north west grip 2013-2022 annex a

202
Gas Regional Investment Plan 2013-2022 North West GRIP Annex A

Upload: brecht-malfait

Post on 15-Mar-2016

224 views

Category:

Documents


1 download

DESCRIPTION

North West Gas regional Investment Plan 2013-2022 Annex A

TRANSCRIPT

Page 1: North West GRIP 2013-2022 Annex A

Cluden

Gas Regional Investment Plan2013-2022

Infrastructure ProjectsAnnex A

A fair partner to all

North West

GRIPAnnex A

bayernets GmbH Poccistraße 7 80336 München

Fluxys TENP TSO S.p.A. Martin-Luther-Platz 28 40212 Düsseldorf

Fluxys Deutschland GmbH Graf-Adolf-Platz 12 40213 Düsseldorf

GASCADE Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

Gasunie Deutschland Transport Services GmbH Pelikanplatz 5 30177 Hannover

bayernets GmbH Poccistraße 7 80336 München

Fluxys TENP TSO S.p.A. Martin-Luther-Platz 28 40212 Düsseldorf

Fluxys Deutschland GmbH Graf-Adolf-Platz 12 40213 Düsseldorf

GASCADE Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

Gasunie Deutschland Transport Services GmbH Pelikanplatz 5 30177 Hannover

bayernets GmbH Poccistraße 7 80336 München

Fluxys TENP TSO S.p.A. Martin-Luther-Platz 28 40212 Düsseldorf

Fluxys Deutschland GmbH Graf-Adolf-Platz 12 40213 Düsseldorf

GASCADE Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

Gasunie Deutschland Transport Services GmbH Pelikanplatz 5 30177 Hannover

bayernets GmbH Poccistraße 7 80336 München

Fluxys TENP TSO S.p.A. Martin-Luther-Platz 28 40212 Düsseldorf

Fluxys Deutschland GmbH Graf-Adolf-Platz 12 40213 Düsseldorf

GASCADE Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

Gasunie Deutschland Transport Services GmbH Pelikanplatz 5 30177 Hannover

bayernets GmbH Poccistraße 7 80336 München

Fluxys TENP TSO S.p.A. Martin-Luther-Platz 28 40212 Düsseldorf

Fluxys Deutschland GmbH Graf-Adolf-Platz 12 40213 Düsseldorf

GASCADE Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

Gasunie Deutschland Transport Services GmbH Pelikanplatz 5 30177 Hannover

Gasunie Ostseeanbindungsleitung GmbH Pelikanplatz 5 30177 Hannover

Gastransport Nord GmbH An der Großen Wisch 9 26133 Oldenburg

GRTgaz Deutschland GmbH Zimmerstraße 56 10117 Berlin

NEL Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

ONTRAS – VNG Gastransport GmbH Maximilianallee 4 04129 Leipzig

Gasunie Ostseeanbindungsleitung GmbH Pelikanplatz 5 30177 Hannover

Gastransport Nord GmbH An der Großen Wisch 9 26133 Oldenburg

GRTgaz Deutschland GmbH Zimmerstraße 56 10117 Berlin

NEL Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

ONTRAS – VNG Gastransport GmbH Maximilianallee 4 04129 Leipzig

Gasunie Ostseeanbindungsleitung GmbH Pelikanplatz 5 30177 Hannover

Gastransport Nord GmbH An der Großen Wisch 9 26133 Oldenburg

GRTgaz Deutschland GmbH Zimmerstraße 56 10117 Berlin

NEL Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

ONTRAS – VNG Gastransport GmbH Maximilianallee 4 04129 Leipzig

Gasunie Ostseeanbindungsleitung GmbH Pelikanplatz 5 30177 Hannover

Gastransport Nord GmbH An der Großen Wisch 9 26133 Oldenburg

GRTgaz Deutschland GmbH Zimmerstraße 56 10117 Berlin

NEL Gastransport GmbH Kölnische Straße 108-112 34119 Kassel

ONTRAS – VNG Gastransport GmbH Maximilianallee 4 04129 Leipzig

Open Grid Europe GmbH Kallenbergstraße 5 45141 Essen

Thyssengas GmbH Kampstraße 49 44137 Dortmund

Gasunie Transport Services b.v.

Concourslaan 17

9700 AD Groningen

The Netherlands

TIGF

17 Chemin de la Plaine - 64140 Billère

Fluxys Belgium SA

Avenue des Arts 31

B-1040 Brussels

Open Grid Europe GmbH Kallenbergstraße 5 45141 Essen

Thyssengas GmbH Kampstraße 49 44137 Dortmund

Gasunie Transport Services b.v.

Concourslaan 17

9700 AD Groningen

The Netherlands

TIGF

17 Chemin de la Plaine - 64140 Billère

Fluxys Belgium SA

Avenue des Arts 31

B-1040 Brussels

Open Grid Europe GmbH Kallenbergstraße 5 45141 Essen

Thyssengas GmbH Kampstraße 49 44137 Dortmund

Gasunie Transport Services b.v.

Concourslaan 17

9700 AD Groningen

The Netherlands

TIGF

17 Chemin de la Plaine - 64140 Billère

Fluxys Belgium SA

Avenue des Arts 31

B-1040 Brussels

Open Grid Europe GmbH Kallenbergstraße 5 45141 Essen

Thyssengas GmbH Kampstraße 49 44137 Dortmund

Gasunie Transport Services b.v.

Concourslaan 17

9700 AD Groningen

The Netherlands

TIGF

17 Chemin de la Plaine - 64140 Billère

Fluxys Belgium SA

Avenue des Arts 31

B-1040 Brussels

Open Grid Europe GmbH Kallenbergstraße 5 45141 Essen

Thyssengas GmbH Kampstraße 49 44137 Dortmund

Gasunie Transport Services b.v.

Concourslaan 17

9700 AD Groningen

The Netherlands

TIGF

17 Chemin de la Plaine - 64140 Billère

Fluxys Belgium SA

Avenue des Arts 31

B-1040 Brussels

Interconnector (UK) Limited

8th Floor

61 Aldwych

London

WC2B 4AE

Premier Transmission Limited

First Floor The Arena Building

85 Ormeau Road,

Belfast,

BT7 1SH

Swedegas AB

Gamlestadsvägen 2-4 B15

415 02 Göteborg

Creos Luxembourg S.A.

2, rue Thomas Edison, Strassen

L-2084 Luxembourg

Interconnector (UK) Limited

8th Floor

61 Aldwych

London

WC2B 4AE

Premier Transmission Limited

First Floor The Arena Building

85 Ormeau Road,

Belfast,

BT7 1SH

Swedegas AB

Gamlestadsvägen 2-4 B15

415 02 Göteborg

Creos Luxembourg S.A.

2, rue Thomas Edison, Strassen

L-2084 Luxembourg

Interconnector (UK) Limited

8th Floor

61 Aldwych

London

WC2B 4AE

Premier Transmission Limited

First Floor The Arena Building

85 Ormeau Road,

Belfast,

BT7 1SH

Swedegas AB

Gamlestadsvägen 2-4 B15

415 02 Göteborg

Creos Luxembourg S.A.

2, rue Thomas Edison, Strassen

L-2084 Luxembourg

Interconnector (UK) Limited

8th Floor

61 Aldwych

London

WC2B 4AE

Premier Transmission Limited

First Floor The Arena Building

85 Ormeau Road,

Belfast,

BT7 1SH

Swedegas AB

Gamlestadsvägen 2-4 B15

415 02 Göteborg

Creos Luxembourg S.A.

2, rue Thomas Edison, Strassen

L-2084 Luxembourg

Energinet.dk

Tonne Kjærsvej 65

DK-7000 Fredericia

Gaslink Independent System Operator Ltd.

Gasworks Road, Cork

National Grid

Warwick Technology Park

Gallows Hill, Warwick, CV34 6DA

Nowega GmbH

Nevinghoff 20

48147 Münster

GRTgaz

Energinet.dk

Tonne Kjærsvej 65

DK-7000 Fredericia

Gaslink Independent System Operator Ltd.

Gasworks Road, Cork

National Grid

Warwick Technology Park

Gallows Hill, Warwick, CV34 6DA

Nowega GmbH

Nevinghoff 20

48147 Münster

GRTgaz

Energinet.dk

Tonne Kjærsvej 65

DK-7000 Fredericia

Gaslink Independent System Operator Ltd.

Gasworks Road, Cork

National Grid

Warwick Technology Park

Gallows Hill, Warwick, CV34 6DA

Nowega GmbH

Nevinghoff 20

48147 Münster

GRTgaz

Energinet.dk

Tonne Kjærsvej 65

DK-7000 Fredericia

Gaslink Independent System Operator Ltd.

Gasworks Road, Cork

National Grid

Warwick Technology Park

Gallows Hill, Warwick, CV34 6DA

Nowega GmbH

Nevinghoff 20

48147 Münster

GRTgaz

Energinet.dk

Tonne Kjærsvej 65

DK-7000 Fredericia

Gaslink Independent System Operator Ltd.

Gasworks Road, Cork

National Grid

Warwick Technology Park

Gallows Hill, Warwick, CV34 6DA

Nowega GmbH

Nevinghoff 20

48147 Münster

GRTgaz 6 rue Raoul Nordling

92277 Bois-Colombes Cedex - France

Page 2: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Belgium

2

Page 3: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Ship  size  (m3)

Reloading  ability  ?

2018/2

+180.000,00

+10,80

Regasification  facility

Expected  volume  (bcm/y)

LNG  Terminal  Zeebrugge

+3,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

No

0%

No

0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

LNG Terminal Zeebrugge - Capacity Extension & 2nd Jetty

Fluxys  LNG

Fluxys  LNG

LNG  Terminal

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-229 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Fluxys  LNG  (100%)  

Undefined  (100,00%)  

3

Page 4: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Construction  of  a  second  jetty  for  berthing  of  LNG  ships  with  a  capacity  from  approximately  3500  m³  LNG  up  to  217000  m³  LNG.

Construction  of  an  additional  storage  tank  with  a  capacity  of  180000  m³  LNG.

Construction  of  additional  send-­‐out  capacity  of  450000  m³(n)/h.

Planned  date  of  commissioning  :-­‐  new  jetty  and  send-­‐out  :  mid  2015  (FID  taken,  Construction  started)-­‐  new  LNG  tank:  Q2  2018

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  Belgium118,80Zeebrugge  LNG

PROJECTED  CAPACITY  INCREASES

Hub  Belgium  (Zeebrugge  Beach)

Security of Supply, Market integration (The increase of capacity will contribute to the integration of market areas in North-­‐West Europe. The overall flexibility of the system is enhanced by the additional LNG storage and the send-­‐out capacity.),Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (Belgium),  N-­‐1  Regional  (NW  Europe),  Back-­‐up  for  renewables,  Higher  Flexibility  for  the  market  due  to  enhanced  reloading  capacity,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

4

Page 5: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2015  Q1

2015/4

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014  Q3

+74,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Alveringem-Maldegem

Fluxys  Belgium

Fluxys  Belgium

Pipeline  including  CS

http://www.fluxys.com/belgium/en/about%20fluxys/investment/projects/alveringem-­‐maldegem.aspx

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-205 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Alveringem-­‐Maldegem,  Fluxys  Belgium  (100%)  

Undefined  (100,00%)  

5

Page 6: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

A new interconnection point between GRTgaz and Fluxys near Veurne (Alveringem) to allow firm physical capacity with non-­‐odorized gas from France to Belgium. Thanks to this new connection, the terminal of Dunkirk will be linked with the IPs of thezone  of  Zeebrugge  (IZT/HUB,  ZPT  and  LNG  terminal)  and  the  North-­‐West  European  market  through  the  virtual  hub  ZTP.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)  (Dunkerque)

270,00New  IP  FR-­‐BE    (FR)  /  Alveringem-­‐Maldegem  (BE)

PROJECTED  CAPACITY  INCREASES

Hub  Belgium  (Zeebrugge  Beach)

Security of Supply, Market integration (This project gives a connection from the LNG terminal of Dunkirk and the PEG-­‐Nord to Belgium and the international markets of North-­‐West Europe.), Reverse Flows, Diversification of sources, Diversification ofroutes,  N-­‐1  National  (Belgium),  N-­‐1  Regional  (NW  Europe),  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

6

Page 7: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Yes

Luxembourg Pipeline

Fluxys  Belgium  &  Creos

Fluxys  Belgium

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-206 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

No

0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+50,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2018

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Undefined  (100%)  

Undefined  (100,00%)  

7

Page 8: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Security  of  Supply,  Market  integration  (BE/LUX),  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (Luxembourg),  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Bras/Petange

PROJECTED  CAPACITY  INCREASES

Hub  Luxemburg10,85

Pipeline  upgrade  to  increase  capacity  from  Belgium  to  Luxembourg  by  reinforcing  the  current  DN300  section  from  Bras  to  Petange  by  DN500.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Belgium

8

Page 9: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Denmark

9

Page 10: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2013

2013/4

+20,00

+0,55

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12011

+94,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

FID0%

2010  Q2FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Not  defined  yet

Ellund-Egtved

Energinet.dk

Energinet.dk

Pipeline  including  CS

energinet.dk/EN/ANLAEG-­‐OG-­‐PROJEKTER/Anlaegsprojekter-­‐gas/Ellund-­‐Egtved/Sider/Ellund-­‐Egtved.aspx

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-015 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Energinet.dk  (100%)  

Public  Financing  (50,00%)  

Private  Financing  (50,00%)  

10

Page 11: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entryYes exit

Pipeline  looping  Ellund-­‐Egtved.  Four  unit  Compressor  Station  in  Egtved.  Increases  capacity  in  Ellund  and  Dragør  Interconnection  Points.

