non-intrusive mpfm case study: challenges and way forward nel sea workshop 2016.pdf ·...
TRANSCRIPT
Non-Intrusive MPFM Case Study: Challenges and Way Forward
Authors:
Anish Gupta, Dahlila Kamat, Nor Aisyah Borhan, Ratan Singh, Bahrom Madon PETRONAS Carigali Sdn Bhd
Hairul Razi, Mohd Zaffarin Abdul Ghaffar, Sciensterra Sdn Bhd and Andrew Jamieson, Dmitry Gazin, David Whittingham, Neftemer Ltd
PRESENTATION OUTLINE
• Introduction and About the Technology
• Pilot Objectives & Success Criteria
• Field-P Pilot
• Field-S Pilot
• Lessons Learnt
• Way Forward
• Conclusion
PRESENTATION OUTLINE
• Introduction and About the Technology
• Pilot Objectives & Success Criteria
• Field-P Pilot
• Field-S Pilot
• Lessons Learnt
• Way Forward
• Conclusion
CHALLENGES
© 2010 PETROLIAM NASIONAL BERHAD (PETRONAS)All rights reserved. No part of this document May be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without
the permission of the copyright owner.
4
• Guessimated / History Matched Readings
• No Well Test DataWell Testing Facility
• 1 well taken once a month on test
• 8-12 hours testing / well
• No continuous monitoring for Well behavior
Well Testing using Test Separator
• Challenge for high GVF conditions and Gas Lifted environment
• Costly in terms of Installation and Logistics Well Test using MPFMs
THE TECHNOLOGY
© 2010 PETROLIAM NASIONAL BERHAD (PETRONAS)All rights reserved. No part of this document May be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without
the permission of the copyright owner.
5
• About the Meter
• GVF: 20-80%;
• Gamma Ray principle
• Provides the mass as output
• Mainly application in oil Wells
Previous Case Histories
• Developed in Russian Oil fieldenvironment
• Trial in Brazil and few other locations
DETECTOR
LEAD SAFETY SHIELD
GAMMA SOURCE HOUSING
MOUNTING BRACKET
FLOWLINE
LOCKABLE SHUTTER
S. No. Characteristic Neftemer Other MPFMs
1 Modification in Line Not required Require – Pressure test, Flushing, Line modification, extra hardware, etc.
2 Weight and Foot-print Less Huge and includes more detailed planning, Logistic and more modifications
3 Clamp-On Type Yes No
4 Production Loss during Installation (on existing wells)
No Yes
5 Installation Time Max. 1 day Min 2-3 days
PRESENTATION OUTLINE
• Introduction and About the Technology
• Pilot Objectives & Success Criteria
• Field-P Pilot
• Field-S Pilot
• Lessons Learnt
• Way Forward
• Conclusion
PILOT OBJECTIVES
1. To test the performance of non-intrusive MPFM at various flow conditions
and identify the flow conditions wherein the non-intrusive MPFM can be
used with reliable accuracy
2. To verify the claim of NEFTEMER of the Measurement Accuracy of the
MPFM: +/- 10% on defined GVF ranges.
3. Analyse the economic value in comparison to a fixed meter
4. To test the logistics involved and installation ease/flexibility of this MPFM for
use as portable well test equipment.
5. To find its applicability as a continuous well production monitoring tool.
© 2010 PETROLIAM NASIONAL BERHAD (PETRONAS)All rights reserved. No part of this document May be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without
the permission of the copyright owner.
7
SUCCESS CRITERIA
© 2010 PETROLIAM NASIONAL BERHAD (PETRONAS)All rights reserved. No part of this document May be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without
the permission of the copyright owner.
