelay/Crane Switchboard

690V/505V1800kVA

480V Auxiliary Switchboard 1 (Port) 480V Auxiliary Switchboard 2 (Starboard)

208-120V sectionBus Bar “A”

208-120V sectionBus Bar “B”

2 out of 3 Interlock

480V ODB2

480V HPDB2

480V ODB4

480V PDB2

480V PDB4

480V FPDB2

480V FPDB4

Group Starter 2

480V ODB1

480V HPDB1

480V ODB3

480V PDB1

480V PDB3

480V FPDB1

480V FPDB3

Group Starter 1

480V Emergency Switchboard

Auto Change Over

Shore Conn. Box

G EG

CAT 3508B1000kW

208/120V Emergency Switchboard

Auto Change Over

Page 51: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 51 of 80 February 4, 2009

6.2 Electrical Generator Control Diagram

Page 52: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 52 of 80 February 4, 2009

6.3 Electric Power System Data

Main System 6.6kV, 60Hz, neutral resistance earthing

Other Systems 690Vac,480Vac,120Vac,110Vdc

Main Engines MAN 8L32/40, MAN 9L32/40 Engine Start Pneumatic

Engine Cooling Split FWC system with mechanical pumps, and header tank

Engine Fuel 2 Day tanks – DG1-3 Fwd, DG4-6 Aft, redundant electric pumps, filters, Cross connects

Engine Lube Self-contained, forced Engine Control

Power 24vdc

Speed/Hz Control

Heinzmann Electronic Governor controlled by raise/lower switch located on switchboard, automatically by Symap protection relay unit, or PMS system.

Generators Hyundai HS7 6.6kV, 0.8pf, 3ph, 60hz, DG1-3 4.2mW, DG4-6 3.7mW

Voltage Control Hyundai 6GA2491 controlled remotely at switchboard or from PMS via Symap protection relay unit.

Main Switchboards

Two switchboards connected in a ring bus configuration with tie links that can be split into open ring configuration

Manufacturer IPT Main Bus ?

DG1-6 Breakers ABB 630A, Symap protection relay unit, manual or automatic control, 110v control power

Bus Tie /Inter-connectors

ABB 1250A, Symap protection relay unit, manual or automatic control, 110v control power

Emergency DG Caterpillar 3508B electronic controlled diesel powered with radiator cooling and a Leroy Somer Generator rated for 1000kW, 3 phase, 480V.

EG Control AVR controlled remotely at emergency switchboard, Symap protection relay unit

Emergency Switchboard

MAS Main Breaker Protection

UV trip coil, interlock, current trips

690V Mission Switchboard

IPT Main Breaker Protection

UV trip coil, interlock, current trips

480V Mission Switchboard

IPT Main Breaker Protection

UV trip coil, interlock, current trips

480V Auxiliary Switchboards

MAS Main Breaker Protection

UV trip coil, interlock, current trips

208V Panels Floating Wye, ground detection, molded case circuit breakers

24V Systems Ground protection, over/under voltage protection.

Other:

Sources: Kepper Sing Marine H340-101.1 Rev 4 Hyundai Generator Specification Sheets Converteam PV1P01C03_B_MV Switchboard Functional Specification IPT Switchboard A drawing, Switchboard B drawing, and Changeover drawing Converteam AV1P03C01_A_Power Management System Caterpillar 07S161-3508B-1, 07S161-2508B-2, 07S161-3508B-3 drawings. MAN Project Guide for 32/40 Engine Plants Document Hyundai Operating Instructions Synchronous Generators Manual Emergency Switchboard and Auxiliary Switchboard information submitted to ABS document titled P69508ESP_S10 & S13_34327281.pdf Dated 21/01/09

Page 53: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 53 of 80 February 4, 2009

6.4 Electric Power System Description

6.4.1 Redundancy Concept: Generally two split with battery backup for vital control systems. This concept is violated by T7’s dioded control power, ESB switch and DC power supplies. The vital DC power supplies (DG 4/5, DG 6/7) should be separated. Additional information is required to confirm the combined power doesn’t threaten both sides of the power split. The isolated DG excitation and speed controls appear to be interconnected through PMS adjustment.

6.4.2 Location: There are two main 6.6kV switchboards and two 480V Auxiliary switchboards with one of each located in the port and starboard switchboard rooms. Three main diesel generator sets (DG1-3), and a fuel day tank are located in the forward engine room. Three main diesel generator sets (DG4-6), and a fuel day tank are located in the aft engine room. The Transformers used to supply reduced voltage to each thruster’s VSD is located near the respective thruster. The 690V and 480V Pipelay/Crane switchboards are located in the mission switchboard room. The emergency switchboard, emergency generator, emergency day tank, and emergency transformers are located in the Emergency Generator Room. Transformers used to supply reduced voltage to the Auxiliary and Pipelay/Crane switchboards is assumed to be located in one of the following three places port, starboard or mission switchboard room. Secondary 208/120V and 24Vdc panels are distributed throughout the vessel.

6.4.3 Main DG Engines: There are two types of MAN diesel engines that supply shaft rotation power to each main generator. Diesel generators 1-3 shaft rotation is powered by 9 cylinder, 4 stroke, 720rpm, 4.3mW MAN 9L32/40 engines. Diesel generators 4-6 shaft rotation is powered by 8 cylinder, 4 stroke, 720rpm, 3.8mW MAN 8L32/40 engines. Diesel generators 1-3 are normally supplied with marine diesel fuel from the port day tank using 1 of 2 electrical pumps arranged in a main/standby configuration. Diesel generators 4-6 are normally supplied with marine diesel fuel from the starboard day tank using 1 of 2 electrical pumps arranged in a main/standby configuration. Each engine has a duplex filter and MDO cooler. All the engines have pneumatic starters. Each engine’s protection and speed control systems are supplied from a 24V distribution board. The battery charger system is fed from the emergency 208V distribution board. The MAN protection will shut down the engine on overspeed, low lube oil pressure, High turbocharger lube oil temperature, or loss of control power.

6.4.4 Main DG Engine Support: Each cooling system consists of two individual mechanically driven pumps per engine, two coolers in parallel and cooled by seawater, and a header tank. The cooling water flow is controlled by the engine’s internal temperature control valves and will not fail on loss of compressed air. Each system has low level and high temperature alarms and the water quality is maintained by chemical dosage. Each system cools its engine’s lube oil, jacket water, generator, pre-heating system, cylinders and its MDO. The lubrication system consists of an internal sump, a mechanically driven pump, filters, cooler and control valves. The engine is equipped with a pre-lube and preheating system.

6.4.5 Main DG Start: If the MAN start permissives are met, then an engine can be started locally from the engine control panel, remotely from the ECR panel by pressing the start request button for one second. For PMS control the PMS must send a “request start/stop authority” to the SaCos system which then must close its “release start/stop authority” external.

Page 54: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 54 of 80 February 4, 2009

6.4.6 Main DG Speed Control: Engine speed controls the alternating current frequency from the driven generator. The engine speed is controlled by balancing the engine load and the fuel supply to achieve the desired speed. The engine is supplied with a Heinzmann Electronic Governor that can be controlled from the switchboard using a raise/lower switch, SYMAP can control the governor to assist in synchronization, or raise/lower contacts being closed from the power management system.

6.4.7 Main DG Synchronization Control Modes: There are two synchronization control modes. When the generator control section is placed in local synchronization to a live bus it is controlled by a common check sync relay. When the generator control section is placed in remote, the synchronization is done automatically via the SYMAP and initiated from the PMS. The synchronization relay monitors the generator frequency and the bus frequency and adjusts the bias voltage until the offline generators frequency and phase are identical to the bus. No adjustment of speed is necessary to connect to a dead bus.