50% European Economic Recovery Programme – expected co-­‐financing of 100million  EUR. 50%  Financed  by  Energinet.dk

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  DenmarkHub  Denmark  (Ellund)Hub  Denmark

13,20184,8044,00

DragørEllund

PROJECTED  CAPACITY  INCREASES

Hub  DenmarkHub  Denmark  (Ellund)

Hub  Sweden

Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National, N-­‐1 Regional, Back-­‐up for renewables, Biogas, The project will ensure supply of gas to the Danish and Swedish markets when thegas production from the Danish North Sea is declining. The project also ensures integration with the gas market in Germany. Furthermore, the project will enhance security of supply also in emergency situations by providing diversification of sourcesand  routes.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

11

Page 12: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Negotiated  (e.g.  Exemption)

2013

2014/4 +0,80

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+175,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

FEED0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Tie-in of Norwegian off-shore natural gas transmission system to Danish off-shore natural gas infrastructure

Maersk  Oil  and  Gas  AS

Maersk  Oil  and  Gas  A/S

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-218 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  TBD  (50%)  0,  TBD  (50%)  

Undefined  (100,00%)  

12

Page 13: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

To  connect  the  Norwegian  off  shore  natural  gas  infrastructure  (Statpipe)  with  the  Danish  off-­‐shore  natural  gas  infrastructure

(Harald  platform).

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Supplier  Norway100,00Statpipe  -­‐  NO  /  Harald  platform  -­‐  DK

PROJECTED  CAPACITY  INCREASES

NP  Send-­‐out  Denmark  (Offshore)

Security  of  Supply,  Market  integration  (Norwegian  off  shore  system  and  Danish/Swedish/German  market),  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (Denmark),  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

13

Page 14: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

France

14

Page 15: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Not  defined  yet

Dunkerque LNG Terminal

EdF

Dunkerque  LNG

LNG  Terminal

Interested  by  PCI  ?

IGAs

Web  Link

LNG-F-210 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Yes

100%

Yes

FID100%

2011  Q2FID

Construction

Commissioning

Last  completed  Phase  :

Regasification  facility

Expected  volume  (bcm/y)

Dunkerque  LNG2010  Q2

+13,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Ship  size  (m3)

Reloading  ability  ?

2011  Q3

2015/4

+570.000,00

+45,60

267.000,00

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

0,  EDF  (65%)  

0,  FLUXYS  (25%)  

0,  TOTAL  (10%)  

Private  Financing  (100,00%)  

15

Page 16: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Yes exit

Yes exit

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Dunkerque  LNG

Dunkerque  LNG  /  FRn

Dunkerque  LNG  /  Avringem  -­‐  BE

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)

Hub  France  (PEG  North)  (Dunkerque)501,60

519,00

270,00

LNG  regasification  Facility  located  in  Dunkirk

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  North)

Hub  France  (PEG  North)  (Dunkerque)

16

Page 17: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

Ship  size  (m3)

Reloading  ability  ?

2015

2019

+360.000,00

+24,00

270.000,00

Regasification  facility

Expected  volume  (bcm/y)

Fos  Faster2015

+8,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Not  yet

0%

Not  yet

Not  yet

Market  test0%

2015FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Fos Faster LNG Terminal

Fos  Faster  LNG

Fos  Faster  LNG

LNG  Terminal

www.fosfaster.com

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-223 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Vopak  (90%)  

0,  Shell  (10%)  

Undefined  (100,00%)  

17

Page 18: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

The  project  aims  to  build  a  new  LNG  terminal  at  Fos-­‐sur-­‐Mer  near  Marseille  in  France  with  an  intial  8bcm/a  capacity  (up  to  16  bcm/a)  allowing  all  type  of  LNG  carriers.  

Our  projected  terminal  is  dedicated  to  be  an  independent,  opened  and  multi-­‐customers  terminal,  including  aa  full  range  of  small  scale  services

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

273,00Fos  Faster

PROJECTED  CAPACITY  INCREASES

Security of Supply, Market integration (South Of France), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (France), N-­‐1 Regional (Western Europe (Spain, Italy, Switzerland)), Back-­‐up for renewables, To diversify thesources  of  supplyTo  debottleneck  the  South  of  FranceTo  open  an  independent  and  multi  customers  terminal  and  thus  contribute  to  the  market  opening  To  support  the  development  of  LNG  Small  scale  activities  (road-­‐transported  LNG,  LNG  transported  to  isolated  markets  such  as  islands,  LNG  as  a  fuel  for  trucks  and  vessels),  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

18

Page 19: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Ship  size  (m3)

Reloading  ability  ?

2016  Q2

2019/4

+190.000,00

+20,00

265.000,00

Regasification  facility

Expected  volume  (bcm/y)

Montoir  LNG  Terminal2016  Q1

+6,50

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

2016  Q1FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Montoir LNG Terminal Expansion

Elengy

Elengy

LNG  Terminal

www.elengy.com/en/projects/montoir-­‐extension.html

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-225 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Elengy  (100%)  

Undefined  (100,00%)  

19

Page 20: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

The  project  aims  to  expand  the  LNG  terminal  capacity  from  10  to  16.5  bcm/y  through  the  construction  of  regasification  units  and  storage  tanks.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  North)220,00Montoir  de  Bretagne

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)

Security of Supply, Market integration (see "A1" and "A2" at raw 160-­‐161), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (France), N-­‐1 Regional (France, Germany, Benelux countries, Switzerland, Italy (Northern)),Back-­‐up for renewables, Thanks to its location, Montoir LNG terminal is, from every points of view, one of the best entry gate in Western Europe for LNG coming from all over the world toward the core of the European gas market in particularFrance,  Germany,  Benelux  countries,  as  well  as  Switzerland  and  Northern  Italy  (through  Switzerland).  In  particular,  the  project  is  very  well  located  to  receive  LNG  from  North  America  where  LNG  liquefaction  is  developping  rapidly.Indeed,  LNG  has  the  tremendous  advantage  of  being  able  to  be  efficiently  delivered  closest  to  the  point  of  consumption,  by  optimizing  pipeline  and  sea  transportation.  Moreover,  the  recent  development  of  reloading  services  has  significantly  increased  the  fonctionalities  of  the  LNG  terminals,  enabling  them  to  offer  possibilities  equivalent  to  reverse  flows,  in  addition  to  the  classical  uses.  

A1: The project will strongly contribute to linking Northern and Southern European markets, through the hubs to which it give access in the North (France, Germany, Benelux countries, Switzerland, Northern Italy), and through "flexible floatingpipeline",  ie  ship  tranfers,    from  and  to  the  South  (in  particular  Spain  and  Portugal).A2:  The  project  will  also  enable  to  free  up  significant  part  of  the  already  existing  /  under  construction  pipeline  interconnection  capacity  between  Spain  and  France,  so  that  this  capacity  can  be  first  and  foremost  utilized  for  short  term  trading.

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

20

Page 21: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Ship  size  (m3)

Reloading  ability  ?

2016  Q2

2019/4

+80.000,00

+7,60

75.000,00

Regasification  facility

Expected  volume  (bcm/y)

Fos  Tonkin  LNG  Terminal2015  Q3

+2,50

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

28/02/11 Not  yet

Market  test0%

2015  Q3FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

No

Fos Tonkin LNG Terminal Expansion

Elengy

Elengy

LNG  Terminal

www.elengy.com/en/projects/fos-­‐tonkin-­‐open-­‐season.html

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-226 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Elengy  (100%)  

Undefined  (100,00%)  

21

Page 22: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

The  project  aims  to  prolong  the  operation  of  the  LNG  terminal  till  2035  and  to  expand  its  capacity    to  5.5  bcm/y  through  in  particular  the  construction  of  a  new  LNG  storage  tank.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  South)132,00Fos  Tonkin

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)

Security  of  Supply,  Market  integration  (see  "A1"  and  "A2"  at  raws  160  -­‐161),  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (France),  N-­‐1  Regional  (France,  Germany,  Benelux  countries,  Switzerland,  Italy  (Northern)

), Back-­‐up for renewables, Thanks to its location, the project is an excellent entry gate in Western Europe for LNG coming from the Mediterranean basin, toward the core of the European gas market in particular France, Germany, Benelux countries aswell as Switzerland and Northern Italy. The project is in particular very well adapted to receive LNG from Skikda (Algeria) where a new LNG liquefaction plant of 5.5 bcm/y dedicated to vessels up 75 000 m3 (up to Medmax vessels, exactly like FosTonkin  LNG  terminal),  has  recently  started.Indeed,  LNG  has  the  tremendous  advantage  of  being  able  to  be  efficiently  delivered  closest  to  the  point  of  consumption,  by  optimizing  pipeline  and  sea  transportation.  Moreover,  the  project  of  reloading  services  will  significantly  increased  the  fonctionalities  of  the  LNG  terminal,  enabling  it  to  offer  possibilities  equivalent  to  reverse  flows,  in  addition  to  the  classical  uses.

A1: The project will strongly contribute to linking Northern and Southern European markets, through the hubs to which it give access in the North (France, Germany, Benelux countries, Switzerland, Northern Italy), and through "flexible floatingpipeline",  ie  ship  tranfers,    from  and  to  the  South  (in  particular  Spain  Italy,  Malta  and  even  Greece).

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

22

Page 23: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Ship  size  (m3)

Reloading  ability  ?

2016  Q2

2020/2

+220.000,00

+28,00

270.000,00

Regasification  facility

Expected  volume  (bcm/y)

Fos  Cavaou  LNG  Terminal2016  Q2

+8,25

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

20/02/13 Not  yet

Planned0%

2016  Q2FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Fos Cavaou LNG Terminal Expansion

Elengy

Fosmax  LNG

LNG  Terminal

http://www.fosmax-­‐lng.com/en/who-­‐are-­‐we/projet-­‐de-­‐developpement.html

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-227 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Fosmax  LNG  (100%)  

Undefined  (100,00%)  

23

Page 24: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

The  project  aims  to  expand  the  LNG  terminal  capacity  from  8.25  to  16.5  bcm/y  through  the  construction  of  regasification  units  and  storage  tanks.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  South)308,00Fos  Cavaou

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)

Security of Supply, Market integration (see "A1" and "A2" at raw 160-­‐161), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (France), N-­‐1 Regional (France, Germany, Benelux countries, Switzerland, Italy (Northern)),Back-­‐up for renewables, Thanks to its location, Fos Cavaou LNG terminal it is from every points of view, the best entry gate in Western Europe for LNG coming from the Mediterranean basin and the Middle East (which represent more than 45% of theworld LNG production), toward the core of the European gas market in particular France, Germany, Benelux countries, as well as Switzerland and Northern Italy (through Switzerland). In addition, Fos Cavaou LNG terminal is also one of the best entrygate  in  Western  Europe  for  gas  coming  from  the  Atlantic  bassin  toward  the  core  of  the  European  gas  market.Indeed,  LNG  has  the  tremendous  advantage  of  being  able  to  be  efficiently  delivered  closest  to  the  point  of  consomption,  by  optimizing  pipeline  and  sea  transportation.Moreover,  the  recent  development  of  reloading  services  has  significantly  increased  the  fonctionalities  of  the  LNG  terminals,  enabling  them  to  offer  possibilities  equivalent  to  reverse  flows,  in  addition  to  the  classical  uses.  

A1: The project will strongly contribute to linking Northern and Southern European markets, through the hubs to which it give access in the North (France, Germany, Benelux countries, Switzerland, Northern Italy), and through "flexible floatingpipeline",  ie  ship  tranfers,    from  and  to  the  South  (Spain,  Italy,  Greece,  Malta  in  the  future).A2:  The  project  will  also  enable  to  free  up  significant  part  of  the  already  existing  /  under  construction  pipeline  interconnection  capacity  between  Spain  and  France,  so  that  this  capacity  can  be  first  and  foremost  utilized  for  short  term  trading.

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

24

Page 25: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014

2016

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

22014

+308,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

FID0%

2011  Q4FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Arc de Dierrey

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-036 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Core  system  developments,  GRTgaz  

(100%)  

Public  Financing  (12,00%)  

Private  Financing  (88,00%)  

25

Page 26: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exitYes exitYes entryYes exit

This  core  system  development  is  necessary  for  several  projects  in  the  North  (Dunkerque  LNG  terminal,  Merger  of  the  North  and  South  zones,  Reverse  capacity  at  Obergailbach,  capacities  increase  at  Oltingue)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)Hub  France  (PEG  North)Hub  France  (PEG  North)

0,00

0,000,000,00

Hub  France  (PEG  North)  (Dunkerque)Hub  France  (PEG  South)

Liaison  Nord  SudOltingue  (FR)  /  Rodersdorf  (CH)Medelsheim  (DE)  /  Obergailbach  (FR)Dunkerque  LNG  /  FRn

PROJECTED  CAPACITY  INCREASES

Hub  SwitzerlandHub  France  (PEG  North)  (Obergailbach)Hub  France  (PEG  North)

Hub  France  (PEG  South)

Security  of  Supply,  Market  integration  (France,  Germany,  Switzerland/Italy),  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  

Hub  France  (PEG  North)Liaison  Nord  Sud 0,00

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

26

Page 27: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2012

2013/4

+8,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12012

+51,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Permitting0%

2010  Q2FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Entry capacity increase from Belgium to France

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-037 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

French  secBon  -­‐  Specific  developments,  

GRTgaz    (100%)  

Public  Financing  (10,00%)  

Private  Financing  (90,00%)  

27

Page 28: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Transmission  systems  development(s)  in  FR  (and  BE)  to  increase  entry  capacity  in  FR  at  Taisnières  (from  590  to  640  GWh/d)  -­‐  OS  in  2009/2010

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Belgium50,00Blarégnies  (BE)  /  Taisnières  (H)  (FR)  (Segeo/Troll)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)

Security  of  Supply,  Market  integration  (France  and  Belgium),  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

28

Page 29: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

Developments for the Dunkerque LNG new terminal

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-038 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

No

FEED0%

2011  Q4FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

22013

+142,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2013

2015/4

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Specific  developments,  GRTgaz  (100%)  

Private  Financing  (100,00%)  

29

Page 30: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Security  of  Supply,  Market  integration  (France  and  Belgium),  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Dunkerque  LNG  /  FRn

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)250,00

The  connection  of  the  terminal  needs  spécific  transmission  system  developement  and  core  system  developements  (Arc  de  Dierrey)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)  (Dunkerque)

30

Page 31: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2012

2013/1

+36,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12012

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Permitting0%

2010  Q1FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Iberian-French corridor: Western Axis (CS Chazelles)

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-039 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

GRTgaz  secDon  -­‐  Specific  developments,  

GRTgaz    (100%)  

Public  Financing  (50,00%)  

Private  Financing  (50,00%)  

31

Page 32: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

GRTgaz  contribution  to  the  transmission  systems  developments  to  develop  FR-­‐ES  IP  at  Larrau  and  Biriatou,  OS  in  2009/2010

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  South)Hub  France  (PEG  TIGF)

70,00175,00

PIR  MIDI

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)Hub  France  (PEG  TIGF)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

32

Page 33: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Yes

Reverse capacity from France to Belgium at Veurne

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-040 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

No

FID0%

2012  Q2FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014

+26,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2014

2015/4

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

French  secBon,  GRTgaz      (100%)  

Private  Financing  (100,00%)  

33

Page 34: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Security  of  Supply,  Market  integration,  Reverse  Flows,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

New  IP  FR-­‐BE    (FR)  /  Alveringem-­‐Maldegem  (BE)

PROJECTED  CAPACITY  INCREASES

Hub  Belgium  (Zeebrugge  Beach)270,00

New  IP  near  Veurne  between  GRTgaz  and  Fluxys  with  capacity  from  FR  to  BE

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)  (Dunkerque)

34

Page 35: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2015

2017

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12015

+220,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

FID0%

2011FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Eridan

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-041 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Core  system  developments,  GRTgaz      

(100%)  

Public  Financing  (15,00%)  

Private  Financing  (85,00%)  

35

Page 36: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entryYes exitYes entryYes entry

This  development  of  the  core  transmission  system,  Saint  Martin  de  Crau  -­‐  Saint  Avit  pipeline,  is  necessary  for  entry/exit  capacity  increases  in  the  South  zone  and  to  merge  the  North  an  South  zones.

