Norse Energy Corp., USA As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing, producing, and marketing gas to the burgeoning premium markets of the metropolitan northeastern United States. Exploring growth opportunities for business in the local area Objective: To provide a brief overview of our operations, and explain our practices.

Upload: nathaniel-berry

Post on 26-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Norse Energy Corp., USA

As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing, producing, and marketing gas to the burgeoning premium markets of the metropolitan northeastern United States.

Exploring growth opportunities for business in the local area

Objective: To provide a brief overview of our operations, and explain our practices.

Page 2: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Start of a Natural Gas Well Lifecycle

Pre Planning: In house Geology Department to gather and evaluate subsurface information Obtain data using seismic testing and information from existing wells Input from Engineering, Marketing, and Pipeline divisions for feasibility and

economic analysis Permitting and Regulations:

NYS DEC Drilling Permit approval requirements:• Survey well location, Environmental Assessment Form, and unit verification• Storm Water Pollution Prevention Plan (SWPPP) establishes erosion and

sedimentation plans and procedures for State Pollutant Discharge System (SPDES)

• Drilling Procedures: Formations to be encountered, casing design, cement types and volumes, and wellbore path

Additional regulatory agencies: OPRHP, Army Corps. of Engineers, NYSDOT, County and Towns, NYS PSC (pipeline), and the SRBC (water withdrawal)

Page 3: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Start of a Natural Gas Well Lifecycle

Site Selection After a site is selected by Geology, field work is coordinated with Land and

Environmental to determine the feasibility of a well at that location.• Land owner is notified of potential well• Access road, well site, equipment placement and pipeline route approval is

received from land owner Spacing Units

Once a site is determined to be feasible, Land Dept. will generate the spacing unit. The spacing unit is prepared in accordance with NYS DEC regulations and

requires their approval. Spacing Unit Examples (As per NYS DEC Regulations)For our current Herkimer wells the following spacing units are in place:

80 Acre units for a depth above 4,000’

160 Acre units for a depth of 4,000-6,000’

320 Acre units for a depth of 6,000-8,000’

Page 4: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Natural Gas Well LifecycleDrilling of the Well

Site Construction When all permitting is in place, the access road and well site are constructed in

cooperation with the landowner. This activity is regularly inspected and monitored by the governing agencies.

Drilling and Casings Spud the well and set conductor if needed Drilling surface hole (usually 12 1/4”) and install the surface casing string (usually

500’) of 9 5/8” and cement the casing to surface Install and pressure test the Blow Out Preventer (BOP) (This is done on each

string of casing as per NYSDEC regulations) Drill intermediate hole (usually 8 3/4”) and install intermediate casing sting (usually

2,000-3,500’) of 7” casing and cement to surface, begin kick at this point. Drill main horizontal hole (usually 6 1/4”) using directional motors

• Install production casing if required (usually 4 1/2”) and cement Present Herkimer Sandstone wells are coming in naturally and do not require the

production casing.

Page 5: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Natural Gas Well Lifecycle:Completions and Hydraulic Fracturing

Completion Procedures If production casing is installed and cemented, the following procedure is followed

to complete the well• Production casing is then perforated along the horizontal at precise intervals to

open pathways through which the frac job can be performed and gas will flow.• During the initial portion of the frac job, water is pumped from the surface under

pressure to create fractures in the rock formation underground. Once the fractures are established, a water/sand combination along with a small

amount of other compounds is pumped into the fractures to prop them open.• Hydraulic Fracturing fluids are typically 99.5% sand and water, with the .5%

remainder consisting of DEC approved compounds. NYS DEC Regulations

Currently NYS DEC Regulations allow a maximum of 80,000 gallons of water for Hydraulic Fracturing of a well.

New Regulations (sGEIS) are pending which will cover large volume Fracturing used in horizontal shale wells.

Page 6: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Natural Gas Well Lifecycle: Restoration, Pipeline, and Marketing

Restoration All free fluids are removed from the pit by a NYS licensed hauler and disposed of

at a NYS approved disposal facility. The pit, which stores drill cuttings and fluids, has a 20 mm lining which is folded

over and covered after the free fluids are removed. Transitioning to Pitless The well site is then filled back and the top soil replaced to allow seeding and

mulching to be done. Final restoration is inspected by NYSDEC for regulatory compliance.

Pipeline The well line is installed from the well to a gathering system. The gathering system transports gas from individual wells to a compressor facility. Compressor facilities are required to increase gas pressure which allows it to feed

into transmission lines All pipelines are regulated by NYSPSC for safety and sometimes for environmental

(dependent on spec’s some pipelines are regulated by FERC) MarketingNorse sells approximately 25% of production to NYSEG and used locally.

Norse sells to the Dominion line, which services the East Coast including NYSEG

Page 7: Norse Energy Corp., USA  As natural gas assumes a far more important role in America’s energy mix, Norse Energy is committed to exploring, developing,

Norse Energy Corp., USAOur Future in New York

Surpassing Expectations and Piloting the Potential • The Herkimer Sandstone Formation in this area is proving to be a very

successful field.• The Marcellus and Utica Shales, stretching throughout our core area,

hold promise of success as well. Production Taxes

• Production is currently taxed on a real property basis.• The rate is established based on a five year rolling average

established by ORPS.• Tax revenues are applied locally: Schools, Towns, Counties, and

Local Fire Departments. Questions?