6.4.8 Main DG Generators: The main generators are self exiting brushless, ten-pole, synchronous, Hyundai HSJ7 generators. All the Generators are rated at 6.6kV, 60Hz, 3phase, wye connection. They differ in kW rating as Generators 1-3 are rated at 4230kW and Generators 4-6 are rated at 3760kW. Each generator’s windings are cooled by ambient air forced by a shaft-mounted fan and cooled by the engines cooling system. The generator bearings are self-contained. The generators are protected by RTD monitored by the vessel management system and have leak detectors for alarm

6.4.9 Main DG Voltage Control: The output voltage of each generator is controlled by the voltage and current in its exciter field poles. Each generator’s excitation is controlled by a thyristor voltage regulator. It measures the output voltage and current and adjusts the field excitation to maintain the correct voltage level over the normal operating load range. The excitation unit supplies a load-dependent field current slightly higher than would be required for producing the rated voltage. The generators AVR can accept external 0-10Vdc signal for remote control of the voltage set point, this input is assumed to be used to control voltage remotely by hand at the switchboard, or by the PMS using the SYMAP protection unit.

6.4.10 Main DG Breaker Controls: The ABB 630A breaker has three main breaker contacts. It is operated by an electric motor and can be tripped by loss of voltage to the under-voltage coil or by activation of the protections in the SYMAP protection unit. Once an engine is up to speed and the generator up to voltage, the breaker can be closed if certain conditions are met; the Generator switch is in local and the sync check relay indicates the generator is in synchronization with the bus then the breaker can be closed by pushing the close push button. If a generator has been started from standby mode by the AVC then if the under-voltage coil is live and the SYMAP synchronization contacts close the generator is in synchronization with the bus and the breaker automatically closes to the bus. The breaker can be opened by placing the Generator switch to local and pressing the open button, pressing the breaker trip directly or by operation of the breaker protections.

6.4.11 Main DG Breaker Protection: Each generator is protected by its breaker’s SYMAP BC protection relay and an under-voltage relay. The SYMAP BC unit trips the breaker on overloads

Page 55: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 55 of 80 February 4, 2009

and short circuits. The protection relays monitors the incomer voltage and current. The protection relay unit provokes an under-voltage trip of the breaker if it loses 110V power, over-voltage (120% for 5s), under-voltage (<85% for 5s), over-frequency (105% for 1.5s), under-frequency (<95% for 1.5s), reverse power (10% for 5s), negative phase sequence (10% for 10 seconds) and Over-Excitation. These failures do not require resetting of the breaker at the switchboard and can be closed again after the fault clears. The following protection comes from the lockout relay which will require the breaker to be reset at the switchboard. These failures are phase over-current, generator differential protection, loss of field excitation, directional sensitive earth fault, NER protection and SYMAP failure. The generator incomer air spaces are assumed to be separated from each other and from the bus air spaces in order to avoid a short circuit bypassing all protection systems.

6.4.12 Bus tie/Interconnector breaker control: The ABB 1250A breaker has three main breaker contacts. It is operated by an electric motor and can be tripped by loss of voltage to the under-voltage coil or by activation of the protections in the SYMAP protection unit. The breaker can be closed if certain conditions are met; the Bus tie/Interconnector panel is in local and the sync check relay indicates the two buses are in synch then the breaker can be closed by pushing the close push button. If a breaker closure request has been started by the PMS, then if the under-voltage coil is live and the SYMAP synchronization contacts close, the two buses are synchronized and the breaker automatically closes to the bus. The breaker can be opened by placing the Generator switch to local and pressing the open button, pressing the breaker trip directly or by operation of the breaker protections. The bus tie must be open for DP2 operations.

6.4.13 6.6kV Switchboard: The main switchboard (MSB) was manufactured by IPT and supplied by Converteam. The 6.6kV electrical system is split into two switchboards with each switchboard divided into three sections. It utilizes an open ring main system and provides breakers to isolate each section of the board supplied by a generator. The main line is split into port and starboard sides with two 1250A breakers. A second tie line with two 1250A breakers completes the ring.

6.4.14 Transformer changeover switch: The 3-pole offload isolator switch comprising 2-off back-to back switches to achieve changeover, permits thruster 7 feeder to be fed from either the port or starboard 6.6kV switchboard. The Changeover switch is housed in a free-standing enclosure that provides manual local control and operator selected remote control change over capability. It has status indications and interlocks to prevent closure of both feeders to the transformers. In order for switching to be effective, the emergency switchboard must be fed from the stbd bus as the port steering pump must be independent of the emergency switchboard pump.

6.4.15 Ship service transformers: There are two 6.6kV to 510V 4100kVA transformers with each one being supplied from separate sides of the bus. Each transformer feeds its associated auxiliary switchboard. The transformer has two cooling fans fed from group starter panels and are cooled by the auxiliary FWC system. The generators are protected by RTD, monitored by the vessel management system and have leak detectors for alarm.

6.4.16 Auxiliary Switchboard Description: The switchboard will operate with the auxiliary tie breakers open. The Auxiliary 480V switchboard is split into two separate boards. Switchboard #1 contains 9 sections. Section A20 contains the incoming breaker from the main port transformer

Page 56: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 56 of 80 February 4, 2009

#1, controls and indications. Section A21 houses Bus A&B Tie breaker, indications and controls. Sections A22-A26 contain the outgoing feeders. Sections A27 and A28 contain port group #1 and #2 starter breaker, controls and indications. Switchboard #2 contains 9 sections. Section A29 contains the incoming breaker from the main starboard transformer #2, controls and indications. Section A30 houses Bus A&B Tie breaker, indications and controls. Sections A31-A35 contain the outgoing feeders. Sections A36 and A37 contain starboard group #1 and #2 starter breaker, controls and indications. The switchboards are connected by bus-tie breakers that feed to bus A and B. A 400A shore power connection is connected to auxiliary switchboard #2 and electrically interlocked to prevent parallel operation with the two main feeds.

6.4.17 480V Auxiliary Switchboard Distribution:

480V Port (swbd. 1) Loads 480V Stbd. (swbd 2) Bus Loads 480V Emergency Swbd Loads

T1 Pre-Charge transformer T2 Pre-Charge transformer 480V service transformer 1 cooling fan #1

T3 Pre-Charge transformer T4 Pre-Charge transformer 480V service transformer 1 cooling fan #2

T5 Pre-Charge transformer T6 Pre-Charge transformer MDO feed pump #2

Bilge/Fire Pump #3 Bilge/Fire Pump #2 MDO supply pump #1

T1 steering pump #1 T2 steering pump #1 ME (aft) SWC pump #3

T3 steering pump #1 T4 steering pump #1 E-Gen. Room supply fan

T5 steering pump #1 T6 steering pump #1 ER Aft Supply Fan

T7 steering pump #1 Incinerator T1 steering pump #2

Thruster (fwd) FWC pump #1 Thruster (aft) FWC pump #2 T2 steering pump #2

Thruster (fwd) SWC pump #1 Thruster (aft) SWC pump #2 T3 steering pump #2

Thruster (aft) FWC pump #1 Thruster (fwd) FWC pump #2 T4 steering pump #2

Thruster (aft) SWC pump #1 Thruster (fwd) SWC pump #2 T5 steering pump #2

ME (aft) SWC pump #1 ME (fwd) SWC pump #1 T6 steering pump #2

ME (aft) SWC pump #2 ME (fwd) SWC pump #2 T7 steering pump #2

T1 MV7000 Aux. Supply T2 MV7000 Aux. Supply Bilge/Fire Pump #1

T3 MV3000 Aux. Supply T4 MV3000 Aux. Supply Start Air Compressor #2

T5 MV3000 Aux. Supply T6 MV3000 Aux. Supply ME (fwd) SWC pump #3

T8 MV3000 Aux. Supply DP Control A/C (AC-2) MDO feed pump #4

Aux. cooling SWC pump #1 Aux, cooling SWC pump #2 Aux. cooling FWC pump #2

Aux. cooling FWC pump #1 Switchboard (stbd) room A/C Sprinkler SW pump

Hydrophore (F.W) module #1 Hydrophore (F.W) module #2 480V service transformer 2 cooling fan #1

AHU #3 ECR A/C (AC-3) 480V service transformer 2 cooling fan #2

Seawater Chiller pump #1 Seawater Chiller pump #2 Sliding WTD Dist. Board

Aft ER Supply Fan fwd ER Supply Fan Emergency Dist. Board #1

Start Air Compressor #1 Incinerator sludge tank Emergency Dist. Board #2

Service Air Compressor #1 Service Air Compressor #2

Service Air Compressor #3 HVAC Control Panel 2

Page 57: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 57 of 80 February 4, 2009