EEPR

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  South)Hub  France  (PEG  North)Hub  France  (PEG  South)

0,00

0,000,000,00

Hub  France  (PEG  TIGF)LNG  Terminals  France  (PEG  South)

Liaison  Nord  Sud

PIR  MIDI

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)Hub  France  (PEG  TIGF)Hub  France  (PEG  South)

Hub  France  (PEG  North)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

Hub  France  (PEG  South)Fos  (Tonkin/Cavaou) 0,00

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

36

Page 37: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2012  Q4

2013/3

+5,50

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12012  Q3

+58,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

No

0%

No

Construction0%

2010  Q1FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Girland - Artère de Guyenne Phase B

TIGF

TIGF

Pipeline  including  CS

www.tigf.fr

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-250 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  TIGF  (100%)  

Undefined  (100,00%)  

37

Page 38: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitNo entryYes entryNo exit

It's  a  DN  900  and  58  km  long  pipeline  that  conects  the  UGS  of  Lussagnet  with  Captieux  with  an  additional  compression  at  Sauveterre  (that  has  been  decided  in  June)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  TIGF)Hub  France  (PEG  South)Hub  France  (PEG  South)

180,00

175,00185,0070,00

Hub  France  (PEG  TIGF)

PIR  MIDI

PIR  MIDI

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  TIGF)Hub  France  (PEG  TIGF)Hub  France  (PEG  South)

Hub  France  (PEG  South)

Security  of  Supply,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

38

Page 39: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014  Q3

2015/4

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014  Q1

+95,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

FEED0%

2012  Q1FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Artère de l'Adour (former Euskadour) (FR-ES interconnection)

TIGF

TIGF

Pipeline  including  CS

www.artere-­‐adour-­‐tigf.fr

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-251 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Arcangues-­‐Coudures,  TIGF  (100%)  

Undefined  (100,00%)  

39

Page 40: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

It's  a  24  inches  and  95  km  long  pipeline  between  Arcangues  and  Coudures  that  will  allow  to  connect  (using  the  existing  infrastructure)  the  UGS  of  Lussagnet  with  the  Spanish  frontier.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  TIGF)Hub  Spain

60,0055,00

Biriatou  (FR)  /  Irun  (ES)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  TIGF)Hub  Spain

Security  of  Supply,  This  project  will  create  the  bidirectional  gas  s  flow  between  France  and  Spain  by  increasing  the  transport  capacity.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

40

Page 41: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2018

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2

+320,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

New interconnection IT-FR to connect Corsica

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-042 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

French  secBon,  GRTgaz        (100%)  

Undefined  (100,00%)  

41

Page 42: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

No entry

This  project  is  linked  to  the  GALSI  project  and  includes  an  offshore  pipeline  from  Sardinia  to  Corsica  and  onshore  pipelines  in  Corsica

Expected

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Italia  (Sardinia)20,00Porto-­‐Vecchio

PROJECTED  CAPACITY  INCREASES

Hub  France  (Corsica)

Security  of  Supply,  Market  integration,  Back-­‐up  for  renewables,  Access  to  Natural  gas  for  Corsica,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

42

Page 43: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2018

+9,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+190,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Val de Saône project

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-043 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Core  system  developments,  GRTgaz        

(100%)  

Private  Financing  (100,00%)  

43

Page 44: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

This reinforcement of the French Network consists in the looping of the Bourgogne pipeline (between Etrez and Voisines). In addition to the projetcs Arc de Dierrey in the North and ERIDAN in the South, this project is needed to merge GRTgaz'sNorth  and  South  market  zones.    

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  South)Hub  France  (PEG  North)

999,00999,00

Liaison  Nord  Sud

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)Hub  France  (PEG  North)

Security  of  Supply,  Market  integration,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

44

Page 45: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2018

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2

+71,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

New interconnection to Luxembourg

GRTgaz

GRTgaz

Pipeline  including  CS

www.grtgaz.com/en/home/major-­‐projects/plan-­‐decennal/10-­‐year-­‐development/

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-044 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

French  sec;on  -­‐  Specific  developments,  

GRTgaz        (100%)  

Private  Financing  (100,00%)  

45

Page 46: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes exit

New  interconnection  for  additional  firm  entry  capacitiy  from  France  to  Luxembourg

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)Hub  France  (PEG  North)

40,009,00

New  IP  France/Luxemburg

PROJECTED  CAPACITY  INCREASES

Hub  LuxemburgHub  Luxemburg

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

46

Page 47: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2017

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Reverse capacity from CH to FR at Oltingue

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-045 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

French  secBon  -­‐  Specific  developments,  

GRTgaz  -­‐-­‐  Infrastructure  Projects  

(100%)  

Private  Financing  (100,00%)  

47

Page 48: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Developements  needed  to  create  this  reverse  capacity

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

48

Page 49: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2022

+30,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

3

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Exit capacity increase to CH at Oltingue

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-046 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

French  secBon  -­‐  Specific  developments,  

GRTgaz        (100%)  

Private  Financing  (100,00%)  

49

Page 50: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitNo exit

Specific  transmission  system  develpements  to  increase  exit  capacity  to  CH  (design  to  confirm  according  to  the  market  demand)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)Hub  France  (PEG  North)

100,0040,00

Oltingue  (FR)  /  Rodersdorf  (CH)

PROJECTED  CAPACITY  INCREASES

Hub  SwitzerlandHub  Switzerland

Security  of  Supply,  Market  integration,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

50

Page 51: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020

+42,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+60,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Reverse capacity from France to Germany at Obergailbach

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-047 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

French  secBon  -­‐  Specific  developments,  

GRTgaz      (100%)  

Private  Financing  (100,00%)  

51

Page 52: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitNo exitNo exit

This  project  includes  pipelines  (including  compression)  and  changes  in  the  odorisation  system  (replacing  odoristaion  stations  at  the  entry  of  the  transmission  system  by  odorisation  stations  at  the  entry  of  the  regional  networks)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)Hub  France  (PEG  North)Hub  France  (PEG  North)

100,00180,00250,00

Medelsheim  (DE)  /  Obergailbach  (FR)

Medelsheim  (DE)  /  Obergailbach  (FR)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)  (Obergailbach)Hub  France  (PEG  North)  (Obergailbach)

Hub  France  (PEG  North)  (Obergailbach)

Security  of  Supply,  Market  integration,  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

52

Page 53: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2018

+10,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+63,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Developments for Montoir LNG terminal expansion at 12,5bcm - 1

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-048 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Specific  developments,  GRTgaz        (100%)  

Private  Financing  (100,00%)  

53

Page 54: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

This  entry  capacity  increase  at  Montoir  only  needs  specific  developments.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  North)55,00Montoir  de  Bretagne

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

54

Page 55: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020

+10,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2

+148,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

No

0%

No

0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Iberian-French corridor: Eastern Axis-Midcat Project

TIGF

TIGF

Pipeline  including  CS

www.tigf.fr

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-252 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  TIGF      (100%)  

Undefined  (100,00%)  

55

Page 56: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

In the French side, it's composed by a 120 km long pipeline between the frontier (near Le Perthus) and the CS of Barbaira, the installation of an aditional compression of 10 MW at Barbaira, and a 28 km long pipeline between Lupiac and Baran (Artèredu  Gascogne).

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  TIGF)Hub  Spain

80,00230,00

Le  Perthus

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  TIGF)Hub  Spain

Security  of  Supply,  Market  integration,  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National,  N-­‐1  Regional,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

56

Page 57: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2019

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

3

+170,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

2015FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Est Lyonnais pipeline

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-253 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Core  system  developments,  GRTgaz      

(100%)  

Private  Financing  (100,00%)  

57

Page 58: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

This  development  of  the  core  transmision  system  is  necessary  to  develop  entry  capacity  in  the  South  (Fos  Projects,  IP  with  spain,  storages)  and  contribute  to  the  South-­‐North  corridor  in  Western  Europe

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  South)0,00Fos  (Tonkin/Cavaou)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

58

Page 59: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2019

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+30,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

2015FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Developments for the Fos faster LNG new terminal

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-254 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Specific  developments,  GRTgaz      (100%)  

Private  Financing  (100,00%)  

59

Page 60: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryNo entry

In  addition  to  this  specific  connection,  the  reinforcement  of  the  core  transmission  system  is  also  needed  (ERIDAN,  East  Lyonnais  pipeline,Bourgogne  and/or  compressions  depending  on  the  developments  already  realized)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  South)LNG  Terminals  France  (PEG  South)

255,00383,00

Fos  (Tonkin/Cavaou)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)Hub  France  (PEG  South)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

60

Page 61: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2019

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

no

Fos Tonkin LNG expansion

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-255 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Specific  developments,  GRTgaz      (100%)  

Private  Financing  (100,00%)  

61

Page 62: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Only  core  system  developments  are  needed  for  this  expansion  :  they  will  depend  on  the  other  entry  capacity  increases  in  the  South  zone

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  South)80,00Fos  (Tonkin/Cavaou)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

62

Page 63: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020

+30,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

yes

Iberian-French corridor: Eastern Axis-Midcat Project (CS Montpellier and CS Saint Martin de Crau)

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-256 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

GRTgaz  secDon  -­‐  Specific  developments,  

GRTgaz    (100%)  

Private  Financing  (100,00%)  

63

Page 64: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

GRTgaz contribution to develop a new FR-­‐ES IP on the Eastern axis -­‐MidCat. In addition to these specific developments, the reinforcement of the core transmission system is also needed (ERIDAN, Arc Lyonnais pipeline, Val de Saône project and/orcompressions  depending  on  the  developments  already  realized)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  South)Hub  France  (PEG  TIGF)

80,00230,00

PIR  MIDI

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)Hub  France  (PEG  TIGF)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

64

Page 65: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2021

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+210,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

New line Between Chemery and Dierrey

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-257 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Core  system  developments,  GRTgaz        

(100%)  

Private  Financing  (100,00%)  

65

Page 66: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

This  core  system  development  develop  West-­‐East  capacity  transit  necessary  for  Montoir  LNG  terminal  expansion2  and  firm  reverse  flow  to  Germany

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  North)0,00Montoir  de  Bretagne

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

66

Page 67: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2021

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+200,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Developments for Montoir LNG terminal expansion at 16,5bcm - 2

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-258 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Specific  developments,  GRTgaz        (100%)  

Private  Financing  (100,00%)  

67

Page 68: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

This  entry  capacity  increase  at  Montoir  needs  specific  developments  and  core  system  developments  (New  line  between  Chemery  and  Dierrey).  

