northern walnut creek trail section 3 - austin,...

18
NORTHERN WALNUT CREEK TRAIL SECTION 3 (IH-35 TO SOUTHERN WALNUT CREEK) PUBLIC MEETING September 17, 2019

Upload: others

Post on 19-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NORTHERN WALNUT CREEK TRAIL SECTION 3(IH-35 TO SOUTHERN WALNUT CREEK)

PUBLIC MEETING

September 17, 2019

Page 2: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

2SEPT. 17, 2019

NORTHERN WALNUT CREEK TRAIL SECTION 3(IH-35 TO SOUTHERN WALNUT CREEK)

PUBLIC MEETINGPreliminary Engineering Report Public Outreach

Page 3: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 3

• About the Urban Trails Program

• NWCT Section 3 Project Team

• Project Summary

• Preliminary Engineering Report

• Evaluation Criteria

• Public Input & Question – Open House Format

AGENDA

Page 4: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

1. ‍Easy access to transportation + recreation users from all parts of the City

2. Connect to on-street bicycle + sidewalk networks3. Adequate width to accommodate transportation +

recreation users4. ‍Include trail amenities/features that create unique

greenways5. Adequate funding and resources to maintain + operate6. Context-sensitive, environmentally sustainable,

preservation + improvement upon wildlife habitat

URBAN TRAIL GOALS

Page 5: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

5NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019

• Completed October 2014

• Proposed Tier 1 Trails:

47 Miles

• Proposed Tier 2 Trails:

360 Miles

URBAN TRAILS PLAN

Page 6: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

6NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019

• Completed October 2014

• Proposed Tier 1 Trails:

47 Miles

• Proposed Tier 2 Trails:

360 Miles

URBAN TRAILS PLAN

Page 7: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 7

PROJECT SUMMARY

Page 8: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 8

PROJECT TIMELINE

• Funded by 2016 Mobility Bond

• Preliminary Engineering Report (PER) process begins

• First draft of PER prepared

• First public meeting held

• Environmental Field Inspections performed

• Environmental Assessment & Resource Inventory finalized

• Archaeological report finalized

• Texas Historical Commission approval received

• Second public meeting held

Page 9: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

9NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019

• Sponsor Department: Austin Public Works (Urban Trails Program)

• Project Manager: Dario Octaviano, Austin Public Works

• Project Coordinator: Ana Seivert, Austin Public Works

• Public Information Officer: Carolynn Calabrese, Austin Public Works

• Project Engineer: Chris Evans, COA Engineering Services Division Project

Engineer

CITY OF AUSTIN PROJECT TEAM

Page 10: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

10NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019

• Connects to existing and proposed trails

— Proposed Trail: NWCT Section 2 (Walnut Creek Metropolitan Park to IH-35)

— Existing Trail: Southern Walnut Creek Trail

— Existing Trail: 290 Shared Use Path

— Existing Trail: Austin to Manor Trail

• 12 ft. concrete trail

• 8 miles

• ADA accessible

TRAIL FEATURES

Project Area

Page 11: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 11

EVALUATION FACTORS

• Public feedback

• Cultural Assessment

• Community Impact

• Cost

• Topography, Accessibility

• Tree Canopy Impacts

• Connectivity

• Location of Utilities

• Property Ownership

• Surrounding Land Use

• Floodplain/Drainage

• Environmental

• Erosion Hazard Zone

• Wildlife Habitat

Page 12: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

12

Existing Austin Energy Easements

Page 13: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

13

Existing Missouri-Kansas Easement

Page 14: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

14

Environmental Features: Rimrock

Page 15: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

15

Environmental Features: Wetlands

Page 16: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

16

IH-35 Crossing

Page 17: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 17

Public Meeting:

Northern Walnut Creek Trail Section 2

(Walnut Creek Metropolitan Park to IH-35)

• WHEN: Tues., October 8th, 2019, 6-7:30 pm

• WHERE: Walnut Creek Elementary

UPCOMING EVENTS

Page 18: NORTHERN WALNUT CREEK TRAIL SECTION 3 - Austin, Texasaustintexas.gov/sites/default/files/files/Public_Works/Urban_Trails/... · NWCT SECTION 3 PROJECT UPDATE – SEPT. 17, 2019 4

THANK YOUContacts

Ana Seivert, Project Coordinator

[email protected] | (512) 974-2858

Carolynn Calabrese, Public Information Specialist

[email protected] | (512) 974-6512

WebsiteAustinTexas.gov/WalnutCreekTrail