Fan Dist. Board #1 Fan Dist. Board #2

Fan Dist. Board #3 Fan Dist. Board #4

Heater Power Dist. Board #1 Heater Power Dist. Board #2

Oil Pumps Dist. Board #1 Oil Pumps Dist. Board #2

Oil Pumps Dist. Board #3 Oil Pumps Dist. Board #4

Power Dist. Board #1 Power Dist. Board #2

Power Dist. Board #3 Power Dist. Board #4

Group Starter 1 Group Starter 2

Power Dist. Board # 7 Power Dist. Board #7

6.4.18 480V Distribution Boards:

Fan Distribution Board 1

Fan Distribution Board 2

Power Dist. Board 1 Power Dist. Board 2

Propulsion Room Aft Port Supply Fan

Thruster Room Exhaust Fan

DG1 Power Stack DG4 Power Stack

Thruster Room Supply Fan

Pump Room/ER Workshop Exhaust Fan

DG2 Power Stack DG5 Power Stack

Pump Room Supply Fan Thruster/Pumps Room Exhaust Fan

DG3 Power Stack DG6 Power Stack

Thruster/Pumps Room Supply Fan

Propulsion Room Aft Stbd. Exhaust Fan

T1 Jensen Filter T2 Jensen Filter

Propulsion Room Aft Port Exhaust Fan

Propulsion Room Aft Stbd. Supply Fan

T3 Jensen Filter T4 Jensen Filter

T5 Jensen Filter T6 Jensen Filter

T7 Jensen Filer Bilge Water Separator

Bilge Pump #1 Bilge Pump #2

UPS #4 UPS #5

UPS #6 UPS #7

Booster Pump(Foam) #1 Booster Pump(Foam) #2

Oil Pumps Dist Board 1 Oil Pumps Dist Board 2 Oil Pumps Dist Board 3 Oil Pumps Dist Board 4

MDO Transfer Pump #1 MDO Transfer Pump #2 T1 Primary L/O Pump T2 Primary L/O Pump

L/O Separator Unit #4 L/O Separator Unit #1 T1 Secondary L/O Pump T2 Secondary L/O Pump

L/O Separator Unit #5 L/O Separator Unit #2 T3 Upper Gearbox T4 Upper Gearbox

L/O Separator Unit #6 L/O Separator Unit #3 T3 Prop. Gearbox T4 Prop. Gearbox

MDO Feed Pump #1 MDO Feed Pump #3 T5 Upper Gearbox T6 Upper Gearbox

Lube Oil Pump #1 Lube Oil Pump #2 T5 Prop. Gearbox T6 Prop. Gearbox

Sludge Lube Oil Pump #1 Sludge Lube Oil Pump #2 T7 Upper Gearbox

MDO Separator Control #1 T7 Prop. Gearbox

Group Starter 1 Power Dist Board 7

(Aux 1 feed)

Group Starter 2 Power Dist Board 7

(Aux 2 feed)

Page 58: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 58 of 80 February 4, 2009

T1 Motor Cooling Fan #1 UPS #1 T2 Motor Cooling Fan #1 UPS #2

T1 Motor Cooling Fan #2 UPS #3 T2 Motor Cooling Fan #2 Converteam deployment machine

T1 Transformer Cooling Fan #1

Tautwire Isolation Transformer 1

T2 Transformer Cooling Fan #1

Tautwire Isolation Transformer 2

T1 Transformer Cooling Fan #2

T2 Transformer Cooling Fan #2

690V Mission Transformer 1 Cooling Fan #1

690V Mission Transformer 2 Cooling Fan #1

690V Mission Transformer 1 Cooling Fan #2

690V Mission Transformer 2 Cooling Fan #2

6.4.19 EG Engine: The emergency generator’s (EG) engine is a Caterpillar 3508B with electric motor start, a mechanical fuel pump connected to a dedicated diesel day tank, self-contained forced lubrication system and a forced air radiator, providing cooling for a self-contained, forced fresh water cooling system. The engine will shut-down on over-speed, high jacket water temp., low lube oil pressure, aftercooler temp high, and high crankcase pressure.

6.4.20 Emergency Generator: The EG is a Leroy Somar LSA50.1M6 480V, 1000kW, 60Hz, 0.8PF, floating three wire, synchronous generator

6.4.21 EG Control & Protection: The emergency generator is started by the engine mode switch and normally a bus voltage relay. The engine mode switch has three settings: Off, Manual, and Auto. Normally, the ESB is supplied from an incomer breaker and the engine mode switch is in Auto. On loss of incomer power, a bus under voltage relay opens and starts after a short time delay then closes a contact used to initiate remote start of the EG. Once the generator is up to voltage and speed, and the switchboard is dead, the EG breaker closes and restores power to the ESB. Placing the engine mode switch in Manual will start the engine and allow manual operation of the breaker, if the bus is dead. Placing the engine mode switch in the off position, will stop the DG and trip its breaker.

6.4.22 ESB Description: The emergency switchboard contains four sections section A10 contains the controls, indications and breaker incomer for the emergency generator. Section A11 contains the controls, indications and main incoming breakers. Sections A12 and A13 contain the emergency outgoing feeder breakers. Emergency switchboard feed from Auxiliary switchboard 1 and 2 with auto changeover control. The emergency switchboard can be supplied 480V by either the auxiliary port or starboard switchboard. The incoming breakers are automatically controlled by a Symap control module located inside section A10. When the Symap control detects a dead bus it automatically starts the emergency generator and connects it to the emergency bus. When main power on either incomer is detected the Symap will open the EG breaker and close the incomer breaker and stop the EG after the cool down time is fulfilled. The Symap has interlock logic that prevents both the EG breaker and any incomer breaker being closed at the same time. The ESB has an on-off switch that can be used to test the EG while main power is supplying the ESB. There is an ESB mode off-on switch that is not fully defined. The assumption is that this will inhibit the auto changeover of the main incomer breakers. Surveyor to verify and define ESB

Page 59: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 59 of 80 February 4, 2009

mode function The auto changeover logic can create a fault that would cause total blackout of the vessel, so in DP2 operations the incomer breakers auto changeover circuit must be placed in manual or disabled, but still allow the EG to automatically start and connect to the bus on loss of power.

6.4.23 Emergency Distribution boards 480V & 208-120V:

480V EDB #1 480V EDB #2 208 Emergency 208 Swbd Bus A 208 Swbd Bus B

UPS #1 UPS #4 DC1 Battery Charger DC4 Battery Charger DC5 Battery Charger

UPS #2 UPS #5 DC2 Battery Charger DC6 Battery Charger DC7 Battery Charger

UPS #3 UPS #6 DC3 Battery Charger

UPS #7 DC4 Battery Charger

DC5 Battery Charger

DC6 Battery Charger

DC7 Battery Charger

EG Battery Charger #2

6.4.24 24V System Description: There are seven DC panels used to provide 24Vdc power throughout the vessel. DC 1 and 2 located on the navigational Bridge and provide power to the navigation electronics. DC 3 provides power to the phone systems. DC 4 and 5 are located in the engine room forward and provide redundant power to DG1-3. DC 4 provides backup power to T1 and T3 Lipstronic control cabinets while DC 5 provides backup power to T5 and T7 Lipstronic control cabinets. DC 6 and 7 are located in the engine room forward and provide redundant power to DG4-6. DC 6 provides backup power to T2 Lipstronic control cabinets while DC 7 provides backup power to T4 and T6 Lipstronic control cabinets. There are breakers in place to allow either DC 4 or 5 to provide power to both DC distribution panels. The same breaker configuration is provided to allow either DC 6 or 7 to provide power to both DC distribution panels. The battery chargers will generate an alarm on failure and a light is illuminated, indicating batteries are discharging. The distribution boards display voltage, current, power available indicator and ground fault.

6.4.25 Redundancy: 6.6kV, 480V auxiliary and emergency switchboard bus ties are open. This is vital to vessel redundancy

Page 60: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 60 of 80 February 4, 2009

6.5 Electric Power FMEA Table

# Failure Effect Indication DP Effect Distribution

1a Port 6.6kV MSB Dead.