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  North)125,00Montoir  de  Bretagne

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  North)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

68

Page 69: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

no

Fosmax (Cavaou) LNG expansion

GRTgaz

GRTgaz

Pipeline  including  CS

http://www.grtgaz.com/fileadmin/plaquettes/en/10years2013_2022_EN.pdf

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-269 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Specific  developments,  GRTgaz      (100%)  

Private  Financing  (100,00%)  

69

Page 70: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Only  core  system  developments  are  needed  for  this  expansion  :  they  will  depend  on  the  other  entry  capacity  increases  in  the  South  zone.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  France  (PEG  South)327,00Fos  (Tonkin/Cavaou)

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  South)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

70

Page 71: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2014/1

+1,20

+4,80

Storage  facility

Working  volume  (mcm)

Hauterives

+60,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

2002

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

Priority  Project

No

Hauterives Storage Project - Stage 1

Storengy

Storengy

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-F-004 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  (100%)  

Undefined  (100,00%)  

71

Page 72: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Development  of  a  new  salt  cavity  storage.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

72

Page 73: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2015/1

+0,80

+3,20

Storage  facility

Working  volume  (mcm)

Hauterives

+40,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

2002

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Priority  Project

No

Hauterives - Stage 2

Storengy

Storengy

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-F-265 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  (100%)  

Undefined  (100,00%)  

73

Page 74: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Development  of  a  new  salt  cavity  storage.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

74

Page 75: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2022/4

+3,00

+9,60

Storage  facility

Working  volume  (mcm)

Alsace  Sud

+200,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

2005

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

No

Alsace Sud

Storengy

Storengy

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-002 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  (100%)  

Undefined  (100,00%)  

75

Page 76: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Creation  of  a  new  salt  cavity  storage  site  of  up  to  200  mcm  of  working  gas  volume

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  o  SoS  o  Market  Integration  (Increase  of  competition)The  project  will  contribute  to  the  increase  of  storage  capacity  in  France,  which  will  enhance  security  of  supply  and  provide  more  flexibility  to  the  market  thus  facilitating  competition.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

76

Page 77: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2015/4 +4,00

Storage  facility

Working  volume  (mcm)

Etrez  Gas  Storage

+60,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Etrez

Storengy

Storengy

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-003 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  (100%)  

Undefined  (100,00%)  

77

Page 78: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Extension  of  the  exisiting  salt  cavity  storage  facilities.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  o  Market  Integration  (Increase  of  competition)The  project  will  contribute  to  the  increase  of  storage  capacity  in  France,  which  will  enhance  security  of  supply  and  provide  more  flexibility  to  the  market  thus  facilitating  competition,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

78

Page 79: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2022/4

+7,00

+24,00

Storage  facility

Working  volume  (mcm)

Etrez  /Manosque  Gas  Storage

+315,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Etrez - Stage 2

Storengy

Storengy

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-264 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  (100%)  

Undefined  (100,00%)  

79

Page 80: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Extension  of  the  exisiting  salt  cavity  storage  facilities.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  o  Market  Integration  (Increase  of  competition)The  project  will  contribute  to  the  increase  of  storage  capacity  in  France,  which  will  enhance  security  of  supply  and  provide  more  flexibility  to  the  market  thus  facilitating  competition,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

80

Page 81: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Germany

81

Page 82: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Not  applicable

Regulated

2016/4

Production  facility

Expected  volume  (bcm/y)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Technical  Capacity  (bcm/y)

End  of  permitting  phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Yes

Project study on the integration of Power to Gas (PtG) facilities into the gas transmission system*

Open  Grid  Europe  GmbH

Open  Grid  Europe  GmbH

Production  Facility

Interested  by  PCI  ?

IGAs

Web  Link

PRD-N-301 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Open  Grid  Europe  GmbH  (100%)  

Undefined  (100,00%)  

82

Page 83: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Identification  of  potential  PtG  locations  in  North-­‐Western  Germany  and  analysis  of  specific  PtG  concepts.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security of Supply, Diversification of sources, Back-­‐up for renewables, Power-­‐to-­‐gas, The European goal to reduce CO2 emissions and to increase the share of renewable energy sources as well as the German decision to shut off the nuclear powerplants necessitate the medium and long term storage of electricity produced from fluctuating renewable sources. It is expected that PtG can provide an economic means to accomplish this goal. The study supports the PtG development by identifyingsuitable  PtG  locations  and  by  analysing  different  PtG  concepts.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

83

Page 84: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014/4

+15,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Yes

Extension of existing gas transmission capacity in the direction to Denmark - 1. Step

Gasunie  Deutschland  Transport  Services  GmbH

Gasunie  Deutschland  Transport  Services  GmbH

Pipeline  including  CS

www.gasunie.de

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-231 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gasunie  Deutschland  (100%)  

Undefined  (100,00%)  

84

Page 85: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)50,81Ellund  (GUD)

PROJECTED  CAPACITY  INCREASES

Hub  Denmark  (Ellund)

Security  of  Supply,  Market  integration,  )o  Better  connection  of  the  gas  hubs  (TTF  in  the  Netherlands  and  market  area  GASPOOL  in  Germany);o  Compensation  of  the  depletion  of  Danish  gas  fields  and  better  connection  of  gas  hubs;o  Connection  of  new  storages  to  the  GUD-­‐grid.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

85

Page 86: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2013  Q1

2014/1

+27,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

22013

+90,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Permitting0%

2012FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Installation of Nord Stream onshore project*

GASCADE  Gastransport  GmbH

GASCADE  Gastransport  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-289 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  GASCADE  (100%)  

Undefined  (100,00%)  

86

Page 87: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)Hub  Germany  (GASPOOL)

30,00105,60

Eynatten  (BE)  //  Lichtenbusch  /  Raeren  (DE)  (GASCADE)Gernsheim

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (NCG)Hub  Belgium

Market  integration  (GASPOOL  /  NCG  (Gernsheim)),  Diversification  of  sources,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

87

Page 88: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2013

2014

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2013

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Permitting0%

2013FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Installing a reverse flow in Mallnow*

GASCADE  Gastransport  GmbH

GASCADE  Gastransport  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-292 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  GASCADE  (100%)  

Undefined  (100,00%)  

88

Page 89: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

new  metering  station

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)168,00Mallnow

PROJECTED  CAPACITY  INCREASES

Interconnector  Poland  /  Yamal

Reverse  Flows,  Diversification  of  sources,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

89

Page 90: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Yes

Bretella

Fluxys

Fluxys  TENP  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-207 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Market  test0%

2014  Q1FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+11,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2017/4

7  to  11

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Fluxys  TENP  GmbH  (100%)  

Undefined  (100,00%)  

90

Page 91: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

Security  of  Supply,  Market  integration  (NCG  and  HUB  Belgium),  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (BE,  DE),  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Eynatten  (BE)  //  Lichtenbusch  /  Raeren  (DE)  (Fluxys  TENP)

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (NCG)Hub  Belgium  (Eynatten)

Building  an  additional  pipeline  between  Stolberg  and  Eynatten  to  allow  a  bi-­‐directional  flow  from  Stolberg  (i.e.  NCG  and  Gaspool)  to  Fluxys  Belgium.  This  is  part  of  the  mid  case  and  high  case  scenarios  of  the  reverse  flow  project.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (NCG)Hub  Belgium  (Eynatten)

91

Page 92: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Yes

Reverse Flow TENP Germany

Fluxys

Fluxys  TENP  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-208 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

Market  test0%

2014  Q1FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

2017/4

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Fluxys  TENP  GmbH  (100%)  

Undefined  (100,00%)  

92

Page 93: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exit

Security  of  Supply,  Market  integration  (NCG,  Gaspool,  PSV,  PEGNord),  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (DE),  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Wallbach  (Fluxys  TENP/FluxSwiss)Stolberg

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (GASPOOL)Hub  Germany  (NCG)

Reversing  the  TENP  compressor  stations  to  be  able  to  source  gas  from  the  south  (Italy)  into  Germany.  This  project  will  reverse  two  compression  stations  and  will  add  compression  capacity  in  Stolberg  to  transfer  gas  from  NCG  to  Gaspool.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  SwitzerlandHub  Germany  (NCG)

93

Page 94: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Not  defined  yet

Nordschwarzwaldleitung

terranets  bw  GmbH

terranets  bw  GmbH

Pipeline  including  CS

www.terranets-­‐bw.de

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-228 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

No

0%

No

Planned0%

2013  Q4FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014  Q1

+70,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2015  Q1

2015/4

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

NOS  2,  terranets  bw  (100%)  

NOS  1,  terranets  bw  (100%)  

Undefined  (100,00%)  

94

Page 95: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

No entry

Security  of  Supply,  Diversification  of  sources,  Diversification  of  routes,  Firm  capacity  can  be  provided  to  downstream  distribution  network  operator.  Security  of  Supply  will  be  increased  in  south-­‐west  Germany.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Au  am  Rhein

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (GASPOOL)72,00

pipeline  between  Au  am  Rhein,  coupling  to  TENP  and  Leonberg/Stuttgart

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (NCG)

95

Page 96: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Project  of  Common  Interest

Yes

Extension of existing gas transmission capacity in the direction to Denmark - 2. Step

Gasunie  Deutschland  Transport  Services  GmbH

Gasunie  Deutschland  Transport  Services  GmbH

Pipeline  including  CS

www.gasunie.de

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-232 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2

+63,50

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2015/4

+16,00

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Gasunie  Deutschland  (100%)  

Undefined  (100,00%)  

96

Page 97: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Security  of  Supply,  Market  integration,  o  Better  connection  of  the  gas  hubs  (TTF  in  the  Netherlands  and  market  ared  GASPOOL  in  Germany);o  Compensation  of  the  depletion  of  Danish  gas  fields  and  better  connection  of  gas  hubs;o  Connection  of  new  storages  to  the  GUD-­‐grid.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Ellund  (GUD)

PROJECTED  CAPACITY  INCREASES

Hub  Denmark  (Ellund)40,56

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)

97

Page 98: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Yes

MONACO section phase II (Finsing-Amerdingen)

bayernets  GmbH

bayernets  GmbH

Pipeline  including  CS

www.bayernets.de/start_netzinformation_en.aspx?int_name=_73792

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-240 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

1

No

0%

Not  yet

Market  test0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12016  Q4

+130,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2018/4

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

bayernets  GmbH  (100%)  

Undefined  (100,00%)  

98

Page 99: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Security of Supply, Market integration, The MONACO project is divided in two phases: 1. Burghausen-­‐Finsing and 2. Finsing-­‐Amerdingen. The new pipeline is targeted to link areas of high demand in Germany and further westwards with liquid gassources in and through Austria (Überackern/Burghausen at the Austrian border, Penta-­‐West, WAG, MEGAL, Hub CEGH Baumgarten) and of Italy (via TGL pipeline, planned to deliver mainly LNG gas northwards). The project increases physical flowcapacity  between  these  market  areas  and  therefore  contributes  to  market  integration,  as  well  as  accelerating  competition  through  the  increased  diversification  of  sources  and  diversification  of  routes.

The project will also provide better access of large Austrian gas reservoirs Haidach and 7 UGS to Germany and further westwards. It thus enhances the resilience of the gas network, shows positive impact on the remaining flexibility of the system andtherefore  contributes  to  Security  of  Supply  in  Europe.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

PROJECTED  CAPACITY  INCREASES

Pipeline  project

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

99

Page 100: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Yes

MONACO section phase I (Burghausen-Finsing)

bayernets  GmbH

bayernets  GmbH

Pipeline  including  CS

www.bayernets.de/start_netzinformation_en.aspx?int_name=_73792

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-241 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

1

No

0%

Not  yet

FEED0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014  Q4

+90,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2017/4

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

bayernets  GmbH  (100%)  

Undefined  (100,00%)  

100

Page 101: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Security of Supply, Market integration, The MONACO project is divided in two phases: 1. Burghausen-­‐Finsing and 2. Finsing-­‐Amerdingen. The new pipeline is targeted to link areas of high demand in Germany and further westwards with liquid gassources in and through Austria (Überackern/Burghausen at the Austrian border, Penta-­‐West, WAG, MEGAL, Hub CEGH Baumgarten) and of Italy (via TGL pipeline, planned to deliver mainly LNG gas northwards). The project increases physical flowcapacity  between  these  market  areas  and  therefore  contributes  to  market  integration,  as  well  as  accelerating  competition  through  the  increased  diversification  of  sources  and  diversification  of  routes.

The project will also provide better access of large Austrian gas reservoirs Haidach and 7 UGS to Germany and further westwards. It thus enhances the resilience of the gas network, shows positive impact on the remaining flexibility of the system andtherefore  contributes  to  Security  of  Supply  in  Europe.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

PROJECTED  CAPACITY  INCREASES

Pipeline  project

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

101

Page 102: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Not  applicable

Not  applicable

2020

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

2020FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

System enhancements, including the connection of gas-fired power plants, storages and the integration of power to gas facilities

Open  Grid  Europe  GmbH

Open  Grid  Europe  GmbH

Pipeline  including  CS

www.open-­‐grid–europe.com

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-243 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  OGE  (100%)  

Undefined  (100,00%)  

102

Page 103: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

<font size=3>Extension of the gas grid infrastructure according to the outcomes of the German Network Development Plan in line with demand forecasts and the optimisation of the overall economy, including the expansion and reversion ofcompressor  stations  and  a  feasibility  study  on  the  integration  of  power  to  gas  facilities  into  the  transmission  system.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  Back-­‐up  for  renewables,  Power-­‐to-­‐gas,  Energy  turnaround:  stabilisation  and  better  interlinkage  with  power  grid,  back-­‐up  for  renewable  energies,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

103

Page 104: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Not  applicable

Not  applicable

2020

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

2020FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Stepwise change-over to physical H-gas operation of L-gas networks

Open  Grid  Europe  GmbH

Open  Grid  Europe  GmbH

Pipeline  including  CS

www.open-­‐grid–europe.com

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-244 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  OGE  (100%)  

Undefined  (100,00%)  

104

Page 105: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Stepwise  change-­‐over  to  physical  H-­‐gas  operation  of  L-­‐gas  networks  (due  to  decreasing  L-­‐gas  supply)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  o  Security  of  Supplyo  Market  Integration  (Increase  of  competition)o  A  decline  in  availability  of  L-­‐gas  necessitates  action.Open Season 2008: The project prioritisation process has been carried out in a non-­‐discriminatory manner based on criteria suggested by BNetzA. It takes into account the factors competition, security of supply, as well as network efficiency.Capacities  were  allotted  to  new  market  entrants.  North-­‐south  and  west-­‐east  de-­‐bottlenecking  strengthens  security  of  supply.Future projects: The overall economic benefit of a physical change-­‐over from L (low calorific) to H-­‐gas (high calorific) is higher than permanent conversion. Furthermore, enabling access of storage and gas fired power stations to the networknecessitates  investments.  These  measures  also  serve  both  market  integration  and  security  of  supply.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

105

Page 106: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2017

2018/1

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12016  Q4

+26,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

new net connection from Rehden to Drohne (new covenant from NEP2012)*

GASCADE  Gastransport  GmbH

GASCADE  Gastransport  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-291 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  GASCADE  (100%)  

Undefined  (100,00%)  

106

Page 107: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

It  is  necessary  to  increase  the  capacity  of  the  pipeline  between  the  OGE  Infrastructure  (market  area  of  NCG)  and  GASCADE  (Market  area  of  GASPOOL).This  connection  will  increase  the  capacity  by  6  GW  to  ensure  the  supply  in  south-­‐west  Germany.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)144,00Drohne  GASCADE  /  OGE

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (NCG)

Market  integration  (GASPOOL  /  NCG),  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

107

Page 108: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020/3

+30,00

+0,90

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+25,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Expansion of Nord Stream connection to markets in western Europe - Exit Bunde-Oude*

Gasunie  Deutschland  Transport  Services  GmbH

Gasunie  Deutschland  Transport  Services  GmbH

Pipeline  including  CS

No  website  available

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-316 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

NoneGerman  sec2on,  

Gasunie  Deutschland  Transport  Services  GmbH  (100%)  

Dutch  sec2on  (if  any),  Gas  Transport  Services  

B.V.  (100%)  

Undefined  (100,00%)  

108

Page 109: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitNo exitNo exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Expansion of transport capacity for transport of additional future Russian supply landing at Greifswald via (the extension of) the Nord Stream pipelines (now under study) , to be further transported towards North West European markets partly viaexisting  pipelines  (western  Germany,  Netherlands,  UK,  Belgium,  France).

