nodal readiness center and readiness scorecard - october ’09 natf meeting
DESCRIPTION
Nodal Readiness Center and Readiness Scorecard - October ’09 NATF Meeting. 10/27/2009 Brandon McElfresh Nodal Readiness and Transformation. Readiness Center & Readiness Scorecard. READINESS CENTER AND READINESS SCORECARD UPDATE. Readiness Center & Readiness Scorecard. Readiness Center - PowerPoint PPT PresentationTRANSCRIPT
Nodal Readiness Center and Readiness Scorecard - October ’09 NATF Meeting
10/27/2009Brandon McElfreshNodal Readiness and Transformation
Readiness Center & Readiness Scorecard
READINESS CENTER AND READINESS SCORECARD UPDATE
Readiness Center & Readiness Scorecard
Readiness Center
- Redesign went live 10/21/2009- Market Trials Structure- Market Outreach- http://nodal.ercot.com/readiness/index.html
Readiness Scorecard
- Telemetry Performance measurement begins (11/18/2009)
- New Functionality- Market Trials Structure- Updated Market Share data- Last Updated Date- Frequency- Links to Readiness Center to access dashboards
- Metric Inventory- Will be posted on the Readiness Center when Telemetry Performance
measurement begins.
Readiness Center & Readiness Scorecard
MARKET PARTICIPANT METRICS
Readiness Center & Readiness Scorecard
METRIC - “Telemetry Performance”
Schedule
November 2009 – February 2010. The first measurements on theNodal Scorecard will be available on 11/18/2009. A market noticewill be sent to Market Participants when the “TelemetryPerformance” metric goes live.
Applies to
QSEs with Resources and TDSPs
Frequency
Aligns with database loads (typically bi-weekly)
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:-Total # of required telemetry points by QSE and TDSP-Total # of SE points missing by QSE and TDSP-Total # of SCED points missing by QSE and TDSP-Telemetry % provided
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Individual MP Criteria
Market-wide MP Criteria
State Estimator Telemetry(11/2009 – 12/31/2009)
SCED Telemetry (required as of 1/2010)
Red< 80% of nodal telemetry points provided
To be determined
Amber>= 80% and < 100% of Nodal telemetry points provided
To be determined
Green100% of Nodal telemetry points provided
100% of Nodal telemetry points provided
QSEs with Resources TDSPs
Red< 90% of ratio share meeting criteria
< 90% of ratio share meeting criteria
Amber>= 90% and < 95% of ratio share meeting criteria
>= 90% and < 95% of ratio share meeting criteria
Green>= 95% of ratio share meeting criteria
>= 95% of ratio share meeting criteria
Readiness Center & Readiness Scorecard
METRIC – “Resource Registration”
Schedule
November 2009 – early 2010
Applies to
Resource Entities and QSEs with Resources
Frequency
Weekly
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:-RARF Submittals-Declarations of Decision Making Authority-Resource Node & Meter Mapping approvals from RE’s
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Individual MP Criteria
Market-wide MP Criteria
11/1/2009 - 12/31/2009
11/1/2009 - 1/29/2010 11/1/2009 – early 2010
Phase Criteria
Resource Entities complete
scheduled RARF submittals.
Resource Entities complete declaration of
Resource Decision Making Authority for
each network modeled Generation Resource.
Resource Entities verifies Resource Node and Meter Mapping.
RedFailure to meet criteria, not responding to escalation calls after the target completion date.
AmberDemonstrating progress in making corrections after target completion date. Score will change to RED after 30-days past target completion date if no corrections are received.
Green All forms received and accepted
Resource Entities QSEs with Resources
Red< 90% of ratio share meeting criteria
< 90% of ratio share meeting criteria
Amber>= 90% and < 95% of ratio share meeting criteria
>= 90% and < 95% of ratio share meeting criteria
Green>= 95% or more of ratio share meeting criteria.
>= 95% of ratio share meeting criteria
Readiness Center & Readiness Scorecard
METRIC - “Real-Time Connectivity Qualification”
Schedule
January 4, 2010 – January 29, 2010
Applies to
QSEs with Resources
Frequency
Weekly
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:
- QSE submission qualification status.
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Individual MP Criteria
Market-wide MP Criteria
1/4/2010 - 1/29/2010 After 1/29/2010
Red No Red CriteriaSubmissions not complete, participation not adequate
Amber No Amber CriteriaIncomplete Submissions, but actively working with ERCOT
Green
The following submissions are completed if applicable:• Current Operating Plan• Energy Offer Curve• Output Schedules• Incremental/Decremental Offer Curves
The following submissions are completed if applicable:• Current Operating Plan• Energy Offer Curve• Output Schedules• Incremental/Decremental Offer Curves
QSEs with Resources
Red < 90% of ratio share meeting criteria.
Amber>= 90% and < 95% of ratio share meeting criteria.
Green >= 95% of ratio share meeting criteria.
Readiness Center & Readiness Scorecard
METRIC - “Day Ahead Market Connectivity Qualification”
Schedule
January 4, 2010 – January 29, 2010
Applies to
All QSEs
Frequency
Weekly
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:
- QSE submission qualification status.