Loss of all T1, T8, T3, T5. Auxiliary SB #1 and associated equipment. T7 will automatically change over to Starboard bus.

Vessel alarms. DP UPS alarm. T1, T8, T3, T5 not ready alarm on DP. T7 power changes to starboard MSB

No loss of heading or position. Remaining thrusters compensate. Loss of T1, T3, T5, T8.

1b Stbd. 6.6kV MSB Dead.

Loss of all T2, T6, T4 Auxiliary SB #2 and associated equipment. Loss of ESB.

Vessel alarms. DP UPS alarm. T2, T4, T6 not ready alarm on DP

No loss of heading or position. Remaining thrusters compensate. Loss of T2, T4, T6.

1c ESB Dead Loss of some redundant services, some systems on battery power and loss of some ventilation.

Vessel alarms. DP UPS alarm. Loss of some lights.

No loss of heading or position.

1d Port Main 6.6kV/480V transformer fault

Loss of all T1, T8, T3, T5. Auxiliary SB #1 and associated equipment. T7 will automatically change over to Starboard bus.

Vessel alarms. DP UPS alarm. T1, T8, T3, T5 not ready alarm on DP. T7 power changes to starboard MSB

No loss of heading or position. Remaining thrusters compensate. Loss of T1, T3, T5, T8.

1e Stbd. Main 6.6kV/480V transformer fault

Loss of all T2, T6, T4 Auxiliary SB #2 and associated equipment. Loss of ESB.

Vessel alarms. DP UPS alarm. T2, T4, T6 not ready alarm on DP

No loss of heading or position. Remaining thrusters compensate. Loss of T2, T4, T6.

1f ESB incomer auto change over (electric lock) failure. Info only. Invalid configuration. See Section 6.6.1

Both port and starboard switchboards will supply power to the emergency switchboard. Two different sources of power without common reference could cause blackout and loss of DP

Loss of ESB and possible loss of auxiliary port and starboard switchboard and loss of all thrusters.

Information Only

SPF: Loss of heading and position do to loss of all thrusters. Invalid configuration. See Section 6.6.1

1g Emergency 480/208V transformer fault

Auto changeover to secondary supply.

Vessel alarms. No immediate effect.

1h Loss of battery charger supply.

Battery system maintains load for minimum of 30 minutes.

Vessel alarms No immediate effect on position keeping.

6.6 Summary of Electric Power System Analysis

6.6.1 Significant failure modes: The electric power system failure modes and effects analysis table found no single point failures and no DPO intervention failures if the equipment is properly configured, but it did note two configuration errors that can cause vulnerability to loss of DP.

Page 61: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 61 of 80 February 4, 2009

Failure 1f – Has the potential to allow two different 480V power sources to be combined causing catastrophic failures if device protections are not correctly set. Failure 1d can be avoided if at least one of the source breakers is open this is normally done with a mechanical interlock. Emergency 480V switchboard automatic switching presents threat to redundancy because it is capable of transferring fault to both switchboards. If a short or other fault occurs in the emergency switchboard or switching mechanism the feeder breaker protection must be reliably capable of tripping before the voltage dip on the main switchboard bus causes loss of other equipment because the switch will transfer the fault to the second switchboard bus upon loss of the first supply. This must be proved by engineering calculation or by testing during trials.

6.6.2 Hidden Failures: The analysis identified some failures that could reduce system redundancy. These failures can be avoided by regular testing, calibration and maintenance.

6.6.3 Configuration Analysis: The main switchboard and Auxiliary switchboard must be run split bus. Port switchboard 110Vdc control voltage must be supplied by Converteam battery charger 1 while starboard switchboard 110Vdc control voltage must be supplied by Converteam battery charger 2. The emergency switchboard must be normally fed from starboard power to ensure T7 redundancy. Auxiliary switchboard #2 CB Q103 to the emergency switchboard is to be closed and Auxiliary switchboard #1 CB Q3 to the emergency switchboard is to be open. This disables the automatic changeover circuit, but still allows the EG to auto start and connect to the bus

6.6.4 Related Failures: These DGs can be affected by fuel system, fire protection and Engine Room ventilation shutdown faults. These failures are examined in the appropriate sections.

6.6.5 Worst Case Failure: port bus Blackout this failure causes loss of T1, T3, T5, T8 and temporary reduction in thrust available until T7 incoming power has been changed to starboard side.

6.6.6 Accuracy: The analysis is based on Converteam and shipyard drawings but the provided drawings conflicted with each other and have not yet been confirmed by survey or testing. Surveyor is to confirm final implementation of the T7 auto change over circuit, confirm where 24Vdc DB4-7 incoming power comes from conflicting information received based on Keppel Singmarine drawing H340-E101.01 Rev. 4 and verify fan and oil distribution board loads. Surveyor is to update documentation as necessary based on findings.

6.6.7 Electric Power Summary:

Single Point Failures 0

DPO Intervention 0

Maintenance Issues -

Analysis Accuracy Medium

Page 62: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 62 of 80 February 4, 2009

7. POWER & VESSEL MANAGEMENT SYSTEM

7.1 Power and Vessel Management System Diagram

FWD. WH

AFT WHECR

WS13(AVC)

WS14(AVC)

CCO8(VMS B)

FS18(T8)

FS17(T7)

FS16(T6)

FS15(T5)

FS14(T4)

FS13(T3)

FS12(T2)

FS11(T1)

A & E Printer

WS11(AVC)

WS12(AVC)

FS01SWBD

1

FS02SWBD

2

NS02(Net B)

NS06(Net B)

NS04(Net B)

NS01(Net A)

NS05(Net A)

NS03(Net A)

A & E Printer

CCO7(PMS B)

A & E Printer

CCO6(VMS A)

CCO5(PMS A)

FS07

FS03(DG1-3)

FS04(DG4-6)

FS05 FS06 FS08 FS09 FS10

LegendNet A

Net B

Serial (RS232)

7.2 Power and Vessel Management System Data

Supplier: Converteam

Design: PLC based vessel and power management system

VMS Functions: Monitors major systems such as power generation, thrusters, tank levels and support systems. Controls some field equipment.

PMS Subsystem: Monitors and controls power generation system. Provides load dependant start/stop, start inhibits, load reduction and limited blackout restart.

Redundancy: Some hardware and communication systems duplicated.

Other:

Sources: Converteam Functional Specification 2007

7.3 Power & Vessel Management System Description

7.3.1 Redundancy Concept: Minimum 2 split for important functions with hardware and software protections.

Page 63: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 63 of 80 February 4, 2009

7.3.2 Overview: The vessel management was supplied by Converteam. It is a PLC based vessel and power management system. The system consists of four control computers, four work stations, ten field stations dedicated to vessel management and eight thruster field stations shared with the DP/IJS systems. These devices are connected by a dual star Ethernet network. Fault immunity of this vital network is discussed under DP.

7.3.3 Location: The Navigation Bridge has one operator workstation with an alarm and event printer. The Aft Bridge has two system control computers and one operator workstation with an alarm and event printer. The ECR has two system control computers and two operator workstations with one alarm and event printer. The field stations are located near the equipment they monitor and control.

7.3.4 Workstations: The workstations have a number of operator mimic screens that allow the operator to monitor system operation and initiate system changes. Each workstation can control the system, but only one workstation can have control of the system at a time. Control of the systems can be transferred between the workstation and if a controlling workstation fails, control can be assumed at the remaining workstation. The workstations are monitored by self-diagnostic routines and have automatic shutdowns to prevent major control errors.

7.3.5 Vessel Management Control Computers: One control computer is in command at a time and it performs the active control functions of the vessel management system. The standby control computer monitors the commanding control computer so it is ready to take command. The control computers are monitored by self-diagnostic routines and have automatic shutdowns to prevent major control errors. If the control computer in command fails, the standby control computer assumes command.

7.3.6 Power Management Control Computers: One control computer is in command at a time and it performs the active control functions of the power management system. The standby control computer monitors the commanding control computer so it is ready to take command. The control computers are monitored by self-diagnostic routines and have automatic shutdowns to prevent major control errors. If the control computer in command fails, the standby control computer assumes command.