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)Hub  Germany  (GASPOOL)Hub  Germany  (GASPOOL)

338,00676,00169,00

Bunde  (DE)  /  Oude  Statenzijl  (H)  (NL)  (GUD)

PROJECTED  CAPACITY  INCREASES

Hub  Netherlands  (VIP  NL/Gaspool)Hub  Netherlands  (VIP  NL/Gaspool)

Hub  Netherlands  (VIP  NL/Gaspool)

Security  of  Supply,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

109

Page 110: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

Expansion of Nord Stream connection to markets in western Europe - Entry Greifswald*

Gasunie  Deutschland  Transport  Services  GmbH

Gasunie  Ostseeanbindungsleitung  GmbH

Pipeline  including  CS

No  website  available

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-321 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+100,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2020/3

+60,00

+0,90

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Gasunie  Ostseeanbindungsleitu

ng  GmbH  (100%)  

Undefined  (100,00%)  

110

Page 111: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

No entry

No entry

Yes entry

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Security  of  Supply,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Greifswald  /  GOAL

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (GASPOOL)

Hub  Germany  (GASPOOL)

Hub  Germany  (GASPOOL)1.188,00

338,00

679,00

Expansion of transport capacity for transport of additional future Russian supply landing at Greifswald via (the extension of) the Nord Stream pipelines (now under study) , to be further transported towards North West European markets partly viaexisting  pipelines  (western  Germany,  Netherlands,  UK,  Belgium,  France).

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Supplier  Russia  /  Nord  Stream  (Greifswald)Supplier  Russia  /  Nord  Stream  (Greifswald)Supplier  Russia  /  Nord  Stream  (Greifswald)

111

Page 112: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2022

+171,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Expansion of Nord Stream connection to markets in western Europe - Entry Greifswalder Bodden area*

GASCADE  Gastransport  GmbH

NEL  Gastransport  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-323 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Undefined  (100,00%)  

112

Page 113: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Onshore  project  to  create  further  gas  capacities  for  North  West  Europe,  in  case  one  of  an  extention  of  the  Nord  Stream  pipeline.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Supplier  Russia  /  Nord  Stream  (Greifswald)

857,00Greifswald  /  NEL

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (GASPOOL)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

113

Page 114: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

Expansion of Nord Stream connection to markets in western Europe - Exit Eynatten*

GASCADE  Gastransport  GmbH

GASCADE  Gastransport  GmbH

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-324 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

3

+440,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2022

+203,00

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Undefined  (100,00%)  

114

Page 115: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Security  of  Supply,  Market  integration,  Diversification  of  sources,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Eynatten  (BE)  //  Lichtenbusch  /  Raeren  (DE)  (GASCADE)Bunde  (DE)  /  Oude  Statenzijl  (H)  (NL)  (GASCADE)

PROJECTED  CAPACITY  INCREASES

Hub  Netherlands  (VIP  NL/Gaspool)Hub  Belgium374,00

234,00

Onshore  project  to  create  further  gas  capacities  for  North  West  Europe,  in  case  one  of  an  extention  of  the  Nord  Stream  pipeline.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)Hub  Germany  (GASPOOL)

115

Page 116: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2014/4

+3,00

+7,00

Storage  facility

Working  volume  (mcm)

Peckensen  Storage

+180,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Peckensen Gas Storage FID*

Storengy

Storengy  Deutschland  GmbH

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-F-317 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  Deutschland  (100%)  

Undefined  (100,00%)  

116

Page 117: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Extension  of  the  existing  salt  cavity  gas  storage.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security of Supply, Market integration (Western and Central Europe), Apart from the benefits listed above, the projects will contribute to increased flexibility of the system which will have a positive impact on both market integration and security ofsupply.  Thanks  to  its  location  (on  the  link  between  the  NGC  market  area  and  the  Gaspool  market  area),  the  project  will  have  a  positive  expected  influence  on  price  convergence  and  arbitrage  opportunities.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

117

Page 118: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Not  defined  yet

Harsefeld

Storengy

Storengy  Deutschland  GmbH

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-001 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Storage  facility

Working  volume  (mcm)

Harsefled  Gas  Storage

+120,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

2020/4

+3,60

+3,60

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

0,  Storengy  Deutschland  (100%)  

Undefined  (100,00%)  

118

Page 119: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Security  of  Supply,  Market  integration,  o  SoS  o  Market  Integration  (Increase  of  competition)The  project  will  contribute  to  the  increase  of  storage  capacity  in  France,  which  will  enhance  security  of  supply  and  provide  more  flexibility  to  the  market  thus  facilitating  competition.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

PROJECTED  CAPACITY  INCREASES

Extension  of  the  existing  salt  cavity  storage  facility  in  Germany

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

119

Page 120: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2017/4

+1,00

+3,00

Storage  facility

Working  volume  (mcm)

Peckensen  Storage

+100,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Peckensen Gas Storage

Storengy

Storengy  Deutschland  GmbH

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-005 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  Deutschland  (100%)  

Undefined  (100,00%)  

120

Page 121: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Extension  of  the  existing  salt  cavity  gas  storage.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security of Supply, Market integration (Western and Central Europe), Apart from the benefits listed above, the projects will contribute to increased flexibility of the system which will have a positive impact on both market integration and security ofsupply.  Thanks  to  its  location  (on  the  link  between  the  NGC  market  area  and  the  Gaspool  market  area),  the  project  will  have  a  positive  expected  influence  on  price  convergence  and  arbitrage  opportunities.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

121

Page 122: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2022/4

+7,00

+14,00

Storage  facility

Working  volume  (mcm)

Behringen  Gas  Storage

+1.000,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Behringen Gas Storage

Storengy

Storengy  Deutschland  GmbH

Storage  Facility

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-049 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  Deutschland  (100%)  

Undefined  (100,00%)  

122

Page 123: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Development  of  a  new  storage  facility  in  a  depleted  gas  field.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

123

Page 124: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Ireland

124

Page 125: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

Ship  size  (m3)

Reloading  ability  ?

2015

2018

+200.000,00

+16,20

265.000,00

Regasification  facility

Expected  volume  (bcm/y)

Shannon  LNG  Limited2014

+2,70

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction No

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Yes

0%

Yes

Market  test100%

2014FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Yes

Shannon LNG Terminal

Shannon  LNG

Shannon  LNG

LNG  Terminal

www.shannonlngplanning.ie

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-030 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

CHP  plant,  Hess  Corpora4on  (100%)  

Shannon  Pipeline,  Hess  Corpora4on  

(100%)  

LNG  terminal,  Hess  Corpora4on  (100%)  

Undefined  (100,00%)  

125

Page 126: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Shannon  LNG  proposes  to  construct  a  liquefied  natural  gas  (LNG)  terminal  on  the  southern  shore  of  the  Shannon  Estuary  in  County  Kerry,  Ireland.  The  ultimate  parent  company  of  Shannon  LNG  is  the  US  based  Hess  Corporation.

Shannon  LNG  has  obtained  all  of  the  major  permits  and  consents  for  the  LNG  project  including  planning  permission  for  the  terminal  and  26  KM  export  pipeline,  pipeline  rights  of  way  and  foreshore  leases  and  licenses.  

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  Ireland191,10Shannon  LNG

PROJECTED  CAPACITY  INCREASES

Hub  Ireland

Security of Supply, Market integration, Diversification of sources, Diversification of routes, N-­‐1 National (Ireland), Back-­‐up for renewables, The Shannon LNG project will increase Irelands security of gas supply. Ireland imports over 90% of its gas viatwo pipelines from Scotland. Ireland is unable to meet its N-­‐1 Infrastruture requirements under Regulation (EU) No 994/2010 demonstrated in the Commission for Energy Regulations Consultation Paper “Draft National Preventive Action Plan – Gas2012-­‐2014 Ireland” (CER/12/088)). If the permitted ultimate capacity from the Shannon LNG terminal is added to the CER's calculation, the result demonstrates that the Shannon LNG terminal has the potential to satisfy the N-­‐1 infrastructurerequirement. The initial phase of the Shannon LNG project (16.2 mcm/d) will be capable of supplying approximatly 60% of forecast Irish peak demand (26.6 mcm/d) for 2020/2021 (Calculated using 1 in 50 Winter Peak Day Demand Scenario forecast,CER 2012 Joint Gas Capacity Statement). The proposed LNG terminal will increase market integration and system flexibility by providing a new gas supply route to Ireland. The project supports emmission reductions and will enhance Irelands long-­‐term  security  of  supply  resiliance  by  providing  an  entirely  new  supply  source  for  Ireland  with  LNG  imported  from  geographies  that  may  include  Africa,  Middle  East,  North  America,  Russia  etc          ,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

126

Page 127: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2017

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+37,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Market  test0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Physical Reverse Flow at Moffat Interconnection Point

Gaslink

Gaslink

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-059 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  BGE(UK)  (100%)  

Undefined  (100,00%)  

127

Page 128: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

The  interconnection  point  at  Moffat  is  currently  uni-­‐directional  with  gas  flow  from  UK  to  Ireland.  This  project  would  be  to  make  the  Moffat  interconnection  point  bi-­‐directional.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

38,50Moffat

PROJECTED  CAPACITY  INCREASES

Security of Supply, Market integration (Ireland & UK; Ireland & Northern ireland), Reverse Flows, Diversification of sources, Diversification of routes, Back-­‐up for renewables, Biogas, 1.New sources of gas supplies will potentially be available in Irelandand Northern Ireland from 2017 onwards and there may be an over supply for exportation to the UK. In order to enable the physical exportation of gas, physical reverse flow is required at Moffat. 2. Increased participation by Irish shippers in the UKmarket  facilitates  closer  linkage  to  the  European  market.  3.  Contributes  to  the  viability  of  LNG  and  storage  projects.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

128

Page 129: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2016  Q1

2016/4 +0,86

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+50,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Market  test0%

FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Not  defined  yet

Twinning of South West Scotland Onshore System

Gaslink

Gaslink

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-060 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

2

0,  Bord  Gais  Eireann  (UK)  (100%)  

Undefined  (100,00%)  

129

Page 130: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Twinning  a  50km  section  of  pipeline  between  Cluden  and  Brighouse  Bay  in  South  West  Scotland.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security of Supply, Market integration (Increases interoperability between Ireland & UK; Ireland & Northern Ireland; UK & Isle of Man), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (Ireland), N-­‐1 Regional (Ireland,Northern Ireland & UK), Biogas, 1.Reinforcing the 50km single section of the SWSOS transmission system guarantees the supply capacity and the security to meet Ireland's future demand requirements in the short, medium and long term.2 Ireland ison the Western peripheral of Europe and is quite isolated from mainland Europe. Ireland would greatly benefit from any infrastructure that would further connect Ireland to the gas system in the UK. It would also remove a capacity 'bottleneck' onthe  Interconnection  System;  this  will  increase  the  Technical  Capacity  of  Moffat  Entry  Point  and  subsequently  increase  the  available  firm  capacity  that  can  be  offered  by  the  transporter  to  the  Shippers.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

130

Page 131: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2017

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Market  test0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Physical Reverse Flow on South North Pipeline

Gaslink

Gaslink

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-071 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gaslink  (100%)  

Undefined  (100,00%)  

131

Page 132: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Currently  gas  flow  between  Ireland  &amp;  Northern  Ireland  via  the  South  North  Pipeline  is  uni-­‐directional  (at  the  Gormanston  Interconnection  Point)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  United  Kingdom27,60Gormanston  (South-­‐North  Interconnection  Point)

PROJECTED  CAPACITY  INCREASES

Hub  Ireland

Security of Supply, Market integration (Northern Ireland), Reverse Flows, Diversification of routes, Back-­‐up for renewables, Biogas, 1.Physical reverse flow between Ireland and Northern Ireland is beneficial to the development of an integratedmarket on the island of ireland, having significant importance in the development and operation of a single gas market between both jurisdictions. 2 It would widen the market that is available to Northern Ireland gas market participants.3Contributes  to  the  viability  of  LNG  and  storage  projects.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

132

Page 133: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2015  Q2

2015/3

+2,80

+3,70

Storage  facility

Working  volume  (mcm)

Southwest  Kinsale  Gas  Storage  Expansion2014  Q4

+174,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  yet

100%

Not  yet

Planned85%

2013  Q4FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Southwest Kinsale Storage Expansion Project

Kinsale  Energy  Ltd

Kinsale  Energy  Ltd

Storage  Facility

www.kinsale-­‐energy.ie

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-197 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Kinsale  Energy  Ltd  (100%)  

Undefined  (100,00%)  

133

Page 134: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exit

The  project  involves  the  expansion  of  the  existing  Southwest  Kinsale  storage  facility  from  226mcm  to  400mcm  through  the  drilling  of  a  new  well  (s)  and  process  equipment  modifications  to  provide  additional  injection  /  withdrawal  capacity

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  IrelandStorage  Ireland

30,8040,70

Kinsale  Southwest

PROJECTED  CAPACITY  INCREASES

Hub  IrelandStorage  Ireland

Security  of  Supply,  Market  integration,  Diversification  of  sources,  N-­‐1  National  (Ireland),  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

134

Page 135: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Luxembourg

135

Page 136: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014  Q2

2017/3

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014  Q2

+2,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

No

0%

No

Construction0%

2013  Q3FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

OS GRTgaz/Creos

Creos  Luxembourg  S.A.