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Individual MP Criteria
Market-wide MP Criteria
QSEs with Resources QSEs
Red< 90% of ratio share meeting criteria
< 90% of ratio share meeting criteria
Amber>= 90% and < 95% ratio share meeting criteria
>= 90% and < 95% of ratio share meeting criteria
Green>= 95% of ratio share meeting criteria
>= 95% of ratio share meeting criteria
1/4/2010 - 1/29/2010 After 1/29/2010
Red No Red CriteriaSubmissions not complete, participation not adequate
Amber No Amber CriteriaIncomplete Submissions, but actively working with ERCOT
Green
The following submissions are completed if applicable:
The following submissions are completed if applicable:
- Three Part Offers - Three Part Offers
- Ancillary Service Offers - Ancillary Service Offers
- Energy-only Offers and Bids - Energy-only Offers and Bids
- Trades (Energy, Ancillary Services, Capacity)
- Trades (Energy, Ancillary Services, Capacity)
- Self-Arranged Ancillary Services - Self-Arranged Ancillary Services
- CRR Offers - CRR Offers
- PTP Obligation Bids - PTP Obligation Bids
- Self Schedules - Self Schedules
- DC Tie Schedules - DC Tie Schedules
- Resource Parameters - Resource Parameters
Readiness Center & Readiness Scorecard
METRIC – “CRR Connectivity Qualification”
Schedule
January 4, 2009 – January 29, 2009
Applies to
CRRAHs
Frequency
Weekly
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:
- CRR qualification status.
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Individual MP Criteria
Market-wide MP Criteria
CRR Account Holders
Red To be determined
Amber To be determined
Green To be determined
1/4/2010 - 1/29/2010 After 1/29/2010
Red No red criteria.Not participating in CRR testing, but intending to participate in the CRR auctions.
Amber No amber criteria.Incomplete CRR testing, but working with ERCOT to resolve.
GreenParticipating in CRR Testing.
Participating in CRR Testing.
Readiness Center & Readiness Scorecard
METRIC – “Real-time Market Participation”
Schedule
February 1, 2009 – 168 Hour Test
Applies to
QSEs with Resources
Frequency
Weekly
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:
- QSE submission status by transaction.
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Individual MP Criteria
Market-wide MP Criteria
QSEs with Resources
Red < 90% of ratio share meeting criteria
Amber>= 90% and < 95% of ratio share meeting criteria
Green >= 95% of ratio share meeting criteria.
2/1/2010 – Closed Loop Test
RedQSE with Resources participating in < 90% of the Real-time Market submissions on a weekly basis
AmberQSE with Resources participating in >= 90% and < 95% of the Real-time Market submissions on a weekly basis
Green
>= 95% of daily submissions completed for the following transactions if applicable:• Current Operating Plan• Energy Offer Curve• Output Schedules• Incremental/Decremental Offer Curves
Readiness Center & Readiness Scorecard
Next time at NATF
- CRR Auction Participation – All CRRAHs, February 2010
- Network Model Validation – TDSPs, February 2010
- Outage Scheduler Connectivity Qualification – TDSPs, QSERs, February 2010 – March 2010
- Day-Ahead Market Participation – All QSEs, March 2010 – 168 Hour Test
Readiness Center & Readiness Scorecard
ERCOT METRICS
Readiness Center & Readiness Scorecard
METRIC – “ERCOT Nodal Procedures”
Schedule
November 2009 – December 2010
Frequency
Monthly
Dashboard
A dashboard containing the following data willbe posted on the Readiness Center:-# of Procedures Developed-# of Procedures Exercised-Total # of Procedures.
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Criteria
Phase 1 - Prior to 9/1/2010 Phase 2 - 9/1/2010 - 12/1/2010
Red
> 3 procedures are not developed 1 month prior to the Market Trial phase where they are scheduled to be exercisedor > 3 procedures scheduled to be exercised in the appropriate Market Trials phase are not exercised.
More than 3 ERCOT procedures are not approved for go-live.
Amber
> 1 and <= 3 procedures are not developed 1 month prior to the Market Trial phase where it is scheduled to be exercised or> 1 and <= 3 procedures scheduled to be exercised in the appropriate Market Trials phase are not exercised.
3 or fewer procedures are not approved for go-live.
Green
<= 1 procedure is not developed 1 month prior to the Market Trials phase where they are scheduled to be exercised and <= 1procedures is not exercised in the appropriate Market Trials phase as scheduled.
All ERCOT procedures are approved for go-live.
Readiness Center & Readiness Scorecard
METRIC – “ERCOT Internal Nodal Training”
Schedule
November 2009 – September 2010
Frequency
Monthly
Dashboard
A dashboard with all departments impacted by Nodal, will be posted on the Readiness Center. Information will include:
•Counts of completed/uncompleted Training Activities•Next Training Activity Due Date•Individual Department Training Status/Points:
The link to the dashboard will be provided in the ReadinessScorecard – metric definition page.
Criteria
11/2009 – 9/2010
Red >6 points, totaled over all impacted departments
Amber 4-6 points, totaled over all impacted departments
Green 0-3 points, totaled over all impacted departments
Overall ERCOT Criteria
The overall ERCOT Internal Training Metric isobtained by summing the points from all of thedepartments, and applying the criteriaposted above.
• Green (0 pt): No uncompleted training due within 30 days
• Amber (1 pt): Uncompleted training due within 30 days
• Red (3 pt): Uncompleted training is past due