7.3.7 Field Stations: The field stations provide the monitoring and control interface to the field equipment. Important redundant services are split between separate field stations. Field station outputs are designed to be failsafe. The channels are electrically separate to prevent propagation of field voltages or grounds to other devices. Failure of a status signal is arranged to create an alarm by using normally closed contacts for healthy states. The control computers are monitored by self-diagnostic routines and have automatic shutdowns to prevent major control errors. The interface of the thruster control and monitoring field stations is summarized in the appropriate thruster section.

7.3.8 VMS Functions: The system is used to remotely start and stop pumps, thrusters, open and close valves, monitor equipment status, tank levels and generate plant alarms. The system interfaces with the watch call panels.

Page 64: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 64 of 80 February 4, 2009

7.3.9 PMS Functions: The system is used to remotely start and stop generators, initiate the synchronization of generators and main bus ties, plus close major breakers and provide power information to DP for its power limiting function. The power management system is capable of supporting split or common bus operation, but split bus is required for power redundancy. The power management system will eliminate and replace failing DGs and start extra DGs based on the load levels required to maintain system redundancy. The PMS has a blackout restart function that, on detection of a dead bus, opens the bus tie and restarts or reconnects generators, attempts to close the bus tie sections and starts thrusters that were online prior to blackout. The following table summarizes the major power management functions:

Power Management System Functions

Standby Selection

Operator selects available, healthy DGs and sets their start priority. If a high priority DG fails to start, the next DG in priority is started. The operator also selects DG stop priorities but a DG that is already unloading has priority.

Load Dependant Start

The next standby main DG is started and synced if spinning reserve drops below operator set point (default =3760kW or 2820kVAR) Low spinning reserve alarm for a bus section in which these conditions persist.

Load Dependent Stop

If the spinning reserve becomes excessive, the last DG started will be unloaded and stopped after a time delay. (default =10575kW or 7935kVAR) Excessive capacity alarm for a bus section in which these conditions persist

Minimum # of DG

Operator selected value that will override load dependant stop and start DGs to match selected number if there is no excess capacity. Otherwise, the operator must start the excess DG.

Fixed Target If enough load is available operator can set individual DGs to maintain constant kW or kVAR.

De-rating Allows the operator to reduce the full load rating of individual DGs

DG replacement If an online DG is unhealthy (hi temp, lo press, etc) and a standby is available, the system will start and sync the stand by and then unload and stop the unhealthy DG.

DG trip A DGs breaker tripped on very high bearing or winding temperature

Load Sharing kW load sharing and kVAR load sharing.

Blackout Recovery

On Complete 6.6kV bus power failure, the system sends command to open all bus tie and thruster breakers after receiving signal that the emergency bus has been restored it; starts main DGs and loads them on the bus. After a DG is on the bus it then closes all bus tie breakers in a pre-defined order, once the main 6.6kV and the Auxiliary 480V switchboards are restored, the system then starts all thrusters that were running prior to blackout. The “blackout restart in progress” signals will timeout after seven minutes. The operator will be responsible for restoring any loads that failed to start.

7.3.10 Load Limitation: This is preformed by the DP system based on bus rather than DG overload. Low bus frequency triggers VSD torque reduction.

7.3.11 Power & Vessel Management System FMEA Table:

# Failure Effect Indication DP Effect Control Computers

1a In command

control computer failed

Control transfers to standby control computer

VMS alarm. No immediate effect on

DP.

Page 65: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 65 of 80 February 4, 2009

# Failure Effect Indication DP Effect

1b Standby control computer failed

Loss of system backup VMS alarm. No immediate effect on

DP.

Workstations

2a Workstation

failed

Control transfers or can be assumed at a

remaining workstation. VMS alarm.

No immediate effect on DP.

2b Workstation monitor fails

Control can be assumed at a remaining workstation

Blank or frozen screen. No alarm.

No immediate effect on DP.

2c Workstation

operator inputs failed

System display still useful Control can be assumed at a remaining workstation

Possibly no alarm. Failure only apparent after system

does not respond.

No immediate effect on DP.

2d Workstation

frozen

Display frozen, inputs useless & internal diagnostics frozen.

Control can be assumed at a remaining workstation

Possible Ethernet alarms. No immediate effect on

DP.

2e Workstation malfunction

Internal error checking shuts down workstation.

Control can be assumed at a remaining workstation

VMS alarms No immediate effect on

DP.

Ethernet

3a One link failed Problem detected.

Communication continues on redundant link.

VMS alarm for failed link. No immediate effect on

DP.

3b Ethernet switch

failed

Shutdown on internal fault detection or loss of power. Communication continues on remaining

Ethernet switch.

VMS alarms for failed network.

No immediate effect on DP.

3c Workstation broadcasting

noise

Problem detected. Workstation isolated from

both networks.

VMS alarms for both workstation links.

No immediate effect on DP.

3d

Control computer

broadcasting noise

Problem detected. Control computer isolated

from both networks.

VMS alarms for both CC links.

No immediate effect on DP.

3e Field station broadcasting

noise

Problem detected. FS isolated from both

networks. Loss of that FS control and monitoring

interface. Engineers must locally control some

systems.

VMS alarms for both FS links.

No immediate effect on DP. Hidden failures more

likely to occur. Duty engineers must be more

vigilant.

3f Data overload

Both networks shutdown by excessive data load. Engineers must locally

control and monitor systems.

VMS alarms for both networks.

No immediate effect on DP. Hidden failures more

likely to occur. Duty engineers must be more

vigilant.

Page 66: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 66 of 80 February 4, 2009

# Failure Effect Indication DP Effect Field Station

4a One Field

station failed

Loss of that FS control and monitoring interface. Engineers must locally control some systems.

VMS alarms for both FS links.

No immediate effect on DP. Hidden failures more

likely to occur. Duty engineers must be more

vigilant.

4b One FS

processor malfunctions

Internal error checking routines detect fault and shutdown one processor. Engineers must locally control some systems.

VMS alarms for both FS links.

No immediate effect on DP. Hidden failures more

likely to occur. Duty engineers must be more

vigilant.

4c Serial input fails Loss of DG or breaker

information to FS. Loss of monitored data

VMS alarm serial link failed alarm.

No immediate effect on DP. Hidden failures more

likely to occur. Duty engineers must be more

vigilant.

4d Loss of digital

input

Loss of valid information for alarm point due to

device, contact or wiring fault.

Alarm for open DI. None for shorted DI. Regular

testing needed to catch all faults.

No immediate effect on DP. Hidden failure

possible but less likely.

4e Loss of digital

output Loss of control output.

No alarm until command fails. Regular testing

needed to catch all faults.

No immediate effect on DP. Hidden & compound

failures more likely to occur.

4f Loss of

analogue input Loss of process data. VMS alarm.

No immediate effect on DP.

7.4 Summary of Power & Vessel Management System Analysis

7.4.1 Significant Failure Modes: None. Regular maintenance should ensure continued operation.

7.4.2 Hidden Failures: The analysis identified possible hidden failures that could reduce system efficiency or redundancy. These failures can be avoided by regular testing, calibration and maintenance.

Failure Problem Solution

Digital Input shorted Possible inaccurate plant conditions seen by Operator

Regular testing

Digital Output failed Loss of remote control to vessel equipment will not be noticed until operator tries to operate equipment

Regular testing

7.4.3 Configuration Analysis: Redundant.

7.4.4 Related Failures: This system can be affected by switchboard failures.

7.4.5 Worst Case Failure: Shorted voltage decrease signals to AVR will cause engine to shed reactive load and enter capacitive operation. Current increases while bus voltage decreases as paralleled

Page 67: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 67 of 80 February 4, 2009

DG is forced down its droop curve. Both DGs may be tripped on UV or the healthy DG tripped on over-current and then the faulty DG on under-voltage. Possible equipment damage if left for extended period

7.4.6 Accuracy: The analysis is based on the referenced documentation. The analysis and the information it is based on has not yet been confirmed by survey and testing on the vessel.