Creos  Luxembourg  S.A.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-013 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Creos  Luxembourg  (100%)  

Public  Financing  (20,00%)  

Private  Financing  (80,00%)  

136

Page 137: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

add  entry  capacity  from  France  to  Lux

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  North)40,00New  IP  France/Luxemburg

PROJECTED  CAPACITY  INCREASES

Hub  Luxemburg

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National,  N-­‐1  Regional,  o  Security  of  Supplyo  Extension  of  transport  capacity  of  Russian  gas  to  the  Westo  Integration  of  Nord  Stream  off-­‐  and  on-­‐Shore  in  the  European  gas  infrastructure,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

137

Page 138: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

The Netherlands

138

Page 139: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

Ship  size  (m3)

Reloading  ability  ?

2015  Q3

2018/3

+180.000,00

+11,00

266.000,00

Regasification  facility

Expected  volume  (bcm/y)

Gate  terminal  Rotterdam2007  Q4

+4,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction No

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Yes

100%

Yes

Permitting0%

2015  Q3FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Gate terminal phase 3

Gate  Terminal  B.V.

Gate  Terminal  B.V.

LNG  Terminal

www.gateterminal.com

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-050 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  OMV    (5%)  0,      (0%)  

0,  Royal  Vopak  NV      (48%)  

0,  NV  Nederlandse  Gasunie    (48%)  

Public  Financing  (39,00%)  

Private  Financing  (61,00%)  

139

Page 140: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Increase  the  capacity  by  4  BCM  p.a.  from  the  current  12  BCM  p.a.  to  16  BCM  p.a.

Unknown   Unknown  

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  Netherlands121,00Gate  Terminal  (I)

PROJECTED  CAPACITY  INCREASES

Hub  Netherlands

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  Back-­‐up  for  renewables,  o  SoS  o  Market  Integration  (Increase  of  competition)Gate  terminal  obtained  an  exempted  ex  Art  22  Gas  Directive  2003/55/EC.  In  order  to  obtain  an  exemption  it  needed  to  be  demonstrated  that  Gate  terminal  enhanced  both  security  of  supply  and  the  competition  on  the  gas  market.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

140

Page 141: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014/3

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+100,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

FID0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

System Enhancements FID update - Gas Transport Services

Gasunie  Transport  Services  B.V.

Gasunie  Transport  Services  B.V.

Pipeline  including  CS

www.integratedopenseason.com  

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-268 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gas  Transport  Services  B.V.  (100%)  

Undefined  (100,00%)  

141

Page 142: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes entryYes entryYes exitYes entry

Various  system  capacity  enhancements  (further  expansion  of  gas  roundabout,  Integrated  Open  Season,  connection  to  Bergermeer  Storage)

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Netherlands  (VIP  NL/NCG)Hub  Netherlands  (VIP  NL/Gaspool)

203,00

97,0024,0073,00

Hub  NetherlandsStorage  Germany

Virtual  IP  (GTS)  NL-­‐DEVirtual  Ips  (GTS)  NL-­‐DE  (NCG)Virtual  Ips  (GTS)  NL-­‐DE  (Gaspool)Virtual  IP  (GTS)  NL-­‐BE

PROJECTED  CAPACITY  INCREASES

Hub  NetherlandsHub  NetherlandsHub  Netherlands  (VIP  NL/BE)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  o  SoS  o  Market  Integration  (Increase  of  competition)o  Importo  Quality  Conversiono  Security  of  SupplyFurther  expansion  of  the  gas  roundabout  increases  SoS  since  it  enables  additional  import  of  gas  and  also  connects  storages  to  the  gas  networks.  Furthermore,  interconnection  capacity  between  TSOs  is  increased  which  increases  market  integration.,  

Hub  NetherlandsUGS  -­‐  NL  -­‐  GTS/DE 111,00

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

142

Page 143: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Blending

Gasunie  Transport  Services  B.V.

Gasunie  Transport  Services  B.V.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-191 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gas  Transport  Services  (100%)  

Undefined  (100,00%)  

143

Page 144: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Additional  blending  facilities  to  allow  additional  Quality  Conversion

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  Diversification  of  sources,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

144

Page 145: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2018

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+25,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Entry capacity expansion GATE terminal

Gasunie  Transport  Services  B.V.

Gasunie  Transport  Services  B.V.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-192 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gas  Transport  Services  (100%)  

Undefined  (100,00%)  

145

Page 146: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Expansion  of  entry  capacity  into  GTS  network

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  Netherlands200,00Gate  Terminal  (I)

PROJECTED  CAPACITY  INCREASES

Hub  Netherlands

Security  of  Supply,  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

146

Page 147: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2015

+540,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Gas Compressor Optimisation Program

Gasunie  Transport  Services  B.V.

Gasunie  Transport  Services  B.V.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-193 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gas  Transport  Services  (100%)  

Undefined  (100,00%)  

147

Page 148: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Project  is  carried  out  in  order  to  to  comply  with  Industrial  Emissions  Directive

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Sustainability  by  reduction  of  emissions,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

148

Page 149: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2022

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

H-gas transport from NL to D*

Gasunie  Transport  Services  B.V.

Gasunie  Transport  Services  B.V.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-313 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  GTS  (100%)  

Undefined  (100,00%)  

149

Page 150: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  NetherlandsHub  Netherlands  (VIP  NL/NCG)

240,00240,00

Virtual  Ips  (GTS)  NL-­‐DE  (NCG)Bocholtz

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (NCG)Hub  Netherlands  (VIP  NL/NCG)

Security  of  Supply,  Market  integration,  Diversification  of  sources,  Diversification  of  routes,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

150

Page 151: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2018

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Transport from OSZ/Bunde to Julianadorp*

Gasunie  Transport  Services  B.V.

Gasunie  Transport  Services  B.V.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-314 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  GTS  (100%)  

Undefined  (100,00%)  

151

Page 152: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryNo exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Firming  up  transmission  capacity

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Netherlands  (VIP  NL/Gaspool)Hub  Netherlands

170,000,00

Virtual  Ips  (GTS)  NL-­‐DE  (Gaspool)Julianadorp  (GTS)  /Balgzand  (BBL)

PROJECTED  CAPACITY  INCREASES

Interconnector  Netherlands  /  BBLHub  Netherlands

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

152

Page 153: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2012  Q2

2014/1

+42,00

+57,00

Storage  facility

Working  volume  (mcm)

Gas  Storage  Bergermeer2012  Q2

+4.100,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Permitting0%

2009  Q4FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

Gas Storage Bergermeer (GSB)

TAQA  Gas  Storage  B.V.

TAQA  Gas  Storage  B.V.

Storage  Facility

www.bergermeergasstorage.com/

Interested  by  PCI  ?

IGAs

Web  Link

UGS-F-052 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  TAQA  Energy  B.V  (60%)  

0,  EBN  B.V.    (40%)  

Private  Financing  (100,00%)  

153

Page 154: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

Open  access  seasonal  storage,  4.1  BCM  working  gas  

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Storage  NetherlandsHub  Netherlands

627,00462,00

Bergermeer

PROJECTED  CAPACITY  INCREASES

Storage  NetherlandsHub  Netherlands

Security  of  Supply,  Market  integration  (Trading,  infrastructure  and  transport  in  northwestern  Europe),  Diversification  of  sources,  N-­‐1  National  (Netherlands),  Back-­‐up  for  renewables,  o  SoS  o  Market  Integration  (Increase  of  competition)Bergermeer Gas Storage will significantly enhance the security of energy supply to Dutch and European consumers, providing a reserve of the equivalent to the annual gas consumption of approximately 1.6 million Dutch households. The plannedworking  volume  amounts  to  4.1  bcm.    It  will  also  be  a  major  contributor  to  liquidity  in  the  North-­‐West  European  gas  markets.  The  project  is  a  valuable  contribution  towards  the  ambition  the  Dutch  State  to  realise  the  ‘gas  roundabout  of  North-­‐West  Europe’  in  The  Netherlands.Once  commercially  operational,  the  majority  of  the  capacity  of  the  facility  will  be  made  available  for  third  party  access.  This  will  contribute  to  increased  competition  on  the  market.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

154

Page 155: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Sweden

155

Page 156: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

Ship  size  (m3)

Reloading  ability  ?

2015

+20.000,00

+2,00

30.000,00

Regasification  facility

Expected  volume  (bcm/y)

Gothenburg  LNG  (preliminary)

+0,50

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction Yes

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

1/06/12 Not  yet

0%

FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Not  defined  yet

Gothenburg LNG (preliminary)

Swedegas  AB

Swedegas  AB

LNG  Terminal

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-032 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None0,  Vopak  LNG  Holding  

BV  (50%)  0,  Swedegas  AB  (50%)  

Private  Financing  (100,00%)  

156

Page 157: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

A  LNG  terminal,  including  connection  to  the  transmission  grid,  placed  in  the  Gothenburg  harbor.  

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

LNG  Terminals  Sweden24,00Gothenburg  LNG

PROJECTED  CAPACITY  INCREASES

Hub  Sweden

Security  of  Supply,  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  Facilitates  supply  to  non  grid  customers,  such  as  industry  replacing  oil  and  future  bunkering  of  ships  to  comply  with  the  coming  SECA  regulation.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

157

Page 158: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

United Kingdom

158

Page 159: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

Isle of Grain - Phase 4 Expansion*

National  Grid  Gas  plc

National  Grid  Gas  plc

LNG  Terminal

http://www.nationalgrid.com/uk/grainlng

Interested  by  PCI  ?

IGAs

Web  Link

LNG-N-290 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Yes

0%

Yes

Market  test0%

FID

Construction

Commissioning

Last  completed  Phase  :

Regasification  facility

Expected  volume  (bcm/y)

Isle  of  Grain

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction No

Storage  capacity  (m3)

Send-­‐out  (mcm/d)

End  of  permitting  phase

Ship  size  (m3)

Reloading  ability  ?

2018

Considered  TPA  Regime

Considered  Tariff  Regime Not  applicable

Regulated

0,  Na8onal  Grid  (100%)  

Private  Financing  (100,00%)  

159

Page 160: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Security  of  Supply,  Diversification  of  sources,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

PROJECTED  CAPACITY  INCREASES

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

160

Page 161: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014

+118,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

3

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

FID0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

System Capacity Enhancements FID

National  Grid  Gas  plc

National  Grid  Gas  plc

Pipeline  including  CS

www.nationalgrid.com/

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-025 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Na3onalgrid  (100%)  

Private  Financing  (100,00%)  

161

Page 162: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

New  electric  drive  unit  to  be  installed  as  part  of  the  Emissions  Reduction  Programme.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

The compression fleet enhancements currently being completed by National Grid are installing alternative compression fuel capability at selected sites; this will enable the bulk of compression at these sites to be electrically driven thereby reducingstation  emission  levels.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

162

Page 163: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

Not  defined  yet

System Capacity Enhancements non-FID - National Grid

National  Grid  Gas  plc

National  Grid  Gas  plc

Pipeline  including  CS

www.nationalgrid.com/

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-026 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2

+93,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2018

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Na3onalgrid  (100%)  

Private  Financing  (100,00%)  

163

Page 164: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

The system capacity enhancements proposed by National Grid will ensure that despite the uncertainty regarding the pattern of supplies – in terms of both volume and location – sufficient gas can be transmitted under a variety of supply scenarios inorder  to  meet  both  the  predicted  peak  demand  and  lower  levels  of  demand.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

PROJECTED  CAPACITY  INCREASES

New  pipelines  to  be  constructed  as  part  of  the  pre-­‐FID  System  Capacity  Enhancements

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

164

Page 165: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014

2016

+9,50

+0,20

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

Not  relevant

Planned0%

2013FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Yes

Physical reverse flow from Northern Ireland to Great Britain and Republic of Ireland via Scotland to Northern Ireland pipeline

Premier  Transmission  Ltd

Premier  Transmission  Ltd

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-027 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Premier  Transmission  Ltd  

(100%)  

Undefined  (100,00%)  

165

Page 166: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

No exit

Installation of bi-­‐drectional compression on Scotland to Northern Ireland pipeline (SNIP); pipework modifications at 2 AGI's to allow bidirectional metering and flow control and moving gas odourisation point to a new point(s) downstream of thebidirectional  transmission  system.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

264,00Twynholm:  Scotland  -­‐  Northern  Ireland  (SNIP)

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (Ireland),  Back-­‐up  for  renewables,  ,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

166

Page 167: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

Network Extensions to the West of Northern Ireland*

Premier  Transmission  Ltd

Premier  Transmission  Ltd

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-293 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+177,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2018

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  TBC  (100%)  

Undefined  (100,00%)  

167

Page 168: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Security  of  Supply,  Diversification  of  routes,  Back-­‐up  for  renewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

PROJECTED  CAPACITY  INCREASES

The  project  aims  to  extend  the  existing  Northern  Ireland  natural  gas  network  to  the  five  largest  towns  in  the  counties  Tyrone,  Fermanagh  and  South  Londonderry.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

168

Page 169: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2014/4

+16,00

+16,00

Storage  facility

Working  volume  (mcm)

Stublach  Gas  Storage

+100,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Yes

0%

Yes

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Stublach - Stage 1

Storengy

Storengy  UK

Storage  Facility

www.storengy.co.uk/About-­‐Storengy/Projects.php

Interested  by  PCI  ?

