AGENDA
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
• Overview of Northrop Grumman Ship Systems• Engineering & ILS Program Labor• Progress/Earned Value/BCWP• Design Engineering EVMS Applications
– LHD 5 & 8
– DDG 51 Class
– Composite Fabrications
November 2002 3
Northrop Grumman Ship Systems (NGSS), headquartered in Pascagoula, Mississippi was formed on August 1, 1999. It includes Ingalls Operations (Pascagoula), Avondale Operations in New Orleans and Tallulah Louisiana, and Gulfport, Mississippi.
NGSS currently employs more than 17,000 shipbuilding professionals and is one of the nation’s leading full service systems companies for the design, engineering, construction and life cycle support for U.S. Navy and commercial surface ships.
NGSS has a funded backlog exceeding $8.0 billion, in a variety of naval and commercial shipbuilding programs.
Ship Systems Overview
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 4
Ship Systems Overview
INGALLS OPERATIONS
AVONDALE OPERATIONS
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 5
Newport News
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 6
LABOR
DIRECT INDIRECT
VESSEL LABOR (SHIP/CRAFT)
PROGRAM LABOR (DIRECT
SUPPORT)
IDENTIFIED BY CONTRACT, SHIP, CWBS, C/C, ACCOUNT
AND WORK PACKAGE (BILL #)
IDENTIFIED BY CONTRACT, CWBS, C/C, ACCOUNT AND
WORK PACKAGE (MWP)
WELDING
FITTINGS
PAINTING
OUTFITTING
ETC.
ENGINEERING
PROGRAMS MANAGEMENT
PRODUCTION PLANNING
PRODUCTION CONTROL
ETC.
Major Budget / Cost Categories - Labor
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
CONTROLLED BY OVERHEAD ACCOUNTS
AND COST CENTERS
November 2002 7
LHD Program Value By Category
Manufacturing Labor36%
Material48%
Other Program Labor
4% Engineering
12%
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 8
Engineering Functions
• Program Engineering
• Systems Engineering
• Field Engineering
• Naval Arch/Elect
• Noise, Shock & Vibration Control
• Engineering Test and Evaluations
• Trials
• Marine Technical
• 3D Detail Design
• 2D Design
• Numerical Controls & MFG Aids
• Electrical Technical
• Electrical Design
• Combat Systems Technical
• Combat Systems Test
• Weight Control
• Engineering Configuration Mgt.
• Engineering R & D
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 9
ILS Functions
• Reliability, Maintainability & Quality
• Maintenance & Provisioning
• Inventory Mgmt & Allowance
• Config. Data Mgt./Life Cycle Mgt.
• Eng. Technical Publications
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 10
Progress /Earned Value :BCWP
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
•EVMS Provides Engineering Supervision a Weekly Detailed Progress Report Bill Listing
•Management Uses this Report to Evaluate the Overall Progress and Performance of the Task
•Discrete Physical Progress
•Apportioned Effort
•Level Of Effort
•Progress is Updated Weekly
November 2002 11
• LHD5 Modification• LHD8 Redesign• DDG 51 Class - Flight IIA• Composite Fabrications
Design Engineering
Earned Value Applications
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 12
LHD Program
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 13
• First Drawing Level earned value application • Initiated by Ingalls & approved by Navy• Reported to First Line Engineering Supervisor• Budget reconciled to Work Packages• Progressed weekly• Progress input to monthly CPR
LHD5 Modifications (April 1992)
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 14
LHD 5 Lessons Learned
• Drawing Work Packages are too detailed• Focus on category of work vs. organization• Good planning tool for Engineering Managers
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 15
• Use local PC files to track individual models & drawings
• Summarize to Work Packages for EVMS• Identify Work Packages to Category• Maintain Supervisor visibility• Ensure budget reconciliation • Continue to progress weekly
LHD8 Application
A ‘Two-Tier’ System
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 16
DDG 51 Program – The ARLEIGH BURKE Class Aegis Destroyers
DDG 51 Program
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 17
DDG 51 Class Flight IIA Design
• Engineering Work Packages by ship zone• Joint reporting with Bath Iron Works (BIW) to
NAVSEA• Weekly progress, cost updates & reporting
Northrop Grumman Ship Systems14th annual International IntegratedProgram Management Conference
Washington D.C.
November 2002 18
Composite Fabrications
• Carderock Naval Surface Warfare Center• Joint project with Ingalls Facility, and Avondale
Facility(Gulfport, MS)• EVMS tracking Engineering & Manufacturing• Shared Drive file showed all Work Packages and
was updated weekly for progress and cost