7.4.7 PMS/VMS System Summary:

Single Point Failures 0

DPO Intervention Required 0

Maintenance Issues 2

Analysis Reliability Medium

Page 68: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 68 of 80 February 4, 2009

8. AUXILIARY SUPPORT SYSTEMS

8.1 Diesel Fuel Oil System

8.1.1 System Diagram:

DBO MDO 7 PS

PS Overflow

Tank

DBO MDO 6 PS

DBO MDO 5 PS

DBO MDO 4 PS

DBO MDO 7 SB

DBO MDO 6 SB

DBO MDO 5 SB

DBO MDO 4 SB

MDO Transfer

MDO Transfer

Bunker Stations

SB Overflow

Tank

NC

NC

NC

PS MDO Settling Tank Aft

SB MDO Settling

Tank Fwd

F/O Seperator

F/O Seperator

NC NC NC

PS MDO Day Tank

Aft

SB MDO Day Tank

fwd

MDO Service

MDO Service

MDO Service

MDO Service

DG1

DG2

DG3

DG4

DG5

DG6

General Diagram not all valves and filters are shown refer to dwg. H340-

P110 for more details

LegendTransferServiceOverflow

NC

EGEG Day

Tank

MD

O S

up

ply

8.1.2 Redundancy Concept: 2 split Engine Room system supplied by common storage system. Redundancy depends on proper fuel handling procedures.

8.1.3 System Description: Each diesel engine runs on marine diesel oil. The Aft Engine Room contains the port side settling and day tanks, two service pumps configured in an automatic primary/secondary configuration that normally supply MDO to DGs 1-3. The forward Engine Room contains the starboard side settling and day tanks, two service pumps configured in an automatic primary/secondary configuration that normally supply MDO to DGs 4-6. The fuel oil supply and return piping is normally arranged in an independent split configuration in an emergency the system can be aligned to supply MDO to all DGs from the same tank. The fuel is transferred from the settling tank to the day tank through the MDO separator. Both the day tank and the settling tanks content can be re-circulated through the separator. The suction valves for the settling and day tanks are pneumatically operated. Each day tank is provided with a high and low level alarm but should be regularly checked by the Engineering Watch. It is assumed that the fuel in the tanks is regularly checked for biological, water and particulate contamination. The fuel oil transfer pumps are started and stopped based on the level alarm switches in the settling tanks. The transfer pumps can be remotely started and stopped from the automation system. The settling tanks are filled automatically via the vessel fuel oil transfer system that consists of eight dedicated fuel storage tanks, two transfer pumps with each one aligned to an individual settling tank with ability to cross connect. All the starboard side tanks vent to the starboard side overflow tank and all the port side tanks vent to the port side overflow tank. Both

Page 69: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 69 of 80 February 4, 2009

overflow tanks have high level alarms. The emergency day tank is filled via a dedicated pump from the PS Aft day tank.

8.1.4 Survivability: If the fuel system is isolated properly then any single systems total fuel failure will result in no worse than the vessels worst case failure

8.1.5 FO FMEA Table:

# Fault System Effect Indication DP Effect

01 PS Aft Day Tank

empty due to rupture or leak

Loss of fuel supply to DG1-3. eventual loss of MSB bus A. Loss of T1,

T3, T5, T8

VMS day tank level indication, day tank low

level alarm, low FO pressure alarm, bilge

high level alarms

No immediate loss of heading or position. System compensates

with remaining thrusters

02 Liquid

contamination in PS Aft Day Tank

Liquid contamination passed to DG1-3.

Engines may run rough or fail depending on the

type and level of contamination

Visual indication at day tank site glass.

Possible DG1-DG3 failed or generator

tripped alarms

No immediate loss of heading or position.

If thrusters lost then system compensates

with remaining thrusters

03 Particle

contamination in PS Aft Day Tank

Particle contamination stopped by system

automatic filer and/or engine filters. Filter

clogs if contamination is excessive. Possible loss of engines but unlikely.

Low fuel pressure alarm. High filter differential

pressure alarm

No loss of heading or position.

04 PS Aft Day Tank

suction clog

Loss of fuel supply to DG1-3. eventual loss of MSB bus A. Loss of T1,

T3, T5, T8

Low fuel pressure alarm.

No immediate loss of heading or position. System compensates

with remaining thrusters

06 PS Aft Day Tank supply line clog

Loss of fuel supply to DG1-3. eventual loss of MSB bus A. Loss of T1,

T3, T5, T8

Low fuel pressure alarm

No immediate loss of heading or position. System compensates

with remaining thrusters

07 Port return line clogs/blocked

Returning fuel creates a back pressure and fails

DG1-3. eventual loss of MSB bus A. Loss of T1,

T3, T5, T8

VMS high FO pressure indication.

No immediate loss of heading or position. System compensates

with remaining thrusters

08 MDO feed pump

fault

Standby pump starts and provides fuel to

generators.

Standby pump start event, loss of Primary

pump alarm.

No immediate loss of heading or position.

09 SB Fwd. Day Tank

empty due to rupture or leak

Loss of fuel supply to DG4-6. eventual loss of MSB bus A. Loss of T2,

T4, T6,

VMS day tank level indication, day tank low

level alarm, low FO pressure alarm, bilge

high level alarms

No immediate loss of heading or position. System compensates

with remaining thrusters

Page 70: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 70 of 80 February 4, 2009

# Fault System Effect Indication DP Effect

10 Liquid

contamination in SB Fwd. Day Tank

Liquid contamination passed to DG4-6.

Engines may run rough or fail depending on the

type and level of contamination

Visual indication at day tank site glass.

Possible DG4-DG6 failed or generator

tripped alarms

No immediate loss of heading or position.

If thrusters lost then system compensates

with remaining thrusters

11 Particle

contamination in SB Fwd. Day Tank

Particle contamination stopped by system

automatic filer and/or engine filters. Filter

clogs if contamination is excessive. Possible loss of engines but unlikely.

Low fuel pressure alarm. High filter differential

pressure alarm

No loss of heading or position.

12 SB Fwd Day Tank

suction clog

Loss of fuel supply to DG4-6. eventual loss of MSB bus A. Loss of T2,

T4, T6

Low fuel pressure alarm.

No immediate loss of heading or position. System compensates

with remaining thrusters

13 SB Fwd Day Tank

supply line clog

Loss of fuel supply to DG4-6. eventual loss of MSB bus A. Loss of T2,

T4, T6

Low fuel pressure alarm

No immediate loss of heading or position. System compensates

with remaining thrusters

14 Port return line clogs/blocked

Returning fuel creates a back pressure and fails

DG4-6. eventual loss of MSB bus A. Loss of T2,

T4, T6

VMS high FO pressure indication.

No immediate loss of heading or position. System compensates

with remaining thrusters

16 EG fuel fault Emergency generators not available as backup

power source.

EG low fuel day tank alarm

EG low fuel pressure alarm

No loss of heading or position.

17 FO transfer system pump, separator or

valve failure.

2 transfer pumps & 2 separators. 24 hour

supply of fuel available from the day & service tanks. Day and service

tanks should be kept topped up to ensure fuel

availability.

VMS Alarms No loss of heading or

position.

18 FO Storage Tanks

Contamination

Contamination transferred to day tanks unless run through the

purifiers.

None

No loss of vessel control or safety if only one day

tank is filled at a time and then left to run

several hours before the second tank is filled.

8.1.6 Summary of Analysis Results: No single point failures will result in loss of DP. Loss of a fuel line or tank can be avoided by maintaining the tank, pipes and hoses and not moving heavy equipment or performing hot work nearby while under way or dynamically holding position.

Page 71: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 71 of 80 February 4, 2009

Contamination can be avoided by using the separators and performing regular testing. Un-alarmed failures such as closed valve, a clog in the emergency generator fuel line, clog in a return line or failed level alarm should be detected during regular watch keeping and testing. The fuel oil system must normally be operated split to maintain redundancy. Analysis is based on Kepper Marine Drawing H340-P110-1 Rev. 2 MDO Service & Supply Service system but has not yet been confirmed by survey and testing of the vessel.