IGAs

Web  Link

UGS-F-006 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  UK  (100%)  

Undefined  (100,00%)  

169

Page 170: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Development  of  a  new  salt  cavern  storage  facility  in  the  UK.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  N-­‐1  National  (UK),  N-­‐1  Regional  (UK,  Ireland),  Back-­‐up  for  renewables,  o  Market  Integration  (Increase  of  competition)The  project  will  contribute  to  the  increase  of  security  of  supply  in  the  region  and  will  provide  more  flexibility  to  the  market  thus  facilitating  competition.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

170

Page 171: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Negotiated  (e.g.  Exemption)

2018/2

+5,20

+8,50

Storage  facility

Working  volume  (mcm)

Saltfleetby  UGS

+775,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Yes

100%

Yes

Permitting100%

2015  Q2FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Saltfleetby

Wingas  Storage  UK  Ltd

Wingas  Storage  UK  Ltd

Storage  Facility

www.wingas-­‐storage.com/

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-033 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Wingas  Storage  UK  Ltd  (100%)  

Private  Financing  (100,00%)  

171

Page 172: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exit

Conversion  of  the  Saltfleetby,  Lincolnshire,  gas  field  to  a  seasonal  gas  storage  facility

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  United  KingdomStorage  United  Kingdom

57,2093,50

Saltfleetby

PROJECTED  CAPACITY  INCREASES

Hub  United  KingdomStorage  United  Kingdom

Security of Supply, The project will provide two clear benefits. First, it will increase the level of gas storage in the UK . Secondly it will provide storage capacity for the shareholders and third parties to enable them better to meet their commercialobjectives,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

172

Page 173: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2014  Q1

2017/4

+32,00

+32,00

Storage  facility

Working  volume  (mcm)

2015  Q2

+348,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Construction0%

2013  Q3FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

King Street Energy Storage Project

King  Street  Enegy  Ltd

King  Street  Enegy  Ltd

Storage  Facility

www.kingstreetenergy.com

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-087 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

1

0,  King  Street  Energy    (100%)  

Undefined  (100,00%)  

173

Page 174: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exit

Storage  facility;  Salt  Cavern  Storage  Facility

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  United  KingdomStorage  United  Kingdom

352,00352,00

King  Street

PROJECTED  CAPACITY  INCREASES

Hub  United  KingdomStorage  United  Kingdom

Market  integration,  Market  Integration  (Increase  of  competition)Project  increases  available  gas  storage  in  the  UK,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

174

Page 175: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2016

2018

+30,00

+30,00

Storage  facility

Working  volume  (mcm)

Preesall2013

+600,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Not  relevant

0%

No

Planned0%

2013FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Not  defined  yet

Preesall Gas Storage

Halite  Energy  Group  Ltd

Halite  Energy  Group  Ltd

Storage  Facility

www.halite-­‐energy.co.uk/

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-203 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  DE  Shaw  (100%)  

Undefined  (100,00%)  

175

Page 176: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

A  fast  cycle  salt  cavern  project  with  shallow  depths  allowing  for  rapid  turnaround  at  low  operating  costs

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Storage  United  KingdomHub  United  Kingdom

330,00330,00

Preesall

PROJECTED  CAPACITY  INCREASES

Storage  United  KingdomHub  United  Kingdom

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

176

Page 177: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

2020

+16,00

+16,00

Storage  facility

Working  volume  (mcm)

Stublach  Gas  Storage

+300,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

Yes

0%

Yes

Construction0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Stublach - Stage 2

Storengy

Storengy  UK

Storage  Facility

www.storengy.co.uk/About-­‐Storengy/Projects.php

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-266 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Storengy  UK  (100%)  

Undefined  (100,00%)  

177

Page 178: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Development  of  a  new  salt  cavern  storage  facility  in  the  UK.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

PROJECTED  CAPACITY  INCREASES

Security  of  Supply,  Market  integration,  N-­‐1  National  (UK),  N-­‐1  Regional  (UK,  Ireland),  Back-­‐up  for  renewables,  o  Market  Integration  (Increase  of  competition)The  project  will  contribute  to  the  increase  of  security  of  supply  in  the  region  and  will  provide  more  flexibility  to  the  market  thus  facilitating  competition.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

178

Page 179: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Project  of  Common  Interest

Yes

Islandmagee Gas Storage Facility*

Premier  Transmission  Ltd

Islandmagee  Storage  Ltd

Storage  Facility

www.islandmageestorage.com

Interested  by  PCI  ?

IGAs

Web  Link

UGS-N-294 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Yes

100%

Yes

Planned100%

2015  Q1FID

Construction

Commissioning

Last  completed  Phase  :

Storage  facility

Working  volume  (mcm)

Islandmagee  Storage  Facility2013  Q4

+500,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Injectability  (mcm/d)

Deliverability  (mcm/d)

End  of  permitting  phase

2015  Q1

2018/2

+12,00

+22,00

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

0,  Islandmagee  Storage  Limted  (100%)  

Undefined  (100,00%)  

179

Page 180: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

No exit

*  A  new  project  in  the  GRIP  2014-­‐2023  data  collection  window,  that  was  not  yet  in  last  TYNDP  2013-­‐2022

Security of Supply, Market integration (Northern Ireland / Ireland / Great Britain), Reverse Flows, Diversification of routes, N-­‐1 National (Northern Ireland / Ireland / Great Britain), N-­‐1 Regional (Northern Ireland / Ireland / Great Britain), Back-­‐up forrenewables,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Moffat

PROJECTED  CAPACITY  INCREASES

12,00

IMSL plans to create seven caverns, capable of storing up to a total of 500 million cubic metres of gas. This facility will safeguard Northern Ireland's ability to meet the increasing peak gas demand, whilst also providing a greater degree of security ofsupply  to  Ireland  and  Great  Britain.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

180

Page 181: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 I Annex A

Projects outside NW Region

181

Page 182: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

GAZELLE project

NET4GAS,  s.r.o.

NET4GAS,  s.r.o.

Pipeline  including  CS

http://www.net4gas.cz/en/projekt-­‐gazela/

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-134 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Yes

0%

Yes

Construction100%

2012FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12012

+158,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2013

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

0,  BRAWA,  a.s.  (100%)  

Undefined  (100,00%)  

182

Page 183: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

Security  of  Supply,  Market  integration  (CEE  Region),  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (the  Czech  Republic),  N-­‐1  Regional  (CEE  Region),  Back-­‐up  for  renewables,  Power-­‐to-­‐gas,  Biogas,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Opal  (DE)/Brandov  (CZ)

PROJECTED  CAPACITY  INCREASES

Interconnector  Czech  Republic  /  Gazelle960,00

The  project  creates  together  with  the  projects  Nord  Stream  and  OPAL  the  so  called  Northern  Route  for  Russian  gas  supplies  to  Europe  and  it  has  important  influence  on  increasing  security  of  supply  through  the  diversification  of  gas  routes.  

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Interconnector  Germany  (GASPOOL)  /  OPAL

183

Page 184: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2015/4

+21,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

No

0%

No

FID0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

No

CS Border at Biriatou)

Enagás  S.A.

ETN  (Enagás  Transporte  del  Norte)

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-F-156 FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Enagás  S.A.  (100%)  

Private  Financing  (100,00%)  

184

Page 185: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exitYes entry

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  SpainHub  France  (PEG  TIGF)

55,0055,00

Biriatou  (FR)  /  Irun  (ES)

PROJECTED  CAPACITY  INCREASES

Hub  SpainHub  France  (PEG  TIGF)

Security  of  Supply,  Market  Integration,  Enhancement  of  Internal  Network;  reduction  of  internal  congestion,  N-­‐1  compliance,  Integration  of  LNG  plants,  Integration  of  UGS,  Integration  of  new  Gas  fired  power  plants,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

185

Page 186: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Project  of  European  Interest

Yes

GALSI Pipeline

Edison

Galsi  S.p.A.

Pipeline  including  CS

www.galsi.it

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-012 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

1

Not  relevant

0%

Not  relevant

FEED0%

2014  Q2FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

32013  Q4

+861,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2015  Q1

2018/1

+151,00

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Hera  Trading  Srl  (10%)  

0,  Sfirs  Spa  (12%)  

0,  Enel  Produzione  Spa  (16%)  

0,  Edison  SpA  (21%)  

0,  Sonatrach  (42%)  

Undefined  (100,00%)  

186

Page 187: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Yes entry

Yes entry

Yes exit

Yes exit

Security  of  Supply,  Market  integration  (The  Galsi  project  represents  an  unique  opportunity  to  bring  natural  gas  to  Sardinia  island,  currently  not  connected  to  the  Italian  gas  network.  Similar benefits could potentially be further extended to Corsica, through the Cyrénéé Projct (see above), improving thereby cohesion within Europe and the already excellent relations between Italy and France. ), Reverse Flows, Diversification ofsources,  Diversification  of  routes,  N-­‐1  National  (On the basis of the “Transportation Capacity Multi – Annual” as published in Snam web site, in the year of commissioning of Galsi project, the largest gas supply infrastructure to Italy – in terms of transportation capacity – will be the Trans AustrianGas  pipeline  (TAG)  with  a  firm  capacity  of  107.000.000  Sm3/day  at  the  entry  point  of  Tarvisio.Therefore,  in  the  event  of  technical  or  political  disruption  of  the  TAG  pipeline,  additional  capacities  could  be  made  available  by  maximizing  the  gas  flow  in  the  Galsi  pipeline,  to  an  extent  that  will  depend  upon  the  then  prevailing  operating  conditions.), Back-­‐up for renewables, Power-­‐to-­‐gas, Biogas, -­‐ The Galsi project will improve security of supply in Italy and Europe, providing for a new and more efficient route for Algerian gas to reach the centre of Italian gas consumption (located in northernItaly) and further on the northern European markets. In the longer term, with the development of new projects interconnecting different gas sources in Africa (e.g. new Algerian shale gas or TSGP project for Nigerian gas), the Galsi pipeline couldprovide  a  highly  strategic  diversification  of  gas  supply  routes  to  European  markets  and  their  supply  flexibility.-­‐ The Galsi project will contribute to the creation of an Italian gas hub for gas supply to Europe which, through the increase of gas liquidity, will enable the export of major gas volumes from Italy to other European markets through the development ofreverse  flow  capacities.  -­‐ Reduction of GHG emissions: the Galsi project complies with sustainable development guidelines, i.e. the promotion of the substitution of high pollutant fossil fuels with a low pollutant such as natural gas, the improvement of efficiency in theelectricity  production  by  switching  from  other  fossil  fuels  to  natural  gas,  and  the  penetration  of  the  use  of  natural  gas  in  industrial/residential  and  tertiary  sector.  -­‐ Support back-­‐up of renewable energy: a significant quota of electricity generation in Italy (today ~50%) is represented by CCGTs whose utilization is increasingly shifting towards a back-­‐up of RES, in the light of their dramatic increase witnessed inthese  last  years.-­‐  Market  Integration:  through  GALSI,  new  entrants  will  be  able  to  develop  and/or  consolidate  their  market  positions  in  the  Italian  gas  market  through  an  independent  infrastructure;,  

Hub  Italia  (Sardinia)Porto  Botte  (Galsi) 244,00

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Interconnector  Italia  (National)  /  GALSIInterconnector  Algeria  (International)  /  GALSI

Olbia  (Galsi)

Algerian  Coast  (Galsi)

Piombino  (Galsi)

PROJECTED  CAPACITY  INCREASES

Interconnector  Italia  (National)  /  GALSI

Interconnector  Algeria  (International)  /  GALSI

Hub  Italia

Hub  Italia  (Sardinia)

244,00

30,50

244,00

244,00

Gas  pipeline  project  aiming  to  create  a  new  link  between  Algeria  and  Italy  via  Sardinia

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Interconnector  Italia  (National)  /  GALSI

Hub  Italia  (Sardinia)

Supplier  Algeria

187

Page 188: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Project  of  common  interest

Yes

Tauerngasleitung Gas Pipeline Project

Tauerngasleitung  GmbH

Tauerngasleitung  GmbH

Pipeline  including  CS

www.tauerngasleitung.at

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-035 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

No

0%

Not  yet

28/04/1026/04/06

20112007

Planned0%

2014  Q2FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

12014  Q4

+290,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2015  Q1

2018/4

+66,00

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

0,  Salzburg  AG  für  Energie,  Verkehr  und  TelekommunikaMon  

(18%)  

0,  E.ON  Ruhrgas  AG  (47%)  

0,  KELAG-­‐Kärntner  Elektrizitäts-­‐

AkMengesellschaV  (4%)  

0,  Energie  AG  Oberösterreich    (18%)  

0,  Rohöl-­‐Aufsuchungs  AkMengesellschaV  

(10%)  

0,  TIGAS-­‐Erdgas  Tirol  GmbH  (3%)  

Private  Financing  (70,00%)  

MulMlateral  Financing  (30,00%)  

188

Page 189: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Yes entry

Yes exit

Yes entry

Yes entry

Yes entry

Yes exit

Yes exit

Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National, N-­‐1 Regional, Back-­‐up for renewables, Power-­‐to-­‐gas, Biogas, SoS: Investments will be necessary, especially in cross-­‐border gastransmission capacity, with a view to diversifying sources of supply, and gas transmission systems in general, especially where capacities may be needed in an emergency to supply areas with capacity shortfalls. The TGL is in line with these objectives,which focus mainly on security of supplies. Market Integration: By linking the Central European (Southern Germany) with the South-­‐East European (mainly Italy) natural gas market, the TGL increases interoperability between gas markets in Europewhich are still separate, develop new natural gas sources for these markets and therefore significantly improve competition within a European single market for natural gas. Diversification of European natural gas supplies: By creating the infrastructurerequired for a functioning North-­‐South/South-­‐North system to develop the North African and Arab supply region, including liquefied natural gas (LNG) for the Mediterranean region, the TGL will reduce dependence on individual suppliers in the Northand  East.,  

Interconnector  Austria  /  Tauerngas  LeitungHaiming  (bayernets)  -­‐  DE  /  Burghausen  (Transit)  -­‐  TGL

Tarvisio  -­‐  IT  /  Arnoldstein  (Transit)  -­‐  TGL Interconnector  Austria  /  Tauerngas  Leitung

Storage  AustriaHaiming  (bayernets)  -­‐  DE  /  Burghausen-­‐Auerbach  (Austrian  Storage)  -­‐  TGL

Haiming-­‐Oberkappel  (OGE)  -­‐  DE  /  Burghausen  (Transit)    -­‐  TGLInterconnector  Austria  /  Tauerngas  Leitung

180,74

65,40

136,65

33,82

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Hub  Italia

Hub  Germany  (NCG)

Hub  Germany  (NCG)

Tarvisio  -­‐  IT  /  Arnoldstein  (Transit)  -­‐  TGL

Haiming  (bayernets)  -­‐  DE  /  Burghausen  (Austrian  Hub)  -­‐  TGL

Haiming  (bayernets)  -­‐  DE  /  Burghausen  (Transit)  -­‐  TGL

Haiming  (OGE)  -­‐  DE  /  Burghausen-­‐Auerbach  (Austrian  Storage)  -­‐  TGL

PROJECTED  CAPACITY  INCREASES

Hub  Austria

Hub  Germany  (NCG)

Storage  Austria

Hub  Italia

143,82

314,96

148,61

30,14

Pipeline  (incl.  compressor  stations)  in  North-­‐South  direction.  TGL  allows  feed  significant  volumes  from  different  sources  from  South-­‐East  regions  towards  Central  Europe.

