We really appreciate your continued understanding and cooperation in Hokkaido's road projects nowadays.
Since April of this year, we have been promoting the Electrical Wire Utility Tunnel Construction (Wire Underground Project) on the Rankoshi-Niseko-Kutchan Line, now we inform you that the construction will be completed.
We would like to express our sincere gratitude to the local people, and road users for your great cooperation in the traffic regulations on roads and sidewalks construction, the power line pull-in of the houses, etc.
Construction completion (planned) date: Monday, September 30, the first year of Reiwa (2019)
September, the first year of Reiwa (2019)
Otaru Department of Public Works Management, Hokkaido Government SHIRIBESHI General Subprefectural Bureau
1-21-1 Okuzawa, Otaru city TEL 0134-25-2195 FAX 0134-27-2354
Makkari Branch Office 117-2 ji-Makkari, Makkari-mura, Abuta-gun
TEL 0136-45-2136 FAX 0136-45-2138
Notice of Construction Completion Electrical Wire Utility Tunnel Construction on the Rankoshi-Niseko-Kutchan Line (Wire Underground Project)
その先の、道へ。北海道 Hokkaido. Expanding Horizons.
Overview of Wire Underground Project on the Rankoshi-Niseko-Kutchan Line
Wire Underground Project on the Rankoshi-Niseko-Kutchan Line L=2.1km
Hirafusaka
Sun Sports LandKutchan
<Before> <Halfway through>
<Before>
Tennis court
Completing wire and communication line burial, installation of underground box, restoration of sidewalk interlocking, ground equipment installation※1, electric pole removal※2
※1 Construction of Hokkaido Electric Power Co., Inc.※2 Construction of Hokkaido Electric Power Co., Inc.
and NTT Infrastructure Net Corporation
<Halfway through >
Location map
Before After
ConstructionsectionKutchan
Conveniencestore
Conveniencestore
Conveniencestore