8.2 Lubricating Oil Systems

8.2.1 System Description: Each thruster and engine has a self-contained, lube oil system. A clean oil distribution system and dirty lube oil system exist to ease oil changing and pollution control but each system is normally isolated during DP operation. Each system’s lubrication is described and analyzed in the appropriate power or thruster sections.

8.3 Hydraulic Oil Systems

8.3.1 System Description: Each thruster has a self-contained, hydraulic actuating system. These systems are described and analyzed in the appropriate thruster sections.

Page 72: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 72 of 80 February 4, 2009

8.4 Cooling Water Systems

8.4.1 System Diagram:

Port seachest

(high)Port SW Pump 1

Cooler

Fwd FWC pump 1

Fwd FWC pump 2

Stbd.Seachest

(Low)

This is only a representative drawing

of the system. For further information

please refer to Vessel As-Built Drawings

Stbd SW Pump 1

Stbd SW Pump 2

Stbd SW Pump 3

Exp. tank

DG4

DG5

DG6

Cooler

Cooler

Exp. tank

DG1

DG2

DG3

Cooler

Overboard

Overboard

Port SW Pump 2

Port SW Pump 3

Fwd Thrusters SW Pump 1

Fwd Thrusters SW Pump 2

Aft Thrusters SW Pump 1

Aft Thrusters SW Pump 2

Exp. tank

Exp. tank

Cooler

Cooler

Overboard

Cooler

Cooler

Overboard

Aft FWC pump 1

Aft FWC pump 2

T5 VSD

T5 Transformer

T5 Hyd. Cooler

T5 LO Cooler

T5 Motor

T6 VSD

T6 Transformer

T6 Hyd. Cooler

T6 LO Cooler

T6 Motor

T7 VSD

T7 Transformer

T7 Hyd. Cooler

T7 LO Cooler

T7 Motor

T8 VSD

T8 Motor

T3 VSD

T3 Transformer

T3 Hyd. Cooler

T3 LO Cooler

T3 Motor

T4 VSD

T4 Transformer

T4 Hyd. Cooler

T4 LO Cooler

T4 Motor

T1 VSD

T1 Transformer

T1 Hyd. Cooler

T1 LO Cooler

T1 Motor

T2 VSD

T2 Motor

T2 Transformer

T2 Hyd. Cooler

T2 LO Cooler

Refer to Section 6.4.16 of this document for pump power distribution

Aux. SW Pump 1

Aux. SW Pump 2

Exp. tank

Cooler

Cooler

Overboard

Aux FWC pump 1

Aux FWC pump 2

Main SBDs

Aux SBDs

Aux Xfrmrs

Main Xfrmrs

Air compressors

Page 73: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 73 of 80 February 4, 2009

8.4.2 Redundancy Concept: 2 split sea chests, coolers, pumps and FWC systems, but common piping. Redundancy is dependent on maintaining equipment condition.

8.4.3 ME SWC System Description: The seawater cooling system suction piping is common and receives seawater from both a high suction sea chest on the port side and the low suction sea chest on the starboard side. There are a total of six pumps and their outputs are split into two groups of three. One set of pumps provides cooling for diesel generators 1-3 while the second set provides cooling for diesel generators 4-6. Two of the pumps that feed DG 4-6 are fed from auxiliary switchboard port section. Two of the pumps that feed DG 1-3 are fed from auxiliary switchboard starboard section. Two pumps (one from each set) are fed from the emergency switchboard. Two out of three pumps per set are required to run to permit sufficient cooling; the third one is in standby and will start automatically on loss of system pressure or pump failure. The system provides two coolers per set piped for parallel operation. The system has cross connects that are normally closed.

8.4.4 Auxiliary Cooling System Description: The auxiliary FWC system consists of a head tank, two electric pumps that supply cooling to transformers, the 6.6kV and 480V switchboard, air compressors and two auxiliary coolers piped in parallel and cooled by the auxiliary SWC system. The auxiliary seawater cooling provides cooling to the auxiliary FWC system via two electric pumps that receive their suction from a sea chest and are arranged in a primary/standby configuration.

8.4.5 Thruster Cooling System Description: The thruster FWC system consists of two separate systems. The aft system provides cooling for thrusters 1-4 while the fwd system provides cooling for thrusters 5-8. Each system consists of a header tank, two pumps arranged in a primary/standby configuration fed from different sources. Pump #1 of both systems is fed from the auxiliary switchboard port side and Pump #2 of both systems is fed from the auxiliary switchboard starboard side. The thruster SWC system arrangement is similar thruster FWC system and provides cooling to the thruster FWC system.

8.4.6 Cooling Systems FMEA Table:

# Fault System Effect Indication DP Effect

01 Port Main SWC

Pump Failure Standby Pump starts on

pressure drop

VMS Event Main Port SWC Standby Pump

started. Possible Low pressure alarm.

No immediate effect on DP

02 Stbd. Main SWC

Pump Failure Standby Pump starts on

pressure drop

VMS Event Main Stbd. SWC Standby Pump

started. Possible Low pressure alarm.

No immediate effect on DP

03 Fwd SWC Pump

Failure Standby Pump starts on

pressure drop

VMS Event Fwd SWC Standby Pump started. Possible Low pressure

alarm.

No immediate effect on DP

04 Aft SWC Pump

Failure Standby Pump starts on

pressure drop

VMS Event Aft SWC Standby Pump started. Possible Low pressure

No immediate effect on DP

Page 74: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 74 of 80 February 4, 2009

# Fault System Effect Indication DP Effect alarm.

05 Aux SWC Pump

Failure Standby Pump starts on

pressure drop

VMS Event Aux SWC Standby Pump started. Possible Low pressure

alarm.

No immediate effect on DP

06 Fwd FWC Pump

Failure Standby Pump starts on

pressure drop

VMS Event Fwd FWC Standby Pump started. Possible Low pressure

alarm.

No immediate effect on DP

07 Aft FWC Pump

Failure Standby Pump starts on

pressure drop

VMS Event Aft FWC Standby Pump started. Possible Low pressure

alarm.

No immediate effect on DP

08 Aux FWC Pump

Failure Standby Pump starts on

pressure drop

VMS Event Aux FWC Standby Pump started. Possible Low pressure

alarm.

No immediate effect on DP

8.4.7 Summary of Analysis Results: No single point failures will result in loss of DP. Loss of a supply line or clogged pipe can be avoided by maintaining the pipes and not moving heavy equipment or performing hot work nearby while under way or dynamically holding position. Analysis is based on Keppe Marine drawings H340-P104-01 Rev. 1 ME Cooling System, H340-P105-02 Rev. 2 Auxiliaries Cooling system, and H340-P105-01 Rev.0 Thrusters FW Cooling System but has not yet been confirmed by survey and testing of the vessel.

Page 75: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 75 of 80 February 4, 2009

8.5 Compressed Air Systems

8.5.1 Compressed Air Diagram:

Air Receiver 1

M

Air Receiver 2

M

Start Air 1 Port Aux

SBD 480V

Start Air 2 ESBD 480V

435psi

435psi

Air Receiver 3

Air Receiver 4

DG1

DG2

DG3

DG4

DG6

DG5

NC

MM

Service Air 1 Port Aux. SBD 480V

Service Air 2 Stbd. Aux. SBD 480V

230psi

230psi

Air Receiver 1

Air Receiver 2

T1

T4

T5

T6 T8

T3

T2

T7 Port Seachest

Stbd. Seachest

LO Purifiers

Oily Water Seperator

FO Purifiers

Bilge System

QCV

Ship Services

Sprinkler system

Representative Drawing Only for further information refer to vessel

Start and Service Air drawings

M

Service Air 3 Port Aux. SBD 480V

230psi

To Tensioner Service Air

8.5.2 Start Air System Description: Two commonly piped start air compressors supply air to four independent, isolatable, receivers split by cross connect valves. Two receivers provide air to diesel generators 1-3 and the other two provide air to diesel generators 4-6. Compressor 1 is powered form the Auxiliary switchboard and Compressor 2 is fed from the emergency switchboard.

8.5.3 Service Air System Description: Two commonly piped rotary compressors with water separators supply air to two service air receivers which are passed through an air dryer before supplying

Page 76: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 76 of 80 February 4, 2009

service air to the thrusters shaft brakes, LO head tank pressure, and quick connect clutches. A third service compressor is mainly used for the tensioner system but can supply air to the two service air compressors. The compressors are powered from different sources.