8
S. No Criteria
1 Safe to operate due to Radioactive nature of equipment Radiation Exposure < 10mSV/year
2 Continuous monitoring of density for all the GVF ranges
3 Continuous monitoring of Oil, Well and Gas flow rates for wells with GVF < +/- 80%
4 Ease of Installation and movement from one place to another (less than 1 day)
5 MPFM must be acceptable as a continuous well production & monitoring tool
PRESENTATION OUTLINE
• Introduction and About the Technology
• Pilot Objectives & Success Criteria
• Field-P Pilot
• Field-S Pilot
• Lessons Learnt
• Way Forward
• Conclusion
PLANNING & EXECUTION – Candidate Selection
• No. of Wells MPFM Installed: 2
• GVF ranges: From 74 to 91 %
• Out of 7 wells, Only 1 well not suitable for Installation due to space limitation
Well#1 Well#2 Well#3S Well#3L Well#4 Well#5 Well#6
Monitoredwith Neftemer
NOWell not flowing
NOWell not flowing
YES NOSpace
limitation
YES NOSpace limitation
NOWell not flowing
GVF (%) 89 91 81 82 86 85 74
Installationfeasibility
YES YES YES NO YES YES*Modify existing
bracket
YES
Pipe Schedule XXS XXS XXS XXS XXS XXS XXS
• Main Challenge was the pipe wall thickness i.e. 17mm (Earlier manufacturer claimed only max 10mm)
• Stretched the Limits (by Project team):- Conducted in-depth investigation, suggested in design of detector and
finally achieved recordable reading up to a max of 22mm thickness plate
RESULTS – Well#3S
Plot shows 24 hours data
• Large density variation – from 100 kg/m3 to 650 kg/m3• Liquid variation from 1250 to 2000 bpd (~23% variation)• Discontinuous Readings – though trend was visible
Liq Flow Rate; Gas Flow Rate; Density; Water Cut
Avg Liq Rate: 1600 bpd
Avg Liq Rate: 1300 bpd
RESULTS – Well#3S
Test 2 Test 3 Test 4 Test 5
0
50
100
150
200
250
0 0.5 1 1.5 2
Liq
uid
Rat
e (b
bl/
day
)
Injected Gas Rate (mmscfd)
Gas Lift Optimization - Verification
• A Gas Lift optimization
exercise was conducted
to test the sensitivity of
meter and prove the
future usage
• (Red Dot) was the
actual Gas Injection
Rate which Field P field
was injecting
• The exercise verified
with actual relative
values that the current
Gas lift injection was an
optimum injection
RESULTS – Well#4
Plot shows 24 hours data• Max Liq: 1850 bpd; Min
Liquid: 1470 bpd; Variation: ~25%
• Trends - %age error increased with increase in GVF
Test 2 Test 3
1.69 2.23
Test 4
Gas lift rate (mmscf/d) 1.20
0
1
2
3
0.00
20.00
40.00
60.00
80.00
100.00
1 2 3 4 5
GV
F an
d %
age
err
ors
Test#
Gas Injected vs Gas Produced GVF @ Line conditions
%age error
Summary of Results– Field P
1. Radioactivity Concern – ok
2. Liq, Oil and Gas flow rates available for GVF ranges < 85%
3. Equipment feasible to be installed in 5 out of 6 locations
4. With increase in GVF, the relative error for gas reading increased
5. Multi-Rate Gas Lift Injection test for both the wells conducted and was successful in terms of
relative results
6. Due to non-availability of test separator, liquid readings and accuracy of meter cannot be
verified
Conclusions:
• Effective for Wells with GVF < 85%.