Own financing 30%. Loans 70% of which 70-­‐80% fromcommercial banks and therest  from  multilateral  financing 20-­‐30%  of  70%  of  the  overall  external  financing  needs

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Interconnector  Austria  /  Tauerngas  Leitung

Hub  Germany  (NCG)

Hub  Germany  (NCG)

Hub  Germany  (NCG)

Interconnector  Austria  /  Tauerngas  Leitung

189

Page 190: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Project  of  European  Interest

Not  defined  yet

Nord Stream 4

Nord  Stream  AG

Nord  Stream  AG

Pipeline  including  CS

www.nord-­‐stream.com

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-069 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+1.225,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2018/4

Considered  TPA  Regime

Considered  Tariff  Regime Not  applicable

Not  applicable

0,  GDF  Suez  (9%)  

0,  N.V.  Nederlandse  Gasunie  (9%)  

0,  E.ON  Global  CommodiCes  SE    (16%)  

0,  Wintershall  Holding  GmbH  (16%)  

0,  OAO  Gazprom  (51%)  

Undefined  (100,00%)  

190

Page 191: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Security of Supply, Diversification of sources, Increasing reliability of supply by a modern, direct pipeline connection; increasing the liquidity of the European gas market; meeting the growing import gap, especially of Northwestern Europe in light ofdeclining  indigenous  production;  will  as  complementary  low  carbon  energy  source  serve  the  EU  to  meet  its  energy  and  de-­‐carbonization  goals,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Greifswald

PROJECTED  CAPACITY  INCREASES

Supplier  Russia  /  Nord  Stream  (Greifswald)871,60

natural  gas  pipeline  from  Russia  to  Germany  through  the  Baltic  Sea

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Interconnector  Russia  /  Nord  Stream

191

Page 192: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2023*

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+25,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

No

0%

No

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

Not  part  of  TEN-­‐E

Yes

Iberian-French corridor: Eastern Axis-Midcat Project (Pipeline Figueras-French border)

Enagás  S.A.

Enagás  S.A.

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-161 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Enagás  S.A.  (100%)  

Private  Financing  (100,00%)  

192

Page 193: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exit

None

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  France  (PEG  TIGF)Hub  Spain

80,00230,00

Le  Perthus

PROJECTED  CAPACITY  INCREASES

Hub  France  (PEG  TIGF)Hub  Spain

Security of Supply, Market integration (Iberian peninsula with Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (Spain, France), N-­‐1 Regional (North-­‐south in Western Europe), Back-­‐up for renewables, Securityof  Supply,  Market  Integration,  Enhancement  of  Internal  Network;  reduction  of  internal  congestion,  N-­‐1  compliance,  Integration  of  LNG  plants,  Integration  of  UGS,  Integration  of  new  Gas  fired  power  plants

Figueras-­‐French Border is necessary for the develpment of the Le Perthus IP subproject, part of the Eastern axis-­‐Midcat Project in the North-­‐South gas interconnections in western Europe, which has been submitted as a PCI. The Iberian-­‐FrenchCorridor  is  crucial  to  better  interconnect  the  Mediterranean  area  and  thus  supplies  from  Africa  and  the  Northern  supply  Corridor  making  a  reality  the  strategy  concept  of  the  North-­‐South  Corridor  in  Western  Europe.  From an European perspective, developing the full IBERIAN-­‐FRENCH CORRIDOR contribute to spread the diversified portfolio of the South Region as well as opens a path to transport gas from Algeria to central Europe through France. The IBERIAN-­‐FRENCH CORRIDOR will contribute to redistribute and balance the entry of supply sources to Europe, increasing the European diversification of supply by reducing the dependence on the incumbent gas source, jointly with the risks linked to securityof  supply.From a regional perspective, highlighted is the better integration of these two countries into the South Region, developing the new cross border interconnection capacity. Developing cross-­‐border capacity between France and Spain will bring theEuropean  gas  market  closer,  making  possible  the  development  of  large  scale  energy  trade  between  countries

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

193

Page 194: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Not  part  of  TEN-­‐E

No

Reverse Flow Transitgas Switzerland

Fluxys

FluxSwiss

Pipeline  including  CS

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-230 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

No

Market  test100%

2014  Q1FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

100%

2017/4

Considered  TPA  Regime

Considered  Tariff  Regime Negotiated  (e.g.  Exemption)

Negotiated  (e.g.  Exemption)

0,  FluxSwiss  (100%)  

Undefined  (100,00%)  

194

Page 195: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exitYes exit

Security  of  Supply,  Market  integration  (NCG/PSV/PEGNord),  Reverse  Flows,  Diversification  of  sources,  Diversification  of  routes,  N-­‐1  National  (DE,  FR),  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Hub  Switzerland

Griespass  (CH)  /  Passo  Gries  (IT)  (FluxSwiss)Wallbach  (Fluxys  TENP/FluxSwiss)Oltingue  (FR)  /  Rodersdorf  (CH)

PROJECTED  CAPACITY  INCREASES

Hub  Germany  (NCG)Hub  France  (PEG  North)

Hub  Switzerland

Modification of the compressor station at Ruswil, the valve station at Lostorf and the metering station at Wallbach to allow the reversal of the border interconnection points at Gries Pass, Wallbach and Oltingue and a south-­‐north use of the Transitgaspipeline.

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Italia  (Passo  Gries)Hub  Switzerland

195

Page 196: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Project  of  European  Interest

Not  defined  yet

Nord Stream 3

Nord  Stream  AG

Nord  Stream  AG

Pipeline  including  CS

www.nord-­‐stream.com

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-267 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

Not  relevant

0%

Not  relevant

Planned0%

FID

Construction

Commissioning

Last  completed  Phase  :

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

1

+1.225,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

2017/4

Considered  TPA  Regime

Considered  Tariff  Regime Not  applicable

Not  applicable

0,  GDF  Suez  (9%)  

0,  N.V.  Nederlandse  Gasunie  (9%)  

0,  E.ON  Global  CommodiCes  SE    (16%)  

0,  Wintershall  Holding  GmbH  (16%)  

0,  OAO  Gazprom  (51%)  

Undefined  (100,00%)  

196

Page 197: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes exit

Security of Supply, Diversification of sources, Increasing reliability of supply by a modern, direct pipeline connection; increasing the liquidity of the European gas market; meeting the growing import gap, especially of Northwestern Europe in light ofdeclining  indigenous  production;  will  as  complementary  low  carbon  energy  source  serve  the  EU  to  meet  its  energy  and  de-­‐carbonization  goals,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

Greifswald

PROJECTED  CAPACITY  INCREASES

Supplier  Russia  /  Nord  Stream  (Greifswald)871,60

natural  gas  pipeline  from  Russia  to  Germany  through  the  Baltic  Sea

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Interconnector  Russia  /  Nord  Stream

197

Page 198: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2020

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

2

+324,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

24/04/0930/06/08

20102009

Planned0%

2015FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Yes

PL - DK interconnection (Baltic Pipe)

GAZ-­‐SYSTEM  S.A.

GAZ-­‐SYSTEM  S.A.

Pipeline  including  CS

en.gaz-­‐system.pl/nasze-­‐inwestycje/integracja-­‐z-­‐europejski-­‐systemem/baltyckibaltic-­‐pipe/

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-271 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gas  Transmission  Operator  GAZ-­‐SYSTEM  

S.A.  (100%)  

Undefined  (100,00%)  

198

Page 199: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entryYes exit

Baltic Pipe aims to connect the gas transmission systems in Poland and Denmark and thus cover the higher import needs of Danish and Swedish markets originating from declining production in the Danish part of the North Sea. The project will alsocover  the  forecasted  growth  of  the  gas  demand  in  Poland  based  on  the  development  of  the  power  generation  sector  and  possible  leverage  for  market  coupling  potential  in  the  Baltic  States  and  Central-­‐Eastern  Europe.

TEN-­‐E  (obtained),  support  from  other  EU  funds  is  expected

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  DenmarkHub  Poland

90,4090,40

Interconnector  PL-­‐DK

PROJECTED  CAPACITY  INCREASES

Hub  DenmarkHub  Poland

Security of Supply, Market integration (market areas in the Baltic Sea region and Central-­‐Eastern Europe), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (Poland, Denmark), N-­‐1 Regional (the Baltic Sea region), Back-­‐up  for  renewables,  Baltic  Pipe  will  have  a  significant  impact  on:increasing  security  of  supply  in  the  Baltic  Sea  region  by  diversifying  supply  routes,  sources  and  counterparts;creating  well-­‐interconnected  gas  infrastructure  in  the  Baltic  Sea  region;enhancing  competition  on  the  regional  markets;promoting  natural  gas  as  a  reliable,  competitive  and  environmentally-­‐friendly  source  of  energy  e.g.  in  the  power  generation  sector.  The Baltic Pipe project also contributes to North-­‐South gas interconnections in Central Eastern and South Eastern Europe, as the project which will allow to transport gas from North Sea deposits to the CEE countries, namely to the Czech Republic andSlovakia  (via  the  North-­‐South  corridor  in  Poland,  PL-­‐CZ  and  PL-­‐SK  interconnections).,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

199

Page 200: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

SPONSORS GENERAL  INFORMATION FINANCING

THIRD-­‐PARTY  ACCESS  REGIME SCHEDULE TECHNICAL  INFORMATION

Date  of  Request Year  Funding  GrantedTEN-­‐E  Requests

Considered  TPA  Regime

Considered  Tariff  Regime Regulated

Regulated

2021

+10,00

#  of  Pipelines,  nodes,  CS

Total  Pipeline  Length  (km)

4

+106,00

Applied  for  Exemption  ?

Exemption  granted  ?

%  Exemption  in  entry  direction

%  Exemption  in  exit  direction

Total  Compressor  Power  (MW)

Expected  Load  Factor

End  of  permitting  phase

Not  relevant

0%

No

2012

Planned0%

2015FID

Construction

Commissioning

Last  completed  Phase  :

Project  of  Common  Interest

Yes

Upgrade of PL-DE interconnection in Lasów

GAZ-­‐SYSTEM  S.A.

GAZ-­‐SYSTEM  S.A.

Pipeline  including  CS

en.gaz-­‐system.pl/nasze-­‐inwestycje/

Interested  by  PCI  ?

IGAs

Web  Link

TRA-N-274 Non-FID

Promoter

Operator

TEN-­‐E  Project  ?

None

0,  Gas  Transmission  Operator  GAZ-­‐SYSTEM  

S.A.  (100%)  

Undefined  (100,00%)  

200

Page 201: North West GRIP 2013-2022 Annex A

North West Gas Regional Investment Plan 2013-2022 - Annex A

Modelled Direction

Yes entry

The main objective of the project is to modernise and expand the transmission system near PL-­‐DE interconnection in Lasów with a view to upgrading the capacity of the interconnection point in Lasow from 1,5 up to 3 bcm/y. The upgraded PL-­‐DEinterconnection in Lasów will improve security of gas supplies, increase reliability of cross-­‐border transmission infrastructure between Poland and Germany and will contribute to well-­‐interconnected gas network in the CEE region. The upgrade of PL-­‐DE  interconnection  in  Lasow  up  to  3  bcm/y  requires  modernization  of  the  transmission  systems  both  in  Poland  and  in  Germany.

Support  from  EU  funds  is  expected

Public  financing Private  financing Multilateral  financing

COMMENTS  ABOUT  THE  PROJECT  FINANCING

Interconnection Capacity  (GWh/d) From  Zone To  Zone

Hub  Germany  (GASPOOL)42,00Lasów

PROJECTED  CAPACITY  INCREASES

Hub  Poland

Security of Supply, Market integration (integration of market areas in Central-­‐Eastern Europe and Western Europe (GASPOOL in Germany)), Reverse Flows, Diversification of sources, Diversification of routes, N-­‐1 National (Poland), N-­‐1 Regional(Central-­‐Eastern  Europe),  Back-­‐up  for  renewables,  The  upgraded  PL-­‐DE  interconnection  in  Lasów  will  have  an  impact  on:improving  security  of  gas  supplies  and  increasing  reliability  of  cross-­‐border  transmission  infrastructure  between  Poland  and  Germany;creating  well-­‐interconnected  gas  network  in  the  CEE  region;enhancing  the  access  of  gas  market  players  in  the  CEE  region  to  a  developed,  competitive  and  diversified  Western  European  gas  market  (Germany);establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the power generation sector and possible leverage for market coupling potential in Central-­‐EasternEurope.,  

DESCRIPTION  OF  THE  PROJECT

EXPECTED  BENEFITS

201

Page 202: North West GRIP 2013-2022 Annex A

Cluden

ENTSOG AISBLAvenue de Cortenbergh 100

B-1000 BrusselsT +32 (0)2 894 51 00

[email protected]