8.5.4 Compressed Air FMEA Table:

# Fault Effect Indication DP Effect

1 Start Air Compressor Failure

Other compressor takes load. Alarm No immediate effect on DP.

2 Service Air Compressor Failure

Other compressor takes load. Alarm No immediate effect on DP.

3 Loss of Port Start Air Backbone

Loss of Air pressure to DG1-3. Loss of pressure to stop engines, reduced load control stability on

No Immediate Effects. Low pressure alarms.

No immediate effect on DP.

4 Loss of Starboard Start Air Backbone

Loss of Air pressure to DG4-6. Loss of pressure to stop engines, reduced load control stability on

No Immediate Effects. Low pressure alarms.

No immediate effect on DP.

5 Loss of Service Air Backbone

Loss of Air Receiver pressure. Loss of clutch pressure to thrusters T3-T7. Lose of Brake Pressure to T1-T7

No Immediate Effects. Low clutch pressure alarms T3-T7

No immediate effect on DP.

8.5.5 Summary of Analysis Results: Lose of start air will have minimal effect on running generator. Analysis done using Keppe Marine drawings H340-P108-01 Rev. 0 Compressed Air Diagram (Starting Air) and H340-P108-02 Rev. 0 Compressed Air Diagram ( Service and Instrument Air) but has not yet been confirmed by survey and testing of the vessel.

8.6 Fire Protection Systems

8.6.1 Fire Alarm System: A T2000 fire alarm system is installed and appears to provide adequate smoke and heat detectors using two different loops. The system has a main control panel located on the Navigation Bridge and a repeater station located in the ECR. The fire alarm system receives main 220V power from the port main switchboard. The main panel has a 24Vdc battery backup and the alarm relay box has a 24Vdc backup supply from DC1. The system has outputs that go to the vessels VDR, alarm and monitoring system, and the general alarm. There are activation buttons located throughout the vessel including critical machinery spaces and control rooms.

Page 77: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 77 of 80 February 4, 2009

8.6.2 Water Mist System Description: The system is a medium-pressure water system that protects the main engines, fuel oil purifier and incinerator. The system can be activated automatically, locally or manually from remote locations. The System can automatically be started if the detection cabinet located in the fire control room receives either a smoke or fire alarm from one of the zones it covers. The system can be activated manually from the main control cabinet located in the fire control room or from remote panels located near equipment. System status indicator panels are located on the bridge and in the ECR. System uses 115V from ESBD5 and backup 24Vdc from DC3.

8.6.3 CO2 System Description: The CO2 flooding system protects the forward and aft engine rooms, port and starboard aft propulsion rooms, emergency generator room, paint store and the incinerator room. CO2 flooding system can be manually triggered from either the fire control room or locally from inside the protected space. Activation initiated by operator manually opening releases activation canister valves. When any release cabinet door is opened a siren sounds in the space. When the main ball valve is opened a normally closed contact opens shutting down ventilation to the space. The system alarms are powered from either 24Vdc from DC1 or DC2 via a changeover switch. The fire dampers are controlled manually from the shutoff damper control panel assumed to be located in the fire control room or the ECR.

8.6.4 FMEA Table: No single point failures.

8.6.5 Summary of Analysis Results: The systems should be fully tested and witnessed by ABS surveyor prior to DP trials.

8.7 Emergency Shutdown Systems

8.7.1 Emergency Stops Description: Emergency stops are provided at each controlling station and locally for each generator and thruster. Wire break of emergency stop circuits associated with thruster VSD will not stop the drive and instead produce an alarm indicating a wire break. E-stops should be checked regularly for proper contact operation.

8.7.2 Emergency Shutdown Systems Summary: The emergency shutdown system is composed of 7 separate groups. All groups except for Group 4 can be remotely stopped from the ECR, fire control room, or bridge. Group four is activated from the galley. All the contacts are normally open and it is assumed they are protected from accidental operation.

Group 1 Group 1F Group 1A Group 2P Group 2S Group 3 Group 4

Non vital fans on DB #1

Tunnel thruster RM supply fan

Propulsion RM aft port supply

and exhaust fans

ODB #1 ODB #2 Fan DB #3 Galley Equipment

Non vital fans on DB #2

ER fwd Supply Fans

Propulsion RM fwd port supply and exhaust fans

EPDB #3 EPDB #3 Fan DB #5

Pump RM supply fan Thruster RM stbd. supply fan

ER aft Supply Fans

Stbd. SBD RM AC

Fwd thruster RM supply fan

Thruster/pump RM aft supply fan

DP Control RM AC

Air Handling Units

Page 78: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 78 of 80 February 4, 2009

8.7.3 QCV Description: The QCV are air operated and normally de-pressurized. Air supplied from a manifold inside a control panel will close the valve.

8.7.4 FMEA Table: Each function has two failure modes – a wire short causing the shutdown to function and an open, causing a wire break alarm at the vessels alarm and monitoring system operator station. An ESD control power short can cause unnecessary loss of an engine unless there is correct breaker coordination.

8.7.5 Summary of Analysis Results: One single point Failure and no DPO interventions. This analysis is based on drawing Keppel Singmarine Fans and Pumps emergency stop system H340-E612.01 Rev. 2 but has not yet been confirmed by survey/testing of this vessel.

8.8 HVAC Systems

8.8.1 System Description: All critical machinery spaces appear to have sufficient ventilation. The ECR and switchboard rooms have redundant air conditioning supplied from different sources. High equipment temperatures can have unpredictable effects on electronic control equipment so if ventilation fails equipment temperatures must be monitored.

8.8.2 FMEA Table: No single point failures.

8.8.3 Summary of Analysis Results: This analysis is based on Keppe Sing Marine H340-101.1 Rev 0 drawing but has not yet been confirmed by survey/testing of this vessel.

8.9 Communication Systems

8.9.1 System Data:

Space Radio Sound Powered

Phone Telephone DP Alert

Bridge Y Y Y Y

DP Control Y Y Y Y

Engine Room fwd Y Y

Engine Room aft Y Y

ECR Y Y Y Y

Port Propulsion Room Aft Y Y

Stbd Propulsion Room Aft Y Y

Port Aft Thruster Room Y Y

Stbd Aft Thruster Room Y Y

Port Thruster Room Y Y

Stbd. Thruster Room Y Y

Emergency Gen. Room Y Y

Port SBD Room Y Y

Stbd. SBD Room Y Y

Page 79: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 79 of 80 February 4, 2009

8.9.2 System Description: There is reliable and clear radio, and telephone communication between the Navigation Bridge, DP control, ECR, Engine Rooms, Switchboard Rooms, Thruster Rooms, and the Emergency Generator Room. There is a redundant means of communication to each of these stations despite any one failure. The vessel is equipped with a DP Alert system. Headsets and flashing lights are fitted in high noise environments.

8.9.3 System Analysis Results: No single point or DPO intervention failures. No single failure can cause loss of communication. This analysis is based on 24Vdc one line diagram H340-E105 Rev. B sound but has not yet been confirmed by survey/testing of this vessel.

8.9.4 Auxiliary Support Systems Summary:

Single Point Failures 0

DPO Intervention 0

Maintenance Issues -

Analysis Accuracy Medium

Page 80: Noble Denton Global 1200 Dp2 Fmea

Global Industries Ltd Global 1200

Pre-trial DP2 FMEA

H8675 Rev C Page 80 of 80 February 4, 2009

This Report is intended for the sole use of the person or organization to which it is addressed and no liability of any nature whatsoever shall be assumed to any other party in respect of its contents. As to the addressee, neither the Company nor the undersigned shall (save as provided in the Company’s Conditions of Business dated 1st April 1999) be liable for any loss or damage whatsoever suffered by virtue of any act, omission or default (whether arising by negligence or otherwise) by the undersigned, the Company or any of its servants.

NOBLE DENTON MARINE INC.

Original Signed by:

Ben Armstrong DP Engineer

Countersigned by:

Paul D Kerr DP Technical Authority