• Good diagnostics for Gas Lift Optimization
• Provided good sensitivity in flow of well regime which indicates a very good diagnostic tool
• With more data and calibration in place, can be effectively used as a well test tool for Field P
and other similar platforms
PRESENTATION OUTLINE
• Introduction and About the Technology
• Pilot Objectives & Success Criteria
• Field-P Pilot
• Field-S Pilot
• Lessons Learnt
• Way Forward
• Conclusion
PLANNING & EXECUTION – Field S Candidates
5T 10S 15S 6L 30T 89L
GVF (%) 98.31Above Range
96.32Above Range
91.17Above Range
96.77Above Range
99Above Range
94.43Above Range
Liquid Flow Rate Range in blpd OK (<1000) OK (<1500) OK (<1500)
OK (>3000) OK (<1500)
Installation feasibility i.e. Vertical Length available in m
OK (1.80) OK (>1.0) OK (1.8) OK (0.87) –managed to
install
OK (>1.0) NO (0.70)
No. of Wells: 5 (as per Installation feasibility)
GVF ranges: From 91 to 98% i.e. all values exceeded the nominal working range of the meter
Field S RESULTS
• Multi-Rate Test – Well#6L• Neftemer was recorded to ensure the sensitivity / response of the Meter with changes in fluid
condition
Date & TimeCurrent GLI
(MMscfd)Density reading (kg/m3) Remarks
20-Sept-14 @ 1030hrs 0.83-0.86 -50-150
21-Sept-14 @ 1000hrs 1 -100-150 Foam
21-Sept-14 @ 2030hrs 0.54-0.64 450-150
22-Sept-14 @ 0130hrs 0.59-0.61 0-150
Optimum gas lift injection need to be determine for optimum production of the system Neftemer can be used as an effective tool for well diagnostic
Summary of Results– Field S
1. Liq, Oil and Gas flow rates not available for GVF ranges > 96%
2. Gas Flow rates not available for 90% < GVF < 96% .
Conclusions:
• Not effective for High GVF wells.
• Good diagnostics, if able to record relative liquid rates depending on flow
regimes
Summary of Results
S. No Criteria Field S Field P
1 Safe to operate due to Radioactive nature of equipment Radiation Exposure < 10mSV/year √ √
2 Continuous monitoring of density for all the GVF ranges √ √
3 Continuous monitoring of Oil, Well and Gas flow rates for wells with GVF < +/- 80% x N/A
4 Accurate Readings for wells with GVF <=80%No wells with GVF <
85%
No reference Measurement due to
separator malfunction
4 Ease of Installation and movement from one place to another (less than 1 day) √ √
5 MPFM must be acceptable as a continuouswell production & monitoring tool x √
PRESENTATION OUTLINE
• Introduction and About the Technology
• Pilot Objectives & Success Criteria
• Field-S Pilot
• Field-P Pilot
• Conclusions & Lessons Learnt
• Way Forward
Conclusions & Lessons Learnt
• Gas lifted wells do have high variation interms of liquid flow rate
• Experience in handling and installation of radioactive equipment
• Gas lift optimization process in wells went well
• Additional trial needed to close the “Accuracy” Gap
Conclusions
• A close monitoring of well test parameters especially of water cut and FTHP is required
• Reference values for Initial installation should be approx. reliable
• Availability of proper test separator could have resulted in better pilot results
Lessons Learnt
WAY FORWARD
1. Additional Trial to close the study for Accurate Measurement
• To test the meter for a last trial in a facility with • Gas Lifted Wells
• GVF < 90%
• Proper Separator measurement
• If possible, facility with experience of MPFMs
• Identified Fields – Plan to be commenced :• Field X– Details below
Platform GVF Max
GVF Min
AvgGVF
A 100% 85% 95%
B 93% 40% 74%
C 93% 73% 85%
D 94% 63% 75%
E 95% 83% 91%
0%
20%
40%
60%
80%
100%
120%
A B C D E
Field-X GVF ranges
GVF Max GVF Min Avg GVF
THANK YOU
PVT Measurement
1. PVT measurement not taken into account during this pilot
2. PVT is used is to account for pressure – volume effects mainly for Gas rates
3. As mentioned in slides, the algorithm is much dependent on flow regimes and calibration, once
the actual rates are known, the calibration factor is expected to consider PVT corrections as
well
Calculations: GVFs and Line Standard Conversions
MPFM records at Line Temp (TL) and Pressure (PL)
QoL QwL QgL𝐺𝑉𝐹𝐿 =
𝑄𝑔𝐿
𝑄𝑔𝐿 + 𝑄𝑜𝐿 + 𝑄𝑤𝐿
𝑄𝑜𝑆 =𝑄𝑜𝐿
𝐵𝑜𝐿
𝑄𝑤𝑆 =𝑄𝑤𝐿
𝐵𝑤𝐿
𝑄𝑔𝑆
= (𝑄𝑜𝑆 𝑥 𝑅𝑠𝐿) +𝑄𝑔𝐿
𝐵𝑔𝐿
From PVT Data of the crude
QoS
QwS
QgS